Indian Institute of Technology Patna Department of Electrical Engineering EE480 - Power System Operation and Control Autumn - 2016 Mid Semester Exam 19 September 2016 1. Consider the 2 bus system. (5 marks) x G 1 y 2 2 y 2 x = 0.1 p.u. SD = 1.2 + 0.9 p.u. y = 2 p.u. The synchronous reactance of generator is 20 %. The magnitude of voltage at bus 2 must equal 1.00 p.u. (a) Determine the voltage that we must maintain at bus 1 in order to achieve the above objective. (b) Compute PG1 and QG1 . 2. Consider the 2 bus system. ( 15 marks) x G 1 y 2 2 y 2 x = 0.1 p.u. SD = 1.2 + 0.9 p.u. y = 2 p.u. The synchronous reactance of generator is 20 %. (a) Form YBus matrix. (b) Find |V2 | and δ2 , if |V1 | = 1.0 p.u and δ1 = 0◦ . Use Newton- Raphson method. Do two iterations. (c) Find PG1 and QG1 . 3. There are two generating units in a plant. The incremental cost curves with their minimum and maximum limits are shown here. Find the optimum dispatch and the incremental cost for a load of 500 MW. (5 marks) λ (Rs/MWhr) λ (Rs/MWhr) 250 400 150 250 100 500 P (MW) 100 500 P (MW) 4. A synchronous generator connected to an infinite bus is running overexcited with 150 %. The synchronous reactance is 120 %. The generator is delivering a real power of 0.4 p.u. If the mechanical input is increased by 50 %, how much will be change in PG and QG . (5 marks) 2