REPORT System Impact Assessment Report CONNECTION ASSESSMENT & APPROVAL PROCESS 2nd Addendum Report CAA ID: 2011-446 Project: Adelaide Wind Energy Centre Applicant: Kerwood Wind Inc Market Facilitation Department Independent Electricity System Operator Date: December 12, 2012 Document Name System Impact Assessment Report Issue 2nd Addendum Report Reason for Issue Revised connection transformer Effective Date December 12, 2012 © 2000, Independent Electricity System Operator. System Impact Assessment Report Proposed Changes and Notification of Conditional Approval Proposed Changes and Notification of Conditional Approval Transformer Change The Bornish, Adelaide and Jericho Wind Energy Centres, as well as the Cedar Point II Wind Power Project, are wind generating projects proposing to connect to 500 kV circuit B562L via a proponent owned 121 kV network and 525 kV/121 kV autotransformer. System Impact Assessments (SIA) for the Bornish, Adelaide and Jericho Wind Energy Centres (CAA ID 2011-443, CAA ID 2011-446 and CAA ID 2011-441 respectively) were conducted and the projects were initially given Notices of Conditional Approval on December 21st 2011. The SIA for the Cedar Point II Wind Power project (CAA ID 2011443) was conducted and the project was given a Notice of Conditional Approval on June 4th 2012. Since the Cedar Point Wind Power Project is being incorporated into the proponent owned network, SIA addendums containing Notices of Conditional Approval for the Bornish, Adelaide and Jericho Wind Energy Centres were issued on June 6th 2012. The connection applicants (Bornish Wind LP, Kerwood Wind Inc., Jericho Wind Inc. and Suncor Energy Products Inc.) are now proposing to connect to the 500 kV system via two separate 525 kV/121 kV/27.6 kV autotransformers, rather than with the single 525 kV/121 kV autotransformer that was part of the first Addendum. The IESO and Hydro One have examined the proposed change and concluded that it is not materially different from the first Addendum’s application data, as the equivalent impedance of the proposed two parallel transformer arrangement is similar to that of the single transformer previously assessed. Hydro One will acknowledge the proposed change separately with a new CIA addendum, indicating that it is acceptable. Bruce Special Protection Scheme Requirement Change The initial SIA report for the Adelaide Wind Energy Centre (the project) included a requirement for the project to participate in the Bruce Special Protection Scheme (BSPS) requiring: i. ii. iii. Hydro One to modify the logic of the BSPS to transmit rejection signals to the project, the procurement of duplicated and physically separated communication paths between Hydro One’s central scheme and the project site, and equipment to be installed at the project site to receive the signals and take action to trip or runback your generation. Subsequent to releasing the SIA report, the IESO conducted detailed studies for the Bruce area and concluded that, at this time, the grid planning criteria can be met without the project participating in the BSPS. Therefore, the IESO does not require the project to participate in the Bruce SPS at this time. For now, Hydro One does not need to modify the BSPS to transmit signals to the project, and the telecommunication between Hydro One’s BSPS and the project for that purpose does not need to be in place. We however foresee that the incorporation of the project into the BSPS may be required in the future. To allow for future incorporation of the project into the BSPS in a timely manner, the IESO requires that you make at this time the necessary provisions in the design and construction of the project to install equipment that is able to receive SPS signals from the BSPS, can automatically take action to reject or runback the project’s generation upon receiving the SPS signals, and is able to send the arming status to the IESO via telemetry or other approved means. 2nd Addendum Report – December 12, 2012 CAA ID 2011-446 1 System Impact Assessment Report Transformer Data Should the need arise in the future, we will direct you and Hydro One to install all the equipment required for the project to participate in the BSPS, as described in the SIA report. We would expect your project to be available for participation in the BSPS in no more than 9 months from our direction. Notification of Conditional Approval Therefore, the IESO recommends that a Notification of Conditional Approval for Connection be issued for the Adelaide Wind Energy Centre subject to implementation of the requirements outlined in this SIA Addendum and the previous SIA reports. Transformer Data Table 1: Previous step-up transformer data Positive Sequence Configuration Rating (MVA) # of Impedance (pu) Transformation Units (ONAN/ONAF/ONAF) HV-Side LV-Side SB= 256 MVA 1 525kV/121kV 256/341/426 MVA 0.0022+j0.1 ULTC@ LV ±10 %, 33 steps Δ Yg Taps Table 2: New step-up transformers’ data Configuration Positive Sequence Rating (MVA) # of Impedance (pu) HV- LVTransformation Units (ONAN/ONAF/ONAF) Tert. SB= 135 MVA Side Side 2 525kV/121kV/ 27.6 kV 135/180/225 MVA j0.1 Y Y Δ Taps ULTC@ HV ±10 %, 33 steps Updated Single Line Diagram Below is an updated single line diagram of the Adelaide Wind Energy Centre, reflecting the changes identified in this Addendum. 2 CAA ID 2011-446 2nd Addendum Report – December 12, 2012 System Impact Assessment Report Updated Single Line Diagram Figure 1: Updated Adelaide Wind Energy Centre Single Line Diagram - 2nd Addendum Report – December 12, 2012 End of Document - CAA ID 2011-446 3