STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 March 19, 2015 Advice Letters: 3121-E Russell G. Worden Director, State Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 SUBJECT: Submission of Contracts for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation. Dear Ms. Scott-Kakures: Advice Letter 3121-E is effective as of March 12, 2015, per Resolution E-4704 Ordering Paragraphs. Sincerely, Edward Randolph, Director Energy Division ADVICE LETTER (AL) SUSPENSION NOTICE ENERGY DIVISION Utility Name: Southern California Edison Date Utility Notified: November 21, 2014 Utility Number/Type: U 338-E [X ] E-Mailed to: AdviceTariffManager@sce.com Advice Letter Number(s): 3121-E ED Staff Contact: Scarlett Liang-Uejio Date AL(s) Filed: October 28, 2014 ED Staff Email: scarlett.liang-uejio@cpuc.ca.gov Utility Contact Person: Darrah Morgan ED Staff Phone No.: (415) 703-1851 Utility Phone No.: (626) 302-2086 [X] INITIAL SUSPENSION (up to 120 DAYS from the expiration of the initial review period) This is to notify that the above-indicated AL is suspended for up to 120 days beginning November 27, 2014 for the following reason(s) below. If the AL requires a Commission resolution and the Commission’s deliberation on the resolution prepared by Energy Division extends beyond the expiration of the initial suspension period, the advice letter will be automatically suspended for up to 180 days beyond the initial suspension period. [X] A Commission Resolution is Required to Dispose of the Advice Letter [X] Advice Letter Requests a Commission Order [X] Advice Letter Requires Staff Review The expected duration of initial suspension period is 120 days [ ] FURTHER SUSPENSION (up to 180 DAYS beyond initial suspension period) The AL requires a Commission resolution and the Commission’s deliberation on the resolution prepared by Energy Division has extended beyond the expiration of the initial suspension period. The advice letter is suspended for up to 180 days beyond the initial suspension period. _____________________________________________ If you have any questions regarding this matter, please contact Scarlett Liang-Uejio at scarlett.lianguejio@cpuc.ca.gov. cc: Energy Division Tariff Unit * Note: reference – Decision D.02-02-049, dated February 21, 2002, and Rule 7.5 in appendix A of D.O7-01-024 Megan Scott-Kakures Vice President, Regulatory Operations ` October 28, 2014 ADVICE 3121-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: I. Submission of Contracts for Procurement of Renewable Energy From SCE’s 2013 Renewables Portfolio Standard Solicitation INTRODUCTION A. Purpose of the Advice Letter Southern California Edison Company (“SCE”) submits this Advice Letter pursuant to California Public Utilities Code Section 399.11 et seq. (the “RPS Legislation”) seeking approval of two Renewables Portfolio Standard (“RPS”) power purchase agreements (the “Mount Signal II Contract” and the “Mount Signal V Contract,” together, the “Mount Signal Contracts”). The Mount Signal II Contract is between SCE and 88FT 8me LLC (“Seller”), a project wholly owned by a joint venture between Silver Ridge Power (“SRP”) and 8minutenergy Renewables, LLC (“8me”). The Mount Signal V Contract is between SCE and 93LF 8me LLC (“Seller”), also a project wholly owned by a joint venture between SRP and 8me. The following table summarizes the Mount Signal Contracts: Seller 88FT 8me LLC (Mount Signal II Contract) 93LF 8me LLC (Mount Signal V Contract) P.O. Box 800 Generation Type Size Megawatts (MW) Estimated Average Energy (GWh/yr) Forecasted Commercial Operation Date Term of Agreement (Years) Solar photovoltaic 153.52 402 June 1, 2020 20 Solar photovoltaic 252.32 660 February 1, 2019 20 8631 Rush Street Rosemead, California 91770 (626) 302-6855 Fax (626) 302-4829 ADVICE 3121-E (U 338-E) -2- October 28, 2014 SCE requests that the California Public Utilities Commission (“Commission” or “CPUC”) issue a final resolution containing findings in the form requested in this Advice Letter within six months (April 28, 2015). In accordance with General Order (“GO”) 96-B, the confidentiality of information included in this Advice Letter is described below. This Advice Letter contains both confidential and public appendices as listed below. Confidential Appendix A: Consistency with Commission Decisions and Rules and Project Development Status Confidential Appendix B: 2013 Solicitation Overview Confidential/Public Appendix C: Independent Evaluator Report Confidential Appendix D.1: Contract Summary for Mount Signal II Contract Confidential Appendix D.2: Contract Summary for Mount Signal V Contract Confidential Appendix E: Comparison of Mount Signal II Contract and the Mount Signal V Contract with SCE’s 2013 Pro Forma Renewable Power Purchase And Sale Agreement Confidential Appendix F: Mount Signal II Contract and the Mount Signal V Contract Confidential/Public Appendix G: Renewable Net Short Calculations Appendix H: Confidentiality Declaration Appendix I: Proposed Protective Order B. Subject of the Advice Letter The project that is contemplated by the Mount Signal II Contract (“Mount Signal Solar Farm II”) is a proposed 153.52 MW solar photovoltaic (“PV”) facility. The project that is contemplated by the Mount Signal V Contract (“Mount Signal Solar Farm V”) is a proposed 252.32 MW solar PV facility. Both projects (the “Mount Signal Projects”) are to be located in southern Imperial County, approximately two miles west of the City of Calexico (the “Site”). Both projects will interconnect at San Diego Gas & Electric Company’s (“SDG&E”) Imperial Valley substation. The Seller under the Mount Signal II Contract is 88FT 8me LLC. The Seller under the Mount Signal V Contract is 93LF 8me LLC. Both Sellers are wholly ADVICE 3121-E (U 338-E) -3- October 28, 2014 owned by a joint venture between SRP and 8me. The Mount Signal Contracts are new contracts that originated from SCE’s 2013 RPS solicitation. C. General Project Description Project Name Mount Signal Solar Farm II Mount Signal Solar Farm V Technology Solar PV Solar PV Capacity (MW)1 153.52 252.32 Capacity Factor (Term Year 1) 31.3% 31.3% Expected Generation (GWh/Year)2 402 660 Initial Commercial Operation Date 6/1/2020 2/1/2019 Date Contract Delivery Term Begins 6/1/2020 2/1/2019 Delivery Term (Years) 20 20 Vintage (New / Existing / Repower) New New Location (City and State) City of Calexico, California City of Calexico, California Control Area (e.g., CAISO, BPA) California Independent System Operator (“CAISO”) CAISO Nearest Competitive Renewable Energy Zone (CREZ) as identified by the Renewable Energy Transmission Initiative (RETI) CREZ 30 Imperial South CREZ 30 Imperial South Type of Cooling, if Applicable Not applicable Not applicable D. Project Location The Site for the Mount Signal Projects is located in southern Imperial County, California. The Projects are co-located approximately two miles west of the City of Calexico. The Site is currently being used as agricultural land. Refer to Appendix A, Section C.3 for information on the Site and relevant permits. Refer to Appendix F, Exhibit B for a map of the Mount Signal Projects’ location. 1 2 See Appendices D-1 and D-2, Section D under “Capacity” for further details on the Mount Signal Projects’ capacities. This expected generation represents the annual average generation that SCE expects to make payments on over the contract term. ADVICE 3121-E (U 338-E) E. -4- October 28, 2014 General Deal Structure The Mount Signal Contracts are based on SCE’s 2013 Pro Forma Renewable Power Purchase and Sale Agreement, which was accepted by the Commission in Decision (“D.”) 13-11-024 on November 14, 2013.3 SCE is purchasing all electric energy produced by both of the Mount Signal Projects throughout each respective contract term, net of station use (if any), and all green attributes, capacity attributes, and resource adequacy benefits generated by, associated with, or attributable to the Mount Signal Projects. The delivery point for the Mount Signal Projects is the point of interconnection with the CAISO-controlled grid at SDG&E’s Imperial Valley substation. Additional information regarding the deal structure of the Mount Signal II Contract and Mount Signal V Contract is provided in Appendices D-1 and D-2. The Mount Signal Projects also met all of the eligibility requirements and preferred project characteristics for SCE’s 2013 Request for Proposals (“RFP”), which are described in further detail in Sections A.2 and A.3. The Mount Signal Projects are expected to deliver a portfolio content category 1 (“Category 1”) product, and have their first point of interconnection within a California Balancing Authority. F. RPS Statutory Goals & Requirements By providing renewable energy from an eligible renewable energy resource (“ERR”) as defined in the RPS Legislation, the Mount Signal Contracts are consistent with, and contribute to, the RPS program’s statutory goals. Pursuant to Public Utilities Code Section 399.11(b), the Legislature determined that procurement of electricity products from ERRs, such as the Mount Signal Projects, provides unique benefits to California, including among other things, displacing fossil fuel consumption within the state, reducing air pollution in the state, meeting the state’s climate change goals by reducing emissions of greenhouse gases associated with electrical generation, and meeting the state’s need for a diversified and balanced energy generation portfolio. Based on SCE’s analysis of its renewable net short (“RNS”) position, SCE projects a long-term renewable procurement need in the third compliance period and beyond. Consistent with this need, the Mount Signal Projects will provide long-term RPS and Category 1-eligible energy over 20-year terms, starting in 2019 and 2020, respectively. SCE’s RNS calculations are included in Appendix G. 3 D.13-11-024 at 69 (Ordering Paragraph 1). ADVICE 3121-E (U 338-E) G. -5- October 28, 2014 Confidentiality SCE is requesting confidential treatment of Appendices A, B, and D.1 through F, and the confidential versions of Appendices C and G to this Advice Letter. The information for which SCE is seeking confidential treatment is identified in the Confidentiality Declaration attached as Appendix H. The confidential version of this Advice Letter will be made available to appropriate parties (in accordance with SCE’s Proposed Protective Order, as discussed below) upon execution of the required non-disclosure agreement. Parties wishing to obtain access to the confidential version of this Advice Letter may contact Amber Wyatt in SCE’s Law Department at amber.wyatt@sce.com or 626-302-6961 to obtain a non-disclosure agreement. In accordance with GO 96-B, a copy of SCE’s Proposed Protective Order is attached as Appendix I. It is appropriate to accord confidential treatment to the information for which SCE requests confidential treatment in the first instance in the advice letter process because such information is entitled to confidentiality protection pursuant to D.06-06-066,4 and is required to be filed by advice letter as part of the process for obtaining Commission approval of RPS power purchase and sale agreements. SCE would object if the information were disclosed in an aggregated format. The information in this Advice Letter for which SCE requests confidential treatment, the pages on which the information appears, and the length of time for which the information should remain confidential, are provided in Appendix H. This information is entitled to confidentiality protection pursuant to D.06-06-066 (as provided in the Investor-Owned Utility (“IOU”) Matrix).5 The specific provisions of the IOU Matrix that apply to the confidential information in this Advice Letter are identified in Appendix H. II. CONSISTENCY WITH COMMISSION DECISIONS A. SCE’s 2013 RPS Procurement Plan 1. SCE’s 2013 RPS Procurement Plan Was Approved by the Commission and SCE Adhered to Commission Guidelines for Filing and Revisions SCE filed its 2013 RPS Procurement Plan on June 28, 2013. On August 28, 2013, SCE filed a motion to amend its 2013 RPS Procurement Plan, which included an amended 2013 RPS Procurement Plan as an attachment. In D.13-11-024, the Commission conditionally accepted SCE’s 2013 RPS Procurement Plan, including the solicitation materials for SCE’s 2013 RPS 4 5 D.06-06-066 at 80 (Ordering Paragraphs 1 and 2). Id., Appendix 1. ADVICE 3121-E (U 338-E) -6- October 28, 2014 solicitation.6 The Commission also ordered SCE to make certain changes to its 2013 RPS Procurement Plan and to file a final plan by December 4, 2013. On December 4, 2013, SCE filed and served its final 2013 RPS Procurement Plan. On December 13, 2013, SCE re-filed and served its final 2013 RPS Procurement Plan to make some minor corrections. Consistent with the schedule set forth in D.13-11-024, SCE issued its 2013 RFP on January 6, 2014. 2. Summary of SCE’s Assessment of Portfolio Needs and Preferred Project Characteristics As explained in SCE’s 2013 RPS Procurement Plan and shown in SCE’s RNS calculations, SCE has a long-term need for renewable energy in the third compliance period and beyond. In the 2013 RPS Procurement Plan, SCE received approval to conduct a targeted solicitation to meet SCE’s need for renewable resources. In its 2013 RPS RFP, SCE accepted proposals for projects with commercial operation dates of January 1, 2016 or later, and limited its procurement to Category 17 products. SCE also required that projects have either a Phase II Interconnection Study or an equivalent or better process or exemption in order to submit a proposal. Projects with a contract capacity of 1.5 MW or greater were eligible to participate in SCE’s 2013 RPS RFP. However, SCE indicated a strong preference for projects with contract capacities: (1) greater than 20 MW – for projects located within the service territories of SCE, Pacific Gas and Electric Company (“PG&E”), and SDG&E and directly interconnected to the CAISO or the distribution systems of SCE, PG&E, or SDG&E; (2) 3 MW or greater – for projects located outside the service territories of SCE, PG&E, and SDG&E and directly interconnected to the transmission or distribution system of a California Balancing Authority; or (3) 1.5 MW or greater – for projects located within the Western Los Angeles sub-area of the Los Angeles basin local reliability area, or in the Moorpark sub-area of the Big Creek/Ventura local reliability area. Additionally, for in-state generating facilities that are, or will be, interconnected to the CAISO, SCE required that the delivery point be where the generating facility connects to the CAISO controlled grid. For in-state generating facilities that are, or will be interconnected to a California Balancing Authority other than the CAISO, SCE required the delivery point be the intertie point where the seller’s transmission provider ties to the CAISO. SCE decided on the total projected contract energy it signed based on several factors laid out in the 2013 RPS Procurement Plan, including projected long-and 6 7 D.13-11-024 at 69 (Ordering Paragraph 1). As defined in Public Utilities Code Section 399.16(b)(1) and D.11-12-052. ADVICE 3121-E (U 338-E) -7- October 28, 2014 short-term needs, the impact of reducing federal tax credits, and expected contract success rates. 3. The Mount Signal Contracts Are Consistent With SCE’s 2013 RPS Procurement Plan, Portfolio Needs, and Preferred Project Characteristics The Mount Signal Contracts align with the portfolio needs identified in SCE’s 2013 RPS Procurement Plan. Specifically, the Mount Signal Contracts will provide renewable energy from new solar PV facilities starting in 2019 and 2020, respectively, for 20-year terms, consistent with SCE’s long-term renewable procurement need in the third compliance period and beyond. The Mount Signal Solar Farm II and Mount Signal Solar Farm V Projects also met all of the eligibility requirements and preferred project characteristics for SCE’s 2013 RFP. The first point of interconnection for both Mount Signal Projects will be with the CAISO, and thus the Mount Signal Projects will provide Category 1 products. Additionally, the Mount Signal Projects’ contract capacities (approximately 154 MW and 252 MW, respectively) are consistent with SCE’s preference for projects with contract capacities of 20 MW or greater (for projects located within the service territories of SCE, PG&E, and SDG&E and directly interconnected to the CAISO or the distribution systems of SCE, PG&E, or SDG&E). The Mount Signal Projects will also satisfy the delivery requirements for SCE’s 2013 RFP, because the projects’ delivery points will be where they connect to the CAISO-controlled grid. 4. The Mount Signal Contracts Optimize SCE’s RPS Portfolio As described in detail in SCE’s 2013 RPS Procurement Plan,8 the objective of SCE’s renewables portfolio optimization strategy is to minimize costs to its customers while ensuring that RPS procurement goals are met or exceeded. SCE determines the procurement target for each RPS solicitation based, in part, on its assessment of SCE’s renewable procurement position and need, i.e., SCE’s RNS. This includes a calculation of SCE’s net short or long renewables position and SCE’s bank. SCE carefully evaluates its renewable procurement need by assessing bundled retail sales, the performance and variability of existing generation, the likelihood of new generation achieving commercial operation, expected commercial operation dates, technology mix, expected curtailment, and the impact of pre-approved procurement programs, among other factors. 8 See Southern California Edison Company’s (U 338-E) Final 2013 Renewables Portfolio Standard Procurement Plan, December 4, 2013 (“Final 2013 RPS Plan”), at 22-25. ADVICE 3121-E (U 338-E) -8- October 28, 2014 The Mount Signal Contracts meet the primary objectives of SCE’s portfolio optimization strategy. The Mount Signal Contracts are expected to start deliveries in 2019 and 2020, respectively, which will help meet SCE’s renewable procurement need in the third compliance period and beyond. Additional information is included in Appendix A, Section A.7. B. Least-Cost Best-Fit (“LCBF”) Methodology and Evaluation SCE evaluates and ranks proposals based on LCBF principles that comply with criteria set forth by the Commission in D.03-06-071 and D.04-07-029 (the “LCBF Decisions”).9 The goal of SCE’s evaluation and selection criteria and processes is to provide decision metrics so that SCE can procure renewable energy economically, while providing the most value to its customers. The LCBF analysis evaluates both quantitative and qualitative aspects of each proposal to estimate its value to SCE’s customers and its relative value in comparison to other proposals. Although assumptions and methodologies have evolved slightly over time, the basic components of SCE’s evaluation and selection criteria and process for RPS contracts were established by the Commission’s LCBF Decisions. Consistent with those LCBF Decisions, the three main steps undertaken by SCE in its evaluation and selection process were: (i) initial data gathering and validation; (ii) a quantitative assessment of proposals; and (iii) adjustments to selections based on proposals’ qualitative attributes. SCE applied these criteria to the proposals received in its 2013 RPS RFP in order to establish a short list of proposals from sellers with whom SCE would engage in a final round of contract discussions. Prior to receiving proposals, SCE finalized the short list selection criteria with the Independent Evaluator (“IE”). SCE then finalized the major assumptions and methodologies that underlie SCE’s valuation, including power and gas price forecasts, SCE’s existing and forecast resource portfolio, and SCE’s firm capacity value forecast. SCE also finalized and published congestion adders for sellers to use in preparing their proposals. Once proposals were received, SCE began an initial review of proposals for completeness and conformity with the solicitation protocol. The review included an initial screen for required submission criteria such as a conforming delivery point, commercial operation date in 2016 or later, a valid interconnection study, minimum project size, and the submission of particular proposal package elements. Sellers lacking any of these items were allowed a reasonable cure period to remedy any deficiencies. Following this check for conformity, SCE 9 The Commission has also made rulings on various evaluation criteria in its decisions on the IOUs’ RPS procurement plans. ADVICE 3121-E (U 338-E) -9- October 28, 2014 conducted an additional review to determine the reasonableness of proposal parameters such as generation profiles and capacity factors. SCE worked directly with sellers to resolve any issues and ensure the data was ready for evaluation. After these reviews, SCE performed a quantitative assessment of each proposal individually and subsequently ranked them based on the proposal’s benefit and cost relationship. Specifically, the total benefits and total costs were used to calculate the net levelized cost or “renewable premium” for each complete and conforming proposal. Benefits were comprised of separate capacity, energy, and congestion components, while costs included the contract payments, debt equivalence, congestion cost, and transmission cost. SCE discounted the monthly benefit and cost streams to a common base date. The result of the quantitative analysis was a merit-order ranking of all complete and conforming proposals’ renewable premiums that helped define the preliminary short list. In parallel with the quantitative analysis, SCE conducted an in-depth assessment of the qualitative attributes of the top proposals with a competitive renewable premium. This analysis utilized the Project Viability Calculator to assess certain factors, including the company/development team, technology, and development milestones. Additional attributes such as transmission area, facility interconnection process progress, portfolio fit of commercial operation date, resource diversity, and counterparty concentration were also considered in the qualitative analysis. These qualitative attributes were then considered to either eliminate non-viable proposals or add projects with high viability or other beneficial qualitative attributes to the final short list of proposals, or to break ties, if any. Following both its quantitative and qualitative analyses, SCE consulted with its Procurement Review Group (“PRG”) regarding the final short list and specific evaluation criteria. SCE then negotiated with the shortlisted sellers for a 90 day period. At the end of the contract negotiation period, all sellers that completed negotiations had a one-time opportunity to submit new pricing. SCE then made final selections based on the new pricing and consulted with its IE and the PRG prior to the execution of the successfully negotiated contracts. SCE’s 2013 RPS Short List Report was submitted to the Commission on April 21, 2014 in Advice 3029-E. On June 26, 2014, SCE filed a supplement to Advice 3029-E to identify two projects that withdrew from the short list. The Energy Division approved SCE’s 2013 RPS Short List Report effective as of July 8, 2014. Using the SCE’s LCBF methodology, the Mount Signal Projects compared favorably to other proposals received in the 2013 RPS RFP, as well as other procurement options available to SCE. ADVICE 3121-E (U 338-E) C. - 10 - October 28, 2014 Compliance With Standard Terms and Conditions In D.04-06-014, the Commission established a number of “modifiable” and “nonmodifiable” standard terms and conditions to be used by retail sellers when contracting for RPS-eligible resources.10 In D.07-11-025, the Commission reduced the number of non-modifiable terms to the following four terms: (1) “CPUC Approval;” (2) “RECs and Green Attributes;”11 (3) “Eligibility;” and (4) “Applicable Law.”12 The remaining non-modifiable terms were converted to modifiable terms.13 In D.10-03-021, as modified by D.11-01-025, the Commission added two new non-modifiable standard terms and conditions for both bundled contracts and contracts for renewable energy credits (“RECs”) only: (1) “Transfer of Renewable Energy Credits;” and (2) “Tracking of RECs in WREGIS.”14 The Commission also added a new version of the non-modifiable “CPUC Approval” standard term and condition for REC-only contracts, and held that the non-modifiable “Applicable Law” standard term and condition also applies to REC-only contracts.15 In D.13-11-024, the Commission updated the non-modifiable “RECs and Green Attributes” term to a modifiable “Bioenergy Transactions” term.16 The Mount Signal Contracts include all non-modifiable standard terms and conditions for bundled contracts without change as indicated in the table below. NON-MODIFIABLE TERM CONTRACT SECTION NUMBER CONTRACT PAGE NUMBER STC 1: CPUC Approval Exhibit A, #57 (See also Section 2.01) Exhibit A, page 5 (Section 2.01 is on page 9) STC 6: Eligibility 10.02(b) Page 61 STC 17: Applicable Law 10.07 Page 67 STC REC 1: Transfer of RECs 10.02(c) Page 61 10 11 12 13 14 15 16 D.04-06-014 at 20 (Ordering Paragraph 1) and Appendix A. In D.08-08-028, Appendix B, the Commission revised the non-modifiable “RECs and Green Attributes” standard term and condition. D.07-11-025 at 33 (Ordering Paragraph 1.a). Id. at 34 (Ordering Paragraph 1.b). Subsequently, in D.08-04-009, the Commission compiled the standard terms and conditions in one document and deleted the modifiable standard term and condition on supplemental energy payments. D.11-01-025 at 46 (Ordering Paragraph 3.P). Id. at 47-48 (Ordering Paragraph 3.Q). D.13-11-024 at 24-25, 70 (Ordering Paragraph 6). ADVICE 3121-E (U 338-E) STC REC 2: Tracking of RECs in WREGIS - 11 - 10.02(e) October 28, 2014 Page 61 Comparisons of the Mount Signal II Contract and Mount Signal V Contract against SCE’s 2013 Pro Forma Renewable Power Purchase and Sale Agreement are provided in Appendix E. D. Portfolio Content Category Claim and Upfront Showing In D.11-12-052, the Commission found that “[a] retail seller claiming that procurement for compliance with the California renewables portfolio standard from a procurement contract or ownership agreement signed . . . on or after June 1, 2010 counts in the portfolio content category described in Pub. Util. Code § 399.16(b)(1), must provide information to the Director of Energy Division sufficient to demonstrate that the generation facility from which the electricity is procured is certified as eligible for the California renewables portfolio standard.”17 Additionally, retail sellers claiming procurement counts as a Category 1 product must provide information to the Energy Division Director sufficient to demonstrate that the generating facility from which the electricity is procured meets the statutory definition of Category 1 products set forth in Public Utilities Code Section 399.16(b)(1).18 One way to make this demonstration is to show that the facility “has its first point of interconnection to the Western Electricity Coordinating Council transmission grid within the metered boundaries of a California balancing authority area.”19 “The retail seller must also demonstrate that the renewable energy credits originally associated with the electricity have not been unbundled and transferred to another owner, and that all other requirements for procurement for compliance with the California renewables portfolio standard are met by the procurement.”20 Furthermore, D.11-12-052 provides that the utilities, in seeking approval of contracts for procurement, should enable the Commission to evaluate the following: “the claimed portfolio content category of the proposed procurement; the risks that the procurement will not ultimately be classified in the claimed portfolio content category; the value to ratepayers of the procurement as proposed and the value to ratepayers if the procurement is not ultimately classified in the claimed portfolio content category.”21 17 18 19 20 21 D.11-12-052 at 75-76 (Ordering Paragraph 1). See id. Id. Id. at 76 (Ordering Paragraph 1). Id. at 80 (Ordering Paragraph 9). ADVICE 3121-E (U 338-E) - 12 - October 28, 2014 Pursuant to the provisions of the Mount Signal Contracts, SCE will procure energy (and associated renewable energy attributes via Western Renewable Energy Generation Information System (“WREGIS”) certificates) generated from California-based eligible renewable resources with a first point of interconnection within the CAISO. In addition, per the contracts, the Mount Signal Projects must obtain and keep current California Energy Commission (“CEC”) certification as ERRs,22 as well as perform all actions necessary to effectuate the transfer of RECs to SCE in WREGIS. The RECs associated with the electricity from the Mount Signal Projects are yet to be delivered and therefore have not been unbundled or transferred to another owner. Such RECs will be transferred to SCE pursuant to the terms of the Mount Signal II Contract and Mount Signal V Contract, respectively. Accordingly, these contracts are Category 1 transactions pursuant to the Public Utilities Code Section 399.16(b)(1) and D.11-12-052.23 A risk that the Mount Signal Contracts will fail to deliver Category 1 RECs has not been identified. Forecast of Portfolio Balance Requirements24 Compliance Period 2 (2014-2016) GWh Compliance Period 3 (2017-2020) GWh PCC 1 Balance Requirement CP 2 = 65% of RECs applied to procurement quantity requirement CP 3 = 75% of RECs applied to procurement quantity requirement Quantity of PCC 1 RECs25 (under contract, not including proposed contract) 8,622 33,633 Quantity of PCC 1 RECs from proposed contract 0 1,573 0 0 Quantity of PCC 2 RECs (under contract, not including proposed contract) 22 23 24 25 The projects must qualify and be certified by the CEC as ERRs as that term is defined in Public Utilities Code Section 399.12(e). D.11-12-052 at 75-76 (Ordering Paragraph 1). SCE’s forecast assumes a 100% success rate for projects in development, not yet online. The “Quantity of PCC 1 RECs (under contract, not including proposed contract)” represents the total forecasted energy deliveries for all executed RPS eligible contracts, including the 2013 RPS RFP contracts, minus the forecasted energy deliveries from the Mount Signal Contracts. ADVICE 3121-E (U 338-E) - 13 - Quantity of PCC 2 RECs from proposed contract 0 October 28, 2014 0 PCC 3 Balance Limitation CP 2 = 15% of RECs applied to procurement quantity requirement CP 3 = 10% of RECs applied to procurement quantity requirement Quantity of PCC 3 RECs (under contract, not including proposed contract) 0 0 Quantity of PCC 3 RECs from proposed contract 0 0 E. Long-Term Contracting Requirement In D.12-06-038, the Commission held that, “[i]n order to count procurement from contracts of less than 10 years duration signed after June 1, 2010 for compliance with the California renewables portfolio standard in a compliance period, a retail seller . . . must sign in the compliance period in which the short-term contract is signed, contracts of at least 10 years in duration with expected generation equal to at least 0.25 percent of its retail sales for the immediately prior compliance period.”26 Because there was not a compliance period prior to the 2011-2013 compliance period, the requirement is 0.25 percent of 2010 retail sales for that compliance period.27 The Mount Signal Contracts are 20-year contracts. Therefore, the long-term contracting requirement does not apply. F. Interim Emissions Performance Standard The California Legislature passed Senate Bill (“SB”) 1368 on August 31, 2006, and Governor Schwarzenegger signed the bill into law on September 29, 2006. Section 2 of SB 1368 adds Public Utilities Code Section 8341(a), which provides, “No load-serving entity or local publicly owned electric utility may enter into a long-term financial commitment unless any baseload generation supplied under the long-term financial commitment complies with the greenhouse gases emission performance standard established by the commission, pursuant to subdivision (d), for a load serving entity . . . .”28 In order to institute the provisions of SB 1368, the Commission instituted Rulemaking 06-04-009. That proceeding resulted in the establishment of a 26 27 28 D.12-06-038 at 98 (Ordering Paragraph 15). See id. at 98 (Ordering Paragraph 16). Cal. Pub. Util. Code § 8341(a). ADVICE 3121-E (U 338-E) - 14 - October 28, 2014 greenhouse gas (“GHG”) emissions performance standard (“EPS”), for carbon dioxide (“CO2”). In D.07-01-039, the Commission noted, “SB 1368 establishes a minimum performance requirement for any long-term financial commitment for baseload generation that will be supplying power to California ratepayers. The new law establishes that the GHG emissions rates for these facilities must be no higher than the GHG emissions rate of a combined-cycle gas turbine (‘CCGT’) powerplant.”29 The decision further explains: SB 1368 describes what types of generation and financial commitments will be subject to the EPS (“covered procurements”). Under SB 1368, the EPS applies to “baseload generation,” but the requirement to comply with it is triggered only if there is a “longterm financial commitment” by an LSE. The statute defines baseload generation as “electricity generation from a powerplant that is designed and intended to provide electricity at an annualized plant capacity factor of at least 60%.” . . . For baseload generation procured under contract, there is a long-term commitment when the LSE enters into “a new or renewed contract with a term of five or more years.”30 The Mount Signal Contracts are exempt from EPS regulations because they have an expected annualized capacity factor well below the threshold baseload capacity factor of 60%, above which the EPS rules would apply.31 G. PRG Participation SCE’s PRG was formed on or around September 10, 2002. Participants include representatives from various divisions within the Commission, the Office of Ratepayer Advocates, The Utility Reform Network, California Utility Employees, the Union of Concerned Scientists, and the California Department of Water Resources. SCE consulted with its PRG during each milestone of the 2013 RPS solicitation process. Among other things, SCE informed the PRG of the initial results of its RFP, explained the evaluation process, and updated the PRG periodically concerning the status of contract formation. On March 19, 2014, SCE advised the PRG of its proposed short list of bids for its 2013 RPS solicitation. On July 16, 2014, SCE briefed the PRG on the proposed execution of the Mount Signal Contracts. 29 30 31 D.07-01-039 at 2-3. Id. at 4. See id., Attachment 7 at 1. ADVICE 3121-E (U 338-E) H. - 15 - October 28, 2014 IE The IE for the 2013 RPS solicitation was Merrimack Energy Group, Inc. The IE joined and contributed to a number of conference calls and negotiation sessions. In addition, the IE reviewed email traffic, the Mount Signal Contracts, and other documents exchanged by the parties. The IE also participated in the PRG review. The IE Report is included as Appendix C. III. PROJECT DEVELOPMENT STATUS32 A. Company/Development Team The Mount Signal Projects are owned by a joint venture between SRP and 8me. SRP is an equal venture between SunEdison, Inc. and Riverstone Holdings, LLC, and is experienced in developing, financing, constructing, and operating largescale PV installations. SRP currently has more than 500 MW of PV projects in operation and employs a team of more than 100 professionals. 8me is an experienced developer in California, focused on land acquisition and interconnection for solar projects both independently and as a co-development partner for the past four years. Most recently, together SRP and 8me completed development of the Mount Signal Solar Farm I, a 200 MW solar PV facility that began generating in May, 2014. B. Technology 1. Technology Type and Level of Technology Maturity The Mount Signal Projects will use mature and proven solar PV technology from financeable panel, inverter, and racking system manufacturers with proven deployment on utility-scale generation projects. The projects will not deploy early stage or unproven technologies. All technologies will be designed for utility-scale operation with significant operating history. 32 Some of the information in this section was provided by Sellers and not independently verified by SCE. ADVICE 3121-E (U 338-E) 2. - 16 - October 28, 2014 Quality of Renewable Resource The Mount Signal Projects are located in Southern Imperial County, California, an area well-recognized for its robust solar resources as demonstrated by several sources of solar generation throughout the region. SCE believes that the Mount Signal Projects will be able to meet the terms of the contracts given the quality of the renewable resources, which is substantiated by the projects’ location. 3. Other Resources Required No additional fuel supply is required for the Mount Signal Projects. The water supply is anticipated to be sufficient to cover the projects’ expected need. C. Development Milestones 1. Site Control The Mount Signal Projects will both be located in the City of Calexico, California. Additional information regarding site control is included in Appendix A. 2. Equipment Procurement As of the filing date of this Advice Letter, neither 88FT 8me LLC nor 93LF 8me LLC have identified any equipment procurement issues that will affect the projects’ ability to meet their respective commercial operation dates. Additional information is included in Appendix A. 3. Permitting/Certifications Status Information regarding permitting/certifications status is included in Appendix A. 4. Production Tax Credits (“PTCs”) / Investment Tax Credits (“ITCs”) Information regarding PTCs and ITCs is provided in Appendix A. 5. Transmission Information regarding transmission is provided in Appendix A. D. Financing Plan Information regarding financing is provided in Appendix A. ADVICE 3121-E (U 338-E) IV. - 17 - October 28, 2014 CONTINGENCIES AND MILESTONES The Mount Signal Solar Farm II Project is expected to begin commercial operation on June 1, 2020. The Mount Signal Solar Farm V Project is expected to begin commercial operation on February 1, 2019. Specific information regarding performance criteria and guaranteed milestones is provided in Appendices D.1 through F. V. SAFETY CONSIDERATIONS SCE is strongly committed to safety in all aspects of its business. Renewable sellers are responsible for the safe construction and operation of their generating facilities and compliance with all applicable safety regulations. SCE has taken several steps to address those issues over which it has the most visibility and control – the delivery of renewable electricity products to SCE in a reliable, safe, and operationally sound manner. SCE’s 2013 Pro Forma Renewable Power Purchase and Sale Agreement already provided that the seller must operate the generating facility in accordance with Prudent Electrical Practices.33 Consistent with SCE’s focus on safety, SCE added a provision to its 2013 Pro Forma Renewable Power Purchase and Sale Agreement providing that, prior to commencement of any construction activities on the project site, the seller must provide to SCE a report from an independent engineer certifying that the seller has a written plan for the safe construction and operation of the generating facility in accordance with Prudent Electrical Practices.34 See Appendix D for more details. 33 34 See Final 2013 RPS Plan, Appendix G.1 at Section 3.12(a), Exhibit A, #215. Prudent Electrical Practices means “those practices, methods and acts that would be implemented and followed by prudent operators of electric generating facilities in the Western United States, similar to the Generating Facility, during the relevant time period, which practices, methods and acts, in the exercise of prudent and responsible professional judgment in the light of the facts known at the time a decision was made, could reasonably have been expected to accomplish the desired result consistent with good business practices, reliability and safety.” Prudent Electrical Practices includes, “at a minimum, those professionally responsible practices, methods and acts described in the preceding sentence that comply with the manufacturer’s warranties, restrictions in this Agreement, and the requirement of Governmental Authorities, WECC standards, the CAISO and Applicable Laws....” See id., Appendix G.1, Section 3.11(e). ADVICE 3121-E (U 338-E) VI. - 18 - October 28, 2014 REQUEST FOR COMMISSION APPROVAL The terms of the Mount Signal Contracts are conditioned on the occurrence of final “CPUC Approval,” as it is described in the Mount Signal Contracts. In order to satisfy that condition with respect to the Mount Signal Contracts, SCE requests that the Commission issue a final resolution no later than April 28, 2015, containing: 1. Approval of the Mount Signal Contracts in their entirety; 2. A finding that the Mount Signal Contracts are consistent with SCE’s 2013 RPS Procurement Plan; 3. A finding that the Mount Signal Contracts are compliant with the Emissions Performance Standard; 4. A finding that any procurement pursuant to the Mount Signal Contracts is procurement from eligible renewable energy resources for purposes of determining SCE’s compliance with any obligation that it may have to procure eligible renewable energy resources pursuant to the California Renewables Portfolio Standard (Public Utilities Code Section 399.11 et seq.), Decision 03-06-071, or other applicable law; 5. A finding that the Mount Signal Contracts, and SCE’s entry into them, is reasonable and prudent for all purposes, including, but not limited to, recovery in rates of payments made pursuant to the Mount Signal Contracts and administrative costs associated with the Mount Signal Contracts, subject only to further review with respect to the reasonableness of SCE’s administration of the Mount Signal Contracts; and 6. Any other and further relief as the Commission finds just and reasonable. VII. TIER DESIGNATION Pursuant to GO 96-B, Energy Industry Rule 5.3, SCE submits this Advice Letter with a Tier 3 designation (effective after Commission approval). VIII. EFFECTIVE DATE This Advice Letter will become effective upon Commission approval. IX. NOTICE Anyone wishing to protest this advice letter may do so by letter via U.S. Mail, facsimile, or electronically, any of which must be received by the Energy Division ADVICE 3121-E (U 338-E) - 19 - October 28, 2014 and SCE no later than 20 days after the date of this advice letter. Protests should be mailed to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Copies should also be mailed to the attention of the Director, Energy Division, Room 4004 (same address as above). In addition, protests and other correspondence regarding this advice letter should also be sent by letter and transmitted via facsimile or electronically to the attention of: Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: AdviceTariffManager@sce.com ADVICE 3121-E (U 338-E) - 20 - October 28, 2014 Michael R. Hoover Director, State Regulatory Affairs Southern California Edison Company c/o Karyn Gansecki 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com With a copy to: Amber Wyatt Senior Attorney Southern California Edison Company 2244 Walnut Grove Avenue, 3rd Floor Rosemead, CA 91770 Facsimile: 626-302-3990 E-mail: amber.wyatt@sce.com There are no restrictions on who may file a protest, but the protest shall set forth specifically the grounds upon which it is based and shall be submitted expeditiously. In accordance with Section 4 of GO 96-B, SCE is furnishing copies of this Advice Letter to the interested parties shown on the attached R.11-05-005 and GO 96-B service lists. Address change requests to the GO 96-B service list should be directed to AdviceTariffManager@sce.com or (626) 302-4039. For changes to any other service list, please contact the Commission’s Process Office at (415) 703-2021 or Process_Office@cpuc.ca.gov. Further, in accordance with Public Utilities Code Section 491, notice to the public is hereby given by filing and keeping the Advice Letter at SCE’s corporate headquarters. To view other SCE advice letters filed with the Commission, log on to SCE’s web site at https://www.sce.com/wps/portal/home/regulatory/adviceletters ADVICE 3121-E (U 338-E) - 21 - October 28, 2014 All questions concerning this Advice Letter should be directed to Katie Sloan at (626) 302-6842 or by electronic mail at Katie.Sloan@sce.com. Southern California Edison Company /s/ Megan Scott-Kakures Megan Scott-Kakures MSK:ks:jm Enclosures CALIFORNIA PUBLIC UTILITIES COMMISSION ADVICE LETTER FILING SUMMARY ENERGY UTILITY MUST BE COMPLETED BY UTILITY (Attach additional pages as needed) Company name/CPUC Utility No.: Southern California Edison Company (U 338-E) Utility type: Contact Person: Darrah Morgan ELC GAS PLC HEAT Phone #: (626) 302-2086 WATER E-mail: Darrah.Morgan@sce.com E-mail Disposition Notice to: AdviceTariffManager@sce.com EXPLANATION OF UTILITY TYPE ELC = Electric PLC = Pipeline GAS = Gas HEAT = Heat Advice Letter (AL) #: Subject of AL: (Date Filed/ Received Stamp by CPUC) WATER = Water 3121-E Tier Designation: 3 Submission of Contract for Procurement of Renewable Energy From SCE’s 2013 Renewables Portfolio Standard Solicitation Keywords (choose from CPUC listing): Compliance, Agreement, Procurement AL filing type: Monthly Quarterly Annual One-Time Other If AL filed in compliance with a Commission order, indicate relevant Decision/Resolution #: Does AL replace a withdrawn or rejected AL? If so, identify the prior AL: Summarize differences between the AL and the prior withdrawn or rejected AL: Confidential treatment requested? Yes No If yes, specification of confidential information: See Appendix H Confidential information will be made available to appropriate parties who execute a nondisclosure agreement. Name and contact information to request nondisclosure agreement/access to confidential information: Amber Wyatt, Law Department, (626) 302-6961 or Amber.Wyatt@sce.com Resolution Required? Yes No Requested effective date: 4/28/15 No. of tariff sheets: -0- Estimated system annual revenue effect: (%): Estimated system average rate effect (%): When rates are affected by AL, include attachment in AL showing average rate effects on customer classes (residential, small commercial, large C/I, agricultural, lighting). Tariff schedules affected: None Service affected and changes proposed1: Pending advice letters that revise the same tariff sheets: 1 Discuss in AL if more space is needed. N/A Protests and all other correspondence regarding this AL are due no later than 20 days after the date of this filing, unless otherwise authorized by the Commission, and shall be sent to: CPUC, Energy Division Attention: Tariff Unit 505 Van Ness Avenue San Francisco, California 94102 E-mail: EDTariffUnit@cpuc.ca.gov Megan Scott-Kakures Vice President, Regulatory Operations Southern California Edison Company 8631 Rush Street Rosemead, California 91770 Facsimile: (626) 302-4829 E-mail: AdviceTariffManager@sce.com Michael R. Hoover Director, State Regulatory Affairs c/o Karyn Gansecki Southern California Edison Company 601 Van Ness Avenue, Suite 2030 San Francisco, California 94102 Facsimile: (415) 929-5544 E-mail: Karyn.Gansecki@sce.com With a copy to: Amber Wyatt Senior Attorney 2244 Walnut Grove Avenue, 3rd Floor Rosemead, California 91770 Facsimile: (626) 302-3990 E-mail: Amber.Wyatt@sce.com Confidential Appendix A Consistency with Commission Decisions and Rules and Project Development Status Confidential Appendix B 2013 Solicitation Overview Confidential Appendix C Independent Evaluator Report Public Appendix C Independent Evaluator Report Southern California Edison Company 2013 Renewable Resource Solicitation Report of the Independent Evaluator Final Selection Process and Review of Power Purchase Agreements with 88FT 8me LLC and 93LF 8me LLC October 2014 Prepared by Merrimack Energy Group, Inc. Merrimack M Energy and New Energy Opportunities, Inc. Table of Contents Executive Summary …………………………………………………………………….. 2 I. 2013 Renewable RFP Overview……………….…………………….……….………9 II. Role of the Independent Evaluator……………………..………………..……….….12 III. Adequacy of Outreach to Potential Sellers…….. …………………………………..18 IV. Fairness and Appropriateness of RPS Bid Evaluation and Selection Methodology. 24 V. Administration of the Bid Evaluation Process ………………………………………38 VI. Approval of Shortlist…………………………………………………………….… 54 VII. Fairness of Project Specific Negotiations ………………………………………….57 VIII. Does the Contract Merit CPUC Approval ………………………………………..66 Appendix A: SCE’s Least Cost Best Fit Evaluation Methodology Appendix B: SCE 2013 RPS RFP Proposal List and Summary Appendix C: SCE Shortlisted Proposals – 2013 RPS RFP Appendix D: Indicative and Final Pricing – 2013 RPS RFP Appendix E: SCE Final Evaluation Results Merrimack Energy Group, Inc. 1 Executive Summary Effective July 31, 2014, Southern California Edison Company (“SCE”) executed power purchase agreements (“PPAs”) with 88FT 8me LLC (“Mount Signal Solar Farm II”) and 93LF 8me LLC (“Mount Signal Solar Farm V”)1 for the purchase of all the electric energy, capacity, Resource Adequacy (“RA”) benefits, and Green Attributes produced by both generating facilities.2 Mount Signal Solar Farm II is a proposed 153.52 MW (AC) solar photovoltaic (“PV”) generating facility and Mount Signal Solar Farm V is a 252.32 MW AC solar PV generating facility. Both projects are to be constructed near the City of Calexico in southern Imperial County, California pursuant to SCE’s 2013 Request for Proposals from Eligible Renewable Energy Resource Suppliers for Renewable Products (“2013 Renewable RFP”). SCE launched the 2013 Renewable RFP on January 6, 2014, received indicative bids on January 31, 2014, and received final offers on June 25, 2014. On July 29, 2014 and July 31, 2014, SCE signed eight power purchase agreements for capacity, energy and other products from eight different projects representing a total of approximately 1,550 MW, including 153.52 MW of energy, capacity and Green Attributes purchased under the PPA with 88FT 8me LLC and 252.32 MW purchased under the PPA with 93LF 8me LLC.3 Through the 2013 Renewable RFP solicitation, SCE sought Proposals for products qualifying as Portfolio Content Category 14 which includes all electric energy produced by an Eligible Renewable Energy Resource (“ERR” or “ERR Generating Facility”) as well as all attributes, including all Green Attributes, all Capacity Attributes, and all Resource Adequacy Benefits generated by, associated with or attributable to the output of the ERR Generating Facility. Pursuant to the 2013 Renewable RFP, SCE received a large number of proposals from renewable energy developers, reviewed and evaluated the proposals relative to the eligibility and conformance requirements listed in the Protocol 1 The proposals for Mount Signal Solar Farms II and V 2 SCE is submitting one Advice Letter filing for both projects since the PPAs are identical with regard to all terms with the exception of project specific information. 3 Capitalized terms when used with reference to the 8 Minute Energy Mount Signal PPAs and not otherwise defined herein are as defined in the PPAs. 4 The first portfolio content category (“Category 1”) is delineated in the California Public Utilities Commission’s Decision Implementing Portfolio Content Categories for the Renewables Portfolio Standard Program, D. 11-12-052 (2011). It consists of products from renewable energy generators: with a first point of interconnection to the Western Electric Coordinating Council transmission system within the boundaries of a California Balancing Authority Area (“CBA”); or with a first point of interconnection with an electricity distribution system used to serve end users within the boundaries of a CBA; or where the renewable generation is scheduled into a CBA without substituting electricity from another source; or where the generation from the renewable facility is dynamically transferred to a CBA. Merrimack Energy Group, Inc. 2 Document, evaluated and ranked the proposals, and determined which of those offers to include on a short list for potential negotiations and contracting.5 In March 2014, SCE selected including three geothermal projects selected out of economic rank order, the 1,600 GWh/year target for this solicitation. Subsequent to short list selection on or around March 19, 2014, for the next three months, SCE negotiated contract terms with shortlisted bidders. Remaining Sellers who had completed negotiations of a final Agreement were allowed to submit refreshed prices for their project(s). Of the shortlisted projects, SCE selected a total of eight projects with expected annual output of 5,466 GWh or approximately 3.4 times need. Among the selected offers were seven solar PV proposals, totaling 3,494 GWh/year, representing 2 times need. In addition, SCE selected a proposal for energy, capacity and Green Attributes from Calpine’s geothermal Geysers project with annual output of 1,972 GWh/year, Table ES-1 provides a short description of the projects for which contracts were executed. Tables ES-1: Executed Contracts from 2013 Renewable Energy Solicitation Selller Recurrent Energy 8 Minutenergy Renewables Sempra First Solar/Tribal Solar 8 Minutenergy Renewables and Silver Ridge Power Panoche Valley Project Name Tranquillity Type Vintage New Start Date 2019 Term (Years) 15 Capacity (MW) 206 Solar PV Borden Solar Farms Copper Mountain Solar Fort Mojave Solar Mount Signal Solar II Solar PV New 2020 20 51 Solar PV New 2020 20 94 Solar PV New 2019 20 328 Solar PV New 2020 20 154 Panoche Solar PV New 2019 20 247 5 SCE implemented a two-step evaluation process for this solicitation. The shortlist selection was the first step in the process. After shortlist selection, SCE initiated contract negotiations with shortlisted projects. At the end of the negotiation period, Sellers who had reached agreement with SCE on the terms of a PPA have a one-time opportunity to submit a final revised price. SCE made final selections and entered into final PPAs based on the revised pricing and a quantitative and qualitative evaluation of the project proposals. Merrimack Energy Group, Inc. 3 Solar, LLC 8 Minutenergy Renewables and Silver Ridge Power Calpine Valley Solar Mount Signal Solar V Geysers Power Solar PV New 2019 20 252 Geothermal Existing 2017 10 225 The Mount Signal Solar Farm II project is a 153.52 MW (AC) single axis tracking solar PV project located in southern Imperial County, California near the City of Calexico. The project is expected to produce approximately 402 GWh annually with an approximately 31% capacity factor and thereafter. The date for commencement of deliveries under the PPA is June 1, 2020, The Mount Signal Solar Farm V project is a 252.32 MW (AC) single axis tracking solar PV project located in southern Imperial County, California near the City of Calexico. The project is expected to produce approximately 660 GWh annually with an approximately 31% capacity factor and thereafter. The date for commencement of deliveries under the PPA is February 1, 2019, 7 The delivery term under both PPAs is 20 years. Prior to the launch of the RFP, SCE retained Merrimack Energy Group, Inc. (“Merrimack Energy”) as the Independent Evaluator (“IE”) for the 2013 Renewable RFP in accordance with regulatory requirements of the California Public Utilities Commission (“CPUC” or “Commission”),8 Following the receipt and evaluation of proposals and selection of the shortlist, Merrimack Energy submitted its Report on the Bid Evaluation and Short List Selection Process and Results (“IE Short List Report”), which was filed with SCE’s advice letter seeking approval of the short list.9 The Office of Ratepayer Advocates filed a protest to SCE’s short listing of the geothermal projects selected out of economic rank order, to which SCE filed a reply supporting its short list. The Energy Division’s Director issued a letter order making the shortlist effective as of July 8, 2014. 7 26 U.S.C. § 48. New Energy Opportunities, Inc. is serving as a subcontractor to Merrimack Energy in this engagement. 9 Advice 3029-E, dated April 21, 2014. 8 Merrimack Energy Group, Inc. 4 As addressed in the IE Short List Report, the IE is required to conduct a range of activities to review, assess, and scrutinize SCE’s processes in implementing its solicitation process. Generally, Merrimack Energy found that the short listing decisions were reasonable based on the 2013 Renewable RFP requirements and evaluation criteria set forth in SCE’s Procurement Protocol.10 The primary purpose of this report is (1) to describe and assess the fairness of the RFP process following SCE’s short listing decisions, which includes (a) a three-month period during which SCE and short listed bidders negotiated contract terms and conditions, (b) bidder submission of final pricing, and (c) SCE’s evaluation of the final offers, final selection decisions, and execution of PPAs; and (2) to describe, with specificity, the fairness of the contract negotiation process with respect to the Mount Signal II and Mount Signal V PPAs, the price, economic ranking, and other attributes of the Mount Signal II and Mount Signal V PPAs, and whether the PPAs merit Commission approval. In addition, this report includes an assessment of the entire RFP process, including a description of IE activities and assessment of SCE’s process from the IE Short List Report to final selection. Key findings are outlined in this executive summary. SCE’s outreach activities, which included contacting a large number of prospective Sellers, holding a RFP Conference for prospective Sellers, and disseminating substantial information about the RFP on its website or the Accion Power website, were effective. This was evidenced by the robust response to the RFP in terms of number of proposals, types of resources proposed, initial delivery dates and maturity of the proposals submitted. SCE’s approach adopted for this RFP was to apply fairly strict threshold requirements, notably, that Sellers had to have a Phase II Interconnection Study or equivalent in order to participate. Although the number of proposals received in this RFP was lower than recent RPS solicitations, the response was still very competitive with more mature and viable projects competing. This solicitation represented the first time SCE used a two-step process for this type of RFP. Under this approach, once proposals are received, SCE begins an initial review for completeness and conformity with the Procurement Protocol. After or during this review and assessment, SCE performs a quantitative assessment of each proposal individually and subsequently ranks them based on the Proposal’s benefit and cost relationship. The result of the quantitative analysis is a merit-order ranking of all complete and conforming Proposals’ Renewable Premiums that help define the preliminary shortlist. Based on this analysis and qualitative considerations, a shortlist is selected. In the second step, SCE negotiates with the shortlisted Sellers for a set period of time, and at the end of the negotiation period, all Sellers that are able to complete negotiations have a one-time opportunity to submit refreshed pricing. SCE then makes final selections and enters into any final Agreements based on the new pricing. 10 The Procurement Protocol is a public document describing the renewable energy products being sought, the 2013 Renewable RFP submission requirements, and SCE’s preferences and evaluation criteria. Merrimack Energy Group, Inc. 5 This two-step process has several advantages and disadvantages relative to the one-step process where a utility negotiates PPAs after it has selected bidders with which to negotiate based on their price offers. Since a bidder in a two-step process will need to expend resources to negotiate a PPA without knowing whether it will obtain an agreement, even if contract terms are agreed upon, the tendency is that bidders will participate in this process only if they believe their projects are reasonably mature, have a reasonable chance of winning, and have the financial strength to assume this risk. In addition, the pricing contained in the final contract reflects the entirety of the risk profile in the contract executed by the parties, which should allow for “tighter” (i.e., lower) pricing. Finally, the process provides for a pre-defined timeframe (that SCE was able to implement punctually), which provides bidders with temporal certainty that is helpful to many bidders as they progress in their project development cycle. One of the major disadvantages of the process is the high cost and associated uncertainty to Sellers who proceed through the negotiation process to final offer submission. The time and cost of negotiations for cases where a contract may not be secured can be substantial. Similarly, there is an additional cost to SCE, at least in terms of staff and management time, to negotiate more PPAs than will obtain contracts. Ultimately, the question is whether the process overall results in net benefits in terms of lower net costs to ratepayers, more ratepayer-friendly PPA terms, and projects which are more likely to be built due to their greater maturity, lower project risk, and greater experience, capability and financial strength of their developers. Overall, SCE maintained its schedule as outlined. Follow-up discussions with Shortlisted Sellers (both with those that did and did not secure a contract) after completion of the solicitation process illustrated that these Sellers felt the process was reasonable and was conducted efficiently and in a timely manner by SCE (although not all favored the twostep process). All in all, the RFP process was fairly and timely conducted. In terms of the selection process, SCE exercised discretion, primarily involving three decisions that involved selection of projects not based entirely on rank order based on the renewable premium metric: 1. Both in the shortlisting process and final selection process, SCE included in its quantitative assessment network upgrade costs of projects interconnecting with the Imperial Irrigation District (“IID”). SCE has traditionally not included reimbursable network upgrade costs from balancing authorities other than the California Independent System Operator (“CAISO”) in its RPS evaluation process as transmission adders for the reason that under existing CAISO tariffs IID customers and not California investorowned utility customers will ultimately pay for such transmission upgrades.11 SCE’s management determined that it imposed a risk on SCE’s customers not to include the cost of such upgrades in its evaluation due to the risk that as IID network upgrade costs increase to help support renewable projects to meet California’s RPS obligations that the costs may ultimately be charged to CAISO 11 The Procurement Documents do not address this issue specifically. Merrimack Energy Group, Inc. 6 and the California investor-owned utilities and their customers. Once these IID transmission network upgrade costs were incorporated in SCE’s evaluation, three solar PV projects fell out of economic rank order in the shortlist evaluation and were not shortlisted. 2. In the final evaluation, SCE revised its congestion forecast for Four Corners resources since congestion at Four Corners will be significantly reduced with the termination of historical deliveries of baseload power to SCE from Four Corners as a result of SCE’s sale of Four Corners Steam Plant Units 4 and 5 to Arizona Public Service Company.12 This affected the evaluation of two projects. Despite the fact that the modification to the expected evaluation methodology improved the projects’ renewable premiums, it did not result in either project being among those in economic rank order based on the 2 times need cut-off. The foregoing modifications to the renewable premium evaluation methodology—inclusion of IID network upgrade costs and revised congestion costs for Four Corners—were referred to by SCE as the “Alternative Renewable Premium,” which SCE used in the final evaluation for economic rank ordering of offers. 3. In the final selection process, SCE selected a proposal for 225 MW of baseload renewable energy from the Geysers geothermal project As an existing facility, the project had little if any project viability risk. It offered fuel diversity in the context of expectations of substantially higher solar PV penetration. Baseload renewable energy provides more predictable output and the expectation of reduced need for increasing SCE’s voluntary margin of over procurement. The methodology and proposed short list selection were vetted with the PRG as were the final selections. 12 The methodology used to derive the congestion forecast used a blend of historical information and a simulation-based forward-looking forecast. Since the Four Corners generating facility will no longer be delivering power to California, SCE believed it was more appropriate to use the congestion forecast only and not include the historical component. The revised congestion forecast for Four Corners did not take into account historical congestion. Merrimack Energy Group, Inc. 7 In the IE’s opinion, SCE’s use of the Alternative Renewable Premium for economic rank ordering in the final selection process was a reasonable exercise of discretion. Applying network upgrade costs that will be incurred by IID in connection with renewable energy procured by SCE appears consistent with fundamental cost causation principles. It does not seem unreasonable that costs incurred to help meet statewide RPS goals should be considered in solicitations to facilitate construction of projects to meet California RPS goals. Moreover, to ignore the incurrence of real costs caused by a candidate project for a power purchase agreement solely because some California constituencies other than the power purchaser’s customers will have to pay for the costs is economically inefficient from a societal standpoint. Including costs incurred by California balancing authorities other than CAISO will also put generators interconnecting within CAISO and other CBAs on an equal footing. Moreover, SCE’s evaluation in both the shortlist and final offer stages was consistent in this regard. Also, SCE’s modification of its congestion assessment for Four Corners was reasonable. While the congestion forecast has been based on a combination of historical data and forecast data, use of historical data for Four Corners is no longer a valid and reasonable representation of the expected congestion at or near this delivery point. SCE short listed three existing geothermal projects, although they were selected out of economic rank order, in order to foster technology diversity, include strongly viable projects on the shortlist, and to include some baseload, non-intermittent generation among shortlisted projects. In the IE’s opinion, this was a reasonable exercise of business judgment by SCE consistent with its Procurement Plan and Procurement Protocol to foster a diverse, robust shortlist. SCE’s selection of seven solar projects was reasonable SCE’s selection of Calpine’s final offer for its Geysers facility, however, raises more difficult issues, which Merrimack Energy will address in more detail in its IE report associated with SCE’s advice letter filing for approval of that PPA. Overall, it is the IE’s assessment that SCE reasonably designed and fairly implemented the 2013 Renewable RFP and appropriately selected the Mount Signal II and Mount Signal V proposals, The Mount Signal II and Mount Signal V projects Merrimack Energy Group, Inc. 8 the PPA was fairly negotiated, and, in the IE’s opinion, the Mount Signal II and Mount Signal V PPAs merit Commission approval. I. 2013 Renewable Request for Proposals (“RFP”) Overview On January 6, 2014, Southern California Edison Company (“SCE”) issued its 2013 Renewable RFP. SCE solicited proposals from Bidders (“Sellers”) to supply Product from Eligible Renewable Energy Resources sufficient to permit SCE to execute power purchase and sale agreements (“PPAs”) in substantially the form as SCE’s Pro Forma Renewable Power Purchase and Sale Agreement (“Pro Forma PPA”) posted on the Accion Power RFP Website. Through the 2013 Renewable RFP solicitation, SCE sought Proposals for product qualifying as Portfolio Content Category 1 (“Category 1”) which includes all electric energy produced by an ERR Generating Facility throughout the term of the Final Agreement, net of Station Use; all Green Attributes; all Capacity Attributes, if any; and all Resource Adequacy Benefits, if any; generated by, associated with, or attributable to the output of the ERR Generating Facility.13 The basic solicitation requirements and conditions are set forth in the 2013 Renewable RFP Procurement Protocol. These include the following: 1. SCE will only consider Proposals to purchase Product from ERR Generating Facilities with commercial operation dates (the “COD”) and initial delivery dates to SCE on January 1, 2016 or later; 2. SCE will consider Proposals from Sellers with ERR Generating Facilities that are located outside the State of California but only if they can deliver Product that qualifies as Category 1;14 3. SCE is only soliciting Product from ERR Generating Facilities which possess: (1) a completed Phase II Interconnection Study or equivalent, (2) documentation showing that the ERR Generating Facility has passed WDAT Fast Track Process screens, (3) a signed Interconnection Agreement, or (4) an equivalent or better interconnection study, agreement, process, or exemption. Further, the interconnection arrangements must support the ERR Generating Facility’s 13 Capitalized terms in this report are as defined in the Procurement Protocol, unless otherwise specified or where terms pertain to the Mount Signal II and Mount Signal V PPAs (and are defined in the Mount Signal PPAs). 14 Category 1 projects are those: with a first point of interconnection to the Western Electric Coordinating Council transmission system within the boundaries of a California Balancing Authority Area; or with a first point of interconnection with an electricity distribution system used to serve end users within the boundaries of a CBA; or where the renewable generation is scheduled into a CBA without substituting electricity from another source; or where the generation from the renewable facility is dynamically transferred to a CBA. The Procurement Protocol states that SCE will not consider Proposals for offers to deliver any Portfolio Content Category 2 products, such as firmed and shaped products, or Portfolio Content Category 3 products, such as Renewable Energy Credit-only transactions. Merrimack Energy Group, Inc. 9 forecasted commercial operation date (“COD”). Should Seller’s interconnection arrangement indicate an interconnection date later than the ERR Generating Facility’s forecasted COD, the proposal will not be given further consideration; 4. Seller may propose any term length equal to or greater than 10 years. If a Seller submits a long-term Proposal with a term length of more than 20 years, the Seller shall also submit an alternative Proposal with a 20 year term; 5. SCE will accept mutually inclusive Proposals (i.e. “package deals” or any similar requirements by Seller that an individual Proposal may only be selected by SCE if other specific Proposals are also selected); 6. SCE will accept mutually-exclusive Proposals (e.g., flat vs escalating pricing for the same ERR Generating Facility or 15-year vs 20-year term for the same ERR Generating Facility); 7. Projects with a Contract Capacity of 1.5 MW or greater are eligible to participate in this Renewable Energy RFP.15 ERR Generating Facilities that are located within the service territory of either Pacific Gas & Electric (“PG&E”), San Diego Gas & Electric (“SDG&E”), or SCE, and directly interconnected to the California Independent System Operator (“CAISO”) or the distribution system of either PG&E, SDG&E, or SCE must offer a proposed contract capacity greater than 20 MW; 8. Seller’s Proposal must demonstrate Site Control; 9. Seller’s generating facility must be a new, existing or repowered generating facility that is an ERR; 10. SCE will consider Proposals with energy storage if the storage technology is only capable of being charged 100% by an ERR and does not result in the delivery of non-ERR electric energy; 11. SCE encourages ERR Generating Facilities in the Western Los Angeles sub-area of the Los Angeles basin local reliability area, and in the Moorpark sub-area of the Big Creek/Ventura local reliability area to participate in the Renewable Energy RFP; 12. SCE encourages Women-Owned, Minority-Owned, and Service Disabled Veteran-Owned Business Enterprises (“WMDVBE”) to participate in the RFP; 13. SCE will only consider Proposals that are substantially complete and include all of the applicable information, representations, warranties, and covenants as set forth in the Form of Seller’s Proposal; 15 SCE also identified preferences for projects that meet specific contract capacity guidelines as described in the RFP document. Merrimack Energy Group, Inc. 10 14. The only method for exchange of information or documents concerning this Renewable Energy RFP, including any such exchange concerning the preparation or submission of Proposals to SCE, will be via the RFP Website. SCE evaluates and ranks Proposals based on Least-Cost Best-Fit principles in accordance with criteria set forth by the CPUC in D.03-06-071 and D.04-07-029 (“LCBF Decisions”). The LCBF analysis evaluates both quantitative and qualitative aspects of each Proposal to estimate its value to SCE’s customers and its relative value in comparison to other Proposals. SCE’s LCBF methodology will be discussed in detail in Section IV of this Report. SCE followed a multi-stage approach for shortlist and final selection as set forth in the Procurement Protocol. In this process, Proposals were initially reviewed for completeness and conformity with the Procurement Protocol. Sellers failing the initial screen were given a limited time to cure and conform their Proposals to solicitation requirements. SCE next evaluated and ranked the proposals based on their total benefits and costs using a Renewable Premium metric. Following the quantitative analysis SCE conducted a qualitative assessment, including use of the Project Viability Calculator for the most competitive Proposals. The qualitative attributes are considered to either eliminate nonviable Proposals or add projects with high viability or other qualitative attributes to the final shortlist of Proposals or to determine tie-breakers, if any. Following shortlist selection, SCE then initiates negotiation of contracts with shortlisted projects. At the end of the negotiation period, Sellers who have reached agreement with SCE on the terms of a PPA will have a one-time opportunity to submit a revised price. SCE will then evaluate the final offers, make final selections and enter into any final PPAs based on the revised pricing. SCE’s 2013 RPS RFP includes several changes from the company’s previous RPS solicitations, including: Limiting the procurement to Category 1 products; Requiring that projects have a Phase II Interconnection Study or an equivalent or better process or exemption in order to submit a proposal; Utilizing a two-step solicitation process, with final selection occurring after (a) shortlisting, (b) a defined period for negotiating contract terms with shortlisted Sellers, and (c) final pricing for Sellers that have reached agreement with SCE on contract terms; Applying incremental congestion adders for energy-only projects; and Elimination of an exclusivity obligation (“Shortlisting Exclusivity”) on shortlisted Sellers who agree to negotiate PPA terms with SCE. These changes were either proposed by SCE and approved by the Commission in a decision conditionally approving the major utility RPS procurement plans (Decision 1311-024 (2013) or in the case of elimination of Shortlisting Exclusivity, directed by the Commission. Merrimack Energy Group, Inc. 11 II. Role of the Independent Evaluator A. Regulatory Requirements for the Independent Evaluator The requirements for participation by an IE in utility solicitations are outlined in Decisions (“D”).04-12-048 (Findings of Fact 94-95, Ordering Paragraph 28), D.06-05039 (Finding of Fact 20, Conclusion of Law 3, Ordering Paragraph 8) of the CPUC, D.09-06-050 and D.10-07-042. The role of the IEs in California IOU procurement processes has evolved over the past ten years. In D.04-12-048 (December 16, 2004), the CPUC required the use of an IE by investor-owned utilities (“IOUs”) in resource solicitations where there is an affiliated bidder or bidders, or where the utility proposed to build a project or where a bidder proposed to sell a project or build a project under a turnkey contract that would ultimately be owned by a utility. The CPUC generally endorsed the guidelines issued by the Federal Energy Regulatory Commission (“FERC”) for independent evaluation where an affiliate of the purchaser is a bidder in a competitive solicitation, but stated that the role of the IE would not be to make binding decisions on behalf of the utilities or administer the entire process.16 Instead, the IE would be consulted by the IOU, along with the Procurement Review Group (“PRG”) on the design, administration, and evaluation aspects of the Request for Proposals (“RFP”). The Decision identifies the technical expertise and experience of the IE with regard to industry contracts, quantitative evaluation methodologies, power market derivatives, and other aspects of power project development. From a process standpoint, the IOU could contract directly with the IE, in consultation with its PRG, but the IE would coordinate with the Energy Division. In D.06-05-039 (May 25, 2006), the CPUC required each IOU to employ an IE regarding all RFPs issued pursuant to the RPS, regardless of whether there are any utility-owned or affiliate-owned projects under consideration. This was extended to any long-term contract for new generation in D.06-07-029 (July 21, 2006). In addition, the CPUC directed the IE for each RFP to provide separate reports (a preliminary report with the shortlist and final reports with IOU advice letters to approve contracts) on the entire bid, solicitation, evaluation and selection process, with the reports submitted to the utility, PRG, and CPUC and made available to the public (subject to confidential treatment of protected information). The IE would also make periodic presentations regarding its findings to the utility and the utility’s PRG consistent with preserving the independence of the IE by ensuring free and unfettered communication between the IE and the CPUC’s Energy Division, and an open, fair, and transparent process that the PRG could confirm. In 2007, the use of an IE was required for any competitive solicitation seeking products for a term of more than three months in D.07-12-052 (December 21, 2007). Also, the process for retaining IEs was modified substantially, with IOUs developing a pool of qualified IEs subject to feedback and any recommendations from the IOU’s PRG and the 16 Decision 04-12-048 at 129-37. The FERC guidelines are set forth in Ameren Energy Generating Company, 108 FERC ¶ 61,081 (June 29, 2004). Merrimack Energy Group, Inc. 12 Energy Division, an internal review process for IE candidates, and final approval of IEs by the Energy Division. In 2008, in D.08-11-008, the CPUC changed the minimum term requirements from three months to two years, and reiterated that an IE must be utilized whenever an affiliate or utility bidder participates in the RFO, regardless of contract duration. In D.09-06-050 issued on June 18, 2009 in Rulemaking 08-08-009, Order Instituting Rulemaking to Continue Implementation and Administration of California Renewable Portfolio Standard Program, the CPUC required that bilateral contracts should be reviewed according to the same processes and standards as contracts that come through a solicitation. This includes review by the utility’s PRG and its IE, including a report filed by the IE. In D.10-07-042 issued on July 29, 2010, the Commission reaffirmed the role of the IE and required the Energy Division to revise the IE Template to ensure that the IEs focus on their core responsibility of evaluating whether an IOU conducted a well-designed, fair, and transparent RFO for the purpose of obtaining the lowest market prices for ratepayers, taking into account many factors (e.g. project viability, transmission access, etc.). This IE report is submitted in conformance with the above requirements and is generally consistent with the requirements outlined in the CPUC’s 2013 RPS Solicitation Shortlist Report Template. B. Description of Key IE Roles In compliance with the CPUC requirements identified above, SCE retained Merrimack Energy in July 2013 to serve as IE for SCE’s 2013 RPS solicitation. Merrimack Energy was retained to provide an independent evaluation of SCE’s bid evaluation methodology and selection process and to provide SCE, SCE’s PRG, and the Energy Division with periodic presentations, findings and other reports as requested. The objective of the role of the IE is to ensure that the solicitation process is undertaken in a fair, consistent, unbiased and objective manner and that the best resources are selected and acquired consistent with the solicitation requirements and criteria. In addition, the IE is required to ensure that no SCE affiliate has an undue advantage over non-affiliates in the solicitation. The IE will be required to make a determination as to whether SCE’s final selection was fair and free from anti-competitive behavior, and was not unfairly influenced by any affiliate relationships.17 In addition to the requirements identified in CPUC Orders, the Purchase Order between Merrimack Energy and SCE identifies the responsibilities and tasks to be performed by the IE. These include the following responsibilities and tasks: 17 SCE did not receive any offers from affiliates. Moreover, Edison International, SCE’s parent company, closed the sale of substantially all of the assets of Edison Mission Energy, Edison International’s independent power generation subsidiary, several months ago. http://www.nawindpower.com/e107_plugins/content/content.php?content.12799. Merrimack Energy Group, Inc. 13 Assist in the development and review of SCE’s existing RFO and RFP protocols and design of the solicitation processes; Monitor the RFO or RFP solicitation process, energy auction, or bilateral negotiation to ensure that all bidders, if applicable, or counterparties, receive access to relevant communications in a non-discriminatory manner; Monitor the RFO or RFP solicitation process, energy auction, or bilateral negotiations and promptly submit recommendations to SCE management to ensure that no bidder has an information advantage provided by SCE; Provide recommendations concerning the precise definition of products sought and price and non-price evaluation criteria, so that all aspects of the products are clearly understood and all bidders may effectively respond to the solicitation; Review the comprehensive quantitative and qualitative bid evaluation criteria and methodologies and assess whether these are applied to all bids in a fair and nondiscriminatory manner; Promptly submit to SCE management any recommendations consistent with the objectives of ensuring a competitive and fair process, and to ensure that the overall scope of the RFO or RFP process is not unnecessarily broad or too narrow; Assess whether SCE’s final selection was fair and was not unduly influenced by affiliate relationships; Provide periodic presentations as requested to SCE management and to the PRG concerning the IE’s findings; Provide final written assessment on whether the solicitation or auction process was competitive and fair and whether any bidder received material information that gave them a competitive advantage or disadvantage relative to other bidders; Report on the outcome of the RFP to the CPUC using the appropriate CPUC Independent Evaluator Report Template. With regard to the role of the IE, Merrimack Energy views that one of the primary roles is to independently evaluate and “challenge” the results of the utility’s evaluation and selection process. Our objective is to ensure that the utility evaluation team can prove that the results of their evaluation are accurate, reasonable and consistent. This role generally involves a detailed review and assessment of the evaluation process and the results of the quantitative and qualitative analysis. Merrimack Energy Group, Inc. 14 This report on the RPS solicitation process provides an assessment of SCE’s 2013 Renewable RFP solicitation from development of the components of the process through selection of the short list, contract negotiations with shortlisted parties, and, finally, SCE’s evaluation and selection of final offers. It is generally organized based on the template provided by the CPUC’s Energy Division entitled 2013 RPS Solicitation Shortlist Report Template (2/19/2014). This report addresses Merrimack Energy’s assessment and conclusions with regard to the following questions: 1. Did SCE conduct adequate outreach to potential bidders and was the solicitation robust? 2. Was SCE’s Least-Cost Best-Fit methodology designed such that all bids were fairly and reasonably evaluated? 3. Was SCE’s LCBF bid evaluation and selection process fairly administered? 4. Did SCE fairly negotiate the terms of contracts with shortlisted bidders? 5. Did SCE make reasonable and consistent choices regarding which indicative bids were shortlisted and which final offers were awarded contracts? 6. With specific regard to the Mount Signal II and Mount Signal V PPAs, did SCE (a) fairly and reasonably negotiate the contract, (b) fairly and reasonably evaluate and select the Mount Signal II and Mount Signal V offers, and (c) do the Mount Signal II and Mount Signal V PPAs merit Commission approval? C. Description of IE Oversight Activities In performing its oversight role, the IE participated in and undertook a number of activities in connection with SCE’s outreach activities, implementation of its evaluation criteria, evaluation methodology, bid evaluation and shortlist selection process, monitoring contract negotiations with shortlisted bidders, and assessment of the final projects selected for contract execution. Merrimack Energy was retained by SCE prior to the development of the Procurement Protocol and therefore had the opportunity to oversee and participate in the development of the evaluation criteria and methodology. Provided below is a description of IE activities in connection with the 2013 Renewable RFP. IE Activities Prior to Receipt of Offers Prior to SCE’s receipt of indicative offers, Merrimack Energy: Reviewed and commented on SCE’s draft Procurement Protocol document; Reviewed SCE’s Procurement Plan filing, including the LCBF methodology, and prepared a number of clarification questions and comments on the proposed methodology for discussion with SCE. The IE held several meetings (in person Merrimack Energy Group, Inc. 15 and over the phone) with the SCE project team to discuss the details of the implementation of the methodology. Issues identified by the IE and addressed with SCE included: o Schedule for conducting the bid evaluation process; o Criteria to be applied for bid evaluation and selection from both a quantitative and qualitative perspective; o Expected date to receive forward curves for lock down prior to the evaluation; o Application of the Project Viability Calculator with regard to the number of Proposals evaluated; o Capacity price forecast and its application; o Methodology for determining the congestion cost adders; o Method for assessing transmission cost adders; o Methodology for evaluating projects with delivery points outside the CAISO; o Credit issues such as the application of collateral adders;18 o The application of other qualitative criteria such as seller concentration. Participated in weekly meetings of the RPS project team to discuss the status of the procurement process; Attended SCE’s Request for Proposals Conference on January 13, 2014 and provided a description of the role of the IE in the procurement process; Reviewed the questions submitted by Sellers to the SCE website and responses provided by SCE and commented on the response to a few questions prior to posting on the website; Reviewed Form of Sellers Proposal submittal requirements prior to posting on the Accion Power website; Reviewed the Accion Power website and held several discussions with Accion Power personnel to review website operations and applications and to better understand how the IE could use the website to conduct an independent assessment of the proposals received; Tested the website through the development of specific reports for summarizing proposals received based on key data and criteria; Prepared a conformance spreadsheet to assess whether the Sellers met the eligibility and other requirements of the RFP upon submission of proposals. Information contained on the spreadsheet; Participated in two meetings with the PRG prior to receipt of offers to discuss the Short List Valuation and Selection Methodology (January 29, 2014) and the Congestion Adder Methodology (December 13, 2013). 18 SCE informed the IE that SCE would not include collateral adders in this solicitation because Sellers were required to submit their proposals based on the collateral requirements set forth in the Pro Forma PPA. Merrimack Energy Group, Inc. 16 IE Activities After Submission of Indicative Offers Through Short Listing After receipt of indicative offers, Merrimack Energy: Prepared several reports using the Accion Power website function to provide high level summaries for each proposal; Compared proposal compilation developed by the IE to SCE’s list of proposals to ensure all proposals were accounted for by the IE and SCE; Conducted a proposal completeness and conformance check; Participated in weekly project team meetings to discuss the status of the proposal conformance and the evaluation process; Participated in several discussions and meetings of SCE’s project team to discuss the conformance of individual proposals and processes for addressing any issues with specific proposals; Reviewed SCE’s preliminary evaluation results and tested the reasonableness of the evaluation results based on project pricing, location, transmission cost, and other factors; raised issues with SCE if results appeared to be inconsistent with the expected results based on project pricing, associated costs, and generation profile; Conducted spot checks for the highest ranked projects based on calculation of the levelized cost of the proposals submitted; Reviewed the emails exchanged between SCE and Sellers regarding any missing information, or requests by SCE for Sellers to clarify proposal information or to explain the basis for information; Reviewed SCE’s proposed shortlist and provided comments; Conducted an independent assessment of the shortlisted proposals and others proximate to the shortlist with respect to the Project Viability Calculator based on the information submitted by Sellers; Participated in several meetings to discuss the proposed shortlist including internal project team meetings, pre-reads with SCE program area management, epRMC19 meeting with senior management, and the PRG meeting of March 19, 2014 at which SCE discussed its short list selection. The IE provided input and comments at all meetings, including observations based on the solicitation results; Participated in a number of calls with Sellers that were not selected for the shortlist but requested a debriefing from SCE. IE Activities Following Shortlisting Through Negotiations and Execution of PPAs Evaluated and Selected Based on Final Offers Submitted by Shortlisted Bidders After SCE decided which offers to shortlist, Merrimack Energy: 19 Prepared a short list report, which SCE filed with its Advice Letter with respect to SCE’s short list for this RPS solicitation; Monitored contract negotiations between SCE and the short listed counterparties; Energy Procurement Risk Management Committee. Merrimack Energy Group, Inc. 17 Attended weekly SCE staff meetings (by teleconference) regarding the progress of negotiations and common issues raised in the various negotiations; o Participated in project-specific discussions regarding how to address issues pertaining to site control, project viability and other matters; Monitored and reviewed emails, and other documents exchanged between the parties during the negotiation process; Reviewed SCE’s evaluation of final offers; Reviewed and discussed with SCE the Company’s selection decisions; Participated in pre-reads, epRMC meeting, and the PRG meeting of July 16, 2014 regarding selection of final offers. D. Any other relevant information or observations No additional information or observations. III. Did SCE Do Adequate Outreach to Bidders and Was the Solicitation Robust? For its 2013 RPS solicitation, SCE sought to procure approximately 1,600 GWh of annual additions starting in 2017 for this solicitation. This section of the report assesses SCE’s process for conducting outreach to potential bidders in an attempt to encourage robust competition and whether the processes used by SCE were successful in meeting its objectives. A. Were the Solicitation Materials Clear and Concise to Ensure That the Information Required by the Utility to Conduct its Evaluation Was Provided by the Bidders? The IE had the opportunity to review and comment on draft solicitation documents and materials. The purpose of our comments was to ensure that the information was consistent and clear to Sellers. In addition, for the first time in an RPS solicitation SCE required Sellers to post their proposal documents on a website, designed by Accion Power, for this solicitation. All submissions by Sellers as well as substantive communications between the Seller and SCE took place via the Accion Power website, thereby requiring Sellers to understand how to use the website for proposal submission. A representative of Accion Power provided an overview of the Accion Power website at SCE’s Request for Proposals Conference on January 13, 2014 and described how to access and use the website for uploading Proposals. In addition, the Accion Power website includes a tab which provides a tutorial for Sellers regarding access to and use of the website. Based on receipt of Proposals and review of the submittals, it appears that Sellers were able to successfully navigate and utilize the website effectively during the solicitation process. All of SCE’s RFP documents were posted on the Accion Power website. The eligibility requirements of Sellers and the documents required of Sellers were clearly identified in the Procurement Protocol. In addition, the Procurement Protocol identifies the documents Merrimack Energy Group, Inc. 18 required of Sellers, provides a description of the evaluation and selection process, and contains a schedule for the solicitation. For example, Associated Document A – Form of Seller’s Proposal – sets forth the documents and data that each Seller must include in its Proposal. This document identified all the documents to be included in the Bidders EBinder and also included a check list for Sellers to review to ensure they included all the information requested. Furthermore, the Accion Power website was set up to allow Sellers to upload their Proposal documents in consistent files to ensure all Sellers essentially submitted the exact form Proposal. The following information was required from each Seller: Fully executed Proposal Structure Letter that provided a brief summary of the proposal and project; Fully executed Seller’s Acknowledgement Letter; Fully executed Consent for Release of Interconnection Related Information; Fully executed Project Viability Calculator completed by the Seller; Complete project generation profile; Fully executed Team Development Experience Letter; Fully executed Site Control Acknowledgement Letter; Fully completed Short-Term Non-Disclosure Agreement; A copy of all the Generating Facility’s Interconnection studies; A detailed Proposal Form that contained project specific information for each proposal that would be used as input into the evaluation of each proposal, including pricing information, project deliverability status, delivery date, project capacity, location, etc. Also, as previously noted, the Procurement Protocol document contained a number of eligibility requirements or preferences of SCE that guided Sellers in the submission of Proposals. For the most part, Sellers conformed their Proposals to these requirements or preferences. Although there was a significant amount of communications between SCE and the Sellers after submission of the Proposals, most of the communications involved clarifying questions from SCE about specific aspects of the Proposals to correct inconsistencies between the Proposal Form and Proposal Structure letter or similar issues. For the most part, Sellers were able to cure any outstanding deficiencies or inconsistencies in their Proposals in short order. Merrimack Energy believes that the contents of SCE’s 2013 RPS RFP solicitation protocol provided clear and comprehensible direction to Sellers on how to prepare and submit a complete Proposal package. In addition, the IE is of the view that the information available publicly and in the Procurement Protocol provided Sellers will a substantial base of information to allow them to determine how they could best compete in the RPS solicitation process. Since the Accion Power website was used for the first time for an RPS solicitation it could be expected that there may have been some glitches associated with Seller use of Merrimack Energy Group, Inc. 19 the system. However, it appeared that this was not the case. Sellers seemed to use the website to upload documents and communicate with SCE with relative ease. Merrimack Energy’s observations regarding the solicitation documents, use of the website, and other means of providing information to Sellers (i.e. Request for Proposals Conference, Frequently Asked Questions, etc.) are provided below: Overall, the Accion Power website was an effective tool for communicating with Sellers and provided a repository of Seller Proposal information which could be accessed by the IE and SCE’s project team. The IE found the website to be very effective for allowing the IE to prepare summary reports on each of the Proposals which the IE used to aid in the assessment of SCE’s evaluation and selection process; Nearly all the Proposals submitted were complete and conforming packages. Although SCE spent a considerable amount of time reviewing the Proposals for conformity and completeness, much of the communications with Sellers involved clarification of the information provided. Issues such as whether Proposals were mutually exclusive or inclusive, clarifying questions about the generation profile, or clarifying questions about the status of the interconnection process were common. SCE and the Sellers were able to correct remaining deficiencies (where it was substantively possible to do so) prior to the completion of the evaluation process; As noted in Section 1 of this report, SCE’s Procurement Protocol documents identified a number of eligibility requirements and SCE preferences. The results of the Proposal submission process indicated that Sellers were well aware of these requirements and satisfied them, with relatively few exceptions. For example, SCE indicated that if a Seller provided a Proposal for a 25 year term it also had to provide a Proposal for a 20 year term. Sellers conformed to this requirement; Sellers, or at least those proposing to build solar projects, were generally planning on meeting a 2016 in-service date deadline to qualify for the 30% Investment Tax Credit (“ITC”) (the ITC reverts back to 10%, under current law, for solar projects with in-service dates after December 31, 2016), while SCE’s needs for new renewable generation are more focused on subsequent years. A significant number of Sellers understood this issue and submitted Proposals more in line with both their own objectives and SCE’s objectives. In follow-up sessions held between SCE and non-shortlisted Sellers, several Sellers said that they did not understand SCE’s bid evaluation process and methodology. The IE found this surprising given that a general description of the methodology can be found through CPUC orders and SCE filings and was also addressed in the Request for Proposals conference. Outreach activities are important to the success of a competitive solicitation process. SCE’s outreach efforts targeted a large number of potential Sellers based on contacts from previous solicitations and business relationships developed since then. SCE prepared a detailed list of potential Sellers with approximately 2,300 contacts that serves Merrimack Energy Group, Inc. 20 as the database for Seller contact and outreach. SCE sent emails to all potential Sellers on this list informing them of the RPS RFP process and the issuance of the Procurement Protocol. SCE did not issue a press release or contact industry trade publications announcing its 2013 Renewable RFP. SCE also established a link on SCE’s RPS 2013 Solicitation webpage for Accion Power’s website, on which the RFP Program documents were accessible to prospective Sellers. SCE’s RPS 2013 Solicitation webpage contains the RPS RFP Proposal Conference Presentation, the CPUC Decision (D.13-11-024) conditionally accepting 2013 Renewable Portfolio Standard Procurement Plans and Integrated Resource Plan and On-Year Supplement, Final Congestion Adders for LCBF valuation, CEC RPS Eligibility Guidebook, and the web address for the Accion Power website for this solicitation. In addition to the program documents, the Accion Power website contained a list of questions and answers related to the solicitation. A total of 28 questions and answers were posted prior to receipt of the Proposals. The Accion Power website also included an Announcement tab with latest information about the RFP, and a calendar. The IE found both the SCE web page and the Accion Power website easy to access and navigate. The IE’s one recommendation with regard to outreach activities for future solicitations is that the SCE web page for the solicitation should also include the solicitation protocol documents to ensure easier access. The Request for Proposals Conference held by SCE for prospective Sellers (on January 13, 2013) provided useful information, including an overview of the solicitation process, schedule, eligibility requirements, products sought by SCE, RFP website documentation, discussion of the Pro Forma PPA, description of the proposal evaluation process, a discussion of the interconnection process, and keys to Seller success. The conference was well attended, with over 150 attendees in person plus others on the phone. A total of 76 Sellers registered on the Accion Power website to submit Proposals and 56 Sellers ultimately did submit Proposals as required. The IE concludes that SCE conducted reasonable and sufficient outreach for this solicitation. The level of interest in the solicitation and the participation in the process indicate that SCE’s outreach was effective in generating a robust response. Although the number of Sellers and projects was much less than in the 2011 RPS solicitation which drew about 1,400 Proposals, the reason for the reduced number of Proposals, in our view, are the stricter minimum requirements in this solicitation relative to the 2011 solicitation, particularly the requirement that each project must have at least a Phase II interconnection study or equivalent. The overall result of this outreach activity was a very robust response from Sellers, even in light of the stricter threshold or minimum requirements established by SCE, demonstrating the maturity of the renewable energy market in California. Proposals were also received from a diverse set of Sellers including experienced, well-financed Sellers as well as new market entrants, involving a variety of technologies, including wind, solar (PV and solar thermal), geothermal, and biomass. Information regarding the Proposals, Merrimack Energy Group, Inc. 21 MW and GWh quantities, types of resources bid, project location, pricing options and project evaluation results are contained in Appendix B to this report. Table 1 provides a summary, by technology, of the Proposals and unique projects submitted. As the table indicates, the response to the solicitation is dominated by solar PV projects which represent 60% of the total number of projects and 73% of the total capacity. Table 1: SCE’s RPS Proposals Received by Technology Technology Biomass Landfill Gas Geothermal Solar PV Solar Thermal Wind Total All Proposals # of Proposals 34 1 15 242 9 66 Capacity (MW Total) 856 43 1,788 33,123 370 7,055 Unique Projects 12 1 6 81 7 27 Capacity (MW Unique) 304 43 470 9,122 310 2,185 367 43,235 134 12,434 According to SCE, approximately 35,000 GWh/year of RPS energy was offered by the unique proposals or projects.20 This compares to SCE’s target for this solicitation of approximately 1,600 GWh or nearly 22 times need. SCE also estimates that the 134 unique projects submitted represented 12,434 MW (AC) of capacity. Overall, SCE received 367 Proposals21 There was also an interesting mix of new projects, existing renewable projects coming off of their contracts looking for a market, and repowering options. Approximately unique RPS Solicitation projects are expected to come on-line in 2016 to capture the ITC benefit. In addition, of the 367 Proposals submitted included an energy storage component. 20 SCE received a number of alternative proposals for the same project including different pricing options, delivery dates and contract term lengths. Also, Sellers offered battery storage options for some projects. SCE’s approach was to include only the most highly ranked Proposal from the options submitted for the same project in the stack of projects to be ranked and evaluated. 21 SCE and the IE compared the results of the Proposals submitted and initially the IE had accounted for eight fewer Proposals than SCE. Upon review, it was determined that there were several mutually exclusive offers that the IE had not included in its Proposal totals that SCE had included. SCE identified the project numbers and the IE was then able to conform the total number of Proposals to the totals identified by SCE. 22 Of the 134 unique projects submitted, Merrimack Energy Group, Inc. 22 In conclusion, the outstanding response of the market to SCE’s 2013 Renewable RFP is evidence that the outreach activities of SCE were effective and Sellers felt they had an adequate opportunity to receive a contract from the process. B. Did the IOU’s Seek Adequate Feedback About the Bidding/Bid Evaluation Process From All Bidders After the Solicitation Was Complete? As noted, SCE offered to talk with non-shortlisted Sellers and answer reasonable questions about the solicitation process and the general reasons why the Seller was not successful in being selected for the shortlist. The IE attended many of the calls. Overall, the Sellers were very appreciative of the opportunity to discuss their projects with SCE and the reasons for non-selection. In addition, following SCE’s announcement of its selection or non-selection of shortlisted bids for contract award, SCE provided both winning and losing bidders with the opportunity to participate in a debriefing session, with the IE in attendance. Several bidders took advantage of this opportunity. During the calls, Merrimack Energy asked participants what they viewed as positive and negative aspects of the solicitation process. Almost all, if not all, of the participants stated that they strongly approved of the timelines set forth in the RFP process and SCE’s adherence to those timelines. This enhanced the predictability of the process from their perspective. Other participants spoke highly of the quality of information provided at the bidder’s conference and the responsiveness of SCE’s contract managers in terms of being available for conference calls and contract negotiations. Since this was the first time in an RPS solicitation that SCE utilized the “two step” process whereby shortlisted parties were given a period to negotiate contract terms before submitting final offers, counterparties addressed the structure of the process in their comments. Almost all of the counterparties liked the time certain associated with the contract negotiation period, although one participant said that it would have liked to have another month to negotiate the contract (there were some unusually difficult issues associated with its particular proposal). Several participants stated that the process required an expenditure of time and funds on legal resources to negotiate the contract terms before they knew that they had a “deal” with the utility, which they viewed as being a negative attribute of the process. However, the majority of counterparties generally viewed the process favorably. Following notification to bidders as to whether their Proposals were shortlisted, SCE conducted a survey similar to the surveys taken for other RPS solicitations. Although there were relatively few responses (seven in all), the bidders who did respond generally reported favorably with respect to the straightforwardness of RPS requirements, the usefulness of the Accion website, and the timeliness of SCE’s responses to questions. C. Any Other Relevant Information or Observations The IE has served in a similar function in a number of solicitation processes throughout the United States and Canada. The approach used by SCE to require that Sellers meet higher threshold standards than in the past has likely served to reduce the number of Merrimack Energy Group, Inc. 23 Proposals but has led to a higher percentage of more mature and viable projects. The response indicates that the California renewable energy market is very mature and that establishing stricter thresholds can be a reasonable and effective strategy to solicit more highly developed projects, while still obtaining a very robust response from the market. IV. Was the IOU’s LCBF Methodology Designed Such that Offers were Fairly Evaluated? This section of the report identifies the principles used by the IE to evaluate SCE’s LCBF evaluation methodology, including its strengths and weaknesses, and identifies how the methodology was applied to the evaluation of the RPS proposals. A. The Principles the IE Used to Evaluate the IOU’s Offer Evaluation Methodology This section of the report addresses the principles and framework underlying Merrimack Energy’s review of SCE’s methodology for Renewable Resource proposal evaluation and selection. While the Energy Division has suggested a set of principles for evaluating the process used by IOU’s for selecting Offers in competitive renewable solicitations, Merrimack Energy has included several additional principles that we often apply in other solicitations. These are included along with the Energy Division’s principles. Key areas of inquiry by the IE and the underlying principles used by the IE to evaluate the methodology include the following: Were the procurement targets, objectives, preferences, products solicited, principles and objectives clearly defined in SCE’s RFP and other materials? Were the bid evaluation and selection process and criteria reasonably transparent such that bidders would have a reasonable indication as to how they would be evaluated and selected? Was SCE’s bid evaluation based on and consistent with the information requested in the RFP to be submitted by bidders in their Proposal documents? Did the evaluation methodology reasonably identify the quantitative and qualitative criteria and describe how they would be used to rank Proposals? Were the bid evaluation criteria consistently applied to all Proposals? Was the quantitative evaluation methodology reasonably consistent with industry standards and did it adequately account for all reasonable costs and benefits identified in the Procurement Protocol? Did the evaluation methodology adequately treat all eligible resources and technologies in a technology neutral manner? Merrimack Energy Group, Inc. 24 Does the price evaluation system allow for consistent evaluation of bids of different sizes, in-service dates, and length of contract? Did the bid evaluation criteria and evaluation process contain any undue or unreasonable bias that might influence project ranking and selection results or in any way favor affiliate Proposals? Was the RFP clear and concise to ensure that the information required by SCE to conduct its evaluation was provided by project sponsors? B. Evaluation of the Strengths and Weaknesses of SCE’s Evaluation and Shortlisting Methodology in This Solicitation As defined in the Shortlist Report Template, the following considerations should be included in the IE’s overall review of the strengths and weaknesses of the IOU’s methodology in this solicitation: 1. Evaluation of consistency with RPS procurement plan, requested products, and portfolio fit. Did the IOU adequately incorporate needs and preferences stated and approved in the RPS procurement plan and protocol? For instance, did the IOU account for contract start dates, contract lengths, and varying generation amounts? Did the IOU adequately take into account a project’s characteristics related to portfolio fit preferences? 2. Market valuation. Were both price and value taken into consideration when projects were shortlisted as well as for final selection? Did the IOU adequately take into consideration all financial benefits and costs of a project when determining the value of projects that were shortlisted and eventually selected for contract award? Did the IOU include the cost of transmission upgrades in the value calculation of projects that were shortlisted? In your opinion, were any costs or benefits that should have been included in the IOU’s LCBF calculation not included? 3. Evaluation of offers’ transmission costs. Did the IOU rely more on TRCR studies than Phase I or Phase II studies to ascertain transmission costs? Did the IOU weigh the total cost of transmission upgrades for a project against the relative value in resource adequacy that the transmission upgrade will provide for each project? Did the IOU perform any data conformance checks related to transmission study results and cost information for projects before they were included on the shortlist? 4. Evaluation of offers’ project viability. Did the IOU (or IE or developer) reasonably measure the viability of each project in the offer evaluation process? Did the IOU perform conformance checks related to the accuracy of the project’s viability scores before the projects were included on the shortlist? Merrimack Energy Group, Inc. 25 5. Other 1. Evaluation of Consistency with RPS Procurement Plan, Requested Products and Portfolio Fit This section discusses whether SCE’s evaluation and selection process and methodology is consistent with its final 2013 Renewable Energy Procurement Plan. Overall, the IE finds that the methodology is generally consistent with the approved plan. The findings of the IE are discussed below. While SCE provided information regarding its annual procurement target in confidential information provided to the PRG, SCE did not communicate its procurement target, or an approximate range of what it intended to procure, to prospective Sellers in any public presentation or document associated with this solicitation. The solicitation Protocol clearly identifies the eligibility requirements of Sellers, including those eligibility requirements and criteria specified in the 2013 Renewable Energy Procurement Plan including the requirements for a Phase II interconnection study or better as well as the type of product required (i.e. Category 1), the commercial operation date (i.e. January 1, 2016 or later), and eligible project sizes. SCE’s Renewable Energy Procurement Plan and Protocol requires Sellers to limit projects with a commercial operation date of January 1, 2016 or later. However, the documents do not specifically identify a preference for projects that begin deliveries at a later date. Not surprisingly, a number of Sellers submitted multiple proposals from the same projects with different initial delivery dates and contract terms. The Protocol indicated that Sellers may propose any term length equal to or greater than 10 years. If a Seller submits a long-term proposal with a term length greater than 20 years, the Seller is also required to submit an alternative Proposal with a 20 year term. While the Protocol clearly requires that a Seller who submitted a proposal with a term greater than 20 years would also have to submit a proposal for 20 years, SCE had little interest in entertaining proposals for greater than 20 years due to SCE’s concern that contracts greater than 20 years would trigger capital lease accounting treatment. The solicitation accepts proposals from new projects and from existing operating facilities (as long as such projects meet the eligibility requirements) and does not state a specific preference for either type.23 SCE did receive proposals for both 23 While the Project Viability Calculator yields higher viability scores for existing projects relative to new projects, there is no bias because existing projects are generally more viable than projects under development. Merrimack Energy Group, Inc. 26 new and existing projects and the evaluation methodology did not contain any biases in the evaluation of one type of resource over another. SCE’s evaluation methodology and process resulted in a shortlist that contained multiple technology types (Solar PV, Solar thermal, wind, and geothermal) and project sizes. Although SCE short listed a few geothermal offers for portfolio diversity reasons, the IE found that there was no apparent bias toward any type of technology or project size based on the evaluation methodology design. The 2013 Renewable Energy Procurement Plan and the Procurement Protocol indicate that SCE seeks proposals that enable SCE to comply with its Resource Adequacy Requirements. The plan and Protocol explain issues of concern with Energy Only Deliverability status relative to Full Capacity Deliverability status and describes how Energy-Only and Full Capacity Deliverability projects will be evaluated.24 Importantly, SCE illustrates that the valuation methodology will essentially reward Full Capacity Deliverability Status interconnections by allocating a capacity value to the project to reflect the RA benefit. Sellers essentially have to weigh whether the additional cost to achieve Full Capacity Deliverability Status is worth the additional capacity value attributed to the project. The 2013 Renewable Energy Procurement Plan indicates that SCE will use the network upgrade cost results from the Phase II study or Interconnection Agreement as the basis for including network upgrade costs in the analysis. The Phase II interconnection requirements help to ensure that more viable projects are the ones competing in the solicitation. At the same time, the availability of more refined and more certain network upgrade costs enhances the accuracy of the evaluation process relative to a methodology that attempts to use less reliable transmission cost estimates to assess project economics (i.e. Phase I studies or TRCRs). In summary, SCE’s evaluation methodology and evaluation process and criteria are consistent with its 2013 Renewable Procurement Plan and are generally consistent with the plan’s stated preferences, eligibility requirements, evaluation criteria, and evaluation process. However, there are a few “preferences” or information requirements that could lead to more transparency to assist Sellers in structuring their proposals in future solicitations. These are described in Section IV.C of this report, along with other suggestions for future LCFB improvements. SCE has required Sellers to propose a 20 year term if they also want to offer a Proposal greater than 20 years. All Sellers who proposed a 25 year term conformed to these requirements by also offering a 20 year option. 24 SCE applied a cost adder for energy only projects of $.47/MWh. The IE found that the adder had no impact on the ranking of proposals and had no influence on shortlist or final selection or economic ranking. Merrimack Energy Group, Inc. 27 2. Market Valuation As a starting point for addressing the strengths and weaknesses of SCE’s market valuation, this section of the report provides an overall description of SCE’s evaluation methodology and criteria applicable to the 2013 Renewable Resources RFP. SCE evaluates and ranks proposals based on LCBF principles intended to comply with criteria set forth by the CPUC in D.03-06-071 and D.04-07-029 (“LCBF Decisions”). The LCBF methodology includes evaluation of both quantitative and qualitative aspects of each proposal to estimate its value to SCE’s customers and relative value in comparison to other proposals. Bid Evaluation Methodology and Selection Process SCE utilizes a “multi-step” bid evaluation and selection process from receipt of proposals through final selection. Once proposals are received,25 SCE begins an initial screen for completeness and conformity with the solicitation protocols and bidder requirements. The review includes an initial screen for required submission criteria and eligibility requirements such as a conforming delivery point, commercial on-line date in 2016 or later, a valid Phase II interconnection study, minimum project size, and submission of particular proposal package elements. Sellers lacking any of these will be allowed a reasonable period to cure any deficiencies. Following this check for conformity, SCE will determine which proposals are clear outliers. For proposals deemed clear outliers, SCE will not conclude any further review. For the remaining proposals, SCE will conduct an additional review to determine the reasonableness of proposal parameters such as generation profiles and capacity factors. SCE’s goal is to work directly with Sellers to resolve any issues and ensure the data is ready for evaluation. After the reviews are undertaken and the data for eligible projects is deemed complete, SCE will perform a quantitative assessment of each proposal individually and rank the proposals based on the relationship between the benefits and costs attributable to the proposal. Total benefits and total costs are combined to calculate the net levelized cost or “Renewable Premium” for each Proposal.26 Benefits are comprised of the value of a Proposal relative to its energy and capacity value in the market based on SCE’s forecast of capacity and energy market values. Costs include contract payments based on the bid price, debt equivalence, congestion costs and transmission upgrade costs. SCE discounts the monthly benefit and cost streams to a common base date. Specifically, the Renewable Premium is defined as Levelized Cost minus Levelized Benefit. The components of the Levelized Cost and Levelized Benefits that comprise the Renewable Premium calculation are illustrated in Table 2. 25 For this solicitation, proposals were received via Accion Power’s website established specifically for this solicitation. 26 As previously noted in this report, SCE also calculated the values for what it calls Alternative Renewable Premium for purposes of undertaking the final evaluation assessments. Merrimack Energy Group, Inc. 28 Table 2: Comparison of Cost and Benefit Valuation Categories Levelized Costs Levelized Benefits Contract Payments – TOD-adjusted based Energy Benefits – Market value of energy on the proposed energy price, expected based on SCE’s internal forecast, taking generation profile and contract term into account dispatchability of the resource. Additional ancillary services and real time benefits may be applied to dispatchable projects. Transmission Costs – Cost adders for Capacity Benefits – Based on SCE’s required network upgrades based on the forecast of net capacity value and the latest Interconnection study or Agreement expected quantity of Resource Adequacy . RA quantities are based on the Commission’s applicable accounting rules (e.g. exceedance methodology for solar and wind) Debt Equivalence Cost – Cost of Congestion – Locational benefit resulting mitigating contract commitments on SCE’s from certain resource locations. balance sheet Integration Costs – Cost of maintaining a reliable energy supply. Pursuant to D.1311-024, the integration cost = $0/MWh Congestion – Locational cost resulting from certain resource locations. Incremental cost adder for Energy-Only projects. In developing its relative merit order ranking of proposals, SCE’s evaluation methodology incorporates information provided by Sellers as well as assumptions prescribed and set by the Company with its internal methodologies and forecasts of market conditions. The result of the quantitative analysis is a merit-order ranking of all complete and conforming Proposals’ Renewable Premiums.27 Following the quantitative analysis, SCE conducts an assessment of the top proposals’ qualitative attributes. The analysis utilizes the Project Viability Calculator28 to assess certain factors including the company/development team experience, technology, and development milestones. The Project Viability Calculator is a tool whose purpose is to 27 SCE initially ranked all the proposals submitted including the mutually exclusive proposals, such as the type of proposals submitted by a number of Sellers who offered the same project but with different delivery dates, contract terms or pricing mechanism. SCE evaluated all the proposals but in the process of ranking proposals for shortlist selection only selected the best offer for each proposal. SCE followed the same general process in evaluating the final offers. 28 For the initial evaluation, the IE also completed the Project Viability Calculator scoring for each project included on the proposed shortlist as well as other projects which were on the fringes of the shortlist. For the final qualitative evaluation the IE along with SCE conducted independent evaluation of final offers based on the Project Viability Calculators and taking into account information about the projects gleaned through the negotiation process and final submittals. Merrimack Energy Group, Inc. 29 help assess the relative likelihood that proposed projects will be successfully developed and constructed. Additional attributes such as transmission area/cluster, generating facility location, seller concentration, project size, dispatchability, and contribution to other programs goals are also considered in the qualitative analysis. Following its analysis, SCE consults with its Procurement Review Group (“PRG”) regarding the short list and the results of its evaluation. SCE then negotiates with the shortlisted Sellers, and at the end of the negotiation period, all Sellers that have successfully completed negotiations have a one-time opportunity to submit new pricing. SCE then evaluates the remaining Proposals based on the same Renewable Premium metric (along with an Alternative Renewable Premium29 metric) to rank projects and make final selections and enter into final agreements based on the revised pricing. SCE’s overall LCBF methodology and approach is described in more detail in Appendix A to this report. Congestion Cost Adders The congestion adders used in the 2013 RPS RFP are new for SCE RPS solicitations. As a result, we address them in detail. There are two elements of congestion costs that are incorporated into SCE’s quantitative evaluation: (1) locational adders; and (2) energyonly cost adder. Locational Adders SCE’s LCBF methodology, contained in its final Procurement Plan, specifies that SCE will apply a locational congestion adder, which may be positive or negative depending on expected congestion in the area, to differentiate the value of energy between different project locations. The locational adders are based on SCE’s forecast of energy locational marginal prices (“LMPs”) in the CAISO market in the location that the seller plans to interconnect or to which it plans to inject energy. SCE produced the forecast using the GridView production simulation model. SCE posted on its website its long-term (2014-2023) forecast of locational congestion adders by eight delivery periods (quarterly on-peak and quarterly off-peak).30 By posting this information, SCE provided prospective bidders information regarding the relative value of locating generation at different locations. The information provided was on a nodal level, with 381 pricing points. Congestion varies from approximately negative $11/MWh on average (Malin) to various pricing nodes with low single digit average positive $/MWh values. These values are based on delivery points to CAISO locations. The forecast was based on a combination of historical data and a long-term forecast.31 29 The Alternative Renewable Premium includes revised congestion forecast for Four Corners resources and IID network upgrade costs. 30 https://www.sce.com/wps/wcm/connect/508bf252-72a8-42e5-98205a2dc066b420/2013_RPSFinalCongestionAddersforLCBFValuation.pdf?MOD=AJPERES. 31 SCE applied locational congestion adders to all projects in California. Merrimack Energy Group, Inc. 30 The IE views SCE’s nodal-level energy price forecast as an improvement over energy forecasts with less local differentiation. In addition, providing the locational adders to prospective bidders provides important guidance regarding the positive and negative values associated with locations for new projects. Energy-Only Adder In addition to the locational adders, SCE developed an additional congestion adder for Energy Only projects. These are projects that are not Full Capacity Deliverability Status (“FCDS”) interconnection projects and do not fund transmission delivery network upgrades. As such Energy Only (“EO”) projects do not qualify as capacity resources and do not receive RA capacity benefit value in SCE’s quantitative evaluation. In its draft Procurement Plan, SCE proposed a congestion adder for Energy Only projects on the basis that these projects increase the risk of congestion to a degree greater than FCDS projects because they do not fund the deliverability upgrades needed to ensure that their energy can serve load and avoid localized congestion. The Commission accepted use of an Energy Only congestion adder for this solicitation on the grounds that “energyonly interconnections may increase congestion risk.”32 However, the Commission did so only for this solicitation, stating that “we expect Energy Division to monitor the impacts of SCE change in LCBF methodology and anticipate that this issue will be further examined in this proceeding when we review LCBF.”33 SCE developed a congestion adder for this solicitation, which is $.47/MWh and is incremental to the locational congestion adder. SCE posted this on its website with the locational congestion adder. The EO congestion cost adder applies to all CAISO projects that selected an EO interconnection, or any EO portion of the contract term if FCDS status is expected to be achieved after the commercial on-line date. This adder is based on SCE’s estimate of the average impact on system congestion from adding incremental capacity without any incremental deliverability network upgrades. It is the same amount for all EO projects. 32 33 D 13-11-024, p. 52. Id. Merrimack Energy Group, Inc. 31 The resulting congestion adder--$.47/MW—is relatively modest. It did not have a material impact on shortlisting or final selection decisions by SCE. While 24% of the unique projects bid with EO interconnections, only one of the shortlisted projects had an EO interconnection. The bigger difference was the foregone capacity value for EO projects— for solar PV projects with FCDS interconnections. The methodology used by SCE seems reasonable on its face. However, the assumptions regarding the amount of renewable generation that could reasonably be built in SP15 on an Energy-Only basis in the foreseeable future appears far in excess of what is likely to occur. However, we do not know what the impact would be on the analysis if SCE assumed a smaller increment of generation built on an EO basis.34 In any event, the amount of the EO congestion adder is relatively small and does not appear unreasonable for purposes of this solicitation. We also concur with SCE’s rationale for incorporating the EO congestion cost adder as part of the LCBF methodology. Adding new generation without network upgrades to assure deliverability is likely to add to congestion. Incorporating the adder, we believe, sends a proper price signal to generators, as does making the amount of the adder public as part of the solicitation process. Overall Market Valuation Assessment As previously described, SCE’s valuation methodology takes into account both the proposed costs and benefits for each project submitted based on the specific proposal submitted. The valuation methodology takes into consideration the total cost to ratepayers of a proposal by including the proposed contract payments (as bid by the Sellers in its Proposal) plus other costs to ratepayers (including the transmission rate impact associated with required network upgrades, congestion cost impacts, and the implications of the estimated cost of imputed debt on the utility’s balance sheet). Importantly, all projects are 34 Merrimack Energy Group, Inc. 32 treated equally using this methodology which allows for a comparison of different types of technologies, with different terms and start dates. Some of the major strengths of the LCBF methodology used by SCE include: All Proposals are treated the same with regard to the cost and benefit components and assessment for each project; All Proposals are evaluated using the same consistent set of input price forecasts for energy, capacity, congestion, and transmission costs; The methodology can be efficiently utilized to evaluate a large number of proposals in a fairly quick manner as compared to other utility methodologies which may rely on detailed system-wide simulation or optimization model assessments; The evaluation methodology generally treated all eligible resources and technologies in a technology neutral manner with no undue biases toward any technology or resource type. This was particularly true of the quantitative evaluation methodology which we felt was generally balanced and technology neutral; The use of a Market Valuation approach such as Renewable Premium or similar process used by other utilities is common and generally accepted in the industry. The weaknesses of this methodology include: There is still much uncertainty associated with transmission access and cost, status of new transmission projects, and the expectations about the initial operation date of the transmission facilities. Network upgrade costs can have a significant impact on the ranking of projects which could influence shortlist selection; The evaluation methodology does not account for integration costs for certain renewable resources which may distort resource decisions. 3. Evaluation of Transmission Costs SCE’s evaluation methodology assigns estimated transmission costs to the contract price of generation in order to compare offers fairly and equitably. Transmission costs are based on the estimated cost of reimbursable network upgrades attributable to individual projects. One of the primary changes in the LCBF methodology has been attributed to SCE’s requirement that all Proposals must demonstrate that they have a Phase II interconnection study or better. To participate in the 2013 RPS RFP, SCE requires Sellers to have an existing Phase II Interconnection Study or an equivalent or better process or exemption in order to submit a proposal. Transmission costs applicable to the project will Merrimack Energy Group, Inc. 33 be based on the applicable completed interconnection study or interconnection agreement. For the 2013 RPS RFP, Sellers were required to provide copies of their Interconnection Studies (at least a Phase II study) and Interconnection Agreement (if they had one) with their proposal, which was uploaded into the Accion Power website. In addition, the Proposal Form required the Seller to provide a significant amount of information on the transmission arrangements for their project including: whether they were interconnecting to a new transmission project; whether the project has an interconnection queue position; what interconnection cluster are they in; what is their interconnection queue position number; what is the interconnection point; whether the project is connecting to a West LA Basin or Moorpark high voltage substation; name of Balancing Authority or utility; whether the Seller will dynamically transfer the product into a California Balancing Authority; interconnection documents provided; status of the project’s interconnection; delivery point; date of interconnection document from which the Delivery Point is transcribed; is conferment of deliverability status by the CAISO subject to the completion of the Tehachapi Renewable Transportation Project (“TRTP”); commercial operation date from Interconnection Agreement; estimated time to construct; name of interconnection document from which the estimated time to construct is transcribed; page number from the Interconnection Document with regard to the time to construct; Seller’s estimated date to sign an Interconnection Agreement; deliverability status (full capacity deliverability or energy only); network upgrade costs; document and page number from which the upgrade is provided; cost of reliability network upgrades and deliverability network upgrades. The information provided to the website allowed SCE to complete a number of cross checks on the information to determine whether the information is consistent. SCE’s RPS project team also provided the transmission information for each project to its transmission group for review and assessment to ensure that the information is reasonable and credible. The SCE project team also sought input from the Transmission and Distribution Group regarding validation of the projects’ transmission information and any other information regarding transmission access and cost. Merrimack Energy Group, Inc. 34 SCE uses the interconnection studies submitted as part of the offer submittal package to determine the applicable network upgrade costs for all projects. SCE applies the required network upgrade costs associated with delivery of the project’s energy to the nearest defined market (e.g. NP15, SP15, ZP26 Generation Trading Hubs). Once total network upgrade costs are determined, SCE allocates the transmission costs over 40 years using a 16% capital cost recovery factor to determine levelized costs. In this solicitation, SCE did not use TRCR studies to assess transmission costs to individual projects. The methodology used by SCE to determine transmission upgrade costs is a major improvement over methodologies that rely on high level estimates (such as TRCR studies or Phase I interconnection studies), since the transmission upgrades are more defined and should be more accurate. Since all Sellers must have completed a Phase II study at a minimum, the projects are also placed on a more level playing field in the evaluation process. Inclusion of more accurate transmission cost estimates in the evaluation also provides a more complete view of all costs attributable to a specific project, including the cost to California ratepayers associated with a new transmission project. The information required of the Sellers by SCE also provides valuable information regarding whether a project will be fully deliverable at the time the project reaches its commercial operation date, which is relevant for assessing project viability capacity value and congestion cost impacts. As will be discussed later in this report, transmission access and cost issues had an influence on final project ranking and selection and affect the contract negotiation process. 4. Evaluation of Offers’ Project Viability Use of the Project Viability Calculator (“PVC”) was incorporated into SCE’s evaluation of the proposals both at the indicative bid and final offer evaluation stages. SCE asked the Sellers to complete the PVC based on their assessment of their own projects, including providing scores for the project and supporting justification for the scores. Also, both the IE and SCE completed the PVC scores (a) at the indicative bid stage for proposed shortlisted projects as well as projects that were close to the shortlist and (b) at the final offer stage for all offers. The original objective of the PVC was to evaluate the viability of renewable energy projects at different stages of development based on a number of traditional project viability criteria such as developers experience, site control, project financing status, environmental permitting status, status of interconnection progress, technical feasibility, transmission system upgrade requirements, and reasonableness of the expected Merrimack Energy Group, Inc. 35 Commercial Operation Date. SCE’s approach for this solicitation to include stricter thresholds essentially changed to a large degree the importance of the PVC as structured. Through the IE’s work on numerous competitive procurement processes throughout the United States and Canada, our assessment is that there is generally a trade-off between stricter threshold criteria and qualitative evaluation criteria such as those effectively included in the PVC. Stricter thresholds generally mean a project has to be more mature in the development process to compete and therefore should score more highly based on qualitative criteria. That proved to be the case in this solicitation. Nevertheless, the PVC has several strengths and weaknesses as a component of the evaluation and selection process. The advantages of the PVC include: The PVC represents a standardized tool to evaluate all projects; The PVC is a transparent tool; As a result, the PVC sends an important signal to Sellers regarding the qualitative criteria, at least those pertaining to project viability, of importance when developing their projects. The IE has found in other processes where the utility conducts a quantitative and qualitative evaluation that the weights and rankings of the various criteria are not explicitly defined but are used by the utility as an internal evaluation and scoring process; The PVC scores along with supporting documentation provided by the Sellers to support its scores provide a valuable base of information on which to evaluate projects. We do note, however, that the Sellers generally scored their own projects more favorably from a project viability perspective than SCE and the IE. There are also disadvantages associated with the PVC that should be considered in future solicitations. These include: While several of the criteria and guidelines are objective and scoring and ranking is fairly obvious, there are several criteria that are ambiguous and unclear and require the analyst to develop his/her own basis for scoring. For some of the criteria personal judgment is used which may vary among analysts. Reasonableness of the COD, Project Financing Status, and Transmission System Upgrade Requirements are somewhat ambiguous criteria. Even in this recent SCE solicitation process, there were differences in the IE and SCE PVC scores for initial shortlist evaluation primarily related to scores associated with Project Development Experience and Project Financing Status. In general, for new projects the IE interpreted the requirements literally based on the criteria specified. For example, the Project Development Experience scores identified are specific. To receive a score of 10 in this category, the company or its development team has to demonstrate that it has completed 2 or more projects of similar technology and similar or larger capacity. There were several cases where a Seller was proposing a solar PV or wind project that was larger than it had previously developed even though the developer had successfully developed several smaller projects of similar technology. The IE interpreted the criteria Merrimack Energy Group, Inc. 36 literally and scored the project based on the literal interpretation. The view of the IE is that such an interpretation is the only way to ensure fairness in the evaluation of the projects from a viability perspective. For final evaluation, the scores generated by the IE and SCE were the same or much closer since more detailed project information became available during the contract negotiation process. As noted, the current PVC has been a valuable tool for assessing project viability in previous solicitations where the threshold criteria were more lenient. However, assuming that SCE continues to maintain stricter threshold criteria it may be worthwhile to reassess the PVC criteria, weights and scores for each criteria to reflect the more mature development status of renewable project proposals in California RPS solicitations. C. Recommended Future LCBF Improvements The IE has several recommendations for future LCBF and solicitation improvements. Identify a target of GWhs to be procured or at least a range of requirements for each year of the solicitation period in a public document. For example, SCE stated in its presentation to the PRG that its procurement target for this solicitation was 1,600 GWh of annual renewable additions per year. If SCE is concerned about being too exact with regard to how much renewable energy it is looking for, the solution could be to provide a range of expected requirements with the caveat that this is an estimate only and not a guaranteed amount. In accordance with a 2009 Commission decision,35 SCE is required to accept and evaluate any proposal with a contract delivery term of more than 20 years. In this RFP, SCE required Sellers to propose a 20 year term if they also want to offer a proposal greater than 20 years, but treated the 20-year proposals in the evaluation as the best offer, even if the quantitative evaluation indicated a superior renewable premium under a 25 year contract term. This is apparently due primarily to SCE’s concerns regarding the potential for adverse accounting treatment—capital lease accounting—associated with PPAs with contract terms longer than 20 years. SCE’s approach did not adversely impact any Seller relative to other Sellers since all Sellers who submitted 25-year proposals also submitted proposals for 20 years as required and their 20-year offers were fairly evaluated. However, in future solicitations, it would promote transparency if the procurement documents addressed how proposals with contract terms of greater than 20 years would be treated in the evaluation. In light of SCE’s and the Commission’s concerns regarding project viability—the likelihood that projects selected in the RPS solicitation process will be permitted, financed and placed in service—consideration should be given to placing the risk 35 Decision Conditionally Accepting 2009 Renewables Portfolio Standard Procurement Plans and Integrated Resource Plan Supplements. D. 09-06-018 (June 8, 2009) pp.39-40. Merrimack Energy Group, Inc. 37 of permitting failure on the Seller in the Pro Forma PPA. Under Section 2.03(a) of the Pro Forma PPA, the Seller has the right to terminate the PPA and get back its security deposit if it fails to obtain necessary construction permits. It is far more typical in renewable energy solicitations of which Merrimack Energy is aware that Sellers who fail to achieve commercial operation due to failure to receiver permits take the financial risk in the PPA—by forfeiting all or a portion of the security deposit as liquidated damages. This may help in reducing the “contract failure” rate, by deterring developers with major project permitting risks from bidding or by requiring them to price the risk into their bids. D. Additional Information or Observations Regarding SCE’s Evaluation Methodology No additional information or observations are provided. V. Did SCE Fairly Administer the Evaluation and Selection Process? This section of the report discusses SCE’s administration of the evaluation and selection process and whether or not the process was conducted fairly and consistently. The IE’s conclusion is that overall the evaluation process was conducted in a fair and consistent manner. The IE agreed with the depth of the shortlist selected by SCE and the proposals selected for the shortlist, including several geothermal proposals that were selected out of economic rank order but offered portfolio diversity to SCE. The IE also concurred with the reasonableness of the evaluation process for final offers. With regard to the selection of final offers, the IE agreed with the seven project proposals selected order to meet a two times need quantity36, but has reservations regarding the selection of the Geysers geothermal proposal, which raises a variety of policy and factual questions for the Commission to address in a competitive solicitation context. This section of the report discusses the evaluation and selection process that led first to the shortlist and then to final offer selections and describes the fairness and reasonableness of the decisions. 36 The seven projects selected The IE was supportive of selection based on two times need because of the risk that several of these projects might not achieve commercial operation. Merrimack Energy Group, Inc. 38 A. Principles and Guidelines Used to Determine Fairness of Process In evaluating SCE’s performance in implementing its evaluation and selection process, Merrimack Energy has applied a number of principles and factors, which incorporate those suggested by the Commission’s Energy Division as well as additional principles that Merrimack Energy has used in its oversight of other competitive bidding processes. These include: Were all proposals treated the same regardless of the identity of the Seller? Were Seller questions answered fairly and consistently and the answers made available to all, where appropriate? Was the economic evaluation of the proposals fair and consistent to all Sellers? What quantitative and qualitative factors were used to evaluate proposals? Did the bid evaluation team maintain consistent scoring and evaluation among and across projects, including different types of projects? Were the requirements and criteria listed in the Procurement Protocol applied in the same manner to all proposals? Was there evidence of any undue bias regarding the evaluation and selection of different type of technologies, project structures, bid sizes, or contract terms that cannot be reasonably explained? Were the proposals given equal credibility in the economic evaluation? Did SCE ask for “clarifications” in a manner that provided a Seller an unfair advantage over others? Did all Sellers have access to the same information? Were all cost factors (e.g. imputed debt, transmission costs) treated in an equitable and consistent manner? Did SCE consistently apply the requirements, procedures and criteria of the evaluation process as identified in the RFP documents to different proposals and types of projects? Was the evaluation and selection process based on adequate information about each proposal and a thorough investigation by SCE’s project team? During the discussions leading up to selection of the shortlist, SCE also considered qualitative attributes to either eliminate or add projects. The qualitative attributes Merrimack Energy Group, Inc. 39 considered included attributes that were identified in SCE’s Procurement Plan as well as specific attributes that were considered based on the circumstances in the market influencing this solicitation.37 The following qualitative attributes were considered in the development of the shortlist: Project viability: new vs. existing projects Term of the offer (10, 15, 20 and 25 years) TRTP timing of build-out IID network upgrade costs spread across transmission access customers Out-of-state resource eligibility—Category 1 (for example; dynamic scheduling) Fuel diversity and the inclusion of geothermal Environmental considerations: SCE reviewed projects using the Nature Conservancy Goggle Earth maps to assess potential environmental impacts and permitting challenges Some of these same issues were considered by SCE in making selections of final offers, especially (a) project viability and diversity benefits of existing geothermal capacity and (b) IID network upgrade costs, B. Description of IE Methodology Used to Evaluate Administration of SCE’s LCBF Process SCE provided the IE access to the data inputs used in the evaluation model as well as the outputs which served as the basis for selection of the shortlist. SCE provided several output files for IE review and comments during the evaluation process, with revisions to the outputs based on updates to proposal information obtained during the cure and conformance period. As previously noted, SCE used the Accion Power website as the bidding platform. Sellers were able to upload their proposals to the website and were required to provide the proposals in consistent file format which facilitated review. Sellers were also provided 37 Several market issues had an influence in informing SCE’s use of business judgment in shortlist selection. First, the inherent conflict between the developers’ interest to construct their projects by December 2016 to take advantage of the current 30% Investment Tax Credit and SCE’s need for energy in the 2019-2020 timeframe led to challenges in evaluation and selection. While SCE’s goal was to allow projects to achieve an earlier commercial operation date (to allow solar projects to qualify for the 30% ITC) to lower cost for customers), SCE preferred a later delivery date for the energy, capacity and renewable attributes. Second, a few projects proposed to deliver power via the Tehachapi Renewable Transmission Project with a proposed delivery date in the 2016 timeframe. SCE’s view was that the TRTP facilities would not be completed in time for a 2016 delivery and therefore SCE did not want to take the risk associated with the generation available in the 2016 timeframe if the TRTP was delayed until 2018 or later. SCE initiated calls with shortlisted Sellers who proposed to deliver energy to TRTP to identify the risk SCE was concerned about and to attempt to reach a resolution to allow the projects to remain on the shortlist. As a result, SCE still selected the projects for the shortlist and attempted to work with the Sellers to find a solution rather than eliminating the proposal from consideration. The IE participated in calls with the affected Sellers to discuss options for addressing this issue. One project proposing to deliver to TRTP withdrew prior to submitting a final offer. The one project for which a resolution was reached on this issue submitted a final offer but was not selected for economic reasons. Merrimack Energy Group, Inc. 40 with a bid number, with a unique identifier for each proposal.38 The IE had access to all proposals and documents submitted to the website. The IE also had access to all questions and communications between SCE and the Seller throughout the process. Most importantly, one of the most attractive features of the website was the ability to create reports to summarize proposal information and to then transform the files into Excel to manage the data. The IE created several reports immediately after submission of the proposals to summarize pertinent high level project information, the pricing proposal, and interconnection and deliverability information. The website also maintained a record of all communications and follow-up information provided by the Sellers, which allowed the IE to remotely monitor all activity and communications. During the course of proposal review, the IE raised a number of questions and comments about the evaluation results, specific questions about individual proposals, and apparent inconsistencies for several proposals. The IE was also present via teleconference for all project team meetings, project management meetings, and epRMC meetings in which proposal review and shortlist and final selection decisions were taking place. The IE raised comments and was asked for its opinion on shortlist selection as well as final offer selection. The basis for selection decisions was made evident at these meetings. The IE conducted a review and assessment of both the quantitative and qualitative aspects of proposal evaluation and selection. With respect to the quantitative analysis, the IE: Reviewed the pricing formulas proposed by each Seller and developed a general ranking of proposals based on the pricing ranges proposed; Conducted a levelized cost analysis for a sample of the lowest cost proposals received after conducting an initial assessment of the offer prices based on the reporting function associated with the Accion Power website; Conducted an initial assessment of each shortlisted proposal based on the Project Viability Calculator prior to shortlisting; Conducted an additional assessment of each final project proposal based on the Project Viability Calculator and including any additional information about the project gleaned during the contract negotiation process; Conducted a comparison of the rankings of selected proposals by SCE in comparison to the rankings based on the IE’s analysis; 38 For example, a Seller who offered three proposals and was classified as Bidder 100, may have proposals 100-1, 100-2 and 100-3 as the identifiers for the three proposals submitted. This allowed SCE and the IE to easily identify specific proposals in reviewing and discussing the offers. Merrimack Energy Group, Inc. 41 Reviewed the output generated by SCE and reviewed the results of the evaluation with SCE’s project team lead; Audited the communications between SCE and Sellers by reviewing the email traffic between the parties during all stages of the solicitation process (i.e. leading up to and after proposal submission, and following shortlist selection through final contract execution) by reviewing the email exchanges on the Accion Power website; Maintained communications with the SCE project team during this process regarding the status of conformance of proposals with SCE eligibility requirements and identifying any proposals that were not yet in conformance with requirements; Reviewed and assessed the decisions made by SCE regarding shortlist and final selection, including revisions to the renewable premium values for specific projects based on updated information; Compared SCE’s evaluation of final offers to the evaluation of indicative bids to check for any potential inconsistencies or potential issues in the evaluation; Reviewed and assessed the decisions made by SCE regarding final offer selection. For qualitative factors, the IE independently scored all of the shortlisted proposals based on the Project Viability Calculator. In scoring for shortlisting purposes, both SCE and the IE generally accepted Seller representations without documentation based on Seller attestations or representations, unless the Seller representations were not merited based on the information submitted with the proposal. Both SCE and the IE also scored all projects that submitted final offers. The IE and SCE conducted a more detailed review and assessment of the qualitative factors for final evaluation. At both stages of the evaluation process, the IE had differences with SCE on some proposals, but the differences were relatively small and were understood based on discussions with SCE contract managers and the IE. Overall, the PVC scoring indicated that the shortlisted projects and projects selected for contracts appeared on the whole to be highly viable and SCE’s scoring was reasonable and consistent. We conclude that SCE on the whole reasonably followed the criteria outlined in the Procurement Protocol. In addition, the evaluation was consistent and equitable across different types of proposals and technologies and reflected the totality of costs and benefits identified in the Procurement Protocol. In the course of the evaluation and selection process, there were several matters that arose that presented some difficult factual matters that SCE needed to address. These are addressed in the following sections of this report. Merrimack Energy Group, Inc. 42 In addition, based on our assessment of the evaluation process relative to the above criteria, it is our opinion that all Sellers were treated fairly and consistently and all had access to the same amount and quality of information. SCE maintained a website dedicated to the 2013 RPS RFP and utilized the Accion Power website which provided same time access to information for all Sellers. The Request for Proposals Conference held by SCE provided useful information to all Sellers with regard to the evaluation methodology and the requirements for Sellers to provide the information requested. We also observed no difference in the treatment of Sellers regarding clarification questions for Sellers, correspondence and communications with Sellers, and follow-up contacts. Finally, SCE generally implemented the evaluation criteria and methodologies as outlined in the Procurement Protocol. C. Did the Utility Identify, for Each Offer, the Terms that Deviate From the Utility RFO? Did the IOU Identify Nonconforming Offers Fairly – Fair Both to the Nonconforming Offers and to Conforming Participants? Shortly after proposals were uploaded by Sellers to Accion Power’s website, SCE performed a detailed review of the proposal packages to identify any deficiencies with the regard to the information required from Sellers and to assess if any offers did not meet the eligibility requirements listed in the Protocol. SCE followed up via the website with regard to any deficiencies in the information required or with clarification questions for the Seller. Sellers were generally cooperative in curing any deficiencies. Common deficiencies included failure to provide a signature page for attestations associated with site control and project experience and failure to provide all interconnection studies secured. There were several issues involving non-conformance based on the status of project interconnection studies and arrangements. As discussed previously, the RFP required that bidders have at least a Phase II interconnection study or equivalent.40 In addition, the Procurement Protocol provides “Should Seller’s interconnection arrangement indicate an 39 We will provide our detailed assessment of the Geysers PPA and the pros and cons as to whether it merits Commission approval in the IE report associated with SCE’s advice letter with respect to that PPA. 40 Procurement Protocol Section 1.03(c). Merrimack Energy Group, Inc. 43 interconnection date later than the ERR Generating Facility’s forecasted COD, the Proposal will not be given further consideration.”41 One of the Sellers, However, no study had been performed for the SCE called the Seller with the IE present on the conference call. SCE confirmed that in fact no interconnection study had been performed for and that the deficiency could not be timely cured. SCE informed the Seller that it did not have sufficient information to properly evaluate the offer. There were also issues regarding whether certain proposals had sufficient site control for proposed gen-tie lines in order to meet the requirements of the RFP. Section 1.03(h) of the Procurement Protocol provides: SCE intends that the definition of “Site” and “Site Control” not only mean the land upon which the ERR Generating Facility is expect to be located, but also encompass any rights-of-way or other real property rights (e.g. land on which Seller’s generation tie line between the ERR Generating Facility and the Interconnection Point shall be constructed) necessary for Seller to be able to deliver the Product to SCE. Seller’s Proposal must demonstrate Site Control or the Proposal will not be given further consideration. SCE did not make a final determination of non-conformity; the projects were not shortlisted on the basis that the offers for these projects were not economically competitive. Based on the information submitted by the Seller, it appears that these proposals did not meet the threshold requirements for site control. Another offer that had conformance issues was a proposal . None of the non-conforming bids were sufficiently competitive to make the shortlist on the basis of their renewable premium scores. Both before and after shortlisting, there were questions as to whether SCE evaluated the final 41 Id. Merrimack Energy Group, Inc. 44 offer, which was not sufficiently economically attractive for final selection based on the 2 times need criterion. During the short listing process, SCE’s project leader indicated that no proposal was rejected due to being incomplete. Rather, they indicated that SCE kept a record of proposals that were incomplete, expecting to revisit any of these proposals that were ranked as economically competitive based on their Renewable Premium scores. In addressing non-conformities issues of a less substantive nature, such as incomplete information, SCE was fairly lenient in allowing a variety of shortcomings, such as errors in submittals, to be cured so that the proposals, as revised, would be sufficiently complete and conforming and could compete in the process. In our view, SCE’s approach was fair, reasonable, and inclusive. D. If the IOU Conducted Any Part of the Offer Evaluation, Were the Parameters and Inputs to the Evaluation Criteria Determined Reasonably and Fairly? What Controls Were in Place to Ensure the Parameters and Inputs Were Reasonable and Fair? The parameters and inputs for the quantitative evaluation were largely developed internally by SCE and were locked down prior to submission of the proposals. The IE had the opportunity to review the input files and forecasts and held discussions with SCE project team members to address the approach used to generate the inputs prior to receipt of proposals.42 All the forward curves were locked down prior to receipt of proposals and would therefore not be influenced by any offer. The IE reviewed the methodology used by SCE to develop its forward curves for energy at different pricing points and felt that the methodology (e.g. use of market quotes in the near term followed by a fundamental forecast for the mid-term and trend analysis beyond a certain date)43 was reasonable and consistent with industry practices. SCE updated its energy price forecasts prior to undertaking the final evaluation and therefore used its May, 2014 market price forecast for undertaking the evaluation of the final offers in June, 2014. 42 The IE was familiar with SCE’s approach for developing its input forecasts based on serving as IE on other solicitations such as the CHP RFO 1 and 2 solicitations. Merrimack Energy Group, Inc. 45 SCE also prepared a forecast of capacity prices for purposes of calculating the capacity benefit for eligible proposals.44 The methodology used to develop the capacity price forecast deviates slightly from the previous forecast and results in a lower long-term capacity price relative to the previous forecast. SCE used its October, 2013 capacity value forecast for both the short list and final offer evaluation. Other inputs such as TOD factors, transmission adders, etc. were identified in the Procurement Protocol and were consistently applied in the evaluation. Furthermore, the quantitative methodology was consistently applied to all Sellers, with the overall methodology (except for the inputs) revised (with some improvements) from the previous solicitation. From the qualitative perspective, the Project Viability Calculator tool developed by the Energy Division was used in the PVC scoring of shortlisted projects. SCE did not make any adjustments to the PVC. Merrimack Energy Group, Inc. 46 E. If the IE or a Third Party Conducted Any Part of the Bid Evaluation, What Information/Data Did the Utility Communicate to that Party and What Controls Did SCE Exercise Over the Quality or Specifics of the Out-Sourced Analysis? As noted, the IE conducted a preliminary independent evaluation of shortlisted proposals and then an evaluation of final offers using the same Project Viability Calculator as SCE. SCE did not attempt to influence the IE’s scoring and evaluation of the proposals. The IE had the same access to information as did SCE in the PVC assessment. Other than the IE’s independent PVC scoring, there was no third party participation in the conduct of the bid evaluation. F. Were Transmission Cost Adders and Integration Costs Properly Assessed and Applied to Bids? SCE’s preferred approach was to use at a minimum the Phase II interconnection study results as the basis for assessing network upgrade costs to individual projects. If a project already had executed an Interconnection Agreement, the costs included in the Agreement were used (except as noted below). There were several issues associated with applying transmission cost adders to particular bids: Determining the extent to which transmission network upgrade costs outside of CAISO should be assigned to the project in the economic evaluation; Assessing the extent to which transmission upgrade costs incurred within CAISO are caused by the particular generator, with costs spread to California ratepayers; Network Upgrade Costs Outside of CAISO SCE’s LCBF methodology does not specifically address whether there should be a transmission cost adder for a project that (a) requires transmission network upgrades, (b) is located in a balancing area outside CAISO, and (c) does not propose to directly interconnect to CAISO. Historically, SCE has not assigned a transmission cost adder for these types of projects, whether they are located outside California or in another balancing authority within California, on the basis that SCE’s customers (or California IOU customers) will not be responsible for paying for any of the transmission network upgrade costs. SCE calculated transmission adders for a number of projects proposing to interconnect with IID. SCE calculated them in the same manner as projects that would interconnect with CAISO. However, SCE did not include the results in the renewable premium quantitative metric and presented them separately as an alternative renewable premium. SCE took this approach since it viewed the transmission adders for IID projects as being part of the qualitative evaluation rather than part of the quantitative evaluation. The Procurement Protocol does not specify that transmission adders apply to projects Merrimack Energy Group, Inc. 47 interconnecting outside of CAISO as part of the quantitative analysis, while “transmission area/cluster” and “generating facility location” are listed as criteria that are part of the qualitative analysis.45 Several of the proposed projects within IID would trigger expensive network upgrades, which, in turn, would trigger increased rates to IID’s ratepayers, all in order to serve the California IOUs and their customers in order to meet RPS obligations. SCE’s management expressed a concern that IID would prevail upon CAISO to assume those costs, or at least a substantial share of them, under the theory that the California IOUs were causing the costs to be incurred. SCE’s management expressed concern that it could be perceived as being irresponsible to enter into contracts based on lower perceived costs while there was a significant risk that the costs its customers might have to pay was much higher. To put this in perspective, the cost of network upgrades for two of the projects represented adders of 33-38% to the cost of the associated generation, an unusually high percentage. At the same time, there were many other projects, including several from the same developer, with very attractive prices without high transmission network upgrade costs. The IE has no independent basis to assess the risk that SCE’s customers may have to pay for network upgrade costs to IID’s system at some future time. However, SCE’s assessment does not appear to be unreasonable. SCE’s approach is consistent with fundamental cost causation principles. It seems reasonable that costs incurred to help meet statewide RPS goals should be considered in solicitations to facilitate construction of projects to meet California RPS goals. Moreover, to ignore the incurrence of real costs caused by a candidate project for a PPA solely because some constituency other than the power purchaser’s customers will have to pay for the costs is economically inefficient from a societal standpoint. At the same time, SCE has drawn the line at the state’s border. Network upgrade costs that will be ultimately paid by ratepayers outside California were not considered in the 45 Procurement Protocol 4.01; see also Procurement Plan, Public Appendix H.1, (LCBF Methodology) II.A.1.b, f, Merrimack Energy Group, Inc. 48 economic evaluation. 6 SCE was consistent in its treatment of non-CAISO network upgrade costs in both the shortlisting and final evaluation stages. On its merits, we do not find SCE’s approach to be unreasonable. It is consistent with fundamental cost causation principles with respect to costs incurred inside California. Consequently, it does not seem unreasonable that there is a risk that at some point in time renewable energy purchases of California IOUs resulting in costs to non-CAISO California balancing authorities will be assigned, at least, in part to CAISO, the California IOUs and their customers. In any event, not to assign a transmission cost adder to IID projects would appear to give them an undue competitive advantage over other California projects within the CAISO.47 At the same time, treating non-California projects differently—there appears to be no realistic risk that network upgrade costs would have to be incurred by California customers—seems to be a reasonable distinction. In light of SCE’s historical approach to not include in its evaluation transmission network upgrade costs in non-CAISO California balancing authorities, SCE’s approach in doing so for this solicitation, whether it is viewed as being part of the quantitative or qualitative evaluation, can reasonably be criticized as a weakness from a procedural standpoint as not having a strong basis in the solicitation documents. 46 We also note that to satisfy RPS Category 1 requirements, out-of-state projects must schedule their energy into a California balancing authority without substituting electricity from another source or must dynamically schedule their energy to a California balancing authority. 47 In fact, the bidder for one of the IID projects with very high network upgrade costs touted that its proposal would result in no network upgrade costs to SCE’s customers. Merrimack Energy Group, Inc. 49 The IE recognizes that SCE’s Procurement Plan and Procurement Protocol were not specific on this issue and SCE’s practice in this solicitation was not consistent with its past practice. In the future, we recommend that the issue of treating in-state reimbursable transmission network upgrade costs incurred in CBAs other than CAISO as transmission cost adders be incorporated in the procurement documents in order to inform prospective Sellers and to facilitate transparency, unless, of course, the Commission decided against this approach. Application of Transmission Cost Adder Methodology to Projects Inside CAISO SCE’s LCBF methodology provides that it will calculate transmission cost adders based on the estimated cost of reimbursable network upgrades attributable to individual projects based on the applicable completed interconnection study (Phase 2 or equivalent) or interconnection agreement. SCE applied these principles to a variety of projects with Phase 2 interconnection studies and interconnection agreements. With respect to one project, SCE determined, based on the facts and circumstances, that to apply this approach in a strict fashion would result in a large overestimate of costs assigned to the project. Most of the investment was for network upgrades that SCE had agreed to finance up-front, and much of the reliability network upgrades have already been built or are in progress. A downsizing of also reduced the need for some network upgrades. The reduction in transmission costs assigned to the project materially improved the quantitative evaluation of the project, but it was not sufficient for the project to be shortlisted. The IE reviewed the documentation provided by the bidder and attended a conference call with the bidder’s representative and SCE’s transmission expert. In the IE’s opinion, SCE’s consideration of changes in circumstances since the execution of the interconnection agreement was reasonable. Also, the substantive assessment on assignability of transmission costs appeared reasonable as well. SCE’s review of interconnection arrangements and calculation of transmission adders appeared reasonable and in accordance with the solicitation documents. Merrimack Energy Group, Inc. 50 SCE did not utilize any integration cost adders in its evaluation. This is consistent with its Procurement Plan and several Commission decisions. G. Describe any additional measures the utility exercised in evaluating affiliate, buyout, and turnkey offers. There were no affiliate, buyout, or turnkey offers. H. Describe Any Additional Criteria or Analysis Used in Creating its Short List (e.g. Seller Concentration, Online Date, Transmission Availability, etc.). Were the Additional Criteria Included in the Solicitation Materials? While SCE rank ordered projects based on the Renewable Premium, there were several areas where SCE exercised judgment in creating the shortlist. The shortlist selection process and the additional criteria used in developing the shortlist are described below. 1. First, SCE finalized its procurement target—1,600 GWh per year. The target was based on SCE’s projected needs to ratably satisfy its RPS obligations. As indicated previously, the procurement target was not in any of the solicitation documents. 2. Once SCE had rank ordered bid projects according to Renewable Premium, it developed several potential shortlists based on multiples of the procurement target. The potential shortlists considered were 3. SCE selected the shortlist based on the following qualitative factors: need was needed to have a sufficiently robust a. A shortlist of at least number of counterparties; b. Due to lack of an exclusivity negotiating obligation on the part of counterparties, some shortlisted projects were expected to drop off the shortlist; c. A larger shortlist would include more projects with contract start dates that were in the timeframe of SCE’s greatest need; d. Technology, size, fuel and location diversity was considered; e. Expiration of the 30% ITC for solar projects in 2016 favored a larger shortlist; f. Project viability in terms of new vs. existing projects; g. Projects associated with build out of the Tehachapi Renewable Transmission Project; and h. As previously mentioned, concerns relating to IID network upgrade costs. Merrimack Energy Group, Inc. 51 4. Three solar PV projects located in IID that otherwise would have been shortlisted because of renewable premium ranking were not shortlisted when IID transmission network upgrade costs were 5. Three existing geothermal projects were added to the shortlist SCE’s rationale was that these existing geothermal projects added value to the shortlist because they had high viability as existing projects and offered non-intermittent production while all other shortlisted projects were solar photovoltaic, wind and solar thermal. SCE also concluded that the pricing offered by these projects compared favorably to pricing generally offered by geothermal projects. 6. Two projects, bid expected commercial operation dates in December 2016. These projects are on the TRTP transmission project. SCE’s project team expressed concerns of their management that the TRTP would not be ready by that time and that negative energy pricing and risk of curtailments might occur before TRTP could be in service and mitigate the problem. Several Sellers proposed energy storage as additional elements of project proposals, including shortlisted projects, but the energy storage offers tended to be vague and not as economically attractive as the offers for the same projects without energy storage. SCE selected the offers without energy storage but indicated that it would entertain more specific offers that included energy storage for shortlisted projects if Sellers wanted to negotiate contract terms that would provide for energy storage features. Merrimack Energy Group, Inc. 52 The result of SCE’s approach was a short list that took into consideration a variety of risks (bidder concentration/project viability/technology/IID network upgrade costs) while being more diverse, with the potential for being larger in size, than if the short list was chosen solely based on the Renewable Premium metric and SCE’s initial procurement target. Since SCE is using a two-stage process for final evaluation and selection of proposals, a deep shortlist should not be an issue and should result in more competitive price pressures for those Sellers and proposals still under consideration. In the IE’s view, SCE’s decision to select a deep short list and use the factors identified above for purposes of structuring the short list was generally reasonable and consistent with the Procurement Protocol. I. Results Analysis 1. Identify instances where the IE and the IOU disagreed in the LCBF evaluation process The IE raised a number of clarifying questions with SCE about its interpretation of the proposals by a few bidders as well as potential inconsistencies in the evaluation results. Generally, the IE identified potential inconsistencies or errors, brought these to SCE’s attention, and held a discussion or exchanged emails with SCE until the issue was resolved. One area where the IE had an issue with shortlist selection was associated with the The IE interpreted the proposal to be mutually exclusive among the three offers while SCE did not view the proposals as being mutually exclusive but offered the option to take any or all projects. After shortlist selection, 2. Overall, was the overall offer evaluation fairly administered In the IE’s opinion, the overall offer evaluation was fairly administered for the reasons previously stated in this report, with the qualification that the selection of the Geysers project proposal SCE, however, presented a strong rationale for its selection of the Geysers proposal, subject to review and approval of the resulting PPA by the Commission, J. Any Other Relevant Information or Observations The IE has replicated the shortlist in Appendix C. The final offers submitted by the shortlisted projects are summarized in Appendix D. Appendix E provides a summary of the final evaluation results. Merrimack Energy Group, Inc. 53 VI. Does the Proposed RPS Shortlist Merit Commission Approval?; Was the Evaluation and Selection Process for Final Offers Reasonable and in Accord with the Procurement Protocol? This section addresses whether SCE’s shortlist merited CPUC approval. The CPUC in a letter order determined that the shortlist was effective, albeit without explanation. This section of the report also addresses the reasonableness of SCE’s evaluation of final offers and its selection decisions. A. Did the IOU Conduct a Fair Solicitation That Was Consistent with Commission Decisions and its Approved LCBF Methodology? For the reasons stated herein, Merrimack Energy concludes that SCE conducted a fair, thorough and detailed solicitation process leading to shortlist selection that was consistent with Commission decisions and SCE’s approved LCBF methodology. SCE followed its stated evaluation process from receipt and initial review of proposals to final shortlist selection. SCE used its LCBF methodology as described to calculate the Renewable Premium values for all proposals, including options proposed by Sellers for the same projects. SCE then selected the option for each proposal or project which had the highest Renewable Premium value, after eliminating proposals with a 25 year term. From there, all proposals were ranked based on the highest to lowest values based on Renewable Premium. Since SCE’s ranking focused on the highest valued proposals for each project, the final shortlist is primarily comprised of the offers that provide the highest value. The three proposals that were not selected were IID projects that had high estimated upgrade costs. SCE chose to augment its shortlist with three geothermal projects that “jumped over” a number of projects on the economic merit order list based on considerations of fuel and technology diversity and project viability. SCE’s shortlisting decisions were reasonable and were grounded in the requirements, evaluation criteria and stated preferences set forth in the Procurement Protocol. The selection of the short list was very inclusive and erred on the side of including more proposals. B. Did the IOU Choose Projects for the Shortlist That Provide the Best Overall Value to Ratepayers While Meeting the IOU’s RPS Compliance Needs? Could the IOU Have Incorporated a Decision-Making Process That Provided for a Different Portfolio of Projects That Provide Better Overall Ratepayer Value While Meeting the IOU’s RPS Compliance Needs? As noted above, SCE selected projects in merit order up to the top , with the exception of three IID projects on the initial shortlist that fell out of economic merit order, when network upgrade costs were assigned to the Renewable Premium evaluation of these bids. Even without these three projects, the total GWhs included on the merit order ranking would still be nearly the estimated procurement target. The only proposals taken out of merit order were the geothermal proposals which have the highest Renewable Premium values. Merrimack Energy Group, Inc. 54 As a result, the projects on the shortlist included the most highly ranked projects from a purely quantitative perspective, eliminated the three projects with the highest risk of very high transmission costs being assigned to SCE customers that were not included in the initial quantitative assessment, and provided for inclusion of three existing nonintermittent geothermal facilities While it is a matter of judgment whether this particular shortlist provides the best overall value for SCE and its customers, the IE concurred with the reasonableness of SCE’s shortlisting decisions to consider IID network upgrade costs in its evaluation and to include the geothermal projects to provide resource diversity at prices that were deemed low for geothermal projects. C. Did the Shortlist Conform to the Needs of the IOU’s Portfolio, RPS Requirements, RPS Procurement Plan and Protocol? The shortlist conforms well to SCEs needs as identified in the RPS Protocol and RPS Procurement Plan. All shortlisted proposals had either an Interconnection Agreement or Phase II interconnection study as required. A large number of the proposals selected have a COD date that conforms to SCE’s needs in the 2019-2020 timeframe. There is also a mix of proposals that include new and existing proposals along with proposals with 10, 15, and 20 year contract terms. Although the shortlist portfolio is heavily weighted toward solar projects, there is a mix of solar PV projects and solar thermal projects. Wind and geothermal projects are also represented on the shortlist. While counterparty concentration is fairly high for one Seller , as the depth of the shortlist increases, supplier concentration ratios decline as more Sellers are brought into the shortlist. With on the shortlist, supplier concentration does not appear problematic. The IE believes that overall SCE followed the methodology described in its RPS Procurement Plan and Procurement Protocol in developing and finalizing a short list using the applicable metrics and criteria and applying reasoned judgment. Overall, SCE’s decisions were consistent with the RPS Procurement Plan, Procurement Protocol and with LCBF principles. D, Did SCE Reasonably Evaluate the Final Offers and Make Reasonable Selection Decisions in Accord with the Procurement Plan and Protocol? As previously noted, in its Procurement Plan SCE proposed to adopt a two-step evaluation process for this evaluation. As in prior solicitations, sellers will submit their proposals and, after evaluating each proposal, SCE selects the best proposals for inclusion on a short list. SCE and shortlisted sellers then negotiates contract terms over a set negotiation period, expected to be approximately three months. Should SCE and a seller be unable to complete negotiations in the time frame, the seller’s proposal is Merrimack Energy Group, Inc. 55 dropped from consideration. At the end of the negotiation period, sellers have an opportunity to refresh their proposed pricing, but no other elements of their proposal or the negotiated contract terms may be changed. SCE then re-evaluates proposals based on the refreshed pricing and execute those contracts that it determines will provide the best value to its customers. SCE indicated in its Procurement Plan that it expects this structure to significantly reduce the amount of time required to negotiate contract terms for both SCE and sellers. Additionally, the two-step solicitation process will alleviate the problem of pricing terms becoming stale because of the time period between shortlisting, contract execution, and Commission review of the contract, which the Commission has identified as a potential problem. After shortlist selection, SCE began to initiate Step 2 in the process. For the remaining projects, SCE identified a Contract Manager to lead contract negotiations with each counterparty, along with an attorney and representative from Credit as the team for the negotiation process with each counterparty. Earlier in the process, SCE had posted the pro forma PPA to the Accion website. SCE now requested the remaining shortlisted sellers to review the PPA and provide a red-line as soon as possible. Once the red-lines were submitted contract negotiations would begin. SCE also offered a debriefing session for any Seller that was not shortlisted. A number of Sellers requested debriefing sessions and SCE accommodated the requests. The IE was a participant on most of the calls. During the early stages of contract negotiations, Once final offers were received, SCE conducted its final evaluation and assessment of each offer and rank ordered the projects based on Renewable Premium and Alternative Renewable Premium values. Merrimack Energy Group, Inc. 56 While the IE was in agreement with the seven solar projects selected we do have some concerns about the Geysers project We will address the relative merits of the Geysers PPA in detail in the IE report associated with SCE’s advice letter for that contract. However, it is our perspective that whether or not the Commission approves the Calpine Geysers PPA should not bear upon the merits of the seven solar PV PPAs VII. The Mount Signal II and Mount Signal V PPAs and the Fairness of the Project-Specific Negotiations A. The Mount Signal II and Mount Signal V Projects and PPAs 8minutenergy Renewables and Silver Ridge Power Mount Signal II and Mount Signal V proposed solar PV projects being developed in southern Imperial County west of the City of Calexico. 8minutenergy Renewables and Silver Ridge Power submitted 8minutenergy Renewables and Silver Ridge Power also submitted Mount Signal V, for Commercial Terms of the Mount Signal II and V PPAs 8minuteenergy Renewables and Silver Ridge Power were successful in reaching timely agreement on contract terms with SCE, which allowed them to submit final offers for the Mount Signal II and Mount Signal V projects. The PPAs were executed on July 31, 2014. This section of the report will provide an overview of the key provisions of the Mount Signal II and Mount Signal V PPAs including project specific provisions, performance and operational provisions. In addition the report addresses Merrimack Energy Group, Inc. 57 There were several issues and considerations associated with the negotiation of contract provisions with the Mount Signal Solar Farms projects, including the following: The key project specific terms of the Mount Signal II and Mount Signal V PPAs are summarized below. Generating Facility Name (Section 1.01(a)) Product (Section 1.01(d)) Type of Facility (Section 1.01(g)) Delivery Point – Section 1.01(f) Location of Facility (Section 1.01(b), Exhibit B Delivery Term – Section 1.05 Mount Signal Solar Farms II Mount Signal Solar Farms V All electric energy produced by the generating facility, net of Station use; all green attributes; all capacity attributes; and all resource adequacy benefits. Solar PV Single access tracking All electric energy produced by the generating facility, net of Station use; all green attributes; all capacity attributes; and all resource adequacy benefits Solar PV Single access tracking At the point of interconnection with the CAISO controlled grid at the Imperial Valley substation City of Calexico, in southern Imperial County, CA 20 years from the Commercial Operation Date At the point of interconnection with the CAISO controlled grid at the Imperial Valley substation City of Calexico, in southern Imperial County, CA 20 years from the Commercial Operation Date Merrimack Energy Group, Inc. 58 Contract Capacity (Section 1.01(h)) Price (Section 1.06(a)) Annual degradation factor (Section 1.01(j)) Commercial Operation Date – Section 1.04 153.52 MW (AC); 252.32 MW (AC); June 1, 2020 February 1, 2019 . Time of Delivery Periods (“TOD Periods”) TOD Period Summer Jun 1st – Sep 30th Winter Oct 1st – May 31st Applicable Days On-Peak Noon – 6:00 p.m. Not Applicable. Weekdays except Holidays. Mid-Peak 8:00 a.m. – Noon 8:00 a.m. - 9:00 p.m. Weekdays except Holidays. 6:00 p.m. – 11:00 p.m. Off-Peak Super-Off-Peak 11:00 p.m. – 8:00 a.m. Weekdays except Holidays. 6:00 a.m. – 8:00 a.m. Weekdays except Holidays. 9:00 p.m. – Midnight Weekdays except Holidays. Midnight – Midnight 6:00 a.m. – Midnight Weekends and Holidays Not Applicable. Midnight – 6:00 a.m. Weekdays, Weekends and Holidays Merrimack Energy Group, Inc. 59 TOD Period Summer On-Peak Fixed Value. 2.64 Mid-Peak Fixed Value. 1.27 Off-Peak Fixed Value. 0.82 Mid-Peak Fixed Value. 0.96 Off-Peak Fixed Value. 0.87 Super-Off-Peak Fixed Value. 0.74 Winter Calculation Method Full Capacity Deliverability Status Product Payment Allocation Factor Season “Holiday” is defined as New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, and Christmas Day. When any Holiday falls on a Sunday, the following Monday will be recognized as a Holiday. No change will be made for Holidays falling on Saturday. SCE’s economic analysis of the costs of the Project was based on post-TOD payments in light of the Project’s production profile. Other PPA Contract Terms and Conditions Merrimack Energy Group, Inc. 60 Merrimack Energy Group, Inc. 61 B. Identify principles used to evaluate the fairness of the negotiations The general principles followed by the IE in evaluating contract negotiations include assurance that the risk allocation provisions in the contract are reasonably balanced between the counterparties and that the utility customers are not placed at undue risk as result of the contracting process. The IE generally “monitors” but does not actively participate in the contract negotiation process but will identify issues to the utility transactors if negotiations are moving off track, if there are biases or inconsistencies in the process, or if the IE wants to ensure that all similar projects being negotiated are treated in a similar manner. It has been our experience in monitoring a number of negotiation processes that contract negotiations can divert off course but eventually return to a balance after contested provisions are resolved. We also attempt to ensure that similarly situated counterparties are treated the same or similarly and that all counterparties are provided with the same message. For example, SCE informed shortlisted bidders throughout the process that this was still a very competitive process with no guarantee of a bidder being awarded a contract since more projects were shortlisted than the amount of renewable energy it was seeking to contract in the solicitation. While SCE did not directly inform shortlisted bidders how much they needed to lower their price to be competitive, there was a clear message that all shortlisted bidders should sharpen their pencils for the final offer pricing. C. Using the above principles (Section V.A.), please evaluate fairness of project-specific negotiations SCE established contract negotiation teams for each counterparty that included a commercial contract manager, attorney and credit analyst. In addition, SCE established a core team to address issues that arose during the contract negotiation process from an internal policy perspective to ensure a consistent message and internal policy was conveyed to all contract negotiation teams. In addition, SCE held weekly core team meetings as well as weekly meetings of the contract negotiation teams to assess the status of negotiations, discuss any policy of contract negotiation issues that may arise and ensure that all contract negotiation teams were fully aware of any issues that may emerge in other contract negotiation processes. The IE found this process to be particularly valuable for keeping everyone on the contract Merrimack Energy Group, Inc. 62 negotiation teams up to speed on any issues that were emerging during the contract negotiation sessions. While the IE concludes that all counterparties were fairly treated during the contract negotiation process, it is fair to say that the time crunch during the final push to finalize contracts prior to the execution date created challenges and the possibility of inconsistent treatment. However, the checks and balances process undertaken by SCE to review and internally approve all contracts prior to execution resulted in consistent treatment for all counterparties, and all of the contract negotiations that were in process were successfully concluded prior to submission of final offers.50 SCE also held a training session for Contract Managers to address the contract negotiation process and ensure all Contract Managers were familiar with the key provisions of the PPA prior to beginning the negotiation process. An SCE attorney conducted the session and walked the participants through each Article in the PPA, identifying the provisions that bidders had previously requested revisions as well as management positions on several provisions and CPUC non-modifiable provisions. The SCE attorney also described the process internally in cases where the counterparties propose new contracting provisions that may affect several PPAs. The attorney noted that if a material change is requested a number of managers at SCE have to sign off. The IE found the session to be informative and an important step in the process to maintain consistency in the negotiation process among different bidders. In the IE’s opinion, SCE acted fairly and responsibly in the contract negotiations and treated Mount Signal II and Mount Signal V in a similar manner to other counter parties in light of the nature of the Mount Signal II and Mount Signal V projects and the contract issues raised by 8minutenergy Renewables and Silver Ridge Power as their developers. D. Identify the terms and conditions that underwent significant changes during the course of negotiations? This section of the report will address the standard PPA terms and conditions that underwent significant change during the course of negotiations. In the case of SCE’s RPS solicitation process, the IE will address two areas of interest. The first are those contract provisions that were revised or added to the PPA that affected many of the shortlisted 50 There were a few contract matters that arose after final offers that required resolution, but they were not of a material nature. Merrimack Energy Group, Inc. 63 projects. The second are provisions that underwent changes for the specific PPA that is the subject of this Advice Letter report. General PPA Changes The starting point for negotiations with all counterparties was the standard Pro Forma Renewable PPA. SCE posted the Pro Forma PPA on the website. SCE’s Pro Forma PPA is structured under the assumption that: Seller’s proposal is based upon the greenfield development of a new Generating Facility; The Generating Facility’s first point of interconnection will be with the CAISO; and SCE will be the Scheduling Coordinator. Shortlisted Bidders were requested to provide a red-line version of the PPA as soon as practical after shortlist notification, although it was typical that red-lines were submitted to the Accion website two to four weeks after shortlist notification. SCE informed the shortlisted Bidders that there was only a three month window for negotiations and encouraged shortlisted Bidders to post the red-line of the Pro Forma within a reasonable timeframe since contract negotiations could not begin in earnest until the red-line had been posted. Several contract provisions were revised or provisions added during the course of negotiations to address issues that were pertinent to most or several projects. Merrimack Energy Group, Inc. 64 Merrimack Energy Group, Inc. 65 E. Was similar information/options made available to other participants, e.g. if a participant was told to reduce its price down to $X, was the same information made available to others? The IE concludes that similar information and options were made available to all participants. Not only were SCE’s processes and procedures established with a goal of ensuring that all projects had access to the same information but SCE on several occasions sent emails and other notification to all shortlisted bidders informing them of the schedule for completing negotiations and finalizing contracts. F. Any other relevant information or observations, such as other data or information used to inform the negotiations VIII. Does the Contract Merit CPUC Approval? A. Provide narrative for each category and describe the project’s ranking relative to: 1) other offers from the solicitation (or recent bilaterals or market information if used in reasonableness comparison; 2) other procurement opportunities (e.g. distributed generation programs); and 3) from an overall market perspective: 1. Contract Price, including transmission cost adders 2. Project’s net market value 3. Consistency with stated RFO goals 4. Portfolio Fit 5. Project Viability 6. a. Project Viability Calculator score b. IOU-specific project viability measures c. Other (credit and collateral, developer’s project development portfolio, transmission, other site-related matters, etc.) Any other relevant factors Merrimack Energy Group, Inc. 66 Merrimack Energy Group, Inc. 67 Both the Mount Solar Farms II and Mount Solar Farms V projects and PPAs meet the key goals of SCE’s 2013 RPS RFP. The projects are being developed by reasonably experienced solar PV developers that are very familiar and active in the California market. From a portfolio fit perspective, both Solar Farms II and V fit SCE’s needs. Combined, the projects are expected to provide approximately 1,062 GWh/year of generation. Also, from a portfolio fit perspective, the delivery date under the contract to SCE will conform to the date of SCE’s need for the renewable energy in the 2019-2020 timeframe. Merrimack Energy Group, Inc. 68 The Project Viability Calculator serves to highlight project strengths and weaknesses in terms of the developer’s likelihood of being able to successfully finance and build the proposed project if the PPA receives regulatory approval. Areas where a project receives less than all of the points in a category can highlight a project weakness in some cases; in other cases, a less than perfect score is not really problematic. For example, 8minutenergy Renewables and Silver Ridge Power have very experienced and apparently very capable project development teams, with a track record of successful completion of hundreds of MWs of solar PV projects. Similarly, the project sponsors have a very strong track record of having obtained financing of projects it has successfully developed. The Mount Signal Solar Farms II and V projects have significant strengths that contribute to project viability. Merrimack Energy Group, Inc. 69 . B. Do you agree with the IOU that the contract merits CPUC approval? Explain the merits of the contract based on offer evaluation, contract negotiations, final price, and viability. Merrimack Energy agrees with SCE that the Mount Signal Solar Farm II and Mount Signal Solar Farm V projects merit CPUC approval. The PPAs were reasonably negotiated with contract terms that taken as a whole appropriately protect the interests of SCE’s ratepayers. All in all, there are very strong reasons to support approving the Mount Signal Solar Farm II and Mount Signal Solar Farm V PPAs. C. Any other relevant information or observations SCE executed eight PPAs arising out of the 2013 RPS solicitation, with expected energy production While exception might be taken to one or more other PPAs that arose out of this RPS solicitation, Merrimack Energy sees no reason why the Mount Signal Solar Farm II and Mount Signal Solar Farm V PPAs should not receive CPUC approval. Merrimack Energy Group, Inc. 70 Appendix A: SCE’s Least Cost Best Fit Evaluation Methodology Market Valuation SCE will evaluate the quantifiable attributes of each Proposal individually and subsequently rank them based on the Proposal’s benefit and cost relationship, specifically the net levelized cost of the project or Renewable Premium. These individual quantitative components include: capacity benefits, energy benefits, contract payments, debt equivalence mitigation cost, transmission cost, and congestion cost. In developing its relative merit order ranking of Proposals, SCE’s evaluation methodology incorporates information provided by Sellers and assumptions prescribed and set by the Commission with its internal methodologies and forecasts of market conditions. The objective of the quantitative assessment and relative Renewable Premium ranking is to develop a preliminary shortlist that is further refined based on the non-quantifiable attributes discussed below. Each of the elements for the RPS quantitative analysis is described below. Benefits 1. Capacity Benefit Each proposal is assigned a capacity benefit, if applicable, based on SCE’s forecast of net capacity value and the quantity of Resource Adequacy derived by SCE based on the seller’s offer capped at the generating facility’s peak capacity contribution factor, calculated for each facility pursuant to the Qualifying Capacity Methodology Manual, based on the hourly generation profile submitted as part of the offer submittal package. For wind and solar Proposals, peak capacity contribution factors are calculated in a manner consistent with the Commission’s Resource Adequacy accounting rules (D.0906-028) utilizing a 70% exceedance factor methodology based on the hourly generation profile submitted as part of the offer submittal package. Peak capacity contribution factors are both technology and location-specific. Technological differentiation does not refer to the fuel source, but rather the method of converting other energy sources into electricity (e.g. solar trough, solar photovoltaic). For Proposals with dispatchable capabilities at SCE’s control, the peak capacity contribution factor is based on the availability of the proposed project. For other technologies without dispatchable capabilities, the quantity of Resource Adequacy benefits is based on a three-year rolling average of production during certain hours. Monthly capacity benefits include the product of SCE’s net capacity value forecast and the quantity of Resource Adequacy capacity determined for each month of the year. Capacity benefits are only applied for those months in which SCE has a capacity need. Additional value will be attributed to facilities located in the Los Angeles Basin or Big Creek/Ventura local reliability areas. Merrimack Energy Group, Inc. 71 2. Energy Benefit SCE measures the energy benefits, as applicable, of a Proposal by evaluating the estimated market value of energy. The evaluation of energy benefits is performed with a base portfolio and system that is consistent with Track II of SCE’s most recent LongTerm Procurement Plan (“LTPP”), with some updates to account for the latest gas price and the results of recent procurement activities. In the event that a Proposal provides additional value to SCE from the provision of one or more ancillary services (regulation, spin, or non-spin), SCE may use an internal forecast for ancillary service prices as a means of evaluating any incremental benefit. For Proposals with must-take energy, SCE calculates the energy benefits of a Proposal based on SCE’s internal forecast of the market value of energy. The hourly energy benefit for the Proposal is the resulting market price multiplied by the hourly sellerprovided generation profile. For Proposals with dispatchable capabilities at SCE’s control, SCE calculates the net energy benefits based on the market value of the energy when the proposed resource dispatches. SCE utilizes Ventyx’s Prosym model to determine the dispatch economics for the proposed resource according to the unit characteristics provided by the seller. SCE’s gas price and power price forecasts are based on a blend of a near-term market view and a longer-term fundamental view of prices. The simulation model, and hence the energy benefit calculation, captures additional quantitative effects that SCE has been asked to consider by the Commission, including dispatchability. The dispatchability benefits, such as ancillary services and real-time flexibility, are implied in the energy benefit and are not addressed separately. Costs 1. Contract Payments The primary costs associated with each Proposal are the contract payments that SCE makes to sellers for the expected renewable energy deliveries. Proposals typically include an all-in price for delivered renewable energy, which is adjusted in each time-of-delivery period by the applicable energy payment allocation factors (“TOD factors”). Total payments are determined by multiplying the generation by the contract price, adjusted for each TOD period 2. Debt Equivalence “Debt Equivalence” is the term used by credit rating agencies to describe the fixed financial obligation resulting from long-term power purchase agreements (“PPAs”). Merrimack Energy Group, Inc. 72 Pursuant to D.04-12-048, the Commission permitted the IOUs to recognize costs associated with the effect debt equivalence has on the IOU’s credit quality and cost of borrowing in their evaluation process. In D.07-12-052, the Commission reversed this position. SCE, however, filed a petition for modification of D.07-12-052. In November 2008, the Commission issued D.08-11-008, which authorized the IOUs to recognize the effects of debt equivalence when comparing PPAs in their bid evaluations, but not when the IOUs are considering a utility-owned generation project. As such, SCE considers debt equivalence in the evaluation process. 3. Congestion Cost Localized congestion may cause a reduction in prices at a particular locational marginal price (“LMP”) in the California Independent System Operator’s (“CAISO”) Market Redesign and Technology Upgrade (“MRTU”) market. In D.11-04-030, the Commission held that the IOUs must incorporate an assessment of these congestion costs in their LCBF evaluation. SCE applies a locational congestion adder to all projects to differentiate between project locations. These locational adders may be positive or negative depending on the expected congestion in the area. The locational adders are based on SCE’s forecast of LMPs in the CAISO market in the location that seller plans to interconnect. Projects that select an Energy-only (“EO”) interconnection do not fund the deliverability upgrades needed to ensure their energy can serve load and avoid localized congestion. As such, these projects increase the risk of congestion in these locations to a degree greater than projects with a Full Capacity Deliverability Status (“FCDS”) interconnection. In order to capture this difference, SCE applies an incremental congestion cost adder to all CAISO projects that selected an EO interconnection, or any EO portion of the contract term if FCDS status is expected to be achieved after the commercial on-line date. The adder is based on LMPs in the MRTU market in the location that the seller plans to interconnect. 4. Transmission Costs Transmission costs are based on the estimated cost of the reimbursable network upgrades attributable to individual projects. To participate in the 2013 RPS RFP, SCE requires sellers to have an existing Phase II Interconnection study, or an equivalent of better process or exemption. Transmission costs applicable to the project will be based on the applicable completed interconnection study or interconnection agreement. SCE uses the interconnection studies submitted as part of the offer submittal package to determine the applicable network upgrade costs for all projects. These costs will not be imputed for projects in transmission-constrained areas. SCE applies the required upgrade costs to get the project delivered to the nearest defined market (e.g. NP15, SP15, ZP26 Generation Trading Hubs). For projects with an assumed delivery point outside the Merrimack Energy Group, Inc. 73 CAISO (e.g. liquid power trading hub), SCE applies a power swapping methodology, where the power is assumed to be sold into the local market. 5. Integration Cost Integration costs, where applicable, are the additional system costs required to provide sufficient ancillary service capability including load following and frequency regulation to integrate renewable resources. As California continues to procure additional intermittent renewable resources, SCE believes that current levels of intermittent renewable resources will require an increase in the provision of ancillary services mentioned above, and that an integration study that reflects updated regulatory and procurement expectations should be used as the basis for integration costs. Moreover, new Public Utilities Code Section 399.13(a)(4)(A)(i) provides that the Commission shall adopt LCBF criteria that take into account estimates of indirect costs associated with needed transmission investments and ongoing electrical corporation expenses resulting from integrating and operating eligible renewable energy resources. However, in D.1211-016, the Commission declined to all the use of non-zero integration cost adders. Portfolio Fit SCE’s LCBF quantitative evaluation process inherently captures the impact of portfolio fit. For example, as different Proposals are added to the overall portfolio, the resultant residual net short or net long position is impacted. Projects that more often increase SCE’s net long capacity positions are assigned less capacity benefits than those projects that are more often filling net short positions. SCE also considers portfolio fit in its qualitative analysis. Specifically, when assessing additional qualitative characteristics to determine advancement to the shortlist or tiebreakers, SCE’s preference is for those projects that have commercial operation dates that match periods of SCE’s need for renewable energy. Credit and Collateral Requirements In order to ensure comparable pricing for ranking, SCE requires sellers to bid conforming Proposals committing to posting SCE’s pro forma performance assurance amount. SCE accepts lesser performance assurance to be bid as long as a conforming Proposal is also submitted. Performance assurance is the collateral posted by the seller during the operating period. Project Viability SCE assesses the following attributes using the Project Viability Calculator: Company/Development Team Project Development Experience Ownership/O&M Experience Merrimack Energy Group, Inc. 74 Technology Technical Feasibility Resource Quality Manufacturing Supply Chain Development Milestones Site Control Permitting Status Project Financing Status Interconnection Progress Transmission Requirements Reasonableness of Commercial Operation Date (COD) Other Qualitative Criteria/Preferences Following the Project Viability Calculator qualitative assessment, SCE considers additional qualitative characteristics to determine advancement to the shortlist or tiebreakers, if any. These additional characteristics may include: Contribution to other SCE program goals (e.g. GHG reductions pursuant to the CHP Settlement Agreement); Transmission area (e.g. Tehachapi, Sunrise, within SCE’s load pocket); Congestion, negative price, and curtailment considerations not captured in the quantitative valuation; EO concentration; Facility interconnection process progress; Portfolio fit of COD; Seller concentration; Contract capacity (MW); Expected generation (GWh/year); Dispatchability; Alternative Renewable Premium; Environmental Impact of seller’s proposed project on California water quality; Resource diversity; Benefits to minority and low income communities; Local reliability; Environmental stewardship. Merrimack Energy Group, Inc. 75 Confidential Appendix D.1 Contract Summary for Mount Signal II Contract Confidential Appendix D.2 Contract Summary for Mount Signal V Contract Confidential Appendix E Comparison of the Mount Signal II Contract and the Mount Signal V Contract with SCE’s 2013 Pro Forma Renewable Power Purchase and Sale Agreement Confidential Appendix F Mount Signal II Contract and Mount Signal V Contract Confidential Appendix G Renewable Net Short Calculations Public Appendix G Renewable Net Short Calculations Physical Renewable Net Short Calculations Based on CPUC Assumptions Deficit from RPS Variable Calculation Item prior to 2011 2012 2013 Reporting Year Actuals Actuals Actuals Forecast Year 2011-2013 CP1 2014 2015 2016 Forecast Forecast Forecast 1 2 3 21.7% 23.3% 25.0% 2014-2016 CP2 2017 2018 2019 2020 Forecast Forecast Forecast Forecast 4 5 6 7 2017-2020 CP3 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast 8 9 10 11 12 13 14 15 16 17 18 19 20 33.0% 33.0% 33.0% Annual RPS Requirement 1 Bundled Retail Sales Forecast (LTPP) A B RPS Procurement Quantity Requirement (%) C A*B D Gross RPS Procurement Quantity Requirement (GWh) Voluntary Margin of Over-procurement E C+D Net RPS Procurement Need (GWh) 73,777 20.0% 14,755 75,597 20.0% 15,119 74,480 223,854 20.0% 14,896 75,747 27.0% 44,771 - - - - 14,755 15,119 14,896 44,771 29.0% 21,967 - - - - - 75,089 31.0% 23,277 75,662 76,194 33.0% 33.0% 24,968 - - - 21,967 23,277 24,968 25,144 - 76,660 33.0% 25,298 76,980 33.0% 25,404 77,205 33.0% 25,478 84,909 33.0% 28,020 86,495 33.0% 28,543 88,203 33.0% 29,107 90,012 33.0% 29,704 91,941 33.0% 30,340 94,003 33.0% 31,021 - - - - - - - - - - 25,144 25,298 25,404 25,478 28,020 28,543 29,107 29,704 30,340 31,021 9,034 RPS-Eligible Procurement Fa Risk-Adjusted RECs from Online Generation 15,654 15,821 16,479 47,953 16,867 16,677 15,892 49,436 15,045 14,688 14,651 13,816 58,200 13,187 13,107 13,109 13,016 12,975 12,779 11,412 10,581 10,425 Faa Forecast Failure Rate for Online Generation (%) 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Fb Risk-Adjusted RECs from RPS Facilities in Development - - 56 56 1,058 2,293 3,364 6,715 3,802 3,839 5,083 6,065 18,790 6,142 6,117 6,093 6,083 6,044 5,999 5,976 5,966 5,929 5,906 Fbb Forecast Failure Rate for RPS Facilities in Development (%) N/A N/A 0.0% 0.0% 6.0% 22.1% 31.3% 25.1% 32.6% 32.4% 35.5% 38.4% 35.3% 38.7% 38.7% 38.8% 38.8% 38.8% 38.8% 38.8% 38.9% 38.9% 38.9% Fc Pre-Approved Generic RECs - - - - - 37 145 182 809 904 907 910 3,529 907 907 907 910 907 907 907 910 907 907 Fe Executed REC Sales 362 778 473 1,614 - - - - - - - - - - - - - - - - - - - 15,291 15,043 16,062 46,396 17,926 19,006 19,401 56,333 19,656 19,431 20,640 20,791 80,519 20,235 20,131 20,109 20,009 19,926 19,685 18,294 17,457 17,262 15,848 2 Fa+Fb+Fc-Fe Total RPS Eligible Procurement (GW F F0 Category 0 RECs 3 15,239 14,912 15,822 45,973 16,887 16,752 15,820 49,460 13,929 12,724 12,527 11,686 50,865 11,055 10,969 10,967 10,870 10,839 10,638 10,420 10,399 10,237 8,841 F1 Category 1 RECs 3 52 131 240 423 1,038 2,217 3,436 6,692 4,918 5,804 7,207 8,196 26,124 8,273 8,255 8,236 8,229 8,180 8,140 6,967 6,148 6,117 6,100 F2 Category 2 RECs 3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,166 1,625 (2,535) (2,637) (4,177) (4,909) (5,167) (5,294) (5,469) (8,094) (8,858) (10,813) (12,247) (13,079) (15,173) 21.6% 20.7% 25.7% 27.5% 27.5% 26.6% 26.3% 26.1% 25.9% 23.5% 22.8% 20.7% 19.4% 18.8% 16.9% Category 3 RECs F3 Gross RPS Position (Physical Net Short) Ga F-E Annual Gross RPS Position (GWh) Gb F/A Annual Gross RPS Position (%) 536 20.7% (76) 19.9% Application of Bank Ha Existing Banked RECs above the PQR Hb RECs above the PQR added to Bank 536 Hc Non-bankable RECs above the PQR - Gross Balance of RECs above the PQR Ia Planned Application of RECs above the PQR towards RPS Comp Ib Planned Sales of RECs above the PQR 0 0 0 Net Balance of RECs above the PQR 536 451 1,586 H Ha+Hb J H-Ia-Ib 3 J0 Category 0 RECs J1 Category 1 RECs 3 J2 Category 2 RECs 3 0 451 0 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 1,136 1,586 - - - - - - - - - - - - - 9 30 39 - - - - - - - - - - - - - 536 451 1,586 1,586 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 - - - - - - - - - - - - - - - 1,164 536 (85) - - 1,586 - 1,586 0 0 0 - 0 - 0 0 0 1,586 5,709 5,709 - 0 0 0 0 0 0 0 0 0 0 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 - - 1,164 - - - - - - - - - - - - - 52 131 240 423 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 6,903 8,050 8,922 9,511 9,824 9,921 10,078 10,071 10,309 10,518 10,574 10,686 11,279 Expiring Contracts K 2,029 RECs from Expiring RPS Contracts 2,524 3,627 8,181 5,589 29,464 Net RPS Position (Optimized Net Short) La Ga+Ia-Ib-Hc Annual Net RPS Position after Bank Optimization (GWh) Lb (F+Ia-Ib-Hc)/AAnnual Net RPS Position after Bank Optimization (%) 536 20.7% (85) 19.9% 1,136 1,586 (2,535) (2,637) (4,177) (4,909) (5,167) (5,294) (5,469) (8,094) (8,858) (10,813) (12,247) (13,079) (15,173) 21.5% 20.7% 25.7% 27.5% 27.5% 26.6% 26.3% 26.1% 25.9% 23.5% 22.8% 20.7% 19.4% 18.8% 16.9% Note: Fields in grey are potected as Confidential under CPUC Confidentiality Rules Note: Values are shown in GWhs Notes: 1 Bundled retail sales forecast for 2014‐2018 and 2025‐2030 is from SCE's bundled retail sales forecast; bundled retail sales forecast for 2019‐2024 is forcast that will be used in 2014 LTPP 2 Includes all contracts executed through 7/31/14; new generation forecast based on individual project specific success rates for large near‐term projects and flat average success rate for remaining projects based on these projects' overall weighted average success rate 3 Forecast of deliveries by portfolio content categories is for executed contracts only; does not include program generics Physical Renewable Net Short Calculations Based on SCE Assumptions Deficit from RPS Variable Calculation Item prior to 2011 2012 2013 Reporting Year Actuals Actuals Actuals Forecast Year 2011-2013 CP1 2014 2015 2016 Forecast Forecast Forecast 1 2 3 21.7% 23.3% 25.0% 2014-2016 CP2 2017 2018 2019 2020 Forecast Forecast Forecast Forecast 4 5 6 7 2017-2020 CP3 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast Forecast 8 9 10 11 12 13 14 15 16 17 18 19 20 33.0% 33.0% 33.0% Annual RPS Requirement A SCE Bundled Sales Forecast1 B RPS Procurement Quantity Requirement (%) C A*B D Gross RPS Procurement Quantity Requirement (GWh) Voluntary Margin of Over-procurement E C+D Net RPS Procurement Need (GWh) 73,777 20.0% 14,755 75,597 20.0% 15,119 74,480 223,854 20.0% 14,896 75,747 27.0% 44,771 - - - - 14,755 15,119 14,896 44,771 29.0% 21,967 - - - - - 76,613 31.0% 23,750 77,673 78,782 33.0% 33.0% 25,632 - - - 21,967 23,750 25,632 25,998 - 80,115 33.0% 26,438 81,663 33.0% 26,949 83,350 33.0% 27,505 84,909 33.0% 28,020 86,495 33.0% 28,543 88,203 33.0% 29,107 90,012 33.0% 29,704 91,941 33.0% 30,340 94,003 33.0% 31,021 - - - - - - - - - - 25,998 26,438 26,949 27,505 28,020 28,543 29,107 29,704 30,340 31,021 9,034 RPS-Eligible Procurement Fa Risk-Adjusted RECs from Online Generation 15,654 15,821 16,479 47,953 16,867 16,677 15,892 49,436 15,045 14,688 14,651 13,816 58,200 13,187 13,107 13,109 13,016 12,975 12,779 11,412 10,581 10,425 Faa Forecast Failure Rate for Online Generation (%) 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Fb Risk-Adjusted RECs from RPS Facilities in Development - - 56 56 1,058 2,293 3,364 6,715 3,802 3,839 5,083 6,065 18,790 6,142 6,117 6,093 6,083 6,044 5,999 5,976 5,966 5,929 5,906 Fbb Forecast Failure Rate for RPS Facilities in Development (%) N/A N/A 0.0% 0.0% 6.0% 22.1% 31.3% 25.1% 32.6% 32.4% 35.5% 38.4% 35.3% 38.7% 38.7% 38.8% 38.8% 38.8% 38.8% 38.8% 38.9% 38.9% 38.9% Fc Pre-Approved Generic RECs - - - - - 37 145 182 809 904 907 910 3,529 907 907 907 910 907 907 907 910 907 907 Fe Executed REC Sales 362 778 473 1,614 - - - - - - - - - - - - - - - - - - - 15,291 15,043 16,062 46,396 17,926 19,006 19,401 56,333 19,656 19,431 20,640 20,791 80,519 20,235 20,131 20,109 20,009 19,926 19,685 18,294 17,457 17,262 15,848 2 Fa+Fb+Fc-Fe Total RPS Eligible Procurement (GW F F0 Category 0 RECs 3 15,239 14,912 15,822 45,973 16,887 16,752 15,820 49,460 13,929 12,724 12,527 11,686 50,865 11,055 10,969 10,967 10,870 10,839 10,638 10,420 10,399 10,237 8,841 F1 Category 1 RECs 3 52 131 240 423 1,038 2,217 3,436 6,692 4,918 5,804 7,207 8,196 26,124 8,273 8,255 8,236 8,229 8,180 8,140 6,967 6,148 6,117 6,100 F2 Category 2 RECs 3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1,166 1,625 (2,535) (3,109) (4,841) (5,763) (6,307) (6,839) (7,497) (8,094) (8,858) (10,813) (12,247) (13,079) (15,173) 21.6% 20.7% 25.7% 26.9% 26.8% 25.7% 25.1% 24.6% 24.0% 23.5% 22.8% 20.7% 19.4% 18.8% 16.9% Category 3 RECs F3 Gross RPS Position (Physical Net Short) Ga F-E Annual Gross RPS Position (GWh) Gb F/A Annual Gross RPS Position (%) 536 20.7% (76) 19.9% Application of Bank Ha Existing Banked RECs above the PQR Hb RECs above the PQR added to Bank 536 Hc Non-bankable RECs above the PQR - Gross Balance of RECs above the PQR Ia Planned Application of RECs above the PQR towards RPS Comp Ib Planned Sales of RECs above the PQR 0 0 0 Net Balance of RECs above the PQR 536 451 1,586 H Ha+Hb J H-Ia-Ib 3 J0 Category 0 RECs J1 Category 1 RECs 3 J2 Category 2 RECs 3 0 451 0 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 1,136 1,586 - - - - - - - - - - - - - 9 30 39 - - - - - - - - - - - - - 536 451 1,586 1,586 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 - - - - - - - - - - - - - - - 1,164 536 (85) - - 1,586 - 1,586 0 0 0 - 0 - 0 0 0 1,586 5,709 5,709 - 0 0 0 0 0 0 0 0 0 0 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 5,709 - - 1,164 - - - - - - - - - - - - - 52 131 240 423 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 6,903 8,050 8,922 9,511 9,824 9,921 10,078 10,071 10,309 10,518 10,574 10,686 11,279 Expiring Contracts K 2,029 RECs from Expiring RPS Contracts 2,524 3,627 8,181 5,589 29,464 Net RPS Position (Optimized Net Short) La Ga+Ia-Ib-Hc Annual Net RPS Position after Bank Optimization (GWh) Lb (Ga+Ia-Ib-Hc)/ Annual Net RPS Position after Bank Optimization (%) 536 20.7% (85) 19.9% 1,136 1,586 (2,535) (3,109) (4,841) (5,763) (6,307) (6,839) (7,497) (8,094) (8,858) (10,813) (12,247) (13,079) (15,173) 21.5% 20.7% 25.7% 26.9% 26.8% 25.7% 25.1% 24.6% 24.0% 23.5% 22.8% 20.7% 19.4% 18.8% 16.9% Note: Fields in grey are potected as Confidential under CPUC Confidentiality Rules Note: Values are shown in GWhs Notes: 1 Based on SCE's March 2013 bundled retail sales forecast 2 Includes all contracts executed through 7/31/14; new generation forecast based on individual project specific success rates for large near‐term projects and flat average success rate for remaining projects based on these projects' overall weighted average success rate 3 Forecast of deliveries by portfolio content categories is for executed contracts only; does not include program generics Appendix H Confidentiality Declaration Appendix I Proposed Protective Order BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Submission of Contracts for Procurement of Renewable Energy From SCE’s 2013 Renewables Portfolio Standard Solicitation ) ) ) Advice 3121-E PROPOSED PROTECTIVE ORDER 1. Scope. This Protective Order shall govern access to and the use of Protected Materials, produced by, or on behalf of, any Disclosing Party (as defined in Paragraph 2 below) in this proceeding. 2. Definitions. In addition to the terms defined and capitalized in other sections of this Protective Order, the following terms are defined for the purposes of this Protective Order: A. For purposes of this Protective Order, the term “Protected Materials” means: (i) trade secret, market sensitive, or other confidential and/or proprietary information as determined by the Disclosing Party in accordance with the provisions of Decision (“D.”) 06-06066 and subsequent decisions, General Order 66-C, Public Utilities Code section 454.5(g), or any other right of confidentiality provided by law; or (ii) any other materials that are made subject to this Protective Order by the Assigned Administrative Law Judge (“Assigned ALJ”), Law and Motion Administrative Law Judge (“Law and Motion ALJ”), Assigned Commissioner, the California Public Utilities Commission (“Commission”), or any court or other body having appropriate authority. Protected Materials also include memoranda, handwritten notes, spreadsheets, computer files and reports, and any other form of information (including information in electronic form) that copies, discloses, incorporates, includes or compiles other Protected Materials or from which such materials may be derived (except that any derivative 1 materials must be separately shown to be confidential). Protected Materials do not include: (i) any information or document contained in the public files of the Commission or any other state or federal agency, or in any state or federal court; or (ii) any information that is public knowledge, or which becomes public knowledge, other than through disclosure in violation of this Protective Order or any other nondisclosure agreement or protective order. B. The term “redacted” refers to situations in which Protected Material in a document, whether the document is in paper or electronic form, have been covered, blocked out, or removed. C. The term “Disclosing Party” means a party who initially discloses any specified Protected Material in this proceeding. D. The term “Requesting Party” means any party that is requesting receipt of Protected Material from a Disclosing Party. E. The term “Party” refers to the Requesting Party or the Disclosing Party and the term “Parties” refers to both the Requesting Party and the Disclosing Party. F. The term “Market Participant” refers to a Requesting Party that is: 1) A person or entity, or an employee of an entity, that engages in the wholesale purchase, sale or marketing of energy or capacity, or the bidding on or purchasing of power plants, or bidding on utility procurement solicitations, or consulting on such matters, subject to the limitations in 3) below. 2) A trade association or similar organization, or an employee of such organization, a) whose primary focus in proceedings at the Commission is to advocate for persons/entities that purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations; or b) a majority of whose members purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations; or 2 3) G. c) formed for the purpose of obtaining Protected Materials; or d) controlled or primarily funded by a person or entity whose primary purpose is to purchase, sell or market energy or capacity at wholesale; bid on, own, or purchase power plants; or bid on utility procurement solicitations. A person or entity that meets the criteria of 1) above is not a Market Participant for purpose of access to Protected Materials unless the person/entity seeking access to Protected Materials has the potential to materially affect the price paid or received for electricity if in possession of such information. An entity will be considered not to have such potential if: a) the person or entity’s participation in the California electricity market is de minimis in nature. In the resource adequacy proceeding (R.05-12-013) it was determined in D.06-06-064 § 3.3.2 that the resource adequacy requirement should be rounded to the nearest megawatt (MW), and load serving entities (LSEs) with local resource adequacy requirements less than 1 MW are not required to make a showing. Therefore, a de minimis amount of energy would be less than 1 MW of capacity per year, and/or an equivalent of energy; and/or b) the person or entity has no ability to dictate the price of electricity it purchases or sells because such price is set by a process over which the person or entity has no control, i.e., where the prices for power put to the grid are completely overseen by the Commission, such as subject to a standard offer contract or tariff price. A person or entity that currently has no ability to dictate the price of electricity it purchases or sells under this section, but that will have such ability within one year because its contract is expiring or other circumstances are changing, does not meet this exception; and/or c) the person or entity is a cogenerator that consumes all the power it generates in its own industrial and commercial processes, if it can establish a legitimate need for Protected Materials. The term “Non-Market Participant” refers to a Requesting Party that does not meet the definition of Market Participant. H. “Reviewing Representatives” are limited to person(s) designated in accordance with Paragraph 5 who meet the following criteria: 3 I. 1) Reviewing Representatives may not currently be engaged in: (a) a transaction for the purchase, sale, or marketing at wholesale of electrical energy or capacity or natural gas (or the direct supervision of any employee(s) engagement in such a transaction); (b) the bidding on or purchasing of power plants (or the direct supervision of any employee(s) engagement in such a transaction); or (c) knowingly providing electricity or gas marketing consulting or advisory services to others in connection with a transaction for the purchase, sale, or marketing at wholesale of electrical energy or capacity or natural gas or the bidding on or purchasing of power plants (or the direct supervision of any employee(s) engagement in such a transaction or consulting). 2) Reviewing Representatives may not be an employee of a Market Participant. If the Market Participant or Non-Market Participant chooses to retain outside attorneys, consultants, or experts in the same law firm or consulting firm to provide advice in connection with marketing activities, then the attorney, consultant, or expert serving as a Reviewing Representative must be separated by an ethics wall consistent with the ethics wall requirements in D.11-07-028, as that decision may be subsequently modified or changed by the Commission, from those in the firm who are involved in wholesale commercial dealings. 3) Reviewing Representatives shall use Protected Materials only for the purpose of participating in the Commission proceeding in which they received the information. 4) Reviewing Representatives are permitted to participate in regulatory proceedings on behalf of Market Participants and Non-Market Participants. 5) All Reviewing Representatives are required to execute the Nondisclosure Certificate attached to this Protective Order and are bound by the terms of this Protective Order. The term “Authorized Reviewers” refers to: (1) a Requesting Party that is a Non-Market Participant; or (2) a Reviewing Representative of a Requesting Party. A Requesting Party that is a Market Participant is not an Authorized Reviewer but it may designate a Reviewing Representative in accordance with Paragraph 5. J. The term “Nondisclosure Certificate” refers to the Nondisclosure Certificate attached as Appendix A. 4 3. Designation, Filing, and Service of Protected Materials. When filing or providing in discovery any documents or items containing Protected Materials, a party shall physically mark such documents (or in the case of non-documentary materials such as computer diskettes, on each item) as “PROTECTED MATERIALS SUBJECT TO PROTECTIVE ORDER,” or with words of similar import as long as one or more of the terms “Protected Materials” or “Protective Order” is included in the designation to indicate that the materials in question are Protected Materials. All materials so designated shall be treated as Protected Materials unless and until: (a) the designation is withdrawn pursuant to Paragraph 14 hereof; (b) an Assigned ALJ, Law and Motion ALJ, Assigned Commissioner, or the Commission makes a determination that: (i) the document does not contain Protected Materials or does not warrant confidential treatment or (ii) denies a motion to file the document under seal; or (c) the document or information becomes public knowledge, other than through disclosure in violation of this Protective Order or any other nondisclosure agreement or protective order. All documents containing Protected Materials that are tendered for filing with the Commission shall be placed in sealed envelopes or otherwise appropriately protected and shall be tendered with a motion to file the document under seal pursuant to Rule 11.4 of the Commission’s Rules of Practice and Procedure. All documents containing Protected Materials that are served on parties in a proceeding shall be placed in sealed envelopes or otherwise appropriately protected and shall be endorsed to the effect that they are served under seal pursuant to this Protective Order. Such documents shall only be served upon Authorized Reviewers and persons employed by or working on behalf of the Commission. Service upon Authorized Reviewers and persons employed by or working on behalf of the Commission may either be: (a) by electronic mail in accordance with the procedures adopted in this proceeding; (b) by facsimile; or (c) by overnight mail or messenger service. Whenever service of a document 5 containing Protected Materials is made by overnight mail or messenger service, the Assigned ALJ shall be served with such document by the same means and at the same time. 4. Redaction of Documents. Whenever a Party files, serves or provides in discovery a document that includes Protected Materials (including but not limited to briefs, testimony, exhibits, and responses to data requests), such Party shall also prepare a redacted version of such document. The redacted version shall enable persons familiar with this proceeding to determine with reasonable certainty the nature of the data that has been redacted and where the redactions occurred. The redacted version of a document to be filed shall be served on all persons on the service list, and the redacted version of a discovery document shall be served on all persons entitled thereto. 5. Designation of Reviewing Representatives. The Requesting Party shall provide written notice identifying its proposed Reviewing Representative(s) to the Disclosing Party before the Disclosing Party provides any Protected Materials to the Requesting Party’s Authorized Reviewers. The written notice shall include the information identified in this paragraph. If the Requesting Party decides to designate any additional Reviewing Representative(s) after the Requesting Party’s Authorized Reviewers receive Protected Materials, the Requesting Party shall identify the additional proposed Reviewing Representative(s) to the Disclosing Party before the Requesting Party provides Protected Materials to the additional Reviewing Representative(s). Within five (5) business days after receiving written notice of the identity of any Reviewing Representative, the Disclosing Party may provide the Requesting Party with a written objection to a specific Reviewing Representative stating the grounds for the objection. Any dispute concerning whether an identified person or entity is an appropriate Reviewing Representative shall be resolved through the dispute resolution procedures in Paragraph 11 of this Protective Order. If a Disclosing Party 6 objects to a specific Reviewing Representative within five (5) business days after the Reviewing Representative is identified, the Parties shall not provide any Protected Materials to the disputed Reviewing Representative until the Parties are able to resolve the dispute consistent with the dispute resolution procedures in Paragraph 11. Failure by the Disclosing Party to object within five (5) business days does not waive the Disclosing Party’s right to later object to the Reviewing Representative, even if Protected Materials has already been disclosed. However, further disclosure of Protected Materials would be stayed until the parties are able to resolve the dispute consistent with the dispute resolution procedures in Paragraph 11. Reviewing Representative(s) have a duty to disclose to the Disclosing Party any potential conflict of interest that puts the Reviewing Representative in violation of D.06-12-030, as modified by subsequent decisions of the Commission. A resume or curriculum vitae is reasonable disclosure of such potential conflicts, and should be the default evidence provided in most cases. 6. Nondisclosure Certificates. A Reviewing Representative shall not inspect, participate in discussions regarding, or otherwise be granted access to, Protected Materials unless and until he or she has first completed and executed a Nondisclosure Certificate, attached hereto as Appendix A, and delivered the signed Nondisclosure Certificate to the Disclosing Party. The Disclosing Party shall retain the executed Nondisclosure Certificates pertaining to the Protected Materials it has disclosed and shall promptly provide copies of the Nondisclosure Certificates to Commission Staff upon request. 7. Access to Protected Materials and Use of Protected Materials. Subject to the terms of this Protective Order, Authorized Reviewers shall be entitled to access any Protected Materials and may make copies of Protected Materials, but such copies become Protected Materials. Authorized Reviewers may make notes of Protected Materials, which shall be treated 7 as Protected Materials if such notes disclose any Protected Materials. Protected Materials obtained by a Party in this proceeding may also be requested by that Party in a subsequent Commission proceeding, subject to the terms of any nondisclosure agreement or protective order governing that subsequent proceeding, without constituting a violation of this Protective Order. 8. Maintaining Confidentiality of Protected Materials. Each Authorized Reviewer shall treat Protected Materials as confidential in accordance with this Protective Order and the Nondisclosure Certificate. Protected Materials shall not be used except as necessary for participation in this proceeding, and shall not be disclosed in any manner to any person except: (i) Authorized Reviewers; (ii) an Authorized Reviewer’s employees and administrative personnel, such as clerks, secretaries, and word processors, to the extent necessary to assist the Authorized Reviewer, provided that they shall first ensure that such personnel are familiar with the terms of this Protective Order and have signed a Nondisclosure Certificate; and (iii) persons employed by or working on behalf of the Commission. Authorized Reviewers shall adopt suitable measures to maintain the confidentiality of Protected Materials they have obtained pursuant to this Protective Order, and shall treat such Protected Materials in the same manner as they treat their own most highly confidential information. Authorized Reviewers shall be liable for any unauthorized disclosure or use by themselves and/or employees, paralegals, or administrative staff. In the event any Authorized Reviewer is requested or required by applicable laws or regulations, or in the course of administrative or judicial proceedings (in response to oral questions, interrogatories, requests for information or documents, subpoena, civil investigative demand or similar process) to disclose any of Protected Materials, the Authorized Reviewer shall immediately inform the Disclosing Party of the request, and the Disclosing Party may, at its sole discretion and cost, direct any challenge or defense against the disclosure requirement, and the Authorized Reviewer shall 8 cooperate in good faith with such Party either to oppose the disclosure of the Protected Materials consistent with applicable law, or to obtain confidential treatment of the Protected Materials by the person or entity who wishes to receive them prior to any such disclosure. If there are multiple requests for substantially similar Protected Materials in the same case or proceeding where an Authorized Reviewer has been ordered to produce certain specific Protected Materials, the Authorized Reviewer may, upon request for substantially similar materials by another person or entity, respond in a manner consistent with that order to those substantially similar requests. 9. Return or Destruction of Protected Materials. Protected Materials shall remain available to Authorized Reviewers until an order terminating this proceeding becomes no longer subject to judicial review. If requested to do so in writing after that date, the Authorized Reviewers shall, within fifteen days after such request, return the Protected Materials to the Disclosing Party that produced such Protected Materials, or shall destroy the materials, except that copies of filings, official transcripts and exhibits in this proceeding that contain Protected Materials, and notes of Protected Materials may be retained, if such Protected Materials are maintained in accordance with Paragraph 8. Within such time period each Authorized Reviewer, if requested to do so, shall also submit to the Disclosing Party an affidavit stating that, to the best of its knowledge, all Protected Materials have been returned or have been destroyed or will be maintained in accordance with Paragraph 8. To the extent Protected Materials are not returned or destroyed, they shall remain subject to this Protective Order. In the event that a Reviewing Representative to whom Protected Materials are disclosed ceases to be engaged to provide services in this proceeding, then access to such materials by that person shall be terminated and the Reviewing Representative shall immediately return or destroy all Protected Materials, or provide an affidavit stating that all Protected Materials and all notes of Protected Materials will be maintained in accordance with Paragraph 8. Even if a Reviewing 9 Representative is no longer engaged in this proceeding, every such person shall continue to be bound by the provisions of this Protective Order and the Nondisclosure Certificate. 10. Access and Use by Governmental Entities. A. In the event the Commission receives a request from the California Energy Commission (“CEC”) for a copy of or access to any Party’s Protected Materials, the procedure for handling such requests shall be as follows. Not less than five (5) business days after delivering written notice to the Disclosing Party of the request, the Commission shall release such Protected Materials to the CEC upon receipt from the CEC of an Interagency Information Request and Confidentiality Agreement (“Interagency Confidentiality Agreement”). Such Interagency Confidentiality Agreement shall: (i) provide that the CEC will treat the requested Protected Materials as confidential in accordance with this Protective Order; (ii) include an explanation of the purpose for the CEC’s request, as well as an explanation of how the request relates to furtherance of the CEC’s functions; (iii) be signed by a person authorized to bind the CEC contractually; and (iv) expressly state that furnishing of the requested Protected Materials to employees or representatives of the CEC does not, by itself, make such Protected Materials public. In addition, the Interagency Confidentiality Agreement shall include an express acknowledgment of the Commission’s sole authority (subject to judicial review) to make the determination whether the Protected Materials should remain confidential or be disclosed to the public, notwithstanding any provision to the contrary in the statutes or regulations applicable to the CEC. B. In the event the Commission receives a request for a copy of or access to a party’s Protected Materials from a state governmental agency other than the CEC that is authorized to enter into a written agreement sufficient to satisfy the requirements for maintaining confidentiality set forth in Government Code Section 6254.5(e), the Commission may, not less 10 than five (5) business days after giving written notice to the Disclosing Party of the request, release such Protected Materials to the requesting governmental agency, upon receiving from the requesting agency an executed Interagency Confidentiality Agreement that contains the same provisions described in Paragraph 10.A above. C. The CEC may use Protected Materials when needed to fulfill its statutory responsibilities or cooperative agreements with the Commission. Commission confidentiality designations will be maintained by the CEC in making such assessments, and the CEC will not publish any assessment that directly reveals the data or allows the data submitted by an individual load serving entity to be “reverse engineered.” 11. Dispute Resolution. All disputes that arise under this Protective Order, including but not limited to alleged violations of this Protective Order and disputes concerning whether materials were properly designated as Protected Materials, shall first be addressed by the parties through a meet and confer process in an attempt to resolve such disputes. If the meet and confer process is unsuccessful, either party may present the dispute for resolution to the Assigned ALJ or the Law and Motion ALJ. 12. Other Objections to Use or Disclosure. Nothing in this Protective Order shall be construed as limiting the right of a Party, the Commission Staff, or a state governmental agency covered by Paragraph 10 to object to the use or disclosure of Protected Materials on any legal ground, including relevance or privilege. 13. Remedies. Any violation of this Protective Order shall constitute a violation of an order of the Commission. Notwithstanding the foregoing, the parties and Commission Staff reserve their rights to pursue any legal or equitable remedies that may be available in the event of an actual or anticipated disclosure of Protected Materials. 11 14. Withdrawal of Designation. A Disclosing Party may agree at any time to remove the “Protected Materials” designation from any materials of such Party if, in its opinion, confidentiality protection is no longer required. In such a case, the Disclosing Party will notify all Requesting Parties that the Disclosing Party has agreed to withdraw its designation of Protected Materials for specific documents or material. 15. Modification. This Protective Order shall remain in effect unless and until it is modified or terminated by the Commission or the Assigned ALJ. The identity of the parties submitting Protected Materials may differ from time to time. In light of this situation, modifications to this Protective Order may become necessary. The Parties shall work cooperatively to develop such modifications and, to the extent the Parties are able to agree to modifications, shall file a motion with the Assigned ALJ or the Commission seeking approval of the modifications. To the extent Parties are unable to agree on modifications after a good faith effort, each party governed by this Protective Order has the right to seek modifications in it as appropriate from the Assigned ALJ or the Commission. 16. Interpretation. Headings are for convenience only and may not be used to restrict the scope of this Protective Order. Entered: __________________________________ Administrative Law Judge Date: __________________________________ 12 APPENDIX A TO PROPOSED PROTECTIVE ORDER BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Submission of Contracts for Procurement of Renewable Energy From SCE’s 2013 Renewables Portfolio Standard Solicitation ) ) ) Advice 3121-E NON-DISCLOSURE CERTIFICATE I hereby certify my understanding that access to Protected Materials is provided to me pursuant to the terms and restrictions of the Protective Order in this proceeding, that I have been given a copy of and have read the Protective Order, and that I agree to be bound by it. I understand that the contents of the Protected Materials, any notes or other memoranda, or any other form of information that copies or discloses Protected Materials shall not be disclosed to anyone other than in accordance with that Protective Order. I acknowledge that a violation of this certificate constitutes a violation of an order of California Public Utilities Commission. Signed: _______________________ Name ________________________ Title: _________________________ Organization: __________________ Dated: ________________________