Harney County Court Request for Proposal Harney County Jail HVAC System Upgrades Issue Date: December 11, 2013 Pre-Bid Conference Date: December 17, 2013, 2 p.m. Harney County Courthouse 450 North Buena Vista Burns, Oregon 97720 Bid Due Date: To Be Determined after Pre-Bid Conference REQUEST FOR PROPOSAL Notice is hereby given that proposals will be received by Harney County Court, Burns, Oregon for: Replacing, repairing and maintaining heating, ventilating and cooling equipment in the Harney County Jail building. The project shall be structured as design/build. The successful contractor will retain the services of professional engineers as necessary or if deemed required by Harney County. Memorandum To: Bidding Contractors C: Judge Steven E. Grasty, Harney County Court From: Anthony J. Dickman, P.E. Date: 12/11/2013 Re: Harney County Jail – HVAC System Upgrades Objective The objective of this project is to replace, repair and maintain heating, ventilating and cooling equipment in the Harney County Jail building, located in Burns, Oregon. The project shall be structured as design/build. The successful contractor will retain the services of professional engineers as necessary or if deemed required by the Owner (Harney County). Description The jail facilities are heated using forced air supplied by small air handlers in various zones throughout the facility. Heating water coils are installed in the ducting directly downstream of the air handlers. An oil-fired boiler and pump located on the premises provide the heating water supply and return flow through the coils. Fresh air intake grilles are located on outside walls and the balance between fresh air and return air is controlled using dampers mounted within the return ducting system. The dampers are presently not clearly marked and possibly need to be replaced or repaired. The existing system utilizes a rooftop-mounted evaporative (swamp) cooler to provide nominal cooling in summer. Although the cooler provides some relief from the heat, the additional humidity makes the building uncomfortable during the warmer days. 1 Harney County Jail – HVAC System Upgrades Bidding Memorandum Project Requirements Bidding Specifications and Other Requirements All work for this project shall be accomplished in accordance with the accompanying specifications: • 15200 – Basic Mechanical Requirements • 15220 – HVAC System Requirements In addition to these specifications, all work shall meet the requirements of local, state and federal codes, including (but not limited to): • Oregon Mechanical Specialty Code – 2007 • ASHRAE Standard 62-2001 Ventilation for Acceptable Indoor Air Quality Potential Contractors shall be required to attend one (1) on-site pre-bid meeting to inspect the existing facilities and systems and review the project requirements with the Owner and Owner’s Representative. Heating System Heating water coils for the various air handlers are to be inspected, cleaned and repaired (if necessary). An inspection of the hydronic system (heating water supply and return) shall also be required to insure that all critical components are present and operating. Based upon an initial inspection, it appears that the system does not include an air separator in the heating water loop. If the air separator is indeed missing, the installation of a new separator shall be included within the scope of this project. Likewise, if insufficient drains and/or air vents are not included in the piping system, required drains and vents shall be installed as part of this project. Cooling System The existing evaporative cooler shall be removed and disposed of properly by the successful Contractor. It shall be replaced by a rooftop unitary heat pump system. The heat pump shall be used primarily for cooling in summer, but may be called upon to provide supplemental heat in winter. For this reason, the heat pump shall include electric resistance heating elements as required to meet the demands of the Burns winter climate. Contractor shall supply a unit equivalent to the Trane “Precedent” system. A brochure for the unit is attached to this memo for reference purposes. Ventilation System Contractor shall be responsible for ensuring that existing dampers are functioning properly. Damaged or otherwise non-functioning dampers shall be replaced as required. Upon completion of the equipment installation and 2 Harney County Jail – HVAC System Upgrades Bidding Memorandum repairs, the air system shall be balanced to ensure proper air flow (supply and return) through the various zones serviced by the individual air handling system. In order to ensure proper ventilation, it may be necessary to include new ducting for return and/or outside air flow. Project Bidding and Schedule The objective is to complete the project before June 2014, sooner if possible. Bidding requirements shall be as defined in the pre-bid meeting, scheduled for Tuesday 17 December in the Harney County Courthouse located in Burns, Oregon. 3 BASIC MECHANICAL REQUIREMENTS SECTION 15200 1 GENERAL 1.1 WORK INCLUDED A. 1.2 This Section specifies the basic requirements for all Contractor-supplied and -installed HVAC systems and equipment. It applies to all sections included in Division 15. RELATED SECTIONS A. This general section shall be used in conjunction with the following other specifications and accompanying document to establish the total requirements for the project equipment and systems: 1. 1.3 DESIGN REQUIREMENTS A. 1.4 Section 15220 – HVAC System Requirements. Compliance by the Contractor and/or Vendor(s) with the provisions of this Specification does not relieve him of the responsibilities of furnishing equipment and materials of proper design, mechanically suited to meet operating guarantees at the specified service conditions. SUBMITTALS A. Bid Information: 1. An individual price and delivery schedule must be quoted for each equipment number. 2. The length of time required for certification of all information, drawings, etc. 3. Estimated equipment weight and support requirements. 4. Electrical power requirements. 5. Utility (cooling water, air, fuel, etc.) requirements. 6. Time and costs required for manufacturer’s startup services as indicated in individual equipment sections. 7. When a data sheet is provided which has blanks for input of information from the bidders, the completed data sheet shall be included with the bid. Harney County Jail Burns, Oregon HVAC System Upgrades Page 1 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 B. Drawings and data within two (2) weeks of award of Contract: Composite outline drawings including the following are required: 1. 1.5 1.6 Certified correct dimensional drawings of completed assembled units, which shall show: a. Identification data for equipment components. b. Rotation. c. Weight. d. Adequate dimensional data, including locations and sizes of seismic restraints, to permit the design of foundation, piping and wiring connections. e. Location of motor junction box(es). f. Piping connections identified with the size, rating, and facing indicated. g. Clearance required for disassembly and maintenance. h. Three (3) copies of operating and maintenance manuals. REGULATORY REQUIREMENTS A. Conformance to the latest Codes and other regulatory requirements is the responsibility of the Contractor and the Vendor(s). B. The Contractor and the Vendor(s) shall obtain all permits and arrange all inspections required by codes applicable to this Section and shall submit written evidence to Owner that required permits, inspections, and code requirements have been secured. DELIVERY, STORAGE AND HANDLING A. Packing and Shipping: 1. Harney County Jail Burns, Oregon HVAC System Upgrades Each unit shall be suitably prepared for the shipment specified and for storage in accordance with manufacturer’s instructions in a manner requiring no disassembly prior to operation. Page 2 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 2. The Contractor shall be solely responsible for the adequacy of the preparation for shipment provisions employed with respect to materials and application. 3. Equipment shall be completely free of water prior to any shipment preparation. 4. Bearings, bearing housings, and oil systems, including reservoirs, coolers, filters, and piping, shall be thoroughly cleaned internally of metal particles, dirt and debris, and coated with a suitable rust preventative prior to shipment. 5. Adequate protection shall be provided against mechanical damage and atmospheric corrosion in transit. 6. Instruments and valves, including auxiliary systems, must be securely mounted and/or supported to eliminate damage during shipment, storage, operation, and maintenance. 7. Supports and rigging connections shall be provided to prevent damage during transit, lifting or unloading. 8. Threaded connections shall be provided with a pipe plug of the same material as the connections (except cast iron connections shall have steel plugs). Plugs shall have a square or hex head. Teflon tape shall be used as a thread sealant. 9. Those openings that require rust preventative shall be suitably tagged to indicate the type and nomenclature of the rust preventative used. 10. Equipment containing insulating oils or other fluids shall be suitably tagged at openings to indicate the nature of the contents, and shipping and storage precautions. 11. Open ends of tubes and pipe shall be capped (just taping is not adequate) for protection. 12. Equipment and components shall be packed, securely anchored (skid mounted when required) and weather protected for the shipment method called for in the Purchase Order. Separate, loose, or spare parts shall be boxed and each part individually protected as required. Each individual container shall be marked Harney County Jail Burns, Oregon HVAC System Upgrades Page 3 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 both inside and outside with the equipment or component number and service for which the parts are intended. 2 13. One (1) complete set of Installation, Operation and Maintenance Instructions shall be packed and shipped with the equipment or components. This set is in addition to the sets that are to be sent directly to the Owner. 14. Each container shall also include a complete Bill of Materials identifying each part. In some instances, such as instruments, specific tagging shall be required. PRODUCTS 2.1 2.2 GENERAL A. Equipment and components shall be the manufacturer’s most recent standard design. Equipment and component designs which have not been previously used successfully in an industrial application are not acceptable unless approved in writing by the Owner. B. Provide one quart of each standard paint used from each equipment and/or materials supplier for touch up. All paint cans are to be adequately labeled to identify where they are to be used. When equipment is involved, the label must at a minimum include Owner’s equipment tag number. C. All equipment over 100 pounds in weight shall be provided with lifting lugs of the manufacturer’s design for easy handling. EQUIPMENT IDENTIFICATION A. Equipment and components shall have an identification tag pinned or fastened in a readily accessible location with the following information at a minimum (when applicable). 1. Manufacturer’s name. 2. Manufacturer’s model number. 3. Date of manufacture. 4. Design operating conditions (where relevant). Harney County Jail Burns, Oregon HVAC System Upgrades Page 4 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 3 5. Design pressure and temperature (where relevant). 6. Serial number. 7. Materials of construction (major). 8. Code stamp (as required). 9. RPM (as required). 10. Electrical power requirements (as required). 11. Equipment name. 12. Equipment identification tag numbers. 13. Equipment capacity. 14. Equipment dimensions. EXECUTION 3.1 INSTALLATION A. Installation shall be in accordance with the requirements of the equipment or component manufacturer, including special requirements for seismic restraints. B. Equipment Manufacturer’s Responsibility and Services: 1. A manufacturer’s representative for major equipment and operating systems shall be provided as necessary to assist the Contractor during installation, and to provide written certification that the equipment has been installed as specified and in accordance with the manufacturer’s requirements. 2. The manufacturer’s representative shall provide the initial startup of equipment in the presence of Owner. Harney County Jail Burns, Oregon HVAC System Upgrades a. Provide a pre-start check of all piping, valves, control devices, control panels, and equipment. b. Calibrate and adjust equipment and controls for operation at the specified design conditions. Page 5 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 3.2 c. Provide a record of all startup events noting problems and their resolution. d. Provide a record of all setpoints for operational controls and devices. 3. Upon the completion of equipment startup, provide adequate instructional time with Owner’s personnel to review the operations and maintenance manuals and perform each step necessary for startup, shutdown, troubleshooting, and routine maintenance. The instructional time shall be scheduled through Owner. 4. Upon completion of the inspections, startup, testing, and checkout procedures, the equipment manufacturer shall submit written notice to Owner that the units are ready for use by Owner. Provide a certificate of calibration for all equipment. MOUNTING AND SHIMMING A. Provisions for mounting special equipment on spring isolators, snubbers and inertia bases shall be included as required by the Drawings. B. Mechanical Services Equipment: 1. Level the equipment by means of 304 stainless steel wedges (stainless steel plates and stainless steel shims) or PVC/poly wedges in areas of extreme corrosive environments. Wedge taper shall not be greater than 1/4 inch per foot. Use double wedges to provide a level bearing surface for the equipment. Secure each pair of wedges in their final positions with one tack weld on each side after leveling is complete. Wedging shall be executed in a manner that will prevent a change in level or springing of the baseplate when the anchor bolts are tightened. 2. Adjust rotating equipment assemblies such that the driving units are properly aligned, plumb and level with the driven units and all interconnecting shafts and couplings. 3. Rotating equipment shall be checked for proper alignment with dial indicators or laser after completion of grouting. The alignment must be within the tolerances required by the equipment manufacturer. Harney County Jail Burns, Oregon HVAC System Upgrades Page 6 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 C. 3.3 3.4 Grouting: For equipment requiring grouting, and after the equipment has been set in position, aligned, and shimmed to the proper elevations, grout the space between the bottom of the baseplate and the concrete foundation and/or inertia base with a poured non-shrinking grout. INSPECTION A. The Contractor shall inspect his work to ensure the installation and workmanship are in accordance with these specifications and acceptable industry standards for the work being done. B. Factory and/or field testing may include full and/or part load performance tests, basic mechanical spin tests, etc. It may also include various nondestructive tests as required by specified codes including those normally required by the manufacturer’s own manufacturing standards. C. It is a requirement of this Specification that Owner’s inspection work be minimized by assigning to the Contractor the responsibility of furnishing the inspector with all necessary material certifications, shop test data, radiographic plates and the like necessary to verify the Contractor’s compliance with the specifications for all Contractor-furnished equipment. D. Where shop inspection is specified, no surfaces or parts are to be painted until the inspection is complete. E. All materials, equipment, and workmanship shall be subject to inspection at any time by Owner. Contractor shall correct any work, materials, or equipment not in accordance with the Contract Documents. SAFETY CONSIDERATIONS A. All equipment shall be installed with suitable access clearances that satisfy OSHA and code requirements for maintenance or removal of replaceable parts and components, and with necessary unions or flanges to perform the maintenance or removal without removing the connecting appurtenances. B. Where equipment requiring periodic maintenance cannot be reached by normal walkways because of interference with ductwork, piping, or other obstructions the Contractor shall notify Owner and propose an alternate safe means of access. These may include construction of an overhead platform with stairway or ladder ends and safety railings or handholds, or Harney County Jail Burns, Oregon HVAC System Upgrades Page 7 of 8 Performance and Bidding Specifications BASIC MECHANICAL REQUIREMENTS SECTION 15200 walk-through duct plenums with hinged access doors, or as required to meet OSHA standards for safe maintenance procedures. 3.5 CLEANING, STARTUP, AND ADJUSTING A. The Contractor shall be responsible for proper operation of systems, minor subsystems, and services provided under this Section. It shall coordinate startup procedures, calibration, and system checkout with subcontractors involved. System operational problems shall be diagnosed; correctional procedures shall be initiated as required to bring the system into compliance with the design, and the problem then shall be re-checked to verify that the system operates normally. Remaining difficulties shall be brought to the attention of Owner. B. Thoroughly clean all parts of the installation at the completion of the work. Clean up and remove from the premises refuse material, crates, and rubbish arising from Work. END OF SECTION Harney County Jail Burns, Oregon HVAC System Upgrades Page 8 of 8 Performance and Bidding Specifications HVAC SYSTEM REQUIREMENTS SECTION 15220 1 GENERAL 1.1 WORK INCLUDED A. 1.2 FINISH AND PAINTING A. 1.3 2 Furnish and install complete heating, cooling and ventilating systems with all equipment, ductwork and controls. Repair, maintain and replace existing equipment that shall remain in the facility. Prime and paint all exposed ductwork as required by Owner. COORDINATION WITH ELECTRICAL CONTRACTOR A. This Contractor shall coordinate with the Electrical Contractor on controls, motors, starters etc. B. Responsibility for furnishing all controls, including thermostats, auxiliary switches, transformers and relays is included in these Heating, Cooling and Ventilating Specifications. C. Low-voltage wiring shall be furnished and installed by this Contractor. D. This Contractor shall review all wiring connections that have any influence on supplied equipment or work, and verify that these connections are correct before permitting any equipment that is furnished, installed or modified under this Contract to be operated. PRODUCTS 2.1 DUCTWORK A. Galvanized sheet steel of thickness recommended in Table 1-4 of the SMACNA HVAC Duct Construction Standards, 1985 edition, for 1" water gauge, 2500 ft/min velocity, except no duct shall be less than 24 gauge. Fabricate in accordance with SMACNA standards except where otherwise specified or indicated. B. Insulate concealed supply and return ductwork with Owens-Corning 11/2" Type 100 FRK, Schuller R-6 Microlite Type FSK, faced fiberglass ductwrap installed per manufacturer's application Specification, 1" approximate installed thickness. Rectangular ductwork may be lined with 1" thickness Owens-Corning Aeroflex, Schuller Linacoustic. Harney County Jail Burns, Oregon HVAC System Upgrades Page 1 of 4 Performance and Bidding Specifications HVAC SYSTEM REQUIREMENTS SECTION 15220 2.2 3 C. Flexible duct connectors at equipment shall be UL listed. D. Fabricate all ductwork in accordance with SMACNA duct manuals and ASHRAE handbook. HEATING AND VENTILATING EQUIPMENT A. See accompanying documents. B. Brand and model shown in accompanying documents are meant to establish quality and equipment type only. Proposed substitutes shall be equal to those indicated in documents. C. Furnish and install all equipment in accordance with accompanying documents, manufacturer's recommendations and all applicable codes. EXECUTION 3.1 3.2 DUCTWORK - HVAC A. All ductwork of sheetmetal shall be in accordance with the applicable SMACNA Manual unless otherwise specified, airtight and supported as recommended. Ductwork shall run concealed unless otherwise noted. B. All ducts shall be supported as recommended by SMACNA. C. There shall be no ducts exposed to weather. D. Any exposed ductwork in conditioned space shall not be insulated. Fresh air and exhaust ducts shall not be insulated. E. Provide volume control extractors or dampers at each branch take-off from main ducts F. No "grey" duct tape shall be used. Metal duct sealing shall be "hard cast" or SMACNA approved foil-backed pressure-sensitive tape. G. Flexible ductwork shall be installed with no runs more than 5'-0" and no more than three (3) bends of 45° maximum each. Flexible ductwork shall be used only at register connections. AIR BALANCE A. The complete air system shall be tested and balanced by competent personnel. Harney County Jail Burns, Oregon HVAC System Upgrades Page 2 of 4 Performance and Bidding Specifications HVAC SYSTEM REQUIREMENTS SECTION 15220 3.3 B. Adjust all air flows to be within ±10% of nomingal. All dampers shall be locked in position and indelibly marked. C. Prove the correct operation of all controls, dampers, heating or ventilating stages, timers, and thermostats. Balance Report shall address the operation of controls. D. The Installing Contractor shall provide labor and materials as required to perform the air balance. This Contractor shall allow for a sheave and belt change on each fan, without additional expense to Owner. E. At the completion of the balancing operation, provide the Owner with a minimum of three (3) copies of the air balance data. Provide data showing: Required CFM and actual measured CFM for each outlet, return, exhaust grille, register, and each zone. 2. Static pressure across fans. 3. Current draw of all motors with nameplate data. 4. Instruments and date of calibration. 5. Room temperature after balance and control set point. Provide date and ambient conditions when readings are taken. 6. Temperature rise across heating water coils under heating conditions. CONTROLS A. 3.4 1. A complete system shall be provided. System shall include all components required to provide temperature control in each zone. System shall provide correct operation of all equipment. Temperature control for electric heat shall be by Electrical Contractor. INSTRUCTION BOOK A. The Contractor shall provide the Owner with three (3) copies of complete written instructions in the operation of the various systems. The instructions shall be bound in booklet form and shall include pertinent maintenance information of the equipment with names of local suppliers and agents. The instructions shall reference all equipment numbers. The Harney County Jail Burns, Oregon HVAC System Upgrades Page 3 of 4 Performance and Bidding Specifications HVAC SYSTEM REQUIREMENTS SECTION 15220 Contractor shall also instruct the Owner or his/her representatives in the operation of the systems. END OF SECTION Harney County Jail Burns, Oregon HVAC System Upgrades Page 4 of 4 Performance and Bidding Specifications Trane® Precedent ™ 3- to 10-ton light commercial rooftop units The right size for high comfort. The lowest installed cost and lowest total Most Trane Precedent rooftop units can be ready in as few as two weeks—the fastest delivery time in the industry—so your project doesn’t get delayed while waiting for equipment. When it comes to HVAC expenses, every dollar counts. From your initial investment to monthly utility costs and maintenance, a light-commercial rooftop unit can have a significant impact on your bottom line—which is why a Trane® Precedent™ lightcommercial rooftop unit can be the perfect choice. No competing light-commercial rooftop unit has a lower installed cost than the Trane Precedent—and with its industry-leading efficiency and low maintenance requirements, no other unit has a lower total cost of ownership. And once you’ve made the wise decision that a Trane Precedent lightcommercial rooftop unit is the right solution for your building, it’s good to know that no other light-commercial rooftop unit can be delivered as quickly as the Trane Precedent, with most units ready in as few as two weeks—order to ship. The lowest costs. The highest efficiency. The fastest delivery time. For all these reasons and more, a Trane Precedent light-commercial rooftop unit isn’t just the perfect choice—it’s the only choice to extend the life of your building and improve the lives of those within it. 2 cost of ownership. Ultra-high efficiency means ultra-low operating costs installation errors. Even the most highly configured Precedent Precedent ultra-high-efficiency models continue the time in the industry. You’ll spend less time waiting for your Trane tradition of leadership in energy efficiency with new Precedent rooftop unit and more time enjoying its these innovations: cooling performance. units are ready in as few as two weeks—the fastest delivery (available fall 2013) deliver the performance building The Trane Human Interface Panel: More information, more effectively delivered occupants need, while also delivering the efficiency The optional Trane Human Interface Panel (available fall building owners want. By precisely matching output to the 2013) represents a breakthrough in unit controls, delivering cooling demands of the space, Trane eFlex compressors comprehensive information about system performance on a and fans operate at their fastest levels when demand is large, easy-to-read color touchscreen display. Unlike competing high, and modulate to slower levels when demand is less, displays, information shown on the Human Interface Panel is for an ultra-high Energy Efficiency Ratio (EER, which understandable at a glance—without requiring time-consuming measures efficiency at peak output) and Integrated Energy decoding. Technicians can quickly and easily monitor important Efficiency Ratio (IEER, a measurement of efficiency at system operating parameters in real time, and compare current variable workloads). The result: lower energy use and information with past performance—information that can be smaller energy bills. invaluable in keeping your Precedent rooftop unit working • Trane eFlex™ variable-speed compressors and fans optimally. The Human Interface Panel also allows technicians to • Trane eDrive direct-drive fans save energy and operate ™ more quietly than competing units. These highly efficient change certain system set points right from the panel, aiding in start-up, preventive maintenance tasks and troubleshooting. fans feature a beltless design, which reduces maintenance over the lifetime of the unit and lowers operating costs. Trane Intelligent Services for 24/7 peace of mind The available Trane Intelligent Services (TIS) can monitor Customized to fit your unique needs and delivered quickly and evaluate real-time data from Precedent units around the Because Trane recognizes that every building is different, we is detected, Trane can notify the building operator or dispatch offer a wide range of factory-installed options on Precedent technicians to the equipment’s location. Continuous monitoring rooftop units, such as coated condenser coils, stainless steel and expert data analysis can allow problems to be addressed drain pans, unit-mounted circuit breakers and more. Every quickly, reducing the likelihood that building occupant comfort Precedent unit can be customized to meet your exact needs, will be impacted. clock, 365 days a year. If an immediate or potential problem so you don’t have to compromise. Factory-installed options are rigorously tested to dramatically reduce the amount of time and money spent installing and commissioning units in the field, as well as the chances for 3 Comfort and low cost of ownership Trane combines technological innovation with legendary durability and performance to create the lowest cost of ownership. Trane® Precedent™ rooftop units not only offer the lowest installed cost, they also can reduce utility bills and maintenance requirements to create the lowest total cost of ownership in units that can operate at peak performance for as long as 20 to 30 years. Trane eFlex variable-speed compressor and fan technology (Available fall 2013) Trane eFlex™ variable-speed compressors and fans deliver the performance building occupants need, while also delivering the efficiency building owners want. By precisely matching output to the cooling demands of the space, Trane eFlex compressors and fans operate at their fastest levels when demand is high, and modulate to slower levels when demand is less, for an ultra-high Energy Efficiency Ratio (EER, which measures efficiency at peak output) and Integrated Energy Efficiency Ratio (IEER, a measurement of efficiency at variable workloads). The result: lower energy use and smaller energy bills. VAV option, the system modulates indoor fan and stage compressors as space temperature changes, for increased Trane eDrive direct-drive fan technology part-load efficiency and more precise temperature control. Trane eDrive direct-drive fans save energy and operate ™ more quietly than competing units. These highly efficient Trane Human Interface Panel (Available fall 2013) fans feature a beltless design, which reduces maintenance A large, easy-to-read color touchscreen display delivers over the lifetime of the unit and lowers operating costs. important system information at a glance—without requiring time-consuming decoding. This factory-installed Variable air volume (VAV) option (Not shown) option allows technicians to quickly and easily monitor Precedent rooftop systems offer both single-zone and important system operating parameters in real time, and multi-space VAV. ReliaTel controls can integrate with compare current information with past performance— existing VAV solutions to interface with both Tracer and information that can be invaluable in keeping your Tracker control platforms. Together, they deliver energy- Precedent rooftop unit working optimally. The Human efficient solutions for every building need—and require Interface Panel also allows technicians to change certain minimal setup and commissioning. With the single-zone system set points right from the panel, aiding in start-up, ™ ™ ™­ preventive maintenance tasks and troubleshooting. 4 Hot gas reheat (Not shown) Heat energy is recycled from the compressor to reduce indoor air humidity, eliminating the need for a separate heat source to do the job—which saves energy and money. Maintaining proper indoor humidity levels improves indoor comfort and can eliminate costly moisture-related damage to the building. Double-sloped condensate drain pan Non-corrosive, double-sloped, reversible condensate drain pan is easy to install and easy to clean, with stainless steel construction available as an option. MERV 8 and MERV 13 filters High-efficiency filtration for better indoor air quality Foil-faced insulation and occupant comfort. Using a MERV 13 air filter, Foil-faced insulation edges are captured and sealed, Precedent units can remove contaminants as small as 0.3 reducing the chance for insulation fibers to enter the air microns in size, which can include bacteria, cooking oil, stream and clog filters, which reduces maintenance needs smoke, insecticide dust and paint pigments. and costs. All-aluminum microchannel (MCHE) condenser coil Hinged access doors A more environmentally friendly condenser coil features maintenance time—and reduces the opportunity for improved durability and reliability. A recessed design roof damage, too. Easy entry to the unit’s service access areas reduces protects fins from incidental damage, while increased coil rigidity enhances durability. The coil’s design dramatically Color-coded, numbered wiring reduces the opportunity for leaks, and all-aluminum Faster identification of wires helps save time and money construction minimizes corrosion and eliminates formicary when servicing and diagnosing the unit. corrosion. An optional coil coating can further safeguard against corrosion. The coil also uses less refrigerant, making it more environmentally friendly and meeting the requirements of LEED EA Credit 4. 5 Trane solutions: Making buildings better for life Performance Innovation Trane® products are designed, engineered, built Founded a century ago on the belief that and tested to be solid performers, quietly doing imagination and inspiration can overcome any their jobs year after year with minimal need for obstacle, the Trane legacy of technological maintenance and repairs. The Trane Precedent breakthroughs has made it an industry legend. light-commercial rooftop units build on a long Today’s Trane Precedent rooftop units contain history of efficient, durable, high-performance numerous innovative solutions to boost HVAC products. And Trane has the Building performance and efficiency while maintaining Information Modeling (BIM) objects to support high levels of reliability. ™ your building design. Trane BIM objects represent your exact specifications and are pre-populated with data unique to each product configuration, saving time, increasing accuracy and improving how buildings are constructed. 6 Commitment Knowledge The Trane commitment to our customers’ To become and remain an industry leader requires satisfaction begins before a product is installed a full understanding of existing knowledge and a and lasts for that product’s entire life. As a never-ending quest for new discoveries. For one company, our livelihood depends on the Trane hundred years, Trane has built and maintained reputation—and the Trane reputation depends its leadership status in the HVAC industry by both on our products’ performance as well as employing the brightest and most inquisitive our relationships with customers. We want every scientists, engineers and design experts—all Trane customer to stay a Trane customer. of whom share a singular passion to know Our commitment to those customers reflects and explore the ever-evolving technology that wish. that improves the lives of our customers. Visit Trane.com/LCU for more information on Trane Precedent light-commercial units—or contact your local Trane account manager to learn more. 7 Scan the code or visit Trane.com/LCU to learn more about Trane® Precedent™ rooftop units. Ingersoll Rand (NYSE:IR) advances the quality of life by creating and sustaining safe, comfortable and efficient environments. Our people and our family of brands—including Club Car®, Ingersoll Rand®, Schlage®, Thermo King® and Trane®—work together to enhance the quality and comfort of air in homes and buildings; transport and protect food and perishables; secure homes and commercial properties; and increase industrial productivity and efficiency. We are a $14 billion global business committed to a world of sustainable progress and enduring results. ingersollrand.com We are committed to using environmentally conscious print practices. © 2013 Ingersoll-Rand Company RT-SLB027-EN April 30, 2013