Request for Proposal

advertisement
Harney County Court
Request for Proposal
Harney County Jail
HVAC System Upgrades
Issue Date: December 11, 2013
Pre-Bid Conference Date:
December 17, 2013, 2 p.m.
Harney County Courthouse
450 North Buena Vista
Burns, Oregon 97720
Bid Due Date: To Be Determined after Pre-Bid Conference
REQUEST FOR PROPOSAL
Notice is hereby given that proposals will be received by Harney County Court, Burns, Oregon
for:
Replacing, repairing and maintaining heating, ventilating and cooling
equipment in the Harney County Jail building. The project shall be structured
as design/build. The successful contractor will retain the services of
professional engineers as necessary or if deemed required by Harney County.
Memorandum
To:
Bidding Contractors
C:
Judge Steven E. Grasty, Harney County Court
From:
Anthony J. Dickman, P.E.
Date:
12/11/2013
Re:
Harney County Jail – HVAC System Upgrades
Objective
The objective of this project is to replace, repair and maintain heating, ventilating
and cooling equipment in the Harney County Jail building, located in Burns,
Oregon. The project shall be structured as design/build. The successful contractor
will retain the services of professional engineers as necessary or if deemed
required by the Owner (Harney County).
Description
The jail facilities are heated using forced air supplied by small air handlers in
various zones throughout the facility. Heating water coils are installed in the
ducting directly downstream of the air handlers. An oil-fired boiler and pump
located on the premises provide the heating water supply and return flow through
the coils.
Fresh air intake grilles are located on outside walls and the balance between fresh
air and return air is controlled using dampers mounted within the return ducting
system. The dampers are presently not clearly marked and possibly need to be
replaced or repaired.
The existing system utilizes a rooftop-mounted evaporative (swamp) cooler to
provide nominal cooling in summer. Although the cooler provides some relief from
the heat, the additional humidity makes the building uncomfortable during the
warmer days.
1
Harney County Jail – HVAC System Upgrades
Bidding Memorandum
Project Requirements
Bidding Specifications and Other Requirements
All work for this project shall be accomplished in accordance with the
accompanying specifications:
•
15200 – Basic Mechanical Requirements
•
15220 – HVAC System Requirements
In addition to these specifications, all work shall meet the requirements of local,
state and federal codes, including (but not limited to):
•
Oregon Mechanical Specialty Code – 2007
•
ASHRAE Standard 62-2001 Ventilation for Acceptable Indoor Air Quality
Potential Contractors shall be required to attend one (1) on-site pre-bid
meeting to inspect the existing facilities and systems and review the project
requirements with the Owner and Owner’s Representative.
Heating System
Heating water coils for the various air handlers are to be inspected, cleaned and
repaired (if necessary). An inspection of the hydronic system (heating water
supply and return) shall also be required to insure that all critical components
are present and operating. Based upon an initial inspection, it appears that the
system does not include an air separator in the heating water loop. If the air
separator is indeed missing, the installation of a new separator shall be
included within the scope of this project. Likewise, if insufficient drains and/or
air vents are not included in the piping system, required drains and vents shall
be installed as part of this project.
Cooling System
The existing evaporative cooler shall be removed and disposed of properly by
the successful Contractor. It shall be replaced by a rooftop unitary heat pump
system. The heat pump shall be used primarily for cooling in summer, but may
be called upon to provide supplemental heat in winter. For this reason, the heat
pump shall include electric resistance heating elements as required to meet the
demands of the Burns winter climate. Contractor shall supply a unit equivalent
to the Trane “Precedent” system. A brochure for the unit is attached to this
memo for reference purposes.
Ventilation System
Contractor shall be responsible for ensuring that existing dampers are
functioning properly. Damaged or otherwise non-functioning dampers shall be
replaced as required. Upon completion of the equipment installation and
2
Harney County Jail – HVAC System Upgrades
Bidding Memorandum
repairs, the air system shall be balanced to ensure proper air flow (supply and
return) through the various zones serviced by the individual air handling
system. In order to ensure proper ventilation, it may be necessary to include
new ducting for return and/or outside air flow.
Project Bidding and Schedule
The objective is to complete the project before June 2014, sooner if possible.
Bidding requirements shall be as defined in the pre-bid meeting, scheduled for
Tuesday 17 December in the Harney County Courthouse located in Burns,
Oregon.
3
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
1
GENERAL
1.1
WORK INCLUDED
A.
1.2
This Section specifies the basic requirements for all Contractor-supplied
and -installed HVAC systems and equipment. It applies to all sections
included in Division 15.
RELATED SECTIONS
A.
This general section shall be used in conjunction with the following other
specifications and accompanying document to establish the total
requirements for the project equipment and systems:
1.
1.3
DESIGN REQUIREMENTS
A.
1.4
Section 15220 – HVAC System Requirements.
Compliance by the Contractor and/or Vendor(s) with the provisions of
this Specification does not relieve him of the responsibilities of furnishing
equipment and materials of proper design, mechanically suited to meet
operating guarantees at the specified service conditions.
SUBMITTALS
A.
Bid Information:
1.
An individual price and delivery schedule must be quoted for each
equipment number.
2.
The length of time required for certification of all information,
drawings, etc.
3.
Estimated equipment weight and support requirements.
4.
Electrical power requirements.
5.
Utility (cooling water, air, fuel, etc.) requirements.
6.
Time and costs required for manufacturer’s startup services as
indicated in individual equipment sections.
7.
When a data sheet is provided which has blanks for input of
information from the bidders, the completed data sheet shall be
included with the bid.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 1 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
B.
Drawings and data within two (2) weeks of award of Contract: Composite
outline drawings including the following are required:
1.
1.5
1.6
Certified correct dimensional drawings of completed assembled
units, which shall show:
a.
Identification data for equipment components.
b.
Rotation.
c.
Weight.
d.
Adequate dimensional data, including locations and sizes
of seismic restraints, to permit the design of foundation,
piping and wiring connections.
e.
Location of motor junction box(es).
f.
Piping connections identified with the size, rating, and
facing indicated.
g.
Clearance required for disassembly and maintenance.
h.
Three (3) copies of operating and maintenance manuals.
REGULATORY REQUIREMENTS
A.
Conformance to the latest Codes and other regulatory requirements is
the responsibility of the Contractor and the Vendor(s).
B.
The Contractor and the Vendor(s) shall obtain all permits and arrange all
inspections required by codes applicable to this Section and shall submit
written evidence to Owner that required permits, inspections, and code
requirements have been secured.
DELIVERY, STORAGE AND HANDLING
A.
Packing and Shipping:
1.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Each unit shall be suitably prepared for the shipment specified
and for storage in accordance with manufacturer’s instructions in
a manner requiring no disassembly prior to operation.
Page 2 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
2.
The Contractor shall be solely responsible for the adequacy of the
preparation for shipment provisions employed with respect to
materials and application.
3.
Equipment shall be completely free of water prior to any
shipment preparation.
4.
Bearings, bearing housings, and oil systems, including reservoirs,
coolers, filters, and piping, shall be thoroughly cleaned internally
of metal particles, dirt and debris, and coated with a suitable rust
preventative prior to shipment.
5.
Adequate protection shall be provided against mechanical
damage and atmospheric corrosion in transit.
6.
Instruments and valves, including auxiliary systems, must be
securely mounted and/or supported to eliminate damage during
shipment, storage, operation, and maintenance.
7.
Supports and rigging connections shall be provided to prevent
damage during transit, lifting or unloading.
8.
Threaded connections shall be provided with a pipe plug of the
same material as the connections (except cast iron connections
shall have steel plugs). Plugs shall have a square or hex head.
Teflon tape shall be used as a thread sealant.
9.
Those openings that require rust preventative shall be suitably
tagged to indicate the type and nomenclature of the rust
preventative used.
10.
Equipment containing insulating oils or other fluids shall be
suitably tagged at openings to indicate the nature of the contents,
and shipping and storage precautions.
11.
Open ends of tubes and pipe shall be capped (just taping is not
adequate) for protection.
12.
Equipment and components shall be packed, securely anchored
(skid mounted when required) and weather protected for the
shipment method called for in the Purchase Order. Separate,
loose, or spare parts shall be boxed and each part individually
protected as required. Each individual container shall be marked
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 3 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
both inside and outside with the equipment or component
number and service for which the parts are intended.
2
13.
One (1) complete set of Installation, Operation and Maintenance
Instructions shall be packed and shipped with the equipment or
components. This set is in addition to the sets that are to be sent
directly to the Owner.
14.
Each container shall also include a complete Bill of Materials
identifying each part. In some instances, such as instruments,
specific tagging shall be required.
PRODUCTS
2.1
2.2
GENERAL
A.
Equipment and components shall be the manufacturer’s most recent
standard design. Equipment and component designs which have not
been previously used successfully in an industrial application are not
acceptable unless approved in writing by the Owner.
B.
Provide one quart of each standard paint used from each equipment
and/or materials supplier for touch up. All paint cans are to be
adequately labeled to identify where they are to be used. When
equipment is involved, the label must at a minimum include Owner’s
equipment tag number.
C.
All equipment over 100 pounds in weight shall be provided with lifting
lugs of the manufacturer’s design for easy handling.
EQUIPMENT IDENTIFICATION
A.
Equipment and components shall have an identification tag pinned or
fastened in a readily accessible location with the following information at
a minimum (when applicable).
1.
Manufacturer’s name.
2.
Manufacturer’s model number.
3.
Date of manufacture.
4.
Design operating conditions (where relevant).
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 4 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
3
5.
Design pressure and temperature (where relevant).
6.
Serial number.
7.
Materials of construction (major).
8.
Code stamp (as required).
9.
RPM (as required).
10.
Electrical power requirements (as required).
11.
Equipment name.
12.
Equipment identification tag numbers.
13.
Equipment capacity.
14.
Equipment dimensions.
EXECUTION
3.1
INSTALLATION
A.
Installation shall be in accordance with the requirements of the
equipment or component manufacturer, including special requirements
for seismic restraints.
B.
Equipment Manufacturer’s Responsibility and Services:
1.
A manufacturer’s representative for major equipment and
operating systems shall be provided as necessary to assist the
Contractor during installation, and to provide written certification
that the equipment has been installed as specified and in
accordance with the manufacturer’s requirements.
2.
The manufacturer’s representative shall provide the initial startup
of equipment in the presence of Owner.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
a.
Provide a pre-start check of all piping, valves, control
devices, control panels, and equipment.
b.
Calibrate and adjust equipment and controls for operation
at the specified design conditions.
Page 5 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
3.2
c.
Provide a record of all startup events noting problems and
their resolution.
d.
Provide a record of all setpoints for operational controls
and devices.
3.
Upon the completion of equipment startup, provide adequate
instructional time with Owner’s personnel to review the
operations and maintenance manuals and perform each step
necessary for startup, shutdown, troubleshooting, and routine
maintenance. The instructional time shall be scheduled through
Owner.
4.
Upon completion of the inspections, startup, testing, and
checkout procedures, the equipment manufacturer shall submit
written notice to Owner that the units are ready for use by
Owner. Provide a certificate of calibration for all equipment.
MOUNTING AND SHIMMING
A.
Provisions for mounting special equipment on spring isolators, snubbers
and inertia bases shall be included as required by the Drawings.
B.
Mechanical Services Equipment:
1.
Level the equipment by means of 304 stainless steel wedges
(stainless steel plates and stainless steel shims) or PVC/poly
wedges in areas of extreme corrosive environments. Wedge taper
shall not be greater than 1/4 inch per foot. Use double wedges to
provide a level bearing surface for the equipment. Secure each
pair of wedges in their final positions with one tack weld on each
side after leveling is complete. Wedging shall be executed in a
manner that will prevent a change in level or springing of the
baseplate when the anchor bolts are tightened.
2.
Adjust rotating equipment assemblies such that the driving units
are properly aligned, plumb and level with the driven units and all
interconnecting shafts and couplings.
3.
Rotating equipment shall be checked for proper alignment with
dial indicators or laser after completion of grouting. The
alignment must be within the tolerances required by the
equipment manufacturer.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 6 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
C.
3.3
3.4
Grouting: For equipment requiring grouting, and after the equipment has
been set in position, aligned, and shimmed to the proper elevations,
grout the space between the bottom of the baseplate and the concrete
foundation and/or inertia base with a poured non-shrinking grout.
INSPECTION
A.
The Contractor shall inspect his work to ensure the installation and
workmanship are in accordance with these specifications and acceptable
industry standards for the work being done.
B.
Factory and/or field testing may include full and/or part load
performance tests, basic mechanical spin tests, etc. It may also include
various nondestructive tests as required by specified codes including
those normally required by the manufacturer’s own manufacturing
standards.
C.
It is a requirement of this Specification that Owner’s inspection work be
minimized by assigning to the Contractor the responsibility of furnishing
the inspector with all necessary material certifications, shop test data,
radiographic plates and the like necessary to verify the Contractor’s
compliance with the specifications for all Contractor-furnished
equipment.
D.
Where shop inspection is specified, no surfaces or parts are to be painted
until the inspection is complete.
E.
All materials, equipment, and workmanship shall be subject to inspection
at any time by Owner. Contractor shall correct any work, materials, or
equipment not in accordance with the Contract Documents.
SAFETY CONSIDERATIONS
A.
All equipment shall be installed with suitable access clearances that
satisfy OSHA and code requirements for maintenance or removal of
replaceable parts and components, and with necessary unions or flanges
to perform the maintenance or removal without removing the
connecting appurtenances.
B.
Where equipment requiring periodic maintenance cannot be reached by
normal walkways because of interference with ductwork, piping, or other
obstructions the Contractor shall notify Owner and propose an alternate
safe means of access. These may include construction of an overhead
platform with stairway or ladder ends and safety railings or handholds, or
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 7 of 8
Performance and
Bidding Specifications
BASIC MECHANICAL REQUIREMENTS
SECTION 15200
walk-through duct plenums with hinged access doors, or as required to
meet OSHA standards for safe maintenance procedures.
3.5
CLEANING, STARTUP, AND ADJUSTING
A.
The Contractor shall be responsible for proper operation of systems,
minor subsystems, and services provided under this Section. It shall
coordinate startup procedures, calibration, and system checkout with
subcontractors involved. System operational problems shall be
diagnosed; correctional procedures shall be initiated as required to bring
the system into compliance with the design, and the problem then shall
be re-checked to verify that the system operates normally. Remaining
difficulties shall be brought to the attention of Owner.
B.
Thoroughly clean all parts of the installation at the completion of the
work. Clean up and remove from the premises refuse material, crates,
and rubbish arising from Work.
END OF SECTION
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 8 of 8
Performance and
Bidding Specifications
HVAC SYSTEM REQUIREMENTS
SECTION 15220
1
GENERAL
1.1
WORK INCLUDED
A.
1.2
FINISH AND PAINTING
A.
1.3
2
Furnish and install complete heating, cooling and ventilating systems with
all equipment, ductwork and controls. Repair, maintain and replace
existing equipment that shall remain in the facility.
Prime and paint all exposed ductwork as required by Owner.
COORDINATION WITH ELECTRICAL CONTRACTOR
A.
This Contractor shall coordinate with the Electrical Contractor on
controls, motors, starters etc.
B.
Responsibility for furnishing all controls, including thermostats, auxiliary
switches, transformers and relays is included in these Heating, Cooling
and Ventilating Specifications.
C.
Low-voltage wiring shall be furnished and installed by this Contractor.
D.
This Contractor shall review all wiring connections that have any
influence on supplied equipment or work, and verify that these
connections are correct before permitting any equipment that is
furnished, installed or modified under this Contract to be operated.
PRODUCTS
2.1
DUCTWORK
A.
Galvanized sheet steel of thickness recommended in Table 1-4 of the
SMACNA HVAC Duct Construction Standards, 1985 edition, for 1" water
gauge, 2500 ft/min velocity, except no duct shall be less than 24 gauge.
Fabricate in accordance with SMACNA standards except where otherwise
specified or indicated.
B.
Insulate concealed supply and return ductwork with Owens-Corning 11/2" Type 100 FRK, Schuller R-6 Microlite Type FSK, faced fiberglass
ductwrap installed per manufacturer's application Specification, 1"
approximate installed thickness. Rectangular ductwork may be lined with
1" thickness Owens-Corning Aeroflex, Schuller Linacoustic.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 1 of 4
Performance and
Bidding Specifications
HVAC SYSTEM REQUIREMENTS
SECTION 15220
2.2
3
C.
Flexible duct connectors at equipment shall be UL listed.
D.
Fabricate all ductwork in accordance with SMACNA duct manuals and
ASHRAE handbook.
HEATING AND VENTILATING EQUIPMENT
A.
See accompanying documents.
B.
Brand and model shown in accompanying documents are meant to
establish quality and equipment type only. Proposed substitutes shall be
equal to those indicated in documents.
C.
Furnish and install all equipment in accordance with accompanying
documents, manufacturer's recommendations and all applicable codes.
EXECUTION
3.1
3.2
DUCTWORK - HVAC
A.
All ductwork of sheetmetal shall be in accordance with the applicable
SMACNA Manual unless otherwise specified, airtight and supported as
recommended. Ductwork shall run concealed unless otherwise noted.
B.
All ducts shall be supported as recommended by SMACNA.
C.
There shall be no ducts exposed to weather.
D.
Any exposed ductwork in conditioned space shall not be insulated. Fresh
air and exhaust ducts shall not be insulated.
E.
Provide volume control extractors or dampers at each branch take-off
from main ducts
F.
No "grey" duct tape shall be used. Metal duct sealing shall be "hard cast"
or SMACNA approved foil-backed pressure-sensitive tape.
G.
Flexible ductwork shall be installed with no runs more than 5'-0" and no
more than three (3) bends of 45° maximum each. Flexible ductwork shall
be used only at register connections.
AIR BALANCE
A.
The complete air system shall be tested and balanced by competent
personnel.
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 2 of 4
Performance and
Bidding Specifications
HVAC SYSTEM REQUIREMENTS
SECTION 15220
3.3
B.
Adjust all air flows to be within ±10% of nomingal. All dampers shall be
locked in position and indelibly marked.
C.
Prove the correct operation of all controls, dampers, heating or
ventilating stages, timers, and thermostats. Balance Report shall address
the operation of controls.
D.
The Installing Contractor shall provide labor and materials as required to
perform the air balance. This Contractor shall allow for a sheave and belt
change on each fan, without additional expense to Owner.
E.
At the completion of the balancing operation, provide the Owner with a
minimum of three (3) copies of the air balance data. Provide data
showing:
Required CFM and actual measured CFM for each outlet, return,
exhaust grille, register, and each zone.
2.
Static pressure across fans.
3.
Current draw of all motors with nameplate data.
4.
Instruments and date of calibration.
5.
Room temperature after balance and control set point. Provide
date and ambient conditions when readings are taken.
6.
Temperature rise across heating water coils under heating
conditions.
CONTROLS
A.
3.4
1.
A complete system shall be provided. System shall include all
components required to provide temperature control in each zone.
System shall provide correct operation of all equipment. Temperature
control for electric heat shall be by Electrical Contractor.
INSTRUCTION BOOK
A.
The Contractor shall provide the Owner with three (3) copies of complete
written instructions in the operation of the various systems. The
instructions shall be bound in booklet form and shall include pertinent
maintenance information of the equipment with names of local suppliers
and agents. The instructions shall reference all equipment numbers. The
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 3 of 4
Performance and
Bidding Specifications
HVAC SYSTEM REQUIREMENTS
SECTION 15220
Contractor shall also instruct the Owner or his/her representatives in the
operation of the systems.
END OF SECTION
Harney County Jail
Burns, Oregon
HVAC System Upgrades
Page 4 of 4
Performance and
Bidding Specifications
Trane® Precedent
™
3- to 10-ton light commercial rooftop units
The right size for high comfort.
The lowest installed cost and lowest total
Most Trane Precedent
rooftop units can be
ready in as few as two
weeks—the fastest
delivery time in the
industry—so your
project doesn’t get
delayed while waiting
for equipment.
When it comes to HVAC expenses, every dollar counts. From
your initial investment to monthly utility costs and maintenance,
a light-commercial rooftop unit can have a significant impact
on your bottom line—which is why a Trane® Precedent™ lightcommercial rooftop unit can be the perfect choice.
No competing light-commercial rooftop unit has a lower installed cost than
the Trane Precedent—and with its industry-leading efficiency and low
maintenance requirements, no other unit has a lower total cost of ownership.
And once you’ve made the wise decision that a Trane Precedent lightcommercial rooftop unit is the right solution for your building, it’s good to
know that no other light-commercial rooftop unit can be delivered as quickly
as the Trane Precedent, with most units ready in as few as two weeks—order
to ship.
The lowest costs. The highest efficiency. The fastest delivery time. For all
these reasons and more, a Trane Precedent light-commercial rooftop unit
isn’t just the perfect choice—it’s the only choice to extend the life of your
building and improve the lives of those within it.
2
cost of ownership.
Ultra-high efficiency means ultra-low
operating costs
installation errors. Even the most highly configured Precedent
Precedent ultra-high-efficiency models continue the
time in the industry. You’ll spend less time waiting for your
Trane tradition of leadership in energy efficiency with
new Precedent rooftop unit and more time enjoying its
these innovations:
cooling performance.
units are ready in as few as two weeks—the fastest delivery
(available fall 2013) deliver the performance building
The Trane Human Interface Panel: More information,
more effectively delivered
occupants need, while also delivering the efficiency
The optional Trane Human Interface Panel (available fall
building owners want. By precisely matching output to the
2013) represents a breakthrough in unit controls, delivering
cooling demands of the space, Trane eFlex compressors
comprehensive information about system performance on a
and fans operate at their fastest levels when demand is
large, easy-to-read color touchscreen display. Unlike competing
high, and modulate to slower levels when demand is less,
displays, information shown on the Human Interface Panel is
for an ultra-high Energy Efficiency Ratio (EER, which
understandable at a glance—without requiring time-consuming
measures efficiency at peak output) and Integrated Energy
decoding. Technicians can quickly and easily monitor important
Efficiency Ratio (IEER, a measurement of efficiency at
system operating parameters in real time, and compare current
variable workloads). The result: lower energy use and
information with past performance—information that can be
smaller energy bills.
invaluable in keeping your Precedent rooftop unit working
• Trane eFlex™ variable-speed compressors and fans
optimally. The Human Interface Panel also allows technicians to
• Trane eDrive direct-drive fans save energy and operate
™
more quietly than competing units. These highly efficient
change certain system set points right from the panel, aiding in
start-up, preventive maintenance tasks and troubleshooting.
fans feature a beltless design, which reduces maintenance
over the lifetime of the unit and lowers operating costs.
Trane Intelligent Services for 24/7 peace of mind
The available Trane Intelligent Services (TIS) can monitor
Customized to fit your unique needs and
delivered quickly
and evaluate real-time data from Precedent units around the
Because Trane recognizes that every building is different, we
is detected, Trane can notify the building operator or dispatch
offer a wide range of factory-installed options on Precedent
technicians to the equipment’s location. Continuous monitoring
rooftop units, such as coated condenser coils, stainless steel
and expert data analysis can allow problems to be addressed
drain pans, unit-mounted circuit breakers and more. Every
quickly, reducing the likelihood that building occupant comfort
Precedent unit can be customized to meet your exact needs,
will be impacted.
clock, 365 days a year. If an immediate or potential problem
so you don’t have to compromise.
Factory-installed options are rigorously tested to dramatically
reduce the amount of time and money spent installing and
commissioning units in the field, as well as the chances for
3
Comfort and low cost of ownership
Trane combines technological innovation with legendary durability
and performance to create the lowest cost of ownership. Trane®
Precedent™ rooftop units not only offer the lowest installed cost,
they also can reduce utility bills and maintenance requirements
to create the lowest total cost of ownership in units that can operate
at peak performance for as long as 20 to 30 years.
Trane eFlex variable-speed compressor and fan
technology (Available fall 2013)
Trane eFlex™ variable-speed compressors and fans
deliver the performance building occupants need, while
also delivering the efficiency building owners want. By
precisely matching output to the cooling demands of
the space, Trane eFlex compressors and fans operate at
their fastest levels when demand is high, and modulate
to slower levels when demand is less, for an ultra-high
Energy Efficiency Ratio (EER, which measures efficiency
at peak output) and Integrated Energy Efficiency Ratio
(IEER, a measurement of efficiency at variable workloads).
The result: lower energy use and smaller energy bills.
VAV option, the system modulates indoor fan and stage
compressors as space temperature changes, for increased
Trane eDrive direct-drive fan technology
part-load efficiency and more precise temperature control.
Trane eDrive direct-drive fans save energy and operate
™
more quietly than competing units. These highly efficient
Trane Human Interface Panel (Available fall 2013)
fans feature a beltless design, which reduces maintenance
A large, easy-to-read color touchscreen display delivers
over the lifetime of the unit and lowers operating costs.
important system information at a glance—without
requiring time-consuming decoding. This factory-installed
Variable air volume (VAV) option (Not shown)
option allows technicians to quickly and easily monitor
Precedent rooftop systems offer both single-zone and
important system operating parameters in real time, and
multi-space VAV. ReliaTel controls can integrate with
compare current information with past performance—
existing VAV solutions to interface with both Tracer and
information that can be invaluable in keeping your
Tracker control platforms. Together, they deliver energy-
Precedent rooftop unit working optimally. The Human
efficient solutions for every building need—and require
Interface Panel also allows technicians to change certain
minimal setup and commissioning. With the single-zone
system set points right from the panel, aiding in start-up,
™
™
™­
preventive maintenance tasks and troubleshooting.
4
Hot gas reheat (Not shown)
Heat energy is recycled from the compressor to reduce
indoor air humidity, eliminating the need for a separate
heat source to do the job—which saves energy and money.
Maintaining proper indoor humidity levels improves indoor
comfort and can eliminate costly moisture-related damage
to the building.
Double-sloped condensate drain pan
Non-corrosive, double-sloped, reversible condensate drain
pan is easy to install and easy to clean, with stainless steel
construction available as an option.
MERV 8 and MERV 13 filters
High-efficiency filtration for better indoor air quality
Foil-faced insulation
and occupant comfort. Using a MERV 13 air filter,
Foil-faced insulation edges are captured and sealed,
Precedent units can remove contaminants as small as 0.3
reducing the chance for insulation fibers to enter the air
microns in size, which can include bacteria, cooking oil,
stream and clog filters, which reduces maintenance needs
smoke, insecticide dust and paint pigments.
and costs.
All-aluminum microchannel (MCHE)
condenser coil
Hinged access doors
A more environmentally friendly condenser coil features
maintenance time—and reduces the opportunity for
improved durability and reliability. A recessed design
roof damage, too.
Easy entry to the unit’s service access areas reduces
protects fins from incidental damage, while increased coil
rigidity enhances durability. The coil’s design dramatically
Color-coded, numbered wiring
reduces the opportunity for leaks, and all-aluminum
Faster identification of wires helps save time and money
construction minimizes corrosion and eliminates formicary
when servicing and diagnosing the unit.
corrosion. An optional coil coating can further safeguard
against corrosion. The coil also uses less refrigerant,
making it more environmentally friendly and meeting
the requirements of LEED EA Credit 4.
5
Trane solutions:
Making buildings better for life
Performance
Innovation
Trane® products are designed, engineered, built
Founded a century ago on the belief that
and tested to be solid performers, quietly doing
imagination and inspiration can overcome any
their jobs year after year with minimal need for
obstacle, the Trane legacy of technological
maintenance and repairs. The Trane Precedent
breakthroughs has made it an industry legend.
light-commercial rooftop units build on a long
Today’s Trane Precedent rooftop units contain
history of efficient, durable, high-performance
numerous innovative solutions to boost
HVAC products. And Trane has the Building
performance and efficiency while maintaining
Information Modeling (BIM) objects to support
high levels of reliability.
™
your building design. Trane BIM objects represent
your exact specifications and are pre-populated
with data unique to each product configuration,
saving time, increasing accuracy and improving
how buildings are constructed.
6
Commitment
Knowledge
The Trane commitment to our customers’
To become and remain an industry leader requires
satisfaction begins before a product is installed
a full understanding of existing knowledge and a
and lasts for that product’s entire life. As a
never-ending quest for new discoveries. For one
company, our livelihood depends on the Trane
hundred years, Trane has built and maintained
reputation—and the Trane reputation depends
its leadership status in the HVAC industry by
both on our products’ performance as well as
employing the brightest and most inquisitive
our relationships with customers. We want every
scientists, engineers and design experts—all
Trane customer to stay a Trane customer.
of whom share a singular passion to know
Our commitment to those customers reflects
and explore the ever-evolving technology
that wish.
that improves the lives of our customers.
Visit Trane.com/LCU for more information on Trane Precedent light-commercial units—or contact your local Trane account manager
to learn more.
7
Scan the code or visit
Trane.com/LCU
to learn more about
Trane® Precedent™
rooftop units.
Ingersoll Rand (NYSE:IR) advances the quality of life by creating and sustaining safe, comfortable and efficient
environments. Our people and our family of brands—including Club Car®, Ingersoll Rand®, Schlage®, Thermo King® and
Trane®—work together to enhance the quality and comfort of air in homes and buildings; transport and protect food
and perishables; secure homes and commercial properties; and increase industrial productivity and efficiency.
We are a $14 billion global business committed to a world of sustainable progress and enduring results.
ingersollrand.com
We are committed to using environmentally conscious print practices.
© 2013 Ingersoll-Rand Company
RT-SLB027-EN
April 30, 2013
Download