3.0 Transmission Line Options 3.1 Technical Analysis Great River Energy has examined four different alternative transmission line projects that could remedy the system deficiencies. Great River Energy’s preferred option is a 69 kV project. The other three are 115 kV projects. The options are described below: Option 1 - Athens to Martin Lake 69 kV Transmission Line (Great River Energy’s preferred solution) This option would involve the construction of approximately 10.2 miles of 69 kV transmission line between the Connexus Energy Martin Lake Substation and the Great River Energy Athens Substation (see Figure 3-1). This option provides a redundant transmission source to the Martin Lake Substation and allows for additional growth in electrical demand to be supported along the Highway 65 corridor via the Linwood Substation. Facilities could be easily integrated into the existing system with 69 kV construction. Option 2 - Chisago County-Martin Lake-Coopers Corner 115 kV line and Coopers Corner 115/69 kV Substation This option would involve the construction of approximately 25 miles of 115 kV transmission line between the Xcel Energy Chisago County Substation, the Martin Lake Substation, and the Coopers Corner Substation. A new 115/69 kV transformer would be established at the Coopers Corner Substation and the Martin Lake Substation would be converted to 115 kV service. Additionally, the Coopers Corner-Athens 69 kV line would be rebuilt as a 69 kV line with equipment to accommodate the higher line flows that would result on this line with the new 115 kV line addition (see Figure 3-2). This option is essentially a duplicate of the preferred alternative (Option 1), but would require that significantly more transmission line be built, and therefore, more new right of way be acquired. Additionally, the increased line mileage between breakers adds to the exposure of the line, reducing reliability. 9 Figure 3-1: Martin Lake-Athens 69 kV Line 10 Figure 3-2: Chisago County-Martin Lake-Coopers Corner 115 kV Line 11 Option 3 - Chisago County-Martin Lake-Coopers Corner-Blaine 115 kV line, Coopers Corner 115/69 kV Substation, and Blaine 230/115 kV Substation Modifications Great River Energy investigated continuing the 115 kV line proposed in Option 2 south to the Blaine Substation. This would require about 50 miles of new 115 kV line and would provide redundant 115 kV transmission feeds to the Coopers Corner Substation. Much of this line would likely be built on existing 69 kV transmission line corridors, replacing the existing 69 kV circuits with new 115-69 kV double circuit structures (see Figure 3-3). However, in addition to the drawbacks cited in Option 2, construction outages would likely be difficult to schedule because significant reconstruction of the Great River Energy 69 kV system would likely be required. Also, due to the significant 115 kV line length between substations, there would be additional line exposure, thus the system would not be as reliable as the preferred option. Option 4 - Blaine-Martin Lake-Athens-Dalbo 115 kV line, Athens 115/69 kV Substation, Rush City-Dalbo-Milaca 230 kV line, and Dalbo 230/115 kV Substation Option 4 would require building a new 115 kV line between the Blaine, Martin Lake and Athens substations, and a new Dalbo 230/115 kV Substation. A new 230 kV line between the Milaca, Dalbo, and Rush City substations would be required to support the 115 kV system. This 230 kV line would provide a 230 kV loop to the Milaca Substation and create a 230 kV ring around the Great River Energy 69 kV system. A new 115/69 kV transformer would be added at the Athens Substation (see Figure 3-4). This would involve approximately 110 miles of 230 and 115 kV line, a new 115/69 kV transformer at the Athens Substation, a new 230/115 kV substation at Dalbo, modifications at the Blaine, Rush City, and Milaca substations, and a voltage conversion of the Martin Lake Substation. A second 230 kV line into the Milaca Substation would be beneficial to the reliability of this substation. Although this is a technically feasible option from a system standpoint, it is clearly not justifiable given the drawbacks. It clearly cannot be justified from a cost standpoint and developing a 230 kV system would have a much more significant environmental impact the preferred option; a new 60 mile corridor would need to be developed. Much of the 115 kV system would likely be double circuited with the existing 69 kV system, which would likely make scheduling construction outages difficult. Also, the permitting and construction schedule for a project of this magnitude may take years, which does not address the required timelines for 69 kV system improvements. Like other alternatives, the 115 kV line exposure would be much greater than the exposure offered by the proposed project, thus reduced reliability would be expected with this alternative. There is also lack of space at Athens Substation for 115 kV expansion, which would make siting a 115/69 kV transformer there extremely difficult. 12 Figure 3-3: Chisago County-Martin Lake-Coopers Corner-Blaine 115 kV Line 13 Figure 3-4: Blaine-Martin Lake-Athens-Dalbo 115 kV Line and Rush City-Dalbo-Milaca 230 kV Line 14 3.2 Cost and System Efficiency Analysis The estimated costs for each of the alternatives considered are tabulated in Table 3-1. These include the project costs incurred by Great River Energy, its member cooperatives, and other transmission-owning utilities that would need to modify their electrical facilities to accommodate the change. Additionally, each of the projects will reduce the amount of line losses (energy generated but not deliverable) currently occurring. These efficiency improvements in delivering electricity to the area Connexus and East Central substations are realized with each of these projects and are summarized in Table 3-2. Table 3-1 Estimated Cost Factors for Options 1- 4 Estimated Cost Option 1: Martin Lake-Athens 69 kV line Option 2: Chisago CountyCoopers Corner 115 kV line Option 3: BlaineCoopers CornerMartin LakeChisago County 115 kV line Option 4: BlaineMartin LakeAthens-Dalbo 115 kV line $6,537,000 $39,700,000 $67,340,000 $124,480,000 Table 3-2 System Peak Loss Improvements for Options 1- 4 System Peak Loss Improvements Estimated Yearly System Loss Savings Value Option 1: Martin Lake‐Athens 69 kV line Option 2: Chisago County‐Coopers Corner 115 kV line Option 3: Blaine‐ Coopers Corner‐ Martin Lake‐ Chisago County 115 kV line Option 4: Blaine‐ Martin Lake‐ Athens‐Dalbo 115 kV line 0.7 MW 3.2 MW 3.7 MW 3.3 MW $169,300 $773,900 $894,850 $798,100 15