TONBRIDGE POWER Green Line Project Plan of Service 108005-00037 – TON-EL-REP-0001 13 June 2011 Bellaire 6330 West Loop South, Bellaire TX 77401, United States Tel: +1 713 407 5005 Fax: +1 713 407 5099 WorleyParsons Limited © Copyright 2011 WorleyParsons TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE SYNOPSIS This report documents the transmission line calculations, results, and recommendations undertaken as part of the Green Line Project for Tonbridge Power. Disclaimer This study report is conceptual in nature and represents the work of WorleyParsons performed to recognized engineering principles and practices appropriate for conceptual engineering work and the terms of reference provided by WorleyParsons’ contractual Customer, Tonbridge Power (the “Customer”). This study report may not be relied upon for detailed implementation or any other purpose not specifically identified within this study report. This study report is confidential and prepared solely for the use of the Customer. The contents of this study report may not be used or relied upon by any party other than the Customer, and neither WorleyParsons, its subconsultants nor their respective employees assume any liability for any reason, including, but not limited to, negligence, to any other party for any information or representation herein. The extent of any warranty or guarantee of this study report or the information contained therein in favor of the Customer is limited to the warranty or guarantee, if any, contained in the contract between the Customer and WorleyParsons. PROJECT 108005-00037 - GREEN LINE PROJECT REV DESCRIPTION A Issued for Review B ORIG REVIEW WORLEYPARSONS APPROVAL C Aderholdt J Glasgow R Simon C Aderholdt J Glasgow R Simon Issued for Review DATE CLIENT APPROVAL 19-May-11 N/A 13-Jun-11 N/A DATE N/A Green Line Report Rev B (16-June-11) Corporate Base Page 2 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE CONTENTS A. EXECUTIVE SUMMARY ..................................................................................................5 B. INTRODUCTION ..............................................................................................................6 C. PLAN BASIS.....................................................................................................................7 D. PLAN ASSUMPTIONS .....................................................................................................8 E. RECOMMENDED PLAN ..................................................................................................9 F. RECOMMENDED PLAN (ALTERNATIVE) .....................................................................10 G. PLAN 3 - DETAILED DESCRIPTION .............................................................................11 G.1 Plan 3 Summary ..............................................................................................11 G.2 Plan 3 Details ..................................................................................................11 G.3 Plan 3 Impact on Area Voltages ......................................................................12 G.4 Plan 3 Impact on Area Transmission Services ................................................12 G.5 Plan 3 Transient Analysis ................................................................................13 G.6 Plan 3 Transmission Line Losses ....................................................................14 G.7 Plan 3 Costs ....................................................................................................14 G.8 Plan 3 Conclusions ..........................................................................................14 H. PLAN 3A - DETAILED DESCRIPTION ...........................................................................15 H.1 Plan 3A Summary ...........................................................................................15 H.2 Plan 3A Details ................................................................................................15 H.3 Plan 3A Impact on Area Voltages ....................................................................16 H.4 Plan 3A Impact on Area Transmission Services ..............................................17 H.5 Plan 3A Transient Analysis..............................................................................18 H.6 Plan 3A Transmission Line Losses..................................................................18 H.7 Plan 3A Costs..................................................................................................18 H.8 Plan 3A Conclusions .......................................................................................18 I. CONCLUSION AND RECOMMENDATIONS .................................................................19 J. SWITCHING STUDY ......................................................................................................20 Green Line Report Rev B (9-June-11) Corporate Base Page 3 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE K. REFERENCES ...............................................................................................................23 Appendices APPENDIX 1 - PLAN COSTS APPENDIX 2 - PLAN SKETCHES APPENDIX 3 - PRELIMINARY 230 KV SWITCHING STATION LAYOUTS APPENDIX 4 - ALTERNATE PLANS FOR CONNECTING GREEN LINE TO GARRISON OR TOWNSEND APPENDIX 5 - ALTERNATE PLANS FOR CONNECTING TONBRIDGE SS TO GREAT FALLS USING A POWER CIRCUIT BREAKER Green Line Report Rev B (9-June-11) Corporate Base Page 4 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE A. EXECUTIVE SUMMARY Tonbridge Power plans to construct a 230 kV transmission line (called the Green Line) in western Montana. The proposed Green Line will connect wind generation in Montana into the existing Colstrip to Taft 500 kV EHV transmission system. Initially two alternate interconnection points for the Green Line were proposed. One plan was to construct a Great Falls to Garrison 230 kV transmission line with one end terminated in the existing Great Falls 230 kV substation and the other end at the Garrison 500 kV substation. The second plan was to construct a Great Falls to Townsend 230 kV transmission line with one end terminated at Great Falls and the other in a new Townsend 500 kV substation. Tonbridge Power submitted two Points of Interconnection requests to the Bonneville Power Administration (BPA) for the Green Line project for a Feasibility Study. Both interconnection requests were alternate Points of Interconnection for the Green Line project. One of the two alternate Points of Interconnection was for an interconnection, for the Green Line, at the existing Garrison 500 kV substation. The other alternative was for an interconnection, for the Green Line, at a site near Townsend. At the existing Garrison 500 kV substation Tonbridge will install two 500/230 kV transformers to connect the 230 kV Green Line to the 500 kV network. The Townsend site will require the construction of a new Townsend 500/230 kV substation and will also require Tonbridge to install two 500/230 kV transformers at the new Townsend 500 kV substation to connect the Green Line to the 500 kV network. BPA completed a Line Loading Interconnection Feasibility Study (LLIFES) for the two Tonbridge Power Point of Interconnection requests November 15, 2010. The BPA feasibility study concluded the Green Line Plan of Service as originally provided by “the developer to get to the Points of Interconnection did not appear to be feasible.” As a result of the BPA feasibility study, Tonbridge Power asked Worley Parsons, Corp to develop a Plan of Service for the Green Line that would meet the BPA system requirements. The purpose of this report is to discuss the alternate Plans of Service for the Green Line developed by Worley Parsons that will meet the NERC, WECC, and member reliability standards, and, to recommend a preferred Plan of Service. Green Line Report Rev B (9-June-11) Corporate Base Page 5 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE B. INTRODUCTION The proposed “Green Line” will connect renewable wind energy in Central Montana to the existing northwest power grid. To connect the wind energy to the northwest power grid will require a Point of Interconnection on the Colstrip to Taft 500 kV transmission line. The two possible interconnection points being considered are the existing Garrsion, MT., 500 kV substation, or, at a new 500 kV substation to be constructed near Townsend, MT. Eight (8) alternate plans were developed for the proposed Green Line transmission line project; four for an interconnection at the existing Garrison 500 kV Substation, and four for an interconnection near Townsend. Each of the alternate plans was studied using the WECC 2014 Light Autumn load base case power system model. The wind turbine generation (WTG) modelled in the base cases for each plan included 300 MW at Hay Lake, and, 150 MW and 500 MW, at the Renewable Collector System (RCS) Substations A and B, respectively. The Green Line alternate plans developed in this study which are recommended are described in detail, along with the power system study results, in Sections G and H of this report. The other plans considered in this study are described in detail in Appendix 4 and 5 of this report. Two additional plans were developed after completion of the initial Green Line study: Plan 3A and Plan 9. Plan 3A is a variation of Plan 3. In Plan 3A, the Green Line is a singlecircuit, 600 MVA, transmission line from the Tonbridge SS to Garrison and there is only one 500/230 kV transformer at Garrison. Plan 9 extends the single-circuit, 600 MVA, Green Line from Garrison to Marias and the Tonbridge switching station is constructed at Maries. Green Line Report Rev B (9-June-11) Corporate Base Page 6 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE C. PLAN BASIS The report basis is the following: 1. PSSE Program Version 32.1.0 2. PSSE power system model and dynamics data originally came from WECC. 3. The results of the Power System Analysis also determined the reactive power requirements at each of the substations. Switching studies must be conducted to determine the maximum MVAR sizes of individual capacitor banks and shunt reactors that can be safely switched. 4. The rating for the proposed Phase Shifting Transformer (PST) and the MATL is 600 MVA. The rating for the 500/230 kV transformers 700 -800 MVA 5. PSSE Model Modifications were made based on the different plans detailed in the Report Sections detailing Plan 1 – Plan 8. Appendix 2 has some sketches to detail 6. The projected in-service for Green Line is estimated to 2013. 7. No cost estimates have been done for connections into the existing Great Falls 230 kV substation. A study will need to be performed to determine the impacts on the existing equipment at Great Falls: PCB’s, bus, switches, transmission lines, etc. 8. No costs were included for the ten miles of 230 kV connecting the proposed Tonbridge 230 kV Switching Station because that circuit is part of the MATL intertie which was looped into the new Tonbridge SS. 9. The existing Montana-Northwest (Mt-NW) path and the West-of-Garrison (WOG) network are both limited to 2200 MW east-to-west. As a result, in this study, generation at Colstrip was reduced to off-set the addition of Wind Turbine Generation (WTG) at Hay Lake and the RCS. Green Line Report Rev B (9-June-11) Corporate Base Page 7 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE D. PLAN ASSUMPTIONS When completing the PSSE calculations, the report assumptions are as follows: 1. WECC 2014 Light Autumn Case Loading – The Montana to Northwest Path is rated 2200 MW east to west and 1350 MW west to east; however, the 2200 MW east to west is only available during light load conditions. 2. The existing Montana-Northwest (Mt-NW) path and the West-of-Garrison (WOG) network are both limited to 2200 MW east-to-west. As a result, in this study, generation at Colstrip was reduced to off-set the addition of Wind Turbine Generation (WTG) at Hay Lake and the RCS. 3. Cost estimates are based on in-house pricing, except for the pricing provided by BPA. 4. The Phase Shifting Transformer rating was matched to the new MATL rating of approximately 600 MVA. 5. The two 500/230 kV transformers ratings were assumed to be in the 700 – 800 MVA range. 6. The proposed Green Line will need to sized to approximately 1600 MVA to accommodate the 600 MVA MATL line and 950 MW of Wind Turbine Generation. 7. The Wind Turbines for the Hay Lake will be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. For the study, it was assumed the Wind Turbines for the Renewable Collector System (RCS) would also be the Acciona 1530 units. 8. The existing Montana-Northwest (Mt-NW) path and the West-of-Garrison (WOG) network are both limited to 2200 MW east-to-west. As a result, in this study, Generation at Colstrip was reduced to off-set the Wind Turbine Generation (WTG) at Hay Lake and the RCS. 9. For outages of the Garrison-Taft 1 & 2 or the Townsend-Garrison 1 & 2, 500 kV transmission lines, with Green Line in-service and with 950 MW of WTG on-line, the existing Colstrip ATR would trip the remaining generation at Colstrip. 10. The existing Western Montana Remedial Action Scheme (RAS) can be modified to include tripping the RCS WTG. 11. Pricing for the AC/DC/AC back-to-back station has been requested from ABB. Green Line Report Rev B (9-June-11) Corporate Base Page 8 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE E. RECOMMENDED PLAN Based on the results of this study, Plan 3 would be the preferred alternative. Plan 3 consists of the following: 1. 2. 3. 4. 5. 6. 7. 8. Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. Loop the Montana-Alberta (MATL) 230 kV interconnection into the new Tonbridge 230 kV SS. At the new Tonbridge SS – Add a phase shifting transformer (PST) in the Tonbridge SS to Great Falls 230 kV circuit (MATL) to limit power flow into Great Falls. At the new Tonbridge SS – Install two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support Construct a 145 mile, double-circuit, 230 kV transmission line (the Green Line) from the new Tonbridge SS to the Garrison 500/230 kV substation. At Garrison add two 500/230 kV transformers to connect to the 230 kV Green Line to the 500 kV network. Garrison 230 kV bus - Install two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. To prevent system collapse and instability following major contingencies, the existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the Renewable Collector System (RCS) 650 MW of Wind Turbine Generation (WTG). Green Line Report Rev B (9-June-11) Corporate Base Page 9 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE F. RECOMMENDED PLAN (ALTERNATIVE) Based on discussions with Tonbridge Power, another version of Plan 3 was developed. Plan 3A is a variation of Plan 3 with the major change being the reduced capacity in the proposed Green Line from approximately 1600 MVA to 600 MVA. This change is based on expected available transmission capacity of about 600 MVA west of Garrison and the possibility the Renewable Collector System (RCS), 650 MW of wind generation, may not be built. Plan 3A consists of the following: 1. 2. 3. 4. 5. 6. 7. Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. Loop the Montana-Alberta (MATL) 230 kV interconnection into the new Tonbridge 230 kV SS. At the new Tonbridge SS – Add a phase shifting transformer (PST) in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. At the new Tonbridge SS – Install two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support Construct a 145 mile, single-circuit, 600 MVA, 230 kV transmission line (the Green Line) from the new Tonbridge SS to the Garrison 500/230 kV substation. At Garrison add one 500/230 kV transformers to connect to the 230 kV Green Line to the 500 kV network. Garrison 230 kV bus - Install two, 230 kV, 80 MAVR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Green Line Report Rev B (9-June-11) Corporate Base Page 10 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE G. PLAN 3 - DETAILED DESCRIPTION G.1 Plan 3 Summary Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. Loop the Montana-Alberta (MATL) 230 kV interconnection into the new Tonbridge 230 kV SS and add a phase shifting transformer (PST) in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. Construct a 145 mile, double-circuit, 230 kV transmission line (the Green Line) from the new Tonbridge SS to the Garrison 500/230 kV substation. At Garrison add two 500/230 kV transformers to connect to the Green Line to the 500 kV network. G.2 Plan 3 Details Plan 3 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV (MATL) transmission line will be looped into the new 230 kV Tonbridge SS and a phase shifting transformer (PST) will be installed in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 145 mile, double-circuit, 230 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Garrison 500/230 kV substation. At Garrison two 500/230 kV transformers will be added to connect the Green Line to the 500 kV network. The Green Line facilities for Plan 3, modelled in the 2014 Light Autumn Load power system study, included the following: 1. 2. 3. 4. 5. 6. 7. Green Line Report Rev B (9-June-11) Construction of a new Tonbridge 230 kV Switching Station (SS) at a site approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Tonbridge SS – Install 230kV Phase-Shifting Transformer (PST) in 230 kV circuit (MATL) to Great Falls. Construct a Tonbridge SS-Garrison 230 kV transmission line (double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA). At Garrison – Add two 500/230 kV transformers. Tonbridge SS – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Garrison Green Line 230 kV bus - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Corporate Base Page 11 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 8. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). 9. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/0.59 MVAR. 10. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). G.3 Plan 3 Impact on Area Voltages The power system analysis results for indicated that for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, the addition of the Green Line, with 950 MW of Wind Turbine Generation (WTG), would have no significant voltage impact. The power system analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated the addition of the Green Line, with 950 MW of WTG, would have no significant voltage impact. The power system contingency analysis for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, compared the impact of an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR), on area voltages, with the Green Line in-service, and with for four different levels of WTG on-line: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated an outage of the Garrison- Taft 1 & 2, 500 kV transmission lines, with the Green Line in-service and 950 MW of WTG on-line, would not have a significant impact on area voltages. The power system contingency analysis for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, compared the impact of an outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR), on area voltages with the Green Line in-service, and, for four base cases different levels of WTG on-line: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated the outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, with the Green Line in-service and 950 MW of WTG on-line, would not have a significant impact on area voltages. G.4 Plan 3 Impact on Area Transmission Services The power system analysis of the impact of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated there would not be any additional overloaded transmission Green Line Report Rev B (9-June-11) Corporate Base Page 12 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line in-service. The power system analysis included base cases with the Green Line in-service and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The power system contingency analysis of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, and 950 MW of WTG, and the Garrison-Taft 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), the Hot Springs 500/230 kV transformer would overload approximately 117 per cent. The study also indicated tripping the 300 MW of WTG at Hay Lake off-line, with the Green Line in-service, and, with the Garrison-Taft 1 & 2, 500 kV lines out, the Hot Springs 500/230 kV transformer would still overload approximately 104 per cent. To reduce the power flow in the Hot Springs 500/230 kV transformer below the Rate A rating of 942 MVA, with the Green Line in-service, and the Garrison-Taft 1 & 2, 500 kV lines out, will require tripping of the 650 MW of WTG in the RCS. The John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent with the Green Line in-service and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the impact of an outage of the TownsendGarrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the case with the Green Line in-service and with 950 MW of WTG would not have any significant transmission system overloads. The study also looked at the Green Line in-service and with four levels of WTG on-line: 950 MW, 650 MW (300 MW at Hay lake tripped off), 300 MW (650 MW at RCS tripped off), and with all 950 MW of WTG off. The John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, overloaded approximately 4 percent with the Green Line in-service and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. G.5 Plan 3 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped concurrently with the Colstrip units. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping of the 650 MW of WTG in the RCS. The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 and 2, 500 kV or the Townsend-Garrison, 1 & 2, 500kV transmission lines may not require the reduction of the 950 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 13 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE G.6 Plan 3 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 285 14 4.7 % Green Line #1 (Tonbridge-Garrison) 463 439 24 5.2 % Green Line #2 (Tonbridge-Garrison) 463 439 24 5.2 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformers (PST) at Substation 120S. G.7 Plan 3 Costs Plan 3 costs are listed in Appendix 1. G.8 Plan 3 Conclusions Plan 3 with the proposed new Tonbridge SS-Garrison, double-circuit, 230 kV transmission line will provide a connection hub for WTG in northern Montana. However, the study results indicated an outage of Garrison-Taft, 1 & 2, 500 kV transmission lines, will require the RCS, 650 MW of WTG to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and maintain system stability. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 14 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE H. PLAN 3A - DETAILED DESCRIPTION H.1 Plan 3A Summary Plan 3A is a variation of Plan 3 based on the expected available transmission capacity west of Garrison and the assumption the Renewable Collector System (RCS) 650 MW of wind generation may not be built. Plan 3A, like Plan 3, would also construct a new 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation, loop the Montana-Alberta (MATL) 230 kV interconnection into the new Tonbridge 230 kV SS, and add a phase shifting transformer (PST) in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. However, Plan 3 A would construct a 145 mile, single-circuit, 600 MVA, 230 kV (1,590,000 ACSR) transmission line (the Green Line) from the new Tonbridge SS to the Garrison 500/230 kV substation. At the Garrison 500 kV substation, Tonbridge would add one 500/230 kV transformer to connect to the Green Line to the 500 kV network. H.2 Plan 3A Details Plan 3A includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV (MATL) transmission line will be looped into the new 230 kV Tonbridge SS and a phase shifting transformer (PST) will be installed in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 145 mile, single-circuit, 600 MVA, 230 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Garrison 500/230 kV substation. At Garrison, one 500/230 kV transformer will be added to connect the Green Line to the 500 kV network. The Green Line facilities for Plan 3A, as modelled in the 2014 Light Autumn Load power system study, included the following: 1. 2. 3. 4. 5. Green Line Report Rev B (9-June-11) Construction of a new Tonbridge 230 kV Switching Station (SS) at a site approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Tonbridge SS – Install 230kV Phase-Shifting Transformer (PST) in 230 kV circuit (MATL) to Great Falls. Construct a Tonbridge SS-Garrison 230 kV transmission line (single-circuit, rated at approximately 600 MVA – 1,590,000 ACSR conductor). At Garrison – Add one 500/230 kV transformer, rated approximately 600 MVA. Corporate Base Page 15 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 6. Tonbridge SS – Add two, 230 kV, 80 MAVR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 7. Garrison 500 kV substation Green Line 230 kV bus - Add two, 230 kV, 80 MAVR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 8. The Colstrip generation Unit 2 was reduced 330 MW to accommodate the addition of the Hay Lake 300 MW of Wind Turbine Generation (WTG). 9. The Hay Lake Wind Turbines were assumed to be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. 10. Contingency studies assumed the Colstrip ATR would trip Colstrip units 1, 3, and 4 (unit 2 is off-line to accommodate the addition of Hay Lake 300 MW of WTG). H.3 Plan 3A Impact on Area Voltages The power system analysis results for indicated that for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, with 300 MW of Wind Turbine Generation (WTG) at Hay Lake and a transfer of 300 MW from Alberta to PGE, the addition of the Green Line, would have no significant high-voltage impact. The power system analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, with 300 MW of Wind Turbine Generation (WTG) at Hay Lake and a transfer of 300 MW from Alberta to PGE, indicated the addition of the Green Line, would have no significant low-voltage impact. The power system contingency analysis results for voltages less than 0.95 per unit (PU), also included the outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR). The contingency analysis examined the voltage impact for the out for three different system conditions: (1) With 300 MW WTG at Hay Lake, and with a transfer of 300 MW from Alberta to PGE, (2) With 300 MW WTG at Hay Lake, and (3) With 0 MW WTG at Hay Lake, and with 0 MW transfer from Alberta to PGE. The study results indicated an outage of the Garrison- Taft 1 & 2, 500 kV transmission lines, with the Green Line in-service and for each of the system conditions studied, would not have a significant impact on area low-voltages. The power system contingency analysis results for voltages less than 0.95 per unit (PU), also included the outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR). The contingency analysis examined the voltage impact for the out for three different system conditions: (1) With 300 MW WTG at Hay Lake, and with a transfer of 300 MW from Alberta to PGE, (2) With 300 MW WTG at Hay Lake, and 0 MW transfer from Alberta to PGE, and (3) With 0 MW WTG at Hay Lake, and with 0 MW transfer from Alberta to PGE. The study results indicated an outage of the Townsend-Garrison, 1 & 2, 500 kV Green Line Report Rev B (9-June-11) Corporate Base Page 16 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE transmission lines, with the Green Line in-service and for each of the system conditions studied, would not have a significant impact on area low-voltages. H.4 Plan 3A Impact on Area Transmission Services The power system analysis of the impact of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line in-service. The power system analysis included base cases with the Green Line in-service and with three different system conditions: (1) With 0 MW WTG at Hay Lake, and with 0 MW transfer from Alberta to PGE, (2) With 300 MW WTG at Hay Lake, and 0 MW transfer Alberta to PGE, (3) With 300 MW WTG at Hay Lake, and 300 MW transfer Alberta to PGE. The power system contingency analysis of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, included the outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR). The contingency analysis included cases with the proposed Green Line in-service and the Garrison-Taft 1&2, 500 kV lines outaged, for three different system conditions: (1) With 300 MW WTG at Hay Lake and 300 MW transfer Alberta to PGE, (2) With 300 MW WTG at Hay Lake, and 0 MW transfer Alberta to PGE, (3) With 0 MW WTG at Hay Lake, and with 0 MW transfer from Alberta to PGE. The results of the contingency studies, with the Green Line inservice, and with an outage of the Garrison-Taft 1&2, 500 kV lines, for the system conditions studied, indicated there would not be any new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, included the outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR). The contingency analysis included cases with the proposed Green Line in-service and the Townsend-Garrison 1&2, 500 kV lines outaged, for three different system conditions: (1) With 300 MW WTG at Hay Lake and 300 MW transfer Alberta to PGE, (2) With 300 MW WTG at Hay Lake, and 0 MW transfer Alberta to PGE, (3) With 0 MW WTG at Hay Lake, and with 0 MW transfer from Alberta to PGE. The results of the contingency studies, with the Green Line in-service, and with an outage of the Townsend-Garrison 1&2, 500 kV lines, for the system conditions studied, indicated there would not be any new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Green Line Report Rev B (9-June-11) Corporate Base Page 17 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE H.5 Plan 3A Transient Analysis The initial transient analysis indicated that for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, or the Townsend-Garrison, 1 & 2, 500kV transmission lines, with the Colstrip ATR in effect, the generation at Hay Lake would remain stable. H.6 Plan 3A Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (MATL120S-Hay Lake)* 196 191 14 2.6 % MATL (Hay Lake-Tonbridge)* 491 452 39 7.9 % Green Line (Tonbridge-Garrison) 452 414 38 8.4 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformers (PST) at Substation 120S. H.7 Plan 3A Costs Plan 3A costs are listed in Appendix 1. H.8 Plan 3A Conclusions Plan 3A with the proposed new Tonbridge SS-Garrison, single-circuit, 230 kV, 600 MVA, transmission line will provide a path for WTG in northern Montana to be connected into the 500 kV network. The study results indicated that an outage of either the Garrison-Taft, 1 & 2, 500 kV transmission lines, or the Townsend-Garrison1 &2, 500 kV lines, with the green Line in-service, with 300 MW of WTG at Hay Lake, and a 300 MW transfer from Alberta to PGE, would not significantly impact the Montana or Northwestern systems. Green Line Report Rev B (9-June-11) Corporate Base Page 18 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE I. CONCLUSION AND RECOMMENDATIONS Based on the results of this study, Plan 3 would be the preferred alternative. Plan 3 includes the construction of a new Tonbridge 230 kV Switching Station (SS) and the construction of a 145 mile, 1600 MVA, 230 kV transmission line (Green Line) from the new Tonbridge SS to Garrison. At Garrison, Tonbridge will install two 500/230 kV transformers to connect the Green Line to the 500 kV network. The interconnection at Garrison will eliminate or sustainably reduce the impact of outages of the Broadview-Townsend 1 & 2, and the Townsend-Garrison 1 & 2, 500 kV lines. The new Tonbridge SS will serve as a hub for the 300 MW of wind turbine generation at Hay Lake and the 650 MW of wind turbine generation in the Renewable Collector System (RCS) in northern Montana. However, recent information indicated the proposed RCS facility may not be built. Based on that information, Plan 3A would be the preferred alternative. The Plan 3A Green Line consists of a 145 mile, single-circuit, 600MVA, 230 kV transmission line and will require only one 500/230 kV transformer at the Garrison 500 kV substation. Green Line Report Rev B (9-June-11) Corporate Base Page 19 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE J. SWITCHING STUDY A Switching Study was performed to determine the voltage increase or decrease caused by switching the capacitors and reactors associated with the MATL, the Green Line, and the Tonbridge Switching Station (SS). The results of the Switching study for the Marias 230 kV bus, the Tonbridge SS 230 kV bus, and the Green Line 230 kV bus at Garrison are tabulated below. MARIAS SWITCHING STATION BUS NAME BASE CASE NO CAP/REACTOR SWITCH SWITCH SWITCH 160 MVAR CAP BK 80 MVAR CAP BK 60 MVAR CAP BK VOLT (PU) VOLT (PU) DELTA (PU) VOLT (PU) DELTA (PU) VOLT (PU) DELTA (PU) MARIAS_N 230KV 1.2171 1.4354 0.2183 1.3202 0.1031 1.2934 0.0763 MARIAS 1.0129 1.1131 0.1002 1.0609 0.0480 1.0485 0.0356 MARIAS_S 230KV 1.0274 1.1577 0.1303 1.0896 0.0622 1.0735 0.0461 The Switching Study results for the Marias Switching Station are tabulated on the above table. As can be seen on the table, switching a 160 MVAR capacitor bank at the Marias 230 kV bus will cause a voltage rise of 21.8 % on the Marias_N 230 kV bus, 10 % on Marias, and 13 % on Marias_S. Switching a 80 MVAR capacitor bank instead of the 160 MVAR bank will cause voltage increases of 10.3 % on the Marias_N 230 kV bus, 4.8 % on Marias, and 6.2 % on Marias_S. Switching a 60 MVAR capacitor bank instead of the 160 MVAR bank will cause voltage increases of 7.6 % on the Marias_N 230 kV bus, 3.6 % on Marias, and 4.6 % on Marias_S. Green Line Report Rev B (9-June-11) Corporate Base Page 20 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE TONBRIDGE SWITCHING STATION BUS NAME BASE CASE NO CAP/REACTOR SWITCH SWITCH 60 MVAR CAP BK 80 MVAR LINE REACTOR VOLT (PU) VOLT (PU) DELT A (PU) VOLT (PU) DELTA (PU) TONBRIDGE SS 230KV 0.9604 0.9920 0.0316 0.9211 -0.0393 GF PST 0.9351 0.9539 0.0188 0.9118 -0.0233 MARIAS_S 230KV 1.1306 1.1340 0.0034 1.1262 -0.0044 MARIAS 230KV 1.0398 1.0588 0.0190 1.0161 -0.0237 MARIAS_N 230KV 1.0920 1.1368 0.0448 1.0369 -0.0551 The Switching Study results for the Tonbridge Switching Station are tabulated on the above table. As can be seen on the table, switching a 60 MVAR capacitor bank at the Tonbridge SS 230 kV bus will cause a voltage rise of approximately 3.2 %. Likewise, switching an 80 MVAR line reactor will decrease the Tonbridge 230 kV bus voltage by 3.9 %. GREEN LINE 230KV BUS AT GARRISON 500 KV SUBSTATION BUS NAME GRN LINE 230KV Green Line Report Rev B (9-June-11) BASE CASE NO CAP/REACTOR SWITCH SWITCH 60 MVAR CAP BK 80 MVAR LINE REACTOR VOLT (PU) VOLT (PU) DELT A (PU) VOLT (PU) DELTA (PU) 1.0070 1.027 8 0.0208 0.9806 -0.0264 Corporate Base Page 21 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE GARRISON 500KV 1.0695 1.077 4 0.0079 1.0593 -0.0102 TONBRIDGE SS 230KV 1.0039 1.008 2 0.0043 0.9985 -0.0054 The Switching Study results for the Tonbridge Green Line 230 kV bus at the Garrison 500 kV substation are tabulated on the above table. As can be seen on the table, switching a 60 MVAR capacitor bank at the Green Line 230 kV bus at Garrison will cause a voltage rise of approximately 2.1 %. Likewise, switching an 80 MVAR line reactor will decrease the Green Line 230 kV bus at Garrison voltage by 2.6 %. Green Line Report Rev B (9-June-11) Corporate Base Page 22 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE K. REFERENCES “The Green Line Pre-Feasibility Study”, Prepared by Big Sky Green Power, Spring 2010. The “Line Load Interconnection Feasibility Study (LLFES) for Requests L0314 and L0315 Agreement Nos. 10TX-14636 & 10TX-14637”, Prepared by the Bonneville Power Administration November 15, 2010. Green Line Report Rev B (9-June-11) Corporate Base Page 23 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Appendix 1 - Green Line Report Rev B (9-June-11) Plan Costs Corporate Base Page 24 Project: Tonbridge Location: Montana Plan No Initial Cost Comparison 1 2 3 3A 4 5 6 7 8 9 6/7/2011 / 9:42 AM Date: May 2011 Appendix 1 $260,140,608 $301,228,432 $272,140,608 $259,635,608 $313,228,432 $260,645,608 $301,733,432 $373,840,608 $403,928,432 $343,635,608 1 of 1 Report Spreadsheets RR2.xls Project: Tonbridge Location: Montana Cost per unit $ $ $ $ $ $ $ $ $ $ $ $ $ 6/7/2011 / 9:47 AM Date: May 2011 Appendix 1 1,200,000 12,000,000 505,000 2,625,108 4,000,000 2,100,000 146,000 2,444,000 756,000 1,495,000 1,384,000 1,560,000 10,120,500 Unit Mile Transformer Breaker (230 kV) Breaker (500 kV) Reactor (80 MVAR) Reactor (60 MVAR) Garrison Substation Fiber Optic Repeater Stations Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s 1 of 1 Report Spreadsheets RR2.xls Two 230 kV PCB’s at Garrison One 500 kV PCB at Garrison (with OH’s) Add two 230kV, 80 MVAR Reactors at Garrison Add two 230kV, 80 MVAR Reactors at Great Falls Add three 230kV, 60 MVAR Capacitor banks at Garrison $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Great Falls $146,000 Garrison Substation $2,444,000 Fiber Optic Repeater Stations $756,000 Great Falls Substation $1,495,000 Hay Lake WTG (300MW) $1,384,000 RCS Site A $1,560,000 RCS Site B $10,120,500 Total Comm & Control with OH’s $260,140,608 $1,010,000 $2,625,108 $8,000,000 $8,000,000 $6,300,000 6/7/2011 / 9:42 AM 1 of 1 Notes 1 Costs estimated by Bonneville Power Administration (BPA). 2013 2013 2013 2013 2013 2013 Total: TOTAL 2013 2013 2013 2013 2013 2013 $174,000,000 Construct 145 mile, 230 kV transmission line $12,000,000 Construct 230 kV Switchyard at Great Falls $24,000,000 Add two 500/230 kV transformers at Garrison 2013 2013 2013 ITEM COST Appendix 1 YEAR Plan 1 Project: Tonbridge Location: Montana 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Comm. & Control Equip. Req’d by BPA Green Line - Great Falls to Garrison 230 kV Connect to existing Great Falls sub via jumpers ITEM DESCRIPTION Date: May 2011 $2,404,000 $2,444,000 $889,000 $1,495,000 $1,384,000 $1,560,000 $30,784,000 $301,228,432 2013 2013 2013 2013 2013 2013 Total: TOTAL: Construct 115 mile, 230 kV transmission line Construct 230 kV Switchyard at Great Falls Add 2,500/230 kV transformers at Townsend Add two 230 kV PCB’s at Townsend Construct a 500 kV, 8 PCB, substation at Townsend (with OH’s) Add two 80 MVAR Reactors at Garrison Add two 80 MVAR Reactors at Great Falls Add three 60 MVAR Capacitor banks at Garrison Add three 60 MVAR Capacitor banks at Great Falls Garrison Substation Typical MW repeaters for SONET loop Garrison to Townsend Townsend Sub Fiber Optics Townsend to Great Falls Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s ITEM Appendix 1 6/7/2011 / 9:43 AM 1 of 1 Costs estimated by Bonneville Power Administration (BPA). $8,000,000 $8,000,000 $6,300,000 $6,300,000 $868,000 $12,636,000 2013 2013 2013 2013 2013 2013 Notes 1 $138,000,000 $12,000,000 $24,000,000 $1,010,000 $43,154,432 COST 2013 2013 2013 2013 2013 YEAR Plan 2 Project: Tonbridge Location: Montana Communication & Control 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Green Line - Great Falls to Garrison 230 kV ITEM DISC Date: May 2011 Appendix 1 1 of 1 COST ITEM $174,000,000 Construct 145 mile, 230 kV transmission line $12,000,000 Construct Tonbridge 230 kV Switching Station (SS) 10 miles north of Great Falls $12,000,000 Install 230 kV Phase-shifting transformer at Tonbridge SS $24,000,000 Add two 500/230 kV transformers at Garrison $1,010,000 Add two 230 kV PCB’s at Garrison $2,625,108 One 500 kV PCB at Garrison (with OH’s) $8,000,000 Add two 230kV, 80 MVAR Reactors at Garrison $8,000,000 Add two 230kV, 80 MVAR Reactors at Tonbridge SS $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Garrison $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Tonbridge SS $146,000 Garrison Substation $2,444,000 Fiber Optic Repeater Stations $756,000 Great Falls Substation $1,495,000 Hay Lake WTG (300MW) $1,384,000 RCS Site A $1,560,000 RCS Site B $10,120,500 Total Comm & Control with OH’s $272,140,608 Costs estimated by Bonneville Power Administration (BPA). 6/7/2011 / 9:44 AM Notes 1 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: YEAR 2013 2013 Plan 3 Project: Tonbridge Location: Montana Communication & Control 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Install in 230kV connection to Great Falls ITEM DESCRIPTION Green Line – Tonbridge SS to Garrison 230 kV New Tonbridge 230 kV Switching Station Date: May 2011 Notes 1 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: YEAR 2013 2013 COST ITEM $174,000,000 Construct 145 mile, 230 kV transmission line $12,000,000 Construct Tonbridge 230 kV Switching Station (SS) 10 miles north of Great Falls $12,000,000 Install 230 kV Phase-shifting transformer at Tonbridge SS $12,000,000 Add one 500/230 kV transformer at Garrison $505,000 Add one 230 kV PCB at Garrison $2,625,108 One 500 kV PCB at Garrison (with OH’s) $8,000,000 Add two 230kV, 80 MVAR Reactors at Garrison $8,000,000 Add two 230kV, 80 MVAR Reactors at Tonbridge SS $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Garrison $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Tonbridge SS $146,000 Garrison Substation $2,444,000 Fiber Optic Repeater Stations $756,000 Great Falls Substation $1,495,000 Hay Lake WTG (300MW) $1,384,000 RCS Site A $1,560,000 RCS Site B $10,120,500 Total Comm & Control with OH’s $259,635,608 Costs estimated by Bonneville Power Administration (BPA). Plan 3A Communication & Control Install in 230kV connection to Great Falls ITEM DESCRIPTION Green Line – Tonbridge SS to Garrison 230 kV New Tonbridge 230 kV Switching Station 1 1 1 1 1 1 1 1 Notes 6/7/2011 / 9:44 AM Appendix 1 1 of 1 Construct 115 mile, 230 kV transmission line Construct new 230 kV Tonbridge Switching Station Add 230kV PST in circuit to Great falls Add two 500/230 kV transformers at Townsend Add two 230 kV PCB’s at Townsend Construct a 500 kV, 8 PCB, substation at Townsend (with OH’s) Add two 230kV, 80 MVAR Reactors at Townsend Add two 230kV, 80 MVAR Reactors at Great Falls Add three 230kV, 60 MVAR Capacitor banks at Townsend Add three 230kV, 60 MVAR Capacitor banks at Great Falls Garrison Substation Typical MW repeaters for SONET loop Garrison to Townsend Townsend Sub Fiber Optics Townsend to Great Falls Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s ITEM Costs estimated by Bonneville Power Administration (BPA). $138,000,000 $12,000,000 $12,000,000 $24,000,000 $1,010,000 $43,154,432 $8,000,000 $8,000,000 $6,300,000 $6,300,000 $868,000 $12,636,000 $2,404,000 $2,444,000 $889,000 $1,495,000 $1,384,000 $1,560,000 $30,784,000 $313,228,432 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: Notes 1 COST YEAR Plan 4 Project: Tonbridge Location: Montana Communication & Control 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Green Line – Tonbridge SS to Townsend 230 kV New Tonbridge SS, 10 miles north of Great Falls ITEM DISC Date: May 2011 Costs estimated by Bonneville Power Administration (BPA). 6/7/2011 / 9:44 AM Notes 1 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: 1 of 1 $174,000,000 Construct 145 mile, 230 kV transmission line $12,000,000 Construct Tonbridge 230 kV Switching Station (SS) 10 miles north of Great Falls $505,000 Install 230 kV PCB at Tonbridge SS $24,000,000 Add two 500/230 kV transformers at Garrison $1,010,000 Add two 230 kV PCB’s at Garrison $2,625,108 One, 500 kV PCB at Garrison (with OH’s) $8,000,000 Add two 230kV, 80 MVAR Reactors at Garrison $8,000,000 Add two 230kV, 80 MVAR Reactors at Tonbridge SS $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Garrison $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Tonbridge SS $146,000 Garrison Substation $2,444,000 Fiber Optic Repeater Stations $756,000 Great Falls Substation $1,495,000 Hay Lake WTG (300MW) $1,384,000 RCS Site A $1,560,000 RCS Site B $10,120,500 Total Comm & Control with OH’s $260,645,608 2013 2013 ITEM COST Appendix 1 YEAR Plan 5 Project: Tonbridge Location: Montana Communication & Control 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Install in 230kV connection to Great Falls Green Line – Tonbridge SS to Garrison 230 kV New Tonbridge 230 kV Switching Station ITEM DISC Date: May 2011 2013 2013 2013 2013 Total: TOTAL: 6/7/2011 / 9:45 AM 1 of 1 $2,404,000 $2,444,000 $889,000 $1,495,000 $1,384,000 $1,560,000 $30,784,000 $301,733,432 Costs estimated by Bonneville Power Administration (BPA). Townsend Sub Fiber Optics Townsend to Great Falls Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s $8,000,000 $8,000,000 $6,300,000 $6,300,000 $868,000 $12,636,000 2013 2013 2013 2013 2013 2013 Notes 1 Construct 115 mile, 230 kV transmission line Construct new 230 kV Tonbridge SS Install 230 kV PCB at Tonbridge SS Add two 500/230 kV transformers at Townsend Add two 230 kV PCB’s at Townsend Construct a 500 kV, 8 PCB, substation at Townsend (with OH’s) Add two 230kV, 80 MVAR Reactors at Townsend Add two 230kV, 80 MVAR Reactors at Tonbridge SS Add three 230kV, 60 MVAR Cap banks at Townsend Add three 230kV, 60 MVAR Cap banks at Tonbridge SS Garrison Substation Typical MW repeaters for SONET loop Garrison to Townsend ITEM $138,000,000 $12,000,000 $505,000 $24,000,000 $1,010,000 $43,154,432 COST Appendix 1 2013 2013 2013 2013 2013 2013 YEAR Plan 6 Project: Tonbridge Location: Montana Communication & Control 1 1 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Green Line – Tonbridge SS to Townsend 230 kV New Tonbridge SS, 10 miles north of Great Falls Install in 230kV connection to Great Falls ITEM DISC Date: May 2011 ITEM Appendix 1 1 of 1 $290,000,000 Construct 145 mile, 500 kV transmission line $12,000,000 Construct Tonbridge 230 kV Switching Station (SS) 10 miles north of Great Falls $12,000,000 Install 230 kV Phase-shifting transformer at Tonbridge SS $24,000,000 Add two 500/230 kV transformers at Tonbridge SS $1,010,000 Add two additional 230 kV PCB’s at Tonbridge SS $2,625,108 One 500 kV PCB at Garrison (with OH’s) $8,000,000 Add two 230kV, 80 MVAR Reactors at Tonbridge SS $6,300,000 Add three 230kV, 60 MVAR Capacitor banks at Tonbridge SS $146,000 Garrison Substation $2,444,000 Fiber Optic Repeater Stations $756,000 Great Falls Substation $1,495,000 Hay Lake WTG (300MW) $1,384,000 RCS Site A $1,560,000 RCS Site B $10,120,500 Total Comm & Control with OH’s $373,840,608 COST Costs estimated by Bonneville Power Administration (BPA). 6/7/2011 / 9:45 AM Notes 1 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: 2013 2013 YEAR Plan 7 Project: Tonbridge Location: Montana Communication & Control Install in 230kV circuit to Great Falls 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls Green Line – Tonbridge SS to Garrison 500 kV New Tonbridge 230 kV Switching Station ITEM DISC Date: May 2011 $2,404,000 $2,444,000 $889,000 $1,495,000 $1,384,000 $1,560,000 $30,784,000 $403,928,432 2013 2013 2013 2013 2013 2013 Total: TOTAL: 6/7/2011 / 9:46 AM Appendix 1 Townsend Sub Fiber Optics Townsend to Great Falls Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s 1 of 1 Add two 500 kV, 120 MVAR Reactors at Townsend Add two 230 kV, 80 MVAR Reactors at Tonbridge SS Add three 230kV, 60 MVAR Cap banks at Tonbridge SS Garrison Substation Typical MW repeaters for SONET loop Garrison to Townsend ITEM Construct 115 mile, 500 kV transmission line Construct new 230 kV Tonbridge SS Add 2,500/230 kV transformers at Tonbridge SS Install 230 kV Phase-shifting transformer at Tonbridge SS Add two additional 230 kV PCB’s at Tonbridge SS Construct a 500 kV, 8 PCB, substation at Townsend (with OH’s) Costs estimated by Bonneville Power Administration (BPA). $13,000,000 $8,000,000 $6,300,000 $868,000 $12,636,000 2013 2013 2013 2013 2013 Notes 1 COST $230,000,000 $12,000,000 $24,000,000 $12,000,000 $1,010,000 $43,154,432 YEAR 2013 2013 2013 2013 2013 2013 Plan 8 Project: Tonbridge Location: Montana Communication & Control Install in 230kV circuit to Great Falls 1 1 1 1 1 1 1 1 1 1 Notes Report Spreadsheets RR2.xls ITEM DESCRIPTION Green Line – Tonbridge SS to Townsend 500 kV New Tonbridge SS, 10 miles north of Great Falls Date: May 2011 Notes 1 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 2013 Total: TOTAL: 2013 YEAR 2013 2013 Plan 9 Loop Bole-Conrad 230 kV line into Tonbrideg/Marias SS Add one 500/230 kV transformer at Garrison Add one 230 kV PCB at Garrison One 500 kV PCB at Garrison (with OH’s) Add two 230kV, 80 MVAR Reactors at Garrison Add two 230kV, 80 MVAR Reactors at Tonbridge SS Add three 230kV, 60 MVAR Capacitor banks at Garrison Add three 230kV, 60 MVAR Capacitor banks at Tonbridge SS Garrison Substation Fiber Optic Repeater Stations Great Falls Substation Hay Lake WTG (300MW) RCS Site A RCS Site B Total Comm & Control with OH’s Costs estimated by Bonneville Power Administration (BPA). $12,000,000 $12,000,000 $505,000 $2,625,108 $8,000,000 $8,000,000 $6,300,000 $6,300,000 $146,000 $2,444,000 $756,000 $1,495,000 $1,384,000 $1,560,000 $10,120,500 $343,635,608 COST ITEM $246,000,000 Construct 220 mile, 230 kV transmission line $12,000,000 Construct Tonbridge/Marias 230 kV Switching Station (SS) at Marias 85 miles north of Great Falls $12,000,000 Install 230 kV Phase-shifting transformer at Tonbridge/Marias SS Communication & Control Install in MATL 230kV connection to Great Falls ITEM DESCRIPTION Green Line – Tonbridge SS to Garrison 230 kV New Tonbridge 230 kV Switching Station 1 1 1 1 1 1 1 1 Notes TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Appendix 2 - Green Line Report Rev B (9-June-11) Plan Sketches Corporate Base Page 26 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Appendix 3 Layouts Green Line Report Rev B (9-June-11) Preliminary 230 kV Switching Station Corporate Base Page 27 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Appendix 4 - Alternate Plans For Connecting Green Line to Garrison or Townsend Green Line Report Rev B (9-June-11) Corporate Base Page 28 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 1 - DETAILED DESCRIPTION Plan 1 Summary Construct a 145 mile, double circuit, 230 kV transmission line (the Green Line) from the Great Falls 230 kV substation to the Garrison 500 kV substation. At Garrison add two 500/230 kV transformers to connect the Green Line to the 500 kV network. At the Great Falls 230 kV substation, construct a new 230 kV switchyard adjacent to the existing Great Falls switch yard and connect the new 230 kV switch yard to the existing Great Falls 230 kV switch yard using 230 kV jumpers. Terminate the new Green Line in the new 230 kV switch yard at Great Falls. Plan 1 Details Plan 1 includes the construction of a 145 mile, double-circuit, 230 kV transmission line from the existing Great Falls 230 kV substation to the Garrison 500 kV substation. The new transmission line, referred to as the “Green Line”, will provide a path for renewable energy from wind generation facilities in Montana to the northwest power grid. The Green Line facilities for Plan 1 as modelled in the 2014 Light Autumn Load base case included the following: 1. Construction of a new 230 kV switchyard at Great Falls connected to existing Great Falls 230 Substation via jumpers. 2. Construction of a 230 kV transmission line (Green Line) from Great Falls to Garrison 500 kV substation. 3. Construction of a new Great Falls to Garrison 230 kV transmission line assumed to be a double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA. 4. At Great Falls - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 5. At Garrison 500 kV sub – Add two 500/230 kV transformers. 6. At new Garrison Green Line 230 kV bus - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 7. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). Green Line Report Rev B (9-June-11) Corporate Base Page 29 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 8. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. 9. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (Colstrip units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 1 Impact on Area Voltages The power system analysis results for indicated that for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, the addition of the Green Line, and 950 MW of Wind Turbine Generation (WTG), would have no significant voltage impact. The power system analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated the addition of the Green Line, and 950 MW of WTG, would have no significant voltage impact The power system analysis for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, compared the impact of an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR), on area voltages, with the Green Line in-service, and with for four different levels of WTG on-line: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated an outage of the Garrison- Taft 1 & 2, 500 kV transmission lines, with the Green Line in-service and 950 MW of WTG on-line, would not have a significant impact on area voltages. The power system analysis for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, compared the impact of an outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR), on area voltages with the Green Line in-service, and, for four base cases different levels of WTG on-line: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated the outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, with the Green Line in-service and 950 MW of WTG on-line, would not have a significant impact on area voltages. Plan 1 Impact on Area Transmission Lines The power system analysis of the impact of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line in-service. The power system analysis included base case with the Green Line Green Line Report Rev B (9-June-11) Corporate Base Page 30 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE in-service and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The power system contingency analysis of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, with 950 MW of WTG, and the Garrison-Taft 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), the Hot Springs 500/230 kV transformer would overload approximately 119 per cent. The study also indicated tripping the 300 MW of WTG at Hay Lake off-line, with the Green Line in-service and the Garrison-Taft 1 & 2, 500 kV lines out, the Hot Springs 500/230 kV transformer would still overload approximately 109 per cent. To totally reduce the power flow in the Hot Springs 500/230 kV transformer below the Rate A rating of 942 MVA, with the Green Line in-service and the Garrison-Taft 1 & 2, 500 kV lines out, will require the tripping of the 650 MW of WTG in the RCS. Northwestern’s John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent with the Green Line in-service and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system analysis of the impact of an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the case with the Green Line in-service and with 950 MW of WTG would not have any significant transmission system overloads. Northwestern’s John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, overloaded approximately 4 percent with the Green Line in-service and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 1 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped concurrently with the Colstrip units to maintain system stability. The existing Western Montana Remedial Action Scheme (RAS) will need to be expanded to include tripping the RCS 650 MW of WTG. The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 & 2, or the Townsend-Garrison, 1 & 2, 500kV transmission lines may not require the reduction of the 950 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 31 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 1 Transmission LIne Losses Sending End Receivin g End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Great Falls)* 299 284 15 5.0 % Green Line #1 (Great Falls-Garrison) 339 328 11 3.2 % Green Line #2 (Great Falls-Garrison) 339 328 11 3.2 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 1 Costs Plan 1 costs are listed in Appendix 1. Plan 1 Conclusions Please note: The existing Great Falls 230 kV substation appears to be congested, and, constructing a new 230 kV switch yard adjacent to the existing switchyard to connect the proposed Green Line, the 230 kV connections to the Renewable Collector System (RCS), and the 230 kV MATL may not be feasible. Plan 1 with the proposed new Great Falls-Garrison, double-circuit, 230 kV transmission line (Green Line) will provide a connection for WTG in northern Montana. However, for an outage of Garrison-Taft 1 & 2, 500 kV lines, the 650 MW of WTG at RCS will need to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and to maintain system stability. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS 650 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 32 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 2 – DETAILED DESCRIPTION Construct a 115 mile, double circuit, 230 kV transmission line (the Green Line) from the Great Falls 230 kV substation to a site near Townsend, MT. At the Townsend site construct a new 500/230 kV substation to interconnect to the 500 kV network. At the Great Falls 230 kV substation, construct a new 230 kV switchyard adjacent to the existing Great Falls 230 kV switch yard and connect the new 230 kV switch yard to the existing 230 kV switch yard using jumpers. Terminate the new Green Line in the new 230 kV switch yard at Great Falls. Plan 2 Details Plan 2 includes the construction of a 115 mile, double-circuit, 230 kV transmission line from the existing Great Falls 230 kV substation to the a site near Townsend. Currently there is not an existing 500 kV substation at Townsend. The construction of the Great Falls to Townsend 230 kV transmission line will require the construction of a new Townsend 500 kV substation. The new transmission line, referred to as the “Green Line”, will provide a path for renewable energy from wind generation facilities in Montana to the northwest power grid. The Green Line facilities for Plan 2 included in the 2014 Light Autumn Load base case power system study included the following: 1. 2. 3. 4. 5. 6. 7. 8. Construction of a new 230 kV switchyard at Great Falls connected to existing Great Falls 230 Substation via jumpers. Construction of a new Great Falls to Townsend 230 kV transmission line – the Green Line (double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA). To connect the proposed Green Line to the 500 kV network at Townsend, BPA will require the construction of new, 8 PCB, 500 kV Townsend substation. At the new Townsend 500 kV substation – Add two, 500/230 kV transformers. At new Townsend Green Line 230 kV bus - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. At Great Falls – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. Green Line Report Rev B (9-June-11) Corporate Base Page 33 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 9. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (Colstrip units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 2 Impact on Area Voltages The power system analysis results for the proposed Green Line, indicated that for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, the addition of the Green Line, with 950 MW of Wind Turbine Generation (WTG), would have no significant voltage impact. The only significant impacts (changes of greater than 0.02 PU) on voltages above 1.10 PU occurred on the Marias N and Marias S 230 kV buses and that was a result of the way the MATL was modelled in the base case. The power system analysis results for the proposed Green Line impact on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated the addition of the Green Line, with 950 MW of WTG, would not have a significant voltage impact The power system contingency analysis for the proposed Green Line impact on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR), with the Green Line in-service would not have a significant impact on area voltages. The study also looked at base cases with the Green Line and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated the outage of the Garrison- Taft 1 & 2, 500 kV transmission lines, with the Green Line inservice, would not have a significant impact on area voltages for any level of WTG. The power system contingency analysis for the proposed Green Line on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, and for an outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR), failed to converge with the Green Line in-service and with 950 MW of WTG. Tripping the 300 MW of WTG at Hay Lake resulted in a solved case, but with numerous voltage violations. Tripping the 650 MW of WTG at the RCS facility did not have any significant voltage violations. Plan 2 – Impact on Area Transmission Facilities The power system analysis of the impact of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line Report Rev B (9-June-11) Corporate Base Page 34 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Green Line in-service. The power system analysis included base cases with the Green Line in-service, and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line inservice. The power system contingency analysis of the proposed Green Line, on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, and 950 MW of WTG, and, with the Garrison-Taft 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), the Hot Springs 500/230 kV transformer would overload approximately 119 per cent. The study results also indicated that with the Green Line in-service, and with the Garrison-Taft 1 & 2, 500 kV transmission lines out, tripping the 300 MW of WTG at Hay Lake, the Hot Springs 500/230 kV transformer would overload approximately 105 per cent. To reduce the loading in the Hot Springs transformer below the Rate A rating of 942 MVA with the Green Line in-service, and with the Garrison-Taft 1 & 2, 500 kV transmission lines out, will require the tripping of the 650 MW of WTG in the RCS. Northwestern’s John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent with the Green Line in-service and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the proposed Green Line, on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, and 950 MW of WTG, and, with the Townsend-Garrison 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), the case would not converge indicating serious system problems. Tripping the 300 MW of WTG at Hay Lake with the Green Line inservice, and with the Townsend-Garrison 1 & 2, 500 kV transmission lines out, overloaded the Great Falls-Landers Fork-Ovando 230 kV transmission line 120 per cent. Several other transmission facilities were overloaded also. Tripping the 650 MW of WTG at the RCS, with the Green Line in-service, and, with Townsend-Garrison 1 & 2, 500 kV transmission lines out, there were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 2 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, or, the Townsend-Garrison, 1 & 2, 500kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped con-currently with the Colstrip units. The existing Colstrip ATR may need to be expanded to include the RCS WTG – or a separate remedial Action Scheme (RAS) will need to be developed. Green Line Report Rev B (9-June-11) Corporate Base Page 35 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 and 2, may not require the reduction of the 950 MW of WTG. Plan 2 Area Losses Transmission Line MATL (Hay Lake-Great Falls)* Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent 299 284 15 5.0 % Green Line Townsend) #1 (Great Falls- 371 360 11 3.0 % Green Line Townsend) #2 (Great Falls- 368 357 11 3.0 % * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 2 Costs Plan 2 costs are listed in Appendix 1. Plan 2 Conclusions Please note: The existing Great Falls 230 kV substation appears to be congested, and, constructing a new 230 kV switch yard adjacent to the existing switchyard to connect the proposed Green Line, the 230 kV connection to the Renewable Collector System (RCS), and the 230 kV MATL (currently under construction) may not be feasible. Plan 2 with the proposed new Great Falls-Townsend, double-circuit, 230 kV transmission line will provide a connection for WTG in northern Montana. However, for an outage of Garrison-Taft, 1 & 2, 500 kV, transmission lines, or, the Townsend-Garrison, 1 & 2, 500kV transmission lines, the 650 MW of WTG at RCS will need to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and to maintain system stability. For outage of the Broadview-Townsend, 1 & 2, 500 kV circuits tripping the RCS, 650 MW of WTG at the RCS may not be required. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 36 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 4 – DETAILED DESCRIPTION Plan 4 Summary Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the Great Falls 230 kV substation. Loop the MATL line into the new Tonbridge SS and add a PST in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. Construct a 115 mile, double-circuit, 230 kV transmission line (the Green Line) from the new Tonbridge SS to a site near Townsend. At the Townsend site construct a new 500/230 kV substation to connect to the Green Line to the 500 kV network. Plan 4 Details Plan 4 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV transmission line (MATL) will be looped into the new 230 kV Tonbridge SS and a phase shifting transformer (PST) will be installed in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 115 mile, double-circuit, 230 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Townsend area. At the Townsend site a new 500 kV, 8 PCB substation will be constructed. At the new Townsend 500 kV substation, two 500/230 kV transformers will be installed to connect the Green Line to the 500 kV network (see Figure 4). The Green Line facilities for Plan 4 included in the 2014 Light Autumn Load power system study included the following: 1. 2. 3. 4. 5. 6. 7. Green Line Report Rev B (9-June-11) Construct a new Tonbridge Switching Station (SS) 10 miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Add a 230 kV Phase-Shifting transformer in the Tonbridge SS to great Falls 230 kV circuit. Construct a new 230 kV transmission line from the Tonbridge SS to Townsend (double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA). To connect the proposed Green Line to the 500 kV network, BPA will require the construction of new, Townsend, 8 PCB, 500 kV substation. At the new Townsend 500 kV substation – Add two 500/230 kV transformers. At new Tonbridge SS - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Corporate Base Page 38 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 8. At new Townsend 500 kV substation 230 kV bus – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 9. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). 10. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/0.59 MVAR. 11. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 4 Impact on Area Voltages The power system analysis results for the proposed Green Line, indicated that for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, the addition of the Green Line, with 950 MW of Wind Turbine Generation (WTG), would have no significant voltage impact. The power system analysis results for the proposed Green Line impact on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated the addition of the Green Line, with 950 MW of WTG, would have no significant voltage impact The power system contingency analysis for the proposed Green Line impact on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, (with Colstrip ATR), with the Green Line in-service would not have a significant impact on area voltages. The study also looked at base cases with the Green Line and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated the outage of the Garrison- Taft 1 & 2, 500 kV transmission lines, with the Green Line inservice, would not have a significant impact on area voltages for any level of WTG. The power system contingency analysis for the proposed Green Line on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, and for an outage of the Townsend-Garrison 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be large number of voltage violations (greater than 0.02 per unit) with the Green Line in-service and with 950 MW of WTG on-line. Tripping the 300 MW of WTG at Hay Lake, with the Green Line in-service, and, with the Townsend-Garrison 1 & 2, 500 kV lines out, also had numerous voltage violations. Tripping the 650 MW of WTG at the RCS facility, with the Green Line in and with Townsend-Garrison 1 & 2 out, did not have any significant voltage violations. Green Line Report Rev B (9-June-11) Corporate Base Page 39 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 4 Impact on Area Transmission Services The power system analysis of the impact of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line in-service. The power system analysis included base cases with the Green Line in-service, and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and all 950 MW WTG off. The study results indicated there would not be any additional overloaded transmission facilities, nor, would there be any significant changes in existing overloaded facilities with the Green Line inservice. The power system contingency analysis of the proposed Green Line, on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, and 950 MW of WTG, and, with the Garrison-Taft 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), the Hot Springs 500/230 kV transformer would overload approximately 118 per cent. The study results also indicated that with the Green Line in-service, and with the Garrison-Taft 1 & 2, 500 kV transmission lines out, tripping the 300 MW of WTG at Hay Lake, the Hot Springs 500/230 kV transformer would overload approximately 104 per cent. To reduce the loading in the Hot Springs transformer below the Rate A rating of 942 MVA with the Green Line in-service, and with the Garrison-Taft 1 & 2, 500 kV transmission lines out, will require the tripping of the 650 MW of WTG in the RCS. The John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent with the Green Line inservice and for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the proposed Green Line, on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, indicated that with the Green Line in-service, and 950 MW of WTG, and, with the Townsend-Garrison 1 & 2, 500 kV transmission lines out, (with Colstrip ATR), indicated there would a number of overloads in Montana. Tripping the 300 MW of WTG at Hay lake with the Green Line inservice, and, with the Townsend-Garrison 1 & 2, 500 kV transmission lines out, eliminated most of the overloads. Several other transmission facilities were overloaded also. Tripping the 650 MW of WTG at the RCS, with the Green Line in-service, and, with TownsendGarrison 1 & 2, 500 kV transmission lines out, indicated there would be no new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Green Line Report Rev B (9-June-11) Corporate Base Page 40 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 4 Transient Analysis The initial transient analysis indicated for an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, or the Townsend-Garrison, 1 & 2, 500 kV, at a minimum, the RCS 650 MW of WTG will need to be tripped con-currently with the Colstrip units. The existing Western Montana Remedial Action Scheme (RASR) will need to be revised to include tripping of the RCS WTG. The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 & 2, may not require the reduction of the 950 MW of WTG. Plan 4 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 285 14 4.7 % Green Line Townsend) #1 (Tonbridge- 463 446 17 3.7 % Green Line Townsend) #2 (Tonbridge- 463 446 17 3.7 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 4 Costs Plan 4 costs are listed in Appendix 1. Plan 4 Conclusions Plan 4 with the proposed new Tonbridge Switching Station and the Tonbridge SSTownsend, double-circuit, 230 kV transmission line will provide a connection for WTG in northern Montana. However, for an outage of Townsend-Garrison, 1 & 2, 500 kV transmission lines, or, the Townsend-Garrison, 1 & 2, 500 kV transmission lines, the 650 MW of WTG at RCS will need to be tripped to prevent overloading the Hot Springs 500/230 kV transformer and maintain system stability. For outage of the Broadview to Townsend 500 Green Line Report Rev B (9-June-11) Corporate Base Page 41 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE kV circuits 1 and 2, tripping the 650 MW of WTG at RCS may not be required. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 42 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 7 - DETAILED DESCRIPTION Plan 7 Details Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the Great Falls 230 kV substation. Loop the MATL line into the new Tonbridge 230 kV SS and add a PST in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. Install two 500/230 kV transformers in the Tonbridge SS and construct a 145 mile, 500 kV, transmission line (the Green Line) from the Tonbridge SS to the Garrison 500 kV substation and connect to the Garrison 500 kV bus. Plan 7 Details Plan 7 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV transmission line (MATL) will be looped into the new 230 kV Tonbridge SS and a phase shifting transformer (PST) will be installed in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 145 mile, 500 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Garrison 500/230 kV substation. At the Tonbridge SS, two 500/230 kV transformers will be added to connect to the 500 kV Green Line. The Green Line facilities for Plan 7, included in the 2014 Light Autumn Load power system study, included the following: 1. 2. 3. 4. 5. 6. 7. Green Line Report Rev B (9-June-11) Construct a new Tonbridge 230 kV Switching Station (SS) approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Install a 230 kV PST in the Tonbridge SS to Great Falls 230 kV circuit. The Tonbridge SS to Garrison 500kV transmission line was assumed to be a single-circuit, three 954,000 ACSR conductors per phase, rated at approximately 2600 MVA (3,000A). Tonbridge SS – Add two 500/230 kV transformers. Tonbridge SS – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). Corporate Base Page 43 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 8. 9. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/0.59 MVAR. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 7 Impact on Area Voltages The power system voltage analysis results for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages above 1.10 PU. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line, indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system contingency analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG, and with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system contingency analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG, and an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated, there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. Plan 7 Impact on Area Transmission Services The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line, indicated there would not be any no new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Green Line Report Rev B (9-June-11) Corporate Base Page 44 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE The power system contingency analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and 950 MW of WTG on-line, and with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Hot Springs 500/230 kV transformer would overload approximately 119 per cent. Also, with the 300 MW at Hay Lake tripped off, the Hot Springs 500/230 kV transformer would still overload approximately 105 per cent. To prevent overloading of the Hot Springs 500/230 kV transformer, tripping the RCS 650 MW of WTG will be required. Also, the John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on-line, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would not be any new overloaded transmission facilities, or, significant changes in existing overloaded facilities. However, Northwestern’s John Day generation facility’s 100/13.8 kV step-up transformers, and, the 500/100 kV transformers TX3 and TX4, were overloaded approximately 4 percent, with the Green Line in-service, and the TownsendGarrison 1 & 2, 500 kV lines out, for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 7 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped concurrently with the Colstrip units. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the 650 MW of WTG at the RCS. The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 & 2, 500 kV transmission lines, or the Townsend-Garrison, 1 & 2, 500 kV transmission lines may not require the reduction of the 950 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 45 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 7 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 286 13 4.3 % Green Line 500 kV) 927 915 12 1.3 % Transmission Line (Tonbridge-Garrison * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 7 Costs Plan 7 costs are listed in Appendix 1. Plan 7 Conclusions Plan 7 with the proposed new Tonbridge 230 kV Switching Station (SS) and the Tonbridge SS-Garrison 500 kV transmission line will provide a connection hub for WTG in northern Montana. However, the study results indicated an outage of Garrison-Taft, 1 & 2, 500 kV transmission lines, will require the RCS, 650 MW of WTG to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and to maintain system stability. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 46 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 8 – DETAILED DESCRIPTION Plan 8 Summary Construct a 230 kV “Tonbridge” Switching Station (SS) approximately 10 miles north of the Great Falls 230 kV substation. Loop the MATL line into the new Tonbridge SS and add a PST in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. Install two 500/230 kV transformers in the Tonbridge SS and construct a 115 mile, 500 kV, transmission line (Green Line) from the Tonbridge SS to Townsend and connect to the Townsend 500 kV bus. Plan 8 Details Plan 8 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV transmission line (MATL) will be looped into the new 230 kV Tonbridge SS and a phase shifting transformer (PST) will be installed in the Tonbridge SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 115 mile, single-circuit, 500 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Townsend area. At the Townsend site construct a new 500 kV, 8 PCB substation. At the new Tonbridge SS install two 500/230 kV transformers to connect to the 500 kV Green Line. The Green Line facilities for Plan 8 in the 2014 Light Autumn Load power system study included the following: 1. 2. 3. 4. 5. 6. 7. Green Line Report Rev B (9-June-11) Construct a new Tonbridge 230 kV Switching Station (SS) approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Add a 230 kV Phase-Shifting transformer in the Tonbridge to Great Falls 230 kV circuit. The Tonbridge to Townsend 500 kV transmission line was assumed to be a single-circuit, three 954,000 ACSR conductors per phase, rated at approximately 2600 MVA (3,000A). At the new Tonbridge SS – Add two, 500/230 kV transformers. BPA will require the construction of new, Townsend, 8 PCB, 500 kV substation. At Tonbridge SS - Install two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Corporate Base Page 47 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 8. At Townsend 500 kV bus (62013) – Add two, 500 kV, 120 MVAR shunt reactors for voltage control. 9. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). 10. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/0.59 MVAR. 11. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 8 Impact on Area Voltages The power system voltage analysis results for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on line, indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages above 1.10 PU. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, , with 950 MW of WTG, and with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be a large number of voltage violations (changes of greater than 0.02 PU). The contingency case with the 300 MW of WTG at Hay Lake off also indicated there would be a large number of voltage violations (changes of greater than 0.02 PU). The contingency base cases with the RCS 650 MW of WTG off, or with all of the 950 MW of WTG off-line did not have any significant voltage problems. Green Line Report Rev B (9-June-11) Corporate Base Page 48 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 8 Impact on Area Transmission Services The power system analysis impacts of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on line indicated there would not be any new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG, and with an outage of the GarrisonTaft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Hot Springs 500/230 kV transformer would overload approximately 119 per cent. Also, with the 300 MW at Hay Lake tripped off, the Hot Springs 500/230 kV transformer would overload approximately 106 per cent. To prevent overloading of the Hot Springs 500/230 kV transformer, tripping the 650 MW of WTG at the RCS will be required. Also, Northwestern’s John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, also overloaded approximately 4 percent, with the Green Line In-service, and the Garrison-Taft 1 & 2, 500 kV lines out, for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTg, and with an outage of the TownsendGarrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be several overloaded transmission facilities in the Montana area. Tripping with the Hay Lake 300 MW of WTG would unload the transmission facilities. There were not any other significant transmission loading problems in the Montana area with the exception of the John Day generation plant’s 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, that overloaded approximately 4 percent for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 8 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, or, the Townsend-Garrison, 1 & 2, 500 kV transmission lines, at a minimum; the RCS 650 MW of WTG will need to be tripped con-currently with the Colstrip units. The existing Colstrip ATR may need to be expanded to include the RCS WTG – or a separate remedial Action Scheme (RAS) will need to be developed. Green Line Report Rev B (9-June-11) Corporate Base Page 49 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 & 2, 500 kV transmission lines, may not require the reduction of the 950 MW of WTG. Plan 8 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 286 13 4.3 % Green Line 500 kV) 927 917 10 1.1 % Transmission Line (Tonbridge-Townsend * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 8 Costs Plan 8 costs are listed in Appendix 1. Plan 8 Conclusions Plan 8 with the proposed new Tonbridge Switching Station and the Tonbridge SS-Townsend 500 kV transmission line will provide a connection for WTG in northern Montana to the Northwest power grid. However, for an outage of Garrison-Taft, 1 & 2, 500 kV transmission lines, or, an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, the 650 MW of WTG at RCS will need to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and maintain system stability. For outage of the Broadview-Townsend 1 & 2 500 kV circuits, tripping the 650 MW of WTG at RCS may not be required. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 50 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 9 – DETAILED DESCRIPTION Plan 9 Summary Construct a 230 kV “Tonbridge” Switching Station (SS) at the Marias site, approximately 85 miles north of the existing Great Falls 230 kV substation. The Marias site is located on the Montana-Alberta 230 kV transmission line (MATL) right-of-way and is where Tonbridge Power plans to install back-to-back series capacitors to aid power flow on the MATL 230 kV interconnection. The new Tonbridge/Marias SS will include a Phase-Shifting Transformer (PST) to control power flow on the MATL line section from the Tonbridge/Marias SS to the Great Falls 230 kV substation. A new 230 kV single-circuit 230 kV transmission line (the Green Line) will be constructed from Marias to the existing Garrison 500 kV substation. At the Garrison 500 kV substation, Tonbridge will install a 500/230 kV transformer to connect the Green Line to the 500 kV network. Plan 9 Details Plan 9 includes the construction of a new 230 kV Tonbridge Switching Station (SS) at Marias, approximately 85 miles north of the existing Great Falls 230 kV substation. The MATL will be looped into the new 230 kV Tonbridge/Marias SS and a phase shifting transformer (PST) will be installed in the Tonbridge/Marias SS to Great Falls 230 kV circuit to limit power flow into Great Falls. A new 220 mile, single-circuit, 230 kV transmission line (the Green Line) will be constructed from Marias to the Garrison 500 kV substation. . At the Garrison 500 kV substation, Tonbridge will install a 500/230 kV transformer to connect the Green Line to the 500 kV network. The Green Line facilities for Plan 9 as modelled in the 2014 Light Autumn Load power system study included the following: 1. 2. 3. 4. 5. Green Line Report Rev B (9-June-11) Construct a new Tonbridge 230 kV Switching Station (SS) at the Marias site, approximately 85 miles north of the existing Great Falls 230 kV substation. Connect the new Tonbridge/Marias SS to the Marias South 230 kV bus. Add a 230 kV Phase-Shifting transformer in the MATL 230 kV transmission line from the new Tonbridge/Marias SS to the existing Great Falls 230 kV substation. Construct a Tonbridge/Marias SS to Garrison 230 kV transmission line (a singlecircuit, 1,590,000 ACSR conductor, transmission line, rated at approximately 600 MVA). At the existing Garrison 500 kV substation – Add one, 500/230 kV transformer. Corporate Base Page 51 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 6. At the new Tonbridge/Marias SS - Install two, 230 kV, 80 MAVR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 7. At the new 230 kV bus at the Garrison 500 kV substation – Install two, 230 kV, 80 MAVR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. 8. The Colstrip generation was reduced 330 MW (Colstrip Unit 2) to accommodate the addition of 300 MW of Wind Turbine Generation (WTG) at Hay Lake. 9. The Wind Turbines for the Hay Lake were assumed to be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. 10. Contingency studies assumed the Colstrip ATR would trip Colstrip units 1, 3, and 4 (unit 2 is already off-line to accommodate the addition of 300 MW of WTG at Hay Lake). Plan 9 Impact on Area Voltages The power system voltage analysis results for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 0 MW of WTG on line, indicated the voltage at the Marias South and the PST 230 kV buses would increase to approximately 1.32 and 1.26 per unit, respectively, which will exceed the WECC upper voltage limit of 1.05 per unit for noncontingency system conditions. The high voltages are a result of interaction between the series, and shunt, capacitors at Marias and the line shunt reactors associated with the Green Line. Switching the 4, 160 MVAR shunt capacitor banks off at Maries resulted in reducing the voltages at the Marias S and PST 230 kV buses to approximately 1.05 per unit each; however, the voltages at the Marias N and Hay Lake 230 kV buses decreased to 0.79 and 0.87 per unit, respectively. The voltages at Marias N and Hay Lake are well below the WECC minimum voltage level of 0.95 per unit. Adding 300 MW of WTG at Hay Lake, with the Marias 4, 160 MVAR shunt capacitors off, resulted in voltages at Marias S, Marias N, Hay Lake, and the PST buses of 1.28, 0.67, 0.84, and 1.23 per unit, respectively, all of which are outside the WECC voltage limits 1.05 per unit maximum and 0.95 per unit minimum. Adding 300 MW of WTG at Hay Lake, with the Marias shunt capacitors off, - and looping the Bole-Conrad 230 kV transmission line into Marias S, resulted in voltages at Marias S, Marias N, Hay Lake, and the PST buses of 106, 107, 105, and 106 per cent, respectively, all of which are slightly above the WECC maximum voltage limit of 105 per cent. Adding a transfer of 200 MW from Alberta to PGE through the MATL 120 PST’s to the 300 MW of WTG at Hay Lake, with the Marias shunt capacitors off, and with the Bole-Conrad Green Line Report Rev B (9-June-11) Corporate Base Page 52 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE line looped into Marias S, resulted in the voltages at Marias S, Marias N, Hay Lake, and the PST buses to 1.07, 1.12, 1.05, and 1.06 per unit, respectively, which also exceeded to the WECC upper limit of 1.05 per unit and would not be acceptable. The power system voltage analysis results for voltages less than 0.95 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 0 MW of WTG on line, indicated the voltage at the Marias N and Hay Lake 230 kV buses would decrease to approximately 0.99 and 1.00 per unit, respectively, which are within the WECC voltage limits of 1.05 and 0.95 per unit for noncontingency system conditions. Switching the 4, 160 MVAR shunt capacitor banks off at Maries resulted in reducing the voltages at the Marias N and Hay Lake 230 kV buses to approximately 0.79 and 0.87 PU, respectively. Both voltages were well below the WECC minimum voltage level of 95 PU. The low voltages are a result of interaction between the series capacitors at Marias and the line shunt reactors associated with the Green Line. Adding 300 MW of WTG at Hay Lake, with the Marias shunt capacitors off, resulted in voltages at Marias N and Hay Lake 230 kV buses of 0.67 and 0.84 PU, respectively, all of which are below the WECC voltage minimum limit of 0.95 per unit. Adding 300 MW of WTG at Hay Lake, with the Marias shunt capacitors off, - and looping the Bole-Conrad 230 kV transmission line into Marias S - resulted in voltages at Marias S, Marias N and Hay Lake 230 kV buses of 1.07 and 1.05 PU, respectively, all of which are only slightly above the WECC maximum voltage limit of 1.05 per unit. Adding a transfer of 200 MW from Alberta to PGE through the MATL 120 PST’s to the 300 MW of WTG at Hay Lake, with the Marias shunt capacitors off, and, with the Bole-Conrad 230 kV line looped into Marias S, resulted in the voltages at Marias N and Hay Lake of 1.12 and 1.05 PU, respectively, which also exceeded to the WECC upper limit of 1.05 PU and would not be acceptable. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 300 MW of WTG at Hay Lake and 200 MW transfer Alberta to PGE, and, with the Bole-Conrad 230 kV line looped into Marias S, with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Marias, Marias N, and Hay Lake voltages would be 1.00, 1.11, and 1.04 PU, respectively. The 1.11 PU voltage at Marias N slightly higher than the WECC limits of 1.10 PU maximum and 0.90 PU minimum for contingency conditions; which may be acceptable. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with Green Line Report Rev B (9-June-11) Corporate Base Page 53 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE the proposed Green Line in-service, with 300 MW of WTG at Hay Lake and 200 MW transfer Alberta to PGE, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Marias, Marias N, and Hay Lake voltages would be 0.99, 1.09, and 1.025 PU, respectively, which are all within the WECC voltage limits of 1.10 PU maximum and 0.90 PU minimum for contingency conditions. Plan 9 Impact on Area Transmission Services The power system analysis impacts of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 300 MW of WTG on line at Hay Lake, and, with a 200 MW transfer from Alberta to PGE, indicated the Tonbridge/Marias SS-Bole 230 kV circuit would overload approximately 142 per cent. The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 300 MW of WTG at Hay Lake, and, with 200 MW transfer from Alberta to PGE, and with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Tonbridge/Marias SS-Bole 230 kV circuit would overload approximately 154 per cent. Also, with the 200 MW transfer from Alberta to PGE reduced to zero, Tonbridge/Marias SS-Bole 230 kV circuit would overload approximately 102 per cent. To prevent overloading of the Tonbridge/Marias SS-Bole 230 kV circuit would require tripping the 300 MW of WTG at Hay Lake and all power transfers from Alberta. The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 300 MW of WTG at Hay Lake, and, with 200 MW transfer from Alberta to PGE, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Tonbridge/Marias SS-Bole 230 kV circuit would overload approximately 131 per cent. To prevent overloading of the Tonbridge/Marias SS-Bole 230 kV circuit would require tripping of all power transfers from Alberta. Plan 9 Transient Analysis The initial transient analysis was not performed because the power system analysis indicated Plan 9 – the Green Line connection from Marias to Garrison would not be feasible. Plan 9 Transmission Line Losses Green Line Report Rev B (9-June-11) Corporate Base Page 54 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Substation 120S-Hay LakeTonbridge)* 189.3 185.1 4.2 2.2% MATL (Hay Lake-Tonbridge)* 485.1 472.5 12.6 2.6 % Green Line (Tonbridge/Marias SSGarrison 230 kV) 265.6 249.6 16.0 6.0 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 9 Costs Plan 9 costs are listed in Appendix 1 Plan 9 Conclusions Plan 9 with the proposed new Tonbridge/Marias Switching Station and the Tonbridge SSGarrison 230 kV transmission line (Green Line) would not be feasible because of the interaction between the series and shunt capacitors at Marias and the Green Line shunt reactors. Switching off the four 160 MVAR capacitor banks at Marias, and looping the BoleConrad 230 kV transmission line into the Maris S bus would help with the voltage issues; however, the loop establishes a 230 kV direct tie to Great Falls which would severely overload (142 per cent) with 300 MW of WTG at Hay Lake and a 200 MW transfer from Alberta to PGE. Green Line Report Rev B (9-June-11) Corporate Base Page 55 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Appendix 5 - Alternate Plans For Connecting Tonbridge SS to Great Falls using a Power Circuit Breaker Green Line Report Rev B (9-June-11) Corporate Base Page 56 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 5 – DETAILED DESCRIPTION Plan 5 Summary Same as Plan 3 except replace the PST in the Tonbridge to Great Falls 230 kV circuit with a 230 kV circuit breaker and operate “Normally Open”. Plan 5 Details Plan 5 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV transmission line (MATL) will be looped into the new 230 kV Tonbridge SS. A 230 kV PCB will be installed in the Tonbridge SS to Great Falls line section and will be operated normally open. A new 145 mile, double-circuit, 230 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Garrison 500/230 kV substation. At Garrison two 500/230 kV transformers will be added to connect the Green Line to the 500 kV network (see Figure 5). The Green Line facilities for Plan 5, included in the 2014 Light Autumn Load power system study are as follows: 1. 2. 3. 4. 5. 6. 7. 8. 9. Green Line Report Rev B (9-June-11) Construct a new Tonbridge 230 kV Switching Station (SS) approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Add a 230 kV PCB (Operate Normally Open) in the Tonbridge SS to Great falls circuit. Construct a new 145 mile, Tonbridge SS to Garrison, 230 kV transmission line (double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA). Install two 500/230 kV transformer at Garrison. Tonbridge SS – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Garrison 230 kV bus - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) were assumed to be Acciona 1530 units with a reactive capacity of +/0.59 MVAR. Corporate Base Page 57 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 10. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 5 Impact on Area Voltages The power system analysis results for impacts of the Green Line on voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case, with the proposed Green Line, and with 950 MW of WTG on line indicated there would be no voltage violations (changes of greater than 0.02 PU) on voltages above 1.10 PU. The power system analysis results for impacts of the Green Line on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on line, indicated there would be no significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system contingency analysis results for the Green Line on voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line, with 950 MW of Generation (WTG), and an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be no significant violations. The study also considered the impact of the Green Line, with the Garrison-Taft 1 & 2, 500 kV lines out, on four base cases with the Green Line in-service, and with different levels of WTG in-service: 950 MW, 650 MW (300 MW off at Hay Lake), 300 MW (650 MW off at RCS), and with all 950 MW of WTG off. The study results indicated there would be no significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system contingency analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the Green Line in-service, with 950 MW of WTG on-line, indicated there would be no significant voltage problems. The study also examined the impacts of the Green Line on base cases with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR). The base cases included four base cases with the Green Line inservice, and with different levels of WTG in-service: 950 MW, 650 MW (300 MW at Hay Lake off), 300 MW (650 MW at RCS off), and with all 950 MW WTG off. The study results indicated there would be no significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. Plan 5 Impact on Area Transmission Services The power system analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the Green Line Report Rev B (9-June-11) Corporate Base Page 58 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE proposed Green Line in-service, and with 950 MW of WTG on line, indicated there would be no new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the impacts of the proposed Green Line on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case, with the Green Line in-service, and 950 MW of WTG on-line, and, with the Garrison-Taft, 1 & 2, 500 kV transmission lines outaged, (with Colstrip ATR), indicated the Hot Springs 500/230 kV transformer would overload 117 per cent. Also, tripping off the 300 MW of WTG at Hay Lake resulted in the Hot Springs 500/230 kV transformer overloaded approximately 106 per cent. To prevent overloading of the Hot Springs 500/230 kV transformer, tripping of the RCS 650 MW of WTG will be required. Also, the study indicated the John Day generation facility 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, would overloaded approximately 4 percent, with the Green Line in-service, and the Garrison-Taft 1 & 2 out, for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis of the Green Line impacts on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the Green Line in-service, with 950 MW of WTG on-line, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would not be any new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 5 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped concurrently with the Colstrip units. The existing Colstrip ATR may need to be expanded to include tripping the RCS WTG – or a separate remedial Action Scheme (RAS) will need to be developed. The Initial transient analysis indicated that outages of the Broadview-Townsend, 1 & 2, 500 kV transmission lines, or the Townsend-Garrison, 1 & 2, 500 kV transmission lines may not require any reduction of the 950 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 59 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 5 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 285 14 4.7 % Green Line #1 (Tonbridge-Garrison) 463 439 24 5.2 % Green Line #2 (Tonbridge-Garrison) 463 439 24 5.2 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 5 Costs Plan 5 costs are listed in Appendix 1. Plan 5 Conclusions Plan 5 with the proposed new Tonbridge 230 kV Switching Station (SS) and the Tonbridge SS-Garrison, double-circuit, 230 kV transmission line will provide a connection hub for WTG in northern Montana. However, the study results indicated an outage of Garrison-Taft, 1 & 2, 500 kV transmission lines, will require the RCS, 650 MW of WTG to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and to maintain system stability. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS 650 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 60 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE PLAN 6 – DETAILED DESCRIPTION Plan 6 Summary Same as Plan 4 except replace the PST in the Tonbridge to Great Falls 230 kV circuit with a 230 kV circuit breaker and operate “Normally Open”. Plan 6 Details Plan 6 includes the construction of a new 230 kV Tonbridge Switching Station (SS) approximately 10 miles north of the existing Great Falls 230 kV substation. The Montana Alberta 230 kV transmission line (MATL) will be looped into the new 230 kV Tonbridge SS. A 230 kV PCB will be installed in the Tonbridge SS to Great Falls 230 kV circuit and will be operated normally open. A new 115 mile, double-circuit, 230 kV transmission line (the Green Line) will be constructed from the new 230 kV Tonbridge SS to the Townsend area. At the Townsend site a new 500 kV, 8 PCB substation will be constructed. At the new Townsend 500 kV substation two 500/230 kV transformers will be installed to connect the Green Line to the 500 kV network. The Green Line facilities for Plan 6 included in the 2014 Light Autumn Load power system are as follows: 1. 2. 3. 4. 5. 6. 7. 8. Green Line Report Rev B (9-June-11) Construct a new Tonbridge 230 kV Switching Station (SS) approximately ten miles north of Great Falls. Loop the MATL 230 kV transmission line into the new Tonbridge SS. Add a 230 kV PCB (Operate Normally Open) in the Tonbridge SS to Great falls circuit. Construct a new Tonbridge to Townsend 230 kV transmission line (assumed to be double-circuit, two 954,000 ACSR conductors per phase, rated at approximately 1600 MVA). BPA will require the construction of new, Townsend, 8 PCB, 500 kV substation. Tonbridge will install two 500/230 kV transformers at new Townsend 500 kV substation. At Tonbridge SS - Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. At new Townsend 500 kV substation 230 kV bus – Add two, 230 kV, 80 MVAR shunt reactors and three, 230 kV, 60 MVAR, capacitor banks for voltage control/support. Corporate Base Page 61 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE 9. The Colstrip generation was reduced 950 MW to accommodate the addition of 950 MW of Wind Turbine Generation (WTG). 10. The Wind Turbines for the Hay Lake and the Renewable Collector System (RCS) will be Acciona 1530 units with a reactive capacity of +/- 0.59 MVAR. 11. Contingency studies assumed the Colstrip ATR would trip Colstrip units 3 and 4 (units 1 and 2 are off-line to accommodate the addition of 950 MW of WTG). Plan 6 Impact on Area Voltages The power system voltage analysis results for voltages greater than 1.10 per unit (PU), in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages above 1.10 PU. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with 950 MW of WTG on line, indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on-line, and, an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would not be any significant impacts (changes of greater than 0.02 PU) on voltages less than 0.95 per unit (PU), and below. The power system voltage analysis results for voltages less than 0.95 per unit (PU), and below, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG on-line, and with an outage of the Townsend-Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be a large number of voltage violations (changes of greater than 0.02 PU). The case with the 300 MW of WTG at Hay Lake off, with the Green Line in-service, and the Townsend-Garrison 1 & 2, 500 kV lines out, also had a large number of voltage violations (changes of greater than 0.02 PU). The contingency base case with the RCS 650 MW of WTG off, or with all of the 950 MW of WTG off with the Green Line in-service, and the Townsend-Garrison 1 & 2, 500 kV lines, out did not have any significant voltage violations. Plan 6 Impact on Area Transmission Services The power system analysis results for the green Line impacts on transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn Green Line Report Rev B (9-June-11) Corporate Base Page 62 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE base case with the proposed Green Line in-service, with 950 MW of WTG on line did not have any no new overloaded transmission facilities, nor, were there any significant changes in existing overloaded transmission facilities. The power system contingency analysis of the loading impacts of the proposed Green Line for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, and with an outage of the Garrison-Taft, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated the Hot Springs 500/230 kV transformer would overload approximately 118 per cent. Also, the study indicated the case with the 300 MW at Hay Lake tripped off, theGreen Line in-service, and with the Garrison-Taft 1 & 2, 500 kV lines out, the Hot Springs 500/230 kV transformer would still overload approximately 105 per cent. To prevent overloading of the Hot Springs 500/230 kV transformer, tripping the 650 MW of WTG at the RCS will be required. The study results also indicated the John Day generation facility 100/13.8 kV stepup transformers, and the 500/100 kV transformers TX3 and TX4, would overload approximately 4 percent, with the Green Line in-service, and with the Garrison-Taft 1 &2, 500 kV lines out. There would not be any other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. The power system contingency analysis results for transmission line loadings, 100 per cent or higher, in the Montana and Northwestern areas, for the 2014 Light Autumn base case with the proposed Green Line in-service, with 950 MW of WTG, and with an outage of the Townsend- Garrison, 1 & 2, 500 kV transmission lines, (with Colstrip ATR), indicated there would be a number of overload transmission facilities in the Montana area. Tripping of the Hay Lake 300 MW of WTG, with the Green Line in-service, and the Townsend-Garrison 1 & 2, 500 kV lines out, eliminated the transmission overloads. There were not any other significant transmission loading problems in the Montana area with the exception of the Northwestern John Day generation plant’s 100/13.8 kV step-up transformers, and the 500/100 kV transformers TX3 and TX4, that overloaded approximately 4 percent with the Green Line in-service, and the Townsend-Garrison 1 & 2, 500 kV lines out, for all levels of WTG. There were no other new overloaded transmission facilities, or, significant changes in existing overloaded facilities. Plan 6 Transient Analysis The initial transient analysis indicated for an outage of the Garrison-Taft 1 & 2, 500 kV transmission lines, or the Townsend-Garrison 1 & 2, 500kV transmission lines, at a minimum, the RCS 650 MW of WTG will need to be tripped con-currently with the Colstrip units. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include the 650 MW of WTG at the RCS. The Initial transient analysis indicated that outage of the Broadview-Townsend 1 & 2, 500 kV transmission line may not require the reduction of the 950 MW of WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 63 TONBRIDGE POWER GREEN LINE PROJECT PLAN OF SERVICE Plan 6 Transmission Line Losses Sending End Receiving End Line Losses Line Losses MW MW MW Per Cent MATL (Hay Lake-Tonbridge)* 299 285 14 4.7 % Green Line #1 (Tonbridge-Garrison) 463 446 17 3.7 % Green Line #2 (Tonbridge-Garrison) 463 446 17 3.7 % Transmission Line * Power flow on the Montana-Alberta Transmissio n Line (MATL) controlled by the phase-shifting transformer (PST) at Substation 120S. Plan 6 Costs Plan 6 costs are listed in Appendix 1. Plan 6 Conclusions Plan 6 with the proposed new Tonbridge Switching Station and the Tonbridge SSTownsend, double-circuit, 230 kV transmission line (Green Line) will provide a connection for WTG in northern Montana. However, for an outage of Garrison-Taft, 1 & 2, 500 kV transmission lines, or, an outage of the Townsend-Garrison, 1 & 2, 500 transmission lines, the 650 MW of WTG at RCS will need to be tripped to prevent overloading the Hot Springs 500/230 kV transformer, and to maintain system stability. For outage of the BroadviewTownsend, 1 & 2, 500 kV transmission lines, tripping the 650 MW of WTG at RCS may not be required. The existing Western Montana Remedial Action Scheme (RAS) will need to be revised to include tripping the RCS WTG. Green Line Report Rev B (9-June-11) Corporate Base Page 64