Engineering Switchgear Manufacturing Co. plc. Company

advertisement
Horizons
Engineering Switchgear Manufacturing Co. plc.
Company Qualifications




 














Qualifications
_____________________
Company Full Name & Address
_________________________
Horizons Engineering Switchgear Manufacturing Co. plc
Head Office
Wasfi Al-Tal Street
Yathreb Center, 5th Floor, Office # 8
P.O.Box 330521
Amman - Jordan
Tel :
++ 962 - 6 - 551 3849
Fax :
++ 962 - 6 - 553 1848
E-mail: hece@go.com.jo
hesmco@go.com.jo
Switchgear Workshops
Marka Industrial Estate
P.O.Box 330607
Amman 11133 - Jordan
Tel :
++ 962 - 6 –488 2114
Fax :
++ 962 - 6 –488 2115
E-Mail: horizons@go.com.jo
mail@horizons-switchgear.com
Web Site: www.horizons-switchgear.com




 














Registration
__________
Ministry of Trade & Industry
Registration No. 39651 dated 4th, April 95
Classification
___________
Manufacture & Assembly of Distribution
& Control Panelboards
Ministry of Industry & Trade
Amman Chamber of Commerce
Amman Chamber of Industry
Jordan Engineers Associations
Jordanian Contractors Association




 














We Are Licensed And Approved By:










ISO 9001,2000 SGS
Authorized Panel Builders
Authorized Panel Builders
Authorized System Integrators
ASTA
IPH-ASTA
Certified 65KA 1 Sec. 143KA Peak
Certified 50KA 1 Sec. 143KA Peak
European Standards IEC 61000
Certified Actuator Maintenance




 














JORDAN ARMED FORCES
( Authorized Switchboard Suppliers )
MINISTRY OF HOUSING & PUBLIC WORKS
( Authorized Switchboard Suppliers )
MINISTRY OF HEALTH
( Authorized Switchboard Suppliers )
MINISTRY OF AGRICULTURE
( Authorized Switchboard Suppliers )




 














Reference List of Executed Projects
Project / Client
Description
Selpho-chemical Plant
Design, Manufacture, Supply and Install Power
Factor Correction Panels 400KVAR & 500KVAR
May1995
Middle East Hotel
Supply and install MCCs ,SMDBs & final
Disribution boards.
Dec 1995
Ministry of Health
Design, Manufacture & Installation of
AutomaticTransferSwitches and Distribution
Panels.. Jerash,Madaba Al-Bashir Hospital,
Ruwaished and others
Motorola Factory
Main Switchgear , Distribution Panels & Motor
Control Centers & Power Factor Correction Panel
Jordan Radio & Television
Main Station Automatic Transfer Switches
Sept 1997
Jordan Radio & Television
Automatic Transfer Switches , Generators
& Main Distribution Panels For T.V Stations
Sept 1997
Transjordan Engineering Co
Automatic Transfer Panels & All Electrical Panels
for several Factories
General Engineering
Industries
Main Switchboards, Distribution Panels &
Motor Control Centers
Nov1997
Mi
ddl
eEas
tI
nt
’
lI
nv
’
tGr
o
up
Soft Drinks & Mineral Water Plant Main
Switchboards, Distribution Panels &
Motor Control Centers & Automation System
Dec 1997
Salini Italstrade J.V.
Karameh Dam Project
Installation of Automation System and
Instrumentation , MV and LV Panelboards and
programming and commissioning.
Sept 1997
Water Authority of Jordan
Autotransformer starter Panels 132Kw
Autotransformer starter Panels 450Kw
June 1998




 














Award
Jan–
Sept 96
Aug 1996
Aug 96-99
Project / Client
Description
Award
Steel & Cast Factory
Main Switchboards
Ministry of Public Works
Automatic Synchronization Panel of
Generating Sets & Main Distribution Board
Al-Omary Boarder
Ministry Of Youth
Olympic Swimming Pool ,Form 4 Switchboards
Motor Control Centers
Jan 1999
Grand Hyatt Hotel
Grand Hyatt Hotel Men & Women Health Club
Panels
Feb 1999
Royal Diving Center Aqaba
Abboud Pools Supply
Aqaba Pool PLC Controlled Pool Panel
Feb 1999
Boskalis-Archirodon J.V.
Arab Potash Co. Project Main & Submain
Distribution Panelboards
Feb 1999
Arab Potash Company
4000Amps Rated 100KA for 1sec Out-door walk-in
Type Draw- out Motor Control Center with PLC
Feb 1999
Nov. 1998
Four
Dec 1999
Control
AEGEK
L.V. Switchboards, Panelboards and
Motor Control Centers for Walla & Mujeb Dams
March 1999
CDM
Engineers
& Automation & Instrumentation Control Panels &
Constructor
Distribution Equipment for Zai Water Treatment
Zai Water treatment Plant
Plant include installation and operation
July 1999
Telecommunication Company Generating Set and Automatic Transfer Switch with
PLC Control For Main Building
Aug 1999
Jopetrol
Form4 MDB’
s& 200Kw Autotransf. Starters
Hugo Boss Jordan Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power Factor Correction Panel
1999-2000
Victoria Secrets Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power FactorCorrection Panel
1999-2000
Miracle Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power FactorCorrection Panel
1999-2000




 














Sep. 2000
Project / Client
Description
Al Israa Hospital
MDB& Submai
nDi
s
t
r
i
but
i
on& MCC’
s
Dec .2000
Al-Haramain Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power Factor Correction Panel
1999-2000
Camel Textile Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power Factor Correction Panel
1999-2000
SARI Factory
Main Switchgear , distribution Panels & Motor
Control Centers & Power Factor
1999-2000
Perrier Factory
Main Distribution Board & Power Factor correction
Jan 2000
Ministry of Public Works
Amman Financial Market Main
& Submain
Distribution Boards & Power Factor Correction &
MCC’
s
Jun 2000
Ministry of Public Works
Amman Central Post Office Main & Submain
Distribution Boards & Power Factor Correction &
MCC’
s&UPS
Jun 2000
Marriott Dead Sea Hotel
Bussiness Tourism Co
(5 Star Hotel) M.V.
Switchgear , Distribution Transformers ,L.V.
Switchboards, Panelboards final DBs & Motor
Control Centers
2000-2001
Cold Install & operate of complete fuctional SCADA
System to control Temp., Humidity, Compressors
and Selonoids Valve and Water Cooling System
for 15 No. Cold rooms
July 2001
South
Stores
Agricultural
Award
King Hussein Medical City
L.V. Switchboards & Motor Control Centers
Intensive Care Unit ( I.C.U)
Nov .2001
JEPCO
Feeder Pillars( 80No. ) outdoor type
Sept .2001




 














Project / Client
Description
Award
Water Authority of Jordan
450KW Autotransformer starters ( 4No. )
Nov .2001
Zaytoona Textile Factory
Main Switchgear , distribution Panels &Motor
Control Centers & Power Factor Correction Panel
Dec.2001
Eyes Hospital
Supply of Distribution Panelboards & Motor
Control Center
Jan. 2002
Arab Steel Mfr. Co.
Supply of Main Distribution PanelBoard
Jan. 2002
Fast Link Mobile Co.
Supply of Main Distribution PanelBoard
Feb 2002
SARI Factory
Supply of Distribution Panelboards & Motor Control
Center
Feb. 2002
Zaytoona Factory
Supply of Distribution Panelboards & Motor Control
Center
Feb. 2002
Barahmeh Company
Supply of Distribution Panelboards & Motor Control
Center
Mar 2002
Al-Dar Contracting Co.
Supply of Main Distribution PanelBoard
Mar 2002
Bromine Co.
Sup
pl
yofMai
nDi
s
t
r
i
but
i
onPane
l
boar
d
s
,SMDB’
s
& Motor Control Center
April 2002
LEMA Company
Supply of Motor Control
Autotransformer Panelbiards
–
April 2002
Numan Mall
Supply of Main Distribution Panelboar
d
s
,SMDB’
s
& Motor Control Center
July 2002
Century Wear
Supply of motor starter panels
July 2002
Queen Alia Heart Institute
Supply of Main Distribution Switchboards 2500A,
Bus Coupler, SMDB panelboard , Motor Control
Center and Power Factor Correction Panelboards
July 2002
Center
Panel




 














Project / Client
Description
Al-Barakah Dairy Co.
Supply of Power Factor Correction Panelboards
Award
2002
Al- Marwa Miniral Water Reprogramming of Touch Screen Megalis
Company.
2002
National Chlorine Co.
Supply of Motor Control Center Back to Back Panel,
and Upgrade and Programming of Existing PLC
TSX47 controlling all new and existing starters and
ACB’
s
2002
Nabeel Factory
Supply of Main Distribution Panelboards
2002
Ahmad Badawieh Co.
C-Town Malls at Shemasani & Jabal Al-hussein
Sup
pl
yofMai
nDi
s
t
r
i
but
i
onPane
l
boar
d
s
,SMDB’
s
& Motor Control Center Power Factor Correction
Panelboards.
2003
The Morganti Group Inc.
Rehabilitation of Greater Amman Water Supply
System ( Contract-15 ) which consists of 20 RTUs
with some 2500I/O and Main Control Room. Each
RTU will have the following:.
-
-
-
Drawout Motor Control Centers complete
with all necessary components and
accessories.
PLC Control Panel including Quantum
Series PLC and Industrial Computer with
Vejio Look SCADA System
SMDB
Power Factor Correction Panel
Sump Pumps Panel
Chlorination Fans Panels
Al
lRTU’
sar
ec
onne
c
t
e
dt
ot
heMai
nCont
r
olRoom
at Dabouq by Twisted Pair Copper Cable and by
Wireless modem. The Control Room is equipped with
Hot Standby Quantum PLC system and Two Hot




 














2003-2004
Project / Client
Description
Award
Redundant Operator Work Stations with Monitor
Pro7 SCADA Sytem.
Four Seasons Hotel
Programming & Operation of Modicon Micro PLC
to operate circulating pump in the Hotel
2003
Water Authority Of Jordan
Water Meters WAJ77
Supply & Installation of Water Meters and Telemetry
System,
which
includes
installation
of
Electromagnetic and Mechanical flowmeters for
more than 200 Location. Installation of GSM
Modems & Data Loggers to be connected through
the GSM network to several
Control Rooms
complete with operator workstation and SCADA
Software
2003 & 04
Jordan Valley Authority
Maintanance of the Water measurement Network on
Water Measurement Network King Abdullah Canal which covers the whole length
on KAC Maintenance
on the Canal and all Valley, Dams and Turn-out
stations. These include more than 40 RTU’
sand
some 2000I/O
Electricity Distribution Co.
Supply of 220No. Feeder Pillars Panelboards with
different rating from1600A-100A
2003 & 04
2003
HOMA-RO Germany Pump Saida Coastal Area Waste Water Project.
Manufacturer
Saida Coastal area waste Supply and Commissioning of Motor Control
water Project
Centers complete with Micro PLC to control the
operation of 17 Pumpstations with different motor
s
t
ar
t
e
r
sandmot
orr
at
i
ng.TheMCC’
sar
ede
s
i
gne
d
to accommodate the proposed SCADA System to be
implemented in the next phase and connect all these
Stations to the Main Control Room
2003
Elissa & Nafaa
Diversion of Jordan River Karameh Dam,Pump
Station with Four 750KW Autotransformer Starters
and PLC Control Panel
2004
CH2M Hill
Haditha Dam Project –Manufacture and Supply of
Motor Control Centers and PLC Control System
Consisting of 4 PLC Control Panels with 1200I/O
count, programming and testing.
2004




 














Project / Client
Description
Award
Haddadin Co.
Dead Sea Convention Center –All Main submain
and Distribution Panelboards, Automatic transfer
Panels 2500Amps and Motor Control Centers
2004
Aqaba Beach Resort
Intercontinental
–MID Contracting
Supply of Main Distribution Switchboards 4000A, 3
Incomers & 2 Bus Coupler, SMDB panelboard ,
Motor Control Center and Power Factor Correction
Panelboards
2004
Water Authority of Jordan
WAJ88 - 750KW Autotransformer Starters
2004
Tri Service Co.
Military Training Center- All Main Switchboards
Rated 2500Amps, Submain and Distribution
Panelboards, Automatic transfer Panels and Motor
Control Centers
2004
Electric Distribution Company Supply of Feeder Pillars Panelboards 2500Amps
( EDCO )
2004
Jordan
Electric
Power Supply of 30No. Feeder Pillars Panelboards rated Company ( JEPCO 14 )
1000A
2004
Sewage Treatment Plant – Complete Automation Control & SCADA System for
Jordan Camp –The Morganti a Membrane type STP including Motor Control
Group Inc.
Center
2004
Jordan
Electric
Power Supply of 24No. Feeder Pillars Panelboards rated Company ( JEPCO 22 )
1000A to 3200A
2004
The Morganti Group - Jordan Supply of L.V. Switchgear, Submain and MCCs for
International Police Training Accommodation 1 and All Site works.
Center
2004
Iraqi Elite Group
Supply of L.V. Switchgear & Submain Distribution
Panelboards
2004
Expansion of East Zarqa PS
Supply and commissioning of SCADA automation
System and Distribution and Control Panels
2005
Pediatric Hospital – MID Supply of Main Distribution Switchboards & Bus
Contracting
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
Generator Synchronization Panels
2005
Wathba & Wadha
Project –Flour Amec
2005
Water Supply of Main Switchboards and Draw Out Motor
Control Centers




 














Project / Client
Description
Award
Khor Al Zubair Power Station Supply of Draw Out Motor Control Centers
Project –Flour Amec
2005
Balad Rooz Water Project – Supply of Draw Out Motor Control Centers
Flour Amec
2005
Rehab Power Plant
Maqintenence of Motorizrd Actuators and Motor
Control Center with Variable Frequency Drives
2005
Hyatt Amman Hotel
Ahmad Badawieh est
Supply of Distribution Panels
2006
Dorch Consult Aleppo Water
Supply & Installation of Water Meters and Telemetry
System,
which
includes
installation
of
Electromagnetic
flowmeters
&
Pressure
Transmitters for around 30 Locatios.. Installation
of GSM Modems & Data Loggers to be connected
through the GSM network to the Control Room
complete with operator workstation and SCADA
Software




 














2006-07
Project / Client
Description
Agbami Oil Platform
Nigeria
DSME Korea/PACS USA
Supply of 81No ABS Approved Electrical
Panelboards complete with Insulation monitoring
Devices.
2006
Kings Academy
Koray –Anel - Tokar
Supply of Main Distribution Switchboards 2500A, ,
SMDB panelboard , Motor Control Center and Final
Panelboards
2006
RO Water Treatment Plant – Complete Automation Control & SCADA System for
Saudi Arabia –The SAWACO a RO Water Treatment Plant including Motor
Group Inc.
Control Center and SCADA System
2006
EDCO
47
Package Supply of 45No. Feeder Pillars Panelboards rated Substations
–
Lanka 1000A to 2500A
Transformers
2006
Movenpick Dead Sea resort Supply of L.V. Switchgear, Submain and MCCs for
Expansion
– Standard new expansion.
electromechanical
2006
NEPCO Metering Panels - Supply of KWH metering and Data Logging Panels
Yasmina
2006
Baqouba
Waste
Treatment Plant –
El-Concorde
Water Supply and commissioning of SCADA automation
System andMain Distribution Panelboards, Motor
Control Centers, Distribution and Control Panels
2005
C-Town Istiklal Mall
Supply of Main Distribution Switchboards & Bus
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
2006
C-Town Makkeh Mall
Supply of Main Distribution Switchboards & Bus
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
2006
C-Town Amman Mall
Supply of Main Distribution Switchboards & Bus
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
2006
Carrefour Mall
Supply of Main Distribution Switchboards & Bus
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
2006
Children Museum
Supply of Main Distribution Switchboards & Bus
2006




 














Award
Coupler, SMDB panelboard , Motor Control Center
and Power Factor Correction Panelboards,
Project / Client
Description
Basra Children Hospital
MID Contracting
Supply of Main Distribution Switchboards 2500A, ,
SMDB panelboard , Motor Control Center and
Final Panelboards
2006
Crown Plaza Hotel Dead Sea
–Arab Construction
Supply of Main Distribution Switchboards 4000A,
2Incomers & 1 Bus Coupler, 2500A MDBs, SMDB
panelboard , Motor Control Center and Power
Factor Correction Panelboards
2006
Holiday Inn Resort Dead Sea
–Arab Construction
Supply of Main Distribution Switchboards 2500A,
3Incomers & 2 Bus Coupler, SMDB panelboard ,
Motor Control Center and Power Factor Correction
Panelboards
2006
Fluor Iraq
Supply of Package Substations rated 1600KVA
Qty: 4No.
2006
JEPCO 117-2006
Jordan
electic
Company
Award
Supply of Feeder Pillars 2500A, , 1600A and
Power 1000Amps –Qty: 65 units
2006
Supply of PLC Control Panels –Schneider Electric
Quantum PLC System
2006
Ghors Supply & Installation of Cmplete SCADA and
Telemetry Control System including PLC Control
Panels –Schneider Electric Quantum PLC System in
Hot Standby Configuration. Fiber Optic and Radio
Communication system
2006
Supply of Main Distribution Switchboards, SMDB
panelboard , Motor Control Center and Power
Factor Correction Panelboards
2006
400MW
GTG
Power Power Control Centers ( PCC ) Rated 3200A Heavy
Generation Plant Baghdad – Duty Switchboards include 21 Draw out ACBs and
International Free Company
all outgoing MCCBs are Draw Out type
2007
Faloujah Hospital - Iraq
Supply of Main Distribution Switchboards, SMDB
panelboard , Motor Control Center and Power
Factor Correction Panelboards
2007
Jaramco - QAIA
Supply of Main Distribution Switchboards, SMDB
panelboard , Motor Control Center and Power
2007
Carbonates Factory
Omya
Mujib & Southern
Irrigation Project
El Issa & Nafaa - JVA
Al Hijaz Towers
–Owners




 














Factor Correction Panelboards
Horizons Engineering Switchgear Mfr. Co. plc