Federal Energy Regulatory Commission Environmental Review Process LEAD FEDERAL AGENCY APPLICANT Federal Energy Regulatory Commission (FERC) Process Atlantic Coast Pipeline (ACP) Process Receives Applicant’s request to begin review of the project within the Pre-Filing Process Assesses market need and project feasibility Formally approves Pre-Filing Process, issues Pre-Filing (PF) Docket Number, and begins project review Participates in Applicant’s public open houses Issues Notice of Intent to prepare an Environmental Assessment (EA)/Environmental Impact Statement (EIS) and opens the National Environmental Policy Act (NEPA) scoping period to seek public comments on the project Holds NEPA scoping meetings and site visits in the project area; consults with interested agencies ACP studies potential project sites and routes, identifies stakeholders, holds round of public open house meetings, and requests use of FERC’s Pre-Filing Process 4 ACP updates government officials/general public and sponsors public open houses 4 4 Public Input Opportunities 4 Receives formal application from ACP and issues Notice of Application Files formal application with the FERC Analyzes data and prepares EA or Draft EIS Issues EA or Draft EIS, opens comment period, and holds meetings in the project area to hear public comments 4 Responds to comments, revises the Draft EIS, and issues the final document (if approved) APPROVES OR DENIES PROJECT Public Input Opportunities Incorporates final recommendations and requirements from FERC and other regulatory agencies before proceeding with construction and operation of the project 4 Public Input Opportunities