gas pipework installations for residential properties guidelines for designers / builders and heat installers 2 Contents and general information Safety for the home owner It is a legal requirement under The Energy (miscellaneous provisions) Act 2006 that all “domestic gas works” must be under taken and certified by a registered gas installer (RGI) who is registered with the RGII (Register Gas Installers of Ireland). This guide prepared by Bord Gáis is intended to assist installers but is not to be used as an alternative to the most up to date edition of I.S.813. Safety, certificate & getting connected Important notice to all installers Steps to admitting gas to new home Commissioning the installation Declaration of Conformance Page 39 Contents Page 2 The Irish Standards & Contact Details Page 40 The Meter box Page 3 Natural gas pipework Gas installation pipework Pipe materials & sizing Jointing of pipes Pipework protection Page Page Page Page Pipework from the Meter to the building Extended pipework runs Page Installation pipework beneath footpaths Page Installation pipework beneath roads & landscaped areas Page Polyethylene pipework Page 4 5 8 9 11 12 12 13 Pipework within the building Pipes laid in floors Vertical pipe runs Dry lined walls Timber framed walls Internal pipework ducts Supports & fixings Page Page Page Page Page Page Natural gas and electrical considerations Gas meters & electrical elements Electrical cross bonding Page 25 Page 26 Appliance connections Cookers / hobs and ovens Natural Gas Fires Central heating boilers Lamps External appliances Page Page Page Page Page Permitted flue termination points & ventilation requirements Flue termination guidelines Ventilation requirements Page 32 Page 33 15 18 19 20 23 24 28 29 30 30 31 2 Page 35 Page 36 Page 37 The meter box Meters Normally meters are fitted in purpose designed cabinets external to the building, (for further details see Booklet 1 of this guide). The meter location should be agreed with Bord Gáis in advance of construction commencing. Only in certain circumstances may meters be fitted inside the dwelling and in such instances care should be taken to ensure that the location is well ventilated accessible and protected from possible impact. Please go to pages 35 to 39 for details on certification of installation and arranging for a Natural Gas connection. Recessed meter box Figure 1: Gas meter box before and after meter being fitted Figurer 2: Typical detail of pipe through Cavity Wall Insulation Recessed Meter Box DPC Concrete floor slab Pipe clip All pipe joints must be outside the sleeve 25mm min. Sleeve Piping in concrete must be protected from corrosion with wrap or PVC coating Ground Leve Polystyrene insulation Foundation 3 Natural Gas pipework Gas installation pipework This section of the Bord Gáis Technical Manual Booklet 2 refers to gas installation pipework in a traditional domestic building. This guide has been prepared to reflect the requirements of I.S. 813:2002 ‘Domestic Gas Installations and I.S. EN 1775 1998. For guidelines to installing Natural Gas to multioccupancy dwellings i.e. apartments, please refer to Booklet 3. Any person installing natural gas must be a registered gas installer and do so in accordance with I.S. 813 ‘Domestic Gas Installations’. This guide prepared by Bord Gáis is intended to assist installers but is not to be used as an alternative to the most up to date edition of I.S.813. Where gas pipework may be confused with other pipework, it must be colour coded bright yellow (Yellow ochre - 08 C 35), indelibly marked along its entire length with the word “GAS”/Marking tape. General Gas pipework is installed in a dwelling in order to convey gas in a safe manner from the point where delivery is made by Bord Gáis (usually at the meter) to connect to the various appliances, which may be installed inside or outside the dwelling. In designing and installing domestic pipework every effort should be made to ensure that it forms a robust, serviceable element constructed within the dwelling and will continue to be serviceable and safe for a period not less than the expected life of other services within the building. Typical appliances which could be provided for when installing pipework, include: n Central Heating Boiler n Water Heater n Cooker/Oven/Hob n Tumble Dryer n Barbeque n Living Flame Fire n Decorative Lighting 4 Pipe materials Piping materials should be selected by considering mechanical strength, appearance, corrosion potential and cost. Copper tubing is normally used for residential gas installation piping. Corrosion protected steel should be considered in external locations where impact damage is a risk. Table 1: Suitable materials for external and internal installation pipework Material Location Specifications Rigid Copper Tubing Soft Copper Tubing C.S.S.T Mild Steel Pipe (coated) Internal / External BS 2871 Table 4 or Equivalent BS 2871 Table 4 or Equivalent BS 7838 BS 1387 table 5 or Equivalent Polyethylene Pipe External / Below ground only EN 1555 Note Polyethlene Pipe may not be brought within any dwelling. If brought above ground, polyethylene pipework must be protected against uv light, impact and sources of heat. (See figure 11). Be Aware ! Polyethylene (PE) pipe has an extremely low melting point. Take care when soldering near PE pipe. Pipe Sizing Pipework for domestic installations should be sized to meet the maximum combined flow rate for all the appliances installed. Be Aware ! Remember The maximum pressure loss between the meter outlet and any appliance should not exceed 1 mbar (with all appliances in normal use). n Keep elbows and tees to a minimum. n Each elbow or branch connection is equivalent to about 0.5m of straight pipe. If the maximum consumption of all appliances is greater than 6m3 /hr, then a larger meter than the standard domestic meter is required. Please contact Bord Gáis. n Use machine or spring formed bends wherever possible. Tables 2 & 3: Typical appliance consumption and conversion factors Typical appliance Consumptions Conversion Factors Domestic Boiler 2.00m3/hr approx 1.00m3 Nat. Gas = 11kW approx Cooker 1.00m3/hr approx 1.00m3 Nat. Gas = 37,500 Btu/hr approx Dryer 0.50m /hr approx 1kW = 3,412 Btu/hr Gas Fire 0.75m3/hr approx 3 5 Table 4: Pipe sizing for copper tubing source: I.S.813: 2002 Tube Diameter mm - Copper length m 6 8 10 12 15 22 28 m3/h Heat m3/h Heat m3/h Heat m3/h Heat m3/h Heat m3/h Heat m3/h Heat input input input input input input input kW kW kW kW kW kW kW 3 0.13 1.5 0.57 6.6 1.11 12.9 1.65 19.1 3.2 37 9.6 111 19.8 230 6 0.07 0.8 0.29 3.3 0.69 8.0 1.10 12.8 2.1 24 6.4 74 13.2 153 9 0.04 0.5 0.19 2.2 0.56 6.5 0.94 10.8 1.7 19 5.1 59 10.3 120 12 0.03 0.4 0.14 1.7 0.52 6.1 0.90 10.5 1.4 17 4.3 50 8.8 102 15 0.03 0.3 0.11 1.3 0.43 5.0 0.76 8.8 1.2 14 3.7 43 7.7 89 20 0.02 0.2 0.08 0.9 0.32 3.8 0.57 6.6 1.0 12 3.2 37 6.5 75 25 0.02 0.2 0.07 0.8 0.26 3.0 0.45 5.2 1.0 12 2.8 32 5.7 66 30 0.01 0.1 0.06 0.6 0.21 2.5 0.37 4.3 1.0 11 2.5 29 5.2 60 40 0.01 0.1 0.03 0.4 0.16 1.9 0.29 3.3 0.7 8 2.1 24 4.3 50 Note: 1mBar = 10 N/m2 = 0.1kPa Effective capacity of a copper tube installation with 1.0 mbar difference between the ends for a gas of relative density 0.6 (air = 1) Table 5: Pipe sizing for mild steel source: I.S.813: 2002 length Tube Diameter mm - Mild Steel m (Natural Gas) 6 8 10 12 15 22 28 m /h Heat m /h Heat m /h Heat m /h Heat m /h Heat m /h Heat m /h Heat input input input input input input input kW kW kW kW kW kW kW 3 3 3 3 3 3 3 3 0.32 3.7 0.88 10.2 2.31 26.8 1.65 19.1 4.7 55 14.3 166 29.7 345 6 0.15 1.8 0.58 6.8 1.54 17.9 1.10 12.8 3.2 37 9.6 112. 20.3 235 9 0.10 1.1 0.54 6.3 1.21 14.0 0.94 10.8 2.5 29 7.9 92 16.2 188 12 0.08 0.9 0.40 4.6 1.02 11.9 0.90 10.5 2.2 26 6.7 78 13.8 160 15 0.06 0.6 0.32 3.7 0.89 10.3 0.76 8.8 1.9 22 5.9 68 12.3 142 20 0.04 0.5 0.24 2.8 0.77 8.9 0.57 6.6 1.7 19 5.0 57 10.6 122 25 0.03 0.4 0.19 2.2 0.76 8.8 0.45 5.2 1.5 18 4.4 51 9.2 106 30 0.03 0.3 0.15 1.8 0.63 7.3 0.37 4.3 1.4 17 3.9 45 8.3 97 40 0.02 0.2 0.12 1.4 0.47 5.5 0.29 3.3 1.3 15 3.3 39 7.0 82 Note: 1mBar = 10 N/m2 = 0.1kPa Effective capacity of a steel pipe installation with 1.0 mbar difference between the ends for a gas of relative density 0.6 (air = 1) 6 Table 6: Pipe sizing for polyethylene pipe source: I.S.813: 2002 length Tube Diameter mm - Polyethylene m (Natural Gas) 25 mm 32 mm 63 mm Heat m3/h input kW Heat m3/h input kW Heat m3/h input kW 3 97.1 8.4 189.9 16.4 1144.9 98.7 6 65.0 5.6 127.6 11.0 774.9 66.8 9 51.4 4.4 100.9 8.7 616.0 53.1 12 43.4 3.7 85.5 7.4 523.2 45.1 15 38.0 3.3 75.1 6.5 460.6 39.7 18 34.2 2.9 67.5 5.8 415.1 35.8 21 31.8 2.7 61.7 5.3 380.1 32.8 24 30.6 2.6 57.1 4.9 352.2 30.4 Note: 1mBar = 10 N/m2 = 0.1kPa Discharge in a straight horizontal polyethylene pipe with 1.0 mbar difference between the ends, for gas of relative density 0.6 (air = 1) Note: 1. The above tables refer to Natural Gas only. Should an installation be on a temporary supply from an LPG tank, awaiting connection of Natural Gas, the above tables must be adhered to. 2. For further details in relation to pipe sizing, please consult the CIBSE Guide Section C4 7 Jointing of pipes Solder Joints Be Aware ! Flux should be used sparingly and only applied to the spigot part of the joint. n White lead based paste is not allowed n Hemp can only be used with paste complying with BS 6956. The joint should not be overheated. Residual flux should be wiped from joints after being made. Sources of ignition When making solder joints extreme care should be taken when using a blow lamp or power tool in the vicinity of combustible materials. Adequate protection must be used when working near timber components and bitumised products and polyethylene pipework. It is known that fluxed, unsoldered joints may satisfy the soundness test, therefore, finished joints should always be visually examined to confirm that the solder has run. When making screwed joints, all threads should be clean and undamaged. Figure 3: Correct protection of back-ground material when coldering copper The preferred method of jointing is to use the correct PTFE tape complying with either. BS 4375 or BS 6974. Hemp should only be used on threaded joints in conjunction with thread sealing paste. If for any reason paste is being used then it must comply with BS 6956. Liquid detergent should never be used when leak testing, it can cause rapid corrosion of copper. Mechanical Joints The use of union joints, compression fittings or screwed joints is ONLY acceptable where they will be readily accessible to allow correct tightening for a sound joint. They should not be used in concealed locations eg. ducts, underfloor, etc. Be Aware ! Breather membrane in the cavity of timber framed houses or the styrofoam insulation in the cavity of block / brick dwellings is particularly vulnerable and once ignited can spread quickly within the cavity. Rectification could involve complete dismantling of the wall with serious cost implications for the installer. Copper Tube Tube ends should be cut square and any burrs, internal or external, removed. Tube lengths should be checked and cleared of any foreign matter before use. Screwed Joints When making screwed joints, all threads should be clean and undamaged. Hemp should only be used on threaded joints in conjunction with thread sealing compounds. When jointing paste is used, it must comply with B.S. 6956 and should only be applied to the external thread. Excess paste should be wiped away on completion of the joint. Specially compounded jointing pastes must be used for Natural Gas - white lead based pastes are not acceptable. 8 Pipework protection Mechanical Fire Protection against physical damage and corrosion must be provided where circumstances dictate. Copper tube should only be considered where mechanical damage is unlikely or where it will be enclosed in a mechanically strong protective cover. Pipework material, jointing methods and locations should be chosen in order to minimise the risk of a fire in the building causing a pipework failure which might add to the extent of the fire. Protective Wrapping Corrosion Tape wrapping is normally used at joints or on short lengths. Any tape wrapping applied should extend at least 25mm beyond the surface of the material likely to cause corrosion. All surfaces should be clean and dry before the tape protection is applied. An overlap of 50% is required to provide a layer of double thickness. Steel pipes run externally or in damp areas will require protection against corrosion. Copper tube will not normally require corrosion protection when run externally. When supporting pipework externally on a horizontal / vertical surface the support brackets must ensure that the pipework remains clear of the surface. Any metallic pipework run underground, embedded in a solid floor / wall or in any other corrosive location should be protected against corrosion by one of the methods shown below. Be Aware ! Bends and joints on factory coated pipe should be further protected by wrapping with a suitable plastic tape. Figure 4: Methods of pipe protection Place the pipe in a non-corrodible sleeve or duct (vent to ventilated area) Pipe wrapped with corrosion resistant tape Pipe with a factory bonded coating of PVC 9 Protection Sleeves Size of Sleeve Pipes passing through external, load bearing and cavity walls should take the shortest route and be sleeved through the cavity. The sleeve should be of a diameter that provides a loose fit to the pipe allowing normal pipe expansion / contraction. The purpose of a sleeve is to: Be Aware ! n Prevent access gas entering a vulnerable space (e.g. cavity wall) in the event leakage. Pipes / sleeves of dissimilar metal (steel to copper) should not contact at ANY point. n To protect the gas installation pipe against corrosion. Sealing of Sleeves n To protect the gas installation pipe from damage by normal building movement. Sleeves should always be sealed to the surrounding structure with a suitable building material (e.g. mastic, mortar, etc.). n To accommodate normal expansion and contraction of the pipework. When gas pipes enter through an outside wall, the gap between the pipe and the sleeve should be sealed to the pipe at the inner end of the sleeve only with a flexible, fire resisting compound. (See figure 29, page 26). Sleeve Material Sleeves should be made of a material capable of containing gas. Suitable materials include polyethylene, PVC, steel and copper. The selection of the sleeve material should reflect the need for mechanical strength corrosion resistance and / or fire retardance where required. Sleeves through internal walls should be sealed to the pipe at entrance and exit. (See detail below). Be Aware ! Pipework within a sleeve should not be jointed. Figure 5: Details of pipe sleeve through cavity wall Insulation Grout Any joint must be outside the sleeve Sleeve 10 Pipework from the meter to the building. Provision of customer isolation valves on extended pipework runs: Figure 6: Locating isolating values for terraced houses Hse 1 Hse 2 Hse 3 Hse 4 Wall Meter Box Meter Box or Cabinet Figure 7: Locating isolating values for duplex units Upper Duplex Unit (See page 22) Ground Floor Unit Internal Rising Duct Figure 8: Locating isolating values in apartments Note: Regardless of the route taken by installation pipework from meter to each dwelling, the pipework must be fitted with a customer isolation valve as soon as the pipe enters the dwelling that it is supplying. External Riser 6 Meter Cabinet Ground Level Meter Manifold Meter Manifold Naturally Ventilated Basement 11 See booklet 3 pages 17 and 18. Installation pipework from the meter Pipework should be protected against corrosion preferably by using pipes with a factory applied PVC coating. Where copper pipes are run externally exposed to the elements but supported clear of other surfaces, corrosion protection is not normally necessary. Consult page 9 for further considerations. Pipework should not be installed under the foundations of a building nor in the ground under the base of a wall footing or foundation. Figure 9: Meter on adjacent wall (pipework beneath footpath) Be Aware ! All underground pipework should be pressure tested before initial wrapping or covering takes place. Installation pipework under concrete paths, (pedestrian traffic only), should have: n Minimum cover of 25mm between sleeve / wrapping and concrete finish, (see figure 9 below). n Pipework must be placed in sleeve or have protective wrapping. Meter Box Protective cover 25mm cover min. Footpath Buried pipework in open soil, lawns, or under gravel paths, areas which can be accessed by vehicle should have: n Minimum trench depth of 375mm. n Minimum sand or fine fill surround required in trench of 150mm. n When area can be accessed by vehicle (under tarmac, cobblestone, etc.), the pipework must also have a protective sleeve, (see figure 10 above). Figure 10: Meter on adjacent wall (pipework beneath soft ground or vehicular traffic) Meter Box 375 mm min. cover Protective sleeve 12 Polyethylene pipework Polyethylene (PE) Gas installation piping Underground PE piping can be used for underground supply of gas to a premises and is a convenient alternative to metallic pipes when used externally. Be Aware ! PE pipework should not be laid above 375mm dept of cover regardless of cover material. External buried PE pipework shall be constructed as follows: n Pipework, which may be subject to vehicular loading eg. under cobble lock driveway, should be, in addition to the minimum depth of cover of 375mm, enclosed in a protective sleeve. n Mechanical fittings in accordance with I.S. 265 can be used on buried PE pipework. n Any metallic joints must be wrapped with a minimum of two layers. n PE pipework must be tested to ensure it is gas tight before being covered. n Pipework in soil should be bedded in sand or fine filling to a depth of 150mm above and below the pipe. The minimum depth of cover of the pipe required is 375mm. Be Aware ! n Polyethylene pipe is not allowed within a building. Any installer engaging in For correct method of entry into building above ground level, see figure 11 below. n Welding n Electrofusion n Pipework insertion by mole or horizontal drilling For correct method of entry into building below ground level, see figure 12 over-leaf. in compliance with I.S. 265 should be suitably trained and certified (GDF1 or equivalent). Figure 11: Polyethylene-metal transition (supply entering building above ground level) Above ground fitting GRP cover fixed to wall Capillary soldered elbow Suitably sized copper pipe GRP sleeve GRP sleeve bend GRP sleeve bend Note: Both GRP sleeve and GRP cover must be used on this section. PE from meter 13 Figure 12: Polyethylene-Metal transition (supply entering building below ground) External Leaf PVC coated copper 375mm minimum dept of cover Anti-shear sleeve 300mm min. PE from meter PE pipe Polyethylene / Metal transition fitting (Two layers of protective wrapping required) Figure 13: Below-ground transition fitting with anti-shear sleeve Below-Ground transition fitting Below-Ground transition fitting with Anti-shear sleeve. Note: The polyethylene-metal transition must be suitable for below ground applications, always consult the supplier. The anti-shear sleeve must be fitted at all times when placing transition beneath the ground. 14 Pipes laid in floors Solid or screeded floors Where the piping is to be laid on a solid floor slab, the finished floor screed must allow 25mm minimum cover over the installed pipe. Pipework laid in solid floors should be: n Tested for soundness before any protective coating or cover is applied. n Protected against corrosion e.g. factory bonded PVC. see fig 15 n Adequately embedded by at least 25mm below the final floor finish. n Sleeved and taken the shortest practicable route when passing vertically through a solid floor. see fig 16. Figure 14: Pipe run on solid floor slab Floor covering Screed 25 mm minimum Floor slab Be Aware ! Compression fittings, screwed joints shall not be used on internal buried metallic pipework. Figure 15: Pipe with factory bonded PVC All joints should be kept to a minimum Figure 16: Sleeving pipework vertically through floors Fire resistant mastic Sleeve Fire resistant mastic 15 Pipes laid in floors Figure 17: Compression fittings. Suspended floors Prior to running pipework below suspended floors, a visual inspection should be carried out to note the position of any electrical cables, junction boxes and ancillary equipment, in order to safely route the gas pipes. Be Aware ! Compression fittings can not be used when pipes are placed beneath / within floors or in inaccessible positions. Where pipes are installed between joists, they should be correctly supported in accordance with the following table: Table 7: Support distances for horizontal runs of pipe in suspended floors. Material Normal size (mm) Interval Horisontal Run (m) Copper Up to 15 22 28 1.2 1.8 1.8 Mild Steel Up to 15 20 25 2 2.5 2.5 Where pipes are laid across joists fitted with floor boards or flooring grade chipboard, the pipe should be located in purpose made notches or circular holes drilled through the joists. Figure 18: Notching or providing holes in joists Max. D/7 Min. S/14 Timber Joist Max. S/4 Depth (D) Span (S) Support wall Support wall Max. Diameter d = D/4 Min. S/14 Depth (D) Max S/4 Support wall CL Min. distance between hole centres - 3d Span (S) Support wall 16 Pipes laid in floors Timber floors Notches should not be made in joists of less than 100mm depth. The depth of any notch should be sufficient to accommodate fully the pipe or fittings, but should not exceed 15% (approximately one seventh) of the joist depth. The notch should be located not further than one quarter of the span from an end support; it should be U-shaped when possible and no wider than necessary to accommodate the pipes. Notches should not extend across the joint between the floor boards. Be Aware ! Care should be taken when re-fixing floor boards to prevent damage to the pipes by nails or screws. Location of under floor pipes should be marked on floor boards using pencil / marker or rotary stamp. Figure 19: Marking areas where pipes are laid Laying pipes Care should be taken to prevent the ingress of dirt and water etc. into the pipes. The bore should be examined before installation and the open ends temporarily sealed or plugged prior to running the pipes through dirty areas, for example, below floor boards, (see detail below) Figure 20: Preventing the ingress of dirt / water within feeding pipework though concealed spaces 17 Vertical pipe runs Protection Particular care is required to ensure that pipes hidden in walls do not become a risk due to accidental damage or structural damage due to building settlement. The ingress of gas into voids or cavities must be avoided. Where pipework is to be chased into a solid wall, it is of particular importance that high quality corrosion protection is applied, preferably factory bonded PVC. This is to ensure that high levels of moisture within the wall do not have any detrimental corrosive effect on the pipework. Vertical Pipe Runs (Only) It is not acceptable for pipework to be run horizontally or at any angle other than vertically in a wall chase. Figure 21: Permitted direction of wall chase (vertical only) Pipes in solid walls Vertical pipes should be placed in ducts on the wall surface with convenient access. If this is not practical, the pipework may be chased into the wall provided that the depth of the chase does not exceed one third of the depth of the block or brick. In this situation, the pipe should be protected against corrosion. Be Aware ! Such chasing is unlikely to be achieved in walls constructed of ‘hollow’ blocks. 18 Gas pipework behind Dry lined walls The installation pipework within dry lined walls should be run within purpose designed channels providing adequate protection, ie. metal protection where required. Be Aware ! Compression/mechanical fittings can not be used when pipes are placed behind plasterboard or in inaccessible positions. Where it is not possible to do this, then it is acceptable to run the pipe on the wall surface behind the dry lining provided that the pipe is: n Securely fixed and supported. n Joints are kept to an absolute minimum. n The pipe is protected against corrosion. n The pipe is protected against mechanical damage, (see details below). Figure 22: Details of pipework behind dry lining PVC Coated Copper Protective 18 swg steel cover Pipe in wall behind dry lining PVC Coated Copper Protective 18 swg steel cover Pipe in channel behind dry lining 19 Timber framed walls The following issues need to be addressed when considering running gas pipework within the walls of timber framed construction: Option 1 Run pipework (* rigid or flexible) in floor slab and exit from the floor to the appliance in front of the finished plasterboard face of the wall - see figure 23 below. n Possible interference with or weakening of structure members of the house frame. n Possibility of inadvertent damage to pipework when using plasterboard or other fixings to the inner timber leaf. n Possibility, in the event of a gas escape that: n a dangerous accumulation could occur or n the gas might migrate into the outer cavity, before the escaping gas is smelled by the occupant. n Possibility that natural movement of the structure could damage the pipe. Be Aware ! *Compression joints are not permitted in slab. Option 1A Run pipework as above but exit from the floor into a separately constructed channel to exit at the appliance. This channel must not allow gas to move into the timber frame or cavity. Termination must be in front of the finished plasterboard face of the wall. One of the following options, chosen at design stage, can be used to ensure the avoidance of the possibilities listed above. Option 2 All pipework to be run on exposed internal wall surface or in plastic ducting on wall surface or within cupboards. Figure 23: Appliance connection in front of timber leaf Plasterboard Recessed Gas Meter Box Concrete floor slab External Brick / Block Leaf 25mm min. Sleeve Piping in concrete protected from corrosion with wrap or PVC coating Ground level Polystyrene insulation Copper joint must be outside sleeve 20 Timber Framed Walls Option 3 Run pipework in timber frame walls using continuous plastic coated soft copper or stainless steel - see figure 24. If copper is used, a protective metal cover must be placed in front of the pipework. Timber framed construction of the inner wall requires particular consideration when it is proposed to run gas installation pipework within it. This should only be considered as a last resort, prefered options are described on the previous page. Where there is no other option, gas installation pipework may be laid within the timber frame construction provided the following is adhered to: n Any gas pipe run should be kept to a minimum and run vertically within purpose designed channels. n Channels should be fitted with insulation and covered with the vapour barrier and plasterboard to the same standard as the rest of the wall. n Gas pipes should be adequately supported on the studs. n Pipe joints should be kept to an absolute minimum. n Compression fittings must not be used. n Studs should not be notched. Holes in studs and holes and notches in horizontal timber / membranes should be kept as small as possible. n Pipes should be coated copper or steel to avoid corrosion. n Where copper pipes are used, they should be enclosed within a 18 swg steel sheet or equivalent metal plate. (See figure 24). Alternatively, mild steel pipes may be used without further mechanical protection. But full corrosion protection is required. n Provision should be made for the pipe to accommodate any normal movement of the building. n Where the gas supply point is to be positioned on a separating (party) wall, the pipe should rise in front of the finished plasterboard face. Be Aware ! n Pipes must not be laid within separating (party) walls dividing individual dwellings. 21 Figure 24: Full storey height riser in timber framed walls Continuous PVC Coated Copper Full storey height riser No mechanical fittings permitted 100 mm Metal cover A A Section A-A Figure 25: Appliance connection point to the front of timber framed walls Appliance connection-point riser PVC Coated Copper Additional noggins required for support Appliance connection point 100 mm A A 22 Internal pipework ducts For Apartment Installation Guidelines: Please consult Booklet 3 For installation of Gas within Duplex units: Please use external risers as per page 11 of Booklet 3. If an external riser can not be facilitated, it is recommended that an internal “filled” duct is used (as per page 16, Booklet 3). Figure 26: Internal ventilated duct Internal ventilated duct PVC coated copper or steel pipework Fire resistant material Gas pipes should not be fitted in lift shafts or protected shafts or in any space where gas could migrate in openings to those shafts. Building services shafts containing compressed air, steam or air conditioning ducts should not be used as a route for gas pipes. For further details on the interaction of natural gas pipework and other services, please consult Booklet 3 of this guide, page 20. Vertical or horizontal purpose-laid ducts, containing pipework, should be ventilated at the top and bottom with an open grille (see fig 26). These vents to the duct must have a free area of 5,000mm2 or 1/500th the cross sectional area of the duct, which ever is greater. The purpose of the vents is to ensure that any escape of gas can transmit to a non-hazardous area and be detected by smell. 23 Pipe Supports and fixings Figure 27: Support of pipework to prevent corrosion caused by contact with aggressive surfaces All pipework should be adequately supported to prevent the pipework from coming into contact with surfaces that are likely to cause corrosion (e.g. concrete, masonry, plaster). Supports made from plastic are generally acceptable. Be Aware ! Ferrous materials e.g. screws and support brackets shall not be in contact with copper piping. Table 8: Supporting pipework (Horizontally and vertically) Pipe Support Distance Material Normal size (mm) Interval for vertical run (m) Interval for horizontal run (m) Copper Up to 15 22 28 35 42 54 2.0 2.5 2.5 3.0 3.0 3.0 1.2 1.8 1.8 2.5 2.5 2.7 Mild steel Up to 15 20 25 32 40 50 2.5 3.0 3.0 3.0 3.5 3.5 2.0 2.5 2.5 2.7 3.0 3.0 24 Gas meters and electrical elements. Pipework should be installed at least 25mm away from the electricity supply, distribution cables. Otherwise an appropriate electrical insulation material should be wrapped around the pipe to prevent arcing. Gas pipework should always be separated by a minimum of 10mm from other metal piped services. Pipework should not be installed closer than 150mm to an electricity meter. When this is not possible, a nonconductive shield should be placed between the pipe and the electrical equipment providing the required separation distance. Gas meters shall not be located above or below nor closer than 400mm to an electrical distribution board. Note: Subject to approval from electricity supplier. Figure 28: Installation in relation to electrical meters etc. Electricity meter 150mm Min. Non-conductive partition Electricity meter 150mm min. 25 Electrical cross bonding of supply pipework For meters installed in external meter boxes, the bonding connection should be as near as practicable to the point of entry. Bonding wires should not be connected in the meter box. Figure 29: External Meter (Cross bonding) Pipework from meter Bond Connection to earth must be outside meter box Temperature resistant mastic Grout Figure 30: Internal Meter (Cross bonding) 500 mm Max In the case where the meters are installed inside the building, the bond should be located within 500mm of the meter outlet pipe. 26 Bonding Connection Electrical Cross Bonding at boiler The current edition of I.S.813: 2002 refers to some requirements, which can be found in current editions of the E.T.C.I. wiring regulations including the necessity to cross bond all ‘extraneous metal work including gas supply, water and central heating pipes’. Figure 31: Cross bonding arrangement near boiler Wall Mounted Gas Boiler Gas Supply C.W. H.W. Be Aware ! installation (see pg 39). If the contractor on site does not confirm this, then a copy of the notice (shown below) should be affixed to the boiler before issue of a conformity declaration to I.S.813: 2002. Installers on sites should check with the building contractor that the electrician is completing all bonding work and the existence of an electrical completion certificate must be confirmed by the installer before issuing a Declaration of Conformance for the gas Example of Safety Notice Electrical safety - equipotential (cross) Bonding In the Gas Safety Installation Standard I.S.813: 2002 there is the safety information that any person who carries out installation pipe work should inform the user that electrical bonding must be checked (& if necessary rectified) by a competent person*, in any dwelling where electrical equipotential bonding may be necessary. Some types of electrical installations are fitted with equipotenial bonding, which is the connection of the internal gas and water pipes to the electrical installation’s earth terminal. In particular those installations with Protective Multiple Earthing (P.M.E) should, for safety reasons, be fitted with equipotential bonding. *For information contact your Electricity Supplier Be Aware ! Risk of Electrical shock if Working on Existing Pipework A temporary continuity bond must be used when carrying out any work on the pipework or fittings which will break electrical continuity through them. 27 Appliance Connections It is necessary to provide an appliance valve within 1 metre of each appliance supplied. Depending on the appliance the preferred valving methods are shown below. Be Aware ! Plug type valves (gas cocks) are not permitted. Cookers Figure 32: Cooker flexible pipe connected to self-closing bayonet valve. Yellow indicates suitability for Nat. Gas Hobs and ovens Figure 33: A valve may be fitted in adjacent cupboards to the left or right of the oven / hob. 28 Fires Figure 34: Valve near builders opening When installed, turn on and refit cover disk and plate Recessed valve located in chimney breast Figure 35: Recessed valve - detail All pipework to be PVC coated copper Ball valve with casing flush to wall surface Be Aware ! If not fitting the fire as standard: 8mm wrapped copper - 1m max. run 1. Do not connect or leave live gas pipework to the builders opening. or 2. Turn off micropoint and cap off the downstream side of the valve. 10mm wrapped copper - 3m max. run Flush fitting ball valve for concealed gas installations 29 Central heating boilers and water heaters Positioning the boiler A room sealed boiler, may be located within any room of the dwelling. If located in bathroom / shower, in an enclosed compartment or understairs, additional requirements must be adhered to. (I.S.813: 2002). Additional requirements are needed if placing a boiler beneath stairs. Be Aware ! Open flue boilers are permitted in a small number of locations. See I.S.813: 2002. Lamps Figure 37: Location for valve for street lamp / garden lamp Figure 36: Boiler Valve These appliances are normally fitted with valve when supplied. Wall Mounted Gas Boiler Gas valve on supply to boiler 30 External pipework External Appliances Where appliances such as barbecues, patio heaters, and gas lights etc. are installed remote from the dwelling and the pipes are run underground, consideration should be given to installing an additional isolation valve on the supply pipe at an accessible position either internally or externally as close as possible to where the pipe exits the dwelling. The valve should be labelled showing “GAS OFF” position. Please consult figure 38 below and page 12 for pipe run requirements. Figure 38: External pipework detail House wall Barbecue Outside gas valve 375 mm min. depth below grass and driveway Plastic wrapped soft copper tube 150 mm sand/fine fill 40 mm min. depth under concrete slabs 25 mm min. depth buried in concrete Figures 39 / 40: Isolation valve and Barbecue point detail Isolation Valve Demountable connection (flexible) with integral valve. 31 Permitted Flue terminal locations Flue termination guidelines Irish standards always take precedence over manufacturers instructions, unless manufacturers instructions call for additional or more strict requirements. Guttering Figure 41: Permitted locations for flue terminations Car ports shall have two open unobstructed sides All dimensions in mm Typical width 100 / 125 mm. Boiler flue termination Sample power Flue termination 32 Ventilation requirements for appliances All appliances require combustion air. Room-sealed appliances are provided with an air supply from outside air through a sealed pipe to the appliance, with products of combustion expelled through the flue. This, more often than not, is provided by a concentric flue arrangement. Figure 42: Recommended venting detail Be Aware ! Vents must not be adjustable or capable of being closed. Be Aware ! The amount of free area from the airbrick and airspace grill should be sought from manufacturer before fitting. Airspace grill Airbrick Sizing of vents If an extraction fan, or cooker hood with an extractor fan, is fitted in the room containing an open appliance, or in a connected space to this room, the size of the vent required should be increased by 500mm2 for each 30 litre per second maximum extraction fan rate. When sizing vents the critical dimension is the amount of free area required. Physical dimensions of a vent are not of concern, but the amount of free area that is available so that air may pass through it is critical. (Note table on page 34, specific requirements for one of each type of appliance within a room). The manufacturer should have a stamp on their products showing total free area. When two or more open appliances are installed in the same compartment or space, whether or not they are supplied as a combined unit, the aggregate input rating should be used for sizing the vents. 33 Table 10: Appliance ventilation requirements Appliance type and input Minimum ventilation opening (free area) required Decorative fuel effect fires 10,000mm2 Open-Flued appliance < 7kW 3,500mm2 Open-Flued appliance > 7kW and < 14kW 6,500mm2 Open-Flued appliance > 14kW and < 70kW 450mm2 per kW Fixed space heater (e.g. flueless fire - see Case Study 9) Permanent openings of a minimum of 12,000mm2 The total ventilation required shall be equally divided between high and low level openings on the same wall, separated by a minimum distance of 1,600mm. Maximum input rate 4.2 kW (See note 2) Note 1: Rooms built in accordance with the 1997 Building Regulations TDG’s have a minimum of 6,500mm2 ventilation, or in excess of 12,000mm2 when a room contains a chimney. To allow this ventilation to count towards the minimum opening required, it must be permanently fixed in the open position. Note 2: As combustion products from this appliance are released directly into the room, additional provisions may be needed to avoid condensation and ensure satisfactory air quality. Advice should be sought from the manufacturer of the specific appliance if not included in the manufacturers instructions. Alternative vents Vents may be incorporated in window frames (Curtains must not restrict air flow) and in doors in order to satisfy the air requirement of gas appliances. The free air requirement must be stated by the manufacturer. Openings must not be adjustable or capable of being closed. 34 Safety for the Home Owner Safety, certification & getting connected Important notice to all installers Under current legislation Bord Gáis must be assured that an installation is safe and complies with Irish Standard 813(I.S 813) Domestic Gas installations before gas can be supplied to the dwelling. It is a legal requirement under The Energy (miscellaneous provisions) Act 2006 that all “domestic gas works” must be under taken and certified by a registered gas installer (RGI) who is registered with the RGII (Register Gas Installers of Ireland) The Declaration of Conformance Certificate ,which must be signed by the RGI carrying out the work, is a declaration by the RGI that the gas work is safe. That it has been carried out in accordance with and conforms to the National standard for Domestic Gas Installations I.S.813. Only a declaration of conformance certificate obtained from the Register of Gas Installers of Ireland (RGII) and completed and signed by a RGI is acceptable for this purpose. Be Aware ! If the steps outlined are not followed, in the interest of safety, the gas will not be supplied by Bord Gáis. See below. Important Notice A Registered gas Installer is only permitted to certify his / her own work or that of a registered Trainee work under supervision. The Public Listing of Registered Gas Installers is available at: www.rgii.ie 35 Domestic gas installation safety Information for Registered Gas Installers (RGI) requiring a new meter fit. n Purge installation in accordance with I.S.813 New Housing Projects n Commission appliances/installation in accordance with manufacturers requirements n Complete post construction section (part 1) of declaration of conformance A Registered Gas Installer must n Complete part 2 of the declaration of conformance n Complete the entire gas installation n Issue a declaration of conformance (post construction section) n Issue customer with a copy of the declaration of conformance n Leave properly completed gas supplier/network operator copy on site with part one (post construction section) completed n Return green copy to RGII within 10 days of meter fit When the meter is fitted the RGI must Be Aware ! n Connect to the gas installation Any person installing gas must be a Registered Gas Installer to do so in accordance with I.S 813 “Domestic Gas Installations” n Purge installation in accordance with I.S.813 n Commission appliances/installation in accordance with manufacturers requirements n Complete part 2 of the declaration of conformance n Issue customer copy of declaration of conformance n Return green copy to RGII within 10 days of issue One off existing/new housing The Bord Gáis procedure for this type of installation allows for gas meters to be fitted pre-construction. If a registered gas installer requires a meter to be fitted in such circumstances then. A Registered Gas Installer must n Issue a declaration of conformance (pre construction section) n Leave properly completed gas supplier/network operator copy on site with part one (pre construction section) completed When the meter is fitted the RGI must n Complete the installation in accordance with I.S. 813 n Connect to the gas meter installation (when ready for commissioning) 36 Commissioning of natural gas installations Conducting a Soundness Test Before a declaration of conformance is issued the R.G.I.I installer must carry out a soundness test to ensure there are no leaks in the piped system. The soundness test is carried out as follows: n All work must be carried out by a Registered Gas Installer. n Use only a pressure gauge / manometer with clearly marked 0.1 mbar gradations. n Shut off all appliance valves. n Pressurise installation with air to 100mbar (on gauge). n Wait for 5 minutes to ensure temperature stabilisation. n Check gauge / manometer and record exact marking. n After 5 minutes, check again. n If pressure has dropped at all from noted mark, the installation can not be regarded as sound and shall not be commissioned until the escape is repaired and the installation re-tested. Pressure test connection at meter outlet n If pressure remains stable, then installation can be deemed sound. n Any component forming part of the installation, which was excluded from the pipework test, shall be reconnected, gas introduced into the installation and purging carried out. These connections and components shall then be tested for soundness using either a leak detection fluid or a gas detector. Be Aware ! Installers must be registered see I.S.813: 2002 Carrying out the soundness text. 37 Commissioning of natural gas installations Purging the installation Purging Method Every installation must be cleared (purged) of air or air / gas mixture whenever a gas supply is made available for the first time or when an existing system has been shutdown and is being recommissioned. n All work must be carried out by Registered Gas Installers n Purging of a new installation should not be undertaken without completion of a satisfactory soundness test. Why is it necessary? n Purging from air to gas should be supervised by a Registered Gas Installer A gas / air mixture in the meter or pipework is potentially explosive and it is necessary therefore to ensure that the installation and appliances are left with only a 100% natural gas concentration. n Ensure the dwelling is well ventilated. n Ensure there are no naked lights or sources of ignition. Whilst an appliance may initially light and burn correctly, if there is a pocket of air in the internal installation, the appliance flame will extinguish as the air reaches the appliance burner. n Select a purge point furthest away from the meter and in a well ventilated area. n If it is necessary to purge from a point in a confined area then the purge should be piped to atmosphere. Be Aware ! n For most domestic installations one burner on the cooker hob is an ideal purge point. It is a legal requirement under The Energy (miscellaneous provisions) Act 2006 that all “domestic gas works” must be under taken and certified by a registered gas installer (RGI) who is registered with the RGII (Register Gas Installers of Ireland. n When a full flow of gas is verified, for example, by a stable burner flame, other appliances in the dwelling should then be purged. n Commission appliances. 38 Declaration of Conformance All elements of the declaration must be completed and signed for and the copies distributed as instructed in the document. Bord Gáis will not supply gas unless a valid, properly completed conformance declaration is submitted for verification in one of the ways described. See page 35 / 36. The completed top copy (white copy) should be given to, or left for, the householder. The Green copy sent to the RGII. The Bord Gáis meter fitter collects and verifies the second (yellow) copy. If you are not present, please leave in meter box or attached to boiler. The installer should retain the remaining copy in a secure place, as it may be of use in the future should any difficulties arise as to the safety or acceptability of the installation. Be Aware ! Only registered installers may issue a conformance declaration. Sample declaration form Figure 35: Certificate: Declaration of Conformance CERT 1 S � Form G01(S) Version 1 39 For gas mains and services For downstream of the meter Bord Gáis install all gas mains and services in accordance with the latest edition of the following Irish Standards: Irish Standard I.S.813: 2002 “Domestic Gas Installations” applies to installations downstream of the meter. I.S. 329 “Code of Practice for Gas Distribution Mains” This Standard is the code of practice for Natural Gas installation requirements downstream of the point of delivery and includes the requirements for meters, appliances and associated pipework in single and multiple occupancy dwellings. & I.S. 265 “Installation of Gas Service Pipes”. All of the above standards can be obtained from the NSAI (National Standards Authority of Ireland). Telephone (01) 8073878. or www.standards.ie RGII contact information List of registered Gas Installers 01 4997998 Conformance Certificates 01 4997998 Web Site: www.rgii.ie For your Next Residential Scheme New Connections 1850 411 511 Construction 1850 411 511 Meter Boxes 1850 411 511 Dial before you dig 1850 42 77 47 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publishers. Information correct at time of printing. The advice above is a guide line only and based on the most authoritative information available at the date of issue and users should ensure that it is relevant to the specific circumstances in which they seek to apply it. Professional advice should always be sought. Users should ensure they have up to date information. © Bord Gáis 40 GSDC 2508/3009d July 2010 Document no: 25697