ATTACHMENT # BID # STATEMENT OF WORK I

advertisement
ATTACHMENT # BID # STATEMENT OF WORK I SCOPE OF WORK: The Commonwealth of Pennsylvania, Department of Corrections, State Correctional Institution at Coal Township, requires maintenance testing of the Switchgear, Breakers, Protective Relays and Analog Meters located in the switchgear room in the boiler house located at 1 Kelley Drive, Coal Township, Pa. 17866. Questions regarding the technical aspect of this bid should be directed to Mr. Gary Hynoski at ext. 2214. Questions regarding the bidding or contracting procedures should be direct to Constance Dunleavy, ext. 2143. II. CONTRACT TASKS: SWITCHGEAR AND SWITCHBOARD ASSEMBLIES: Visual and Mechanical Inspection 1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Inspect physical, electrical and mechanical condition including evidence of moisture or corona. Inspect anchorage, alignment, grounding and required area clearances. Verify that current and voltage transformer ratios correspond to drawings. Inspect bolted electrical connections for high resistance using one of the following methods: Verify tightness of accessible bolted electrical connections by calibrated torque‐wrench method in accordance with manufacturer’s published data or Table 100.12. Confirm correct operation and sequencing of electrical and mechanical interlock systems. Attempt closure on locked‐open devices. Attempt to open locked‐closed devices. Use appropriate lubrication on moving current‐carrying parts and on moving and sliding surfaces. Verify correct barrier and shutter installation and operation. Exercise all active components. Inspect mechanical indicating devices for correct operation. Verify that filters are in place and/or vents are clear. Perform visual and mechanical inspection of instrument transformers in accordance with Section 7.10. Inspect control power transformers. a. Inspect for physical damage, cracked insulation, broken leads, tightness of connections, defective wiring and overall general condition. b. Verify that primary and secondary fuse ratings or circuit breakers match drawings. c. Verify correct functioning of drawout disconnecting and grounding contacts and interlocks. ELECTRICAL TESTS: 1. Perform resistance measurements through bolted electrical connections with a low‐resistance ohmmeter in accordance with Section 7.1.1, if applicable. 2. Perform insulation‐resistance tests for one minute on each bus section, phase‐to‐phase and phase‐to‐
ground. Apply voltage in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 100.1. 3. Perform electrical tests on instrument transformers in accordance with Section 7.10. 4. Perform ground‐resistance tests in accordance with Section 7.13. 5. Determine accuracy of all meters and calibrate watthour meters in accordance with Section 6.11. 6. Control Power Transformers. a. Perform insulation‐resistance tests. Perform measurements from winding‐to‐winding and each winding‐to‐ground. Test voltages shall be in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 100.1. b. Verify correct function of control transfer relays located in switchgear with multiple power sources. 7. Verify operation of switchgear/switchboard heaters and their controller, if applicable. 8. Perform system function tests in accordance with Section 8. CIRCUIT BREAKERS, MEDIUM‐VOLTAGE Visual and Mechanical Inspection: 1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Inspect physical and mechanical condition. Inspect anchorage, alignment and grounding. Verify that all maintenance devices are available for servicing and operating the breaker. Clean the unit. Inspect vacuum bottle assemblies. Measure critical distances such as contact gap as recommended by the manufacturer. If recommended by the manufacturer, slow close/open the breaker and check for binding friction, contact alignment, contact sequence and penetration. Perform all mechanical operation tests on the operating mechanism in accordance with manufacturer’s published data. Inspect bolted electrical connections for high resistance using one of the following methods: a. Verify tightness of accessible bolted electrical connections by calibrated torque‐wrench method in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 100.12 Verify cell fit and element alignment. Verify racking mechanism operation. Inspect vacuum bellows operation. Use appropriate lubrication on moving current‐carrying parts and on moving and sliding surfaces. Electrical Tests: 1. Perform insulation‐resistance tests for one minute on each pole, phase‐to‐phase and phase‐to‐ground with circuit breaker closed and across each pole with the breaker open. Apply voltage in accordance with manufacturer’s published data. In the absence of manufacturer’s published data, use Table 100.1. 2. Perform a contact/pole‐resistance test. 3. With breaker in a test position, perform the following tests a. Trip and close breaker with the control switch. b. Trip breaker by operating each of its protective relays. c. Verify mechanism charge, trip‐free, and antipump functions. 4. Perform a vacuum bottle integrity (overpotential) test across each vacuum bottle with the breaker in the open position in strict accordance with manufacturer’s published data. Do not exceed maximum voltage stipulated for this test. Provide adequate barriers and protection against x‐radiation during athis test. Do not perform this test unless the contact displacement of each interrupter is within manufacturer’s tolerance. Be aware that some dc high‐potential test sets are half‐wave rectified and may produce peak voltages in excess of the breaker manufacturer’s recommended maximum. 5. Test Instrument transformers in accordance with Section 7.10. PROTECTIVE RELAYS, ELECTROMECHANICAL AND SOLID‐STATE Visual and Mechanical Inspection: 1.
2.
3.
4.
5.
6.
7.
Inspect relays and cases for physical damage. Clean the unit. Relay Case Clean cover glass. Inspect shorting hardware, connection paddles, and/or knife switches. Verify target reset. Verify that all settings are in accordance with coordination study or setting sheet supplied by owner. Perform as‐left tests. Electrical Tests: 1.
2.
3.
4.
Inspect targets and indicators. Determine pickup and dropout of electromechanical targets. Verify operation of all light‐emitting diode indicators. Set contrast for liquid‐crystal display readouts. FUNCTIONAL OPERATION (IF APPLICABLE) 1. 27 Undervoltage Relay Determine dropout voltage. Determine time delay. Determine the time delay at a second point on the timing curve for inverse time relays. 2. 40 Loss of Field (Impedance) Relay Determine maximum reach. Determine maximum torque angle. Determine offset. Determine time delay at 300 percent of setting. Determine a second point on the operating curve. 3. 50 Instantaneous Overcurrent Relay Determine pickup. Determine dropout. 4. 51 Time Overcurrent Determine minimum pickup. Determine time delay at two points on the time current curve. 5. 55 Power Factor Relay Determine tripping angle. Determine time delay. 6. 59 Overvoltage Relay Determine overvoltage pickup. Determine time delay to close the contact with sudden application of 120 percent of pickup. 7. Control Verification Verify that each of the relay contacts performs its intended function in the control scheme including breaker trip tests, close inhibit tests, 86 lockout tests, and alarm functions. III. SITE VISIT A site visit is not mandatory but can be arranged if there is a need. Please contact Mr. Gary Shopmer at extension 2213 to make arrangements. IV. CONTRACTOR REFERENCES: After the bid opening and prior to awarding of the contract, the Department has the right to request references (name, addresses and telephone numbers) of similar work performed in the previous two (2) years as proof of qualifications to perform the work involved in this contract. V. CONTRACT REQUIREMENTS: The contractor must comply with International Electrical Testing Association Standards. The contractor shall abide by all Department of Corrections rules and regulations while on State Property . SECURITY CLEARANCE INFORMATION FOR VENDORS All vendors or their subcontractors, who utilize regular delivery transportation, will have to submit clearance checks through the original vendor, for all drivers (regardless if delivery is inside or outside of the fence). Common carriers will not be required to render clearance checks, however are subject to search and escort procedures. ALL CARRIERS reporting to outside warehouses must secure their vehicle (windows closed and doors locked), sign in at warehouse and wait for further directions from correctional staff. VI. CONTRACT TERM: The contract term shall commence upon execution and receipt of purchase order or July 1, 2012, whichever is later, and terminate June 30, 2013. VII. BID AWARD: The bidder shall complete and return the RFQ‐Invitation for Bids sheet. Bid will be awarded based on the lowest total sum. The vendor is responsible for costs associated with the completion of the project, i.e. insurances, fuel, equipment, permits, as applicable. VIII. PAYMENT TERMS: Payments shall be made on a reimbursement basis for actual services performed. All invoices for this contract MUST be sent to the following address: Commonwealth of PA‐PO Invoice P.O. Box 69180 Harrisburg, Pa. 17106 All invoices must have the Purchase Order Number, as well as your SAP Vendor Number, on the invoice. Failure to provide this could result in a delay of your payment. Invoice format must be in accordance with the RFQ‐Invitation for Bids sheet. IX. RECEIPT AND OPENING OF BIDS: No paper bids will be accepted. If paper bids are mailed; they will automatically be disqualified. Bids must be submitted electronically, thru the following website www.pasupplierportal.state.pa.us. Please make sure that all of Attributes which are 28 questions are answered. Bids will be opened on the date and time specified in the invitation for bid. Bid tabulations will be posted on the day after the bid opening, on the Department of General Services eMarketplace website http://www.emarketplace.state.pa.us Tabulations are for information only and do NOT constitute actual award/.execution of a contract. The results of the apparent bidders and all bids are under review until final award of the purchase order. 
Download