following items - Indian Railway

advertisement
Government of India (Bharat Sarkar)
Ministry of Railways (Rail Mantralaya)
(Railway Board)
BID INVITATION FOR ELECTRONIC OFFERS
OPEN E-TENDER No.226
Electronic bids are invited for and on behalf of the President of India from bidders for supply of the
following items:
Group-1
(i)
(ii)
Group-2
(i)
Group-3
(i)
Brief Description of
stores
Supply,
Installation,
Testing,
Commissioning
&
Maintenance of 2x50
KWp
Solar
photo
Voltaic
Modules
without battery backup
(i.e two system of
50KWp capacity having
independent “Balance
of the system” for
independent operation
of two system)
Supply, Installation,
Testing,
Commissioning &
Maintenance of 45
KWp Solar photo
Voltaic Modules
without battery backup
Specification No.
RDSO/PE/SPEC/PS/0092-2008
(Rev.0) Amendment ‘5’ to be read
with Annexure Technical
01
(RDSO, Lucknow)
Supply, Installation,
Testing,
Commissioning &
Maintenance of 10
KWp Solar photo
Voltaic Modules
battery backup
RDSO/2009/EM/SPEC/0004
(Rev. ‘1’)-2012 to be read with
Annexure Technical
200
(Remote Railway
Stations of IR)
RDSO/PE/SPEC/PS/0092-2008
(Rev.0) Amendment ‘5’ to be read
with Annexure Technical
Supply,
Installation, RDSO/PE/SPEC/PS/0092-2008
Testing,
(Rev.0) Amendment ‘5’ to be read
Commissioning
& with Annexure Technical
Maintenance of 500
KWp
Solar
photo
Voltaic
Modules
without battery backup
Quantity
(nos.)
20
(1 in each Zonal
Railways Headquarter
office and DLW,ICF and
RCF )
05
1
Cost of Bid Documents
Bid Guarantee Amount
Indian Rupees
5000.00
Indian Rupees
10,00,000
(RupeesTen Lakh)
Last date for submission & opening of Bids
16.10.2014
Note:1. The AMC for 5 years will be applicable for 2 years during warranty period & 3 years after expiry of
the warranty period of two years. The rates for AMC shall be quoted separately by the bidders. The cost
of AMC for 5 years will be taken for evaluation. The prices have to be quoted in line with the conditions
stipulated in the instructions to bidders, offer form & Special Condition of Contract
2. Non-transferable Bid documents containing detailed description of stores required, as also other terms
and conditions are available at www.ireps.gov.in and may be downloaded therefrom for online
submission of their E-bid.
3. The cost of the Bid document is to be deposited with the FA&CAO, Northern Railway, Baroda House,
New Delhi-110001. The scanned copy of receipt as documentary evidence for payment of cost of bid
documents shall be uploaded along with their e-bid at www.ireps.gov.in site. Original receipt towards the
payment of cost of bid documents should be submitted manually with other documents to Director,
Railway Stores (F), Ministry of Railways, Railway Board, Rail Bhavan, Room No.342A, New Delhi110001 upto 14.30 hrs on the date specified for opening of e-bids.
4. The tender cost can also be paid by submitting a Bank Draft drawn on any Indian Nationalised Bank in
favour of the FA & CAO, Northern Railway, Baroda House, New Delhi payable at New Delhi. Scanned
copy of Bank draft towards the cost of bid documents may be uploaded with the e-bid and original bank
draft may be submitted manually along with other documents. Bidder who has already purchased tender
documents need not purchase it again & they may upload scanned copy of Bank draft/payment receipt
along with their e-bid at www.ireps.gov.in.
5. Receiving of e-bids against this tender will be closed at 1430 hrs. on 16.10.2014 and the same will be
opened on the same day at 1500 hrs.
6. No manual offers will be accepted against this tender.
7. Bids from bidders who have not purchased the bid documents, bids not accompanied by bid guarantee,
bids with validity less then 180 days are liable to be summarily rejected.
8. The bidder has the option of either quoting for all 21 locations for 100 KWp/45 KWp (i.e
Group-1) or all 200 locations for 10 KWp ( i.e Group-2) or all 5 locations of 500KWp (i.e
Group-3) or any two groups together or for all 3 Groups ( i.e Group-1, Group-2 and
Group-3 together). However Offers for part locations of Group-1 and/or Group-2 and/or
Group-3 will be rejected.
DIRECTOR, RAILWAY STORES (F)
MINISTRY OF RAILWAYS/(RAILWAY BOARD)
RAIL BHAVAN, RAISINA ROAD/NEW DELHI-110001
TELEFAXNO.0091-11-23388394/23388598
2
INVITATION OF TENDER AND INSTRUCTIONS TO BIDDERS
TENDER NO OP-226
Supply, Installation, Testing,
Commissioning and
Maintenance of
Solar Photo Voltaic
Modules
at 17 Zonal Railways Head Office and
3 PUs (DLW,ICF, RCF) & 01 at
RDSO and various stations of Indian
Railways
Government of India
Ministry of Railways
August, 2014
3
TABLE OF CONTENTS
Sl. No.
Contents
1.0
INTRODUCTION
2.0
INSTRUCTIONS TO BIDDERS
3.0
SCHEDULE OF REQUIREMENTS
4.0
SCHEDULE OF RATES
5.0
SPECIAL CONDITION OF CONTRACT
ANNEXURE-A
OFFER FORM
ANNEXURE- B
STATEMENT OF DEVIATION FROM STANDARD SPECIFICATION
ANNEXURE- C
STATEMENT OF DEVIATION FROM TERMS AND CONDITIONS OF THE TENDER
ANNEXURE- D –(I)
PERFORMANCE STATEMENT OR DETAILS OF PAST SUPPLIES AND CURRENT OUTSTANDING
ORDERS(GROUP-1)
ANNEXURE- D –(II)
ANNEXURE- D –(III)
ANNEXURE- D –(IV)
Performance statement or details of past supplies and current outstanding orders(Group-2)
Financial Capacity of the Applicant
Performance statement or details of past supplies and current outstanding orders(Group-2)
ANNEXURE- D –(V)
Financial Capacity of the Applicant
ANNEXURE- E
Performa for equipment and quality control
ANNEXURE- F
Performa for production capacity
ANNEXURE- G
Format for Power of Attorney for signing of Application
ANNEXURE- H
Performa of Bank Guarantee for bid guarantee/ earnest money
ANNEXURE I
ANNEXURE J
ONLY TO BE QUOTED ELECTRONICALLY
Tentative location of Solar Voltaic Modules
ANNEXURE K
PROFORMA OF BANK GUARANTEE FOR CONTRACT PERFORMANCE GUARANTEE BOND/ SECURITY
DEPOSIT
ANNEXURE L
PROFORMA OF BANK GUARANTEE FOR 10% CONTRACT VALUE TOWARDS WARRANTY
GUARANTEE
ANNEXURE M
Page No.
MOU
Joint Bidding Agreement
ANNEXURE N
Proforma of Power of Attorney from the Lead Member of Consortium
ANNEXURE O
ANNEXURE P
ANNEXURE Q
Indian Railways Standard Conditions of contract
RDSO Spec. No. RDSO/PE/SPEC/PS/0092-2008 (Rev-0) Amdt.-5 & RDSO/2009/EM/SPEC/004
(Rev. ‘i’)-2012 to be read with Annexure-Technical
4
1. INTRODUCTION
1.1 The Ministry of Railways (the “Purchaser”) intends to promote clean environment. As part of
this endeavour to harness green energy the Purchaser has decided to install 20 nos. Solar
Voltaic Modules one each at Zonal Railways Headquarter office, DLW, ICF & RCF & 01 nos.
at RDSO/Lucknow, 05 nos. of 500 KWp at different locations and 200 numbers of Solar
Voltaic Modules at different remote stations of Indian Railways across the country and intend
to have a warranty of two years. The AMC for 5 years will be applicable for 2 years during
warranty period and 3 years after expiry of the warranty period. The rates for AMC shall be
quoted separately by the bidders. The cost of AMC for 05 years will be taken for evaluation.
The President of India herein after referred to as the ‘Purchaser’ (Government of India,
Ministry of Railways (Railway Board) proposes to obtain stores detailed in the “schedule of
requirements” from established and reliable manufacturers.
1.2 The contractor shall Manufacture, supply, provide installation and commissioning of Solar
Voltaic Modules including AMC of 05 years at Zonal Railways Headquarter office and DLW,
ICF, RCF & RDSO/Lucknow and remote stations on Indian Railways as per “Schedule of
Requirement” vide clause 3.1.
1.3 The entity while offering a proposal will be called “Bidder” while entity to whom contract will
be placed shall be referred as “ Contractor”.
1.4 The Purchaser intends to pre-qualify and short-list suitable Bidders, evaluate the offer of
Bidder (the “Bidders”) and award the “Contract” through an open competitive e-bidding
process in accordance with the procedure set out herein. The successful bidder to whom
“Contract” is awarded has to supply, install, commission, test , certify and maintain the Solar
Voltaic Modules under warranty period and AMC period.
1.5
Bidding Process : E-Tender
Bidders are requested to visit site www.ireps.gov.in. and go through the e-bid documents
carefully.
2. INSTRUCTIONS TO BIDDERS
2.1
BID DUE DATE :
e-BIDS WILL BE RECEIVED UPTO
e-BIDS WILL BE OPENED AT
:
:
2.30 P.M. on due date
3.00 P.M. on due date
AMOUNT OF BID GUARANTEE TO BE FURNISHED
2.2
CONTRACTS MADE UNDER THIS TENDER WILL BE GOVERNED BY
I.
Indian Railways Standard Conditions of contract.
II. Special Condition of Contract
III. Invitation of tender and Instructions to Bidders
5
IV.
V
Conditions in the offer forms (All enclosed)
INDIAN RAILWAYS Schedule of Technical requirements mentioned in the attached
“schedule of requirements” of this tender.
In case of conflict, the order of priority for document determining the conditions will be
Special conditions of the contract, Instruction to Bidders, Technical specification to be
read Annexure Technical and Indian Railways Standard Conditions of the Contract
(IRS).
2.3
PARTICULARS, SPECIFICATION AND DRAWING :
The Indian Standard Specification may be obtained from Indian Standard institution,
Manak Bhavan, 9, Bahadur Shah Zafar Marg, New Delhi-110 001.(Telegram
Manaksanstha) or from their branches at
1.
2.
3.
4.
5.
Novelty chambers, Grant Road, Mumbai-7
5, Chowringhee Approach, Calcutta-13
5 9 201/2, Chirag Ali Lane, Hyderabad-11
117/418-B Sarvodaya Nagar, Kanpur-5
54, General, Patters Road, Chennai-2
Indian Railways Standard Specification may be obtained on payment from the Manager of
Publications Civil Lines, Delhi(Telegram : EXINFOR DELHI). RDSO’s schedule of
Technical requirements mentioned in the attached schedule of requirements may be
obtained directly from Executive Director EE(M), RDSO, Manak Nagar, Lucknow.
2.4
MANDATORY REQUIREMENTS OF ELECTRONIC TENDERS:
(a) Bidder is required to fill-in and uploads required information/details as per prescribed
proforma at the time of on-line submission of their e-bid. Hard copy of the same duly
signed should also be submitted manually along with other documents to this office within
the specified time limit i.e. upto 14.30 hours on bid opening date
.
S.No. Requirement
Remarks
1.
Have you remitted the cost of the Bid Money receipt No.
date
Documents or submitted the cost of bid …………………...
documents with offer ?
And amount Rs. ……..……. Or Bank
(if yes please fill-up the money receipt No. Draft No. ………….date ……….. for
and other details)
Rs.
………
….
Name
of
bank………………..
2.
Have you submitted a Bid Guarantee as Bid Guarantee No.
………………..
per clause 2.12 of Instructions to Bidders Date………..
?
Amount …………. Name of bank
(if yes Please fill-up the bid guarantee No. issuing bid Guarantee …………
and other details)
(b) The other required document is also to be filled-in and uploaded as per prescribed proforma
at the time of on-line submission of their e-bid. Hard copy of the same duly signed should also
6
be submitted manually along with other documents to this office within the specified time limit
i.e. upto 14.30 hours on bid opening date.
2.4.1 SPECIAL NOTES :(a) The e-bids should be uploaded at www.ireps.gov.in before the time and date specified for the
same. Only the rates and the details required as per mandatory requirements as per para 2.4
above, are to be uploaded on the IREPS site. Other documents are to be uploaded and also
submitted manually to the Director Railway Stores (F), Ministry of Railways (Railway Board),
Room No. 342-A, Rail Bhawan, New Delhi before the date & time specified for bid opening.
Copy of bid with complete documents shall be submitted manually in 3 copies marked as
‘ORIGINAL’, ‘DUPLICATE’ and ‘TRIPLICATE’ and each copy of the bids should be complete
in all respects. Please note all the three copies of bid must be hard/Spiral bound. Bidders
must note that original copy of Bid Guarantee (EMD) instruments must reach this office within
the specified time of bid submission/opening on bid opening date. In case original copies of
aforesaid documents not received upto 14.30 hrs of bid opening date, bid will be summarily
rejected.
(b) The bidders should quote to the specifications in all respects. Clause wise compliance of
Technical Specification is to be uploaded on the web site with their e-bid and a copy of same
shall also be submitted manually with other documents. If there are any deviations to the
Technical Specification, a Deviation Statement indicating clauses/sub-clauses, deviation
proposed and justification thereof should be enclosed in the prescribed format given as
Annexure-B.
2.5
PERIOD FOR WHICH THE OFFER WILL REMAIN OPEN
Firms should note that the offer should remain open for a period of 180 days from the date
of opening of the bid, for acceptance.
2.6 Language
The bid and all related correspondence and documents in relation to the Bidding Process
shall be in English language. Supporting documents and printed literature furnished by the
Bidder with the Bid may be in any other language provided that they are accompanied by
translations of all the pertinent passages in the English language, duly authenticated and
certified by the Bidder. Supporting materials, which are not translated into English, may not be
considered. For the purpose of interpretation and evaluation of the Bid, the English language
translation shall prevail.
2.7
PRICES
2.7.1 The price must be stated in Indian Rupees only. Excise Duty, Sales Tax /VAT (State-wise),
Service Tax, Insurance, packing / forwarding / freight, AMC charges for each year should be
shown separately. Except for Excise Duty, Sales Tax and Service Tax any other tax, Duty,
Municipal Levy ( Octroi, Entry Tax etc.) shall be to the supplier’s account.
2.7.2 Statutory Duties shall be paid against documentary evidence as per actuals as applicable
during the currency of the contract.
For Octroi and Entry tax necessary exemption
certificate shall be issued by the consignee. Incase this certificate is not accepted by the
State authorities / Local bodies the same shall be on contractor’s account.
7
2.7.3 New statutory taxes/ duties and changes in existing statutory taxes/duties will be paid as
actuals during currency of contract. Documentary evidence regarding imposition of such
duties and taxes and payments made must be furnished for any reimbursements. Purchaser
reserves the right to make recoveries in case of any waiver or reduction of such duties, with
retrospective effect, by the government.
2.7.4 For the states in which VAT has not yet been introduced, the existing system of Sales Tax
will continue
2.7.5 CENVAT CREDIT:
2.7.5.1The prices quoted by the bidders should take into account the credit availed on inputs under
the CENVAT credit rules 2004. The bidders should also state quantum set offs in respect of
duties on inputs (as admissible under law) that is being totally and unconditionally passed
on to the purchaser, in the prices quoted per unit of the item.
2.7.5.2 In the event of additional CENVAT credit being extended by the Govt. of India, to cover
items ordered against present tender, the same shall be passed on to the purchaser. The
bill for payment should accompany the following certificate:
a) We hereby declare that no additional CENVAT benefit has accrued to us beyond what
has already taken into account while submitting our offer and incorporated in the rates
shown in the contract.
b) We hereby declare that no additional CENVAT benefit of Rs….. per machine/unit has
accrued to us beyond what was taken into account while submitting our offer &
incorporated in the rates shown in the contract. We are passing on the same to the
purchaser and the bill has been prepared accordingly.
2.7.5.3 Sales Tax/CST/VAT/Input Tax under VAT scheme:
2.7.5.4 (a) The concessional tax regime so far as available to the Govt. departments has been
withdrawn w.e.f. 1.4.2007. Govt. Departments will have to pay CST @ normal VAT rates
prevalent in the seller’s state for purchase involving inter-state movement of goods.
(b) As the rate of Sales tax/VAT varies for supply of goods inter-state/ intra-state, the
consignees of each group have been further categorized into different sub- groups (statewise). Firm must quote exact rate of Sales Tax/VAT applicable for each sub-group.
2.7.5.5 However, goods of special importance (called declared goods) as incorporated in Section
14 of the CST Act will continue to suffer/enjoy confessional rate of tax since State
Governments cannot impose tax at higher rates than envisaged in CST Act. Iron and steel
items as listed in Section 14 of CST Act 1956, for instance will suffer CST @ 4% only.
2.7.5.6The bidder should quote the exact percentage of VAT that they will be charging extra.
2.7.5.7While quoting the rates the bidder should pass on ( by way of reduction in prices) the set off/
input tax credit that would become available to them by switching over to the system of VAT
from the existing system of sales tax, duly stating the quantum of such credit per unit of the
item quoted for.
2.7.5.8The bidder while quoting for tenders should give the following declaration:
“We agree to pass on such additional set offs/input tax credit as may become available in
future in respect of all the inputs used in the manufacture of the final product on the date of
supply under the VAT scheme by way of reduction in price and advise the purchaser
accordingly.
2.7.5.9The suppliers while claiming the payments will furnish the following certificate to the Paying
authority:
8
“ We hereby declare that additional set off/input tax credit to the tune of Rs…..has accrued
and accordingly the same is being passed on to the purchaser and to that effect the payable
amount may be adjusted”.
2.7.6
a) Wherever two or more firms quote equal rates and cartel formation is suspected,
Railways reserve the right to place order on one or more firms with exclusion of the
rest without assigning any reasons thereof.
b) The bidder has the option of either quoting for all 21 locations for 100 KWp/45
KWp (i.e Group-1) or all 200 locations for 10 KWp ( i.e Group-2) or all 5 locations
of 500KWp (i.e Group-3) or any two groups together or all 3 Groups together ( i.e
Group-1, Group-2 and Group-3 together). However Offers for part locations of
Group-1 and/or Group-2 and/or Group-3 will be rejected.
2.8.
PAYMENT TERMS;
The terms of payment shall be as per clause 5.3 of the enclosed ‘Special Condition of
Contract’.
2.9
TERMS OF DELIVERY:
2.9.1
Deliveries to be maintained as per schedule given at clause 3.2
‘Schedule of Requirement’.
2.9.2
In case of failure on the part of contractor to arrange supplies as per the delivery
schedule/installments fixed in advance, save force majeure conditions or delays
attributable to the purchaser, the purchaser reserves the right to levy “liquidated
damages” which shall be levied as under:
of the enclosed
Liquidated Damages and not by way of penalty, a sum equivalent to 2% ( two percent) of
the price of delayed stores ( including elements of taxes, duties freight etc.) which the
contractor has failed to deliver within the period fixed for delivery in the contract or as
extended for each month or part of a month during which the delivery of such stores may
be in arrears where delivery thereof is accepted after expiry of the aforesaid period,
subject to a maximum of ten percent of value of the delayed supplies .For the purpose
of “liquidated damages” the date of commissioning of solar photo voltaic will be
considered as delivery period.
2.10
THE BIDDERS SHOULD QUOTE RATES F.O.R. DESTINATION
Bidders should quote FOR destination rate in the financial offer of E-bid. As the rate of
Sales tax/VAT for supply of goods varies inter-state/ intra-state, firm must quote exact rate
of Sales Tax/VAT for each sub-group within a Group.
2.11
CORRECTIONS:
Correction should be avoided, but if there are any, all such corrections in the tenders
should be initialed by bidder. Erasures /Correction fluid and over-writing shall not be made.
2.12
EARNEST MONEY (BID GUARANTEE)
9
2.12.1 The bidder must deposit an earnest money of Rs. 10,00,000/-(Rupees Ten lakhs only) in
the manner specified in para 2.13.2 below and attach the same with the original offer of
bid. The EMD should remain valid for a period of 45 days beyond the final bid validity
period i.e for 225 days . The earnest money will be returned without interest to the
bidders, whose tenders are not accepted. Tenders without earnest money are liable to be
rejected. Amount of earnest money will remain same whether the firm quotes for any one
group or all the groups.
2.12.2 The earnest money, deposited is liable to be forfeited, if the bidder unilaterally withdraws,
amends, impairs or derogates from the bid in any respect within the period of validity of his
offer.
2.13
SECURITY DEPOSIT/ PERFORMANCE GUARANTEE
2.13.1 The successful bidder shall, as per clause 0500 of Indian Railway Standard Conditions of
contract, deposit, a sum of equal to 10% of the total value of the stores for which the
tender has been accepted subject to a maximum of Rs.20,00,000/- as security deposit for
the due fulfillment of the contract before issue of contract.
2.13.2 The Earnest money and security deposit may be paid in any of the following manner:
(i) In the form of deposit receipts, Pay Orders, Demand Drafts in favour of FA&CAO/
Northern Railway and Guarantee Bonds of the State Bank of India or any of the
Nationalised or Scheduled Commercial Banks. For Earnest Money, Proforma for Bid
Guarantee Bond is as per Annexure-H and for Performance Guarantee Bond is as per
Annexure-K.
(ii) Government securities at 5% below the market value.
(iii) Deposit in the Post Office Saving Bank.
(iv) Bonds of Indian Railway Finance Corporation & KRCL Bonds.
Deposits in the Post Office Saving Bank should be hypothecated by the depositor to the
Financial Adviser and Chief Accounts Officer of the Railway and pass book will remain in
the custody of the Chief Cashier.
When deposits are made in Government Securities, it should be seen that all accrued
interest to the debit on the G.P. Notes is duly collected by depositors prior to the G.P.
Notes being endorsed to the Financial Adviser and Chief Accounts Officer. There should
be at least two blank pages on the G.P. Notes after the last endorsement by the depositor.
These are necessary to enable further endorsement by the Railway to the Reserve Bank
of India.
The payment of Security Deposit and Earnest Money in the form of Pay Order/Demand
Draft should be made in favour of FA & CAO of Northern Railway.
In case of endorsement signed “PER BEARER” “FOR” power of attorney is necessary duly
registered and such endorsement need be certified by the Public Department Office of the
Reserve Bank of India with their rubber stamp before G.P. Notes are delivered to the
Railways.
2.14
PRINTED CONDITIONS FOR SUPPLY
Printed conditions for supply of goods on the letters /on the back of the letters sent by the
bidders will be ignored as forming part of their tender. In case any terms and conditions of
10
contract applicable to this invitation to tender are not acceptable to the bidder, they should
specify such deviation in the “statement of deviations” as mentioned in bid document. It
may be clearly understood that deviations from IRS Conditions of contract are neither
appreciated nor generally acceptable.
2.14.1 If any departure or substitution from the particular specification is involved this should be
clearly indicated in the Annexure to the offer form. Attention of the tenderer is invited to the
statement of Deviations from Tender Specification (Annexure ‘B’).
2.15
PACKING:
Attention is drawn to clause 1800 of Indian Railway Standard Conditions of Contract.
2.16
PERFORMANCE STATEMENT
Firms must fill-in and upload Performance Statement as per Annexure-D-(i), D-(ii) & D(iv),
Financial Capacity as per Annexure- D(iii) & D(v), Equipment and quality control as per
Annexure-E and Production Capacity as per Annexure-F. Hard copy of the same duly
signed should also be submitted manually along with other documents to this office within
the specified time limit i.e. upto 14.30 hours on bid opening date
2.17
Banker’s details :
Bidders should indicate the names and addresses of their Bankers.
2.18
TRANSIT INSURANCE
The purchaser will not pay separately for transit insurance and the supplier will be
responsible till the entire stores contracted for, arrive in good condition at destination.
2.19
PRICE PREFERENCE FOR EARLIER DELIVERY: Deleted
2.20
RIGHT OF ACCEPTANCE
This office does not pledge itself to accept the lowest or any tender and reserves
itself the right of acceptance of the whole or any part of the tender or portion of the
quantity offered and you shall supply the same at rate quoted.
2.21
TRANSFERABILITY:
This tender is not transferable.
2.22
NUMBER OF BIDS AND COSTS THEREOF
2.22.1 No Bidder shall submit more than one Bid for the Project.
2.22.2 The Bidders shall be responsible for all costs associated with the preparation of their Bids
and their participation in the Bid Process. The Purchaser will not be responsible or in any
way liable for such costs, regardless of the conduct or outcome of the Bidding Process.
2.23
ACKNOWLEDGEMENT BY BIDDER
2.23.1 It shall be deemed that by submitting the Bid, the Bidder has:
(a)
made a complete and careful examination of the tender document;
(b)
received all relevant information requested from the Purchaser;
(c)
accepted the risk of inadequacy, error or mistake in the information provided in the
tender document furnished by or on behalf of the Purchaser relating to the bid.
11
(d)
agreed to be bound by the undertakings provided by it under and in terms hereof.
2.23.2 The Purchaser shall not be liable for any omission, mistake or error in respect of any of the
above or on account of any matter or thing arising out of or concerning or relating to the
tender document or the bidding process, including any error or mistake therein or in any
information or data given by the Purchaser.
2.24
RIGHT TO ACCEPT OR REJECT ANY OR ALL BID /BIDS
2.24.1 Notwithstanding anything contained in this tender document, the Purchaser reserves the
right to accept or reject any Bid and to annul the Bidding Process and reject all Bid/ Bids,
at any time without any liability or any obligation for such acceptance, rejection or
annulment, and without assigning any reasons therefore. In the event that the Purchaser
rejects or annuls all the Bids, it may, in its discretion, invite all eligible Bidders to submit
fresh Bids hereunder.
2.24.2 The Purchaser reserves the right to reject any Bid and/ or Bids if:
(a) at any time, a material misrepresentation is made or uncovered, or
(b) the Bidder does not provide, within the time specified by the Purchaser, the supplemental
information sought by the Purchaser for evaluation of the Bid.
2.24.3
In case it is found during the evaluation or at any time before signing of the Agreement or
after its execution and during the period of subsistence thereof, including the contract
thereby granted by the Purchaser, that one or more of the pre-qualification conditions
have not been met by the Bidder, or the Bidder has made material misrepresentation or
has given any materially incorrect or false information, the Bidder shall be disqualified
forthwith if not yet appointed as the contractor either by issue of the LOA or entering into
of the Agreement, and if the Bidder has already been issued the LOA or has entered into
the Agreement, as the case may be, the same shall, notwithstanding anything to the
contrary contained therein or in this tender document, be liable to be terminated, by a
communication in writing by the Purchaser to the bidder, without the Purchaser being
liable in any manner whatsoever to the bidder and without prejudice to any other right or
remedy which the Purchaser may have under this tender document, the Bidding
Documents, the Agreement or under applicable law.
2.24.4 The Purchaser reserves the right to verify all statements, information and documents
submitted by the Bidder in response to the TENDER DOCUMENT. Any such verification or
lack of such verification by the Purchaser shall not relieve the Bidder of its obligations or
liabilities hereunder nor will it affect any rights of the Purchaser there under.
2.25
CLARIFICATIONS
2.25.1.Bidders requiring any clarification on the bid documents may notify the Purchaser in writing.
They should send in their queries no later than 20 days before the date of submission
specified in bid document.
2.25.2 The Purchaser shall endeavour to respond to the questions raised or clarifications sought by
the bidders. However, the Purchaser reserves the right not to respond to any question or
provide any clarification, in its sole discretion, and nothing in this clause shall be taken or
read as compelling or requiring the Purchaser to respond to any question or to provide any
clarification.
2.25.3 To facilitate evaluation of Bids, the Purchaser may, at its sole discretion, seek clarifications
from any Bidder regarding its Bid. Such clarification(s) shall be provided within the time
12
specified by the Purchaser for this purpose. Any request for clarification(s) and all
clarification(s) in response thereto shall be in writing.
2.26
AMENDMENT OF TENDER DOCUMENT
2.26.1 At any time prior to the deadline for submission of bid, the Purchaser may, for any reason,
whether at its own initiative or in response to clarifications requested by an bidder, modify
the tender document by the issuance of amendment.
2.26.2 Any amendment thus issued will be sent in writing to all those who have purchased the
tender document and will be publicised on website.
2.26.3 In order to afford the bidders a reasonable time for taking an amendment into account, or for
any other reason, the Purchaser may, in its sole discretion, extend the Bid Due Date.
2.27
In case, the date of bid opening falls on a gazetted holiday or is subsequently declared as
such, the bids will be opened on the next working day at the appointed time.
2.28
E-bid are liable to be rejected if-
(a) E-Bids not supported with proof of remitting the cost of bid documents shall be rejected.
(b) E-Bids received not accompanied with specified ‘Bid Guarantee’ shall be considered
un-responsive & rejected. Any FAX message/ communication from the bank for
establishing/issuing the bid guarantee later on will not be entertained.
(c) E-Bids received after stipulated time & date of opening shall not be considered.
(d) In case hard copy of bid related documents is not received manually within the specified
time on date of bid opening, the bid will be rejected.
(e) E-Bid is not valid for acceptance for a minimum period of 180 days from the due date of
opening of bid and Bid Guarantee is not valid for 225 days.
2.29 EVALUATION CRITERIA
2.29.1 The offers received will be evaluated considering total cost of each Group separately
(defined in Bid invitation) for supply, installation, testing, commissioning and maintenance
of Solar Photo Voltaic at various stations on Indian Railway as per RDSO specification of
that group.
2.29.2 The cost of AMC for 5 years will also be considered for evaluation.
13
3.0
3.1
(i)
SCHEDULE OF REQUIREMENTS
Description of Stores & quantity required
Group-1
(i)
(ii)
Group-2
(i)
Group-3
(i)
Brief Description of
stores
Supply, Installation,
Testing,
Commissioning &
Maintenance of 2x50
KWp Solar photo
Voltaic Modules
without battery backup
with warranty of two (2)
years(i.e two system of
50KWp capacity having
independent operation
of two system)
Supply, Installation,
Testing,
Commissioning &
Maintenance of 45
KWp Solar photo
Voltaic Modules
without battery backup
Specification No.
Quantity
(nos.)
RDSO/PE/SPEC/PS/0092-2008
(Rev.0) Amendment ‘5’ to be read
with Annexure technical
20
(each in Zonal Railways
Headquarter office and
DLW,ICF and RCF
RDSO/PE/SPEC/PS/0092-2008
(Rev.0) Amendment ‘5’ to be read
with Annexure technical
01
(RDSO, Lucknow)
Supply, Installation,
Testing,
Commissioning &
Maintenance of 10
KWp Solar photo
Voltaic Modules
battery backup
RDSO/2009/EM/SPEC/0004
(Rev.’1’)-2012 to be read with
Annexure technical
200
(Remote Railway
Stations of IR)
Supply, Installation,
Testing,
Commissioning &
Maintenance of 500
KWp Solar photo
Voltaic Modules
without battery backup
RDSO/PE/SPEC/PS/0092-2008
(Rev.0) Amendment ‘5’ to be read
with Annexure technical
05
(ii) The Annual Maintenance Contract (AMC) for 5 years will be applicable 2 years during warranty
period and 3 years after expiry of the warranty period. The rates for AMC shall be quoted
separately by the bidders which will be considered for evaluation of bid offer.
3.2.
Delivery: Delivery & installation should be completed within 09 months from the award of
the contract.
14
3.3. Annual Maintenance Contract (AMC):
(i)
(ii)
(iii)
The contractor shall provide 5 years AMC, 2 years during warranty period and 3
years after expiry of the warranty period.
The AMC for the Solar Photo Voltaic Modules will be comprehensive and cleaning of
panels and tightening of connections shall be carried out at least once in three
months or as per the requirement to meet desired performance parameters. In any
case inferior performance of equipment shall not be attributed to non-clearing/nonavailability of water by Railway. For maintenance of PCU, one set of essential spares
shall be kept ready/aside.
AMC agreement shall be entered with individual Zonal Railways as per the accepted
rate in the bid.
3.4 Quantity Variation Clause:
Purchaser reserves the right to vary the quantity mentioned in the “Schedule of Requirements” by
plus/minus 30% during the currency of the contract
15
4.0 SCHEDULE OF RATES (SOR)
Unit rate and total rate for the offer shall be quoted by the bidder electronically on the
IREPS site.
The following things may be kept in mind when quoting :-:
a. The rate quoted by the bidder shall be inclusive of manufacture, supply, installation
and commissioning of Solar photo Voltaic Modules at various offices and stations on
Indian Railway. This shall also include cost of structural stability as mentioned at
Para 7.0 of RDSO specification and cost of 2 years comprehensive warranty. Taxes
and duties shall be quoted separately as applicable.
b. The warranty period of goods will start after successful commissioning of Solar photo
Voltaic Modules at site.
c. Quantity Variation (+/- ) 30%.
d. In exceptional case, name of the administrative building/station may be changed by
Purchaser.
e. The AMC for 5 years will be applicable, 2 years during warranty period and 3 years
after expiry of the warranty period.
f. AMC cost will be paid as per cost/solar PV module quoted by the bidder. However
for evaluation purpose total cost of AMC shall be worked out after taking into account
10% NPV discounting factor as tabulated below.
AMC for 3 years after expiry of two years warranty period as per clause 3.3 of Schedule of
Requirements
Cost /Solar PV
Module ( in
Rs)
A
i
First year
ii
Second year
iii
Third year
AMC cost
Fourth year
AMC cost
Fifth year
AMC cost
iv
v
NPV Factor @ Quantity Total Cost of AMC after
10% per
discounting factor
(in Rs)
annum
(For evaluation purpose
B
C
D=A x B x C
UNDER WARRANTY
UNDER WARRANTY
0.7513
0.6830
0.6209
Total
16
5.0 SPECIAL CONDITIONS OF CONTRACT
5.1
Eligibility criteria:
5.1.1 Eligibility criteria for Group-1(2x50 KWp)
The bidder shall fulfill the following eligibility criteria5.1.1. (i) The “Bidder” shall be an Indian manufacturer or a JV consortium having maximum two
members with one Indian manufacturer who shall be lead member having experience as
defined in Technical Capabilities.
(ii)Technical Capability:
a) The bidder shall possess experience as a Indian manufacturer of Solar PV modules
for at least one year.
b) The bidder shall have established after sales service in India
c) The bidder must have at least three years experience of supplying, installing,
commissioning of solar photovoltaic modules of Single unit of 50 KWp 500KWp in India with aggregate of capacity of such panels supplied in any one
of the preceding three years (Financial year 2013-14, 2012-13 & 2011-12) in
India shall be at least 750 KWp.
d) The bidder must have technical capability for integrating total systems and at
least successfully executed 10 “projects” each of at least 50 KWp-500 KWp
capacity, during last one year (Financial year 2013-14).
e)
The bidder shall submit proof of supply & commissioning for the above
information in the prescribed Performa enclosed at Annexure D(i). The proof for
(a) and (b) above shall also be submitted.
(iii) Financial Capacity:
Average annual turnover of the bidder shall be at least INR 60 crores during the last
three Financial Years (i.e 2013-14, 2012-13 & 2011-12) at the close of the Financial Year
before the bid due date. The average annual turnover of lead member should be at least
50% of specified turnover of bidder i.e 60 crores. Audited accounts of bidder shall be
submitted along with the bid. Financial capacity details to be submitted as per Annexure
D-(iii).
5.1.2 Eligibility criteria for Group-2(10 KWp System)
The bidder shall fulfill the following eligibility criteria5.1.2.(i) The “Bidder” shall be an Indian manufacturer or a JV consortium having maximum two
members with one Indian manufacturer who shall be lead member having experience as
defined in Technical Capabilities.
(ii) Technical Capability:
17
a) The bidder shall possess experience as a Indian manufacturer of Solar PV modules
for at least one year.
b) The bidder shall have established after sales service in India
c) The bidder must have at least three years experience of supplying, installing,
commissioning of solar photovoltaic modules of Single unit of 10 KWp -50
KWp with battery backup in India with aggregate of capacity of such panels
supplied in any one of the preceding three years (Financial year 2013-14, 201213 & 2011-12) in India shall be at least 750 KWp.
d) The bidder must have technical capability for integrating total systems and at
least successfully executed 10 “projects” each of at least 10 KWp-50 KWp
capacity, during last one year (Financial year 2013-14) 10 system each of 50
KWp-500 KWp capacity, during last one year.
e)
The bidder shall submit proof of supply & commissioning for the above
information in the prescribed Performa enclosed at Annexure D(ii). The proof for
(a) and (b) above shall also be submitted.
(iii) Financial Capacity:
Average annual turnover capacity of the bidder shall be at least INR 75 crores during
the last three Financial Years at the close of the Financial Year before the bid due date.
The average annual turnover of lead member should be at least 50% of specified turnover
of bidder i.e 75 crores. Audited accounts of bidder shall be submitted alongwith the bid.
Financial capacity details to be submitted as per Annexure D-(iii).
5.1.3 Eligibility criteria for Group-3(5 System of 500 KWp)
The bidder shall fulfill the following eligibility criteria5.1.3.(i) The “Bidder” shall be an Indian manufacturer or a JV consortium having maximum two
members with one Indian manufacturer who shall be lead member having experience as
defined in Technical Capabilities.
(ii) Technical Capability:
a) The bidder shall possess experience as a Indian manufacturer of Solar PV modules
for at least one year.
b) The bidder shall have established after sales service in India
c) The bidder must have at least three years experience of supplying, installing,
commissioning of solar photovoltaic modules of Single unit of 500 KWp or
above in India with aggregate of capacity of such panels supplied in any one
of the preceding three years (Financial year 2013-14, 2012-13 & 2011-12) in
India shall be at least 875 KWp.
d) The bidder must have technical capability for integrating total systems and at
least successfully executed 2 “projects” each of 500 KWp or above during last
one year (Financial year 2013-14.)
e)
The bidder shall submit proof of supply & commissioning for the above
information in the prescribed Performa enclosed at Annexure D(iv).
(iii) Financial Capacity:
18
Average annual turnover capacity of the bidder shall be at least INR 48.75 crores
during the last three Financial Years at the close of the Financial Year before the bid due
date. The average annual turnover of lead member should be at least 50% of specified
turnover of bidder i.e 48.75 crores. Audited accounts of bidder shall be submitted
alongwith the bid. Financial capacity details to be submitted as per Annexure D-(v).
5.2
Consignee
The consignee will be Sr.DEE(G) /DEE(G)/Dy.CEE, in charge of the site where solar
photo voltaic modules is to be commissioned.
5.3
Payment Schedule :
The payment shall be made by FA&CAO of the Northern Railway.
Payment for 1st unit of each type of Solar PV module in each group will be made
after prototype testing by RDSO at site. For balance system following shall be
followed(b) Single stage Payment- 100% payment after successful erection, testing, and
commissioning of solar PV modules at site on Commissioning certification by Sr.
DEE/DEE/Dy. CEE in charge of site after submission of “Acceptance test” &
Routine tests as per clause C of “Annexure- Technical and after submitting of bank
guarantee of 10% value of the stores supplied and commissioned towards warranty
as per clause 5.10 of Special condition of contract.
or
Two Stage Payment
(i)
60% payment excluding AMC after receipt of Solar PV modules at site by
consignee against submission of BG of equivalent amount & after submission
of “Acceptance test” & Routine tests as per clause C of “Annexure-technical”.
(a)
(ii)
(c)
5.4
40% payment excluding AMC after successful erection, testing, and
commissioning of solar PV modules at site on certification by Sr. DEE/DEE/Dy.
CEE in charge of site based on “Acceptance test” Performa and after
submitting of bank guarantee of 10% value of the stores supplied and
commissioned towards warranty as per clause 5.10 of bid document.
(iii) The above BG for 60% payment will be released after successful erection,
testing and commissioning of solar PV modules and issue of Commissioning
certification by Sr.DEE/DEE/Dy.CEE in-charge of site.
Payment of AMC charges will be made on six monthly basis.
Warranty
The warranty period will be two years from the date of commissioning.
5.5
Special conditions
5.5.1 The bidder shall get himself acquainted with the site condition to know exact amount of
work involved before quoting.
19
5.6
Testing and Inspection
Testing & Inspection shall be as per Technical Specification as per which Type test will be
either done by RDSO or certified copies of Type Test Certificates in lieu of actual Tests if
conducted by accredited testing Agency/Lab will be accepted. Acceptance tests will be
conducted by Consignee for regular supplies. However prototype testing/acceptance test of
1st unit each of 500KWp, 2x50 KWp. 45 KWp & 10KWp will be carried out by RDSO at site.
5.7
Submission of drawings :
The contractor shall furnish at his own expense all calculations, designs, drawings,
explanatory notes, schedule information, procedure for approval and submission of drawings
and designs for approval to RDSO.
5.8
Loading and unloading of heavy materials:
The contractor shall make his own arrangements for loading or unloading of all
materials at his depot or at worksites. Railway may facilitate the contractor whenever
required.
5.9
Monthly progress report :
The contractor shall furnish during the first week of every calendar month, a progress
showing progress of finalization of designs and drawings, materials received at site and
the works carried out during the preceding months. As far as possible the presentation
shall be neat and tabulation form accompanied by coloured diagram wherever applicable.
RDSO will coordinate for web based monitoring requirement as per MNRE guideline.
5.10 Warranty Bank Guarantee:
5.10.1 As per para 22 of RDSO specification. The contractor shall submit a bank guarantee of 10%
value of the stores supplied and commissioned towards warranty before claiming 100%
payment .
5.10.2 The Bank Guarantee fully indemnifying the purchaser against all losses incurred by the
purchaser during the warranty period stipulated in the warranty clause is to be submitted as
per Annexure-L.
5.10.3 10% WBG submitted by supplier will be released after successful completion of warranty
obligations and submission of BG for 10% of total value for 1 year of AMC charges which
shall be renewed till the tenure of AMC period.
5.10.4 BG for 10% of total AMC charges for 1 year shall be renewed every year and will be
released after successful completion of AMC period.
20
ANNEXURE-A
OFFER FORM FOR TECHNICAL BID
To
The President of India,
through
The Director, Railway Stores(F),
Ministry of Railways (Railway Board),
Rail Bhavan, Raisina Road,
New Delhi-110 001.
Ref: Tender No.
Sir,
(The following information shall be summerised in the offer latter :- )
1.
Name of bidder -
2.
Lead Member & other members of consortium/ joint venture, if applicable-
3.
Manufacturers of Solar PV modules- certification of manufacturing of Solar PV modules in
India to be attached.
4.
We are equipped with adequate machinery for production, quality control and
testing of the materials manufactured and used by us. We certify that we fully comply with
the eligibility criteria in clause 5.0 of the ‘Special Condition of Contract’.
5.
6.
7.
PLACE OF MANUFACTURE: _______________
We agree in the Warranty/Guarantee clause
We enclose the following statements as required by you.
7.1
Statement of deviations from Indian Railways Standard Specifications
(Annexure-B) (Send a NIL STATEMENT if there is no deviation).
Statement of deviations from the tender terms and General & Special conditions of contract
(Annexure-C) (Send a NIL STATEMENT if there is no deviation).
7.2
7.3
Performance statement (Annexure-D-(i), D-(ii).D-(iv) and Financial Capacity of the Applicant
- Annexure D-(iii) & D-(v)
7.4
7.5
7.6
7.7
7.8
7.9
7.10
Proforma for equipment and quality control (Annexure-E).
Proforma for production capacity (Annexure-F).
Performa for Power of Attorney for signing of Application (Annexure - G)
Performa of Bank Guarantee for bid guarantee/ earnest money (Annexure - H)
Performa for offer form for commercial bid (Annexure–I to be filled electronically)
Tentative locations of Solar Photo voltaic modules(Annexure - J)
Performa of bank guarantee for contract performance guarantee bond/ security deposit
(Annexure- K)
7.11 Performa of bank guarantee for 10% contract value towards warranty guarantee
(Annexure- L)
7.12
MOU (Annexure - M)
7.13
Joint Bidding Agreement (Annexure -N)
21
7.13
Performa for Power of Attorney for Lead Member of Consortium (Annexure- O)
8.
VALIDITY
8.1
We agree to keep our offer valid for acceptance for a period of 180 days from the date of the
opening of technical Bid and shall be bound by a communication of acceptance within the
time.
9.0
We have read and understood the terms of the Indian Railway Standard Conditions of
contract (latest revision) and also the terms of the invitation of tender and instructions to
bidders and undertake to supply the stores as per these terms. The deviations from the
above terms and conditions are only those mentioned in relevant annexures.
Signature of Bidder
Address
Date:
Telephone No.
Telegraphic Address:
(* See item No.5 of the
invitation to tender)
Encls: as per 8 above.
22
ANNEXURE- B
STATEMENT OF DEVIATION FROM STANDARD SPECIFICATION
TENDER NO.______________________ DATE ____________________
NAME OF BIDDER __________________________INDIAN RAILWAYS
ITEM NO.
DESCRIPTION
PARTICULARS OF
DEVIATIONS.
REMARKS
Signature of Bidder
23
ANNEXURE- C
STATEMENT OF DEVIATION FROM TERMS
AND CONDITIONS OF THE TENDER
TENDER NO.______________________ DATE ____________________
NAME OF BIDDER __________________________INDIAN RAILWAYS
SL.NO.
REFERENCE TO TERMS AND
CONDITIONS OF TENDER
DEVIATIONS IN
THE OFFER
REMARKS
Signature of Bidder
24
Annexure D-(i)
Performa for details of supply & commissioning of Solar Photo voltaic modules
Group-1 :20 nos. of 2x50 KWp & 1x45 KWp system
SN
1
2
3
A
B
C
P.O./
Contract
quantity
P.O.
with
date
Customer
Name &
Address,
Contract
NO.
With/
Without
battery
PV
capacity
for single
system
(as
per
para
5.1.1.(ii))
Year wise supplied/commissioning
Remarks
of PV modules
01.04.2011 01.04.2012 01.04.2013
to
to
to
31.03.2012 31.03.2013 31.03.2014
X1
X2
X3
Total Capacity
Total
Commissioned
in
last
3
years(X1+X2+X3)
Nos of “systems” of 50-500 KWp capacity:
Total supplied & Commissioned/years
Note: 1. Supporting documents e.g P.O, proof of supply & commissioning/performance etc.
to be enclosed. All documents shall be in English. If documents are in languages
other than English, a true translation of above key information duly certified shall also
be submitted.
2. Date of supply would mean date of receipt of Solar PV modules by the
consignee/ end user and shall be supported by relevant certificate
3. Date of commissioning would mean completion of testing & commissioning and
shall be supported by relevant commissioning document
P.O.- Purchase order
Signature of Bidder
25
Annexure D-(ii)
Performa for details of supply & commissioning of Solar Photo voltaic modules
Group-2 :200 nos. of 10 KWp system with battery backup
SN
1
2
3
A
B
C
P.O./
Contract
quantity
P.O.
with
date
Customer
Name &
Address,
Contract
NO.
With/
Without
battery
PV
Year wise supplied/commissioning
Remarks
capacity of PV modules
for
01.04.2011 01.04.2012 01.04.2013
single
to
to
to
system 31.03.2012 31.03.2013 31.03.2014
(as per
X1
X2
X3
para
5.1.2.(ii))
Total Capacity
Total Commissioned in last 3 years(X1+X2+X3)
Nos of “systems” of 10-50 KWp capacity: Total
supplied & Commissioned/years
Note: 1. Supporting documents e.g P.O, proof of supply & commissioning/performance etc.
to be enclosed. All documents shall be in English. If documents are in languages
other than English, a true translation of above key information duly certified shall also
be submitted.
2. Date of supply would mean date of receipt of Solar PV modules by the
consignee/ end user and shall be supported by relevant certificate
3. Date of commissioning would mean completion of testing & commissioning and
shall be supported by relevant commissioning document
P.O.- Purchase order
Signature of Bidder
26
Annexure-D-(iii)
Financial Capacity of the Applicant
For Group-1 & Group-2 (In Rs. crore)
Net turn over (Rs crores)
Bidder
Year1
Year2
(i)
(ii)
Year3
Total turn
over (Rs
crores)
(iii)
(i)+(ii)+(iii)
Avg. turn over
(Rs crores)
TOTAL
Instructions:
1.
As a support of above details, the bidder (single utility) shall submit certificate(s) duly signed
by its statutory auditor.
Signature of Bidder
27
Annexure D-(iv)
Performa for details of supply & commissioning of Solar Photo voltaic modules
Group-3 : 5 nos. of 500 KWp system
SN
1
2
3
A
B
C
P.O./
Contract
quantity
P.O.
with
date
Customer
Name &
Address,
Contract
NO.
With/
Without
battery
PV
Year wise supplied/commissioning
Remarks
capacity of PV modules
for
01.04.2011 01.04.2012 01.04.2013
single
to
to
to
system 31.03.2012 31.03.2013 31.03.2014
(as per
X1
X2
X3
para
5.1.2.(ii))
Total Capacity
Total Commissioned in last 3 years(X1+X2+X3)
Nos of “systems” of ≥ 500 KWp capacity: Total
supplied & Commissioned/years
Note: 1. Supporting documents e.g P.O, proof of supply & commissioning/performance etc.
to be enclosed. All documents shall be in English. If documents are in languages
other than English, a true translation of above key information duly certified shall also
be submitted.
2. Date of supply would mean date of receipt of Solar PV modules by the
consignee/ end user and shall be supported by relevant certificate
3. Date of commissioning would mean completion of testing & commissioning and
shall be supported by relevant commissioning document
P.O.- Purchase order
Signature of Bidder
28
Annexure-D-(v)
Financial Capacity of the Applicant
For Group-3
(In Rs. crore)
Net turn over (Rs crores)
Bidder
Year1
Year2
(i)
(ii)
Year3
Total turn
over (Rs
crores)
(iii)
(i)+(ii)+(iii)
Avg. turn over
(Rs crores)
TOTAL
Instructions:
1.
As a support of above details, the bidder (single utility) shall submit certificate(s) duly signed
by its statutory auditor.
Signature of Bidder
29
ANNEXURE- E
PROFORMA FOR EQUIPMENT AND QUALITY CONTROL
Tender No. ………………………………Date …………………………..
Name of the firm …………………………………………………………………
( Note : All details required only for the items tendered)
1.
2.
2.1
3.
4.
5.
6.
7.
7.1
7.2
8.
9.
9.1
9.2
9.3
10.
11.
12.
Name & address of the firm:
Telephone No. Office/Factory/Works.
Telegraphic Address.
Location of the Manufacturing Factory.
Details of Industrial License, where required as per Statutory Regulations
Details of Plant and Machinery executed and function in each department
(Monographs & description pamphlets be supplied, if available).
Details and stocks of raw material held.
Production capacity of item(s) quoted for, with the existing plant and machinery.
Normal.
Maximum.
Details of arrangement for quality control of products such as laboratory etc.
Details of Technical Supervisory staff-in-charge of production and quality control.
Skilled labour employed.
Un-skilled labour employed.
Maximum number of workers (Skilled & un-skilled) employed on any day during the
19 months preceding the date of bid.
Whether stores were tested to any standard specification, if so, copies of original
test certificates should be submitted in triplicate.
Are you registered with the Directorate General of Supplies and Disposals, New
Delhi, for these stores, if so, furnish full particulars of registration period of currency
etc.
Are you a Small Scale Unit registered with the National Small Industries Corporation
Ltd., for the items offered against this tender, if so,, furnish full particulars of
registration with currency period.(Attach copy of registration certificate)
Signature of Bidder
30
ANNEXURE- F
PROFORMA FOR PRODUCTION CAPACITY
TENDER NO.--------------------------------& DATE……………………………
1.
Name & address of the Manufacturer
2.
Location of the Factory.
3.
Have the items of stores offered by the Tenderer been approved by the Railway
designs and standard Organizations (RDSO), Lucknow? If so, necessary reference
may be quoted?
4.
(a) The installed monthly capacity for Solar PV modules is _____________
and the type of Solar PV modules covered in this tender is_____________.
(b)
For the type of Solar PV modules covered in this tender, indicate the capacity
separately on a single shift basis and on multiple shift basis, if so worked.
5.
What is the average monthly production of Solar PV modules during the last 5 (five)
years on single shift basis?
6.
What is the existing load for Solar PV modules production ?
7.
How much of the above is covered by order of the Railways ?
8.
What portion of the actual production capacity will be reserved for this contract ?
This should be indicated clearly in terms of number of items or stores per month.
9.
Have you supplied the stores tendered for or other identical items in the past ? If so,
details of supplies in the last 12 months may be furnished.
(1)
Description
(2)
Total quantity ordered.
(3)
Total quantity supplied.
(4)
Total quantity pending on the date of tendering.
Signature of the Bidder.
31
Annexure G
Power of Attorney for signing of Application
Know all men by these presents, We…………………………………………….. (name of the
firm and address of the registered office) do hereby irrevocably constitute, nominate,
appoint and authorise Mr/ Ms (name), …………………… son/daughter/wife of
……………………………… and presently residing at …………………., who is (presently
employed with us/ the Lead Member of our Consortium and holding the position of
……………………………. ), as our true and lawful attorney (hereinafter referred to as the
“Attorney”) to do in our name and on our behalf, all such acts, deeds and things as are
necessary or required in connection with or incidental to submission of our application for
submission of our bid for procurement, installation, testing and commissioning of Solar PV
modules at zonal Railways headquarters offices and DLW, ICF, RCF and RDSO Lucknow
and various remote stations on Indian Railway proposed or being developed by the Ministry
of Railways (the “Purchaser”) including but not limited to signing and submission of all
applications, bids and other documents and writings, participate in Pre- Purchaser and
other conferences and providing information/ responses to the Purchaser, representing us
in all matters before the Purchaser, signing and execution of all contracts including the
Agreement and undertakings consequent to acceptance of our bid, and generally dealing
with the Purchaser in all matters in connection with or relating to or arising out of our bid for
the said Project and/ or upon award thereof to us and/or till the entering into of the
Agreement with the Purchaser.
AND we hereby agree to ratify and confirm and do hereby ratify and confirm all acts, deeds
and things done or caused to be done by our said Attorney pursuant to and in exercise of
the powers conferred by this Power of Attorney and that all acts, deeds and things done by
our said Attorney in exercise of the powers hereby conferred shall and shall always be
deemed to have been done by us.
IN WITNESS WHEREOF WE, …………………………., THE ABOVE NAMED PRINCIPAL
HAVE EXECUTED THIS POWER OF ATTORNEY ON THIS ……… DAY OF ………….,
2……..
For …………………………..
(Signature)
(Name, Title and Address)
(Signature, name and designation of the authorised signatory)
Witnesses:
1.
(Notarised)
2.
Accepted
……………………………
(Signature)
32
(Name, Title and Address
of the Attorney)
Notes:

The mode of execution of the Power of Attorney should be in accordance with the
procedure, if any, laid down by the applicable law and the charter documents of the
executant(s) and when it is so required, the same should be under common seal affixed
in accordance with the required procedure.

Wherever required, the Applicant should submit for verification the extract of the charter
documents and documents such as a board or shareholders’ resolution/ power of
attorney in favour of the person executing this Power of Attorney for the delegation of
power hereunder on behalf of the Applicant.

For a Power of Attorney executed and issued overseas, the document will also have to
be legalised by the Indian Embassy and notarised in the jurisdiction where the Power of
Attorney is being issued. However, the Power of Attorney provided by Applicants from
countries that have signed the Hague Legislation Convention 1961 are not required to
be legalised by the Indian Embassy if it carries a conforming Appostille7 certificate.
33
ANNEXURE H
PROFORMA OF BANK GUARANTEE FOR BID GUARANTEE
(On Bank’s Letter Head with Adhesive stamp)
Ref……………
Date………….
Bank Guarantee No………
To,
The President Of India
Acting through the Director, Railway Stores (F),
Ministry of Railways(Railway Board)
Rail Bhavan,
New Delhi-110001.
Dear Sir,
In accordance with your invitation to tender No……………………. for supply of
………………..M/s…………………………hereinafter called the bidder with the
following Directors on their Board of Directors/Partners of the firm:
1.
2.
3.
4.
Wish to participate in the said tender for the supply of ----------------------------------------------------------------As a Bank Guarantee against Bid Guarantee for a sum of ……………………… .(
in words and figures) valid for (225 ) Two hundred and twenty five days from
…………….. required to be submitted by the bidder as a condition for the
participation, this Bank hereby guarantees and undertakes during the above said
period of (225) two hundred and twenty five days to immediately pay, on demand by
the Director, Railway Stores (F), Ministry of Railways ( Railway Board), New Delhi110001, INDIA, in writing the amount of ………………………………………..( in
words and figures) to the said Director, Railway Stores (F), Ministry of Railways
(Railway Board), New Delhi-110001, INDIA and without any reservation and
recourse if :
(i)
the bidder after submitting his tender, modifies the rates or any of the terms
and conditions thereof, except with the previous written consent of the
purchaser; or
(ii)
the bidder withdraws the bid within 225 days after opening of bid; or
(iii)
the bidder having not withdrawn the bid, fails to execute the contractual
documents within the period provided in the contract; or
(iv)
having executed the contracts fails to give the bonds so aforesaid within the
period provided in the contract.
34
This guarantee shall be irrevocable and shall remain valid upto 4.00 PM on
……………….if further extension to this guarantee is required, the same shall be
extended to such required period on receiving instructions from
M/s………………………………. on whose behalf this guarantee is issued.
Date
Place
Signature………………….
Witness
Printed name……………….
(Designation)
………………………
(Bank’s common seal)
35
ANNEXURE I
(To be filled electronically only)
36
Annexure-J
Tentative location of Solar Photo voltaic modules
Group-1
Provision of solar PV modules of 100 kWp & 45 kWp Solar PV module without battery back
up at 20 nos. Administrative buildings i.e. General Manager Hdqrs. Office’s or adjacent
buildings and RDSO, Lucknow.
SN
Railway
Concerned Railway
Capacity
Address
Telephone No.
officer
of Splar
(DOT)
panel in
Kwp
Sub Group-A (Maharashtra)
1
Central
Railway(CR)
Chief Electrical
Engineer
100
2
Western
Railway (WR)
Chief Electrical
Engineer
100
Hdqrs. office,
CR Mumbai
CST.
Hdqrs. office,
WR,
Churchgate,
Mumbai.
022-22620867
07752-41035
Sub Group-B (West Bengal)
3
Eastern
Railway(ER)
Chief Electrical
Engineer
100
Hdqrs. office,
ER Kolkata
022-22300446
4
South Eastern
Railway
Chief Electrical
Engineer
100
Hdqrs. office,
SER, Kolkata
040-27825243
5
Metro Railway
Chief Electrical
Engineer
100
Metro Railway,
Hdqrs. office,
Kolkata
033-22264673
Chief Electrical
Engineer
100
Hdqrs. office,
ECR Hajipur.
06224-274456
Chief Electrical
Engineer
100
Hdqrs. Office,
ECoR
Bhubaneswar
0674-2303515
Chief Electrical
Engineer
100
Hdqrs. office,
NR, Baroda
House, New
Delhi
011- 23387198
Sub Group-C (Bihar)
6
East Central
Railway (ECR)
Sub Group-D (Orissa)
7
East Coast
Railway(ECoR)
Sub Group-E (Delhi)
8
Northern
Railway (NR)
Sub Group-F (Uttar Pradesh)
9
North Central
Railway (NCR)
Chief Electrical
Engineer
100
Hdqrs. office,
NCR, Allahabad
0532-2230217
10
North Eastern
Railway (NER)
Chief Electrical
Engineer
100
Hdqrs. office
,NER,
Gorakhpur
0551-2200552
37
11
Diesel
Locomotive
Works (DLW)
Sub Group-G (Assam)
12
Northeast
Frontier
Railway (NFR)
Chief Electrical
Engineer
100
Administrative
Building, DLW,
Varanasi.
0542-2270170
Chief Electrical
Engineer
100
Hdqrs. office,
NFR, Maligaon,
Guwahati,
(Assam)
0361-2676029
Chief Electrical
Engineer
100
Hdqrs. office,
NWR, Jaipur
0361-2676029
Sub Group-H (Rajasthan)
13
North Western
Railway (NWR)
Sub Group-I (Tamil Nadu)
14
Southern
Railway (SR)
Chief Electrical
Engineer
100
Hdqrs. office,
SR, Chennai
0141-2725865
15
Integral Coach
Factory (ICF)
Chief Electrical
Engineer
100
Administrative
Building, ICF,
Chennai
044-26260675
100
Hdqrs. office,
SCR,
Secunderabad
044-25353717
100
Hdqrs. office,
SWR, Hubli
033-24391566
100
Hdqrs. office,
SECRR,
Bilaspur
0836-2365212
Chief Electrical
Engineer
100
Hdqrs. office,
WCR, Jabalpur
Chief Electrical
Engineer
100
Administrative
Building, RCF,
Kapurthala
01822-228201
45
Administrative
Building
,RDSO,
Lucknow
0522-2465714
Sub Group-J (Andhra Pradesh)
16
South Central
Railway (SCR)
Chief Electrical
Engineer
Sub Group-K (Karnataka)
17
South Western
Railway (SWR)
Chief Electrical
Engineer
Sub Group-L (Chhattisgarh)
18
South East
Chief Electrical
Central
Engineer
Railway
(SECR)
Sub Group-M (Madhya Pradesh)
19
West Central
Railway
Sub Group-N (Punjab)
20
Rail Coach
Factory (RCF)
Sub Group-O (Uttar Pradesh)
21
Research
Development
& Standard
Organization
(RDSO)
Exec. Director, (EEM)
38
Group-2
Provision of 10 KWp solar PV modules at no. of stations non-electrified section( Non-RE )
S.N.
Rly.
Sub Group-P(UP)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
NER
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
State
Name of Station
Category of
Station
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
Nakaha Jungle
Maniram
Peppeganj
Campierganj
Lachhmipur
Brijmanganj
Uska Bazar
Chilhia
Shohratgarh
Parsa
Pachperwa
Gainsari
Tulsipur
Kauwapur
Jharkhandi
Intiathok
Subhagpur
Gangadham
Bangain
Bishewarganj
Payagpur
Chilwaria
Risia
Matera
Mihinpurwa
Kakarha R. house
E
E
D
E
E
E
E
E
D
E
E
E
D
E
E
E
E
E
E
E
D
E
D
E
D
E
UP
UP
UP
UP
UP
UP
UP
UP
Murtiha
Nishangara
Bichhiya
Tikunia
Belrayan
Sonaripur
Dudwa
Palia Kalan
E
E
D
D
E
E
E
B
Division
Lucknow
39
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
Varanasi
62
63
64
65
66
67
68
69
70
Sub Group-Q (Rajasthan)
71
72
73
74
NWR
JU
75
76
77
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Bhira Kheri
Rajnarainpur
Golagokaran Nath
Razganj
Pharedahan
Deokali
Khiri Town
Oel
Hargaon
Jharekapur
Khairabad Awadh
Kamlapur
Sidhauli
Ataria
Itaunja
Bakshi Ka Talab
Mohibullapur
Dudahi
Kathkuiyan
Barharaganj
Ramkola
Lakshmiganj
Paniahwa
Khadda
Siswa Bazar
Ghughli
Bodawar
Pipraich
Unaula
Khurhat
Sathiaon
Sarai Rani
Phariha
Sarai Mir
Khorason Road
Didarganj Road
E
E
D
E
E
E
E
E
D
E
E
E
D
E
E
E
D
E
E
E
E
E
E
D
D
D
E
D
E
E
E
E
E
D
B
E
Bomadra
Rajkiawas
Kheduli
Ren
Jalsu
Gachhipura
Besroli
E
E
E
E
E
E
E
40
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
BKN
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Borawar
Kuchaman City
Naya Khardia
Govindi Marwar
Satlana
Dudia
Dundara
Ajit
Parlu
Janiyana
Khed temple
Tilwara
Gole
Bhimarlai
Bamsin
Rakhi
Mokalsar
Balwara
Bishangath
Bheempura
Ledarmer
Malwara
Marwar Ratanpur
Bhikamkor
Samrau
Shatan SinghNagar
Odania Chacha
Shri Bhadaria Lathi
Jetha Chandan
Thaiyat Hamira
Kiroda
Khatu
Tal Chhapar
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Nal
Gajner
Kolayat
Dyatra Road
Nokhra
Sird
Bap
Malar
Kanasar
Jamsar
Jagdevwala
E
E
E
E
E
E
E
E
E
E
E
41
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
Sub Group-R (Haryana)
148
149 NWR
BKN
150
Sub Group-S (Assam)
151
152
153
154
TSK
155
156
157
NFR
158
159
160
LMG
161
162
163
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Dhirera
Dulmera
Lunkaransar
Nathawana
Malkisar
Mahajan
Rajaisar
Arjunsar
Gadwala
Napasar
Sudsar
Benisar
Sridungargarh
Bigga
Persneu
Rajaldelsar
Molisar
Juharpur
Depalsar
Asalu
Dhudhwakhara
Hadyal
Dokawa
Surtpura
Harpalu
Rampura Beri
E
E
D
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
Haryana
Haryana
Haryana
Pervejpur
Sohansara
Satnali
E
E
E
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
SLGR
BOJ
LAX
DBRD
NAM
MRG
NTSK
BRLF
LCT
NLN
PKB
LKG
HWX
D
E
E
A
E
E
A
E
E
E
E
E
E
42
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
Assam
DHRY
MYD
HTL
LGT
PDJ
MXR
MGE
BF
HFG
JTG
LJO
MGX
HJO
DTC
BXJ
BXK
DCA
SHTT
JQD
AMONI
RAHA
PUY
BEE
SCE
SNBR
ALGP
KTX
HKD
SCA
LLBR
MSSN
DLCR
BRGM
TBX
PKGM
ARCL
PNGM
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
43
Group-3
SN
1
2
3
4
5
Sub
Group
T
U
V
W
X
State
Delhi
Rajasthan
Andhra
Pradesh
Maharashtra
West Bengal
Rly.
NR
NWR
Locations
New Delhi Railway station building
Lalgarh (Bikaner Division)
SCR
CR
Metro Rly.
Secunderabad station, PRS Boiguda side.
ZRT/Bhusawal school building
Noapara Carshed Metro Railway Kolkata
44
Annexure-K
PROFORMA OF BANK GUARANTEE FOR CONTRACT PERFORMANCE GUARANTEE BOND
Ref...............
Date-----------------Bank Guarantee No................
To,
THE PRESIDENT OF INDIA.
acting through the Director, Railway Stores (F)
Ministry of Railway,
(Railway Board). Rail Bhawan,
New Delhi-110001, INDIA.
1. Against contract vide Advance Acceptance of the Tender No...................................
dated.................................... covering supply of.........................................................
(hereinafter called the said ‘contract’) entered into between the President of India
and...........................................................................(hereinafter called the ‘Contractor) this is
to certify that at the request of the Contractor we............................................................. Bank
Ltd., are holding in trust in favour of the President of India, the amount
of.......................................................................................................... (write the sum here in
words) to indemnity and keep indemnified the President of India (Govt. of India) against any
loss or damage that may be caused to or suffered by the President of India (Govt. of India)
by reason of any breach by the Contractor of any of the terms and conditions of the said
contract and/or the performance thereof. We agree that the decision of the President of India (Govt. of
India), whether any breach of any of the terms and conditions of the said contract and/or in the
performance thereof has been committed by the Contractor and the amount of loss or damage that
has been caused or suffered by the President of India (Govt. of India) shall be final and binding on
us and the amount of the said loss or damage shall be paid by us forthwith on demand and without
demur to the President of India (Govt. of India).
2.We............................ ........................................Bank Ltd., further agree that the
guarantee herein contained shall remain in full force and effect during the period that would be taken
for satisfactory performance and fulfilment in all respects of the said contract by the
Contractor i.e. till.............................................(viz. the date up to 12 months after the
date of last delivery, of the goods ordered) hereinafter called the ‘said date’ and that if any claim
accrues or arises against us.................................... Bank Ltd., by virtue of this guarantee
before
the
said
date,
the
same
shall
be
enforceable
against
us......................................................Bank Ltd.), notwithstanding the fact that the same is
enforced within six months after the said date, provided that notice of any such claim has been
given to us.......................................Bank/Ltd., by the President of India (Govt. of India) before
the said date. Payment under this letter of guarantee shall be made promptly upon our receipt of
notice to that effect from the president of India (Govt. of India).
3. It is fully understood that this guarantee is effective from the date of the said contract
and that we................................................Bank Ltd., undertake not to revoke this
guarantee during its currency without the consent in writing of the President of India (Govt. of
India).
4. We undertake to pay to the Government any money so demanded notwithstanding
any dispute or disputes raised by the Contractor in any suit or proceeding pending before any
Court or Tribunal relating thereto our liability under this present being absolute and
45
unequivocal. The payments so made by us under this bond shall be a valid discharge of our liability
for payment thereunder and the Contractor shall have no claim against us for making such payment.
5. We....................................Bank Ltd., further agree that the President of India(Govt. of India) shall
have the fullest liberty, without affecting in any manner our obligations hereunder to vary any of the
terms and conditions of the said contract or to extend time of performance by the Contractor from
time to time or to postpone for any time or form time to time any of the powers exercisable by the
President of India (Govt. of India), against the said Contractor and to for bear or enforce any of the
terms and conditions relating to the said contracts and we....................................Bank Ltd., shall not be
released from our liability under this guarantee by reason of any such variation or extension being
granted to the said Contractor or for any forbearance and/ or omission on the part of the President of
India or any indulgence by the President of India >>>>>>>>>> the said Contractor or by any other
matter or thing what-so-ever, which under the law relating to sureties, would, but for this provision
have the effect of so releasing us from our liability under this guarantee.
6. This guarantee will not be discharged due to the change in the constitution of the Bank or the
Contractor.
Date...........................
Signature.............................
Place...........................
Printed Name........................
Witness........................
(Designation)
........................................
…………………………….
Bank’s Common Seal
46
Annexure-L
PROFORMA OF BANK GUARANTEE FOR 10% CONTRACT VALUE TOWARDS
WARRANTY GUARANTEE
To,
THE PRESIDENT OF INDIA,
acting through the Director, Railway Stores (F),
Ministry of Railway,
(Railway Board), Rail Bhawan, Raisina Road,
New Delhi-110001, INDIA.
Sub.— Guarantee No.......................................for..................... (Amount).
Covering equipment (s) Serial no......................................................................supplied
to...........,.............................................................(Consignee/s)
Ref.— Contract No.........................................................dated..............................
Placed on M/s..........................................................................................
1. WHEREAS M/s...............................................................one of our constituents,
(hereinafter called the “Sellers”) have agreed to sell to you (hereinafter referred to as the
“Government”) Nos. of........................................................................ (give description)
as per contract No.....................................................................................
dated.........................................................(hereinafter called “the said contract”)
2. AND WHEREAS according to the terms of said contract, it has been stipulated that payment of
the stores would be made, provided that the Sellers furnish to the Purchaser a Bank
Guarantee from a recognised bank, acceptable to the Purchaser for 10 per cent of the value of
the said contract, valid for a period covering in full the Guarantee Period as per the warranty
clause of the said conditions of the contract, being the conditions attached to and forming part of
the said contract.
3. AND WHEREAS the Sellers have approached us to give the said Bank Guarantee on their
behalf in your favour for an amount representing 10 per cent of the value of the said
contract which you have agreed to accept.
4. That in consideration of the promises and at the request of the said Sellers, we
hereby irrevocably undertake and guarantee to pay to the Government of India or at
such other place as may be determined by you forthwith on demand and without any
demur, any sum upto a maximum amount of........................ representing 10 per cent
of the value of the stores despatched under the said contract in case the seller make
default in paying the said sum or make any default in the performance, observance
or discharge of the guarantee contained in the said contract.
5. We agree that the decision of the Government, whether any default has occurred or has
been committed by the Sellers in the performance, observance or discharge of the
guarantee aforesaid shall be conclusive and binding on us M/s.................................
6. Government shall be at liberty, from time to time, to grant or allow extension of time
or give other indulgence to the said Sellers or to modify the terms and conditions of the
contract with the said Sellers without affecting or impairing this guarantee or our liability
hereunder.
7. We undertake to pay to the Government any money so demanded notwithstanding any
dispute or disputes raised by the Sellers in any suit or proceeding pending before any
47
Court or Tribunal relating thereto our liability under this present being absolute and
unequivocal. We also undertake to pay to the Government any money so demanded against
the Purchaser’s claims in any other contracts placed on the said sellers.
The payment so made by us under this bond shall, be a valid discharge of our liability for
payment thereunder and the Sellers shall have no claim against us for making such payment.
8. This bank guarantee comes into force when the balance ten percent of the value of
the
stores,
dispatched
per
dispatched
Invioce
No.........................................................dated..........................................
or
R/RNo..............................dated........................ under the said contract, has been
paid and will remain in full force and effect up to..............................i.e.
for..............................months counted from the date of placing the stores in service,
and shall continue to be enforceable for further five months i.e. up
to..................................(date), hereinafter called the said date.
9. This guarantee will not be discharged due to the change in the constitution of the
Bank or the Sellers.
10. That no claim under this guarantee shall be entertained by us unless the same has
been preferred by the Government within the said date.
Date...........................
Signature.............................
Place...........................
Printed Name.........................
Witness........................
(Designation)
........................................
Bank’s Common Seal
48
ANNEXURE-M
Requirement to be met in case of MOU :
The MOU in case of consortium/Joint Venture should define at least following
responsibilities of each of the member of consortium:
a. The responsibility of member for supply for materials and service as per bid documents.
b. The consortium/joint venture shall own the complete responsibility for undertaking the
manufacture, supply, installation, commissioning, maintenance, after sales service for
provision of PV modules and supply of spares for the period of MOU.
c. The manufacturer shall ensure continuous availability of spares through any member of
consortium and will ensure technical support to Indian Railways for the period of MOU.
d. The consortium shall undertake the responsibility of imparting necessary training and
support to the personnel of the Railways.
e. The members of the Consortium shall be jointly and severally liable and responsible for
the purpose of this tender and execution of the work.
f. Each consortium will nominate a lead bidder/lead member who shall be responsible for
submitting the bid and interaction with the Indian Railways.
g. The MOU shall be valid at least for a period of 5 years or till the completion of AMC
period.
Note: The other additional conditions, if any, in the MOU shall not be contradictory to the
above conditions.
49
ANNEXURE N
Joint Bidding Agreement
(To be executed on Stamp paper of appropriate value)
THIS JOINT BIDDING AGREEMENT is entered into on this the ………… day of …………
20…
AMONGST
1.
{………… Limited, a company incorporated under the Companies Act, 1956} and
having its registered office at ………… (hereinafter referred to as the “First Part”
which expression shall, unless repugnant to the context include its successors and
permitted assigns)
AND
2.
{………… Limited, a company incorporated under the Companies Act, 1956} and
having its registered office at ………… (hereinafter referred to as the “Second Part”
which expression shall, unless repugnant to the context include its successors and
permitted assigns)
:
:
:
The above mentioned parties of the FIRST, SECOND,…. PART are collectively referred
to as the “Bidder” and each is individually referred to as a “Member”.
WHEREAS,
(A)
THE MINISTRY OF RAILWAYS, GOVERNMENT OF INDIA, represented by its
Director, Railway Stores (F) Railway Board and having its principal offices at Rail Bhavan,
Raisina Road, New Delhi-110001 (hereinafter referred to as the “Purchaser” which
expression shall, unless repugnant to the context or meaning thereof, include its
administrators, successors and assigns) has invited bids (the Bids”) for supply and
maintenance of Solar photo voltaic modules (the “Tender”).
(B)
The Bidder are interested in jointly bidding for the Tender as members of a
Consortium and in accordance with the terms and conditions of the bid documents in
respect of the Tender, and
NOW IT IS HEREBY AGREED as follows:
1.
Definitions and Interpretations
In this Agreement, the capitalized terms shall, unless the context otherwise requires,
have the meaning ascribed thereto under the TENDER.
2.
Consortium
2.1
The Bidder do hereby irrevocably constitute a consortium (the “Consortium”) for the
purposes of jointly participating in the Bidding Process for the Tender.
2.2
The Bidder hereby undertake to participate in the Bidding Process only through this
Consortium and not individually and/ or through any other consortium constituted for
this Tender, either directly or indirectly or through any of their Associates.
3.
Role of the Bidder
50
The Bidder hereby undertake to perform the roles and responsibilities as described
below:
(a)
Party of the First Part shall be the Lead member of the Consortium. He shall
have the power of attorney from all Bidder for conducting all business for and
on behalf of the Consortium during the Bidding Process ;
(b)
Party of the Second/Third Part shall be Manufacturer of Solar photo voltaic
modules /Indian partner/ Finance firm of the Consortium serving;
4.
Special condition for roles of Members: The member shall satisfy the eligibility
criteria given at para 5.1.1 & 5.1.2.
5.
Joint and Several Liability
The Bidder do hereby undertake to be jointly and severally responsible for all
obligations and liabilities relating to the Tender and in accordance with the terms of
the bidding document and the Agreement, till such time as the Agreement comes
into force and effect.
6.
Representation of the Bidder
Each Party represents to the other Bidder as of the date of this Agreement that:
(a)
Such Party is duly organised, validly existing and in good standing under the
laws of its incorporation and has all requisite power and Purchaser to enter
into this Agreement;
(b)
The execution, delivery and performance by such Party of this Agreement has
been authorised by all necessary and appropriate corporate or governmental
action and a copy of the extract of the charter documents and board
resolution/ power of attorney in favour of the person executing this Agreement
for the delegation of power and Purchaser to execute this Agreement on
behalf of the Consortium Member is annexed to this Agreement, and will not,
to the best of its knowledge:
(i)
require any consent or approval not already obtained;
(ii)
violate any Applicable Law presently in effect and having applicability
to it;
(iii)
violate the memorandum and articles of association, by-laws or other
applicable organisational documents thereof;
(iv)
violate any clearance, permit, concession, grant, license or other
governmental authorisation, approval, judgement, order or decree or
any mortgage agreement, indenture or any other instrument to which
such Party is a party or by which such Party or any of its properties or
assets are bound or that is otherwise applicable to such Party; or
(v)
create or impose any liens, mortgages, pledges, claims, security
interests, charges or Encumbrances or obligations to create a lien,
charge, pledge, security interest, encumbrances or mortgage in or on
the property of such Party, except for encumbrances that would not,
individually or in the aggregate, have a material adverse effect on the
financial condition or prospects or business of such Party so as to
prevent such Party from fulfilling its obligations under this Agreement;
51
7.
(c)
this Agreement is the legal and binding obligation of such Party, enforceable
in accordance with its terms against it; and
(d)
there is no litigation pending or, to the best of such Party's knowledge,
threatened to which it or any of its Affiliates is a party that presently affects or
which would have a material adverse effect on the financial condition or
prospects or business of such Party in the fulfillment of its obligations under
this Agreement.
Termination
This Agreement shall be effective from the date hereof and shall continue in full force
and effect until the Agreement comes into effect and force, in case the Tender is
awarded to the Consortium. However, in case the Consortium is either not prequalified for the Tender or does not get selected for award of the Tender, the
Agreement will stand terminated in case the Bidder is not pre-qualified or upon return
of the Bid Security by the Purchaser to the Bidder, as the case may be.
8.
Miscellaneous
8.1
This Joint Bidding Agreement shall be governed by laws of India.
8.2
The Bidder acknowledge and accept that this Agreement shall not be amended by
the Bidder without the prior written consent of the Purchaser.
Note: The other additional conditions in para 4. above of the Special conditions, if any, in
the JBA shall not be contradictory to the any of the conditions specified in this document.
IN WITNESS WHEREOF THE BIDDER ABOVE NAMED HAVE EXECUTED AND
DELIVERED THIS AGREEMENT AS OF THE DATE FIRST ABOVE WRITTEN.
SIGNED, SEALED AND DELIVERED
SIGNED, SEALED AND DELIVERED
For and on behalf of
LEAD MEMBER by:
SECOND PART
(Signature)
(Signature)
(Name)
(Name)
(Designation)
(Designation)
(Address)
(Address)
Notes:
1.
The mode of the execution of the Joint Bidding Agreement should be in
accordance with the procedure, if any, laid down by the Applicable Law and the
charter documents of the executant(s) and when it is so required, the same
should be under common seal affixed in accordance with the required
procedure.
2.
Each Joint Bidding Agreement should attach a copy of the extract of the charter
documents and documents such as resolution / power of attorney in favour of
the person executing this Agreement for the delegation of power and Purchaser
to execute this Agreement on behalf of the Consortium Member.
52
3.
For a Joint Bidding Agreement executed and issued overseas, the document
shall be legalised by the Indian Embassy and notarized in the jurisdiction where
the Power of Attorney has been executed. However, the Power of Attorney
provided by Bidders from countries that have signed the Hague Legislation
Convention 1961 are not required to be legalised by the Indian Embassy if it
carries a conforming Appostille certificate.
**********
53
ANNEXURE O
Power of Attorney for Lead Member of Consortium
Whereas the Ministry of Railways (“the Purchaser”) has invited applications from interested
parties for the Application for supply, installation, testing commissioning & maintenance of
solar photo voltaic modules at zonal Railway headquarter office, DLW, ICF, RCF, RDSO
and
various stations on Indian Railway as per RDSO specification no.
RDSO/PE/SPEC/PS/0092-2008 (Rev.0) Amendment ‘4’ Whereas, …………………….., and
…………………….. (collectively the “Consortium”) being Members of the Consortium are
interested in bidding for the bid in accordance with the terms and conditions of the bid
document and
Whereas, it is necessary for the Members of the Consortium to designate one of them as
the Lead Member with all necessary power and Purchaser to do for and on behalf of the
Consortium, all acts, deeds and things as may be necessary in connection with the
Consortium’s bid for the bid and its execution.
NOW, THEREFORE, KNOW ALL MEN BY THESE PRESENTS
We, …………………….. having our registered office at ……………………..,
M/s.
…………………….. having our registered office at ……………………..,
(hereinafter
collectively referred to as the “Principals”) do hereby irrevocably designate, nominate,
constitute, appoint and authorise M/S …………………….. having its registered office at
…………………….., being one of the Members of the Consortium, as the Lead Member
and true and lawful attorney of the Consortium (hereinafter referred to as the “Attorney”).
We hereby irrevocably authorise the Attorney (with power to sub-delegate) to conduct all
business for and on behalf of the Consortium and any one of us during the bidding process
and, in the event the Consortium is awarded the contract, during the execution of the bid
and in this regard, to do on our behalf and on behalf of the Consortium, all or any of such
acts, deeds or things as are necessary or required or incidental to the pre-qualification of
the Consortium and submission of its bid, including but not limited to signing and
submission of all applications, bids and other documents and writings, participate in bidders
and other conferences, respond to queries, submit information/ documents, sign and
execute contracts and undertakings consequent to acceptance of bid of the Consortium and
generally to represent the Consortium in all its dealings with the Purchaser, and/ or any
other Government Agency or any person, in all matters in connection with or relating to or
arising out of the Consortium’s bid and/ or upon award thereof till the Agreement is entered
into with the Purchaser.
AND hereby agree to ratify and confirm and do hereby ratify and confirm all acts, deeds and
things done or caused to be done by our said Attorney pursuant to and in exercise of the
powers conferred by this Power of Attorney and that all acts, deeds and things done by our
said Attorney in exercise of the powers hereby conferred shall and shall always be deemed
to have been done by us/ Consortium.
IN WITNESS WHERE OF WE THE PRINCIPALS ABOVE NAMED HAVE EXECUTED
THIS POWER OF ATTORNEY ON THIS ……….. DAY OF ……….2………..
For ……………………..
(Signature)
……………………..
(Name & Title)
54
For ……………………..
(Signature)
……………………..
(Name & Title)
For ……………………..
(Signature)
……………………..
(Name & Title)
Witnesses:
1.
2.
………………………………………
(Executants)
(To be executed by all the Members of the Consortium)
Notes:

The mode of execution of the Power of Attorney should be in accordance with the
procedure, if any, laid down by the applicable law and the charter documents of the
executant(s) and when it is so required, the same should be under common seal affixed
in accordance with the required procedure.

Also, wherever required, the Applicant should submit for verification the extract of the
charter documents and documents such as a board or shareholders’ resolution/ power
of attorney in favour of the person executing this Power of Attorney for the delegation of
power hereunder on behalf of the Applicant.

For a Power of Attorney executed and issued overseas, the document will also have
to be legalised by the Indian Embassy and notarised in the jurisdiction where the Power of
Attorney is being issued. However, the Power of Attorney provided by Applicants from
countries that have signed the Hague Legislation Convention 1961 are not required to be
legalised by the Indian Embassy if it carries a conforming Appostille certificate.
55
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
INDIAN RAILWAY STANDARD CONDITIONS OF CONTRACT:
(Vide Para 417 of the Indian Railway Code for the Stores Department)
DESCRIPTION
Definitions and Interpretation:
CLAUSE DESCRIPTION
0100 Freight:
Removal
of
0200
Stores:
Parties:
Quotations
Contractors:
of
rates
by
0300
CLAUSE
2100
Rejected
System of Payment:
2200
2300
Contract:
0400
Security Deposit:
0500
Delivery:
0600
Time for and Date of Delivery:
0700
Extension of Time for Delivery:
Examination
of
Drawing,
Specifications and Patterns:
Mistakes in Drawing:
Samples:
Risk of Loss or Damage to
Government
or
Purchaser's
Property:
Inspection by Inspecting Officer:
Charges for Work Necessary for
Completion of the Contract:
Responsibility of the Contractor
for Executing the Contract:
Use of Raw Materials secured
with Government Assistance:
Indemnity:
0800
Withholding and lien in
respect of sums claimed:
Corrupt Practices:
Insolvency and Breach of
Contract:
Laws
governing
the
Contract:
Headings:
0900
Arbitration:
2900
1000
1100
Fall Clause:
Inspection &Rejection:
3000
3100
1200
Warranty/Guarantee:
3200
1300
Book Examination Clause:
Inspection at the Fag End
of the Delivery Period:
3300
Special conditions:
3500
Packing:
1800
Notification of Delivery:
1900
Progress Reports:
2000
1400
1500
1600
1700
Purpose of Contract and
Parties to the Contract:
Delivery:
Increase or Decrease of
Quantities:
Maintenance
and
Replacement of Stocks:
Reporting
Progress
of
Contract:
2400
2500
2600
2700
2800
3400
3600
3700
3800
3900
4000
0100. Definitions
Definitions and Interpretation.
0101. In the Contract, unless the context otherwise requires
;
0102. "Acceptance of Tender" means the letter of memorandum communicating
to the Contractor the acceptance of his tender and includes an advance
acceptance of his tender;
0103. "Consignee" means where the stores are required by the acceptance of
tender to be despatched by rail, road, air or steamer, the person specified in the
Acceptance of Tender to whom they are to be delivered at the destination;
Where the Stores
Stores are required by the acceptance of tender to be delivered to a
person as an interim consignee for the purpose of despatch to another person,
such other persons; and in any other case the person to whom the stores are
required by the acceptance of tender to be delivered in the manner therein
specified
0104. "Contract" means and includes the invitation to tender, instructions to
tenderers, tender, acceptance of tender, Standard Conditions of Contract,
other
her conditions specified in
Special Conditions of Contract, particulars and the ot
the acceptance of tender and includes a repeat order which has been accepted
or acted upon by the contractor and a formal agreement if executed;
0105. The "Contractor" means the person, firm or company with whom the order
for the supply is placed and shall be deemed to include the contractor's
successors (approved by the Purchaser), representatives, heirs, executors and
administrators as the case may be, unless excluded by the terms of the contract
0106. "The SubSub-contractor" means any person, firm or company from whom the
Contractor may obtain any material or fittings to be used in the supply or
manufacture of the stores,
0107. "Drawing" means the drawing or drawings specified in or annexed to the
Schedule or Specifications
0108. "Government" means the Central Government or a State Government, as
the case may be;
0109. "The Inspecting Officer ” means the person specified in the contract for
the purpose of Inspection of stores or work under the contract and includes his
authorised
authorised representative;
0110. "Material" means anything used in the manufacture or fabrication of the
stores
0111. "Particulars" includeinclude(a) Specifications
(b) Drawings
(c) Pattern bearing the seal and signature of
of the Inspecting Officer
(hereinafter called the sealed pattern) which shall include also a certified copy
thereof sealed by the Purchaser for the guidance of the Inspecting Officer;
(d) Sample sealed by the Purchaser for guidance of the Inspecting
Inspecting Officer
(hereinafter called the certified sample) which shall include a certified copy
thereof sealed by the Purchaser for the guidance of the Inspecting Officer;
(e) Trade pattern, that is to say, a pattern, stores conforming to which are
obtainable in the open market and which denotes a standard of the Indian
Standard Institute or other standardising authority or a general standard of the
industry;
(f) "Proprietary mark "or " brand " means the mark or brand of a product
which
which is owned by an industrial firm
(g) any other details governing the construction, manufacture or supply
of stores as may be prescribed by the contract
0112. " Purchase Officer " means the officer signing the acceptance of tender
and
includes
includes
any
officer who has authority to execute the relevant contract on behalf of the
Purchaser
0113. " The Purchaser " means the President of India in the case of stores
ordered for the Indian Government Railways and includes his successors and
assignees
0114. "Signed" includes stamped, except in the case of an acceptance of tender
or any amendment thereof
0115. "Site" means the place specified in the contract at which any work is
otherr place
required to be executed by the contractor under the contract or any othe
approved by the Purchaser for the purpose;
0116. "Stores" means the goods specified in the contract which the contractor
has agreed to supply under the contract;
0117. "Supply Order" means an order for supply of stores and includes an order
for performance of service
0118. "Test" means such test as is prescribed by the particulars or considered
necessary by the Inspecting Officer whether performed or made by the
Inspecting Officer or any agency acting under the direction of the Inspecting
officer;
officer;
0119. "Unit" and "Quantity" means the unit and quantity specified in the contract;
0120. "Writing" or "Written" includes matter either in whole or in part, in
manuscript, typewritten, lithographed, cyclostyled, photographed or printed under
or over
over signature or seal, as the case may be;
0121. The delivery of the stores shall be deemed to take place on delivery of the
stores in accordance with the terms of the contract, after approval by the
Inspecting Officer if so provided in the contract to (a) the consignee at his premises ; or
(b) where so provided the interim consignee at his premises , or
(c) a carrier or other person named in the contract for the purpose of
transmission to the consignee, or
(d) The consignee
consignee at the destination station in case of contract stipulating
for delivery of stores at destination station.
0122. Words in the singular include the plural and vice versa
0123. Words importing the masculine gender shall be taken to include the
feminine
feminine gender and words importing persons shall include any company or
association or body of individuals, whether incorporated or not;
0124. The heading of these conditions shall not affect the interpretation or
construction thereof;
0125. Terms and expression
expression not herein defined shall have the meanings
assigned to them in the Indian Sale of Goods Act, 1930 (as amended), or the
Indian Contract Act, 1872 (as amended) or the General Clauses Act, 1897 (as
amended), as the case may be.
0200. PartiesParties- The parties
parties to the contract are the Contractor and the Purchaser,
as defined in Clauses 0105 and 0113.
0201. Authority of person signing the Contract on behalf of the ContractorContractor-A
person signing the tender or any other document in respect of the Contract on
behalf of the Contractor without disclosing his authority to do so shall be deemed
to warrant that he has authority to bind the Contractor. If it is discovered at any
time that the person so signing has no authority to do so, the Purchaser may,
without prejudice
prejudice to any other right or remedy of the Purchaser, cancel the
contract and make or authorize the making of a purchase of the stores at the risk
and cost of such person and hold such person liable to the Purchaser for all
costs and damages arising from the cancellation
cancellation of the contract including any
loss which the Purchaser may sustain on account of such purchase. The
provisions of Clause 0700 shall apply to every such purchase as far as
applicable.
0202. Address of the Contractor and notices and communications
communications on behalf of
the
Purchaser:-Purchaser:
(a) For all purposes of the contract, including arbitration thereunder, the address
of the Contractor mentioned in the tender shall be the address to which all
unless
ss the Contractor
communications addressed to the Contractor shall be sent, unle
has notified change by a separate letter containing no other communication and
sent by registered post acknowledgement due to the Purchaser. The Contractor
shall be solely responsible for the consequence of an omission to notify a change
of address in the manner aforesaid.
(b) Any communication or notice on behalf of the Purchaser in relation to the
contract may be issued to the Contractor by the Purchase Officer and all such
communications and notices may be served on the Contractor either
either by
registered posts or under certificate of posting or by ordinary post or by hand
delivery at the option of such officer.
0300. Quotations of rates by Contractors
(a) The price quoted by the Contractor shall not be higher than the controlled
price fixed by law for the stores or where there is no controlled price, it shall not
exceed the prices or contravenes the norms for fixation of prices laid down by
Government or where no such prices or norms have been fixed by the
Government, it shall not exceed
exceed the price appearing in any agreement relating to
price regulation by any industry in consultation with the Government. In any
case, save for special reasons stated in the tender, the price quoted shall not be
higher than the lowest price charged by the Contractor for stores of the same
nature, class or description to a private purchaser, domestic or foreign as well as
Purchaser Governments.
(b) If the price quoted is higher than the controlled price or where there is no
controlled price, the price usually
usually charged by the Contractor from a private
Purchaser, domestic or foreign, as well as Purchaser Government for the stores
of the same nature, class or description the Contractor will specifically mention
this fact in his tender giving reasons for quoting higher price(s). If he fails to do
so or makes any mismis-statement, it shall be lawful for the Purchaser, (i) to revise
the price at any stage so as to bring it in conformity with the Sub clause (a)
Security
urity Deposit.
above or (ii) to terminate the contract and forfeit the Sec
0400. Contract.
0401.
This contract is for the supply of the stores of the description,
specifications and drawings, and in the quantities set forth in the contract on the
date or dates specified therein. Unless otherwise specified, the stores shall be
entirely brand new and of the best quality and workmanship to the satisfaction of
the Inspecting Officer. The stores shall further be in all respects acceptable to
the Inspecting Officer.
0402. Any variation or amendment of the contract shall not be binding on the
Purchaser unless and until the same is duly endorsed on the contract
incorporated in a formal instrument or in exchange of letters and signed by the
parties.
0500. Security Deposit.
0501. Unless otherwise agreed between the Purchaser and the Contractor, the
Contractor shall, within 14 days after written notices of acceptance of the tender
has been posted to the Contractor, deposit with the railway concerned (in cash or
the equivalent in Government Securities or approved Banker's
Banker's Guarantee Bond)
a sum equal to 5 per cent of the total value of the stores detailed in the contract
for which the tender has been accepted, subject to a maximum of Rs. 1,00,000
as a security for the due fulfilment of the contract.
0502. If the Contractor,
Contractor, having been called upon by the Purchaser to furnish
security, fails to make and to maintain a security deposit within the specified
period, it shall be lawful for the Purchaser -
(a) to recover from the Contractor the amount of such security deposit
deposit by
deducting the amount from the pending bills of the Contractor under the contract
or any other contract with the Purchaser or the Government or any person
contracting through the Purchaser or otherwise howsoever, or
(b) to cancel the contract or any part
part thereof and to purchase or authorise the
purchase of the stores at the risk and cost of the Contractor and in that event the
provisions of Clause 0702 shall apply as far as applicable.
0503. No claim shall lie against the Purchaser in respect of interest
interest on cash
deposits or Government Securities or depreciation thereof.
0504. The Purchaser shall be entitled and it shall be lawful on his part to forfeit
the said security deposit in whole or in part in the event of any default, failure or
neglect on the
the part of the Contractor in the fulfilment or performance in all
respect of the contract under reference or any other contract with the Purchaser
or any part thereof to the satisfaction of the Purchaser and the Purchaser shall
also be entitled to deduct from
from the said deposits any loss or damage which the
Purchaser may suffer or be put by reason of or due to any act or other default,
recoverable by the Purchaser from the Contractor in respect of the contract
under reference or any other contract and in either
either of the events aforesaid to call
upon the Contractor to maintain the said security deposit at its original limit by
making further deposits, provided further that the Purchaser shall be entitled to
recover any such claim from any sum then due or which at any time thereafter
may become due to the Contractor under this or any other contracts with the
Purchaser.
0600. Delivery.
0601. The Contractor shall as may be required by the Purchaser either deliver
free or f.o.r. or c.i.f. at the place/places detailed
detailed in the contract, the quantities of
the stores detailed therein and the stores shall be delivered or despatched not
later than the date specified in the contract. The delivery, will not be deemed to
be complete until and unless the stores are inspected and accepted by the
Inspecting Officer as provided in the contract.
0602. The Purchaser shall not be liable to render assistance to the Contractor in
securing or to arrange for or provide transport to the Contractor unless it is so
specifically stated in
in the contract, notwithstanding that transport of the stores, is
controlled by or under the orders of the Government.
0603. Notwithstanding any inspection and approval by the Inspecting Officer on
the Contractor's premises, property in the stores shall not
not pass on to the
Purchaser until the stores have been received, inspected and accepted by the
consignee.
0604. No stores shall be deliverable to the consignee's depots on Sundays and
public holidays without the written permission of the consignee.
0700.
0700. Time for and Date of Delivery;
Delivery; the Essence of the ContractContract-
The time for and the date specified in the contract or as extended for the
delivery of the stores shall be deemed to be of the essence of the contract and
delivery must be completed not later
later than the date(s) so specified or extended.
0701. Progressing of DeliveriesDeliveries- The Contractor shall allow reasonable facilities
and free access to his works and records to the Inspecting Officer, Progress
Officer or such other Officer as may be nominated by the Purchaser for the
purpose of ascertaining the progress of the deliveries under the contract.
0702. Failure and Termination:Termination:- If the Contractor fails to deliver the stores or any
instalment thereof within the period fixed for such delivery in the contract or as
extended or at any time repudiates the contract before the expiry of such period
the Purchaser may without prejudice to his other rights:rights:-
(a) Recover from the Contractor as agreed liquidated damages and not by way of
penalty a sum equivalent
equivalent to 2 per cent of the price of any stores (including
elements of taxes, duties, freight, etc.) which the Contractor has failed to deliver
within the period fixed for delivery in the contract or as extended for each month
or part of a month during which the
the delivery of such stores may be in arrears
where delivery thereof is accepted after expiry of the aforesaid period, or
(b) Cancel the contract or a portion thereof and if so desired purchase or
authorize the purchase of the stores not so delivered or others
others of a similar
description (where stores exactly complying with particulars are not in the opinion
of the Purchaser, which shall be final, readily procurable) at the risk and cost of
the Contractor. It shall, however, be in the discretion of the purchaser
purchaser to collect
or not, the security deposit from the firm/firms on whom the contract is placed at
the risk and expense of the defaulted firm.
Where action is taken under Sub clause (b) above, the Contractor shall be
liable for any loss which the Purchaser
Purchaser may sustain on that account provided the
purchase, or, if there is an agreement to purchase 1 such agreement is made, in
case of failure to deliver the stores within the period fixed for such delivery in the
contract or as extended within six months
months from the date of such failure and in
case of repudiation of the contract before the expiry of the aforesaid period of
delivery, within six months from the date of cancellation of the contract. The
Contractor shall not be entitled to any gain on such purchase
purchase and the manner
and method of such purchase shall be in the entire discretion of the Purchaser.
It shall not be necessary for the Purchaser to serve a notice of such purchase on
the Contractor.
Note-Note-- In respect of the stores which are not easily available
available in the market and
where procurement difficulties are experienced the period for making risk
purchase shall be nine months instead of six months provided above.
0703. Consequence of RejectionRejection- If on the stores being rejected by the
Inspecting Officer
Officer or Interim Consignee or Consignee at the destination, the
Contractor fails to make satisfactory supplies within the stipulated period of
delivery, the Purchaser shall be at liberty to: -
(i) Require the Contractor to replace the rejected stores forthwith
forthwith but in any event
not later than a period of 21 days from the date of rejection and the Contractor
shall bear all cost of such replacement including freight, if any, on such replacing
and replaced stores but without being entitled to any extra payment on
on that or
any other account, or
(ii) Purchase or authorize the purchase of quantity of the stores rejected or
others of a similar description (when stores exactly complying with particulars are
not in the opinion of the Purchaser, which shall be final, readily
readily available) without
notice to the Contractor at his risk and cost and without affecting the Contractor's
liability as regards the supply of any further instalment due under the contract, or
(iii) Cancel the contract and purchase or authorize the purc
purchase
hase of the stores or
others of a similar description (when stores exactly complying with particulars are
not, in the opinion of the Purchaser, which shall be final, readily available) at the
risk and cost of the Contractor. In the event of action being taken
taken under Sub
clause (ii) above or under this SubSub-clause, the provision of Clause 0702 above
will apply as far as applicable.
(iv) Where under the contract the price payable is fixed f.o.r. despatching station,
the Contractor shall, if the stores are rejected
rejected at destination by the consignee, be
liable, in addition to his other liabilities, including refund of price recoverable in
respect of the stores so rejected, to reimburse to the Purchaser the freight and all
other expenses incurred by the Purchaser in
in this regard.
0800. Extension of Time for DeliveryDelivery- If such failure as aforesaid shall have
arisen from any cause which the Purchaser may admit as reasonable ground for
extension of time, the Purchaser shall allow such additional time as he considers
to be justified by the circumstance of the case, and shall forgo the whole or such
part, as he may consider reasonable, of his claim for such loss or damage as
aforesaid. Any failure or delay on the part of subsub-contractor, though their
employment may have been
been sanctioned under Condition 1500 hereof, shall not
be admitted as a reasonable ground for any extension of time or for exempting
the Contractor from liability for any such loss or damage as aforesaid.
0900. Examination of Drawing, Specifications and Patterns
Patternsatterns- When tenders are
called for in accordance with a drawing, specification or sealed pattern the
Contractor's tenders to supply in accordance with such drawing, specifications or
sealed pattern shall, be deemed to be an admission on his part that he has fully
acquainted himself with the details thereof and, in no circumstances, will any
claim on his part which may arise on account of his insufficient examination of
the said drawing, specification or scaled pattern be considered.
1000. Mistakes in Drawing.
Drawing.
The Contractor shall be responsible for and shall pay for any alterations for the
works due to any discrepancies, errors or omissions in the drawings or other
particulars supplied by him whether such drawings or particulars have been
approved by the
the Purchaser or not provided that such discrepancies, errors or
omissions be not due to inaccurate information or particulars furnished to the
Contractor on behalf of the Purchaser. If any dimension figure upon a drawing or
plan differ from those obtained by scaling the drawing or plan, the dimensions as
figured upon the drawing or plan shall be taken as correct.
1100. Samples.
1101. Advance SampleSample- Where an advance sample is required to be approved
under the terms of the contract, the Contractor shall submit the sample free of
cost to the Inspecting Officer within the time specified in the acceptance of
tender. If the Contractor is unable to do so, he must apply immediately to the
Office issuing the acceptance of tender for extension of time stating the
the reasons
for the delay. If the Purchaser is satisfied that a reasonable ground for an
extension of time exists, he may allow such additional time as he considers to be
justified (and his decision shall be final) with or without alteration in the delivery
period stipulated in the acceptance of tender and on such conditions as he
deems fit. In the event of the failure of the Contractor to deliver the advance
sample by the date specified in the acceptance of tender or any other date to
which the time may be extended as aforesaid by the Purchaser or of the rejection
of the sample, the Purchaser shall be entitled to cancel the contract and, if so
desired, purchase or authorize the purchase of the stores at the risk and cost of
the Contractor, in which case the provisions of Clause 0700 shall apply as far as
applicable.
1102. Unless otherwise provided in the contract, all samples required for test
shall be supplied by the Contractor free of cost. Where sample, which is
supplied free, is rejected after examination
examination and test, the same or whatever
remains of the sample, after examination and test will be returned to the
Contractor at his request and cost within three months of the date of such
rejection at public tariff rate at Owner's risk.
1103. MarkingMarking- Samples
Samples submitted shall be clearly labelled with the Contractor's
name and address and the acceptance of tender number.
1104. If the Contractor submits a sample whether with, before or after the
tender, the same shall not govern the standard of supply except when it has
been specifically stated so in the acceptance of tender.
1105. Where under the contract, the Contractor is required to submit an
advance sample, any expenses incurred by the Contractor on or in connection
with the production of stores in bulk,
bulk, before the sample has been approved
unconditionally, shall be borne by the Contractor and he shall not claim any
compensation in the event of such sample being found unacceptable by the
Inspecting Officer.
1106. The rejection of the sample by the Inspecting
Inspecting Authority or Inspecting
Officer
shall
be
final
and
binding
on
the
Contractor.
1107. Where the contract does not require any advance sample to be approved,
the Contractor may before proceeding with bulk manufacture or delivery of the
stores, if he so
so desires, submit to the Inspecting Officer for inspection a sample
of the stores in which case a quantity not less than one per cent of the total
quantity to be supplied unless otherwise authorized by the Inspecting Officer
shall be submitted. The Contractor
Contractor shall not, however, be entitled to be shown
any consideration or give any extension of time or claim to be exonerated from
completing the delivery within the stipulated period only on the ground of delay in
the approval of any such sample.
1108. If, under the contract, supplies are governed by a sealed pattern the
Contractor shall be bound to examine such pattern before preparing a sample or
manufacturing the stores in bulk as the case may be.
1109. Loan of SampleSample- If a certified sample is lent to the Contractor, it will bear a
label containing inter alia variations known to the Inspecting Officer between the
said sample and the stores desired. If the Contractor finds any further variation
between the certified sample and the particulars of specifications
specifications mentioned in
the contract he shall at once refer the matter to the Inspecting Officer and the
Contractors shall also give intimation of such discrepancy to the Purchase
Officer. The Contractor shall follow the instructions of the Inspecting Officer
Officer as to
what sample of particulars should guide the production of stores and the decision
of the Inspecting Officer in the matter shall be final and binding on the
Contractor.
1110. The Contractor shall not detach the said label from the certified sample
and if for any reasons the said label gets detached the Contractor shall at once
return the certified sample to the Inspecting Officer for attaching a fresh label.
1200. Risk of Loss or Damage to Government or Purchaser's Property.
1201. All the property
property of the Government or Purchaser loaned whether with or
without deposit on terms and conditions to be separately agreed upon in respect
of each particular contract to the Contractor in connection with the contract shall
remain the property of the Government
Government or the Purchaser, as the case may be.
The Contractor shall use such property for the purpose of the execution of the
contract and for no other purpose whatsoever.
1202. All such property shall be deemed to be in good condition when received
by the Contractor
Contractor unless he shall have within twentytwenty-four hours of the receipt
thereof notified the Purchase Officer to the contrarct. If the Contractor fails to
notify any defect in the condition or quality of such property he shall be deemed
to have lost the right
right to do so at any subsequent stage.
1203. The Contractor shall return all such property and shall be responsible for
the full value thereof to be assessed by the Purchaser whose decision shall be
final and binding on the Contractor. The Contractor shall
shall be liable for loss or
damage to such property from whatever cause happening while such property is
in the possession of or under the control of the Contractor, his servants workmen
or agents.
1204. Where such property is insured by the Contractor against
against loss or fire at
the request of the Government or Purchaser such insurance shall be deemed to
be effected by way of additional Precaution and shall not prejudice the liability of
the Contractor as aforesaid.
1300. Inspection by Inspecting Officer.
1301.
1301. (a) When inspection during manufacture or before delivery or despatch is
required, notice in writing shall be sent by the Contractor to the Inspecting Officer
when the stores or material to be supplied are ready for inspection and test, and
no stores shall
shall be delivered or despatched until the Inspecting Officer has
certified in writing that such stores have been inspected and approved by him.
(b) In cases where the Inspecting Authority specified in the contract requires on
behalf of the Purchaser that cduring
cduring the manufacturing process of the
component/stores, etc. is also to be done, notice in writing shall be sent by the
Contractor to the Inspecting Officer to visit his premises/works to test the raw
materials and/or conduct necessary inspection during the manufacturing process
of the component / stores, etc. as deemed essential.
1302. Marking of StoresStores- The Contractor shall, if so required, at his own
expense, mark all the approved stores with a recognized Government or
Purchaser's mark. The stores which
which cannot be so marked shall, if so required by
the Inspecting Officer, be packed at his own expense in suitable packages or
cases, each of which shall be sealed and marked with such mark.
The Inspecting Officer shall also have power to mark the rejected
stores with a rejection mark so that they may be easily identified, if resubmitted
for inspection.
1303. Facilities for test and ExaminationExamination- The Contractor shall, at his own
expense afford to the Inspecting Officer all reasonable facilities
facilities as may be
necessary for satisfying himself, that the stores are being and/or have been
manufactured in accordance with the particulars. The Inspecting Officer shall
have full and free access at any time during the execution of the contract to the
Contractor's
Contractor's work for the purpose aforesaid, and he may require the Contractor
to make arrangements for inspection of the stores or any part thereof or any
material at his premises or at any other place specified by the Inspecting Officer
and if the Contractor
Contractor has been permitted to employ the services of a SubSub-
Contractor, he shall in his contract with the SubSub-Contractor, reserve to the
Inspecting Officer a similar right.
1304. Cost of TestTest- The Contractor shall provide, without any extra charge, all
materials,
materials, tools, labour and assistance of every kind which the Inspecting Officer
may demand of him for any test and examination, other than special or
independent
test,
which
he
shall
require
to
make
on
the
pay
y all costs attendant
Contractor'sPremisesandtheContractor shall bear and pa
thereon. If the Contractor fails to comply with the conditions aforesaid, the
Inspecting Officer shall, in his sole judgement, be entitled to remove for test and
examination all or any of the stores manufactured by the Contractor to any
premises other than his (Contractor's) and in all such cases the Contractor shall
bear the cost of transport and/or carrying out such tests elsewhere. A certificate
in writing of the Inspecting Officer, that the Contractor has failed to provide the
facilities
facilities and the means, for test examination shall be final.
1305. Delivery of Stores for TestTest- The Contractor shall also provide and deliver
for test, free of charge, at such place other than his premises as the Inspecting
Officer may specify, such material
material or stores as he may require.
1306. Liability for Costs of Special or Independent TestTest- In the events of
rejection of stores or any part thereof by the Inspecting Officer in the
places
aces of
consequence of the sample which is removed to the laboratory or other pl
test, being found on test not in conformity with the Contract and in the event of
the failure of the Contractor for any reason to deliver the stores passed on test
within the stipulated period, the Contractor shall, on demand pay to the
Purchaser all
all costs incurred in the inspection and/or test. Cost of test shall be
assessed at the rate charged by the laboratory to private persons for similar
work.
1307. Method of TestingTesting- The Inspecting Officer shall have the right to put all the
stores or materials
materials forming part of the same or any part thereof to such tests as
he may think fit and proper. The Contractor shall not be entitled to object on any
ground whatsoever to the method of testing adopted by the Inspecting Officer.
1308. Stores Expended in TestTest- Unless otherwise provided for in the contract if
the test proves satisfactory and the stores or any instalment thereof is accepted,
the quantity of the stores or materials expended in the test will be deemed to
have been taken delivery of by the Purchaser
Purchaser and be paid for as such.
1309. Powers of Inspecting OfficerOfficer- The Inspecting Officer shall have the power
(i) before any stores or part thereof are submitted for inspection to certify that
they can not be in accordance with the contract owing to the
the adoption of any
unsatisfactory
method
of
manufacture.
(ii) to reject any stores submitted as not being in accordance with the particulars.
(iii) to reject the whole of the instalment tendered for inspection, if after inspection
of such portion thereof as "he may in his discretion think fit, he is satisfied that
the same is unsatisfactory.
(iv) the Inspecting Officer's decision as regards the rejection shall be final and
binding on the Contractor.
1400. Charges for Work Necessary for Completion of the
the ContractContract- The
Contractor shall pay all charges for handling, stamping, painting, marking,
protecting or preserving patent rights, drawings, templates, models and gauges
and for all such measures as the Purchaser or the Inspecting Officer may deem
necessary
necessary for the proper completion of the contract, though special provision
therefore may not be made in the specification of drawings.
1500. Responsibility of the Contractor for Executing the Contract.
1501. Risk in the StoresStores- The Contractor shall perform the contract in all
respects in accordance with the terms and conditions thereof. The stores and
every constituent part thereof, whether in the possession or control of the
Contractor, his agents or servants or a carrier, or in the joint possession of the
the
Contractor, his agents or servants and the Purchaser, his agents or servants,
shall remain in every respect at the risk of the Contractor, until their actual
delivery to the consignee at the stipulated place or destination or, where go
provided in the acceptance
acceptance of tender, until their delivery to a person specified in
the contract as interim consignee for the purpose of despatch to the consignee.
The Contractor shall be responsible for all loss, destruction, damage or
deterioration of or to the stores from
from any cause whatsoever while the stores after
approval by the Inspecting Officer are awaiting despatch or delivery or are in the
course of transit from the Contractor to the consignee or, as the case may be,
interim consignee. The Contractor shall alone be entitled and responsible to
make claims against a Railway Administration or other carrier in respect of nonnondelivery, short delivery, misdelivery, loss, destruction, damage or deterioration of
the goods entrusted to such carrier by the Contractor for transmission
transmission to the
consignee or the interim consignee as the case may be.
1502. Consignees Right of Rejection – Notwithstanding any approval which the
Inspecting Officer may have given in respect of the stores or any materials or
other particulars or the work or workmanship involved in the performance of the
contract (whether with or without any test carried out by the Contractor or the
Inspecting Officer or under the direction of the Inspecting Officer) and not with
standing delivery of the stores where so
so provided to the interim consignee, it
shall be lawful for the consignee, on behalf of the Purchaser, to reject the stores
or any part, portion or consignment thereof within a reasonable time after actual
delivery thereof to him at the place or destination
destination specified in the contract if such
stores or part, portion or consignment thereof is not in all respects in conformity
with the terms and conditions of the contract whether on account of any loss,
deterioration or damage before despatch or delivery or during
during transit or otherwise
howsoever.
NoteNote- In respect of materials prepre-inspected at the firm's premises the consignee
will issue rejection advice within 90 days from the date of receipt.
1503. Provided that where, under the terms of the contract the stores
stores are
required to be delivered to an interim consignee for the purpose of despatch to
the consignee, the stores shall be at the Purchaser's risk after their delivery to
the interim consignee, but nevertheless it shall be lawful for the consignee on
behalf of the Purchaser to reject the stores or any part, portion of consignment
thereof upon their actual delivery to him at the destination if they are not in all
respects in conformity with the terms and conditions of contract except where
they have been damaged
damaged or have deteriorated in the course of transit or
otherwise after their delivery to the interim consignee.
1504. The provisions contained in Clause 2200 relating to the removal of stores
rejected by the Inspecting Officer shall mutatis mutandis apply to stores rejected
by the consignee as herein provided.
NoteNote- In respect of stores inspected during manufacture or before delivery or
despatch at contractor's premises the consignee will issue communication of
rejection within 90 days from the date of actual
actual delivery thereof.
1505. Subletting and AssignmentAssignment- The Contractor shall not, save with the
previous consent in writing of the Purchaser, sublet, transfer or assign the
contract or any part thereof or interest therein or benefit or advantage thereof any
any
manner whatsoever.
In the event of the Contractor's subletting or assigning this contract
or any part thereof without such permission, the Purchaser shall be entitled to
he Contractor's
cancel the contract and to purchase the stores elsewhere on tthe
account and risk and the Contractor shall be liable for any loss or damage which
the Purchaser may sustain in consequence or arising out of such purpose.
1506. Changes in a FirmFirm(a) Where the Contractor is a partnership firm, a new partner
partner shall not be
introduced in the firm except with the previous consent in writing of the
Purchaser, which may be granted only upon execution of a written undertaking
by the new partner to perform the contract and accept all liabilities incurred by
the firm
firm under the contract prior to the date of such undertaking.
(b) On the death or retirement of any partner of the Contractor firm before
complete performance of the contract, the Purchaser may, at his option, cancel
the contract and in such case the Contractor
Contractor shall have no claim whatsoever to
compensation
against
the
Purchaser.
(c) If the contract is not determined as provided in Sub
Sub--clause (b) above
notwithstanding the retirement of a partner from the firm he shall continue to be
liable under the contract
contract for acts of the firm until a copy of the public notice given
by him under Section 32 of the Partnership Act, has been sent by him to the
Purchaser by registered post acknowledgement due.
(d) Consequence of breach Should a partner in the Contractor firm
firm commit a
breach of Sub clause 1505 above or the Contractor should commit a breach of
the conditions 1506(a) of this Sub clause, it shall be lawful for the Purchaser to
cancel the contract and purchase or authorize the purchase of the stores at the
risk and
and cost of the Contractor and in that event the provisions of Clauses 0600
and 0700 as far as applicable shall apply.
(e) The decision of the Purchaser as to any matter or thing concerning or arising
Contractor
ontractor or any partner
out of this sub clause or on any question whether the C
of the Contractor firm has committed a breach of any of the conditions in this sub
clause contained shall be final and binding on the Contractor.
1507. Assistance to the ContractorContractor-
(a) The Contractor shall be solely responsible
responsible to procure any material or obtain
any import or other licence or permit required for the fulfilment of the contract and
the grant by the Purchaser or any other authority of a quota certificate or permit
required under any law for distribution or acquisition
acquisition of iron and steel or any other
commodity or any other form of assistance in the procurement of the material
aforesaid or any attempt to render assistance in the matter aforesaid, or shall not
be construed as a representation on the part of the Purchaser
Purchaser that the material
covered by such licence or permit or quota certificate is available or constitute
any promise, undertaking or assurance on the part of the Purchaser regarding
liabilities
ties of
the procurement of the same or effect any variation in the rights and liabili
the parties under the contract. But, if by reason of any such assistance as
aforesaid, the Contractor obtains any materials at less than their market price or
the cost of production of the stores is lowered the price of the stores payable
under the
the contract shall be reduced proportionately, and the extent of such
reduction shall be determined by the Purchaser whose decision shall be final and
binding on the Contractor.
(b) Every effort made by the Purchaser to supply, or give assistance in the
procurement
procurement of materials, whether from the Government stock or by purchase
under a permit or release order issued by or on behalf of or under authority from
Government or by any officer empowered in that behalf by law or under other
arrangements made by the Purchaser
Purchaser shall be deemed to be subject to the
condition that it will be performed with due regard to the other demands and only
if it is found practicable to do so within the stipulated time and the decision of the
Purchaser whether it was practicable to supply
supply or give assistance as aforesaid or
not shall be final and binding on the Contractor.
1600. Use of Raw Materials secured with Government Assistance.
1601.
(a) Where any raw material is procured for the execution of a contract with the
assistance of
of the Government rendered in the form of permit, or licence or quota
certificate/essentiality certificate or release order issued by or on behalf of or
under the authority of the Government or by an officer empowered in that behalf,
or
(b) where the raw material
material is issued to the Contractor from Government stock, or
(c) where advance payments are made to the Contractor to enable him to
purchase the raw material, or
(d) Where raw material is arranged by the Government, the ContractorContractor(i) shall hold such material as trustee for the Government,
(ii) Shall use such material economically and solely for the purpose of the
contract.
(iii) shall not dispose of the same without the previous permission in writing of the
Purchaser, and
(iv) shall render due account
account of such material and return to the Government at
such place as the purchaser may direct all surplus or unserviceable material that
may be left after the completion of the contract or its termination for any reason
whatsoever.
On returning such material, the Contractor shall be entitled to
such price therefor as the Purchaser may fix, having regard to the condition of
such material.
1602. Where the contract is terminated due to any default on the part of the
Contractor, the
the Contractor shall pay all transport charges incurred for returning
any material up to such destination as may be determined by the Purchaser and
the decision of the Purchaser in that behalf shall be final and binding on the
Contractor.
1603. If the Contractor
Contractor commits breach of any of the conditions in this clause
specified, he shall, without prejudice to any other liability, penal or otherwise, be
liable to account to the Government for all moneys, advantages or profits
accruing from or which, in the usual
usual course, would have accrued to him by
reason of such breach.
1604. Where the stores manufactured or fabricated by the Contractor out of the
material arranged or procured by or on behalf of the Government are rejected,
the Contractor shall, without prejudice
prejudice to any other right or remedy of the
Government, pay to the Government, on demand, the cost price or market value
of all such materials whichever is greater.
1700. Indemnity.
1701. The Contractor shall at all times indemnify the Purchaser against all
claims which may be made in respect of the stores for infringement of any right
protected by patent, registration of designs or trade mark . Provided always that
in the event of any claim in respect of alleged breach of letters patent, registered
designs
designs or trade mark being made against the Purchaser, the Purchaser shall
notify the Contractor of the same and the Contractor shall, at his own expense,
either settle any such dispute or conduct any litigation that may arise there from.
1702. The Contractor
Contractor shall not be liable for payment of any royalty, licence fee
or other expenses in respect of or for making use of patents or designs with
respect to which he is according to the terms of the contract, to be treated as an
agent of the Government for the purpose of making use of patent or trade mark
for fulfilment of the contract.
1800. Packing.
1801. The Contractor shall pack at his own cost the stores sufficiently and
properly for transit by rail/road, air and/or sea as provided in the contract so as to
ensure their being free from loss or damage on arrival at their destination.
1802. Unless otherwise, provided in the contract all containers (including
packing cases, boxes, tins, drums and wrappings) in which the stores are
supplied by the contractor,
contractor, shall be considered as nonnon-returnable and their cost
as having been included in the contract price.
1803. If the contract provides that the containers shall be returnable, they
must be marked “ Returnable ” and they will be returned to the
the Contractor as
per terms of the contract.
1804. If the contract provides that returnable containers shall be separately
charged, they shall be invoiced by the Contractor at the price specified in
acceptance of tender. In such cases, the Contractor shall
shall give full credit for the
invoiced amount if the containers are returned to the Contractor. Return of
containers shall be made within a reasonable time and in the event of any
dispute or difference arising as to whether the containers were so returned, the
the
decision of the Purchaser thereon shall be final and binding and the Purchaser
may, in his discretion award, such compensations as may in his opinion be
proper for any undue delay in returning the containers.
1805. Each bale or package delivered under the contract shall be marked by the
Contractor at his own expense. Such marking shall be distinct (all previous
irrelevant marking being carefully obliterated) and shall clearly indicate the
description and quantity of the stores, the name and address of the Consignee,
the gross weight of the package and the name of the Contractor with a distinctive
number or mark sufficient for the purpose of identification. All markings shall be
carried out with such material as may be found satisfactory by the Inspecting
Inspecting
Officer as regards quickness of drying, fastness and indelibility.
1806. The Inspecting Officer may reject the stores if the stores are not packed/or
marked as aforesaid and in case where the packing materials are separately
prescribed, if such materials
materials are not in accordance with the terms of the
contract. Such rejection of the stores by the Inspecting Officer shall be final and
binding on the Contractor.
1807. Each bale or package shall contain a packing note specifying the name
and address of the
the Contractor, the number and date of the acceptance of tender
or supply order and the designation of the Purchase Officer issuing the supply
order, the description of the stores and the quantity contained in such bale or
package.
1900. Notification of Delivery.
Delivery.
Notification of delivery or despatch in regard to each and every
instalment shall be made to the consignee and to the indentor immediately on
despatch or delivery. The Contractor shall further supply to the consignee, or the
interim consignee, as the case may be, a packing account Quoting number of the
acceptance of tender and/or supply or repeat and date of despatch of the stores.
All packages, containers, bundles and loose materials part of each and every
instalment shall
shall be fully described in the packing account and full details of the
contents of the packages and quantity of materials shall be given to enable the
consignee to check the stores on arrival at destination.
The Railway
Receipt/Consignment Note or Bill of Lading, if any, shall be forwarded to the
consignee by registered post immediately on the despatch of stores. The
Contractor shall bear and reimburse to the Purchaser demurrage charges, if any,
forwarding
arding the Railway
paid by reason of delay on the part of the Contractor in forw
Receipt, Consignment Note or Bill of Lading.
2000. Progress Reports.
2001. The Contractor shall from timetime-toto-time, render such reports concerning the
progress of the contract and/or supply of the stores in such form as may be
required
required by the Purchaser.
2002. The submission, receipt and acceptance of such reports shall not
prejudice the rights of the Purchaser under the contract, nor shall operate as an
estoppel against Purchaser merely by reason of the fact that he has not taken
notice
notice of/or subjected to test any information contained in such report.
2100. Freight.
The stores shall be despatched at public tariff rates. In the case of f.o.r.,
station of despatch contract, the stores shall be booked by the most economical
route or most economical tariff available at the time of despatch as the case may
be. Failure to do so will render the Contractor liable for any avoidable
expenditure caused to the Purchaser. Where alternative routes exist, the
Purchaser shall, if called
called upon to do so, indicate the most economical route
available, or name the authority whose advice in the matter shall be taken and
acted upon. If any advice of any such authority is sought, his decision or advice
in the matter shall be final and binding on
on the Contractor,
2101. In respect of road deliveries where the Municipal/local authorities do not
accept Octroi Duty exemption Certificate, the Octroi Duty shall be borne by the
Seller.
2200. Removal of Rejected Stores.
2201. On rejection of all stores
stores submitted for inspection at a place other than the
premises of the Contractor, such stores shall be removed by the Contractor at
his own cost subject as hereinafter stipulated, within 21 days of the date of
intimation of such rejection. If the concerned
concerned communication is addressed and
posted to the Contractor at the address mentioned in the contract, it will be
deemed to have been served on him at the time when such communication
would be in the course of ordinary post reach the Contractor. Provided that
that the
Inspecting Officer may call upon the Contractor to remove dangerous, infected or
perishable stores within 48 hours of the receipt of such communication and the
decision of the Inspecting Officer in this behalf shall be final in all respects.
Provided
Provided further that where the price or part thereof has been paid, the
consignee is entitled without prejudice to his other rights to retain the rejected
stores till the price paid for such stores is refunded by the Contractor save that
such retention shall not in any circumstances be deemed to be acceptance of the
stores or waiver of rejection thereon.
2202. All rejected stores shall in any event and circumstances remain and
always be at the risk of the Contractor immediately on such rejection. If such
stores
stores are not removed by the Contractor within the periods aforementioned, the
Inspection Officer may remove the rejected stores and either return the same to
the contractor at his risk and cost by such mode of transport as the Purchaser or
Inspecting Officer may decide, or dispose of such stores at the Contractor's risk
and on his account and retain such portion of the proceeds, if any from such
disposal as may necessary to recover any expense incurred in connection with
such disposals (or any price refundable as a consequence of such rejection).
The Purchaser shall, in addition, be entitled to recover from the Contractor
ground rent/demurrage charges on the rejected stores after the expiry of the time
limit mentioned above.
2203. The stores that have been despatched
despatched by rail and rejected after arrival at
destination may be taken back by the Contractor either at the station where they
were rejected or at the station from which they were sent, after refunding the
price paid for such stores and other charges refundable
refundable as a consequence of
such rejection. If the contract placed for delivery f o. r. station of despatch, the
Contractor shall pay the carriage charges on the rejected consignment at public
tariff rates from the station of despatch to the station where they are rejected. If
the Contractor elects to take back the goods at the station from which they were
despatched, the goods shall in addition, be booked back to him freight to pay at
public tariff rates and at owner's risk. The Contractor shall be liable
liable to reimburse
packing and incidental costs and charges incurred in such return or rejected
stores in addition to other charges refundable as a consequence of rejection.
The goods shall remain the property of the Contractor unless and until accepted
by the
the Purchaser after inspection.
2300. System of Payment.
2301. Unless otherwise agreed upon between the parties, payment for delivery
of the stores will be made on submission of bills in the prescribed form which
may be obtained from the Purchase Officer
Officer in accordance with the instructions
given in the Acceptance of Tender, by a cheque or demand draft on a branch of
the Reserve Bank of India or State Bank of India transacting government
business as may be decided by the Purchaser.
2302. Payment for the
the stores or for each consignment thereof will be made to
the Contractor on submission of bills accompanied by required document in
accordance with the following procedure in contracts where such a facility to the
Contractor has specifically been agreed to by the Purchaser: -
(a) 95 per cent payments for the stores or each consignment thereof will be
made to the firms against proof of inspection and despatch. The original railway
receipt should be sent to the Accounts Officer responsible for payment along with
95 per cent bill advising the particulars of despatch to the consignee. The
Accounts Officer after passing the 95 per cent bill should pass on the original
railway receipt to the consignee for taking delivery of the consignment. It should,
however, be ensured that there is no delay in the Accounts Office transmitting
the original railway receipt to the consignee.
(b) The balance 5 percent shall be paid on receipt of the stores or each
consignment thereof in accordance with the terms of the contract in good
condition by the consignee, with a certificate to that effect endorsed on the copy
of the Inspection Note by the Consignee which shall accompany the bill
submitted by the Contractor.
(c) In the case of F.O.B. & C. & F. contract 95 per cent of the price will be paid on
presentation of shipping documents and inspection certificate and the remaining
5 per cent on receipt of the stores in accordance with the terms of the contract in
good condition by the Consignee, and on producing the certificate of such receipt
endorsed on one copy of the Inspection Note by the Consignee, or alternatively
at the Contractor's option, the full value of the stores will be paid after inspection,
on receipt of the consignment in accordance with the terms of the contract in
in
good condition by the Consignee and on producing a certificate of such receipt
endorsed on one copy of the Inspection Note.
2303. In all other contracts or in contracts where the Inspecting Officer also acts
as the interim consignee or where inspection is carried on by the Consignee
himself at destination and in all cases of local delivery full payment shall be made
on submission of " Final 100 percent bill " supported by the Inspection
Certificates and consignee's receipt as aforesaid to the Accounts Officer
Officer
concerned.
NoteNote-
(1) The system of 95 percent and 5 percent payment is not applicable to claims
amounting to Rs.1000/Rs.1000/- or below. In such cases only a single bill for value should
he submitted.
(2) In the case of Running Contracts, the system of payment
payment will be similar to the
above except that payment would be 98 per cent and 2 per cent instead of 95
per cent and 5 per cent specified above.
2400. Withholding and lien in respect of sums claimed.
2401. Whenever any claim or claims for payment of a sum of money arises out
of or under the contract against the Contractor, the Purchaser shall be entitled to
withhold and also have a lien to retain such sum or sums in whole or in part from
purpose
rpose aforesaid,
the security, if any, deposited by the Contractor and for the pu
the Purchaser shall be entitled to withhold the said cash security deposit or the
security, if any, furnished as the case may be and also have a lien over the same
pending finalisation or adjudication of any such claim. In the event of the
the security
being insufficient to cover the claimed amount or amounts or if no security has
been taken from the Contractor, the Purchaser shall be entitled to withhold and
have lien to retain to the extent of the such claimed amount or amounts referred
to supra,
supra, from any sum or sums found payable or which at any time thereafter
may become payable to the Contractor under the same contract or any other
contract with the Purchaser or the Government pending finalisation or
adjudication of any such claim.
It is an agreed term of the contract that the sum of money or moneys
so withheld or retained under the lien referred to above, by the Purchaser will be
kept withheld or retained as such by the Purchaser till the claim arising out of or
under the
the contract is determined by the Arbitrator (if the contract is governed by
the arbitration clause) or by the competent court as prescribed under clause
2703 hereinafter provided, as the case may be, and that the Contractor will have
no claim for interest or damages whatsoever on any account in respect of such
withholding or retention under the lien referred to supra and duly notified as' such
to the Contractor.
2402. For the purpose of Clause 2401, where the Contractor is a partnership
firm or a limited company, the Purchaser shall be entitled to withhold and also
have a lien to retain towards such claimed amount or amounts in whole or in part
from any sum found payable to any partner / limited company, as the case may
be, whether in his individual capacity
capacity or otherwise.
2403. Lien in respect of Claims in other ContractsContracts- Any sum of money due and
payable to the Contractor (including the security deposit returnable to him) under
the contract may withhold or retain by way of lien by the Purchaser or
Government
Government against any claim of the Purchaser or Government in respect of
payment of a sum of money arising out of or under any other contract made by
the Contractor with the Purchaser or Government.
It is an agreed term of the contract that the sum of money so withheld
or retained under this clause by the Purchaser or Government will be kept
withheld or retained as such by the Purchaser or Government till his claim arising
out of the same contract or any other contract is either mutually settled or
determined by the arbitrator, if the contract is governed by the arbitration clause
or by the competent court under Clause 2703 hereinafter provided, as the case
may be, and that the Contractor shall have no claim for interest or damages
whatsoever on this account or on any other ground in respect of any sum of
money withheld or retained under this clause and duly notified as such to the
Contractor.
2500. Corrupt Practices.
2501. The Contractor shall not offer or give or agree to give to any person in the
employment of the Purchaser or working under the orders of the Purchaser any
gift or consideration of any kind as an inducement or reward for doing or
forbearing to do or for having done or forborne to do any act in relation to the
obtaining or execution
execution of the contract or any other contract with the Purchaser or
Government or for showing any favour or for bearing to show disfavour to any
person in relation to the contract or any other contract with the Purchaser or
Government. Any breach of the aforesaid
aforesaid condition by the Contractor, or any
one employed by him or acting on his behalf (whether with or without the
knowledge of the Contractor) or the commission of any offence by the Contractor
or by any one employed by him or acting on his behalf under IX of the Indian
Penal Code, 1860 or the Prevention of Corruption Act, 1947 or any other act
enacted for the prevention of corruption by public servants shall entitle the
Purchaser to cancel the contract and all or any other contracts with the
Contractor and
and to recover from the Contractor the amount of any loss arising
from such cancellation in accordance with the provisions of Clauses 0600 and
0700.
2502. Any dispute or difference in respect of either the interpretation effect or
application or the above condition or of the amount recoverable thereunder by
the Purchaser from the Contractor, shall be decided by the Purchaser, whose
decision there on shall be final and binding on the Contractor.
2600. Insolvency and Breach of Contract.
2601. The Purchaser
Purchaser may at any time, by notice in writing summarily
determine the contract without compensation to the Contractor in any of the
following events, that is to say
(a) if the Contractor being an individual or if a firm, any partner thereof, shall at
any time, be adjudged insolvent or shall have a receiving order or order for
administration of his estate made against him or shall take any proceeding for
composition under any Insolvency Act for the time being in force or make any
conveyance or assignment
assignment of his effects or enter into any assignment or
composition with his creditors or suspend payment or if the firm be dissolved
under the Partnership Act, or
(b) if the Contractor being a company is wound up voluntarily or by the order of a
Court or a Receiver,
Receiver, Liquidator or Manager on behalf of the Debenture holders is
appointed or circumstances shall have arisen which entitle the Court or
Debenture holders to appoint a Receiver, Liquidator or Manager, or
(c) if the Contractor commits any breach of the contract
contract not herein specifically
provided
for.
Provided always that such determination shall not prejudice any right of action or
remedy which shall have accrued or shall accrue there after to the Purchaser
and provided also the Contractor shall be liable to
to pay to the Purchaser for any
extra expenditure he is thereby put to and Contractor shall, under no
circumstances, be entitled to any given on rere-purchase.
2700. Laws governing the Contract.
2701. This contract shall be governed by the Laws of India for
for the time being in
force.
2702. Irrespective of the place of delivery, the place of performance or place of
payment under the contract, the contract shall he deemed to have been made at
the place from which the acceptance of tender has been issued.
2703
2703.
03. Jurisdiction of courtscourts- This Courts of the place from where the acceptance
of tender has been issued shall alone have jurisdiction to decide any dispute
arising out of or in respect of the contract.
2704. Marking of storesstores- The marking of the stores must comply with the
requirements of the laws relating to merchandise marks for the time being in
force in India.
2705. Compliance with provisions of Contract Labour (Regulation and Abolition)
Act, 1970
(1) The Contractor shall comply with the provisions
provisions of the Contract Labour
(Regulation and Abolition) Act, 1970 and the Contractor Labour (Regulation and
Abolition) Central Rules, 1971, as modified from timetime-toto-time, wherever
applicable and shall also indemnify the Purchaser from and against any claims
under the aforesaid Act and the Rules.
(2) The Contractor shall obtain a valid licence under the aforesaid Act as
modified from timetime-toto-time before the commencement of the contract and
continue to have a valid licence until the completion of the contract. Any failure
to fulfil this requirement shall attract the penal provisions of the contract arising
out of the resultant non execution of the contract.
(3) The Contractor shall pay to labour employed by him directly or through SubSubContractors the wages as per provisions of the aforesaid Act and the Rules
wherever applicable. The Contractor, shall, notwithstanding the provisions of the
contract to the contrary, cause to be paid the wages to labour indirectly engaged
on the contract including any engaged by his SubSub-Contractors in connection with
the said contract, as if the labour had been immediately employed by him.
(4) In respect of all labour directly or indirectly employed in the contract for
performance of the Contractor's part of the contract, the Contractor
Contractor shall comply
with or cause to be complied with the provisions of the aforesaid Act and the
Rules wherever applicable.
(5) In every case in which, by virtue of the provisions of the aforesaid Act or the
Rules, the, Purchaser is obliged to pay any amount
amount of wages to a workman
employed by the Contractor or his SubSub-Contractor in execution of the contract or
to incur any expenditure in providing welfare and health amenities required to be
provided under the aforesaid Act and the Rules or to incur any expenditure
expenditure on
account of the contingent liability of the Purchaser due to the Contractor's failure
to fulfil his statutory obligations under the aforesaid Act or the Rules the
Purchaser will recover from the Contractor, the amount of wages so paid or the
amount
amount of expenditure so incurred, and without prejudice to the rights of the
Purchaser under Section 20, SubSub-section (2) and Section 21, SubSub-section (4) of
the aforesaid Act, the Purchaser shall be at liberty to recover such amount or
part thereof by deducting
deducting it from the security deposit and/or from any sum due by
the Purchaser to the Contractor whether under the contract or otherwise. The
Purchaser shall not be bound to contest any claim made against it under SubSub-
section (i) of Section 20 and SubSub-section (4) of Section 21 of the aforesaid Act
except on the written request of the Contractor and upon his giving to the
Purchaser fun security for all costs for which the Purchaser might become liable
in contesting such claim. The decision of the Purchaser regarding
regarding the amount
actually recoverable from the Contractor as stated above, shall be final and
binding on the Contractor.
2800. Headings.
The headings of conditions here to shall not affect the construction thereof.
2900. Arbitration.
(a) In the event of any question, dispute or difference arising under these
conditions or any special conditions of contract, or in connection with this
contract (except as to any matters the decision of which is specially provided for
by these or the special conditions) the same shall be referred to the sole
arbitration of a Gazetted Railway Officer appointed to be the arbitrator, by the
General Manager in the case of contracts entered into by the Zonal Railways and
Production Units; by any Member of the Railway Board, in the case of contracts
entered into by the Railway Board and by the Head of the Organisation in
respect of contracts entered into by the other Organisations under the Ministry of
Railways. The Gazetted Railway Officer to be appointed as arbitrator however
will not be one of those who had an opportunity to deal with the matters to which
the contract relates or who in the course of their duties as railway servant have
expressed views on all or any of the matters under dispute or difference. The
award of the arbitrator shall be final and binding on the parties to this contract.
(b) In the event of the arbitrator dying, neglecting or refusing to act or resigning
or being unable to act for any reason, or his award being set aside by the court
for any reason, it shall be lawful for the authority appointing the arbitrator to
appoint another arbitrator in place of the outgoing arbitrator in the manner
aforesaid.
(c) It is further a term of this contract that no person other than the person
appointed by the authority
authority as aforesaid should act as arbitrator and that if for any
reason that is not possible, the matter is not to be referred to 'arbitration at all.
(d) The arbitrator may from timetime-toto-time with the consent of all the parties to the
contract enlarge the time
time for making the award.
(e) Upon every and any such reference, the assessment of the cost incidental to
the reference and award respectively shall be in the discretion of the arbitrator.
(f) Subject as aforesaid, the Arbitration Act, 1940 and the rules thereunder
thereunder and
any statutory modifications thereof for the time being in force shall be deemed to
apply to the arbitration proceedings under this clause.
(g) The venue of arbitration shall be the place from which the acceptance note is
issued or such other place as the arbitrator at his discretion may determine.
(h) In this clause the authority, to appoint the arbitrator includes, if there be no
such authority, the officer who is for the time being discharging the functions of
that authority, whether in addition
addition to other functions or otherwise.
3000. Fall Clause.
All contract if and when placed will be subject to following fall clause
3001. The price charged for the stores supplied under the Contract by the
contractor shall in no event exceed the lowest price at which the contractor sells
the stores or offer to sell stores of identical description. To any personnel
organisations including the purchaser or any Department of the Central
case,
ase, may
Government or any Railway Office or any Railway Undertaking, as the c
be during the period till performance of all Supply Orders placed during the
currency of the contract is completed. The lower price will be applicable to
supplies made after the date of coming into force of such reduction or sale or
offer to sell at a reduced rate.
3002. If at any time, during the said period the contractor reduces the sale price,
sells or offer to sell such stores to any persons organisation including the
orr
purchaser or any Department of Central Government or any Railway Office o
any Railway Undertaking as the case may be at a price lower than the price
chargeable under the contract, he shall forthwith notify such reduction or sale or
offer of sale to the Purchaser and the price payable under the contract for the
stores supplied after the date of coming into force or such reduction or sale or
offer of sale shall stand correspondingly reduced.
The above stipulation will, however, not apply to
(a) Exports by the Contractor
(b) Sale of goods as original equipment at prices lower than
than the prices charged
for normal replacement.
(c) Sale of goods such as drugs which have expiry dates.
3003. The Contractor shall fumish the following certificate to the concerned
Accounts Officer along with each bill for payment of supplies made against
against the
Rate Contract.
* I/We certify that there has been no reduction in sale price of the stores of
description identical to the stores supplied to the Government under the contract
herein and such stores have not been offered sold by me/us to any
person/organisation
person/organisation including the purchaser or any Department of Central
Government or any Railway Office or any Railway Undertaking as the case may
be upto the date of bill/ the date of completion of supplies against all supply
orders placed during the currency
currency of the contract at a price lower than the price
charged to the Government under the contract except for quantity of stores
categories under sub clauses (a), (b) and (c) of subsub-para (ii) above, details of
which are as follows
Note.Note.-The contractor will also
also inform the FA& CA0 concerned and the COS as
soon as supplies against all supply order placed against the contract are
completed.
INSPECTION & REJECTION
3100. Where under a contract the price payable is fixed on F.O.R. station of
despatch basis, the
the Contractor shall, if the consignee rejects the stores at
destination be liable in addition to his other liabilities, to reimburse to the
Purchaser the freight paid by the Purchaser.
3101. Notification of Result of lnspection.
lnspection.-Unless otherwise provided in the
specification of schedule, the examination of the stores will be made as soon as
practicable after the same have been submitted for inspection and the result of
the examination will be notified to the Contractor.
3102. Inspection Notes.
Notes.--On
--On the stores
stores being found acceptable by the inspecting
Officer he shall furnish the Contractor with necessary copies of Inspection Notes
duly completed, for being attached to the Contractor's bill in support thereof.
3200. Warranty/GuaranteeWarranty/Guarantee-
3201. The Contractor/Seller
Contractor/Seller hereby covenants that it is a condition of the
contract that all goods/stores/articles furnished to the Purchaser under this
contract shall be of the highest grade. free of all defects and faults and of the
best materials, quality, manufacture and
and workmanship throughout and consistent
with the established and generally accepted standards for materials of the type
ordered and in full conformity with the contract specification, drawing or sample,
if any and shall, if operable, operate properly.
3202.
3202. The Contractor also guarantees that the said goods/stores/articles would
continue to conform to the description and quality as aforesaid, for a period of 30
months after their delivery or 24 months from the date of placement in service
whichever shall be sooner, and this warranty shall survive notwithstanding the
fact that the goods/stores/articles may have been inspected, accepted and
payment therefor made by the Purchaser.
3203. If during the aforesaid period, the said goods/stores/articles be discovered
discovered
not to conform to the description and quality aforesaid or have deteriorated,
otherwise that by fair wear and tear the decision of the Purchaser in that behalf
being final and conclusive that the Purchaser will be entitled to reject the said
goods/stores/articles
goods/stores/articles or such portions thereof as may be discovered not to
conform to the said description and quality.
goods/stores/articles will be at the Seller's risk.
On such rejection, the
If the Contractor/Seller so desires, the rejected goods may be taken
taken over by him
or his agents for disposal such manner as he may deem fit within a period of 3
months from the date of such rejection. At the expiry of the period, no claim
whatsoever
shall
lie
against
the
Purchaser
in
respect
of
the
said
goods/stores/articles,
goods/stores/articles, which may be disposed of by the Purchaser in such
manner as he thinks fit. Without prejudice to the generality of the foregoing, all
the provisions in the Indian Railways Standard Conditions of Contract relating to
the ‘rejection of stores' and ‘failure'
‘failure' and 'termination' add and Clause 31003100-02
above shall apply.
3204. The Contractor/Seller shall, if required, replace the goods or such portion
there of as have been rejected by the Purchaser, free of cost, at the ultimate
destination, or at the option
option of the Purchaser, the Contractor/Seller shall pay to
the Purchaser, the value thereof at the contract price and such other expenditure
and damage as may arise by reason of the breach of the conditions herein
before specified. Nothing herein contained shall
shall prejudice any other right of the
Purchaser in that behalf under this contract or -otherwise.
3300. Book Examination ClauseClause-The Government reserves the right for 'Book
Examination' as follows: -
(i) The Contractor shall whenever called upon and requiring
requiring to produce or cause
to be produced for examination by any Government Officer duly authorised in
that behalf, any cost or other account book of account, voucher, receipt, letter,
memorandum, paper or writing or any copy of or extract from any such document
document
and also furnish information any way relating to such transaction and procedure
before the duly authorised Government Officer returns verified in such manner as
may be required relating in any way to the execution of this contract or relevant
for verifying
verifying or ascertaining the cost of execution of this contract (the decision of
such Government Officer on the question of relevancy of any document,
information of return being final and binding on the parties).
The obligation imposed by this clause is without
without prejudice to the obligation of the
contractor under any statute, rules or orders shall be binding on the Contractor.
(ii) The Contractor shall, if the authorised Government Officer so requires
(whether before or after the prices have been finally fixed),
fixed), afford facilities to the
Government Officer concerned to visit the Contractors works for the purpose of
examining the processes of manufacture and estimating or ascertaining the cost
of production of the articles. If any portion of the work be entrusted
entrusted or carried out
by a subsub-contractor or any of its subsidiary or allied firm or company, the
authorised Government Officer shall have power to examine all the relevant
books of such subsub-contractor or any subsidiary or allied firm or company shall be
open
open to his inspection as mentioned in clause (i).
(iii) If on such examination, it is established that the contracted price is in excess
of the actual cost plus reasonable margin of profit, the Purchaser shall have the
right to reduce the price and determine
determine the amount to a reasonable level.
(iv) Where a contract provides for book examination clause, the Contractor or its
agency is bound to allow examination of its books within a period of 60 days from
the date the notice is received by the Contractor, or its
its agencies calling for the
production of documents as under clause (i) above. In the event of Contractor's
or his agency's failure to do so, the contract price would be reduced and
determined according to the best judgement of the Purchaser which would be
be
final and binding on the Contractor and his agencies.
3400. Inspection at the Fag End of the Delivery PeriodPeriod-In cases where only a
portion of the stores ordered is tendered for inspection at the Fag end of the
delivery period and also in cases where inspection
inspection is not completed in respect of
the portion of the stores tendered for inspection during the delivery period, the
Purchaser reserves the right to cancel the balance quantity not tendered for
inspection within the delivery period fixed in the contractor
contractor the risk and expense
of the Contractor without any further reference to him. If the stores tendered for
inspection during or at the fag end of the delivery period are not found
acceptable after carrying out the inspection, the purchaser is entitled to
to cancel
the contract in respect of the same at the risk and expense of the contractor. If,
however, the stores tendered for inspection are found acceptable, the Purchaser
may grant an extension of the delivery period subject to the following conditions:
-
(a) The Purchaser has the right to recover from the contractor under the
provision of clause 0702 (a) of I.R.S. Conditions of Contract liquidated damages
on the stores which the Contractor has failed to deliver within the period fixed for
delivery.
(b) That no increase in price on account of any statutory increase in or fresh
imposition of Customs Duty, Excise Duty, Sales Tax on account of Foreign
Exchange variation or on account of any other tax or duty liveable in respect of
stores specified in the contract which takes place after the date of the delivery
period stipulated in the contract shall be admissible on such of the said stores as
are delivered after the date of the delivery stipulated in the contract.
(C) That not with standing any stipulation
stipulation in the contract for increase in price on
any other ground no such increase which takes place after the date of the
delivery stipulated in the contract shall be admissible on such of the said stores
as are delivered after the expiry of the delivery period
period stipulated in the contract.
(d) But nevertheless, the Purchaser shall be entitled to the benefit fit of any
decrease in price on account of reduction in or remission of Custom Duty, Sales
Tax or on account of Foreign Exchange variation or on account of any other Tax
or Duty or on other ground as stipulated in the price variation, clause which takes
place after the expiry of the date of delivery period stipulated in the contract.
3401. The Contractor shall not despatch the Stores till such time as an
extension
extension in terms of para 3400 (a) to (d) above is granted by the Purchaser and
accepted by the Contractor. If the stores are despatched by the Contractor
before an extension letter as aforesaid is issued by the Purchaser and the same
are accepted by the Consignee,
Consignee, the acceptance of the stores shall be deemed to
be subject to the conditions (a) to (d) mentioned in the paragraph 3400 above.
3402. In case where the entire quantity has not been tendered for inspection
with in the delivery period stipulated in
in the contract and the Purchaser chooses
to grant an extension of the delivery period the same would be subject to
conditions (a) to (d) mentioned in the paragraph 3400 above.
3500. These (special) conditions wherever they differ from the Invitation to
Tender
and
Instruction
to
Tenderers
over
ride
the
latter.
(ADDITIONAL) SPECIAL CONDITIONS
(Vide Para 417417-S)
In addition to Standard Conditions of Contract, the following special conditions
shall apply to (Running) Contract: -
3600. Purpose of Contract and Parties to the Contract.
3601. The parties to the contract, which shall be deemed to be a "Running
Contract" and which is intended for the supply of the stores of the descriptions
and approximately in the quantities set forth in the contract during the period
specified therein, shall be the Contractor of the one part and the authorities
named in the contract hereinafter called the Purchaser (which expression shall,
where
where the context so admits or implies, be deemed to include his successors and
assigns) of the other part. The quantities shown in the said Contract, are only
approximate, and cannot be guaranteed.
3602. The Purchaser may authorise any officer (who shall hereinafter be called
Direct Demanding Officer) at any time during the period of the contract, to place
orders direct on the Contractor.
3603. Any variation of this contract shall not be binding on the Purchaser unless
or until same is endorsed on the contract
contract or incorporated in a formal instrument
in exchange of letters and signed by the parties.
3700. Delivery.
3701. The Contractor shall as may be required by the Purchaser either deliver
free or f.o.r or c.i.f. at the place or places specified in the
the contract such quantifies
of the stores detailed in the said contract as may be ordered direct from the
Contractor from timetime-toto-time by the Purchaser or by the Direct Demanding
Officer. The Contractor shall deliver or despatch the full quantity of the stores
stores so
ordered with in the period specified in the said contract.
3800. Increase or Decrease of Quantities.
The Purchaser shall be entitled at any time to increase or decrease the
approximate total quantities of each description of stores shown in the said
contract by not more than 30 per cent and will give reasonable notice in writing of
any such increase or decrease to the Contractor.
3900. Maintenance and Replacement of Stocks.
3901. To meet casual demands, the Contractor shall maintain at all time
time in stock
(until 75 per cent of the requirements have been drawn), at the place (s)
specified in the contract, the quantity /quantities mentioned therein. All demands
should be complied with immediately they are received by the Contractor or
within the period, if any, stipulated in individual orders. As soon as the
Contractor is called upon to effect supplies, he shall take action to replenish the
guaranteed stocks until such time as 75 percent of the total approximate
requirement has been drawn and such
such replenishment shall be completed with
the period specified in the contract, after the receipt by the Contractor of casual
demands. Due notice will be given to the Contractor by the Direct Demanding
Officers or by the Purchaser, if any additional quantities
quantities over and above 75 per
cent of the total approximate requirements are required and Contractor shall then
arrange stocks accordingly.
3902. The period for replenishment of stocks will be allowed only if the material
is not in stock. If the material is in stock, this Provision will be in operative even
tough the guaranteed stock quantity may have been supplied against the
contract.
4000. Reporting Progress of Contract.
The Contractor shall, three calendar months before the termination of the contract
or at such intervals as may be specified in the contract, submit a report to the
Purchaser stating the total quantity of stores delivered or despatched under the
contract.
4100. Special conditions where they differ from Standard Conditions override the
latter.
Annexure Technical
Provisions & technical parameters under this Annexure applicable for this tender will
override the relevant clauses of RDSO’s technical mentioned below. Provision of other
clauses of technical specifications will remain same.
A.
The technical details in reference to annexure-2 of RDSO SPEC. No.
RDSO/2009/EM/SPEC/0004 (rev. ‘1’) – 2012 for 10 KWp SPV based power
supply for railway stations are as under 1. System:
Sn
1
2
3
4
Description
Requirement
Whether 1-ph 230 or 415V 3-ph system is required ? 230V, 1 phase
Whether wind-cum-solar or only solar based system is Only solar
required ? (Refer Cl. 2.0)
Galvanization Thickness (Refer Cl. 6.2.6 & 6.3.19(iii))
85 μm
Is the supply of Export Meter required {Refer Cl. 6.5.5} No
2. Wind Turbine and Support Structure: Not Applicable
3. SPV Module and Support Structure:
Sn
1
2
Description
Requirement
Total power rating of SPV system (KWp)
10KWp
Support structure, design and foundation wind 150Kmph
withstanding capability required (see Cl. 6.3.19 v)
NOTE: The installation of SPV modules should not impact the waterproofing of the
existing terrace structure. The contractor shall be responsible for restoring the
waterproofing to its original condition and for provision of additional waterproofing
in the areas where RCC blocks are secured onto the terrace.
4. Inverter:
Sn
1
2
Description
KVA rating of the Inverter required?
Output voltage rating of Inverter?
Requirement
5KVA
230V 1-phase
5. Battery
Sn
1
2
Description
Battery type (see Cl. 6.6(i))
Battery capacity
Requirement
LMLA type Battery
57,600VAH(min)
NOTE: The bidder must furnish details as per Annexure – 3 of the RDSO
specification No. RDSO/2009/EM/SPEC/0004 (Rev. ‘1’) – 2012
B.
The technical details in reference to Annexure-C of RDSO Spec. no.
RDSO/PE/SPEC/PS/0092-2008 (Rev. ‘0’), Amdt-5 for 2x50 KWp, 1x45 KWP,
500KWp SPV based power supply for railway stations are as under –
Sn
1
Description
Requirement
Total System Power Rating (KWp): 2x50KWp, 1x45KWp and 500
KWp
2
Is Compliance and certification to
salt mist corrosion testing as per
IEC 61701 required {Refer Cl.
6.9.1} (Yes/No), Applicable for ‘A’
above)
Required galvanization thickness
1.
(Refer Cl. 6.10.3)
Support structure, design and
2.
foundation
wind
withstanding
capability required (see Cl. 6.10.5):
3
4
No
85 μm
150Kmph
NOTE: The installation of SPV
modules should not impact the
waterproofing of the existing
terrace structure. The contractor
shall be responsible for restoring
the waterproofing to its original
condition and for provision of
additional waterproofing in the
areas where RCC blocks are
secured onto the terrace.
5
Is supply of Export Metering
- required for 2x50 KWp & 1x45
required {Refer Cl. 4.1, 5.4}
KWp system,
-required for 500 KWp system
NOTE: The bidder must furnish details as per Annexure – D of the RDSO
specification No. RDSO/PE/SPEC/PS/0092-2008 (Rev. ‘0’), Amdt -5.
C. Following clauses are added to above mentioned RDSO’s specificationsSpecification &
Item
Testing
Remark
Clause No.
authority
RDSO/PE/SPEC Prototype
RDSO
As per Clause 5.3(a)- Payment
/PS/0092-2008 testing
for 1st unit of each type of
(Rev-0) Amtd-5
Solar PV module will be made
clause 6.17 &
after prototype testing by
13 and
RDSO at site.
RDSO/2009/EM Routine test Manufact Manufacturer to carry out
/ SPEC/ 0004
urer
tests at his works and submit
(Rev-1) 2012
the results.
Clause 11
Acceptance
RITES
To be carried out by M/s
test
RITES
at site based on
“Acceptance test” as per
referred RDSO’s specification
lR;eso t;rs
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
Hkkjr ljdkj
jsy ea=ky;
GRID CONNECT SOLAR GENERATING SYSTEM
OF CAPACITY 10 KWp to 500 KWp
10 ls 500 fd-ok- ikWoj {kerk ds fxzM la;ksftr
ÅtkZ mRiknu iz.kkyh gsrq fof’kf"V
Specification No. RDSO/PE/SPEC/PS/0092-2008 (Rev. ‘0’), Amdt. 5
fof’kf"V la0 % vkjMh,lvks@ihbZ@Lisd@ih,l@0092&2008 ¼fjoh-*0*½ vesUMesVa -5
S.
N.
1.
Amendment
No.
Date
1st
19.02.09
Revision
No.
Date
-
2.
2nd
13.05.09
-
-
3.
3rd
27.09.10
-
-
4.
4th
12.10.12
-
-
5.
5th
19.08.13
-
-
tkjhdrkZ
ÅtkZ izcU/ku funs’kky;
vuqla/kku vfHkdYi ,oa ekud laxBu
ekud uxj] y[kuÅ&226011
Approved by:
Executive Director/(EM)
Reason
Annexure-A modified as per Rly. Bd’s letter no. 2002/ Elect (G) /
150/Ptdt 30.12.2008
Annexure ’A’ modified as per Railway Board No. letter no.
2002/Elect.(G)/150/9/Pt dated 31.03.2009
Added clause 3.0 in Annexure ‘B’. Modification by additions/deletions in
Clause nos. 1.0, 3.0, 5.4, 6.1, 6.9.1, 6.9.2, 6.9.4, 6.9.5, 6.9.6, 6.9.9,
6.9.13, 6.12.1, 6.12.7, 6.12.14, 6.15, 6.17.
Clause No. 10.0 (Guarantee/ Warranty)
and Annexure ‘A’ (Eligibility
Criterion for Bidding) deleted as per Railway Board’s letter No.
2006/Elect.(G)/150/9/Pt. dated 10.09.2010.
Added clauses 5.8, 5.9, 5.10, 6.9.16, 6.9.17, 6.9.18, 6.12.17, 6.12.18,
6.12.19, 6.12.20, 6.12.21, 6.12.22, 6.12.23, 6.12.24, 6.12.25, 6.12.26,
6.12.27, 6.12.28, 6.13.3, 6.13.4, 6.13.5, 6.17.1, 6.17.2,13, Annexure C
and Annexure D.
Deleted clause nos. 6.9.14, 6.10.11, 6.10.12, 6.10.13, 6.11, 6.12.3 and
6.12.14.
Modification by additions/deletions in cover page and clause nos. 1.0,
2.0, 3.0, 4.0, 4.2, 4.3, 4.4, 4.5, 4.6, 5.1, 5.2, 5.3, 5.4, 5.6, 6.1, 6.2, 6.4,
6.7.1, 6.7.2, 6.7.3, 6.7.4, 6.8, 6.9.1, 6.9.10, 6.9.12, 6.9.13, 6.10.3,
6.10.4, 6.10.5, 6.10.6, 6.10.8, 6.10.9, 6.10.10, 6.12, 6.12.1, 6.12.2,
6.12.4, 6.12.5, 6.12.6, 6.12.7, 6.12.9, 6.12.10, 6.12.15, 6.12.16, 6.12.17,
6.12.18, 6.13, 6.15, 6.17, 6.18, 9.0 and annexure-B.
Added clauses no. 5.3, 6.15(vii)
Deleted clause no. 7.2, 7.3, 7.4
Modification by additions/deletions in cover page and clauses nos. 2.0,
4.3, 4.4, 5.1, 5.2, 5.3, 5.4, 5.9, 6.1, 6.3, 6.5, 6.7.2, 6.7.3, 6.10.2, 6.10.3,
6.10.7, 6.10.8, 6.12, 6.12.4, 6.12.5, 6.12.17, 6.12.27, 6.15, 6.18, 7.0,
12.0 and Annexure-C
ISSUED BY
ENERGY MANAGEMENT DIRECTORATE
RESEARCH DESIGNS AND STANDARDS ORGANISATION
MANAK NAGAR, LUCKNOW- 226011
Page 2 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
INDEX
S. No.
DESCRIPTION
PAGE NO.
1.0
Foreword
3
2.0
Scope
3
3.0
Reference Standards
3
4.0
System Description
4
5.0
General Requirements
5
6.0
Technical Requirements
7
7.0
Installation & Commissioning
19
8.0
Documentation
20
9.0
After Sales Service
20
10.0
Guarantee/Warranty (Deleted)
20
11.0
Log Books
20
12.0
Annual Maintenance Contract
20
13.0
Test
20
Annexure ‘A’ (deleted)
25
Annexure ‘B’
25
Annexure ‘C’
28
Annexure ‘D’
29
Page 3 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
SPECIFICATION FOR GRID CONNECT SOLAR GENERATING SYSTEM OF
CAPACITY 10 KWp TO 500 KWp
1.0
FOREWORD:
Government of India is laying great emphasis on reducing the country’s
carbon footprint. In this pursuance, the Hon’ble Prime Minister of India
has on 30th June, 2008 released the National Action Plan for Climate
Change (NAPCC). One of the NAPCC missions is the National Solar
Mission and it aims to increase the share of solar energy in India’s
overall energy mix. Accordingly, Indian Railways accords high priority to
harnessing of solar energy.
The energy generated by grid connect solar photovoltaic system will be
utilized to feed railways’ electrical loads during daytime. As a result,
during daytime, the purchase of electricity from the electricity authority
will get reduced.
2.0
SCOPE:
This specification provides the generic requirement for grid connect
solar photovoltaic (SPV) system capacities in the range 10 KWp to 500
KWp. The user will specify the SPV system’s KWp capacity, after duly
considering the MNRE norms for subsidy, electrical load and availability
of space for installation of SPV modules. In instances where none of the
standard available Power conditioning unit (PCU) KVA ratingsare
commensurate with the purchaser specified KWp of SPV system, in
such case the purchaser can consider accepting the PCU of next higher
standard rating.
The specification covers general and technical requirements for design,
manufacturing, testing, supply, installation and commissioning of Grid
connect solar generating system to be provided at railway premises for
meeting the railway requirements of lighting, ventilation and other
electrical services. The solar photovoltaic generating system’s inverter
will operate in parallel with the general electric supply system on
railway premises.
3.0
REFERENCE STANDARDS:
IS: 12834:1989
Solar Photovoltaic Energy Systems –
(reaffirmed 2000)
Terminology
IEC : 61215 Ed 2 or Crystalline silicon terrestrial photovoltaic
latest
(PV) modules – Design qualification and type
approval
Page 4 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
IEC: 61730 Pt 1 & 2
Photovoltaic (PV) module safety qualification
-Part 1: Requirements for construction
Part 2: Requirements for testing
IEC: 61701
Salt mist corrosion testing of photovoltaic
(PV) modules
IEC:60904-1(2006)
Photovoltaic Devices- Part-I: Measurement
of Photovoltaic current-Voltage
Characteristic
IS: 9000
Basic environmental testing procedure for
Electronic and electrical items.
IEC:60068
Environmental testing
IEC 61723 Ed1.0
Safety Guidelines for grid connected
photovoltaic systems mounted on the
buildings
IEC 60364-7-712
Electrical Installations of Buildings Part 7:
(2002)
requirements for special installations or
locations
Section, 712: Photovoltaic power supply
systems.
IEC 62446 (2009)
Grid connected photovoltaic systemsMinimum
requirements
for
system
documentation, commissioning tests and
inspection
Note: Normally latest version of the standards shall be referred to.
4.0
SYSTEM DESCRIPTION:
4.1
Solar Photovoltaic (SPV) grid connect system shall consist of mainly the
following: -
4.2
i)
Solar panels
ii)
Module mounting structure
iii)
Junction boxes
iv)
Power conditioning unit (PCU)
v)
Import & Export metering
vi)
Cable and other accessories
The PV array converts the light energy of the sun to DC power. The
module mounting structure shall be used to hold the module in
position. The DC power shall be converted to AC by PCU to supply AC
loads such as computers, lights, fans, etc. within the railway premises.
Solar power shall be integrated with the premises power supply from
electricity authority.
Page 5 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
4.3
DC distribution board/ combiner shall be provided in between solar
array and PCU. It shall have DC Disconnector/MCCB of suitable rating
for connection and disconnection of array section. Type II Surge
Arrestor should be incorporated for surge protection. It shall have
meters for measuring the array voltage and array current. Appropriate
IP protection shall be provided. In case of string inverters, if the
requirements served by DC distribution board are fully taken care of by
string inverter(s), then firms’ proposal (if any) for elimination of DC
distribution board from the system design, can be considered.
4.4
AC distribution board shall be provided in between PCU and loads. It
shall have an integrated energy meter, voltmeter and ammeter. As for
energy, generally the parameter of interest shall be the aggregate energy
output of inverter(s) fed into the individual AC distribution board(s).
Though not mandatory, firms are however encouraged to also offer the
facility for recording the energy output data of each inverter (wherever
multiple inverters are feeding into an AC distribution board). Class I + II
(as per IEC 62305) 100 kA Surge Arrestor should be incorporated for
protection against surges.
4.5
No electrical storage batteries shall be required and accordingly, these
are not included in the scope of work.
4.6
The system shall comply IEC 60364-7-712 and 62446.
5.0
GENERAL REQUIREMENTS:
5.1
Solar generating system shall supply part/ full load of railway service
buildings/ areas. Thereby, the PV system shall reduce the electric
energy units drawn by railway from the grid and reduce IR’s CO2
emissions.
5.2
Solar panels and array junction boxes shall be installed on shade free
roof while the transformer based PCU and distribution boards, etc. shall
be housed inside the room provided by Railways. In case of string
inverters, railways should carefully weigh the option of indoor vs.
outdoor installation. The installation of SPV modules on roof-tops must
not impact the waterproofing of the existing terrace structure. The
contractor shall be responsible for restoring the waterproofing to its
original condition and for provision of additional waterproofing in the
areas where RCC blocks are secured on to the terrace. Even though
roof-top mounting of solar panels shall be the preferred option, if
necessary, railways can at their option specify a ground mounted solar
system for part or full system KWp capacity. In the event that railways
decide on a ground mounted solar system, they must specifically
mention this in their tender and also specify the fencing requirements
as will be appropriate to the site (ref. item 6 of Annexure - C). For
ground mounted solar systems, railways may need to: carry out site
preparation works (e.g. site levelling, removal of obstructions, etc.); plan
Page 6 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
suitable arrangements for preventing theft, vandalism, etc.; ensure the
availability of adequate railway base load; identify a reliable railway grid
power supply line and be responsible for carrying out any
supplementary works required for feeding the renewable energy into the
identified railway grid power supply line.
5.3
For individual systems above 20KWp, availability of requisite space on a
single roof-top can at times become a constraint. In such case, the
system’s overall KWp capacity can be distributed across multiple rooftops and each of the rooftops shall then feed to the grid power supply
system. In works involving such distributed systems, the purchaser
must mention the KWp of individual constituent solar systems in the
tender (refer item 7 of Annexure - C). If the purchaser doesnot mention
anything against item 7 of Annexure - C, it will be deemed that
adequate space is available on a single rooftop for the entire KWp
capacity of the system.
5.4
If required, statutory approval of local authorities/state electricity
distribution company, etc. shall be obtained by the Railway Authority.
An export meter (for recording the number of units exported to the grid),
if required, shall be either installed by state electricity distribution
company or else the respective Railway Authority may include the same
in their scope of work. Export metering will be an optional item; it will
be specifically mentioned by purchaser, if the same is required to be
within the contractor’s scope of supply (see Annex C item 5). It is
emphasized here, that primary purpose of installing the SPV system
covered by this spec., is to meet railway’s own energy requirement,
rather than supplying renewable energy to the public grid.
5.5
Railway Authority shall provide a shadow free area @ 125 - 150 sq.
ft./KWp of solar array.
5.6
Array structure of PV yard and all electrical equipments such as PCU,
inverters, etc. shall be grounded properly. Towards this end, the
contractor will supply and install an adequate number and appropriate
size of IS:3043 – 1987 compliant earthing kits; at least one each for AC
circuit, DC circuit and lighting protection system.
5.7
Suitable marking shall be provided on the bus for easy identification.
5.8
PV modules may be connected in series up to the maximum allowed
operating voltage of the PV modules and the PV inverter, whichever is
lower.
5.9
The reverse current of blocking diodes (connected in series), if required/
provided, shall be rated for 2 X VOC STC of the PV string.
5.10 Proper sealing arrangements at the points of cables entering the
enclosures/ buildings should be incorporated. Although not mandatory,
Page 7 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
manufacturers are however encouraged that the cables entering into
the enclosures be sealed with modular EPDM based cable sealing and
protection system based on multi-diameter technology.
6.0
TECHNICAL REQUIREMENTS:
6.1
The DC output from the modules shall be fed to array junction box
and the strings are paralleled at sub Main & Main junction boxes.
Then PCU shall convert DC energy produced by the solar array to AC
energy. The AC power output of the inverter shall be fed to the AC
distribution board (metering panel & isolation panel), which also houses
the energy meter. The AC output of grid-connect SPV system should be
paralleled with railway’s general electric power supply i.e.the power
supply received from the electricity authority.
6.2
The system shall automatically wake-up in the morning and supply
power, provided there is sufficient solar energy and the grid voltage and
frequency are in range.
6.3
When the grid voltage and/or frequency go out of preset range, the
inverter shall be immediately disconnected from the grid. The inverter
will reconnect after a pre-determined time when the grid is back in the
range.
6.4
Array to inverter voltage drop shall be less than 3% at the
power output of the array.
6.5
Railways shall provide adequate space and ventilation for the inverter. If
string inverters are used, thesecan be installed below the solar array.
6.6
For safety reasons, PV inverter system shall be disconnected from
network following a fault or loss of supply on the power network.
6.7
The performance and generation data shall be recorded using a data
logger. The monitoring system shall comprise of the following main
components:
maximum
the
6.7.1 PCU will log the inverter performance data and transmit the same to the
data logger. It shall also monitor basic parameters like power generated,
etc.
6.7.2 Data logger shall gather information and monitor the performance of
the inverter. It shall also support measurements from the external
sensors. Data Logger shall also monitor the Solar Insolation and Temp
of Array Yard. RDSO and the concerned railway shall be afforded free of
cost facility for viewing the system performance data on the
manufacturer’s or system integrator’s or railway’s web portal for until
the contractual warranty period of the system. It is advisable that the
facility of web based system monitoring should continue even after
Page 8 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
completion of warranty period. After the warranty period, the web based
monitoring facility shall be available as a part of AMC, if any (see Cl.
12.0). Else, if the railway desires to enter into a separate new agreement
with the contractor solely for post-warranty web based monitoring for a
specified period, then it should provide for the same in special condition
of tender and ask the tenderers to quote for the same (refer item 8 of
Annexure-C).
6.7.3 Data logging system/software shall enable automatic long-term
storage of measured data from PV plant. It shall allow visualization,
monitoring, commissioning and service of the installation. The data
logger shall be web enabled. It should be possible to access the data
logger with any standard web browser like internet explorer, google
chrome, etc. and for this purpose, relevant software/ hardware will be
supplied by the contractor. In addition to the web portal, it should also
be possible to retrieve the data directly from the data logger. The
software for access/ visualization of data from data logger should also
be provided by the supplier. Necessary executable files, if any, will be
required to be given free of cost by the supplier on a CD/ any other
storage device.
6.7.4 Communication interface
The system should offer RS232/RS485 port and LAN/ WAN interface to
facilitate remote monitoring of the system.
6.8
Sizing of the SPV system
Sizing of the system should be decided on the basis of railway’s
electrical load requirement and the availability of space for installation
of SPV system.
6.9
SPV Module
6.9.1 Individual Solar PV Module should be of minimum capacity 230 Wp
conforming to IEC:61215 Ed 2 or latest, IEC : 61730 – I :2007, IEC :
61730 – II : 2007, manufactured in a plant certified under ISO 9001 :
2008 and type tested by an accredited national/international testing
laboratory. The Solar PV Module should be made from mono/poly
crystalline Silicon Solar Cell connected in series. Imported SPV module
or cell will not be accepted, unless MNRE’s policy/ rules permit the
same. PV modules
to be used in a highly corrosive atmosphere (coastal areas, etc.) must
qualify Salt Mist Corrosion Testing as per IEC 61701; this compliance
and certification will not be required, unless the purchaser specifically
asks for the same. Cut cells should not be used (see Annex C, item 2).
6.9.2 SPV modules of similar output with +5Wp tolerance in single string
shall be employed to avoid array mismatch losses.
Page 9 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.9.3 SPV module shall contain crystalline high power silicon solar cells. The
solar cell shall have surface anti-reflective coating to help to absorb
more light in all weather conditions.
6.9.4 Photo-electric conversion efficiency of SPV module shall not be less
than 14%.
6.9.5 Fill factor of the module shall not be less than 72%.
6.9.6 Each module shall have low iron tempered glass front for strength
and superior light transmission. It shall also have tough multi- layered
polymer back sheet for environmental protection against moisture and
provide high voltage electrical insulation. Transmitivity of glass shall
not be less than 91%.
6.9.7 Module junction box and terminal block (weather resistant) shall be
designed for long life outdoor operation in harsh environment.
6.9.8 Bird spike shall be provided so as to avoid bird sitting on the solar
modules at the highest point of the array/module structure.
6.9.9 SPV module shall be highly reliable, light weight and shall have a
service life of more than 25 years. SPV modules shall have a limited
power loss of not more than 10% of nominal output at the end of 10
years and of not more than 20% of nominal output at the end of 25
years.
6.9.10 The output of any supplied module shall not be less than the rated
output and shall not exceed the rated power by more than 5Wp. Each
module, therefore, has to be tested and rating displayed.
6.9.11 Whenever more than one module is required, identical modules
be used.
shall
6.9.12 The module shall perform satisfactorily in relative humidity upto 95%
and temperature between -10oC and +85oC.
6.9.13 The solar modules shall have suitable encapsulation and sealing
arrangements to protect the silicon cells from the environment. The
encapsulation arrangement shall ensure complete moisture proofing
for the entire life of solar modules. The terminal block shall be
preferably of Noryl rubber with weatherproof design (min. IP 65) and
shall have a provision for opening /replacing the cables if required.
6.9.14 Deleted
Page 10 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.9.15 Marking
Each module shall carry the following clear and indelible markings:i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
x)
xi)
xii)
Name, monogram or symbol of manufacturer
Type or model number
Serial number
Polarity of terminals or leads (colour coding is permissible)
Open – circuit voltage
Operating voltage
Maximum system voltage for which the module is suitable
Operating current
Short circuit current
Date & place of manufacture
Weight of the module
Module Wp tolerance (if it is cumbersome to supply this
marking, then this marking can be left out)
6.9.16 Each PV module must use a RF identification tag (RFID), which must
contain the following information. The RFID can be inside or outside
the module laminate, but must be able to withstand harsh
environmental conditions.
i)
ii)
iii)
Name of the manufacturer of PV Module
Name of the Manufacturer of Solar cells
Month and year of the manufacture (separately for solar cells
and module)
iv)
Country of origin (separately for solar cells and module)
v)
I-V curve for the module
vi)
Peak Wattage, Im, Vm and FF for the module
vii) Unique Serial No and Model No of the module
viii) Date and year of obtaining IEC PV module qualification
certificate
ix) Name of the test lab issuing IEC certificate
x)
Other relevant information on traceability of solar cells and
modules as per ISO 9000 series
6.9.17 Modules shall be tested as per clause-13.1.
6.9.18 Insulation Resistance of the module shall not be less than 50M-ohm
when measured with a 500V DC megger.
6.10
Module Mounting Structure
6.10.1
The array structure shall be so designed that it will occupy
minimum space without sacrificing the output from SPV panels.
6.10.2
The structure shall be designed to allow easy replacement of any
module by authorized personnel and shall be in line with the site
requirements.
Page 11 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.10.3
The array structure shall be made of hot dipped galvanized MS
angles (or alternate MS sections) of suitable size. Galvanization
thickness shall be of min. 85μm. If the systems are installed in
coastal/ corrosive areas, the minimum galvanization thickness of
array structure shall be 120μm. Unless the purchaser has
specifically asked for 120 μm thickness, normally 85 μm will be
supplied (see Annex C item 3).
6.10.4
The foundation for module mounting structure shall be preferably
1:2:4 RCC construction or any other combination
based on the
local site condition requirement for which design details shall be
submitted.
6.10.5
The support structure, design and foundation shall normally be
designed to withstand wind speed upto 150 kmph. In coastal/ high
wind areas, the support structure, design and foundation shall be
designed to withstand wind speed upto 200 kmph. If the purchaser
does not specify anything to the contrary, then 150 kmph wind
withstanding capability shall be provided (Refer item 4 of AnnexureC).
6.10.6
The clearance between lowest part of the module structure and the
developed ground level shall normally not be less than 500mm.
However, in exceptional cases, lower clearances may be allowed on
case to case basis.
6.10.7
The module alignment and tilt angle shall be calculated to provide
the maximum annual energy output. This shall be decided based on
the location of array installation.The SPV panel shall have a
provision for angular adjustment of the mounting structure to get
maximum utilization of incident sunlight. It shall be mounted facing
south and tilted to an angle equal to the latitude (where being used),
for optimum performance.
6.10.8
Generally, fasteners shall be of stainless steel SS304. To prevent
pilferage, anti-theft fasteners shall be provided at appropriate
locations.
6.10.9
Junction Boxes
i) The module junction box (if any) shall be certified as per IEC
61215. Else, they should have the same properties as mentioned
for array junction boxes. Array sub-main and main junction
boxes, shall have the following properties:
a. They shall be dust, vermin & waterproof and made of
Polycarbonate-Glass Fibre Substance (PC-GFS) thermoplastic.
The enclosure should be double insulated with protection
class II as per IEC 61439-1. Material and the protection class
shall be marked on the enclosure.
b. The enclosure shall have a transparent front lid for enabling
easy visibility.
Page 12 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
c. The enclosures shall have IP 65/66 protection in accordance
with IEC 60529. Third party conformance certificate is
required to be given for IP 65/ IP 66 degree of protection.
d. Minimum requirements for fire protection in the event of
internal faults: Glow wire test in accordance with IEC 60 6952-11 at 960C for box and 850C for conducting components.
e. Burning Behavior: Base part of Polycarbonate Enclosure shall
be UL94-V-0 compliant and Lid part of PC Enclosure shall be
UL94-V-2 compliant.
f. The enclosures shall have IK 08 degree of protection for
mechanical load.
g. The material used shall be halogen, silicon free conforming to
RoHS directive 2002/95/EC.
h. The enclosure shall have a usage temperature rating of -10C
to 55C.
i. The enclosure should be chemically resistant to acid, lye,
petrol, mineral oil & partially resistant to benzene.
j. The enclosures shall have a rated insulated voltage of 1000V
DC and dielectric strength of 4.65 KV DC.
k. The material of the enclosure shall be UV stabilized.
l. Though not mandatory, manufacturers are encouraged to
provide breather glands in the array junction boxes to prevent
overheating and explosions.
Unless otherwise stipulated, the properties mentioned above
should be demonstrated through datasheet of the manufacturer.
ii) SPDs Class II as per IEC 61643-1, shall be used at the terminals of
array junction boxes for external surge protection. Internal Surge
protection (SPDs) shall consist of three MOV type arrestors
connected from + ve and – ve terminal to earth (Via Y arrangement)
for higher withstand of the continuous PV-DC voltage during earth
fault condition. SPD shall have safe disconnection & short circuit
interruption arrangement through integrated DC in-built bypass
fuse (parallel) which should get tripped during failure mode of
MOV, extinguishing DC arc safely (created by inbuilt thermal
disconnection) in order to protect the installation against fire
hazards. Nominal discharge current (In) at 8/ 20 microseconds
shall be minimum 10 KA with maximum discharge current (Imax)
of minimum 20 KA at 8/20 microseconds with visual indication
(through mechanical flag) in all modules to monitor the life of SPD.
TheIscwpv (Short Circuit current withstand capacity of arrester)
would be at least 10% more than Nominal output current of the
combiner box and AJB. Detailed internal schematic for the above
SPDs, compliant to these specifications, should be submitted by
the manufacturers.
Page 13 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
iii) The junction boxes shall have suitable cable entry points with
cable glands of appropriate sizes for both incoming and outgoing
cables. Though not mandatory, manufacturers are encouraged to
provide suitable cable entry points fitted with MC-4 Connectors.
iv) Suitable markings should be provided on the bus bar for easy
identification, and cable ferrules shall be fitted at the cable
termination points for identification.
v) The Array Junction Box should preferably have maximum 08 input
and 01 output with SPD and Terminal block.
6.10.10 Earthing for PV array, Balance of System (BOS), lightning
protection and other components.
i)
The photovoltaic modules, Balance of system (BOS) and other
components of power plant require proper grounding for
protection against any serious faults as guided by IEC 60364.
ii) The earthing resistance must not exceed the limits generally in
practice for such applications.
iii) The Bidder shall submit the detailed scheme of earthing and
grounding.
iv) The contractor will supply and install an adequate number and
appropriate size of IS:3043 – 1987 compliant earthing kits; at least
one each for AC circuit, DC circuit and lighting protection system.
v) The source of over voltage can be lightning or other atmospheric
disturbance. Main aim of over voltage protection is to reduce the
overvoltage to a tolerable level before it reaches the PV or other
sub-system components. Lightning protection should be provided
as per IEC 62305.
vi) Necessary concrete foundation or any other arrangement for
holding the lightning conductor in position is to be made after
giving due consideration to shadow on PV array, maximum wind
speed and maintenance requirement at site in future.
vii) The lightning conductor and structures shall be earthed through
flats as per applicable Indian Standards with earth pits. Each
lightning conductor shall be fitted with individual earth pit as per
required Standards including accessories, and providing masonry
enclosure. Else, a matrix of lightning conductors is to be created
which will be required to be connected to an earth.
viii) If necessary, more numbers of lightning conductors may be
provided.
ix) The Bidder shall submit the drawings and detailed specifications
of the PV array lightning protection equipment.
6.10.11 Deleted
6.10.12 Deleted
Page 14 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.10.13 Deleted
6.11
Deleted
6.12
Power Conditioning Unit (PCU)
PCU shall supply the DC energy produced by array to DC bus for
inverting to AC voltage using its MPPT (Maximum Power Point
Tracking) control to extract maximum energy from solar array and
produce 415V (+15% and -20%) AC, 3 phase, 50 ± 5% Hz (47.5 to
52.5 Hz) to synchronize with the local grid. For sizing ofgrid connect
inverter,the general guideline will be that the ratio of SPV KWp
rating to inverter’s KVA rating shall be within 1.15. The array output
should be well within the input voltage range of the inverter so that
the inverter works in MPPT range for most of the solar insolation
range. This should be applicable for the whole life of the solar array
and needs to be substantiated through design calculations. PCU
should be able to handle maximum open circuit DC voltage of
1,000V.
6.12.1
MPPT controller, inverter and associated control and protection
devices, etc. all shall be integrated into the PCU.
6.12.2
PCU/ string inverter shall provide 3 phase, 415V (with grid tracking
of +15%/-20%), 50 Hz (with grid tracking of ±5% i.e. 47.5 to 52.5 Hz)
supply on AC side with voltage THD of less than 3% and current
THD of less than 5%.
6.12.3
Deleted
6.12.4
Efficiency of PCU with transformer shall not be less than 92% for
systems from 10KWp to less than 30 KWp, 93% for systems from
30KWp to less than 50KWp and 94% for systems greater than or
equal to 50KWp. For transformer-less design, it shall be minimum
96%.
6.12.5
Degree of protection will be minimum IP20 for non-electronics
portion where transformer, etc. are mounted, if any and for the rest
of the portion including electronics, it will be IP31 for units of
capacities upto 15KWp and IP41 for units of capacities greater than
15KWp.For inverters to be installed outdoors, IP65 protection shall
be required. In future, RDSO will actively consider upgrading the
requirement of IP protection, keeping in view the highly dusty
environment in Indian subcontinent. Therefore, manufacturers are
encouraged to develop even higher IP protected systems for future
requirements of IR.
Page 15 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.12.6
Railways should carefully weigh the option of indoor vs. outdoor
location for string inverter.
6.12.7
The inverter shall be efficient with IGBT based reliable design. The
control system should be of highest reliability preferably based on
Digital Signal Processors.Though not mandatory, the manufacturers
are encouraged to provide the control system of redundant type.
6.12.8
The PCU shall be capable of complete automatic operation, including
wake-up, synchronization and shut down.
6.12.9
PCU shall have the facility to display the basic parameters of the
system on a typical 4 line by 20 characters type LED/LCD display.
Displays of a bigger size can also be provided.
6.12.10 PCU shall be able to synchronize independently and automatically/
phase-lock with POWER SUPPLY AUTHORITY grid power line
frequency to attain synchronization.
6.12.11 Built-in data logging to monitor plant performance through external
PC shall be provided.
6.12.12 Inverter shall be tested for islanding protection performance.
6.12.13 Only isolated inverters shall be grounded on DC side.
6.12.14 Deleted
6.12.15 Indications (through LEDs/ LCD display)
Following is an indicative listof indications (the actual scheme will be
finalized at design stage):
i)
ii)
iii)
iv)
v)
vi)
Inverter ON
Grid ON
Inverter under voltage/over voltage
Inverter over-load
Inverter over-temperature
Earth Fault
6.12.16 Protections
Following is an indicative list of protections (the actual scheme will
be finalized at design stage):
i)
ii)
iii)
iv)
Over-voltage both at input and output
Over-current both at input and output
Over/under grid frequency
Over temperature
Page 16 of 29
Effective from August 2013
v)
vi)
vii)
viii)
ix)
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Short circuit on AC side
Reverse polarity protection
Array ground fault protection
Protection against lightning induced surges Class II, 10 kA
as per IEC 61643-1
Protection against surge voltage induced at output due to
external source
6.12.17 Night consumption of the PCU shall be less than 0.2% of the rated
power of the inverter for system capacities of 25KWp or more. It shall
be less than or equal to 50W for system capacities of less than
25KWp.
6.12.18 Noise level of the PCU should be less than 65 dBA (nominal) at 1m.
6.12.19 DC insulation resistance should be more than 50MΩ.
6.12.20 EMI and EMC Requirements:PCU shall comply the following EMI
and EMC requirements:
i) Emitted interference as per IEC: 61000-6-4.
ii) Interference emitted as per IEC: 61000-6-2.
6.12.21 An integrated earth fault detection device is provided to detect
eventual earth fault on DC side and shall send message to the
supervisory system.
6.12.22 Idling current at no load shall not exceed 2% of the full load current.
6.12.23 PCU shall withstand high voltage test of 2,000 Vrms between either
the input or the output terminals and the cabinet (chassis).
6.12.24 PCU includes ground lugs for equipment and PV array groundings.
The DC circuit ground shall be a solid single point ground
connection.
6.12.25 Where PCU hasnot been provided with galvanic isolation, a type B
residual current device (RCD) according to IEC 60755 amendment
2 shall be installed to provide fault protection by automatic
disconnection of supply. Inbuilt RCD will also be accepted.
6.12.26 To allow maintenance of the PCU, means of isolating the PCU from
the DC side and the AC side shall be provided.
6.12.27 PCU can be a centralized unit or a combination of multiple string
inverters.
6.12.28 The PCU should withstand the environmental tests (as per IEC
60068/ IS 9000) listed below with the PCU working at full load for at
least last half an hour. For SPV systems of 10 KWp or higher
Page 17 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
capacity, environmental test results in respect of any similar design
PCU for at least 10 KWp SPV systems will be adequate.
a) Dry Heat Test: 50C±2C for 16 hours
b) Damp Heat Test (Steady state): 40C, 93% RH for 4 days
c) Damp Heat Test (Cyclic): 40C, 93% RH for 6 cycles (duration of
one cycle shall be 24hrs)
d) Cold Test: 0C for 16 hours
e) Change of temperature Test: -10C/-5C to 50C for 3 cycles (rate
of change in temperature shall be 3oC per minute)
6.13
Cables and Hardwares
The cables used in module/ array wiring shall be TUV 2Pfg
1169/08.2007 or VDE EPV 01:2008-02 or UL4703 certified.
Cables of appropriate size to be used in the rest of the system shall
have the following characteristics:
i)
Temp. Range –10ºC to +120ºC.
ii)
Voltage rating 600/1000V
iii)
Excellent resistance to heat, cold, water, oil, abrasion, UV
radiation, ozone and weathering
iv)
Halogen-free, low smoke, low toxicity.
v)
Flame retardant
vi)
Flexible
vii) Fulfills IEC 60332-1 requirements. Accredited
report/Manufacturer’s test report shall be attached.
lab
test
viii) Conductor class IEC 60228 class 5. Accredited
report/Manufacturer’s test report shall be attached.
lab
test
6.13.1 Cabling on DC side of the system shall be as short as possible to
minimize the voltage drop in the wiring.
6.13.2 Components and hardware shall be vandal and theft resistant. All
parts shall be corrosion-resistant.
6.13.3 Voltage drop on the DC side from array to the inverter should not be
more than 3%. Necessary calculations in this regard shall also be
submitted during design approval.
6.13.4 Overload protection may be omitted to PV string and PV array cables
when the continuous current-carrying capacity of the cable is equal to
or greater than 1.25 times ISC STC at any location. Necessary
calculations in this regard shall be submitted during design approval.
Page 18 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
6.13.5 Overload protection may be omitted to PV main cable if the
continuous current-carrying capacity of the cable is equal to or
greater than 1.25 times ISC STC of the PV generator. Necessary
calculations in this regard shall be submitted during design approval.
6.14
The system description, general/technical requirements, etc. are
given for general guidance only. The supplier/manufacturer shall
submit the detailed design of the complete solar generating system by
using their software to optimize the combination of modules
considering the specific location, insolation, nature of load, etc.
6.15
AC Distribution Board (ACDB):
The ACDB shall be used to terminate single or multiple PCU
outputs.The ACDB must have the following features:
i) Cables connecting bus bar should be minimum 3 times capacity of
Solar Power plant.
ii) Input Grid Line should come from such Distribution Board of client
so that the railway load is fed parallely by the grid as well as SPV
system.
iii) The Solar Power should be exported to the bus bar inside the
ACDB through a LCD display Energy Meter. In case the systems
are installed on multiple rooftops, then for each individual rooftop
system, an independent ACDB shall be generally required.
iv) The Designated Load should be routed through ACDB and an
Energy Meter to register the Load Energy Consumption from Solar
and Grid during Week Days and Holiday.
v) The SPV system will help Railways to obtain GRIHA/ ECBC
certification for the buildings.
vi) ACDB should have Class I + II (as per IEC 62305; IEC 61643 and
IEC 60364-5-53), 100 kA Surge Suppression inbuilt for surge
protection. Surge protection on AC side (Type 1 + Type 2) shall
consist of Pre wired metal encapsulated spark gap based solution
for fire safe and fire proof operation at site, consisting of base part
and plug in protection modules. Total discharge capacity/
Lightning Impulse current (Iimp) at 10/350 μ sec and nominal
discharge current (In) at 8/ 20 μ sec shall be minimum 100 KA for
three phase power supply system and 50 KA for single phase power
supply system. The discharge capability of L-N connected module
shall be 25 KA at 10/350 μ sec and 8/20 μ sec. All the L-N & N-E
connected arresters shall have built in mechanical health
indication. Complete solution shall have voltage protection level
(Up) of <= 1.5 KV to protect the sensitive electronics inside the
Page 19 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Invertors, having follow current extinguishing and limiting
capability up to 25 KA rms (at 255V) without tripping of even small
rating 32 AGL/gG fuse and approved from international
independent test labs like KEMA or VDE or UL as per latest IEC
61643-1 or equivalent EN 61643-11 standard. SPDs on the ACDB
shall be provided if the same haven’t been provided on the PCU.
vii) Appropriate IP protection shall be provided
6.16 Approval of System Design
6.16.1
The concept plan/design of each sub-system shall be submitted to
RDSO for approval. The wiring diagram and operation and
maintenance information details shall be given as detailed in IEC
62446.
6.16.2
Quality Assurance Plan should include design control, process
control, quality control, testing of sub-system, integration and
bill
of material intended to be used.
6.17
Prototype Testing
6.17.1
RDSO shall conduct prototype testing of Grid connect Solar
Generating System of individual capacity separately. For certain
tests, the type testing authority i.e. RDSO may choose to rely upon
previous type test reports/conformance certificates, as long as they
pertain to similar design and are of comparable rating. However, the
manufacturer cannot demand this as a matter of right.
6.17.2
Until the railways are able to issue their vendor list, they may in the
interim period invite tender/ place order with the provision of
accepting the material on the basis of firm’s written clause-by-clause
confirmation of the spec. and acceptance test alone, wherever this is
considered necessary by CEE.
6.18
Cleaning of SPV modules
For the purpose of cleaning of SPV modules, railways shall ensure
that the Array Yard is equippedwith permanent Water Line, Butterfly
valve and rubber hose. During the warranty period, the contractor
shall carry out the cleaning of SPV modules, on an average, once in
three months; in addition, railway on its part will be responsible to
arrange for cleaning of SPV modules once in every two weeks.
7.0
INSTALLATION & COMMISSIONING:
The installation shall be done by the supplier/manufacturer who
is responsible for system performance, direction of installation and
structural stability. The supplier shall conduct a detailed site
assessment. The PV installer shall obtain data specific to the site,
rather than relying on general data. While making foundation
Page 20 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
design, due consideration shall be given to weight of the module
assembly, maximum wind speed at the site, etc.
8.0
DOCUMENTATION:
The supplier shall provide easy-to-use illustrated installation and
operation manual in English for easy installation and trouble-free
usage. Manual shall contain complete system details such as array
layout, schematic of the system, working principle, clear instruction
on regular maintenance, trouble-shooting of the solar generating
system, emergency shutdown procedure, etc.
9.0
AFTER SALES SERVICE:
The details of service centers in India shall be provided along with
the offer. All essential materials and manpower shall be placed at the
service centers to ensure quick and efficient after sales service.
10.0
GUARANTEE / WARRANTY - (Deleted)
11.0
LOG BOOKS:
Railways shall maintain a logbook detailing inspection and operating
activities. This logbook must be kept in a secure place and shall be
made available, whenever required for inspection. Testing of all
protection devices shall be carried out at regular intervals (no longer
than six months) by the customer and recorded in the logbook.
12.0
ANNUAL MAINTENANCE CONTRACT:
The contractor will have to quote the rates for Comprehensive Annual
Maintenance Contract (AMC). During the AMC period, the contractor
shall also carry out the cleaning of SPV modules, on an average, once
in three months; in addition, railway on its part will be responsible to
arrange for cleaning of SPV modules once in every two weeks. Further,
unless otherwise stipulated by the purchaser in the tender, during the
AMC period, the contractor shall also provide web based monitoring
facility (as detailed in Cl. 6.7.2).
13.0
TESTS:
The manufacturer shall carry out routine tests at his works and shall
maintain records for the same. Acceptance testing shall be carried out
by the purchaser or his representative or by any agency deputed by
the purchaser on his behalf.
Page 21 of 29
13.1
S.N.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Test on SPV Module
Name of Test
Type
Test
Routine
Test
Visual
Examination
Design
Qualification
Safety
Qualification
Photo Electrical
Conversion
Efficiency
Fill Factor
√
√
√
√
√*
IEC 61215
√
√
√*
IEC 61730- I & II
√
√
√
By Sun simulator(Refer
Cl. 6.9.4)
√
√
√
Transmitivity of
Glass
Rated output of
module
Module
mismatch test
Array mismatch
test
Encapsulation
and sealing
Terminal block
Provision of Bird
Spike
Provision of
RFID tag with
requisite details
Environmental
tests
Provision of
Earthing
Marking
√
By Sun simulator (Refer
Cl. 6.9.5)
Refer Cl. 6.9.6
√
√
√
By Sun simulator. Refer
Cl. 6.9.1
Refer Cl 6.9.10
√
Refer Cl 6.9.2
√
Accept
Method
ance
Test
√
Refer Annexure B
√
√
√
Refer Cl 6.9.13
√
√
√
√
√
Refer Cl 6.9.13
Refer Cl 6.9.8
√
√
√
Refer Cl 6.9.16
√
√**
√
√
Refer Cl 6.10.10
√
Refer Cl 6.9.15
√
√
Refer Annexure B
* Copy of the latest conformance certificates should be asked
** If compliance has already been checked during type testing, the same will
be relied upon, otherwise compliance will be ensured through physical tests
13.2
S.N.
1.
Tests on Module Mounting Structure
Name of Test
Visual Examination
Type
Test
Routin
e Test
√
√
Accepta
nce
Test
√
Method
Page 22 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
2.
Dimension
√
√
√
3.
√
√
√
√
Refer Cl 6.10.6
√
Refer Cl 6.10.3
6.
Design calculation on
wind withstand
capability
Clearance between
module and ground
Galvanization
thickness
Foundation
As per
manufacturer’s
data sheet
Refer Cl 6.10.5
√
Refer Cl 6.10.4
7.
Provision of Earthing
√
√
Refer Cl. 6.10.10
8.
Fasteners
√
√
Refer Cl. 6.10.8
4.
5.
13.3
Tests on module
Junction Box
√
√
√
junction box,
Array sub-main and main
S.N.
Name of Test
Type
Test
Routine
Test
1.
Visual Examination
√
√
Accept
ance
Test
√
2.
3.
4.
5.
Material
IP Protection
Surge Protection
Cable Glands
√
√
√
√
√
√
√
√
√
√
√
13.4
Name of Test
Type
Test
Routine
Test
1.
2.
3.
4.
5.
Visual Examination
MPPT range
Voltage Range
Frequency range
Harmonics on AC
side
PCU efficiency
Protection Tests
Surge Protection
√
√
√
√
√
√
√
√
√
Acceptance
Test
√
√
√£
√£
√
√
√
õ
√
√
√
õ
IP protection
Control Circuit
√
√
9.
10.
Refer Cl
6.10.9(i),(iii), (iv) &
(v)
Refer Cl 6.10.9(i)
Refer Cl 6.10.9(i)
Refer Cl 6.10.9(ii)
Refer Cl 6.10.9(iii)
Test on Power Conditioning Unit (PCU)
S.N.
6.
7.
8.
Method
√
Method
Refer
Refer
Refer
Refer
Cl.
Cl.
Cl.
Cl.
Refer Cl.
Refer Cl.
Refer Cl.
6.15(vi)
Refer Cl.
Refer Cl.
6.12
6.12
6.12
6.12.2
6.12.4
6.12.16
6.12.16,
6.12.5
6.12.7
Page 23 of 29
S.N.
Effective from August 2013
Name of Test
24.
redundancy
Automatic operation
& synchronization
Islanding Protection
Displaying of basic
Parameters on
LED/LCD display
Data logging,
Communication
interface and web
application
Night Consumption
Noise Level
Power Factor
Measurement
Insulation
resistance
EMI/EMC
Idling current
High Voltage test
Provision of RCD
Provision of
Isolation
Earthing
25.
Environmental Test
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Type
Test
Routine
Test
Acceptance
Test
Method
√
√
√
√
√
√
√
√
Refer Cl. 6.12.8,
6.12.10
Refer Cl. 6.12.12
Refer Cl. 6.12.9
√
√
√
Refer Cl. 6.7
√
Refer Cl. 6.12.17
Refer Cl. 6.12.18
√
√
√
√
√
√
√
Refer Cl. 6.12.19
√
√£
√
√
√
√
√
Refer
Refer
Refer
Refer
Refer
√
√
√
√
√
√
√
√
√
√£
Cl.
Cl.
Cl.
Cl.
Cl.
6.12.20
6.12.22
6.12.23
6.12.25
6.12.26
Refer Cl. 6.12.24,
6.10.10
Refer Cl. 6.12.28
If compliance has already been checked during type testing, the same will
be relied upon, otherwise compliance will be ensured through physical tests
µ Datasheet of the manufacturer will be relied upon
£
13.5
Tests on Cables
S.N.
Name of Test
Type
Test
Routine
Test
1.
2.
3.
4.
Visual Examination
Temperature range
Voltage rating
Resistance to heat,
cold, water, oil,
abrasion, UV
radiation, ozone
and weathering
Halogen –free,
√
√β
√β
√β
√
√β
√β
√β
√β
√β
5.
AcceptMethod
ance
Test
√
√β
Refer Cl 6.13(i)
√β
Refer Cl 6.13(ii)
β
√
Refer Cl 6.13(iii)
√β
Refer Cl 6.13(iv)
Page 24 of 29
S.N.
6.
7.
8.
9.
10.
11.
Name of Test
Low smoke and
Low toxicity
Flame retardant
Flexible
IEC 60332-1
requirements
IEC 60228 class 5
Module/ array
wiring
Sizing of cable
β
13.6
S.N.
Effective from August 2013
Type
Test
Routine
Test
Acceptance
Test
√β
√β
√β
√β
√β
√β
√β
√β
√β
Refer Cl 6.13(v)
Refer Cl 6.13(vi)
Refer Cl 6.13(vii)
√β
√
√β
√
√β
√
Ref. Cl 6.13(viii)
Ref. Cl 6.13
√
√
√
Ref. Cl 6.13.4,
6.13.5
Other tests
Name of Test
Type Routine
Test
Test
√
√
Visual Examination
2.
DCDB
√
3.
ACDB
√
4.
Configuration of
supply
System design
6.
Method
Manufacturer’s data sheet shall be relied upon
1.
5.
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Data Logger and
Web Based
Monitoring
Acceptance
Method
Test
√
Refer Cl 4.3,
4.4, 6.1,6.15,
and 6.16
√
Refer Cl 4.3
√
√
√
√
√
√
Refer Cl 4.4 and
6.15
Refer Cl 6.1
Refer Cl 6.16,
6.13.4, 6.13.5
Refer Cl 6.7
Page 25 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Annexure -A
Eligibility Criterion for Bidding – (Deleted)
Annexure-B
Quality Testing of PV-Module
Modules used in solar panels shall have IEC 61215 Ed 2 or latest compliance
certificate. The qualification testing procedure is defined in IEC 61215 Ed 2
or latest to examine the impact of mechanical, thermal and electrical stress
on power output. The bidder shall submit appropriate
type approval
certificate for the offered solar modules from accredited test laboratory.
Method of Testing
1.0
Visual Inspection:
Each module shall be carefully inspected under an illumination of not
less than 1,000 lux for the following conditions:
1.1
Racked, bent, misaligned or torn external surfaces.
1.2
Broken / cracked cells
1.3
Faulty interconnections or joints
1.4
Cells touching one another or the frame
1.5
Failure of adhesive bonds; bubbles or delaminations forming a
continuous path between a cell and edge of the module
1.6
Faulty terminations and exposed live electrical parts
1.7
Junction box should have common terminals with suitable blocking
diode to prevent reverse current flow.
2.0
Performance at STC: (Clause 10.1 of IEC 61215 Ed 2 or latest)
The current-voltage characteristics of the module shall be determined
in accordance with IEC 60904-1 at a specific set of irradiance and
temperature conditions. Performance of PV-Module shall be generally
Page 26 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
evaluated at
Standard-Test-Conditions (STC) as defined in IEC
60904 standards:
i)
ii)
iii)
3.0
4.0
Cell temp. of 25° C,
Incident solar irradiance of 1000W/m2,
Spectral distribution of light spectrum with an air mass
AM=1.5
All PV modules supplied shall be accompanied with I-V curves
(tested in the manufacturing unit, clearly indicating the serial
number, batch number, date and country of origin).
Environmental Testing:
Following environmental test shall be conducted on offered module or
on module of similar design, for initial clearance of the offered system.
Test
Cold
Test
Dry
Heat
Salt spray*
Wind
Rain
Dust
Others
Test Details
Temp. (-) 100C
Duration: 16 hrs.
Temp. (+) 700C
Duration: 16 hrs
Temp. (+) 350C, RH 95%
Duration: 2 hrs spray and 22
hrs conditioning
No. of Cycle : 01
Pressure equivalent to an air
velocity of 200 km/hr.
Test as required in the
mentioned standards
Temp : 40°C, RH < 50%
Duration – 1 hr
Electrical
Isolation
test
Routine test
Actual
test
to
be
carried out at Govt.
Recognized
Lab
or
manufacturer premises
as per standard
IEC-68-2-1
IEC-68-2-2
IEC-68-2-11 Test Ka
JSS: 55555 (Test No. 12)
JSS: 55555 (Test No. 14)
Shall be done at
manufacturers place for
every modules offered
* If compliance to IEC 61701 has been asked by the purchaser, then this
test will not be required.
Note- Before and after the environmental testing the solar modules shall be
subjected to performance test on sun simulator and insulation
resistance test, and no degradation of maximum output power shall
not exceed 5% of the value measured before the test.
Page 27 of 29
5.0
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Acceptance Criteria:
The module is deemed to have passed the tests if the sample meets
the following criteria:
5.1
There is no evidence of a major visual defect such as a cracked or
broken window, bubbles or de-lamination in the encapsulant etc.
5.2
There is no cell breakage and no water infiltration into terminal
boxes.
5.3
No sample exhibits any open circuit or ground fault.
5.4
No visible evidence of major defects that may affect performance of
the module.
5.6
Insulation Resistance not less than 50M-ohm at 500 V DC.
5.7
Degradation of performance may not exceed 5% after each single test
or 8% after the whole sequence.
Page 28 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Annexure - C
Technical details to be furnished by the purchaser in his tender
1.
System Power Rating (KWp) and place of installation:
2.
Is Compliance and certification to salt mist corrosion testing as per IEC
61701 required {Refer Cl. 6.9.1} (Yes/No):
3.
Required galvanization thickness (Refer Cl. 6.10.3)
4.
Support structure, design and foundation wind withstanding capability
required (see Cl. 6.10.5)
5.
Is supply of Export Metering required {Refer Cl. 4.1, 5.4} (Yes/No):
6.
(a) Is ground mounted solar system required {Refer Cl. 5.2} (Yes/No):
(b) If the answer to 6(a) is ‘yes’, then please specify the ground mounted
system’s KWp capacity, site location and fencing requirements.
7.
(a) Will the overall rooftop KWp capacity be distributed across multiple
rooftops {Refer Cl. 5.3} (Yes/No):
(b) If the answer to 7(a) is ‘yes’, then please give necessary details i.e.
KWp distribution on multiple rooftops, inverters, site locations, etc.
8.
In what manner does the railway propose to continue to avail of web
based monitoring service after the completion of warranty period:
(a) As a part of AMC services {Cl. 12.0} (Yes/ No); OR
(b) Through a separate new agreement with the contractor for web based
monitoring {Cl. 6.7.2}(Yes/ No)
Note:
In the event that the overall KWp capacity (at Sr no. 1) is split between rooftop and
ground based installations, the total of KWp capacities in Sr. no. 6 & 7 shall not
exceed the overall KWp capacity as indicated at Sr. no. 1
Page 29 of 29
Effective from August 2013
Spec. no. RDSO/PE/SPEC/PS/0092-2008 (Rev.‘0’),Amdt.-5
Annexure-D
Technical data to be furnished by the tenderer in his offer
1. Total Power rating of Solar System
a) System power rating(KWp)
2. Solar Panel
a) Make and model no.
b) Power rating of the module
c) Name of the manufacturer of PV Module
d) Name of the Manufacturer of Solar cells
e) Country of origin (separately for solar cells and module- Refer
Clause 6.9.1)
f) Peak Wattage, Im and Vm for the module(Refer Clause 6.9.1)
g) Operating voltage of array(Refer Clause 6.12)
h) Efficiency of the module(Refer Clause 6.9.4)
i) Fill Factor of the module(Refer Clause 6.9.5)
j) Variation band of rated output of the module (Refer Clause 6.9.10)
k) Galvanization thickness of the module mounting structure (Refer
Clause 6.10.3)
3. Power Conditioning Unit (PCU)
a) Make and Model no
b) Power rating
c) Output voltage and frequency range(Refer Clause 6.12)
d) Voltage range of grid synchronization (from nominal)
e) Frequency range of grid synchronization (from nominal)
f) Communication interfaces offered
g) Data communication protocols
h) Input voltage range for MPPT operation(Refer Clause 6.12)
i) Efficiency(Refer Clause 6.12.4)
j) Voltage and Current THD(Refer Clause 6.12.2)
k) IP protection(Refer Clause 6.12.5)
l) Noise level(Refer Clause 6.12.18)
m) Idling current
n) Surge protection on DC and AC side
o) Name of URL at which the purchaser can view the system
performance data (Refer Cl. 6.7.2)
4. Compliance and certification to salt mist corrosion testing as per
IEC61701 {Refer Cl. 6.9.1} (only if the purchaser has asked for this
compliance):
5. Details of Export Meter offered {Refer Cl. 5.4} (only if the purchaser has
asked for this item):
6. Details of all cables to be supplied by the firm
7. Details of RCD (in case galvanic isolation doesn’t exist in PCU)
--------------
lR;eso t;rs
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
Hkkjr ljdkj
jsy ea=ky;
TECHNICAL SPECIFICATION FOR
INTEGRATED RENEWABLE ENERGY BASED
POWER SUPPLY ARRANGEMENT
,dhÑr uohdj.kh; ÅtkZ iz.kkyh vk/kkfjr fo|qr
vkiwfrZ O;oLFkk gsrq rduhdh fof’kf"VA
Specification No. RDSO/2009/EM/SPEC/0004 (Rev. ‘1’) - 2012
fof’kf"V la0 vkjMh,lvks@2009@bZ,e@Lisd@0004 ¼fjoh- ‘1’½&2012
S. N.
1.
2.
Amendment
No.
Date
1
19.10.2010
-
-
No.
-
‘1’
Revision
Date
-
12.10.2012
Reason
Clause No. 10.0 (Guarantee/Warranty deleted,
Clause Nos. 7.2.10 and 13.0 modified as per
Railway Board’s letter No.2006/Elect.(G)/150/
9/Pt. dated 10.09.2010
Rationalized the spec. and major editorial
changes to improve its readability and clarity
ISSUED BYENERGY MANAGEMENT DIRECTORATE
RESEARCH DESIGNS AND STANDARDS ORGANISATION
MANAK NAGAR, LUCKNOW- 226011
tkjhdrkZ&
ÅtkZ izcU/ku funs’kky;
vuqla/kku vfHkdYi ,oa ekud laxBu
ekud uxj] y[kuÅ&226011
Page 2 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
INDEX
S. No.
DESCRIPTION
PAGE No.
1.0
Foreword
3
2.0
Scope
3
3.0
Reference Standards
3
4.0
Description
4
5.0
General Requirements
4
6.0
Technical Requirements
5
7.0
Installation & Commissioning
23
8.0
Documentation
23
9.0
Design Approval
23
10.0
Prototype Approval
23
11.0
Tests
24
Annexure - 1
31
Annexure - 2
33
Annexure - 3
34
Page 3 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
INTEGRATED RENEWABLE ENERGY BASED POWER SUPPLY
ARRANGEMENT
1.0
FOREWORD:
The Wind and Sun are inexhaustible, reliable and non-polluting sources of
power. Keeping in view the rising concerns over climate change and depleting
reserves of petroleum and coal, it is important to integrate these renewable
energy systems into the existing electricity supply. For locations where the
availability and quality of grid electricity supply is poor, integration of solar or
wind-solar systems (with battery back-up) with the grid supply system can
help to ensure uninterrupted availability of electricity for electrical services at
railway stations, railway offices, etc. with minimal or nil dependence on DG
sets.
2.0
SCOPE:
This specification covers the general and technical requirements of integrated
renewable energy (solar/ wind-solar) based power supply for railway stations,
railway offices, etc. The system covered by this specification encompasses
Wind Turbine (WT), Solar Photovoltaic modules (SPV), Solar Charge
Controller (SCC), Wind Charge Controller (WCC), Grid-synchronizing Invertercum-Charger and Battery. At sites having annual average wind speed of 4.17
m/s or above (at 20m height), wind-solar hybrid systems can be considered.
But at sites which do not meet the aforesaid wind speed criterion, a SPV only
system should be specified by the purchaser (Refer Item 1.2 of Annexure-2).
3.0
REFERENCE STANDARDS:
IS: 12834:1989 (reaffirmed 2000)
IEC: 61215 (2005)
IEC: 61730 Pt 1 & 2
IEC: 60904-1(2006)
IEC: 61701
IEC: 60068
IS: 9000
IEC -61400-12-1
Solar Photovoltaic Energy Systems –
Terminology
Crystalline silicon terrestrial photovoltaic
(PV) modules – Design qualification and
type approval
Photovoltaic (PV) module safety
qualification - Part 1: Requirements for
construction
Part 2: Requirements for testing
Photovoltaic Devices - Part-I:
Measurement of Photovoltaic currentVoltage Characteristic
Salt mist corrosion testing of photovoltaic
(PV) modules
Environmental testing
Basic environmental testing procedure
for Electronic and electrical items.
Power performance measurement of
wind turbines.
Page 4 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
IEC -61400-2
Safety and function test and Duration test
of wind turbines.
ASTM – B-117
Salt spray testing standards for
protection of exposed parts of wind
turbine in harsh marine environment.
Note: Latest version of the standards shall be referred to.
4.0
DESCRIPTION:
The integrated renewable energy based power supply system shall consist of
the following elements:
i)
Wind Turbine (WT) to convert Wind energy to electricity.
ii)
Hot dip galvanized MS tower with necessary accessories for mounting
of WT.
iii)
SPV Module to convert solar radiation directly into electricity.
iv)
Module mounting structure of galvanized MS sections (For smaller
systems, SPV panels can be mounted on the WT tower, if feasible).
v)
Following charge controllers will be provided:
a) Solar charge controller.
b) Wind charge controller.
c) A Master Controller (or functionality thereof), for co-ordinating the
above charge controllers and the grid/DG set fed battery charger.
vi)
Battery bank to store the electric energy from renewable sources and
the grid.
vii)
A grid synchronizing type Inverter to convert the DC voltage from
renewable sources to AC voltage. This Inverter should be capable of
also functioning in reverse power flow mode for charging the battery
from grid power supply/DG set. The manufacturer is encouraged to
integrate the Inverter-cum-Charger, solar and/ or wind charge
controller, etc. into one cabinet.
viii) Interconnecting wires, cables and hardware.
5.0
GENERAL REQUIREMENTS:
5.1
The system shall reduce the electric energy units drawn by railway from the
grid and thereby reduce IR’s CO2 emissions.
5.2
All wiring, enclosures and fixtures that are mounted outdoor must be resistant
to high humidity conditions, corrosion, insect and dust intrusion.
5.3
Proper sealing arrangements at the points of cables entering the enclosures/
buildings should be incorporated. Although not mandatory, manufacturers are
Page 5 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
however encouraged that the cables entering into the enclosures be sealed
with modular EPDM based cable sealing and protection system based on
multi-diameter technology.
5.4
In general, bolt, nuts, shims and other hardware should be zinc plated.
Fasteners visible to the public shall generally be of stainless steel SS304. The
generally applicable engineering principle will be that fasteners shall be equal
to or of greater corrosion resistance than the most corrosion resistant metals
being fastened.
5.5
The main components shall be integrated in such a way as to allow
replacement (in case of failure) with a similarly functioning component of a
newer design or a different brand.
5.6
Electronic components used in the controller or elsewhere in the system shall
generally meet the requirements mentioned as follows (documentary evidence
in support of the same should be given):
i)
ii)
iii)
iv)
v)
DC Link capacitors shall be rated for max temp of 85° C and other
capacitors shall be rated for max. temp of 105° C.
Resistances shall preferably be made of metal film of adequate rating
having a tolerance of not more than 5%.
Switching devices such as transistors, IGBTs, MOSFETs, etc. shall
have minimum junction temp. of 150° C.
Devices shall have adequate thermal margin at ambient temp. of 55°C
Fiber glass epoxy of grade FR 4 or superior shall be used for PCB
boards having a nominal board thickness of 1.6mm and copper
cladding thickness of 70 microns for power cards and 35 microns for
control cards. Both track width and spacing between the tracks shall be
0.5 mm nominal and in no case shall be less than 0.3 mm. Assembled
PCBs shall be given a conformal coating for protection/resistance
against chemicals, fungus and humid weather.
5.7
The system shall comply IEC 60364-7-712 and 62446.
5.8
Appropriate external lighting protection system shall be provided as per
prevailing best practices in the field.
6.0
TECHNICAL REQUIREMENTS:
6.1
System design, ratio of wind-solar energy and system sizing
6.1.1 System design
The system will be designed to preferentially utilize renewable energy for
supplying the essential general electrical loads and charging the battery. But
when the battery gets discharged beyond a point, it will be possible to charge
Page 6 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
the battery from grid electricity supply or else, in the event of grid supply
outage, the system should be able to automatically start the DG set through
potential free contact and utilizing AMF panel of DG set. The system will
include a grid-synchronizing Inverter which will receive DC input from SCC/
WCC with Battery floated across the DC bus and deliver AC output for feeding
the essential general electrical loads at railway stations, offices, etc. When the
battery is in a fully charged state, the SCC and WCC will feed entirely to the
Inverter and feed excess available power to the grid, if any; else, the SCC and
WCC will charge the battery and any remnant excess power will be fed to the
Inverter to supply other electrical loads/grid. The Inverter will be capable of bidirectional power flow so that it can also function as a charger. The Inverter
should be capable of operating in parallel with the local grid power supply
during excess energy grid feed mode. Thereby, under heavy load conditions,
any balance power requirement over and above that available from the
Inverter, can be fed by grid power supply. Also, during the time period when
the station or office load is low, it should be possible to set up/ program the
system to export any surplus renewable energy.
6.1.2 Ratio of wind-solar energy and sizing of the system
In specifying the system, ratio of wind and solar energy should be decided in
a manner that is economically beneficial to railways; in this regard, the MNRE
norms for subsidy should also be taken into account. Sizing of SPV, WT,
SCC, WCC, Inverter-cum-Charger, Battery, etc. will depend on the system
load to be catered and the required autonomy. From economy considerations,
it is recommended that sizing of the system should take into account only the
most essential loads and two days (24-hrs) autonomy. In laying down the
aforesaid autonomy, it has been presumed that the railway station/ office is
equipped with grid electricity supply and a DG set. But if local conditions
require so, the purchaser can size the system for an autonomy higher than
24-hrs. The purchaser must mention his specific requirements as per
performa provided in Annexure-2 of this spec (Refer Item 5.2 in Annexure-2).
6.2
Wind Turbine (WT)
6.2.1 The WT must have undergone IEC 61400-12-1 type testing for power
performance measurement and IEC 61400-2 type testing for safety from an
accredited test house such as Govt of India’s Centre for Wind Energy
Technology (CWET), NREL, etc. Further, the offered WT should also have
regular empanelment from CWET (Refer Item 2.1 of Annexure-2).
6.2.2 All exposed/external parts of WT shall be suitably coated for prevention of
corrosion in harsh marine environment. Although it is being kept optional (at
the choice of purchaser) for now, manufacturers however are encouraged to
get the WT type tested for salt spray test as per ASTM B-117 for a minimum
period of 1,000 hours, if they have not already done so. In case of bulk
tenders, zonal railways can consider specifying that the contractor furnish this
type test certificate (Refer Item 2.2 of Annexure-2).
Page 7 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.2.3 The manufacturer will need to furnish evidence that the WT being supplied is
the same as the one type tested as per IEC 61400-12-1 and IEC 61400-2.
Although it is not being made mandatory for now, manufacturers however are
encouraged to create the necessary testing infrastructure for enabling the
purchaser to verify the IEC 61400-12-1 certified power (watts) vs. rotational
speed (RPM) in steps of 100 RPM, prior to dispatch.
6.2.4 Suitable protection such as furling mechanism, pitch control of blades or
electromagnetic braking shall be provided for protection of WT against high
velocity wind, storms and over-speeding.
6.2.5 The WT shall be able to withstand wind speeds of 55 m/sec or 198 kmph.
6.2.6 Mounting Towers shall be of 15 meter height and made of hot dip galvanized
mild steel. Galvanization thickness shall be of min. 85μm. If the systems are
installed in coastal/ corrosive areas, the minimum galvanization thickness
shall be 120μm. Unless the purchaser has specifically asked for 120 μm
thickness, normally 85 μm will be supplied. The turbine hub height shall be at
least 5 meter above any obstruction within 200 meter radius. If at certain
locations, tower height more than 15 m is required, then the same must be
especially mentioned in the tender schedule. The tower has to be designed to
withstand a minimum wind speed of 55 m/s or 198 kmph (Refer Items 1.3 &
2.3 of Annexure-2).
6.2.7 WT shall be grounded properly. Towards this end, the contractor will supply
and install an adequate number and size of IS: 3043-1987 compliant earthing
kits.
6.3
SPV Modules and related items
6.3.1 Solar panels and array junction boxes shall be installed on shade free roof
while the PCU and distribution boards, etc. shall be housed indoors in the
space to be provided by Railways.
6.3.2 The SPV panel shall have a provision for angular adjustment of the mounting
structure to get maximum utilization of incident sunlight. It shall be mounted
facing south and tilted to an angle equal to the latitude where being used, for
optimum performance.
6.3.3 Railway Authority shall provide a shadow free area @ 125 - 150 sq. ft./ KWp
of solar array.
6.3.4 Array structure of PV yard and all electrical equipments such as PCU,
inverters, etc. shall be grounded properly. Towards this end, the contractor will
supply and install an adequate number and appropriate size of IS: 3043-1987
compliant earthing kits; at least one each for AC circuit, DC circuit and
lightning arrestor (if any).
Page 8 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.3.5 Individual Solar PV Module should be of following minimum capacity: 230Wp
for systems of 5KWp or above; 180Wp for systems of 3KWp to less than
5KWp; and 125Wp for systems below 3KWp. The modules used shall be
conforming to IEC:61215 Ed 2 or latest – Edition II, IEC:61730 – I :2007, IEC:
61730 – II : 2007, manufactured in a plant certified under ISO 9001 : 2008 and
type tested by an accredited national/international testing laboratory. The
Solar PV Module should be made from single/poly crystalline Silicon Solar
Cell connected in series. Imported SPV module or cell will not be accepted,
unless MNRE’s policy/ rules permit the same. PV modules to be used in a
highly corrosive atmosphere (coastal areas, etc.) must qualify Salt Mist
Corrosion Testing as per IEC 61701; this compliance and certification will not
be required, unless the purchaser specifically asks for the same. Cut cells
should not be used for modules of 230Wp or above (Refer Item 3.2 of
Annexure-2).
6.3.6 SPV modules of similar output with ± 2% tolerance in single string shall be
employed to avoid array mismatch losses.
6.3.7 SPV module shall contain crystalline high power silicon solar cells. The solar
cell shall have surface anti-reflective coating to help to absorb more light in all
weather conditions.
6.3.8 Photo-electric conversion efficiency of SPV module shall not be less than 14%
for modules rated equal to or above 180Wp and 13% for modules of 125 Wp
to less than 180Wp.
6.3.9 Fill factor of the module shall not be less than 72%.
6.3.10 Each module shall have low iron tempered glass front for strength and
superior light transmission. It shall also have tough multi-layered polymer back
sheet for environmental protection against moisture and provide high voltage
electrical insulation. Transmitivity of glass shall not be less than 91%.
6.3.11 Module junction box and terminal block (weather resistant with min. IP 65)
shall be designed for long life outdoor operation in harsh environment.
6.3.12 Bird spike shall be provided so as to avoid bird sitting on the solar modules at
the highest point of the array/module structure.
6.3.13 SPV module shall be highly reliable, light weight and shall have a service life
of more than 25 years. SPV modules shall have a limited power loss of not
more than 10% of nominal output at the end of 10 years and of not more than
20% of nominal output at the end of 25 years.
6.3.14 The rated output of any supplied modules shall not vary by more than 3%
from the rated power rating of the module. Each module, therefore, has to be
tested and rating displayed.
Page 9 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.3.15 Whenever more than one module is required, identical modules shall be used.
6.3.16 The solar modules shall have suitable encapsulation and sealing
arrangements to protect the silicon cells from the environment. The
encapsulation arrangement shall ensure complete moisture proofing for the
entire life of solar modules. The terminal block shall preferably be of Noryl
rubber and shall have a provision for opening /replacing the cables if required.
6.3.17 Marking
Each module shall carry the following clear and indelible markings:i)
ii)
iii)
iv)
vi)
vii)
viii)
ix)
x)
xi)
xii)
Name, monogram or symbol of manufacturer
Type or model number
Serial number
Polarity of terminals or leads (colour coding is permissible)
Open – circuit voltage
Operating voltage
Maximum system voltage for which the module is suitable
Operating current
Short circuit current
Date and place of manufacture
Weight of the module
6.3.18 Each PV module must use a RF identification tag (RFID), which must contain
the following information. The RFID can be inside or outside the module
laminate, but must be able to withstand harsh environmental conditions.
i)
ii)
iii)
Name of the manufacturer of PV Module
Name of the Manufacturer of Solar cells
Month and year of the manufacture (separately for solar cells and
module)
iv) Country of origin (separately for solar cells and module)
v)
I-V curve for the module
vi) Peak Wattage, Im, Vm and FF for the module
vii) Unique Serial No. and Model No of the module
viii) Date and year of obtaining IEC PV module qualification certificate
ix) Name of the test lab issuing IEC certificate
x)
Other relevant information on traceability of solar cells and
module as per ISO 9000 series.
6.3.19 Module Mounting Structure
i)
ii)
The array structure shall be so designed that it will occupy minimum
space without sacrificing the output from SPV panels.
The structure shall be designed to allow easy replacement of any
module and shall be in line with the site requirements.
Page 10 of 35
iii)
iv)
v)
vi)
vii)
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
The array structure shall be made of hot dipped galvanized MS angles
of suitable size. Galvanization thickness shall be of min. 85μm. If the
systems are installed in coastal/ corrosive areas, the minimum
galvanization thickness of array structure shall be 120μm. Unless the
purchaser has specifically asked for 120 μm thickness, normally 85 μm
will be supplied (Refer Item 1.3 of Annexure-2).
The foundation for module mounting structure shall be preferably 1:2:4
RCC construction or any other combination based on the local site
condition requirement for which design details shall be submitted.
The support structure, design and foundation shall normally be
designed to withstand wind speed upto 150 kmph. In coastal/ high wind
areas, the support structure, design and foundation shall be designed
to withstand wind speed upto 200 kmph. If the purchaser does not
specify anything to the contrary, then 150 kmph wind withstanding
capability shall be provided (Refer Item 3.3 of Annexure-2).
The clearance between the lowest part of the module structure and the
developed ground level shall normally not be less than 500mm.
However, in exceptional cases, lower clearances may be allowed on
case to case basis.
The module alignment and tilt angle shall be calculated to provide the
maximum annual energy output. This shall be decided based on the
location of array installation.
6.3.20 Junction Boxes
i)
The module junction boxes (if any) shall be certified as per IEC 61215.
Else, they should have the same properties as mentioned for array
junction boxes. Array sub-main and main junction boxes shall have the
following properties:
a. They shall be dust, vermin and waterproof and made of
Polycarbonate - Glass Fibre Substance (PC-GFS) thermoplastic.
The enclosure should be double insulated with protection class II as
per IEC 61439-1. Material and the protection class shall be marked
on the enclosure.
b. The enclosure shall have a transparent front lid for enabling easy
visibility.
c. The enclosures shall have IP 65/66 protection in accordance with
IEC 60529. Third party conformance certificate is required to be
given for IP 65/ IP 66 degree of protection.
d. Minimum requirements for fire protection in the event of internal
faults: Glow wire test in accordance with IEC 60 695-2-11 at 960C
for box and 850C for conducting components
e. Burning Behavior: Base part of Polycarbonate Enclosure shall be
UL94-V-0 compliant and Lid part of PC Enclosure shall be UL94-V2 compliant.
Page 11 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
f. The enclosures shall have IK 08 degree of protection for
mechanical load.
g. The material used shall be halogen, silicon free conforming to
RoHS directive 2002/95/EC.
h. The enclosure shall have a usage temperature rating of -10C to
55C.
i. The enclosure should be chemically resistant to acid, lye, petrol,
mineral oil & partially resistant to benzene.
j. The enclosures shall have a rated insulated voltage of 1000V DC
and dielectric strength of 4.65 KV DC.
k. The material of the enclosure shall be UV stabilized.
Unless specifically asked for, the properties mentioned above should be
demonstrated through datasheet of the manufacturer.
ii)
iii)
iv)
v)
Class II SPDs as per IEC 61643-1, shall be used at the terminals of
array junction boxes for external surge protection. Internal Surge
protection (SPDs) shall consist of three MOV type arrestors connected
from + ve and – ve terminal to earth (Via Y arrangement) for higher
withstanding capacity with respect to the continuous PV-DC voltage
during earth fault condition. SPD shall have safe disconnection and
short circuit interruption arrangement through integrated DC in-built
bypass fuse (parallel) which should get tripped during failure mode of
MOV, extinguishing DC arc safely (created by inbuilt thermal
disconnection) in order to protect the installation against fire hazards.
Nominal discharge current (In) at 8/ 20 microseconds shall be minimum
10 KA with maximum discharge current (Imax) of minimum 20 KA at 8/
20 microseconds with visual indication (through mechanical flag) in all
modules to monitor the life of SPD. The Iscwpv (Short Circuit current
withstand capacity of arrester) would be at least 10% more than
nominal output current of the combiner box and AJB. Detailed internal
schematic for the above SPDs, compliant to these specifications,
should be submitted by the manufacturers.
The junction boxes shall have suitable cable entry points fitted with
cable glands of appropriate sizes for both incoming and outgoing
cables. Though not mandatory, manufacturers are encouraged to
provide suitable cable entry points fitted with MC-4 Connectors.
Suitable markings should be provided on the bus bar for easy
identification and cable ferrules shall be fitted at the cable termination
points for identification.
The Array Junction Box should preferably have maximum 08 input and
01 output with SPD and Terminal block.
Page 12 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.3.21 Maintenance System:
Railway shall equip the Array Yard with permanent Water Line along with
Butterfly valve and rubber hose so that cleaning can be done by vendor
during warranty period and later on by railway staff or agency.
6.3.22 Module and associated items shall be tested as per clauses 11.1, 11.2 and
11.3 of the specification.
6.3.23 The array voltage shall be so chosen that it lies well within the MPPT voltage
range of the PCU over the entire lifetime of the modules.
6.4
Charge Controllers
6.4.1 Solar charge controller
The Solar Charge Controller (SCC) will comply the following requirements:
i)
ii)
SUITABLE for charging LMLA as well as VRLA battery.
Suitable for receiving input from PV system and delivering DC power
at appropriate voltage for battery charging and for supplying to the
Inverter.
iii) Compliant to IEC 62509 with the exception of self consumption and set
point accuracy (±3% will be allowed).
iv) IP 31 protection. Manufacturers are however encouraged to provide
higher IP protection.
v)
Capable of handling 120% of module’s rated current.
vi) MPPT technology. Manufacturers are encouraged to provide algorithm
efficiency of 98% or higher.
vii) Efficiency at rated output voltage and full load should not be less than
93% up to less than 30KWp and not less than 95% from 30KWp
upwards. Even at less than full load, efficiency should not drop to less
than 90% (for up to less than 30KWp) and not less than 92% (from
30KWp upwards) at 30% full load.
viii) Temperature compensated charging.
ix) Provision of blocking diode, preferably a Schottky diode, to prevent the
battery from discharging itself through the SPV system/ charge
controller. The current capacity of the blocking diode shall be 50%
higher than the short circuit current at STC. The peak inverse voltage
(PIV) of the diode shall be at least equal to the open circuit battery
voltage. In case any alternative to Schottky diode is proposed, then
technical literature and evidence in support of successful working of the
same should be submitted for the consideration of RDSO/ purchaser.
x)
On the SPV power source side, the charge controller shall be protected
against lightning and surges with the help of SPDs if the distance
between charge controller and AJB is more than 10 m. The SPDs used
Page 13 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
shall be rated for at least 10KA at 8/20 μSec for protection against
lightning induced surges Class II as per IEC 61643-1. The voltage
rating of the SPDs shall be at least 10V higher than the specified value
of the SPV array.
xi) Protection shall also be provided against the following: battery
overload, battery overcharge, short circuit and reverse polarity. Auto
resettable reverse polarity protection should be provided.
xii) Cables of appropriate size shall be used to reduce the voltage drop
between SPV and battery; and battery and the output of the charge
controller.
xiii) The charge controller shall incorporate the auto, bulk and float charging
methods. Though not mandatory, manufacturers are however
encouraged to provide equalization charging facility also. Battery
charging modes shall be selectable as per battery type.
xiv) The charge controller shall withstand a test voltage of 2,000V applied
between DC line terminals and earth for one minute without any
puncture and arcing.
xv) The charge controller should withstand the environmental tests (as per
IEC 60068/ IS 9000) listed below with the charge controller working at
full load for at least last half an hour. For SPV systems of 10 KWp or
higher capacity, environmental test results in respect of any similar
design charge controller for at least 10 KWp SPV systems will be
adequate. In respect of SPV systems of less than 10 KWp, test results
for charge controller of identical capacity or any higher capacity will be
adequate.
a) Dry Heat Test: 50C±2C for 16 hours
b) Damp Heat Test (Steady state): 40C, 95% RH for 4 days
c) Damp Heat Test (Cyclic): 40C, 93% RH for 6 cycles (duration of
one cycle shall be 24hrs)
d) Cold Test: 0C for 16 hours
e) Change of temperature Test: -10C to 50C for 3 cycles (rate of
change in temperature shall be 3oC per minute)
6.4.2 Wind charge controller
The Wind Charge Controller (WCC) will comply the following requirements:
i)
ii)
iii)
iv)
Suitable for charging LMLA as well as VRLA battery.
Suitable for accepting multi-phase AC input from wind turbine and
delivering DC power supply at appropriate voltage for battery charging
and for supplying to the Inverter.
To be at least PWM based; manufacturers are however encouraged to
offer MPPT technology.
No minimum limit for efficiency is being mandated for now; but
manufacturers are encouraged to provide the highest technically
feasible efficiency.
Page 14 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
v)
vi)
Temperature compensated charging.
Provision of blocking diode, preferably a Schottky diode, to prevent
battery from discharging itself through the WT/ charge controller. In
case any alternative to Schottky diode is proposed, then technical
literature and evidence in support of successful working of the same
should be submitted for the consideration of RDSO/ purchaser.
vii) To save the WT from over-speeding (in event of generated energy not
being consumed) and consequential damage, a resistive dump load of
adequate rating will be provided. The dump load’s rating shall be
commensurate with that of the WT. Its material shall be Stainless Steel
(SS 304) or any other material with proven design and with cooling fins,
suitable for convection cooling and SS/ Brass mounting hardware. If
any alternative to dump load is offered by the tenderer, then he should
furnish literature endorsing such a design and/or evidence of
successful working of the same for at least two years.
viii) Protection against the following shall be provided: battery overload,
battery overcharge, short circuit and reverse polarity. Resettable
reverse polarity protection shall be provided. Although not mandatory,
manufacturers are encouraged to provide auto resettable reverse
polarity protection.
ix) Rating of offered WCC shall be appropriate for the WT’s power rating.
x)
On the WT power source side, the charge controller shall be protected
against lightning and surges. The SPDs used shall be rated for at least
10KA at 8/20 μSec. The voltage rating of the SPDs shall be at least
10V higher than the specified value of the WT.
6.4.3 Master controller
It will be necessary that the aforesaid charge controllers as also the grid/DG
fed charger maintain the battery to the highest possible State of Charge
(SOC) while protecting the battery from deep discharge or extended
overcharge. Such a technical arrangement is being termed here as ‘Master
Controller’. In as far as possible, renewable energy will be utilized for battery
charging. But if the battery’s state of charge drops below a point, then the
master controller will enable the battery to be charged through the grid power
supply or through a DG set, if grid power supply is not available. It should be
possible for the purchaser to set the battery voltage at which the grid/ DG set
fed Charger will be cut in.
6.4.4 Indications and meters
Relevant meters/display should be provided for voltage, current and indication
for Low Battery, Battery on charge and Battery fully charged. Detailed scheme
shall be submitted at design/ drawing approval stage.
Page 15 of 35
6.5
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Power Conditioning Unit (PCU)
6.5.1 Constituents of PCU
The term ‘Power Conditioning Unit (PCU)’ generally refers to the MPPT
controller, Inverter and associated items. The PCU should preferably integrate
within itself, all of the following systems:
i)
ii)
iii)
iv)
v)
vi)
vii)
Inverter, capable of bi-directional power flow
MPPT based solar charge controller
Wind charge controller (if it is a wind-solar hybrid system)
Master controller
Isolation transformer at output (alternate scheme, if any, will need to be
examined/approved at design scrutiny stage)
Essential protection devices
Suitable breaker/isolator at Array, Battery and PCU output.
Hereafter, the term PCU will be used to collectively refer to all the above subsystems.
6.5.2 Minimal functionality of PCU
Following will be the minimal functional requirements for PCU:
i)
PCU should be a solar and wind priority based system, so as to ensure
maximum utilization of available renewable energy. It should be
possible to set priority between array/grid/battery. The priority setting
should be menu driven from the front panel.
ii)
PCU Inverter shall be of grid synchronizing type and operate in parallel
with the grid electricity supply.
iii) It should be possible to charge the batteries through the solar charge
controller, wind charge controller and grid/ DG fed charger.
iv) In the event that battery is in a low state of charge and if grid supply is
not available, the PCU must have the facility to provide a potential free
contact (PFC) signal to enable starting and stopping of the DG set
through railway’s external AMF panel. It must have the ability to
synchronize with the DG set and optimally use the DG set power to
charge battery bank as well as feed the load simultaneously.
v) Whenever the grid voltage and frequency are beyond the operating
range, the Inverter will be disconnected from the grid. PCU will supply
continuous power to load without any interruption.
vi) The MPPT voltage range of the PCU shall be well within the array
voltage of the solar modules over their entire lifetime.
vii) Where PCU hasn’t been provided with galvanic isolation, a type B
residual current device (RCD) according to IEC 60755 amendment 2
shall be installed to provide fault protection by automatic disconnection
of supply.
Page 16 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.5.3 System operation modes for inverter
i)
Standalone Mode: When grid supply is absent, the Inverter works in a
stand-alone configuration. The solar and wind charge controllers will
charge the battery and simultaneously feed the load through the
inverter. If neither grid nor renewable energy supply is available at a
point of time, then battery will support the load.
ii)
Grid Charging Mode: Battery charging through Grid shall be activated
via the bidirectional inverter when the battery’s state of charge is low.
Battery charging current from Solar and Grid shall be settable. Max
power from Grid shall be max.125% of PCU capacity.
iii)
Grid Export Mode: It should be possible to feed AC power to Grid if
there is excess SPV and/or WT generation and battery is fully charged.
Anti Islanding protection should be in-built.
iv)
Auto Mode: Depending on the actual situation occurring in field, the
system will intelligently select any one of the aforementioned operating
modes.
v)
Sleep mode: Although not a mandatory requirement, firms are
however encouraged to provide enable/disable feature so that in event
of no load being connected or no export power being available, the
system will go into sleep mode.
6.5.4 Other technical features of the PCU
Following will be the other technical features of PCU:
S. N.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Parameters
Inverter Type
Nominal Inverter rating
Nominal battery DC input
voltage
Description
Frequency PWM IGBT based
Dependent on the load connected
Dependent on system power rating (for
10KWp and above, it should be 96 V
DC or higher)
230V 1-ph or 415V 3-ph AC
50Hz ± 0.5Hz in standalone mode.
± 2%
Pure Sine wave
230VAC ±15%/ 415V AC ±15%
Output voltage
Frequency
Voltage regulation
Waveform
Operation AC voltage
range
Frequency synchronizing
50Hz ± 5%
Range
THD & PF
i) Output Voltage THD <5% (manufacturers are however encouraged to
provide 3%).
Page 17 of 35
S. N.
Effective from October 2012
Parameters
11.
Load Power factor
12.
13.
14.
15.
Overload
Crest factor
Audible Noise
Inverter efficiency
16.
Protection
17.
Ingress protection
18.
19.
Back up DG Interface
Display / Indications
20.
Indications & Alarms
21.
Connectivity
22.
Data Logging
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Description
ii) Current THD during battery charging
through grid current distortion shall be
<10%.
iii) During import and export, power factor
shall be >0.97
0.65 to unity, output will remain within
the rated KVA capacity.
150% for 60 sec
3:1
Less than 65 dB at 1 Meter
Min. 90% upto 5KVA and 92% for >5KVA
at full load. Manufacturers are however
encouraged to offer higher efficiencies.
i) Output Overload, Short circuit, Output
under voltage, DC under and Over
voltage
ii) Protection against surge voltage
induced at output due to external
source if the same is not provided on
ACDB. Scheme should be the same
as described in ACDB.
iii) Anti-islanding
iv) Over-temperature
IP21 for transformer portion (if any) and
IP31 for PCBs and Electronics portion.
Manufacturers are encouraged to
provide better IP protections
Through PFC (Potential free contact)
LCD /LED type displays indicating the
important parameters of:
i) Array
ii) Battery
iii) Grid
iv) Output
For all faults, visible and audible alarm
should be given.
RS 232 port for local monitoring;
Provision of LAN/ WAN interface for
monitoring.
i) Adjustable logging repetition from 1
sec to 7 minutes.
ii) Storage capacity of up to 100 days
with 5 mins logs.
iii) Time and date stamped log entries
iv) Time and date marked fault log with
fault description and details.
Page 18 of 35
S. N.
23.
24.
Effective from October 2012
Parameters
Parameters to be logged
EMI/EMC
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Description
i) Inverter input & output KWh, Battery
input & output KWh, Solar KWh, Grid,
Wind KWh & DG Set KWh, etc.
ii) System parameters of Grid, Inverter,
Battery, Solar, Wind charge current,
etc.
iii) Solar insolation and temperature of
Array Yard; Wind Speed (if WT is
provided).
Compliance to IEC 62040-2. Though not
mandatory,
manufacturers
are
encouraged to comply IEC 61000-6-2
and IEC 61000-6-4.
Note:
1.
Provision of LAN/ WAN interface and web monitoring is mandatory for
total system peak power of 10KW and above.
2.
Measurement/ logging of Solar insolation and Yard temperature is
mandatory for SPV rating of 10KWp and above.
3.
Wind Speed measurement is mandatory for WT power rating of 5KW
and above.
4.
Manufacturers are however encouraged to provide the features
mentioned in note no. 1, 2 and 3 even for systems of lower capacities.
6.5.5 Export Metering
If required, statutory approval of local authorities/ state electricity distribution
company, etc. shall be obtained by the Railway Authority. An export meter (for
recording the number of units exported to the grid), if required, shall be either
installed by state electricity distribution company or else the respective
Railway Authority may include the same in their scope of work. It is
emphasized here, that the primary purpose of installing SPV system covered
by this spec., is to meet railway’s own energy requirement, rather than
supplying renewable energy to the public grid. Export metering will be an
optional item; it will be specifically mentioned by purchaser, if required (Refer
Item 1.4 of Annexure-2).
6.5.6 Distribution Boards
Distribution Board arrangement, as appropriate to the system rating, should
be provided. In this regard, the following general guidelines will be applicable:
i)
DC distribution board/ combiner shall be provided in between solar
array and PCU. It shall have DC Disconnector/ MCCB of suitable rating
for connection and disconnection of array section. It shall have meters,
preferably of digital type for measuring the array voltage and array
current.
Page 19 of 35
ii)
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
AC distribution board shall be provided in between PCU and loads. It
shall have an integrated energy meter, voltmeter and ammeter, which
is preferably of digital type. ACDB should have Class I + II (as per IEC
62305; IEC 61643 and IEC 60364-5-53), 100 kA Surge Suppression
inbuilt for surge protection. Surge protection on AC side (Type 1 + Type
2), consisting of base part and plug in protection modules, shall be
provided for fire safe and fire proof operation at site. Total discharge
capacity/ Lightning Impulse current (Iimp) at 10/350 μ sec and nominal
discharge current (In) at 8/ 20 μ sec shall be minimum 100 KA for three
phase power supply system and 50 KA for single phase power supply
system. The discharge capability of L-N connected module shall be 25
KA at 10/350 μ sec and 8/20 μ sec. All the L-N & N-E connected
arresters shall have built in mechanical health indication. The aforesaid
arrangement shall offer voltage protection level (Up) of <= 1.5 KV to
protect the sensitive electronics inside the Inverters, having follow
current extinguishing and limiting capability up to 25 KA rms (at 255V)
without tripping of even small rating 32 AGL/ gG fuse and approved
from international independent test labs like KEMA or VDE or UL as per
latest IEC 61643-1: 2005 or equivalent EN 61643-11: 2002 + A 11:
2007 standards. SPDs on the ACDB shall only be provided if the same
haven’t been provided on the PCU.
6.5.7 Web based system monitoring
RDSO and the concerned railway shall be afforded free of cost facility for
viewing the system performance data on the manufacturer’s or system
integrator’s or RDSO’s web portal for the contractual warranty period of the
system. Arrangements thereafter shall be as may be agreed between railway
and the firm.
6.5.8 Environmental Testing of Inverter
The inverter should withstand the environmental tests (as per IEC 60068/ IS
9000) listed below with the inverter working at full load for at least last half an
hour. For inverters of 5 KVA or higher rating, environmental test results in
respect of any similar design inverter for at least 5 KVA rating will be
adequate. In respect of inverter rating less than 5 KVA, environmental test
results for inverter of identical capacity or any higher capacity will be
adequate.
a)
Dry Heat Test: 50C±2C for 16 hours
b)
Damp Heat Test (Steady state): 40C, 95% RH for 4 days
c)
Damp Heat Test (Cyclic): 40C, 93% RH for 6 cycles (duration
of one cycle shall be 24hrs)
d)
Cold Test: 0C for 16 hours
e)
Change of temperature Test: -10C to 50C for 3 cycles (rate of
change in temperature shall be 3oC per minute)
Page 20 of 35
6.6
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Battery Bank:
i)
Unless otherwise specified by the purchaser, the contractor shall
supply tubular LMLA battery suitable for solar applications. The
purchaser can at his option specify low maintenance lead acid
OPzS/TBS or any other type of battery, depending on the specific site
requirements (Refer Item 5.1 of Annexure-2).
ii)
If LMLA battery is used then it should be tubular lead acid battery as
per IS 13369/IS 1651. The permissible self-discharge rate shall not be
more than 3% at 27°C/30°C. Battery shall have cycle life of 5000 cycles
at 20% depth of discharge (DOD) and 1500 cycles at 80% DOD. The
battery shall have a minimum designed life expectancy of 8 years. If
called for, the manufacturer shall be able to justify the designed life
through accelerated life test as per IEEE 535 or other relevant national
or international standard. The Ah efficiency as measured in accordance
with the relevant IS shall not be less than 90%. The Wh efficiency as
measured in accordance with the relevant IS shall not be less than
80%. The batteries shall have topping up frequency of not less than 6
months. Battery shall be provided with micro-porous vent plugs and
acid level indicator.
iii)
If low maintenance lead acid OPzS/TBS (tubular stationary cells in
transparent Strene SAN container) type of battery shall be used, it shall
conform to DIN 40736/40737. The battery shall have a minimum
designed life expectancy of 15 years. If called for, the manufacturer
shall be able to justify the designed life through accelerated life test as
per IEEE 535 or other relevant national or international standard. The
Ah efficiency as measured in accordance with the relevant IS shall not
be less than 90%. The Wh efficiency as measured in accordance with
the relevant IS shall not be less than 80%. The batteries shall have
topping up frequency of not less than 12 months.
iv)
The capacity of the batteries shall be so chosen that they can be
discharged up to 80% DOD. The capacity of the batteries will also be
dependent on the autonomy required, load and its profile (Refer Item
5.2 in Annexure-2).
v)
The charging instructions shall be provided along with the batteries.
vi)
Make of the battery shall be finalized at the system design stage.
vii)
Battery Testing:
a.
b.
All routine tests as per applicable standards shall be conducted on
the batteries.
Following Battery performance characteristic curves shall be
submitted:
Page 21 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
i) Discharge characteristics at different rates of discharge
ii) Self discharge at various ambient temperatures.
iii) Capacity vs Rate of discharge.
iv) State of charge vs. Sp. Gravity of electrolyte.
v) Depth of discharge vs number of cycles
vi) Test data of accelerated life test as per IEEE 535 or other
relevant national or international standard for a representative
cell.
Test reports from a govt. accredited laboratory shall be accepted. In case of
OPzS batteries, internal test reports of the manufacturer shall also be
acceptable. Manufacturers are however encouraged to get the OPzS battery
test reports from accredited labs; in the future, test report from accredited
laboratory is likely to be made a mandatory requirement.
6.7
Cables and Hardware
6.7.1 Cabling of the system shall be as short as possible to minimize the voltage
drop in the wiring.
6.7.2 The cables used in module/ array wiring shall be TUV 2Pfg 1169/08.2007 or
VDE EPV 01:2008-02 or UL4703 certified.
6.7.3 Cables of appropriate size to be used in the rest of the system shall have the
following characteristics:
Temp. Range –10ºC to +120ºC.
Voltage rating 600/1000V
Excellent resistance to heat, cold, water, oil, abrasion, UV radiation,
ozone and weathering
iv) Low smoke, low toxicity.
v)
Flame retardant
vi) Flexible
vii) Fulfills
IEC
60332-1
requirements.
Accredited
lab
test
report/Manufacturers test report shall be attached.
viii) Conductor class IEC 60228 class 5. Accredited lab test
report/Manufacturers test report shall be attached.
i)
ii)
iii)
6.7.4 All wiring must be sized to keep line voltage losses to less than 3% in each
sub circuit and to allow the circuit to operate within the ampere rating of the
wire.
6.7.5 Components and hardware shall be vandal and theft resistant. All parts shall
be corrosion-resistant.
Page 22 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.7.6 Voltage drop on the DC side from array to the inverter should not be more
than 3%. Necessary calculations in this regard shall also be submitted during
design approval.
6.7.7 Overload protection may be omitted for PV string and PV array cables when
the continuous current-carrying capacity of the cable is equal to or greater
than 1.25 times ISC STC at any location. Necessary calculations in this regard
shall be submitted during design approval.
6.7.8 Overload protection may be omitted for PV main cable if the continuous
current-carrying capacity of the cable is equal to or greater than 1.25 times I SC
STC of the PV generator. Necessary calculations in this regard shall be
submitted during design approval.
6.8
Protections
6.8.1 Adequate protection shall be incorporated under no-load conditions (i.e. when
the system is ON and there is no load) from master controller output side.
6.8.2 If any other protection is necessary, the same will be deemed to be a part of
the specification.
6.9
Marking
Each system shall carry the following clear and indelible markings on the
controller:
-
Name, monogram or symbol of system integrator;
Type or model number;
Serial number;
Polarity of terminals or leads (colour coding is permissible);
Output voltage.
Max. Power output
Date of supply
SPV details, as specified in Cl. 6.3.17
- WT details
Serial no.
Operating voltage
Wattage at rated wind speed.
Rated wind speed
Date of manufacture
At which lab type testing was done
Date of CWET regular empanelment
-Battery details
Battery Technology details
Battery Voltage
Total AH
No./AH of batteries
Page 23 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
6.10
The system description, general/technical requirements, etc. are given for
general guidance only. The supplier/manufacturer shall submit the detailed
design of the complete solar generating system, WT, etc. by using their
software to optimize the combination of modules considering the specific
location, insolation, nature of load, etc.
7.0
INSTALLATION & COMMISSIONING:
The installation shall be done by the supplier/manufacturer who is responsible
for the system’s performance, direction of installation and structural stability.
The supplier shall conduct a detailed site assessment. The installer shall
obtain data specific to the site, rather than relying on general data. The wiring
diagram and operation and maintenance information details shall be given as
detailed in IEC 62446.
8.0
DOCUMENTATION:
The supplier shall provide easy-to-use illustrated installation and operation
manual in English and local language for easy installation and trouble-free
usage. Manual shall contain complete system details such as array layout,
schematic of the system, working principle, clear instructions on regular
maintenance, trouble shooting of the system and emergency shutdown
procedures.
9.0
DESIGN APPROVAL:
Design for complete system and sub-system shall be approved by RDSO at
design stage before manufacture of prototype conforming to this specification.
The criteria for selection of sub-system / component shall be based on sound
engineering practice conforming to the International / Indian Standards,
wherever specific standard is not specified in this specification. The wiring
diagram and operation and maintenance information details shall be given as
detailed in IEC 62446.The detailed calculation/simulated results shall be
submitted in support of system/sub-system rating. Adequate safety margin as
stipulated in respective specification shall be used.
10.0
PROTOTYPE APPROVAL:
10.1
The prototype system shall be offered to RDSO for type testing and approval.
10.2
For certain tests, the type testing authority i.e. RDSO may choose to rely upon
previous type test reports/conformance certificates, as long as they pertain to
similar design and comparable rating. However, the manufacturer cannot
demand this as a matter of right.
10.3
Until the railways are able to issue their vendor list, they may in the interim
period invite tender/ place order with the provision of accepting the material on
Page 24 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
the basis of firm’s written clause-by-clause confirmation of the spec. and
acceptance test alone, wherever this is considered necessary by CEE.
11.0
TESTS:
The manufacturer shall carry out routine tests at his works and shall maintain
records for the same. Acceptance testing shall be carried out by the
purchaser or his representative or by any agency deputed by the purchaser
on his behalf.
11.1
Test on SPV Module
S.N.
Name of Test
1.
Visual Examination
Type
Test
√
Routine
Test
√
Acceptance
Method
Test
√
Refer Annexure 1
2.
Design Qualification
√
√
√*
IEC 61215 & Cl.
6.3.5
3.
Safety Test
√
√
√*
IEC 61730 & Cl.
6.3.5
4.
Photo Electrical
Conversion
Efficiency
√
√
√
By Sun simulator
on each module &
Cl. 6.3.8
5.
Fill Factor
√
√
√
By Sun simulator
on each module&
Cl. 6.3.9
6.
Transmitivity of
Glass
√
7.
Rated output of
module
√
8.
Module mismatch test
9.
As per Cl. 6.3.10
√
√
By Sun simulator
on each module.
Also refer Cl. 6.3.5
√
√
Refer Cl 6.3.14
Terminal block
√
√
Refer Cl. 6.3.11
and Cl. 6.3.16
10.
Provision of Bird
Spike
√
√
Refer Cl 6.3.12
11.
Provision of RFID
tag with requisite
details
√
√
Refer Cl 6.3.18
12.
Environmental tests
√
13.
Marking
√
14.
Provision of Earthing
√
√
√**
√
Refer Annexure 1
√
Refer Cl. 6.3.17
√
Refer Cl. 6.3.4
Page 25 of 35
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Effective from October 2012
S.N.
Name of Test
Type
Test
√
Routine
Test
15.
Warranty Certificate
for the modules
16.
17.
Acceptance
Method
Test
√
Refer Cl. 6.3.13
Voltage range to be
within MPPT range
of the PCU
√
√
√
Refer Cl. 6.3.23
Cable used in
module/ array
√
√
√
Refer Cl. 6.7.2
* Copy of the latest conformance certificates should be asked.
** If compliance has already been checked during type testing, the same will be
relied upon, otherwise compliance will be ensured through physical tests.
11.2
Test on Module Mounting Structure/ WT Tower
S. N.
Name of Test
Type Routine
Test
Test
√
√
√
1.
2.
Visual Examination
Dimension
3.
5.
Design calculation on
Tower wind withstand
capability
Clearance between
module and ground
Galvanization thickness
6.
Foundation
7.
Provision for angular
adjustment of the
mounting structure
4.
11.3
√
Acceptance
Method
Test
√
√
As per
manufacturer’s
data sheet
√
Refer Cl. 6.2.6 &
6.3.19(v)
√
√
√
√
√
√
Refer
Cl6.3.19(vi)
Refer Cl. 6.2.6 &
6.3.19(iii)
Refer
Cl.6.3.19(iv)
Refer Cl. 6.3.2
Test on module junction box, Array sub-main and main Junction Box
S. N.
Name of Test
Type
Test
√
Routine
Test
√
Acceptance
Test
√
Method
1.
Visual Examination
Refer Cl.6.3.20
2.
Material
√
√
Refer Cl. 6.3.20(i)
3.
IP Protection
√
√
Refer Cl. 6.3.20(i)c
4.
Surge Protection
√
√
Refer Cl. 6.3.20(ii)
5.
Cable entry and
markings
√
Refer Cl. 6.3.20(iii)
& (iv)
Page 26 of 35
11.4
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Test on Wind Turbine
S.N.
€
Effective from October 2012
Name of Test
Type
Test
√
Routine
Test
√
Acceptance
Test
√
Method
√
√
As per Cl. 6.2.1
√€
As per Cl. 6.2.2
1.
Visual Examination
2.
Power Rating as
per CWET/
accredited test
house
√
3.
Corrosion
resistance
√
4.
Power vs RPM
curve
√
5.
Protection against
high velocity/
overspeeding
√
√
√
As per Cl. 6.2.4
6.
Mounting Structure
and its
galvanization
thickness
√
√
√
As per Cl. 6.2.6
7.
Design calculation
on tower wind
withstand capability
√
√
√€
As per Cl. 6.2.6
8.
Provision of
earthing
√
√€
As per Cl. 6.2.7
As per Cl. 6.2.3
To verify test certificate
11.5
Test on Solar Charge Controller
S.N.
Name of Test
Type
Test
√
Routine
Test
√
Acceptance
Test
√
√
√
1.
Visual Examination
2.
Rating
√
3.
Compliance to IEC: 62509
√
√£
4.
Auto, bulk, float and
equalization charging of
battery
MPPT Technology
√
√
√
√
Capability for handling
120% of rated current
√
√
5.
6.
Method
Refer Cl.
6.4.1-(iii)
Refer Cl.
6.4.1-(xiii)
Refer Cl.
6.4.1-(vi)
Refer Cl.
6.4.1-(v)
Page 27 of 35
S.N.
£
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Effective from October 2012
Name of Test
Type
Test
√
7.
Efficiency
8.
Temp. Compensation
√
9.
Protection Test
√
Routine
Test
Acceptance
Test
√
√
√
√
10. IP protection
√
√
11. Surge protection
√
√
12. Functionality and rating of
the charge controller
13. Blocking Diode
√
√
√
√
√
√
14. Over Voltage Test
√
√
15. Environmental Test
√
√£
16. Suitability for both LMLA as
well as VRLA
17. Checking of electronic
components
18. Output to be cut-off on 80%
DOD of battery
√
√
√
√
√
√
Method
Refer Cl.
6.4.1-(vii)
Refer Cl.
6.4.1-(viii)
Refer Cl.
6.4.1-(xi)
Refer Cl.
6.4.1-(iv)
Refer Cl.
6.4.1-(x)
Refer Cl.
6.4.1
Refer Cl.
6.4.1-(ix)
Refer Cl.
6.4.1-(xiv)
Refer Cl.
6.4.1-(xv)
Refer Cl.
6.4.1-(i)
Refer Cl
5.6
Refer Cl.
6.6(iv)
√
√
√
Refer Cl.
19. Master Controller & charger
functionality (if any)
6.4.3
If compliance has already been checked during type testing, the same will be
relied upon, otherwise compliance will be ensured through physical tests.
11.6
Test on Wind Charge Controller
S.N. Name of Test
Type
Test
√
Routine
Test
√
Acceptance Method
Test
√
1.
Visual Examination
2.
Rating of WCC
√
√
√
3.
Efficiency
√
√
√
4.
Temperature
Compensation
Provision of blocking
diode
Protection
√
√
√
5.
6.
√
As per Cl
6.4.2(ix)
As per Cl
6.4.2(iv)
As per Cl
6.4.2(v)
As per Cl
6.4.2(vi)
Page 28 of 35
Effective from October 2012
S.N. Name of Test
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Type
Test
√
7.
Battery overvoltage
8.
Short Circuit
√
9.
Reverse Polarity
√
10.
Output to be cut-off on
80% DOD of battery
Dump load
√
11.
11.7
Routine
Test
Acceptance Method
Test
√
As per Cl
6.4.2(viii)
√
√
√
√
√
√
√
Refer Cl.
6.6(iv)
As per Cl
6.4.2(vii)
Tests on Battery
S.N.
Name of Test
Type
Test
√
Routine
Test
√
Acceptance
Test
√
Method
1.
Visual Examination
2.
3.
√
√
√
√
Refer Cl. 6.6(i)
Refer Cl. 6.6(iv)
4.
Battery Type
Battery Voltage and
AH
Ah Efficiency
√*
ô
5.
Wh Efficiency
√*
ô
6.
Battery Life
√*
ô
7.
Self-Discharge Test
√*
ô
8.
Battery
Characteristics
√*
ô
Refer Cl. 6.6 (ii) &
(iii)
Refer Cl. 6.6 (ii) &
(iii)
Refer Cl. 6.6 (ii) &
(iii)
Refer Cl. 6.6 (ii) &
(iii)
Refer Cl. 6.6 (ii),
(iii) & (vii-b)
¥
To be relied on datasheets and test reports
11.8
Tests on PCU
S. N.
1.
2.
3.
4.
5.
6.
7.
Description
Visual Examination
MPPT function
Efficiency
EMI/EMC
Output Voltage
Regulation
AC voltage range
Waveform
Type
test
√
√
√
√
√
√
√
Routine
test
√
√
√
Acceptance
Test
√
Remark
√
√
√β
√
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
√
√
√
Refer Cl. 6.5.4
Page 29 of 35
S. N.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
β
Effective from October 2012
Description
THD
Frequency in
standalone mode
Frequency range in
synchronizing mode
Load power factor
Overload capability
Crest factor
Noise level
IP protection
Protection
Overload
Short circuit
DC Over voltage
Grid
over/under
voltage
Anti Islanding
Over temperature
Solar-Grid-Battery
priority functionality.
Grid Export function
Grid Import function
DG interface
functionality
Connectivity to other
systems and to web
Environmental Test
of inverter
Provision of RCD
Type
test
√
√
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Routine
test
Acceptance
Test
√
√
√
Remark
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
√
√
√
√
√
√
√
√
√
√
√
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
√
√
√
√
√
√
√
√
√
√
√
√
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.4
√
√
√
√
√
√
√
√
√
Refer Cl. 6.5.4
Refer Cl. 6.5.4
Refer Cl. 6.5.2
√
√
√
√
√
√
√
√
Refer Cl. 6.5.3
Refer Cl. 6.5.3
Refer Cl. 6.5.4
√
√
√
Refer Cl. 6.5.4
√
√β
Refer Cl. 6.5.8
√
√
Refer
6.5.2(vii)
Cl.
If compliance has already been checked during type testing, the same will be relied
upon, otherwise compliance will be ensured through physical tests.
11.9
S. N.
Tests on Cable
Description
1.
Cable size
2.
Temperature
range
Voltage rating
3.
Type
test
√
Routine
test
√
Acceptance
Test
√
Remark
√*&
√*&
√*&
Refer Cl 6.4.1(xii),
6.7.1, 6.7.4, 6.7.6,
6.7.7 & 6.7.8
Refer Cl. 6.7.3(i)
√*&
√*&
√*&
Refer Cl. 6.7.3(ii)
Page 30 of 35
4.
5.
6.
7.
8.
9.
10.
11.
Effective from October 2012
Resistance
to
heat, cold, water,
oil, abrasion
Resistance
to
UV radiation
Resistance
to
Ozone
Low smoke, low
toxicity
Flame retardant
Flexibility
IEC
60332-1
compliant
IEC 60228 Class
5 compliant
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
√*&
√*&
√*&
Refer Cl. 6.7.3(iii)
√*&
√*&
√*&
Refer Cl. 6.7.3(iii)
√*&
√*&
√*&
Refer Cl. 6.7.3(iii)
√*&
√*&
√*&
Refer Cl. 6.7.3(iv)
√*&
√
√*&
√*&
√
√*&
√*&
√
√*&
Refer Cl. 6.7.3(v)
Physical inspection
Refer Cl. 6.7.3(vii)
√*&
√*&
√*&
Refer Cl. 6.7.3(viii)
*& Accredited lab test report/Manufacturers test report shall be acceptable.
11.10 Tests on Distribution Boards, Export metering and Web based
monitoring
S. N.
1.
2.
3.
4.
Description
DCDB- Provision
of DC
disconnector, etc.
ACDB
Export Metering
Web
Based
Monitoring
Type Routine test AcceptRemark
test
ance Test
√
√
√
Refer Cl. 6.5.6(i)
√
√
√
√
√
√
√
Refer Cl. 6.5.6(ii)
Refer Cl. 6.5.5
Refer Cl. 6.5.7
Page 31 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Annexure - 1
Quality Testing of PV-Module
Solar PV module shall be certified according to IEC 61215. The qualification
testing procedure is defined in IEC 61215 to examine the impact of
mechanical, thermal and electrical stress on power output. Bidder shall submit
appropriate type approval certificate for the offered solar modules from IEC
accredited laboratories.
Method of Testing
1.0
Visual Inspection:
Each module shall be carefully inspected under an illumination of not less
than1000 lux for the following conditions:
i)
ii)
iii)
iv)
v)
vi)
vii)
2.0
Cracked, bent, misaligned or torn external surfaces
Broken/ cracked cells
Faulty interconnections or joints
Cells touching one another or the frame
Failure of adhesive bonds, bubbles or delaminations forming a
continuous path between a cell and edge of the module
Faulty terminations, exposed live electrical parts
Junction box should have common terminals with suitable bypass diode
for preventing hot spot problem.
Performance at STC: (Clause 10.1 of IEC 61215:2005)
The current-voltage characteristics of the module shall be determined in
accordance with IEC 60904-1 at a specific set of irradiance and temperature
conditions.
Performance of PV-Module shall be generally evaluated at Standard-TestConditions (STC) as defined in IEC 60904 standards:
i)
ii)
iii)
3.0
Cell temp of 25° C,
Incident solar irradiance of 1000W/m2,
Spectral distribution of light spectrum with an air mass AM=1.5
Environmental Testing:
Following environmental tests shall be conducted on offered module or on
module of similar design, for initial clearance of the offered system:
Test
Cold Test
Dry Heat
Test Details
0
Temp. (-) 10 C
Duration: 16 hrs.
Temp. (+) 700C
Duration: 16 hrs
Relevant Standards
IEC-68-2-1
IEC-68-2-2
Page 32 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Temp. (+) 350C, RH 95%
Duration: 2 hrs spray and
22 hrs conditioning
No. of Cycle : 01
Wind
Pressure equivalent to an
air velocity of 200 km/hr.
Rain
Test as required in the
mentioned standards
Dust
Temp : 40°C, RH < 50%
Duration – 1 hr
* If compliance to IEC 61701 has been asked by
will not be required.
Salt spray*
IEC-68-2-11 Test Ka
JSS: 55555 (Test No. 12)
JSS: 55555 (Test No. 14)
the purchaser, then this test
Note: Before and after each environmental test, the solar modules shall be
subjected to performance test on sun simulator and insulation
resistance test. Degradation of the maximum output power shall not
exceed 5% of the value measured before the test.
4.0
Acceptance Criteria:
The Module is deemed to have passed the tests if the sample meets the
following criteria:






There is no evidence of a major visual defect such as a cracked or broken
window, bubbles or de-lamination in the encapsulant, etc.
There is no cell breakage and no water infiltration into terminal boxes.
No sample exhibits any open circuit or ground fault.
No visible evidence of major defects that may affect the performance of
the module.
Insulation Resistance not less than 50M-ohm at 500 V DC.
Degradation of performance may not exceed 5% after each single test or
8% after the whole sequence.
-------------
Page 33 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Annexure - 2
TECHNICAL DETAILS TO BE FURNISHED BY THE PURCHASER IN HIS
REQUISITION/ TENDER
1. System:
.1
.2
.3
.4
Whether 1-ph 230 or 415V 3-ph system is required ?
Whether wind-cum-solar or only solar based system is
required ? (Refer Cl. 2.0)
Galvanization Thickness (Refer Cl. 6.2.6 & 6.3.19(iii))
Is the supply of Export Meter required {Refer Cl. 6.5.5}
(Yes/No):
2. Wind Turbine and Support Structure:
Total power rating of wind turbines (WT) required#
(Refer Cl. 6.2.1)
.2
Is the firm required to submit type test certificate for salt
spray test as per ASTM B-117 for a minimum period of
1,000 hours? (Refer Cl. 6.2.2) (Yes/No)
.3
Will the height of all towers be 15m? (Yes/No)
If no, then mention number of towers >15m along with
their height. This will also need to be mentioned in
tender work schedule. (Refer Cl. 6.2.6)
# Before specifying the WT rating, the purchaser must consult C-WET’s
latest regular empanelment list, etc.
.1
3. SPV Module and Support Structure:
.1
.2
.3
Total power rating of SPV system (KWp)
Is the firm required to submit type test certificate for
Salt Mist Corrosion Testing? (see Cl. 6.3.5) (Yes/No)
Support structure, design and foundation wind
withstanding capability required (see Cl. 6.3.19 v)
4. Inverter:
.1
.2
KVA rating of the Inverter required?
Output voltage rating of Inverter?
5. Battery
.1
.2
Battery type (see Cl. 6.6(i))
Battery capacity required (VAH) (see Cl. 6.1.2 and Cl.
6.6 (iv))
Page 34 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
Annexure - 3
TECHNICAL DATA TO BE FURNISHED BY THE TENDERER IN HIS
OFFER
1. Wind Turbine:
i)
ii)
iii)
iv)
v)
Make and model no.
Rating of individual Wind Turbine (CWET certified
power rating)
No. of Wind Turbines used
Regular empanelment from C-WET? (Yes/ No)
Provision of dump load in case of wind turbines
(Yes/No)
If no, then literature endorsing your alternate arrgt/
design and/or evidence of successful working of the
same (Refer Cl. 6.4.2(vii))
2. SPV Module:
i)
ii)
iii)
iv)
v)
Make and model no. ( Refer Cl. 6.3.5)
Cumulative Power (KWp)
DC voltage range generated by the SPV array
Module efficiency ( Refer Cl. 6.3.8)
Module Fill factor (Refer Cl. 6.3.9)
3. Charge Controllers:
(please provide complete details for WCC, SCC and explain the master
controller functionality)
i)
ii)
iii)
iv)
Make and model no.
Ratings
DC Voltage output
Input voltage range for MPPT operation
4. Inverter:
i)
ii)
iii)
iv)
v)
Make and Model no
KVA rating of the inverter used
Output frequency range( Refer Cl. 6.5.4 item 5)
Voltage range of grid synchronization (from nominal)
( Refer Cl. 6.5.4 item 8)
Frequency range of grid synchronization (from
nominal)
( Refer Cl. 6.5.4 item 9)
Page 35 of 35
Effective from October 2012
Spec No. RDSO/2009/EM/SPEC/0004 (Rev.‘1’) - 2012
5. Export Meter:
i)
Details of Export Meter offered (only if the purchaser
has asked for it)
6. Battery:
i)
ii)
iii)
iv)
Make and model no.
Battery type
Nominal Battery Voltage
Battery capacity (AH)
7. Web based system monitoring: Name of URL at which the purchaser can
view the system performance data during warranty period.
Download