The Consulting Engineer in the 21st Century Presented by: 1. David C Russell Summary This paper looks at the challenging, and changing, role of the consulting engineer in the 21st century. It looks at past experiences and how to use consulting engineers in a highly competitive world. The perspective is from both sides of the industry, from that of the operating companies looking to implement a project which requires specialised knowledge, to the consulting engineers themselves, seeking to match their expertise with the operating companies expectations. Examples are given of how the resources bank of an engineering consultancy can be used to improve and enhance the outcome of pulp and paper company projects. Consulting engineers also work for vendor and equipment supply companies, both in the provision of engineering services and in interfacing between different processing units. The role of the consulting engineer is indeed a challenge in the 21st century, but by following a few simple guidelines, operating companies, vendors and consultants can achieve a mutually satisfying outcome at the end of the day. 2. Introduction Until about 15-20 years ago, it was common for the pulp and paper companies to have their own project engineering departments. Some still do, but for the most part the large engineering departments have shrunk to mere skeletons of their former selves. For example, in the mid 1980’s Carter Holt Harvey, Kinleith, had the largest projects engineering department outside the public sector. The emphasis on core business and the competitive nature of the pulp and paper business required a different approach. © Copyright Beca 2010, all rights reserved unless expressly agreed. Senior Project Manager, Beca Traditionally the preserve of civil and structural engineers, the consulting engineering business has expanded to include engineers of all disciplines. Initially a number of these came from the pulp and paper companies themselves, with project and operating backgrounds, but latterly the consultant companies are supplementing their basic strengths with graduate engineers and engineers from other industries and backgrounds. The consulting engineering companies have become repositories or banks of skills which are available for use by the pulp and paper operating companies. 3. The cost impact pyramid Before looking more closely at the role of the consulting engineer, it is timely to look at the cost impact pyramid, because of its relationship to the success or failure of a project. $1 Conceptual $10 Preliminary Design $100 Detailed Design $1,000 Final Delivered Drawings $10,000 During Construction $100,000 After Construction Figure 1. The Cost Impact Pyramid Page 1 The information provided in this publication is for information purposes only. Neither the author nor Beca assumes any duty of care to the reader or gives any representation or warranty in relation to the contents of this publication. You should not rely on this information as professional advice or as a substitute for professional advice. Specialist professional advice should always be sought for your particular circumstances. 1.1 The Consulting Engineer in the 21st Century The point of the cost impact pyramid is that good engineering in the first phases of the project has a very substantial effect on the later costs, particularly as the project moves towards start up. The message is clear but not always recognised: money spent up front is well repaid in the later stages of the project. Whilst hard data is not easy to come by, anecdotal evidence suggests that the return from good engineering in the front end of the project has a yield of the order of ten fold in capital cost. That is, spending an extra dollar on engineering at the front will save around $10 on capital. 4. The parties We can define the main parties as these: The consulting engineering company which sells expertise and knowledge, supplementing that resident within the operating and/or equipment supply companies; The vendor or equipment supply company, which can supply engineering services in addition to equipment, but may also require the consulting engineering company’s service to supplement its own, and/or to engineer the interfaces between their units and the services required for these units; The operating company, with a specific need, either on-going or one-off, for project or maintenance engineering which it cannot meet from its own resources. The problem is therefore one of matching needs to resources. We can now look in more detail at the nature of each player. 4.1 The operating company An operating or manufacturing company derives its income from the production of a product, for which there is a market. If both product and market exist in an environment which generates acceptable returns, the company generates sufficient income to pay its staff, meet its bills, and generate a return to shareholders. Company effort is directed towards production and marketing. Engineering services are largely, although not exclusively, directed towards solving problems in the process which are impeding production and which by definition are short term in nature. The emphasis remains, and will remain, on producing product at the appropriate cost and quality. 4.2 The vendor The main purpose of the vendor or equipment supply company is to sell equipment. This may be specialised equipment, for example digesters, screens, washing units, as well as complete systems such as pulp dryers or paper machines. The vendor company may offer engineering as well as equipment. Within the industry, views differ on whether the supply of engineering services is part of the vendor company’s core business. Some vendor companies have moved away from the engineering services area altogether whilst other companies have sub-contracted the supply of engineering services. Regardless of the approach, in times of high demand the vendor company may look to the engineering consulting company to supplement its own resources, in a similar manner to that of the operating company. Vendor engineering is a valuable asset when used appropriately, and that is when the design of components such as piping systems is integrally connected and in close proximity to the process equipment. However, two cautions should be noted when operating companies start to consider whether vendor engineering is suitable for their project: 1. Vendor engineering applies only to the package of work for which that vendor is responsible. If the operating company has “cherry picked” – selected what it considers the best packages available from different vendors – then someone, typically a consulting engineer, is required to connect the various packages together in such a way as to achieve the aims of the project. 2. Vendor engineering can be offered on a reduced fee or even a no-fee basis. However, costs always appear in one form or another, so operating companies should examine where the engineering costs are located. 4.3 The consulting engineering company The consulting engineering company has no “manufactured” product in the normally accepted sense. Instead, it relies on commissioned work to generate its income and to pay its employees. The two “products” which the consulting engineering company markets are time and expertise. Both “products” are related to resources. Time is related through the availability of people to carry out the necessary work. Expertise is available through the experience which the consultant has acquired when working on different projects for a range of operating companies, and from the additional skills which are usually available from international ownership and/or affiliation. The use of its services is a direct result of the requirements of the operating company and to a lesser extent, the vendor company. An analysis of pulp and paper project activity shows this to be cyclical: periods of high activity interspersed with periods of relatively quiescent activity. For example, an analysis of activity at the Kinleith mill complex over the last 15 years shows this pattern, with the following peaks: 1985-86: Recovery boiler and evaporator installation. 1989-90: Bleach plant revamp; new oxygen delignification; screening and washing upgrade. 1996-98: Paper machine modernisation Page 2 1.1 The Consulting Engineer in the 21st Century Obviously, a consultant engineering company, which relies on major project work from one operating company, will have a lean time indeed. In order to survive during periods of low activity, a consultant company needs a minimum of two clients, neither of whom are carrying out major project work at the same time. Preferably, the consultant company will also have client companies which operate in different industries. In addition, the consulting engineering company has available to it a number of systems and procedures which provide a disciplined approach to conducting a project, regardless of size. These systems cover areas such as: Quality systems, such as certification to ISO 9001. Verification and Validation Procedures Documentation Production and Control Job management and contract administration Risk Management The implementation of these systems lends a degree of assurance to the operating company that the conduct of its project is proceeding in a disciplined and well-ordered manner. A casual or informal request suggests that the work content, or scope, is not well known or defined. In this case it is imperative that the consultant responds to the request with an outline of the scope, as he understands it, in order to confirm the operating company’s request. At the very least, this provides an opportunity to minimise misunderstanding at the outset of the project, when the consultant has one expectation and the operating company may have another, and different, expectation. 5.2 The invitation The invitation to bid typically comes in the form of documents from the operating company inviting the consultant to make a proposal. Again the scope of work to be covered is critical and it is not uncommon for the consultant to assist the operating company in preparing the invitation to bid. If the project is still in its initial stages, the consultant will respond with a proposal for a pre-feasibility or feasibility study. The proposal outlines the work to be covered, the resources to be employed, the conditions of contract and the accuracy of the cost estimate. In the next section, we outline these in more detail for a typical project. The consulting engineering company needs to replenish its “human capital” from time to time, through losses from natural attrition, and retirements. What attracts graduates to join an engineering consultancy? The answer is straightforward: a high level of job satisfaction. Moving from one project to another, each with its own particular challenges, provides the opportunity to increase skills, knowledge and expertise, combined with an always present challenge. 6. 5. Typically projects proceed through a number of stages, each with a different range of accuracy in the scope and estimate. For example, the following criteria could be used for project implementation and execution, as summarised in Table 1: The relationships The discussion above pre-supposes that a relationship exists between the two parties. In order to develop the relationship, a desire for closer contact must exist on both sides. The process can begin in a number of ways, for example: 5.1 The informal approach If the consultant is well known to the operating company, the consultant may have advance notice of proposed new projects. The process may begin on an informal basis from the operating company’s perspective, such as a casual request to look into the feasibility of a project. However, “casual request” is not a term in the consultant’s vocabulary, because of the constraints on the consultant’s method of operation. The consultant has to respond formally because it has to operate on the basis of a contract, both from a quality and procedural point of view as well as from a liability point of view. Outlining the costs In preparing a proposal, the consultant looks at both the cost of the project, in terms of equipment, and the cost of services. At the same time the consulting engineer is confirming its understanding of the project requirements with the client, which may be either the operating company or the vendor company. 6.1 Stages of the estimate Table 1. Phases and Range of Accuracy Project Phase Range of Accuracy Conceptual + 50% Approval in Principle + 25% Execution +10% The level of accuracy is determined by the needs of the operating company For example, a project which is but one of a number is unlikely to require or justify the expenditure necessary for a + 10% order of accuracy. Instead, an order of accuracy around the 20-30% mark is sufficient to indicate whether the project has sufficient economic health to advance to the next stage. Page 3 1.1 The Consulting Engineer in the 21st Century Note that the order of accuracy is a plus/minus figure. It is not always recognised that even a firm and fixed quotation could be + 10% on the price – through items not included in the quote (for example, freight/insurance, spare parts and possibly exchange rate variations). Operating companies have a tendency to assume that a plus/minus 10% quote is in fact a plus zero % minus 10% quote but this is not the case. Even at this level the numbers can be significant: on a $100 million project, 10% is $10 million, not an insignificant amount. Similar comments apply to the other order of accuracy estimates. 6.2 Resources We have already seen that the consultant supplies resources to complement those of the operating company, when the workload requires this. We can see through Figure 2 that the normal resource requirement for a project is in a bell shaped curve, with the requirements rising rapidly as the project gets underway, followed by a peak, then a fall as the project is taken over by the operating company’s production staff. Consultant Resources 7. Ongoing relationships The stage is now set for a fruitful and harmonious relationship, but there are still some requirements which must be met from the parties: 7.1 Corporate commitment: Corporate commitment is required on both sides. If the operating company abrogates its corporate commitment and employs a “hands off “ type approach, the scene is being set for a poor, and potentially disastrous, outcome. The operating company must understand that it cannot pass its responsibilities over to a consultant company without losing a large measure of control. It is importance of the operating company having available a team, with the necessary skills, to manage the consultant. The maintenance of the consultant/operating company interface, with a clear view of the objective, is a driving force in the success or failure of the project. 7.2 Risk Management One of the tensions which frequently develops on a project is the assignment of risk. Risk in this context is defined as the risk that the project will not generate the desired outcome and can be broken into three major categories: Resources 7.3 Process risk Company Resources Time The process risk covers the possibility that the process selected for the project is inappropriate or only partly successful. The operating company may wish to assign this process risk to the consultant or to the equipment vendor. Whilst this may appear attractive on the surface to the operating company, it becomes less attractive when examined in detail: The consultant and vendor companies will inevitably limit the Figure 2. Resource Requirements The span over which the resources are supplemented by the consultant varies with the nature of the project, as does the number of resources supplied. For example, on a recent major pulp and paper mill upgrade, the resource requirement spanned over an 18 month period and peaked at 160 supplementary staff supplied by the consultant. degree to which they are exposed to risk. Insurance companies will not generally insure against process risk. More importantly, the party most at risk is not the consultant or even the vendor, but the operating company, because it has a much greater financial outlay than any other party. A number of operating companies now accept that the transference of process risk to another party is largely impossible. Page 4 1.1 The Consulting Engineer in the 21st Century 7.4 Schedule risk Schedule risk - the risk of the project running beyond the agreed date - would appear to be an area where the operating company is largely responsible, but again a more detailed examination reveals that both parties have obligations in this area. The parties must agree on the project scope of work. If the operating company changes its mind on the scope of the work, a claim for the additional impact may be raised. This impact was earlier illustrated in the Cost Impact Pyramid (Figure 1). 2. Unforeseen delays, usually equipment delays, which did not come to light in the earlier and less detailed phase of the project. Whilst the schedule will normally have some float available, the operating company will wish to reduce the float to the minimum and this may later impact on the schedule. 3. Shutdown schedules, which impact on the time which is available for installing the equipment for the project. This applies to the situation when a project is implemented in an existing mill. The operating company must respond to requests for information in a timely fashion. Whilst it is relatively common for contracts to have “turnaround” clauses, these require a reasonable degree of discipline for both parties. Again, if the turnaround periods are not observed, the schedule can slip. Information from the vendor company is also an area where the timely flow of information contributes to the project’s success. Timely decision making by the operating company. For example, it would be normal for the consultant to obtain quotes on equipment and put these forward to the operating company with a recommendation. Normally an allowance is made in the schedule for the operating company to consider the recommendation and authorise negotiations to proceed with the preferred vendor. Any delays, either through lack of resources or because the operating company wants different avenues pursued, will impact on the schedule. The solution is to have an agreed list of vendors at the outset, together with an agreed timetable for decision making. Agreement on the schedule. Typically the operating company will have a target completion date, within which the consultant prepares a schedule of the necessary activities. After agreement on the schedule, it is common for one of three processes to take place: 1. The operating company delays the start date but maintains the end date. This places the consultant in an awkward situation: it must either increase resources (although these may not be available) and incur additional costs, or inform the operating company that the schedule can no longer be met. 7.5 Budget risk The risk of over-spending the budget depends largely on two factors: the schedule, discussed above, and the quality of estimating, covered in Section 8 (i). In all respects, the cost estimate must be realistic even if this means that the project is revaluated on its economic justification. All engineers tend to be optimists, and occasionally budgets reflect this optimism. The role of the consultant is to prepare a realistic budget, which is generally higher than the operating company’s first estimate. The consultant knows, through experience, of the many unaccounted-for items which could crop up in the project. In turn, the operating company needs to be quite clear on why it is carrying out the project, and to identify the go/no go point. Most consultants, and probably most operating companies, know of projects where enthusiasm over-ruled good sense, and a project proceeded which in retrospect failed to produce the required return on investment because the costs escalated to a higher than expected point. For example, a project which starts with a budget of $100 million is considered, on the normal grounds of project assessment, to give an acceptable return on funds employed. If this budget has been unduly optimistic, and the real figure is $150 million, a point may have been reached where the market cannot accommodate the extra cost associated with production. For any project, the consultant can assist in the management of the project budget, with a range of tools . One of the basic tools is a cost curve. This curve measures the actual expenditure against the forecast expenditure, and an example for an actual project is given in Figure 3: Page 5 1.1 The Consulting Engineer in the 21st Century With the realisation that a closer relationship between operating company and consultant usually works better than a distant relationship, EPC contract arrangements should be entered into with considerable forethought and recognition of the inherent risks. 8.2 Liability Figure 3. Project Cumulative Cost Curve This curve flags up significant departures from the planned budget at an early stage. A lower expenditure than forecast in the budget may indicate a schedule problem; a higher expenditure than forecast may indicate an optimistic budget. Such curves are applicable to both large and small projects. 8. Structural considerations The operating, vendor and consulting companies have decisions to make on the structure of their project, and in these the consultant also has a role. 8.1 EPC or EPCM Liability covers the area of who pays when the project does not perform as expected. As already discussed, it is difficult, if not impossible, for the operating company to pass its process risk to the consultant. As well, open liability would not be acceptable to a consultant. Most standard forms of contract limit consultant liability to set sums. For example, the IPENZ Conditions of Engagement (Short Form – Commercial) limits consultant liability to the greater of five times the value of the fees or NZ$100,000. The conditions of engagement also require that the consultant carries professional indemnity insurance for the value of the contract liability. 9. Rules and results Finally, what is the 21st century formula for a productive and mutually satisfying relationship between operating, vendor and consulting engineering companies? The following are general points which should lead to an harmonious understanding between all parties: Two major structural forms of project structure exist: EPC (Engineer, Procure, Construct) and EPCM (Engineer, Procure, Construction Management). The essential differences between these two forms are: A common goal for the outcome of the project and what it is EPC: Fixed price, little or no operating company involvement. The owner shifts costs, schedule and process risks to the contractor. A defined scope of work agreed to by all parties. EPCM: Work up to a target manhour/cost budget, higher operating company involvement. A plan which outlines the resources required and available, The price of an EPC type project arrangement is almost always higher than an EPCM arrangement, because the risk carried by the consultant is higher. Furthermore, EPC type contracts are a “hands off” type of approach from both parties. designed to achieve. Clear lines of communication and a willingness to share information. A defined budget and schedule for controlling the project. and matches need with demand. Other more project specific criteria could be added, but when the project concludes, all parties want to be able to state: The project worked, and it was achieved on schedule and within budget. Page 6