SUMMARY GUIDANCE ON IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 IMPLEMENTATION OF REMEDIATION PROJECTS This guidance addresses processes for implementation of remediation projects, from the point of view of the implementing agent or authority. Projects will have to be consistent with the specific procedures of national authorities and/or with donor requirements but broadly similar approaches would generally apply to all projects. The Note provides a possible agenda for discussions on the preparation and implementation of the project. KEY POINTS Deciding on the Project Management approach is a critical early step. Once the overall scope and scale of the remediation project is agreed, a decision has to be made on whether the project will be implemented with the team's own resources or will be contracted out. The choice of approach determines the skills and resources needed within the project management team. Planning to address the site requires: Definition of the nature and extent of contamination (remedial investigation) Identification and evaluation of practical remediation options (feasibility study) Development of a workplan Preparation of a long-term stewardship plan • • • • Preparation for remediation, once the overall workplan has been agreed, should cover: Ensuring ongoing local involvement Clear responsibilities and lines of communication Agreement on specific remediation project objectives Confirmation of funding and completion of contracting Confirmation of legal and regulatory clearances Definition of implementation, oversight and close-out procedures Agreement on project action plan for all involved parties • • • • • • • Execution of the remediation covers the core physical works which deal with the contamination and which restore or secure the site in order to achieve the agreed remediation objectives. Key steps in this would include: • • • • • • Possession of the site and containment and/or preparatory works as required Preparation of any on- or off-site storage/disposal facilities Initial/urgent engineering works Further technical investigations as needed Implementation in stages, as appropriate Documentation of work completed GAHP Guidance Notes provide information on international good practices and regulations in remediation. They are prepared to assist GAHP members in dealing with practical problems of remediation of polluted sites and are intended to assist readers to identify key points that should be taken into account in reviewing or approving any proposal. Guidance notes reflect the views of individual GAHP specialists and of invited outside experts and do not necessarily represent the views of any specific government or agency. Additional background and material may be found on the GAPH website. IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 INTRODUCTION AND SCOPE This Guidance is designed primarily to support discussions with the key people responsible for preparing and implementing a contaminated site remediation project, in a context where administrative procedures and specific technical requirements are not well defined. These people may be local authority or government officials, community or NGO leaders, or other institutions or organisations (public or private) who have committed to practical actions to address a problem site. This note provides a possible agenda for discussions between the project team leadership and responsible authorities, financing agencies and representatives of local bodies. It is not a comprehensive implementation manual. It is assumed that the site in question has been identified as contaminated to an unacceptable level and that decisions have been taken that the site is a priority for remediation. (Separate guidance is provided on identification and prioritisation of contaminated sites.) DECIDING THE PROJECT MANAGEMENT APPROACH Implementation of the project will be strongly affected by the number of different parties and organisations involved and by the existing relationships between them. A mapping of relevant and interested parties should be made at an early stage. Apart from those directly engaged in design and implementation, aspects such as access, approvals, clearances, community engagement, etc may all require different parties to be involved. Larger projects, particularly those involving public funding, will probably require formalised and documented implementation agreements with key parties. The financial resources available will clearly have a major bearing on design and implementation options. It is usually necessary to work within a tight budget and to achieve the highest level of remediation possible with a constrained budget. Decisions have to be made and agreed about the scope of the project and the type of interventions. For example, whether the project can address all the problems across the site and achieve complete remediation, or whether it will be focused on isolating/resolving the worst areas and providing an interim remedial solution. Agreement on acceptable interim remedial measures may be an effective way to achieve significant and important improvements in the first phase of interventions. At this point, it will normally be possible to clarify the practical technologies that may be applicable and to identify a shortlist of possible remediation schemes. Decisions also have to be made on broader interventions which will accompany the physical site works, such as community education campaigns, health interventions, enforcement/support in relation to polluting activities, capacity building etc. All of these should be targeted at supporting the long term objective of protecting and improving community health and the local environment. Select the project management structure. Once the overall scope and scale of the interventions have been agreed, the fundamental strategic choice is between carrying out the physical work with the lead agency's own resources or using a contract approach. This will depend not only on the resources and skills available but also on the sources of funding and any institutional requirements that may accompany these. Implementation with own resources may be preferable if: o o o o The implementing team and local partners have relevant technical experience and access to equipment. The remediation approach is simple and straightforward. The funding is available and adequate There is strong local support and no identified bureaucratic or political obstacles 2 IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 Contracting out the main implementation activities is likely to be appropriate if: o o o o The lead agency is a government entity whose standard practices include contracting of technical works Key funders such as government agencies and international donors have procurement rules which require competitive bidding. The remediation requires advanced approaches for investigations or implementation, for which outside technical expertise is required The amount of the funding or the scale of the works requires the transparency which contracting can bring. Even in a contracted out approach, there will be important components of the overall remediation process which remain to be carried out by the project team. A critical consequence of this, which is not always recognised, is that when the works are contracted the skills required of the overall implementing body must relate to tendering procedures and contractual management rather than technical implementation. However, the project team should also have relevant technical expertise to ensure adequate oversight of the contractor. This note does not address these skills. This guidance note addresses the key steps in planning and executing a remediation project. These steps are generally common to both own-managed and contracted approaches although the details will vary from project to project. PLANNING TO ADDRESS THE SITE Once the overall implementation approach is determined, then the necessary structures and personnel need to be put in place, with the necessary authority to make the relevant decisions. A named Project Manager should be appointed to carry out the routine processing of project preparation, reporting as appropriate to a Steering Committee and/or a Stakeholder Group. Implementation of physical remediation works would include the following steps. Define the nature and extent of contamination. The initial site screening will already have set out the broad characteristics of the site(s) and the identifiable impacts. This screening includes establishing a Conceptual Site Model (CSM) which identifies the sources, pathway and people potentially impacted. The CSM provides the basis for the initial risk assessment, which allows the site to be ranked against others in terms of priority for intervention. At this project preparation stage, the initial information should be reviewed, gaps in data or understanding identified, and further site specific investigations and tests carried out as required to refine the CSM. A walkover of the site and surrounding areas by an experienced specialist will provide additional information and confirmation of key factors. The availability of on-line geographical and mapping tools means that a reasonably accurate base map can be prepared for most sites with limited resources. Hand-held GPS allows key features on the ground to be located to within a few metres. Simple field testing is adequate for defining bounds for areas of high pollution (with some check samples being tested in local laboratories). Sites with groundwater contamination will require that test wells be installed and sampled. Technical support from qualified professionals is usually necessary and often available through the relevant government agencies or local technical or scientific institutes. On the basis of this information, the sources and pathways are better defined and a more detailed risk assessment should be carried out. This risk assessment will provide the basis for discussion and agreement of relevant standards and targets. In terms of the immediate intervention to reduce immediate health risks or acute environmental damage, interim levels may be appropriate to use if achievement of desirable long term levels requires resources which realistically are not available in the short term. Identify, evaluate and select remedial options. The initial assessment of the site and discussions over the scope of the project and the funding required/available will normally have identified a small number of technical approaches which could be practical and affordable at the specific site. Key parameters governing 3 IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 selection of plausible options are the size, location and other physical characteristics of the site, and the financial and human resources available. Other important factors that need to be taken into account are the potential values and use of the site, the biodegradablity or the persistence of the main pollutants, and whether transport off site, especially via groundwater, is a major issue. (Separate guidance on remediation technology is being prepared.) At this stage, the acceptable technical approaches have to be refined and agreed. Relevant technical expertise will be required to support this identification of technical preferences but extensive studies are not always necessary in order to take initial action to deal with urgent problems. The level of detail required for the technical documentation at this stage depends greatly on the implementation approach adopted. For a small and simple project led by an experienced project manager, it may be sufficient to have a good estimate of the quantities/scale involved and confirmation of the availability and costs of the necessary equipment. For a large complex project, which is to be contracted out to qualified and experienced firms, the relevant approach may be to set out realistic performance criteria to be achieved and to leave the details to be proposed and agreed during the contracting process. A mid-scale project is likely to be the most complicated to implement if it requires the technical details to be worked out in advance, in a way which can be implemented by contractors who may have limited relevant experience. In this case, specialist technical advice will be required during the preparation and contracting process. In many cases, collection and removal from the site of highly contaminated material may be an option but this will often be constrained by the availability and cost of approved secure disposal facilities. Investigation of the feasibility and cost of using existing approved facilities is often an important early step in consideration of technical options. Develop the work plan. Once the overall approach and the management structure have been determined, a work plan needs to be developed. The work plan is a clear, time-bound summary of the actions required by each party for the successful remediation of the site. It will focus on the physical actions which are the core of a remediation intervention but must also address related institutional controls and social mobilisation actions which may be part of the overall solution. To the extent that there is a specific health intervention included in the overall process, this should also be included in the plan, with the necessary coordination clearly defined. Prepare a long-term stewardship plan. In conjunction with the work plan for the remediation project, a long term strategy and plan should be prepared and agreed for the control and maintenance of the site going forward (at whatever level is appropriate). This should set out the responsibilities and the resources required (and available) to ensure that the benefits of remediation are sustained in the long run. Where related environmental management controls on industry or artisanal activity are required to ensure that the contamination does not re-occur, the necessary commitments and resources from the relevant authorities need to be put in place, as part of this remediation project. PREPARATION FOR REMEDIATION Ensure effective local involvement. Remediation projects under GAHP are targeted at serious urgent problems, where immediate action is justified. The urgency must be confirmed by evidence of real risk and by a local constituency for the intervention. There may be objections or resistance to the project and these must be clarified and addressed through a broad based committee, stakeholder group or similar mechanism. This may be a formal structure, such as a committee established by the authorities or it may be an ad-hoc group set-up to help address the specific problem. This has to be more than just a consultation process. It needs to involve the various groups who can influence decisions and undertake specific actions, in support of the agreed objectives. The committee should typically comprise representatives of local authorities and community groups, the agencies responsible for different aspects, the business community, technical institutions with capabilities relevant to the project, and any national authorities which have relevant authority or jurisdiction over the problem. There must be a strong facilitator – preferably a “champion” who is recognized as a fair proponent of finding 4 IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 practical solutions. The role of the group is to implement an effective solution. It may begin with recriminations but the mandate of the facilitator is to move the participants to agreement on what each can do to support a practical resolution. Reach agreement on remediation priorities: The Project Manager, working with the committee, must begin by generating agreement on the priorities for the present phase of remediation process. This will be based on the updated investigation and information on the site and the resources available. Set project specific remediation objectives and design the intervention. Specific, monitorable remediation design objectives should be developed and agreed for the project. There may be a wide range of different perceptions of problems, risk and solutions. It is important at this stage to reach agreement on immediate objectives and on the timeframe and process to be used in achieving those objectives. This will often be focused on removing a specific perceived health or environment threat or on securing/improving a particular site. Depending on the scale of the problem and the resources available, it may not be realistic to plan for full remediation of all the site(s) in the first project and it may be necessary to set achievable interim remediation objectives. In that case, the interim nature of the outcomes must be made clear and a strategy must be set out for moving towards full remediation. The timeframe for reaching remediation objectives should be realistic, taking into account downtime due to weather, equipment breakdown, and unforeseen conditions such as discovery of unknown hazards. There will inevitably be some gaps in the data available for a legacy site. Polluters are inherently unwilling to measure and report levels of contamination. Impacts on health or on the environment are difficult to measure directly and so appropriate proxy measures (such as levels of exposure or contamination) are used. In the absence of “scientific proof” of cause and effect, the approach adopted for the remediation is that of risk assessment. It is important that this approach be spelt out clearly and be accepted by all the stakeholders. It cannot be guaranteed that no possible risk will remain after initial remediation, but it should be emphasized that the intervention will reduce the risk significantly. In circumstances where there are a number of sites to be addressed or where there are other strong directly competing priorities, it will be important to have a clear and documented decision to proceed, setting out objectives, constraints and resources committed or anticipated for the implementation. If implementation of the works is subject to certain decisions and/or availability of financial or other resources, then these caveats should be noted and monitored. Longer term aims, such as redevelopment or complete remediation, can be discussed in parallel but lack of consensus on these aims should not be a reason for delaying necessary short term interventions. Further work required to complete full remediation can be outlined and a broad strategy agreed for moving forward to achieve this. Confirm financing. The project will not have progressed to this implementation stage without agreement having been reached on the sources and scale of funding for both the preparation and the implementation. However, there are often difficulties and delays in the actual provision of agreed financing and it is a critical task for the project manager to confirm the availability of the funds and to adjust the project plans for any shortfalls or increases. Adjustments to the project plans resulting from shortfalls should be communicated to the stakeholders so expectations established earlier can be downgraded to match actual outcome. (Options for FINANCING REMEDIATION are discussed in separate guidance.) Define implementation and oversight procedures. The physical clean-up of the sites(s) must be implemented under clear and open process and procedures; the works must be carried out in an efficient and equitable way; and the results must be demonstrated to achieve the specified design objectives. The procurement and financial management systems used will vary with the scale of the project and the institutional context but whatever system is used should meet these criteria. o o o Establish clear process and procedures and apply these in an open manner. Select the contracting process to balance efficient use of resources with high levels of local and appropriate inputs. Provision of resources directly to the project by those responsible for the pollution is encouraged. Supervise the implementation at the appropriate level of detail. On-site quality control is often the best way to ensure efficient and effective remediation works. 5 IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 Monitor and report on the parameters established in under the design objectives and provide commentary on the achievement of the objectives Require a project completion report summarising the aims, activities and outcomes o o Obtain legal and regulatory clearances. Remediation activities, even if undertaken for worthy health and environmental reasons, still need to satisfy, or to be exempted from, the necessary legal and regulatory requirements. Delays in implementation can be caused by failure to deal with issues such as access rights, formal environmental approvals, hazardous materials regulations, statutory planning consents and so on. If the site or the pollution caused is the subject of legal proceedings, then any consequences for those proceedings of starting remediation needs to be assessed and addressed as necessary. One task in the initial preparation should therefore be to determine all relevant legal considerations and to ensure that necessary notifications, waivers and/or approvals are all in hand. Agree specific priority actions. Effective remediation will involve the participation and cooperation of a number of the parties involved and therefore agreement on an action plan will require discussion and negotiation. The technical team should provide clear options for consideration, including estimates of cost effectiveness. However, the final plan must be broadly accepted and cooperative if it is going to be implemented successfully. This is a key role for the project committee, where the pros and cons of the different options should be discussed, and their implications in terms of risk and costs for each party clearly understood. EXECUTION OF REMEDIATION Once the remediation process has been defined and started, the full scale implementation can then be put in process. This note cannot address all of the many aspects of an implementation project but points to be taken into consideration include: o o o o o o o o o o Possession of the site Define “hot spot” or high priority areas within in the site Preparation of any on- or off-site storage/disposal facilities Community education and health monitoring, as appropriate Preparatory and urgent engineering works as required Further technical investigations if needed Implementation in stages, as appropriate Documentation of work completed Long term social or health monitoring programmes Final review/acceptance of site and implementation of monitoring Possession of the site. An immediate first step will often be to gain access to and possession of the site. Even if access has been provided for investigations, it is important to ensure that there is practical access and no objections to occupation of the site for remediation activities. Requirements for access and egress of heavy machinery and loaded vehicles must be decided and agreed with local residents who may be affected. If the area to be remediated is part of a larger site, then the working area needs to be clearly delineated and access restricted. Ideally some form of fencing would be used to control movement onto or across the site. Security, either through physical measures or provision of guards, is likely to be necessary if equipment and fuel are stored on site. This will normally be the responsibility of the contractor. Confirm or define “hot spot” areas. Once the site is available, the areas of high level contamination which are the priority for remediation should be confirmed or defined and marked out. Initial understanding of locations, depths and quantities can be refined and any necessary adjustments made to the working plan. Even with good site investigation, it is unlikely that all the details of the contamination will have been identified. Some areas may be designated for different remedial actions (for example some areas may be treated insitu while others are excavated) and these different areas should be clearly marked out. Preparation of disposal facilities. Preparation of disposal facilities, particularly if these are off-site, should be commenced as early as possible, in order to confirm feasibility and to identify any unforeseen constraints 6 IMPLEMENTATION OF REMEDIATION PROJECTS Version 1.1 - Aug 2014 or difficulties. Fencing and control of an off-site disposal area should be carried out in a similar manner to the main remediation site. Community education and health monitoring. Where education or health campaigns are part of the overall set of interventions, it may be effective to launch these at around the same time as the physical works, in order to take advantage of local interest and publicity. Public information processes may also usefully be launched at this point in order to gain additional support for the interventions and to reduce concerns about any inconvenience caused during the construction work. Preparatory or urgent engineering works. Once the site is secured, the first stages of engineering works can be commenced. These could include upgrading access and clearing the site. At this point, any urgent engineering work should be done, such as securing derelict buildings and making safe any unstable slopes, ponds holes etc. At this initial phase, only experienced staff and contractors should be working on the site. Further technical investigations as needed. Once the site is contained and secure, it will be possible to carry out any additional technical investigations that have been identified as necessary. These are likely to include investigations which require mechanical equipment, such as trial pits or boreholes. If the initial site review after taking possession has identified important differences from the earlier investigations and understanding, then a considered decision should be made as to that further site investigation would be justified, in terms of overall cost management, as opposed to continuing with the original plan and accepting the need for some additional works. Implementation in stages, as appropriate. Implementation of the project should follow the defined contractual approach and the agreed programme of work. In cases where the precise extent of the contamination across the site cannot be determined or where there are a number of different areas of contamination, the work should be planned and implemented in stages, allowing for checking of each area as completed. Finishing up of details is always a challenge and therefore time and resources must be allowed to ensure that the work is fully completed as planned. Documentation of work as completed. Good records should be kept during implementation of samples taken, contaminated material removed, and new fill or construction. All of the records should be carefully geo-referenced and must be completed and checked at the end of implementation. In particular, any areas which were not fully remediated or which have been identified for future additional remediation works must be surveyed, marked and recorded in an agreed fashion. Long term social or health monitoring programmes. Completion of the physical works is often not the end of the remediation intervention. Any associated social programmes or health monitoring systems should be put in place before the project is closed. In particular, any institutional measures which are relevant to the long term security and success of the remediation, such as controls over access or use of land, must be put in place. Final review and acceptance of site and implementation of monitoring. At the end of the physical works, after any outstanding "snags" have been identified and resolved, there should be a formal process of reviewing the implementation against the contractual commitments and against the overall objectives. Any off-site works - particularly any off-site disposal facility - must be also be reviewed, documented and signed off as part of the completion of the remediation. Any remaining issues which need to be resolved, especially those relating to the future use and management of the site, must be discussed with the relevant parties and the responsible authorities. Decisions and agreements should be recorded. All relevant site documentation and contractual records must be copied as needed and carefully archived with the respective parties. A final step in acceptance is to test the monitoring system (both hardware and procedures) and to formally hand over responsibility to the party assigned. 7