PUENTE DE LA UNIDAD Monterrey, Mexico INTERNATIONAL BRIDGE TECHNOLOGIES, INC. Project Description CABLE STAYED BRIDGE Overview The signature structure of Puente de la Unidad project is a 304m (997ft) long asymmetrical cablestayed bridge, with a main clear span of 185.6m (609ft). The main pylon is inclined 30° to the vertical and reaches a total height of 152.1m (499ft) from the top of foundation. Nearly all the main structural components are made of 50MPa (7.25ksi) strength concrete. Thirteen pairs of harped stay cables support the main span and are anchored on the outside of the roadway. One pair of vertical stays is anchored into the back of the pylon. Main span carries 2 lanes of traffic in each direction with pedestrian walkway provided in middle. Pictures of the bridge are shown below. International Bridge Technologies (IBT) was the lead designer for the bridge. The specific design tasks included: • • • • • Main Span: Conceptual, Preliminary, and Final Design Stay-Cables: Conceptual, Preliminary, and Final Design Construction Methods: Conceptual, Preliminary, Final Design, and on-site support Pylon: Conceptual, Preliminary, and Oversight of Final Design Foundation: Conceptual, Preliminary, and Oversight of Final Design The design of the bridge included detailed, 3-D FEM, non-linear, and time-dependent analysis. In addition, detailed studies were performed to ensure compatibility of the extensive network of post-tensioning tendons and non-orthogonal reinforcement. Sistemas Optimos Constructivos S.A. (SOCSA) served as the prime consultant for the full viaduct project. SOCSA performed preliminary analysis and final design for the pylon and foundation. West Wind Inc. provided wind studies and cable damping requirements. ©2009 Copyright International Bridge Technologies, Inc. PUENTE DE LA UNIDAD Monterrey, Mexico INTERNATIONAL BRIDGE TECHNOLOGIES, INC. STRUCTURAL SYSTEMS • Original or Innovative Applications of New or Existing Techniques: • Social and Economic Considerations: The bridge project includes a long viaduct to provide The fundamental behavior of a cable-stayed structure congestion relief to the crowded streets of Monterrey. is well understood. Typically the bridges are Also, the Santa Catarina riverbed can crest at a level symmetric by span and pier layout, and the balancing where most other adjacent bridges are under water. of forces is accounted for in the basic concept. In This bridge will provide a critical escape route for the case of this bridge, the asymmetry required the the citizens on the South side of the river. In addi- design to go back to a more basic level to ensure tion to these benefits, the design was performed with the structural load paths were well-established and consideration of local materials and construction skill adequate capacities provided. Because the main span level. The bridge details were all considered in such is reliant on the counter- to promote ease of a away a balance of the pylon, a construction. co delicate balance exists. The • Complexity: The Puente structural capacity of the de la Unidad project pre- pylon must be considered sented many challenges due se in parallel with the ballast it to its complexity. Typically provides, and these two goalss the roadway geometry is th did not always work in the adjusted to accommodate ad same direction. The Puente the bridge, but the opposite th de la Unidad project is a good d example of an existing was done for this project. project The T complexities included bridge concept (cable-stay) used in an alternate way large openings in the pylon at grade to allow traf- to provide a striking visual appearance, and achieve fic flow, the introduction of a vertical curve to the the goal of providing a single support outside of the alignment of the bridge deck, variable cross-fall at the main riverbed. span along the pylon, and allowing for ramp connec- • Future Value to the Engineering Profes- tions on either side of the bridge. All challenges were sion: As indicated above, this project presents a successfully incorporated into the final design. good example how a complex project can be solved • Meeting and Exceeding Owner/Client by understanding the basic behavior and providing Needs: The primary achievement for the Puente de reliable load paths. The value of dedicating time la Unidad project was the delivery of a design under at the conceptual phase is reflected in this project. a very tight schedule. The design schedule was 9 Three locations on the bridge illustrate this. The first months, and the contractor selection was selected in is the transition from the force in the edge beams to advance of the final design completion. The bridge the pylon, the second is the resolution of axial loads construction was completed in 15 months, a time between the pylon and main span, and third the frame rarely achieved for this complex of structure. specially shaped spread footing to accommodate the The bridge was completed for $16.8 million, and was monotonic loads. These solutions are shown on the within 3% of estimated costs. following pages. ©2009 Copyright International Bridge Technologies, Inc. PUENTE DE LA UNIDAD Monterrey, Mexico INTERNATIONAL BRIDGE TECHNOLOGIES, INC. FOUNDATION, PYLON BASE, AND TRANSITION SPAN Excavation of Foundation Foundation Reinforcement Cage Starter Bars for Pylon Foundation Post-Tensioning F un Fo und dati dati tion on P Pos ostt-T Tensiio Tens ioni ning ing g Key Features • Soil was injection grouted for added strength. • Foundation was a spread footing and posttensioned in primary directions. • Spread footing dimensions were optimized for the monotonic loading. A trapezoidal plan area was designed with a wider toe at the front of the footing. Transition T Tr ansi siti iti tion on S Spa Span p n Fram pa F Frame rame e • 8000m3 (10500yd3) of concrete used for foundation. Mass concrete casting procedures implemented. • Large axial forces at edge beams need to be transferred to central pylon. Well-defined load path provided by central and diagonal beams. Flow Fl ow o off Forc F Forces orces es ©2009 Copyright International Bridge Technologies, Inc. PUENTE DE LA UNIDAD Monterrey, Mexico INTERNATIONAL BRIDGE TECHNOLOGIES, INC. MAIN PYLON Pylon Section Climbing Form Pylon Back Wall Post-Tensioning Pylon Elevation Completed Pylon Key Features • Pylon is hollow with a typical width of 5m (16.4ft), which tapers to 15m (49.2ft) from deck to foundation. The back wall of the pylon is post-tensioned. • Pylon inclination provides significant balance to main span forces. • Pylon and deck forces resolved at one location and distributed to the foundation by twin legs. • Pedestrian access permitted through pylon. • Pylon and span designed to allow for loss of back stays (i.e. terrorist attack.) ©2009 Copyright International Bridge Technologies, Inc. PUENTE DE LA UNIDAD Monterrey, Mexico INTERNATIONAL BRIDGE TECHNOLOGIES, INC. MAIN SPAN Main Span Section Main Span Section Construction Pre-cast Panel Placement Completed Bridge, Stay Anchors Key Features • Main Span cast in 12m (39.3ft) sections. Edge beams and steel beams cast in place, followed by pre-cast panels with CIP stitch. • In place of standard cantilever construction, a moving casting table was used. The table would launch to cast each segment and be supported on the river bed. The bridge geometry was evaluated on a real-time basis and adjusted for each new casting. • New in-line stay damper used to suppress cable vibrations. Completed Bridge, Elevation ©2009 Copyright International Bridge Technologies, Inc.