Project: Stawell Id 1 Taak Duur Begindatum Einddatum Execution 65,2 wkn vri 1-4-16 vri 30-6-17 2 landleveling 6 wkn vri 1-4-16 don 12-5-16 3 gridconnection 1 wk maa 15-8-16 vri 19-8-16 4 6 wkn vri 13-5-16 don 23-6-16 5 preparation of construction site, laydown area, service dirth roads, etc groundworks of the stormwater retention basin 6 wkn vri 24-6-16 don 4-8-16 6 foundations greenhouse and technical area 4 wkn maa 15-8-16 vri 9-9-16 7 8 wkn maa 15-8-16 vri 7-10-16 8 preparation and execution of the concrete slab for packing hall concrete slab curing 3 wkn maa 10-10-16 vri 28-10-16 9 concrete slab for HST 4 wkn maa 10-10-16 vri 4-11-16 10 HST floor curring 3 wkn maa 7-11-16 vri 25-11-16 11 Building/welding HST 8 wkn maa 28-11-16 vri 20-1-17 12 in the ground heating transport piping 3 wkn maa 12-9-16 vri 30-9-16 13 erection of greenhouse structure, aluminium and glazing electrical connection of gh vents 16 wkn maa 3-10-16 vri 20-1-17 2 wkn maa 9-1-17 vri 20-1-17 maa 31-10-16 vri 9-12-16 16 erection of structure and cladding of packing hall and 6 wkn technicall rooms placing boiler, manifold, possible chp etc 20 wkn maa 12-12-16 vri 28-4-17 17 in the ground piping in the irrigation room 4 wkn maa 12-12-16 vri 6-1-17 18 built the inside of the irrigation room 20 wkn maa 9-1-17 vri 26-5-17 19 maa 12-12-16 vri 28-4-17 maa 6-3-17 vri 23-6-17 21 make office and toilets change rooms inside packing 20 wkn hall coldstorage and sorting and packing machines inside 16 wkn the packing hall wall heating pipes 3 wkn maa 9-1-17 vri 27-1-17 22 in the ground irrigation pipes in the greenhouse 2 wkn maa 16-1-17 vri 27-1-17 23 growlights in the ground cabeling 1 wk maa 9-1-17 vri 13-1-17 24 screen endwall works 2 wkn maa 16-1-17 vri 27-1-17 25 sunscreen overhead wires and motors and axes 4 wkn maa 30-1-17 vri 24-2-17 26 all electrical works in gh 13 wkn maa 30-1-17 vri 28-4-17 27 final ground leveling inside gh 2 wkn maa 20-2-17 vri 3-3-17 28 mounting of AHU,s 8 wkn maa 6-2-17 vri 31-3-17 29 delevery of minitransformers 2 wkn maa 6-2-17 vri 17-2-17 30 pipeheating welding inside gh 4 wkn maa 27-2-17 vri 24-3-17 31 overhead cropwires 2 wkn maa 27-3-17 vri 7-4-17 32 concrete middle math 3 wkn maa 10-4-17 vri 28-4-17 33 curing middle path 2 wkn maa 1-5-17 vri 12-5-17 34 making and placing crop gutters 1 wk maa 15-5-17 vri 19-5-17 35 growlight fixtures 1 wk maa 22-5-17 vri 26-5-17 36 screencloth 1 wk maa 29-5-17 vri 2-6-17 37 ground covers and driplines 1 wk maa 5-6-17 vri 9-6-17 38 commisioning and testing 2 wkn maa 12-6-17 vri 23-6-17 39 planting 1 wk maa 26-6-17 vri 30-6-17 14 15 20 Project: Stawell Datum: don 25-2-16 Pagina: 1 Taak 2016 2017 1ste kwartaal 2de kwartaal 3de kwartaal 4de kwartaal 1ste kwartaal 2de kwartaal 3de kwartaal 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Mijlpaal Deelproject