Exterior Enclosure Commissioning: 1 NIBS Guideline 3-2012 ASTM E2813-12 The U.S. Green Building Council – Illinois Chapter is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 2 USGBC – ILLINOIS CHAPTER 3 Information to be added by USGBC-Illinois Staff member 1.5 Presenter Micheal Lough, AIA Copyright Materials This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of the presentation without written permission of Integral Consulting is prohibited. ©Integral Consulting 2012 4 Learning Objectives • The program shall provide learners with an outline of The Exterior Enclosure Technical Requirements for the Commissioning Process NIBS Guideline 3-2006, Building Enclosure Commissioning Process BECx • The program shall provide learners with an outline of Fundamental and Enhanced Building Enclosure Commissioning requirements per ASTM E2813-12, Standard Practice for Building Enclosure Commissioning • Learners shall understand what the Owners Project Requirements (OPR) written document should entail as part of the Pre-Design phase and the development of the Basis of Design (BOD) during the Design and Pre-Construction phases • LEED v.4, Building Design & Construction, EA Credit: Enhanced Commissioning, Option 2. Envelope Commissioning (2 points) 5 Why? • Problematic issues of enclosures which manifest themselves during construction and the quality of built enclosures are a frustration to owners and a reflection of the services provided by design teams. • Increased complexity and the drive for improved performance of building enclosures especially with regard to energy savings and other sustainability considerations. • LEED v.4 will offer two points for Building Enclosure Commissioning as an option to Enhanced Commissioning 6 Referenced Documents • ASHRAE Guideline 0-2005, The Commissioning Process [ASHRAE 0] • NIBS Guideline 3-2012, Building Enclosure Commissioning Process BECx [NIBS 3] • ASTM E2813-12, Standard Practice for Building Enclosure Commissioning [ASTM E2813] • U.S. Green Building Council LEED Reference Guide for Green Building Design and Construction, 2009 ed., Energy and Atmosphere Prerequisite 1 / Fundamental Commissioning of Building Energy Systems [LEED EAp1] • LEED Building Design & Construction draft v.4, Energy and Atmosphere EA Credit: Enhanced Commissioning, Option 2. Envelope Commissioning [LEED EA BECx] • International Green Construction Code – 2012 [IgCC] 7 Standards / Guidelines • All of the Referenced Documents were developed through the consensus process by groups of well qualified professionals • Guidelines -- describe general operating practices and procedures as a Best Practice • Standard Practice – defines specific sequences of operations which are requirements • LEED – Certification process – Green Building Certification Institute (GBCI) 8 ASHRAE Guideline 0-2005 The Commissioning Process [ASHRAE 0] • The American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) published a commissioning guideline in 1989, an updated version in 1996 which contained both general commissioning process requirements & HVAC technical requirements. • Guideline 0-2005, The Commissioning Process, only commissioning process and a platform for total building commissioning • The Commissioning Process is a quality-oriented process for achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria • The Commissioning Process begins at project inception and continues for the life of the facility 9 Participants • Owner – Owner’s Project Requirements (OPR) • Architect (Design Team) – Basis of Design (BOD) • Contractor – Executes OPR and BOD • Commissioning Authority designations: • CxA -- Commissioning Authority or Agent • BECxA – Building Enclosure Commissioning Authority • BES – Building Enclosure Specialist 10 Owner’s Project Requirements (OPR) Basis of Design (BOD) • NIBS Guideline 3-2012 – considers the performance objectives required by an Owner for the building enclosure, including: • control of moisture • condensation • heat flow • air flow • water vapor flow • noise • fire • vibrations • energy migration • light 11 Owner’s Project Requirements (OPR) Basis of Design (BOD) • NIBS Guideline 3-2012 Owner – continued • infrared radiation • ultraviolet radiation • structural performance • durability • resiliency • security • reliability • aesthetics • value • constructability • maintainability 12 • sustainability Pre-Design Phase Pre-Design Phase • Define Responsibilities, team members, Commissioning Authority –[ASHRAE 0] [NIBS 3] [ASTM E2813]; [LEED EAp1] • Kick-off Meeting – [NIBS 3] [ASTM E2813] • Owner’s Project Requirements (OPR) – Owner’s responsibility, BECxA provides Technical Assistance – [ASHRAE 0 - process] [NIBS 3 – detailed checklist] [ASTM E2813 – OPR Development Guideline]; [LEED EAp1 – Owner required to document] • Develop Scope and Budget for Commissioning Process – [NIBS 3 ASTM E2813] • Commissioning Plan – Includes roles and responsibilities of team members, communication protocols, communication processes, construction checklists, facility maintenance personnel training, issues / non-conformance log [ASHRAE 0 NIBS 3; LEED EAp1] 13 Design Phase Design Phase Schematic Design, Design Development, Construction Documents • Basis of Design Documents (BOD) – Prepared by Design Team submitted with the SD’s -- [ASHRAE 0 – process NIBS 3 – review by BECxA at SD, updated and review at DD and CD ASTM E2813 – BECxA review and provide technical assistance; LEED EAp1] • Technical Peer Reviews – SD review includes impact on the OPR – DD review of detailing, alternative building enclosure systems, plans and details for interface of the various enclosure systems, specifications, thermal analysis, advice on laboratory and filed mockups -- [NIBS 3 ASTM E2813] • LEED requires the CxA to review the OPR and BOD and requires at lease 1 commissioning design review prior to mid-construction documents – [LEED EAp1] • Construction Checklists – construction checklists which aid the installers by providing specific information on OPR for equipment and assemblies [ASHRAE 0] 14 Design Phase Design Phase Schematic Design, Design Development, Construction Documents • Commissioning Plan – Update and expand the commissioning plan to include systems and assemblies to be tested, expand commission plan to address Construction Phase and Occupancy and Operations phase activities -- [ASHRAE 0 NIBS 3 ASTM E2813; LEED EAp1] • BECx Reports – At the end of SD, DD and CD the BECx prepares a report reviewing the objectives of the phase and documenting whether or not the objectives had been met -- [NIBS 3] • Systems Manual – The system manual is one of the key documents of ASHRAE 0; it includes the OPR, BOD , record documents, specifications and submittals, O&M manuals, training materials and commissioning process report -- [ASHRAE 0] 15 Pre-Construction Phase 16 Pre-Construction Phase The only reference source which specifically designates a separate Pre-Construction Phase is ASTM E2813. Some of the other reference sources, ASHRAE 0 and NIBS 3, require participation in a pre-bid conference. • Pre-Bid Conference – Attend a Pre-Bid Conference to review BECx specification -- [ASTM E2813] • Evaluation of Enclosure – Review bidder requests and bids -- [ASTM E 2813] Construction Phase Construction Phase LEED EA BECx requires that the EA Prerequisite for Fundamental Commissioning also apply to the building’s thermal envelope in order to comply with the Envelope Commissioning credit requirements. The additional Enhanced Commissioning requirements to achieve the BECx points are specific to the Construction Phase and the Occupancy and Operations Phase. • Updates – Update OPR, commissioning plan, communication channels, etc. – [ASHRAE 0] • Review Submittals • a sampling strategy selecting 5% to 10% [ASHRAE 0] • A thorough review of submittals, including shop drawings, mockups, samples, schedules [NIBS 3], ASTM also requires “technical assistance” during the review of submittals [ASTM E 2813] • a review of contractor submittals [LEED EA BECx] 17 Construction Phase Construction Phase • Checklists – Verify the completion of the Construction Checklists -[ASHRAE 0 NIBS 3] • BECx Performance Testing Requirements -- ASHRAE 0, NIBS 3 and LEED EAp1 require testing of systems but they are not very specific. However, the ASTM E2813 Standard is very specific establishing two levels of testing, Fundamental and Enhanced (not linked to LEED Fundamental and Enhanced Commissioning) • Acoustic performance • Air leakage • Infrared imaging of roofing systems • Static and dynamic water penetration • Sealant 18 Construction Phase Construction Phase • Pre-Construction and Pre-Installation Meetings – Direct and substantive participation [ASTM E2813] • Site Visits – Conduct periodic site visits to verify and document compliance with the Contract Documents [ASHRAE 0 NIBS 3 ASTM E2813] • Verify Training – Specified training should be completed during the Construction Phase; generally by Substantial Completion [ASHRAE 0 LEED EA BECx] • Closeout Documents -- Systems Manual update: Record drawings, test procedures, updated OPR, updated BOD, updated commissioning plan, outline of “open” items, guideline for maintenance – [ASHRAE 0 NIBS 3 ASTM E2813] 19 Occupancy & Operations Phase Occupancy and Operations Phase ASHRAE 0 views the commissioning Process as extending through the contractual warranty period which is generally one year from Substantial Completion • On-going guidance, follow-up and warranty service – During the warranty period activities including following up on open items, warranty issues, contractor callbacks, training, continual updates of Systems Manual and other activities -- [ASHRAE 0 NIBS 3] • Occupancy and Operations Planning Meeting – BECxA attends a meeting with property management and building engineering team to review enclosure related issues -- [ASTM E2813] • Warranty Period Walk Through -- Conduct a walk through 10 months after substantial completion reviewing the building enclosure and operations of enclosure -- [NIBS 3 LEED EA BECx] • Final Commissioning Report – Prepare final project commissioning report – [ASHRAE 0 NIBS 3 LEED EA BECx] 20 Conclusion Why Owners and Architects should embrace Building Enclosure Commissioning 21 • The Extent to which Problematic Issues of Enclosures Manifest themselves during Construction and during the Occupancy and Operations phase • The increased complexity and the drive for improved performance of building enclosures especially with regard to energy savings and other sustainability considerations Is Building Enclosure Commissioning going to gain Traction? Conclusion Review: • ASHRAE – first commissioning guideline in 1989; ASHRAE 0-2005 • NIBS 3 – 2006; 2012 • ASTM E2813-12 (April) • IgCC – 2012 – includes commissioning for HVAC • LEED v.4 in 2013 • LEED v.4 – 2 points for Building Enclosure Option of Enhanced Commissioning • Recognition of the need • Key – Value Added 22 Conclusion Value Added The key is to craft a commissioning service appropriate to the project utilizing the sources referenced in this presentation • LEED v.4 – establishes a reasonable minimum level of services • OPR and BOD • 1 Peer Review at mid-construction documents • Submittal review • Close-out documents; Systems Manual and training • Verify testing • 10 month walk-through • On-going Commissioning Plan 23 Qualifications: Conclusion Building Enclosure Commissioning Agent (BECxA) Building Enclosure Specialist (BES) Currently there are no established certification programs in place for BECxA or BES • University of Wisconsin-Madison College of Engineering Department of Engineering Professional Development – October 2012 first part of a new Certification program in development – second part in February 2013 – unclear of status of development • The International Accreditation Service, a subsidiary of the International Code Council – forming a certification committee • ASTM Committee E06 on Performance of Buildings is also forming a certification committee to address BECxA and BES 24 Qualifications: Conclusion Building Enclosure Commissioning Agent (BECxA) University of Wisconsin – Established Certification Program • CxAP: Commissioning Process Authority Professional • CxM: Commissioning Process Manager • CxTS: Commissioning Process Technical Service Provider • GCxP: Green Commissioning Process Provider Commissioning Agent – reflect ASHRAE 0 “The Commissioning Process”; management and administrative 25 Qualifications: Conclusion Building Enclosure Specialist (BES) An opinion of minimum requirements • Project Experience: 10 years as an Architect, contractor or related professional where they have direct hands-on experience in all phases of the design and construction processes • Education: College degree in architecture or construction management • Active professional affiliations: • Demonstrable technical expertise: Qualifying exams [CSI CDT/CCS or LEED AP]; building science, testing, etc. • Continuing education: Similar to AIA CES program of learning units 26 53 West Jackson Boulevard Suite 1020 Chicago, Illinois 60604 T 312.929.4146 M 708.738.1996 mlough@integral-consulting.net Questions? Thank you for your time! 27