For low to very tall applications, structural tile, or joist-based decks.
Height Range: 1-3/4”” to 40”.
Threaded for fine adjustment.
Corrects slopes from 1% to 10%.
Tile Spacer Widths of 1/8”, 1/4”, 3/8”.
Top slope correction for 1-3/4” to 40”
Supports 3,500 lbs.
Bottom slope correction for 5” to 40”
Handbook, VersiJack®Pedestal System 48-00404-00A
Components of the VersiJack® System
Low Height Pedestals
Product
Description
EVJ-0000 VersiJack® > adjusts from 1-3/4” to 2-1/8”.
EVJ-000 VersiJack® > adjusts from 2-1/4” to 3”.
EVJ-00 VersiJack® > adjusts from 3-1/8” to 4-5/8”.
Tall Height Pedestals
Product
Description
EVJ-0 VersiJack® > adjusts from 4-7/8” to 7-7/8”.
EVJ-1 VersiJack® > adjusts from 8” to 11”.
EVJ-2 VersiJack® > adjusts from 11-1/2” to 17-1/2”.
EVJ-3 VersiJack® > adjusts from 14-1/4” to 20-5/8””.
EVJ-4 VersiJack® > adjusts from 18” to 27”.
EVJ-5 VersiJack® > adjusts from 20-3/4” to 30-3/8””.
EVJ-6 VersiJack® > adjusts from 24-5/8” to 36-3/4””.
EVJ-7 VersiJack® > adjusts from 27” to 40”.
Slope Corrector System
Product
Description
EA-SCT Top Slope Corrector
> Corrects slopes from 1% to 5% in 1% increments.
> Can be used on all height ranges.
> Combine with bottom slope corrector for slopes between 6% - 10%.
EVJ-SCB Bottom Slope Corrector
> Corrects slopes from 1% to 5% in 1% increments.
> Use when height range is between 5-1/8” to 40” tall, or when roof slope exceeds 5%.
> Combine with top slope corrector for slopes between 6% - 10%.
> Works with EVJ-0, -1, -2, -3, -4, -5, -6, and -7.
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
2
Accessories
Product
Description
EVJ-TT Turning Tool
> Designed for the VersiJack system.
> Attaches to standard drill with 1/2” chuck.
> Raises or lowers taller pedestals more quickly than turning by hand.
> Huge labor savings for tall pedestals.
EA-BH Beam Holder
> Supports joists from 1-1/2” to 3-1/2” on top of pedestal
> Works with single or twinned 2x4, 2x6, or 2x8 joists.
EA-TF01 Tile Fastener
> Fixes in place the corners of structural hardwood tiles. Requires that tiles have a 1/4” (6mm) corner slot.
EA-PS4 Spacer for Pavers with 1/8” Wide Spacer Tabs
> Snap off tabs for edge and corner locations.
EA-PS6 1/4” Wide Spacer Tabs
> Snap off tabs for edge and corner locations.
EA-PS10 3/8” Wide Spacer Tabs
> Snap off tabs for edge and corner locations.
EA-01 1mm Shims
> Can be used as a whole, two halves, or four quarters on top of pedestal.
EA-02 2mm Shims
> Can be used as a whole, two halves, or four quarters on top of pedestal.
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
3
VersiJack® Checklist
Type of Project
Item
Notes
Decks
w/Joist
System
Structural
Hardwood
Tiles
Structural
Porcelain
Tiles
Slope Correction
Stone &
Concrete
Pavers
1% - 5%
w/Top
Corrector
1% - 5%
w/Bottom
Corrector
6% - 10%
w/Top &
Bottom
Correctors
Pedestals - Low Range
EVJ-0000, -000, -00
C H O O S E
A N Y
S I Z E
√
C H O O S E
A N Y
S I Z E
√
Pedestals - High Range
EVJ -0, -1, -2, -3, -4, -5, -6, -7
√
√
Slope System
EA-SCT (Top Corrector)
√
EVJ-SCB (Bottom Corrector)
√
√
√
√
√
√
O P T I O N A L
√
Accessories
EA-BH (Beam Holder)
EA-TF01 (Tile Fastener)
√
√
EA-PS4 (1/8” Spacer Tab)
EA-PS6 (1/4” Spacer Tab)
EA-PS10 (3/8” Spacer Tab)
√
CHOOSE
ANY
SIZE
EA-01 - 1mm Shims
EA-02 - 2mm Shims
Handbook, VersiJack®Pedestal System 48-00404-00A
CHOOSE
ANY
SIZE
√
√
√
VersiJack®Pedestal System
4
VersiJack® Height Computation Chart
Low Range
Item No.
Pedestal
Pedestal
Pedestal
EA-SCT
Top Slope Corrector
EA-SCT
Top Slope Corrector
+
+
+
+
EA-PS
Paver Spacer
EA-BH Beam Holder
EVJ-0000
1-3/4” to 2-1/8”
1-3/4 to 2-1/4”
2-1/8” to 2-1/2”
EVJ-000
2-1/4” to 3”
2-1/4” to 3-1/8””
2-1/2” to 3-3/8”
EVJ-00
3-1/8” to 4-5/8”
3-1/4” to 4-7/8”
3-1/2” to 5-1/8”
High Range
Item No.
Pedestal
Pedestal
Pedestal
Pedestal
Pedestal
EVJ-SCB
Bottom Slope
Corrector
EVJ-SCB
Bottom Slope
Corrector
EA-SCT
Top Slope
Corrector
EA-SCT
Top Slope
Corrector
+
+
+
EA-BH Beam
Holder
+
+
EA-PS
(adds no height)
+
+
EA-BH Beam
Holder
Pedestal
Pedestal
+
EVJ-SCB
Bottom Slope
Corrector
+
+
EVJ-SCB
Bottom Slope
Corrector
+
EA-SCT
Top Slope
Corrector
EA-SCT
Top Slope
Corrector
EA-PS
(adds no height)
EA-BH Beam
Holder
+
+
EVJ-0
4-7/8” to 7-7/8”
5-1/8” to 8-3/8”
5-1/4” to 8-5/8”
5” to 8-1/8”
5-1/4” to 8-3/8”
5-1/4” to 8-1/2”
5-3/8” to 8-3/4”
EVJ-1
8” to 11”
8-1/4” to 11-1/2”
8-3/8” to 11-3/4”
8-1/8” to 11-3/8”
8-3/8” to 11”
8-3/8” to 11-5/8”
8-1/2” to 11-7/8”
EVJ-2
11-1/2” to 17-1/2”
11-5/8” to 18”
11-7/8” to 18-1/4”
11-5/8” to 17-3/4”
11-3/4” to 18”
11-3/4” to 18-1/8”
12” to 18-3/8”
EVJ-3
14-1/4”” to 20-5/8”
14-1/2” to 21-1/8”
14-5/8” to 21-3/8”
14-3/8” to 21”
14-5/8” to 21-1/4”
14-5/8” to 21-1/4”
14-3/4” to 21-1/2”
EVJ-4
18” to 27”
18-1/4” to 27-5/8”
18-3/8” to 27-7/8”
18” to 27-3/8”
18-3/8” to 27-5/8”
18-5/8” to 27-3/4”
18-1/2” to 28”
EVJ-5
20-3/4” to 30-3/8”
21” to 30-3/4”
21-1/8” to 31-1/8”
20-7/8” to 30-3/4”
21-1/8” to 30-7/8”
21-1/8” to 30-7/8”
21-1/4” to 31-1/4”
EVJ-6
24-5/8” to 36-3/4”
24-3/4” to 37-1/4”
25” to 37-1/2”
24-3/4” to 37”
24-7/8” to 37-1/4”
24-7/8” to 37-3/8”
25-1/8” to 37-5/8”
EVJ-7
27” to 40”
27-1/4” to 40-1/2”
27-1/2” to 40-3/4”
27-1/8” to 40-3/8”
27-3/8” to 47-5/8”
27-3/8” to 40-5/8”
27-5/8” to 40-7/8”
Accessory Heights
EA-SCT Top Slope Corrector
Adds approx. 1/8” height
EVJ-SCB Bottom Slope Corrector
Adds approx. 3/8” height
EA-BH Beam Holder
Adds approx. 1/4” height
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
5
VersiJack® Building Hints
Decks (Joist System)
• For design purposes, the total combined height of an EVJ-0000 (minimum height)
+ EA-SCT + EA-BH + 2x4” joist = 5-5/8.” This will be the minimum height to plan for at the
project’s starting point such as a door threshold or entryway.
• EA-BH supports joists from 1-1/2” to 3-1/2” wide on top of pedestal. Works with single or
twinned 2x4, 2x6, or 2x8 joists.
• Pedestal spacing with different sized joists:
Joist
Spacing
2x4” Joist
Pedestal every 24” max.
2x6” Joist
Pedestal every 30” max.
2x8” Joist
Pedestal every 36” max.
Twinned 2x4” Joist
Pedestal every 48” max.
5-5/8”
• Drive fastening screw through tabs of support to fasten joist in place.
Structural Hardwood Tiles
• Place pedestal along edge under tile after you snap off x2 aligned spacer tabs.
Corner pedestals will typically not require spacer tabs.
• Be sure tabs fit snugly up and into space between 2 boards.
• Structural hardwood tiles are typically light weight and may rock if not fastened.
• Use the EA-TF01 to fasten down corners of each tile.
* See “Wood Tile Fastener Installation” (page 10) for additional instruction.
Natural Stone and Hydrapressed Concrete Pavers
• If using a non-igneous sedimentary stone (e.g., sandstone), ensure it has appropriate thickness
to avoid failure.
• For natural stone, order extra 1mm (EA-01) and 2mm (EA-02) shims to create even surface due
to unequal tolerances of thicknesses.
• Be sure your concrete paver is “hydrapressed” type.
• Always place a 2mm shim on top of each pedestal.
• Never cut more than 1/3 of width or less than 8” wide for perimeter cuts.
Structural Porcelain Tile (3/4” thick)
• Always place a 2mm shim on top of each pedestal.
• Never cut more than 1/3 of width, or less than 8” wide or perimeter cuts.
Stone, Concrete and Porcelain Tile
• Use a “slab grabber” tool to lift up tiles.
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
6
Correcting Slopes 1 - 5% > Using the EA-SCT Top Slope Corrector
EA-SCT
Up-Slope
Match the open
arrow and slope %
number to the
on the VersiJack
pedestal, then press
together to secure.
+
=
Rotate pedestal so
that the up slope
arrow on the EASCT is oriented in
the same direction
as the roof’s
up- slope.
Down-Slope
VersiJack Pedestal
Correcting Slopes 1 - 5% > Using the EVJ-SCB Bottom Slope Corrector
For use on EVJ-0, -1, -2, -3, -4, -5, -6, or -7 pedestals only.
Match the on
the EVJ-SCB with
the desired slope
% number on the
VersiJack base.
Lift pedestal up and
rotate to desired
slope correction.
EVJ Pedestal
Rotate pedestal and
slope corrector so
“down slope” and
the
orientate
with roof’s down
slope.
=
+
Down-Slope
EVJ-SCB
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
7
Correcting Slopes 6 - 10% > Example: Creating an 8% slope
Step One
Always combine
pedestal and EVJSCB Bottom Slope
corrector to make
5% correction.
Connect the 5%
indicator on the
pedestal to the
indicator on the
EVJ-SCB Bottom
Slope Corrector.
+
=
Set at 5%.
Step Two
Connect the EA-SCT
Top Slope Connector
to the top of the
existing pedestal
and EVJ-SCB combination.
Set EA-SCT at 3%.
=
Connect the 3%
indicator on the
Top Slope Corrector
to the
indicator on the
pedestal base.
(3% + 5% = 8%)
Step Three
Up-Slope
Rotate the pedestal
until “Downslope”
indicator on bottom
slope corrector is
oriented with the
roof’s bottom down
slope.
Down-Slope
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
8
Spacer Tabs
Firmly connect
spacer tab-set in
the hole on top of
pedestal.
+
=
Rotate tab in any
direction to achieve
desired orientation.
Beam Holder for Joist-Based Decking Platforms
Deckboards
Joist
Joist
Spacing
2x4” Joist
Pedestal every 24” max.
2x6” Joist
Pedestal every 30” max.
2x8” Joist
Pedestal every 36” max.
Twinned 2x4” Joist
Pedestal every 48” max.
+
+
EA-BH Beam Holder
+
VersiJack Pedestal
Handbook, VersiJack®Pedestal System 48-00404-00A
=
VersiJack®Pedestal System
9
Wood Tile Fastener Installation > Four Steps
Note: Wood tile fastener is designed to be used with pavers that have a 1/4” (6mm) edge groove.
The tile fastener is designed to sit atop the VersiJack pedestal without adding any additional height to the
pedestal assembly. When using the tile fastener, pavers will be spaced 1/4” (min. 0.2”) apart.
Step 1: Placing Tile Fasteners
If the tile lock is not already free
to move, loosen the screw that
holds it secure until the lock can
slide from side-to-side. Place
the tile fastener assembly onto
the pedestal and press into place.
Shift the lock to one side to allow
tiles to be placed.
Slide lock to one side.
Step 2: Place Tiles
Place the tiles upon the pedestal.
With two tiles placed, shift the
lock into the notches of the tiles
to allow placement of additional
tiles. Place the remaining tiles
onto the pedestal.
Tiles placed atop the spacer tab.
Shift lock into placed tiles.
Note: If the height of the pedestal support needs adjusting, it can be adjusted with the tiles in place and the spacer tab will
pivot independent of the pedestals allowing the tiles to stay in place.
Step 3: Secure Lock
With all four tiles in place,
shift the lock until it is
centered on the pedestal. It
may be necessary to use a
screwdriver or other tool to
access the lock between the
tiles. With the lock centered,
tighten the screw until the
lock is secure and will not
move.
Secured lock.
Handbook, VersiJack®Pedestal System 48-00404-00A
Step 4: Removal
Whether one or all tiles need
to be removed, the lock must
be unlocked. To unlock any
tile, the process is the reverse
of the locking procedure.
Loosen the screw enough to
allow the lock to slide from
side-to-side. Using a tool,
slide the lock away from the
tile to be removed. Do this
on all corners or where a
fastener secures the tile. With
all locks moved, the tile can be
removed.
VersiJack®Pedestal System
10
Adjusting Pedestal Height > Five Steps
Step 1:
Hold base.
Step 3:
Rotate top section
clockwise to reduce
height.
Step 2:
Loosen locking ring.
Step 4:
Rotate top section
counter-clockwise
(as shown) to
increase height.
Step 5:
Once height is
adjusted, tighten
locking ring to
secure.
Shims > Using the EA-01, EA-02 1mm and 2mm Shims
Whole
Always use a 2mm
FA-02 whole shim
underneath stone
pavers, concrete
pavers, and structural porcelain tiles.
Half
Quarter
Stacked
EA-01 and EA-02
can be used
together to create
level surfaces when
using pavers of varying thicknesses.
Handbook, VersiJack®Pedestal System 48-00404-00A
VersiJack®Pedestal System
11
Download