Petrofac Gas Dehydration SECTION 13 SHUTDOWN SYSTEMS AND ESDV TESTING 1 Introduction 2 Fire and Gas Detection Systems 3 4 2.1 Fire and Gas/ESD Interfaces 2.2 Fire Detection 2.3 Gas Detection Emergency Shutdown Levels 3.1 Level 1 – Unit Control/Unit Shutdown 3.2 Level 2 – Process Shutdown/Surface Platform Shutdown (SPS) 3.3 Level 3 – Process Shutdown with Depressurisation/Blowdown 3.4 Level 4 – Power Outage/Total Platform Shutdown (TPS) 3.5 High Integrity Protection Systems Emergency Shutdown Valve Testing 4.1 General Requirement 4.2 Leakage Acceptance Criteria 4.3 Records Table 12.1 Colour Code Figures 13.1 Overall Platform Shutdown Block Diagram 13.2 ESD Block Diagram 13.3 Smoke Detector 13.4 Crude Export 13.5 Emergency Pipeline Valve Regulations 1989 3-monthly Inspection Record 13.6 Emergency Pipeline Valve Regulations 1989 6-monthly Partial Closure Test Record 13.7 Emergency Pipeline Valve Regulations 1989 6-monthly Full Closure Test Record Training Services Page 1 of 11 © Petrofac 2010 Petrofac Gas Dehydration 1 INTRODUCTION In the event of an emergency arising on an offshore installation, emergency shutdown (ESD) systems are installed in order to protect personnel, plant and equipment. The ESD system is designed to provide a rapid means of: • Shutting down, isolating and depressurising hydrocarbon processing systems • Shutting down non-essential utility systems • Isolating the platform both from the reservoir and from import/export pipelines Subsequent actions following ESD situations are to alert personnel via the public address system, and to provide automatic startup of platform protection equipment such as firepumps. Once an ESD sequence has been initiated and completed, the platform will be in as safe a condition as possible and essential systems will be available so that personnel can tackle the emergency adequately. The platform ESD system normally interfaces with the following equipment in order to bring it to a safe and steady condition swiftly and effectively: 2 • Fire and gas system • Instrument marshalling cabinet (IMC) • Platform control system (PCS) • Subsea control system (SCS) • Computer aided process operations (CAPO) FIRE AND GAS DETECTION SYSTEMS Fixed fire and gas detection systems are installed on offshore installations in order to provide continuous automatic monitoring of the platform work areas, process/utility systems, accommodation and other areas. They are designed to indicate both audibly and visually, the presence of: • A fire in any of the monitored areas on the installation • An accumulation of flammable gas in any part of the installation monitored by the system The system will indicate the presence of fire and/or gas both locally at satellite panels and centrally at the main point of control, typically the central control room. Training Services Page 2 of 11 © Petrofac 2010 Petrofac Gas Dehydration 2.1 Fire and Gas/ESD Interfaces As well as triggering protection systems such as water sprinklers or deluge systems, an alarm condition arising from confirmed fire or high gas in the detection system is connected to the platform ESD system, and therefore initiates the necessary level of shutdown required. Typical examples of shutdown system hierarchy are shown in Figures 13.1 and 13.2 which show the levels at which fire and gas actions tie into the associated ESD systems. In both cases it can be seen that they connect at the higher levels of shutdown. Normally fire and gas/ESD actions stop and depressurise the oil and gas process plants, close the downhole safety valves on the various wells, and isolate flowlines which feed in from external sources. 2.2 Fire Detection Fire detectors are installed to provide the necessary alarms upon detection of flame, heat or smoke. Various types of detectors are used, among them being temperature sensing elements (TSE) or infrared (IR) flame detectors. Thermal detectors are colour coded (refer to the Table 13.1) to indicate the temperature at which they operate eg 60°C, 140°F - yellow, up to 385°C, 725°F -black dot on orange. Should a fire occur in an area, the heat generated causes a set of contacts to close due to differing coefficients of linear expansion. Table 13.1 Colour Code Temperature Settings Colour Code 60°C 140°F Yellow 88°C 190°F White 108°C 225°F Black Dot on White 163°C 325°F Red 232°C 450°F Green 316°C 600°F Orange 385°C 725°F Black Dot on Orange Training Services Page 3 of 11 © Petrofac 2010 Petrofac Gas Dehydration Smoke detectors use ionisation of the air in inner and outer chambers to detect smoke (refer to Figure 13.3). The outer sampling chamber is open to the atmosphere, allowing smoke to enter, and is separated from the inner reference chamber by a perforated intermediate electrode. The air in both chambers is ionised by alpha radiation from a radioactive source mounted within the inner chamber. Under normal conditions ie “no smoke”, a regulated voltage causes a small current to pass through the ionised air and an electrode is charged to a balanced potential by the ionisation current. When smoke enters the chambers, a low level of ionisation is achieved, resulting in a reduced current flow which leads to a change in the balanced potential at the electrode, triggering detection. An example of a smoke detector is shown in Figure 13.3. 2.3 Gas Detection Gas detection systems are designed to give an alarm and initiate protective action when gases exist in dangerous concentrations in various areas of the installation. Detectors located at strategic locations, sense the level of gas concentration and transmit a corresponding signal to dedicated control modules located on the fire and gas panels in the control rooms. Control modules normally have two alarm levels, set at percentages of the lower explosive limit (LEL), typically 20% and 60%. 100% LEL is the point at which there is sufficient gas in a mixture of gas and air to support combustion. NB Gas detectors are usually distributed at the following locations: • In hazardous areas where there is a potential source of gas leak • Non-hazardous areas (no potential source of gas leak) but where gas could accumulate through pressurisation failure • Ventilation inlet and outlet ducts • Gas turbine enclosures and void areas under gas compressors etc As the concentration of gas in an area increases it is sensed by the detector which consists of a pair of sensing elements, one of which is rendered insensitive to gas (the reference element). When exposed to flammable gas the sensing element produces heat, raising its temperature and electrical resistance. Both elements are connected to a Wheatstone bridge circuit, which in turn generates the alarm signal. The reference element provides automatic compensation for changes in ambient temperature, humidity and pressure. Training Services Page 4 of 11 © Petrofac 2010 Petrofac Gas Dehydration 3 EMERGENCY SHUTDOWN LEVELS An ESD system is primarily designed to isolate the overall process system into sections, and depending on the level of shutdown, may cause depressurisation of the process plant. Shutdown of some of the utility systems may also be initiated. Process system isolation is effected by closure of block valves located at strategic positions within the process plants primarily around significant equipment items. ESD system logic is normally distributed on a modular basis usually from panels located within respective module local equipment rooms (LERs). A central panel(s) detailing all plant status is located in the central control room to enable monitoring/control from a central source. Typically there are up to five levels of shutdown classified as follows: 3.1 Level 1 - Unit Control/Unit Shutdown A unit shutdown can be effected either manually or automatically by process detectors mounted in the field. This level will shut down specific items or units if abnormal conditions such as pressure, temperature and flow are detected local to each item. Depending upon which unit is affected there can be a knock-on or domino effect extending to other sections of the plant. 3.2 Level 2 - Process Shutdown/Surface Platform Shutdown (SPS) A process shutdown can be initiated manually or automatically as a result of abnormal conditions or loss of essential specific units. It may also be due to abnormal conditions in systems that are not directly part of the process system, such as instrument air or fuel supply. A process shutdown stops all oil and gas production and isolates the systems into sections which remain at operating pressure - sometimes referred to as a stop and hold. Wells are shut in, pumps and compressors are stopped. Usually utilities are unaffected, but where turbines for example are running on fuel gas, they would switch over to diesel fuel. A surface platform shutdown is initiated typically by the following actions: Training Services Page 5 of 11 © Petrofac 2010 Petrofac Gas Dehydration • Confirmed fire or gas • Manual pushbuttons • Loss of ac power • High levels in separator or flare drums • Low instrument air pressure • Wellhead fusible loop • Manual shutdown pushbuttons which are located installation at strategic points on the various levels around the The wellhead fusible loop arrangement comprises a flexible tubing manifold which is looped around the wellhead area and charged with air. A pressure switch will activate the shutdown upon detecting low pressure. In the event of a fire burning through the pressurised loop the low pressure trip acts as a backup signal to the fire and gas system. 3.3 Level 3 - Process Shutdown with Depressurisation/Blowdown This level of shutdown can be initiated: • Manually from pushbuttons located at strategic locations • Automatically from a higher level of shutdown or • Usually by an input from the fire and gas protection system A “trip and depressure” stops all gas and oil production, isolates the process system into sections and then automatically depressurises them to flare. Vessels will depressurise at differing controlled rates depending on the product that they contain and the temperature and pressures at which they operate. Flare systems are designed to accept depressurisation of the entire process system simultaneously. Depending on where the fire or gas is detected, riser isolation valves and/or subsea isolation valves may be directed to close. In certain situations it may be necessary to halt or delay the blowdown action, for example if the flare system was damaged. Therefore on some installations a blowdown cancel facility exists which allows a 15 minute delay once it has been initiated. During this time blowdown is inoperative unless overridden by a manual action or by confirmed fire in the process area, in which case the blowdown is operated immediately. Use of such a facility obviously requires careful assessment of the situation before initiation. Training Services Page 6 of 11 © Petrofac 2010 Petrofac Gas Dehydration 3.4 Level 4 - Power Outage/Total Platform Shutdown (TPS) This level of shutdown is typically initiated either manually or automatically by a total loss of power. This level of shutdown will stop main and emergency power generation, isolate all power distribution (other than that required for post-level operations) and initiate the lower levels of shutdown. TPS can be initiated by manual pushbuttons, again typically located as follows: • Central control room • OIM’s lifeboat • Helideck Upon initiation, the system activates various shutdown functions via the hierarchical structure of the SPS and US functions. This is the highest level of shutdown and will shut down all items of equipment except the emergency generator. TPS level allows a permissive to the uninterruptible power supply (UPS) shutdown. UPS shutdown pushbuttons are normally located in the same areas as the TPS pushbuttons. The action of initiating a UPS shutdown will isolate all UPS batteries and shut down the emergency generator at the same time. 3.5 High Integrity Protection Systems High integrity protection systems (HIPS) provide an alternative (electronic) means of protection and act as a backup to the main ESD system. They use independent process sensors and pilot solenoid valves in order to drive final control elements. Normally HIPS employ triplicated field devices to sense extreme out of limit process conditions using “two-out-of-three” (2OO3) voting solid state logic circuitry. HIPS solid state circuitry provides high-speed response between field input and output signals in the range of 100 milliseconds. An example of using HIPS for both high and low pressure protection on a typical crude oil export system can be seen in Figure 13.4. Training Services Page 7 of 11 © Petrofac 2010 Petrofac Gas Dehydration 4 EMERGENCY SHUTDOWN VALVE TESTING 4.1 General Requirement The essence of the Emergency Pipeline Valve Regulations SI 1989 1029 is the requirement to ensure that an ESDV is installed in the optimum location on all pipeline risers that have internal diameters 40mm and above, and achieve maximum reliability. Thus the ESDV location, design, procurement, testing, inspection, maintenance and operation should ensure that the ESDV will at all times operate on demand or fail-safe close, so minimising the possibility of an uncontrolled release of the pipeline inventory inboard of the ESDV. Once closed the ESDV should remain closed until the safety of the platform is assured and the control system is operated to open the valve. ESDVs should be capable of stopping the flow of substance within the pipeline, disregarding any minor leakage past the ESDV which cannot represent a threat to safety. 4.2 ESDV System Failures ESDV reliability is demonstrated by frequent and successful testing. Any test failure is serious as it indicates that, at some time prior to the failed test, life may have been put at risk. If at any time the ESDV is unable to close, the pipeline should not be operated until the fault has been rectified. 4.3 Multiple ESDVs The ESDV must be located above the highest wave crest which may reasonably be anticipated - such that the distance between the bottom of the riser and the ESDV is minimised. Thus where owners propose the use of two or more ESDVs, only one ESDV can fulfil the above requirement and so falls within the scope of SI 1989/1029. This ESDV is therefore considered as the primary ESDV. 4.4 ESDV Types ESDVs should be rapid acting isolation valves suitable for remote and local operation. ESDVs should be capable of closing against maximum differential pipeline pressure and under maximum flow conditions. The ESDVs should, in the case of piggable pipeline systems, also be piggable and therefore ball or gate valves will be suitable types. Choice of ESDV type should primarily reflect the need to achieve both maximum reliability and rapid controlled closure. ESDV selection should also consider valve characteristics such as leak tightness and maintainability. ESDVs should be matched to the actuator such that the operator can demonstrate that the actuator, drive train, and valve stem are adequately sized so as to close the ESDV under all foreseeable operating conditions. Training Services Page 8 of 11 © Petrofac 2010 Petrofac Gas Dehydration 4.5 Valve Operation 4.5.1 Local Closure Regulations require in effect that the ESDV is capable of local closure. This capability is intended to allow immediate valve closure by a person who sees a hazard which may not be detected and/or transmitted by instrumentation to the control room or ESD system, or where detection may not be fast enough. 4.5.2 ESDV Reopening Regulations only permit ESDVs to be reopened, once operated, if the reason for the ESDV operation has been established to the satisfaction of the Offshore Installation Manager (OIM) and he has authorised its reopening. This requirement does not extend to reopening after closing for testing purposes. With the sole exception of testing, ESDVs should only be used for blocking flow. They shall not be used for controlling flow during precommissioning, commissioning, decommissioning, and routine pigging operations. After an ESDV has closed, either via the ESD system or the local control panel, the OIM should ensure that the Manager of every other Offshore Installation to which the pipeline is connected and the pipeline control centre is notified of the ESDV closure. The ESDV shall not be reopened until the reasons for closure have been established to the satisfaction of the OIM and until every other OIM has been notified. 4.6 Inspection and Testing The inspection and testing requirements are designed to demonstrate that the required reliability is being achieved. 4.6.1 Inspection Regulations require that at intervals not exceeding 3 months, valves and actuators shall be subject to an inspection for the purpose of identifying external leaks, external damage, and external corrosion. Each inspection record shall be signed by the inspection personnel and countersigned by the OIM or a person nominated by him for such purposes. The person should be a senior member of staff. A typical record sheet is shown in Figure 13.5. Training Services Page 9 of 11 © Petrofac 2010 Petrofac Gas Dehydration 4.6.2 Testing The testing philosophy reflects the importance of demonstrating that the ESDV is capable of fully closing. For this, it is not considered essential that full closures are required for every test as generally the loads to initiate movement of the ball (or gate) are higher than those required to continue its closure. Thus regulations require a minimum of two partial closures per year (not exceeding 6 month intervals) and a full closure test to be performed not less than 2 months or more than 4 months after each partial closure test. Regulation 5 requires that the ESDV should always be capable of blocking flow. To demonstrate this the operator should consider conducting a seal leak test at least once a year. The seal leak test will require the ESDV to be fully closed and the pressure on the inboard side of the valve to be completely vented. All tests should be subject to operator approved procedures and during the test period all precautions should be taken to reduce any hazards to a minimum, including conducting the test as quickly and as safely as possible. 4.6.3 Partial Closure Tests Refer to Figure 13.6 Regulations require that partial closure/reopening tests are conducted by persons standing by the ESDV, ie using the local control panel. The extent of partial closure should be such that the ESDV movement is clearly visible. 4.6.4 Full Closure Tests Refer to Figure 13.7 Regulations require that full closure/reopening tests are completed using the Offshore Installation ESD system. During such tests it is recommended that the performance of the ESDV actuator and control system is demonstrated; eg time to close, time to open, differential pressure and torque/power levels to actuate the ESDV. On at least alternate full closures, it is recommended that an internal seal leak test is also conducted. A differential pressure should be applied across the ESDV equal to the prevailing pipeline operating pressure, by depressurisation of the topside pipework inboard of the ESDV. For liquid lines measurement of flowrates will be an acceptable method of leak rate detection. For gas lines measurement of pressure changes will suffice. Training Services Page 10 of 11 © Petrofac 2010 Petrofac Gas Dehydration 4.6.5 Failure to Close In the event of a full closure test failure, or if it is not safe to conduct a full closure test, then the pipeline should not be operated until the fault has been rectified. 4.7 Leakage Acceptance Criteria 4.7.1 Internal Body Seal Leakage The following maximum leakage rates are suggested: • Oil pipelines - 6kg/minute • Gas pipelines - 1 standard m3/minute Leakage rates in excess of the above criteria are considered to contravene Regulation 5(1). In such an event action should be taken which would result in: • Altering the pipeline pressure until the allowable leakage rates are not exceeded, or • Non-operation of the pipeline until the ESDV is repaired 4.7.2 External Leakage Regulation 8(1) requires the ESDV, the actuator, and accumulators to be inspected for external leakage, at intervals not exceeding 3 months. Leakage from ESDVs should only be tolerated when assessed as being insignificant. Where leakage from an actuator and/or accumulators compromise the failsafe closure of the ESDV they should immediately be repaired. 4.8 Records Under Regulation 8(4) a copy of the records and associated documents must be kept on the offshore installation for a minimum of 2 years from the date on which the event associated with the record occurred. A copy must also be maintained for a minimum of 5 years at a principal place of business in the United Kingdom of the owner of the pipeline. All records and documents should be preserved in a manner which prevents their deterioration and provides ease of access. Training Services Page 11 of 11 © Petrofac 2010 Petrofac Training Services © Petrofac 2010 SECTION 13 SHUTDOWN SYSTEMS AND ESDV TESTING Figures 13.1 Process and Fire/Gas 13.2 ESD Cause and Effects Charts 13.3 ESD Block Diagram 13.3b Ionised Smoke Detectors 13.4 Gas Export Pipeline © Petrofac Training Services / June 2010 Production Operations Figure 13.1a © Petrofac Training Services / June 2010 Fire and Gas Cause and Effects Chart Production Operations Typical Process Cause and Effects Chart Fig 13.1b © Petrofac Training Services / June 2010 Typical Process and Fire/Gas Cause and Effects Char Level 4 Abandon Platform Pushbuttons at Lifeboats and Helideck Level 3 Fire and Gas Shutdown Level 2 Surface Process Shutdown Level 1 Partial Process Shutdown Fig 13.2 Typical ESD Levels © Petrofac Training Services / June 2010 © Petrofac Training Services / June 2010 Fig 13b Ionised Smoke Detector © Petrofac Training Services / June 2010 Production Operations Figure 13.4 Gas Export Pipeline © Petrofac Training Services / June 2010