VANCOUVER ISLAND TRANSMISSION REINFORCEMENT PROJECT ARNOTT SUBSTATION, DELTA, B.C. TO VANCOUVER ISLAND TERMINAL, DUNCAN, B.C. Submitted to: British Columbia Environmental Assessment Office 2nd Floor - 836 Yates Street Victoria, B.C. V8W lL8 Canadian Environmental Assessment Agency 320 - 727 West Hastings Street Sinclair Centre Vancouver, B.C. 6C 1A1 Prepared by: Rev. 4 January 2005 Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 TABLE OF CONTENTS Section Subject Page EXECUTIVE SUMMARY ............................................................................................iv Project Objectives ......................................................................................................iv Project Components.................................................................................................... v Project Schedule and Staging....................................................................................vii Environmental Assessment....................................................................................... viii LIST OF ABBREVIATIONS......................................................................................... x CONTRIBUTORS .......................................................................................................xi 1.0 GENERAL INFORMATION ....................................................................... 1 1.1 Key Proponent Contacts................................................................ 3 1.2 Project Objectives.......................................................................... 3 2.0 PROJECT SCHEDULE AND STAGING ................................................... 4 3.0 PROJECT COMPONENTS AND INFRASTRUCTURE............................. 6 4.0 PROJECT ALTERNATIVES...................................................................... 7 5.0 SUMMARY OF REGULATORY AGENCIES AND KEY STAKEHOLDERS ............................................................................. 9 5.1 Consultations Held....................................................................... 11 5.1.1 Regulatory Agency Consultation...................................... 11 5.2 Consultations Planned or Proposed ............................................ 13 5.3 Public and First Nations Consultation.......................................... 14 6.0 PROJECT INFORMATION...................................................................... 16 6.1 Existing Infrastructure .................................................................. 16 6.1.1 Existing 138 kV System - Overhead Components ........... 16 6.1.2 Existing 138 kV System - Submarine Components ......... 17 6.2 Proposed Project Components and Infrastructure....................... 18 6.2.1 Overhead Transmission Lines ......................................... 18 6.2.2 Submarine Cables ........................................................... 20 6.2.3 Terminals and Substations .............................................. 25 7.0 SCOPE OF ENVIRONMENTAL ASSESSMENT .................................... 27 7.1 Marine Flora and Fauna Resources ............................................ 28 7.2 Freshwater Fish and Aquatic Resources..................................... 29 7.3 Terrestrial Environment ............................................................... 29 7.4 Land Use ..................................................................................... 30 7.5 Archaeological and Heritage Resources ..................................... 31 7.6 Visual and Recreational Resources............................................. 32 7.7 Electromagnetic Fields (EMF) ..................................................... 32 7.8 Public Health Issues .................................................................... 32 -iBritish Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 TABLE OF CONTENTS - Cont'd Section Subject Page SCOPE OF ENVIRONMENTAL ASSESSMENT - Cont'd 7.9 7.10 7.11 Resource and Material Requirements ......................................... 32 Spill Prevention and Emergency Response ................................ 33 Waste Disposal............................................................................ 34 8.0 CONCLUSIONS ...................................................................................... 35 9.0 REFERENCES ........................................................................................ 36 LIST OF TABLES Table 1: List of Potential Stakeholders for the Vancouver Island Transmission Reinforcement Project .............................................................................. 9 LIST OF FIGURES Figure 1: Vancouver Island Transmission Reinforcement Project Study Area ...... 41 Figure 2: Project Schedule (Sheets 1 and 2)......................................................... 42 Figure 3: Project Corridor through Corporation of Delta from Arnott Substation to English Bluff Cable Terminal .............................................................. 44 Figure 4: Project Corridor across Galiano Island from Taylor Bay Cable Terminal to Montague Cable Terminal on Parker Island ........................ 45 Figure 5: Project Corridor across Salt Spring Island from Maricaibo Cable Terminal to Vancouver Island Terminal................................................................. 46 Figure 6: Existing Cable Layout and Bathymetry 138 kV and HVDC Corridors .... 47 Figure 7: Cross Section of a Typical High Voltage Submarine Transmission Cable ............................................................................................... 48 Figure 8: Existing English Bluff Terminal 138 kV Cable Terminal , Tsawwassen, B.C................................................................................... 49 Figure 9: Existing Taylor Bay 138 kV Cable Terminal, Galiano Island .................. 49 Figure 10: Existing Montague Harbour 138 kV Cable Terminal, Galiano Island, (Parker Island) ........................................................................................ 50 Figure 11: Existing Maricaibo Terminal 138 kV Cable Terminal, Salt Spring Island ...................................................................................................... 50 - ii British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 TABLE OF CONTENTS - Cont'd LIST OF APPENDICES Appendix I Summary of Canadian Federal Permits, Approvals, and Authorizations for Construction of the Vancouver Island Transmission Reinforcement Project (Replacement and Upgrade of Circuits 1L17/18) Appendix II Summary of Selected U.S. Federal, State and Local Environmental Permits and Authorizations Relevant to the Vancouver Island Transmission Reinforcement Project (Replacement and Upgrade of Circuits 1L17/18) Appendix III Existing 138 kV Overhead Transmission Line System from Arnott Substation to Vancouver Island Terminal Appendix IV Proposed 230 kV Overhead Transmission Line System Design Features and Construction Processes Appendix V Submarine Cable Design Features Appendix VI Overview Level Environmental Inventory of Marine Flora and Fauna Resources - iii British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 EXECUTIVE SUMMARY British Columbia Transmission Corporation (BCTC) is a provincial Crown Corporation responsible for managing, operating, and maintaining most of the provincial power transmission system and its interconnections with the larger North American grid. In order to meet current and projected electricity demand on Vancouver Island and to maintain reliable grid operations, BCTC is proposing to replace and upgrade the existing 138 kV facilities connecting southern Vancouver Island to the Lower Mainland with new 230 kV infrastructure. New facilities are proposed within an existing transmission corridor from Arnott Substation in Delta, B.C., to Vancouver Island Terminal Station north of Duncan, B.C. These facilities will be operated and maintained by BCTC and owned by BC Hydro. The name of the project is the Vancouver Island Transmission Reinforcement Project (the Project). The Project is subject to a screening level review under the Canadian Environmental Assessment Act (CEAA) since federal approvals and authorizations from Fisheries and Oceans Canada (DFO) and the Transport Canada Marine Division are required. Although there is some uncertainty whether the Project would be automatically reviewable under definitions in the British Columbia Environmental Assessment Act (BCEAA), BCTC has requested the British Columbia Environmental Assessment Office (BCEAO) to voluntarily designate the Vancouver Island Transmission Reinforcement Project a reviewable project under Section 7 of the BCEAA. Various permits and approvals will also be required from U.S. federal, state, and county regulatory agencies since a portion of the proposed submarine cable route in the Strait of Georgia is located within U.S. jurisdiction. PROJECT OBJECTIVES The Project is required to achieve the following objectives: y To provide adequate system reliability on Vancouver Island. The existing HVDC voltage conversion system is nearing the end of its service life and cannot be - iv British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description considered as reliable capacity beyond 2007. Rev. 4, January 2005 Some of the critical AC/DC conversion equipment is obsolete and no longer supported with spare parts or maintenance services from the original manufacturer. y To meet current and future electricity demand on Vancouver Island by providing greater firm electrical transmission capacity than is available with the existing infrastructure. The existing 138 kV alternating current (AC) transmission system between the lower mainland and Vancouver Island is approximately 50 years old and is beyond its design service life. Its primary use is for electric service to the South Gulf Islands and is no longer used for bulk electricity transfer to Vancouver Island. y To reduce on going operating and maintenance costs. Due to aging equipment, the existing facilities require increasing levels of expenditure for maintenance and repairs. y To reduce the potential for negative environmental impacts resulting from cable failures and ongoing construction activities needed to repair or replace failed sections of cable. y To decrease exposure to system failures due to seismic events (earthquakes). The existing HVDC conversion equipment is vulnerable to earthquake damage, especially at the Arnott Substation terminal. PROJECT COMPONENTS The principal components of the Project include replacement of the following overhead transmission line and submarine cable segments of the two existing 138 kV circuits (1L17/1L18) between the Arnott substation (ARN) in Delta and the Vancouver Island Terminal (VIT) north of Duncan: y Two 138 kV overhead transmission circuits from ARN to English Bluff Terminal (EBT) in Tsawwassen. This includes line termination works at ARN including disconnect switches, circuit breakers, protection and controls; y Two 138 kV submarine cable circuits (6 single-phase cables) beneath Georgia Strait between EBT and Taylor Bay Terminal (TBY) on Galiano Island; y Two 138 kV overhead transmission circuits from TBY, across Galiano Island and Montague Harbour, to Montague Terminal (MTG) on Parker Island; -vBritish Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 Two 138 kV submarine cable circuits (6 single-phase cables) beneath Trincomali Channel between MTG on Parker Island to Maricaibo Terminal (MBO) on Salt Spring Island; and y Two 138 kV overhead transmission circuits between MBO on Salt Spring Island and VIT on Vancouver Island. This includes line termination works at VIT including disconnect switches, circuit breakers, protection and controls, plus a phase shifting transformer to control load flow. Lengths of the 5 segments of each circuit are as follows: Location Description Length Delta (Lower Mainland) ARN to EBT (Overhead) 12.0 km (7.5 miles) Straight of Georgia EBT to TBY (Cable) 25.5 km (16 miles) Galiano and Parker Islands TBY to MTG (Overhead) 5.2 km (3.2 miles) Trincomali Channel MTG to MBO (Cable) 4.5 km (3 miles) Salt Spring and Vancouver Islands MBO to VIT (Overhead) 21.8 km (13.5 miles) The total corridor length is approximately 69 km (43 miles) long. The three overhead segments of each existing circuit total approximately 39 km (24 miles) and consist of new transmission support structures (either steel poles or lattice steel structures depending on location), guys, and 3 conductors or wires. The submarine cable segments total approximately 30 km (19 miles). The segment in the Strait of Georgia passes through approximately 12 km (7.5 miles) of U.S. territorial waters west of Point Roberts. Two new 230 kV circuits (both the overhead and submarine portions) would be installed within the same corridor. Modifications of the existing substations at each end of the corridor will be required to install new 230 kV terminal facilities. At the VIT, it is possible that the station boundary may be expanded somewhat to accommodate the phase shifting transformer. Any such expansion would be within the existing site. The design life of the new cables would be approximately 50 years, although the actual life span is expected to achieve 60 years or more with proper maintenance and repairs. Design life of the overhead lines should exceed 60 years. - vi British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 PROJECT SCHEDULE AND STAGING Removal of existing facilities and construction of replacement overhead transmission lines and submarine cables would be undertaken in two stages, as follows: 1. Stage 1: new double-circuit 230 kV overhead line structures and conductors would be installed from Arnott Substation (ARN) to English Bluff Terminal (EBT) in Tsawwassen, from Taylor Bay Terminal (TBY) to Montague Terminal (MTG) on Parker Island, and from Maricaibo Terminal (MBO) on Salt Spring Island to Vancouver Island Terminal Station (VIT). One of two circuits on the new overhead structures would continue to operate at 138 kV to supply the South Gulf Islands until the second stage is completed. For the Georgia Strait (EBT to TBY) and Trincomali Channel (MTG to MBO) submarine cable crossings, three existing single-phase 138 kV cables would be removed and replaced with three new single-phase 230 kV cables, using modified cable termination equipment at each of the cable terminals (i.e., EBT, TBY, MTG and MBO). The remaining 138 kV submarine circuit would continue to supply Salt Spring Substation (SAL) and Galiano Substation (GLS) from Arnott Substation and Vancouver Island Terminal Station. Improvements to the infrastructure would be made at each cable-landing site and would involve work in the subtidal, intertidal and foreshore areas. The focus of the current environmental assessment will be on the construction, operation, and eventual decommissioning for the first stage of the Vancouver Island Transmission Reinforcement Project only. Construction activities for the first stage of the Vancouver Island Transmission Reinforcement Project are currently scheduled to commence in late 2006, depending on agency approvals, with an in-service date of 31 October 2008. 2. Stage 2: the three remaining 138 kV cables would be removed and replaced with three additional 230 kV submarine cables across Georgia Strait and Trincomali Channel. The second circuit on the new overhead line structures - vii British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 installed during stage one would then be converted from 138 kV to 230 kV operation. The service configuration for Galiano and Salt Spring Substations would also be changed at this time to permit continued reliable service to customers on the South Gulf Islands. The approximate in-service date for the second stage would be in year 2018, based on current projections of on-island electrical demands at that time. Stage two activities are not part of the current project scope. Additional, separate environmental assessment and project approval processes will be required, beginning several years before that projected date. ENVIRONMENTAL ASSESSMENT BCTC will prepare and submit draft Terms of Reference (TOR) for regulatory review and approval. The TOR will outline the proposed scope of the technical studies, assessment methodologies, public and First Nations consultation programs, and general format and organisation for preparation of the Application for an Environmental Assessment Certificate under BCEAA. Concurrently, the TOR will include requirements for a screening level environmental assessment under CEAA. The draft Terms of Reference will also identify scope of the environmental assessments to be undertaken to satisfy U.S. regulatory permitting and approval requirements. The environmental assessment will consider potential effects to biological, physical, and cultural resources. The assessment will also consider potential impacts to project facilities caused by natural events (seismic or weather) or other environmental conditions, as required by CEAA. The Application for an Environmental Assessment Certificate/ Screening Level Environmental Assessment will also evaluate potential environmental effects of accidents and equipment malfunctions, and cumulative environmental effects that may occur in connection with construction and operation of the Project, as required by Section 16 of the Canadian Environmental Assessment Act (CEAA). Based on the detailed technical assessments of various disciplines, environmental mitigation and monitoring measures will be recommended for reducing, and where - viii British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 appropriate, precluding potentially adverse impacts associated with the construction and operation of the Vancouver Island Transmission Reinforcement Project. The environmental assessment will include a determination of the significance of residual effects after implementation of the recommended mitigation measures. BCTC plans to engage in consultation with First Nations and public stakeholders throughout the preparation of the environmental assessment report, to invite comment and feedback on potential negative impacts, and to recommend mitigation measures. BCTC will also undertake formal public consultation programs such as public open houses, information sessions, and town hall meetings following completion and submission of the environmental assessment report. First Nations and public consultation will also be integral components of BCTC’s application for a Certificate of Public Convenience and Necessity (CPCN) from the British Columbia Utilities Commission (BCUC). Accordingly, BCTC will coordinate the technical submissions and consultation programs between concurrent applications under the BCUC and the BCEAA/CEAA processes. - ix British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 LIST OF ABBREVIATIONS Acronym Definition AOA Archaeological Overview Assessment AIA Archaeological Impact Assessment ARN Arnott Substation BC Hydro British Columbia Hydro and Power Authority BCEAA British Columbia Environmental Assessment Act BCEAO British Columbia Environmental Assessment Office BCTC British Columbia Transmission Corporation BCUC British Columbia Utilities Commission CDC Conservation Data Centre CEA Agency Canadian Environmental Assessment Agency CEAA Canadian Environmental Assessment Act COSEWIC Committee on the Status of Endangered Wildlife in Canada CPCN Certificate of Public Convenience and Necessity CWS Canadian Wildlife Service DFO Fisheries and Oceans Canada DPAs Development Permit Areas EA Environmental Assessment EBT English Bluff Terminal EMF Electromagnetic Field Effects EMP Environmental Management Plan ESA Endangered Species Act ESAs Environmentally Sensitive Areas FREMP Fraser River Estuary Management Program GPS Global Positioning System HADD Harmful Alteration, Disruption, or Destruction JARPA Joint Aquatic Resources Permit Application kV Kilovolt MBO Maricaibo Terminal MTG Montague Harbour Terminal MWLAP Ministry of Water, Land and Air Protection RA(s) Responsible Authority(ies) under CEAA SARA Species at Risk Act SEPA State Environmental Policy Act TBY Taylor Bay Terminal TEM Terrestrial Ecosystem Mapping VIT Vancouver Island Terminal -xBritish Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 CONTRIBUTORS British Columbia Transmission Corporation Bruce Barrett, Program Manager Melissa Holland, Regulatory Donna McGeachie, Community and Stakeholder Relations Robert Pan, System Planning BC Hydro Engineering Services Ross Nelson, Transmission Cables, Project Manager Gary Barnett, Transmission Overhead Allen MacPhail, Transmission Cables Takashi Kojima, Transmission Cables Francis Liang, Transmission Cables Lauren Caldwell, Environment and Sustainability Sandra Wilson, Environment and Sustainability Bob Bradley, Environment and Sustainability Gary Holisko, Environment and Sustainability BC Hydro Jim Fralick, Aboriginal Relations Department Ted Olynyk, Community Relations Subconsultants Don Gamble, Golder Associates Ltd. Guy Martel, Triton Environmental Consultants Ltd. - xi British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description 1.0 Rev. 4, January 2005 GENERAL INFORMATION This Project Description provides an overview of the proposed Vancouver Island Transmission Reinforcement Project (Replacement and Upgrade of Circuits IL17/18). The proponent for this Project is the British Columbia Transmission Corporation (BCTC). BC Hydro Engineering is providing the engineering design services and environmental assessment studies on behalf of BCTC. BCTC is a provincial Crown Corporation responsible for managing, operating, and maintaining most of the provincial power transmission system and its interconnections with the larger North American grid. In order to meet current and projected electricity demand on Vancouver Island and to maintain reliable grid operations, BCTC is proposing to replace and upgrade the existing 138 kV facilities connecting southern Vancouver Island to the Lower Mainland with 230 kV infrastructure. New facilities are proposed within an existing transmission corridor from the Arnott Substation in Delta, B.C., to the Vancouver Island Terminal Station north of Duncan, B.C. (Figure 1). These facilities will be operated and maintained by BCTC and owned by BC Hydro. This Project will be regulated by the British Columbia Utilities Commission (BCUC) under the terms and conditions of a Certificate of Public Convenience and Necessity. BCTC will provide BCUC with the information, material, evidence and documents that it prescribes. This information may include an evaluation of potential impacts and mitigation measures with respect to the construction and operation of the Project. BCUC has the discretion whether or not to hold public hearings on an application for a Certificate of Public Convenience and Necessity (Section 46(2)). The Project is subject to a screening level review under the Canadian Environmental Assessment Act (CEAA) due to the requirement for federal approvals and authorizations from Fisheries and Oceans Canada (DFO) and the Transport Canada Marine Division. There is some uncertainty whether the Project would be automatically reviewable based on the shoreline modification trigger, as defined in Part 5 of the Reviewable Projects Regulations of the British Columbia Environmental Assessment Act (BCEAA). Therefore, BCTC has -1- British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 requested the British Columbia Environmental Assessment Office (BCEAO) to designate the Project as reviewable under the BCEAA. BCTC anticipates that the BCEAA process will help facilitate a coordinated technical review with regulatory agencies, public stakeholders, and First Nations within the context of an Application for an Environmental Assessment Certificate. Specifically, the BCEAA process will enable: y formal notification and consultation procedures and timelines, which in turn may assist in optimizing stakeholder consultations required through the British Columbia Utilities Commission (BCUC) regulatory process; y a coordinated review process with other agencies, stakeholders and jurisdictions, and is consistent with the spirit of the Canada-British Columbia Agreement on Environmental Assessment Cooperation (March 2004); y a formal mechanism for coordination of information sharing on major projects with U.S. regulatory agencies and stakeholders consistent with the Memorandum of Understanding (MOU) between the Washington State Department of Ecology and the British Columbia Environmental Assessment Office (November 2003); and y a mechanism for concurrent application for provincially administered permits and approvals at the time of submitting the Application for an Environmental Assessment Certificate. This Project Description has been prepared to satisfy the general information requirements of the Canadian Environmental Assessment and with guidelines administered by the British Columbia Environmental Assessment Office (BCEAO) under BCEAA. This Project Description provides a general overview of the proposed nature of the project, its components, alternatives considered, applicable environmental assessment and approval processes within Canadian and U.S. jurisdiction. It also provides a preliminary identification of the anticipated biophysical and cultural resources that will need to be managed during construction, operation, -2British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 and decommissioning of the Vancouver Island Transmission Reinforcement Project. 1.1 Key Proponent Contacts Proponent: BC Transmission Corporation (BCTC) Bruce Barrett, P.Eng. Vancouver Island Transmission Reinforcement Project, Program Manager British Columbia Transmission Corporation (BCTC) 10th Floor – 1055 Dunsmuir Street Vancouver, B.C. V7X 1V5 Phone: (604) 699-7380 Fax: (604) 699-7471 Email: Bruce.Barrett@bctc.com Agent (on behalf of BCTC): BC Hydro Engineering 1.2 Ross Nelson, P.Eng. Lauren Caldwell, B.C.S.L.A. Project Manager Environmental Task Manager BC Hydro Engineering BC Hydro Engineering 6911 Southpoint Dr 6911 Southpoint Drive Burnaby, BC, V3N 4X8 Burnaby, BC, V3N 4X8 Phone: 604-528-2292 Phone: 604-528-2103 Fax: 604-528-2940 Fax: 604-528-2940 Email: ross.nelson@bchydro.com Email: lauren.caldwell@bchydro.com Project Objectives BCTC is proposing to replace and upgrade BC Hydro’s existing 138 kV overhead and submarine cable transmission line system with a 230 kV system from the Arnott substation in Delta, to the Vancouver Island Terminal (VIT) north of Duncan, B.C. The Project is required to achieve the following objectives: y To provide adequate system reliability on Vancouver Island. The existing HVDC voltage conversion system is nearing the end of its service life and cannot be considered as reliable capacity beyond 2007. Some of the critical AC/DC conversion equipment is -3- British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description obsolete and no longer Rev. 4, January 2005 supported with spare parts or maintenance services from the original manufacturer. y To meet current and future electricity demand on Vancouver Island by providing greater firm electrical transmission capacity than is available with the existing infrastructure. The existing 138 kV alternating current (AC) transmission system between the lower mainland and Vancouver Island is approximately 50 years old and is beyond its design service life. Its primary use is for electric service to the South Gulf Islands and is no longer used for bulk electricity transfer to Vancouver Island. y To reduce on going operating and maintenance costs. Due to aging equipment, the existing facilities require increasing levels of expenditure for maintenance and repairs. y To reduce potential for environmental impacts resulting from cable failures and the construction activities needed to repair or replace failed sections of cable. y To decrease exposure to system failures due to seismic events (earthquakes). The existing HVDC conversion equipment is vulnerable to earthquake damage, especially at the Arnott Substation terminal. 2.0 PROJECT SCHEDULE AND STAGING The definition and permitting phase of the Project schedule is shown in Figure 2. Removal of existing facilities and construction of replacement overhead transmission lines and submarine cables would be undertaken in two stages, as follows: Stage 1: new double-circuit 230 kV overhead line structures and conductors would be installed from Arnott Substation (ARN) to English Bluff Terminal (EBT) in Tsawwassen, from Taylor Bay Terminal (TBY) to Montague Terminal (MTG) on Parker Island, and from Maricaibo Terminal (MBO) on Salt Spring Island to Vancouver Island Terminal Station (VIT). One of two circuits on the new -4- British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 overhead structures would continue to operate at 138 kV to supply the South Gulf Islands until the second stage is completed. For the Georgia Strait (EBT to TBY) and Trincomali Channel (MTG to MBO) submarine cable crossings, three existing single-phase 138 kV cables would be removed and replaced with three new 230 kV cables, using modified cable termination equipment at each of the cable terminals (i.e., EBT, TBY, MTG and MBO). The remaining 138 kV submarine circuit would continue to supply Salt Spring Substation (SAL) and Galiano Substation (GLS) from Arnott Substation and Vancouver Island Terminal Station. Improvements to the infrastructure would be made at each cable-landing site and would involve work in the subtidal, intertidal and foreshore areas. The focus of the current environmental assessment will be on the construction, operation, and eventual decommissioning for the first stage of the Vancouver Island Transmission Reinforcement Project only. Construction activities for the first stage of the Vancouver Island Transmission Reinforcement Project are currently scheduled to commence in late 2006, depending on agency approvals, with an in-service date of October 31, 2008. Stage 2: the three remaining 138 kV cables would be removed and replaced with three additional 230 kV submarine cables across Georgia Strait and Trincomali Channel. The second circuit on the new overhead line structures installed during stage one would then be converted from 138 kV to 230 kV operation. The service configuration for Galiano and Salt Spring Substations would also be changed at this time to permit continued reliable service to customers on the South Gulf Islands. The approximate in-service date for the second stage would be in year 2018, based on current projections of on-island electrical demands at that time. Stage two activities are not part of the current project scope. A separate environmental assessment and project approval processes will be required, beginning several years before that projected date. -5British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description 3.0 Rev. 4, January 2005 PROJECT COMPONENTS AND INFRASTRUCTURE The principal components of the Project include replacement of the following overhead transmission line and submarine cable segments: y Two 138 kV overhead transmission circuits from Arnott Substation (ARN) to English Bluff Terminal (EBT) in Tsawwassen. This includes line termination works at ARN including disconnect switches, circuit breakers, protection and controls; y Two 138 kV submarine cable circuits (6 single-phase cables) beneath Georgia Strait between EBT and Taylor Bay Terminal (TBY) on Galiano Island; y Two 138 kV overhead transmission circuits from TBY, across Galiano Island and Montague Harbour, to Montague Terminal (MTG) on Parker Island; y Two 138 kV submarine cable circuits (6 single-phase cables) beneath Trincomali Channel between MTG on Parker Island to Maricaibo Terminal (MBO) on Salt Spring Island; and y Two 138 kV overhead transmission circuits between MBO on Salt Spring Island and VIT on Vancouver Island. This includes line termination works at VIT including disconnect switches, circuit breakers, protection and controls, plus a phase shifting transformer to control load flow. Lengths of the 5 segments of each circuit are as follows: Location Description Length Delta (Lower Mainland) ARN to EBT (Overhead) 12.0 km (7.5 miles) Straight of Georgia EBT to TBY (Cable) 25.5 km (16 miles) Galiano and Parker Islands TBY to MTG (Overhead) 5.2 km (3.2 miles) Trincomali Channel MTG to MBO (Cable) 4.5 km (3 miles) Salt Spring and Vancouver Islands MBO to VIT (Overhead) 21.8 km (13.5 miles) The total corridor length is approximately 69 km (43 Miles) long. The three overhead segments of each existing circuit total approximately 39 km (24 miles) and consist of new transmission support structures, guys, and 3 conductors or wires. -6British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 The submarine cable segments total approximately 30 km (19 miles). The segment in the Strait of Georgia passes through approximately 12 km (7.5 miles) of U.S. territorial waters west of Point Roberts. Two new 230 kV circuits (both the overhead and submarine portions) would be installed within the same corridor. Modifications of the existing substations at each end of the corridor will be required to install new 230 kV terminal facilities. At the VIT, it is possible that the station boundary may be expanded somewhat to accommodate the phase shifting transformer. Any such expansion would be within the existing site. The design life of the new cables would be approximately 50 years, although the actual life span is expected to achieve 60 years or more with proper maintenance and repairs. Design life of the overhead lines should exceed 60 years. 4.0 PROJECT ALTERNATIVES Project alternatives will be considered within the context of "alternatives to" the Project. Alternatives to the Project Analysis of alternatives to the Project will describe the process that BCTC proposes to use to determine that the Project is technically, economically and environmentally viable. Alternatives to the Vancouver Island Transmission Reinforcement Project would include, for example: Development of on-island power projects capable of meeting Vancouver Island’s projected power demands; Replacement of the existing High Voltage Direct Current (HVDC) system between the lower mainland and southern Vancouver Island, and; Replacement and upgrading of the existing 138 kV transmission line and submarine cable with a much larger capacity 500 kV line. -7British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Alternative Means of Carrying out a Project "Alternative means of carrying out the project" are not required for a Screening Level Environmental Assessment under CEAA; such alternative means will only be examined and discussed briefly within the context of the Screening Level EA. Alternative means of carrying out the Vancouver Island Transmission Reinforcement Project include, for example: Evaluation of alternative overhead transmission line and submarine cable crossing alignments, including right-of-way variations; Evaluation of alternative routings in the Tsawwassen area; Evaluation of undergrounding portions of the overhead lines; Evaluation of alternative transmission line support structures, span lengths, and heights; Evaluation of alternative techniques and methods for installing the new submarine cable, including trenching, hydro-jetting, and other burial techniques to ensure system security in view of seismic and anchor damage risks; Evaluation of alternative techniques and methods for decommissioning, removing, and disposing of the existing submarine cables and overhead transmission line; and, Evaluation of alternative station locations. There are likely to be constraints associated with any alternative right-of-way for the submarine cables. submarine cable An alternative corridor to the south of the existing right-of-way would likely require securing additional authorizations for working and maintaining a longer cable system within U.S. territorial waters than currently exists. In addition, there are increased geotechnical and seismic risks north of the existing right-of-way, as well as constraints with respect to shipping traffic within the vicinity of the Tsawwassen B.C. Ferry Terminal and the Vancouver Port Authority Container Terminal at Roberts Bank. -8British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description 5.0 Rev. 4, January 2005 SUMMARY OF REGULATORY AGENCIES AND KEY STAKEHOLDERS The Project crosses several jurisdictions and communities within the Lower Mainland, on the Gulf Islands, and on Vancouver Island. An initial list of regulatory agencies, public stakeholders, and First Nations likely to have an interest in certain aspects of the Project is provided below in Table 1. This list is not all-inclusive, but rather, representative of the range and types of regulatory agencies and potential stakeholders who will need to be consulted with during the environmental assessment and regulatory review process for this Project. Table 1: List of Potential Stakeholders for the Vancouver Island Transmission Reinforcement Project Canadian Agencies Federal y y y y y y y y Canadian Environmental Assessment Agency Fisheries and Oceans Canada (DFO) Environment Canada (Canadian Wildlife Service, Pollution Prevention) Transport Canada (Transport Canada Marine Division) Indian and Northern Affairs Canada (INAC) Vancouver Port Authority (VPA) Parks Canada (Gulf Island National Park Reserve) Health Canada Provincial y y y y y y BC Environmental Assessment Office (BCEAO) BC Ministry of Water Land and Air Protection (MWLAP) BC Ministry of Sustainable Resources Management (Archaeology Branch) Land and Water BC (LWBC) Ministry of Transportation Agricultural Land Commission Regional y y y Greater Vancouver Regional District Islands Trust Cowichan Valley Regional District Municipal y y y y y Corporation of Delta Corporation of the District of North Cowichan City of Duncan Salt Spring Island Galiano Island First Nations y y y Tsawwassen First Nation Musqueam First Nation Semiahmoo First Nation -9British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y y y y y y y y y y y y y y y Rev. 4, January 2005 Sto:lo First Nation Te’mexw Treaty Association Cowichan First Nation Lake Cowichan First Nation Halalt First Nation Penelakut First Nation Lyackson First Nation Tsartlip First Nation Tsawout First Nation Tseycum First Nation Pauquachin First Nation Malahat First Nation Chemainus First Nation Tsleil-Waututh First Nation Katzie First Nation Industries and Companies y y y y y y y y BC Ferries Telus Terasen Gas Inc. Boundary Bay Airport BC Rail The British Columbia Coast Pilots Ltd. Rivtow Seaspan Community/ Public Stakeholder Groups/ Non-government Organizations y y y y y y y y y y y Tsawwassen Beach Access Association Residents and property owners of Tsawwassen, Delta, Galiano, Salt Spring, Cowichan Valley Regional District Community Groups (e.g. Homeowners Associations) Parks Committees (Tsawwassen, Delta, Galiano, Salt Spring, District of North Cowichan, Cowichan Valley Regional District) Boundary Bay Conservation Committee Point Roberts Heron Preservation Committee David Suzuki Foundation Georgia Strait Alliance Marine Conservation Program Friends of Boundary Bay Sierra Club United States Agencies Federal y y y y y y y y y U.S. Department of Energy U.S. Environmental Protection Agency (EPA) U.S. Army Corps of Engineers (COE) U.S. Coast Guard (USCG) National Marine Fisheries Service U.S. Fish and Wildlife Service Advisory Council on Historic Preservation Office of Coastal Zone Management Secretary of the Treasury - 10 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 Homeland Security Department State y Washington Department of Natural Resources y Washington Department of Fish & Wildlife y Washington Department of Ecology County Whatcom County Local Point Roberts First Nations Lummi Nation Nooksack Indian Tribe Industries and Companies To be determined Community/Public Stakeholder Groups/Non-government Organizations To be determined 5.1 Consultations Held 5.1.1 Regulatory Agency Consultation Canadian Environmental Assessment Agency British Columbia Transmission Commission (BCTC) and BC Hydro Engineering met with representatives of the Canadian Environmental Assessment Agency, Fisheries and Oceans Canada (DFO), and Transport Canada (Transport Canada Marine Division) on July 20th, 2004. The purpose for the meeting was to provide an overview of the Project, including: y the rationale and justification for replacing and upgrading both of the overhead transmission lines and submarine cables; y preliminary scope of the environmental assessment work; and, y regulatory triggers for project approvals pursuant to the Canadian Environmental Assessment Act (CEAA). - 11 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 This pre-assessment meeting served to confirm that the Project would trigger a screening level review under the Canadian Environmental Assessment Act (CEAA), due to the requirements for federal approvals and authorizations from DFO and Transport Canada. Specifically, these include: Habitat Authorization Agreement under Section 35(2) of y the Fisheries Act from DFO for the "harmful alteration, disruption, or destruction" (HADD) of fish habitat; and Approval under Section 5(1) of the Navigable Waters y Protection Act from Transport Canada for "works built or placed in, on, over, under, through or across any navigable water". This meeting also provided an opportunity to receive preliminary input from the federal agency representatives regarding anticipated issues and concerns, and to discuss other concurrent environmental assessment processes that may be required, such as a review under the British Columbia Environmental Assessment Act (BCEAA) and U.S. legislation. British Columbia Environmental Assessment Office (BCEAO) BCTC and BC Hydro Engineering met with representatives of the British Columbia Environmental Assessment Office (BCEAO) on October 6th, 2004 to provide an overview of the Project, and to confirm whether the Project would be deemed "reviewable" under the Reviewable Projects Regulations. Since the Project is still in a preliminary planning and conceptual design phase, the length and area of shoreline modification required for installation of the new 230 kV cables and removal of the existing 138 kV cables has not yet been confirmed. In view of this uncertainty, and in order to optimize regulatory review and stakeholder consultations, BCTC has applied to have the Vancouver Island Transmission Reinforcement Project deemed reviewable by the BCEAA - 12 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 process. The BCEAO subsequently confirmed its acceptance to review the Project under this process on December 1st, 2004. A summary of various federal and provincial permits and approvals, as well as local government bylaws and development permit area processes that will likely apply to the Vancouver Island Transmission Reinforcement Project are provided for reference in Appendix I. Following the pre-application meetings with the Canadian Environmental Assessment Agency and the British Columbia Environmental Assessment Office (BCEAO), it was confirmed by each agency that approvals from the National Energy Board (NEB) would not required for the Vancouver Island Transmission Reinforcement Project, since the Project does not transfer power inter-provincially or internationally. 5.2 Consultations Planned or Proposed U.S. Regulatory Agencies Since a portion of the submarine cables within the Strait of Georgia are located within U.S. jurisdiction, the scope and methods for the environmental assessment will need to satisfy regulatory review requirements of the federal and Washington State agencies having jurisdiction. BCTC and BC Hydro Engineering participated in a pre-application meeting with various U.S. federal and state regulatory agencies and Whatcom County on 17 November 2004 to provide an overview presentation, and to confirm the environmental assessment and regulatory permitting processes applicable to the portion of the submarine cable replacement activities to be undertaken in U.S. territorial waters. It is anticipated that the state and federal agencies will likely review the Project through the State Environmental Policy Act (SEPA) and/or the National Environmental Policy Act (NEPA), which would be initiated when - 13 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 BCTC submits a Joint Aquatic Resources Permit Application (JARPA) to the U.S. agencies for review and approval under their respective mandates. Appendix II provides an overview summary of various U.S. federal and state legislation, including approval process administered through Whatcom County, some or all of which may apply to the regulatory review and approval of the portion of the Vancouver Island Transmission Reinforcement Project which is within U.S. jurisdiction. 5.3 Public and First Nations Consultation General Approach BCTC’s general approach for notifying and consulting with public stakeholders and First Nations includes the following principles: Research Identifying key audiences, gathering the views of stakeholders and identifying issues. Program Design Developing communication and consultation objectives, based on reasonable commitment of personnel and financial resources to meet the objectives. Information Programs Creating relevant project information and distributing it to the appropriate public stakeholders and First Nations in a timely fashion; ensuring programs are sufficiently flexible to respond to the public and First Nations interests, availability, and ideas Decision Making Incorporating local knowledge into the project decision making process and seeking public acceptance to accommodate as many interests as possible The priorities of the public and First Nations consultation programs are to: y Distribute information about the Project and build awareness; - 14 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 Create meaningful opportunities for public stakeholders and First Nations to become informed about the Project and to provide constructive feedback; and, y Seek public and community acceptance for the Project through ongoing dialogue with interested parties. First Nations Consultation BCTC will commit to undertaking notification and consultation activities with First Nations to build sustainable relationships. Consultation initiatives will be undertaken during the preparation of the Application for an Environmental Assessment Certificate/ Screening Level Environmental Assessment Report, and subsequently, during the public comment period following submission of the Application for technical and public review. There will be broad mix of interests and means of First Nations representation for this Project. Although the Vancouver Island Transmission Reinforcement Project corridor does not appear to cross First Nations reserves or treaty settlement lands, it does overlap with the traditional territories of a number of First Nations. Public Consultation BCTC will undertake public notification and consultation activities throughout the preparation of the Application for an Environmental Assessment Certificate/ Screening Level Environmental Assessment Report to engage in meaningful public input and feedback. BCTC will also undertake formal public consultation activities, such as scheduled public meetings, information sessions, and town hall meetings during the public comment period following submission of the Application for regulatory and public review. - 15 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description 6.0 Rev. 4, January 2005 PROJECT INFORMATION 6.1 Existing Infrastructure The existing electrical transmission infrastructure system, including the overhead transmission lines and submarine cables, between the lower mainland of British Columbia and Vancouver Island was constructed in the mid-1950’s. The following provides a general summary of the key features of the existing overhead transmission line and submarine cable components of this existing system. 6.1.1 Existing 138 kV System - Overhead Components The overhead transmission line and submarine cable system which supplies power to the southern Gulf Island and Vancouver Island originates at the Arnott Substation Station (ARN) in Delta, and terminates at the Vancouver Island Terminal (VIT) near Duncan on Vancouver Island. The existing overhead portion of this transmission infrastructure system is comprised of two 138 kV circuits (1L17 and 1L18). There are presently 254 structures along the overhead sections of this corridor, including 156 single circuit wood poles and H-frame structures and 98 lattice steel structures. The length of the overhead sections of each circuit is approximately 39.0 km as summarized below: Location Description Length Delta (Lower Mainland) Arnott Substation (ARN) to the English Bluff Cable Terminal (EBT) 12.0 km Galiano Island Taylor Bay Cable Terminal (TBY) to Montague Cable Terminal (MTG) on Parker Island 5.2 km Salt Spring and Vancouver Islands Maricaibo Cable Terminal (MBO) to Vancouver Island Terminal (VIT) 21.8 km - 16 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 The existing 1L17/18 structure heights along the corridor are summarized below: Location Structure Type Range in Height (m) 16 to 27 Average Height (m) 17.5 Arnott Substation to English Bluff Terminal Wood poles Galiano Island from Taylor Bay Terminal to Montague Harbour Steel Lattice Structures 19 to 26 22 Galiano Island to Parker Island across Montague Harbour Steel Lattice Structures 41 41 Salt Spring Island Steel Lattice Structures 19 to 32 22 Vancouver Island Steel Lattice Structures 20 to 33 22 Vancouver Island Wood Poles 16 to 21 17.5 The right-of-way width for circuits 1L17 and 1L18, exclusive of any overlaps due to widening for added circuits, is 53.34 m (175 ft). The two circuits are typically 21 m apart along the right-of-way. A general description of the engineering features of the existing overhead transmission line infrastructure across the Municipality of Delta, on Galiano and Salt Spring Islands, and across to Vancouver Island is presented in Appendix III. 6.1.2 Existing 138 kV System - Submarine Components The existing submarine cable corridor is shown is Figure 6. At the time of installation in the mid 1950s, this submarine cable system was the longest of its kind without factory or field splices. Initially, the five most southerly cables were installed in 1956, and two more were added in 1958. Since then, one of these cables was taken out of service in September 1990, due to leakage of nitrogen gas caused by abrasion and vibration damage to the cable as a result of underwater currents along the Galiano Ridge area, approximately 2.5 km east of Galiano Island. - 17 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 The design transmission capacity was originally 120 MW for each circuit, but they have since been down-rated to 100 MW due to armour wire corrosion. The 100 mm diameter cables are the "self contained gas-filled" (SCGF) type, in which the insulation is pressurized with nitrogen gas. This type of cable is no longer manufactured and is only suitable for use up to the 138 kV level. 6.2 Proposed Project Components and Infrastructure 6.2.1 Overhead Transmission Lines It is proposed that the replacement overhead transmission lines will be designed and built for 230 kV operation. The proposed 230 kV double-circuit will replace the existing 138 kV transmission system between Delta and Vancouver Island, utilizing the existing overhead right-of-way, cable terminal sites and underwater rights-of-way. While the ultimate configuration of the new infrastructure is for two 230 kV circuits, each with a nominal rating of 600 MW, initially only one circuit will be energized at 230 kV. It is proposed that the overhead transmission line sections will be built on double circuit structures, and that all overhead transmission line construction activities would be completed in the first stage. The second 230 kV circuit will be operated at 138 kV to supply the southern Gulf Islands from both the Arnott Substation in Delta, and the Vancouver Island Terminal north of Duncan until the second 230 kV cable circuit is required. Structure Design The design of the new transmission support structures will be based on engineering design requirements, as well as the following objectives: y minimize disruption to the current land uses along the right-of-way; y minimize construction of new roads and vegetation removal; and - 18 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 optimize aesthetic appearance of the right-of-way. The structures will be lattice steel structures or steel poles. With the exception of a few special crossing structures, all new structures will be capable of supporting two 230 kV circuits (double circuit). Narrow configuration single circuit steel poles will be considered as an alternative to the double circuit structures as a means of mitigating overall heights of the structures, where desirable. In total, approximately 165 new replacement structures would be installed to replace the existing wooden poles and lattice steel structures the 39 km overhead transmission line corridor. The majority of the new replacement structures would be placed at existing structure sites, and therefore, be located in positions that will minimize right-of-way preparation and site disturbance requirements. Appendix IV provides a general description of the engineering features and configuration of the conductors and structures proposed for the Vancouver Island Transmission Reinforcement Project. Overhead Construction Techniques Construction activities associated with the proposed replacement and upgrading of the overhead transmission line infrastructure include: y Site preparation along the right-of-way including vegetation clearing and access improvements; y Removal of the existing 138 kV conductors and structures; y Installation of pole foundations and anchors for the new replacement structures (i.e. steel poles or lattice steel structures, depending on location); - 19 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Installation of new replacement transmission support y structures; Installation of conductors, overhead ground wires, and y counterpoise (horizontal buried wires to provide additional grounding of the transmission structures); and Site y restoration along the right-of-way, including decommissioning of temporary construction access roads. Each of these phases of construction activities associated with the overhead transmission line are briefly discussed in Appendix IV. 6.2.2 Submarine Cables As indicated above, during the first stage of the Vancouver Island Transmission Reinforcement Project, three of the existing 138 kV submarine cables would be removed and replaced with three new 230 kV cables within the Georgia Strait and Trincomali Channel submarine cable crossings. The remaining 138 kV circuit would continue to supply Salt Spring Substation and Galiano Substation from the Arnott Substation and Vancouver Island Terminal. The design life of the replacement submarine cables would be approximately 50 years, although the actual life span could achieve 60 years. The following provides a summary of the proposed cable designs and cable-laying and removal procedures to be considered for the Project. Cable Designs The new submarine cables would be self-contained fluid-filled (SCFF), in which the cable insulation is pressurized with insulating fluid supplied from the cable terminals. The outside cable diameter would be approximately 125 mm (5 inches). This is presently the only cable type with proven reliability, suitable for - 20 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 the long distance, deep-water high-voltage AC installation across Georgia Strait; however, BCTC and BC Hydro are continuously monitoring technological developments and will consider any new proven technologies during the final design stage. A cross-section of a typical SCFF submarine cable is shown in Figure 7. The central stranded copper conductor is the current-carrying component. Its hollow core provides a passageway for insulating fluid under static pressure provided by equipment at the cable terminals. The insulating fluid saturates the cable insulation, maintaining the integrity of the cable, and prevents damaging ingress of water in the event of an underwater leak. The proposed insulating fluid is linear alkylbenzene (LAB), which provides optimal electrical, hydraulic and biodegradability characteristics. This fluid is necessary to control the high electric stresses in the insulation, which is important for the higher voltage (230 kV) application. The fluid’s low viscosity aids in maintaining internal cable pressure requirements when the electrical load changes rapidly. It also evaporates relatively quickly, in the unlikely event of a leak. Further details regarding the cables designs are provided in Appendix V. Submarine Cable Replacement Replacement and upgrade of the three southerly most 138 kV submarine cables with new 230 kV cables within the existing IL17/18 circuit right-of-way will involve the following sequence of construction activities. - 21 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Cable Removal The three southerly most 138 kV cables will be removed before installation of the three new 230 kV cables commences. It is presently expected that this will be done via a removal and disposal contract, with the metal components ultimately being recovered and recycled. It may be necessary to use air-lifting and water-jetting equipment to uncover the cables where they are presently buried to approximately the –3 m bathymetric contour. Similar controls on water turbidity and trench width will apply, as for installation of the new cables as discussed below. Cable Installation The new 230 kV cables will be installed in the same right-of-way corridor as the existing 138 kV cables. Their final position will be controlled and final locations known with precision, using modern navigation and laying equipment. The new submarine cables will be installed to ensure that the new circuit will meet BCTC’s and BC Hydro’s seismic performance requirements. A marine-based geotechnical investigation is in progress to evaluate the seismic risks, and to provide input into the routing for the proposed 230 kV submarine cables, and to identify possible design mitigation measures. The area of greatest potential challenges for installation of the new cables is anticipated to be within the intertidal and shallow subtidal areas west of English Bluff Terminal and Point Roberts, coinciding with the southern-most part of the Fraser River delta. Geotechnical investigation is required to characterize the marine geology and geophysics in this area, particularly with respect to stability during a seismic event and susceptibility of the cables to erosion caused by wave action. It is proposed that the new submarine cables would be located south of the existing cables within the existing right-of-way, over a - 22 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 distance approximately 4 km west of the English Bluff Terminal landing. Based on preliminary geotechnical analysis, this proposed configuration would minimize potential risk of damage to the cables during seismically induced underwater slides along the southern edge of the Fraser River delta. For the English Bluff Terminal installation, the cables would use the existing cable tunnel from the high water level to near the centre of Fred Gingell Park, immediately west of English Bluff Road. From there, the existing concrete chaseways would be used to route the new 230 kV cables to their new termination positions, located at approximately the same locations as the existing 138 kV terminations (Figure 8). From the lower tunnel entrance, the cables would be installed across the intertidal mud flats, and then water-jetted to a vertical depth of approximately 1.0 m beneath the sea bottom, out to the –3 m bathymetric contour, referenced to the vertical survey datum at mean lower low water (MLLW). Protective split-pipe covers would be placed around the cables in the upper intertidal zone to provide additional protection against high wave energy and seasonal sediment transport. For the Taylor Bay, Montague Harbour, and Maricaibo Terminal installations, the cables would use the existing concrete chaseways from the high water level to the new 230 kV cable termination footings. Figures 9 and 10 show concrete chaseways at Taylor Bay and Montague Harbour (Galiano Island), and Figure 11 shows concrete chaseways at Maricaibo Terminal (Salt Spring Island). Sunshades would be installed over the exposed chaseways to reduce solar heating effects. Installation of the submarine cables will require a dedicated cable laying vessel, with dynamic positioning capabilities and - 23 - British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 touchdown monitoring using an underwater remotely operated vehicle (ROV). This will be especially necessary for laying across the rugged Galiano Ridge underwater feature, and for some of the rocky shore approaches. It is proposed that each cable will be installed in one continuous length between cable terminal landings, except for the potential sea splices within the intertidal and subtidal zones. Bringing the cable end ashore to English Bluff Terminal will be challenging due to the approximate 2 km long, shallow intertidal mud flats, and the relatively deep draft of cable laying vessels. At all terminals, the cable end will be floated ashore guided by shallow draft workboats during favourable weather conditions. Once the cables are safely pulled ashore, they will be buried, probably using a mechanized water jetting machine. Some disturbance to the eelgrass is likely. Landing the submarine cables at the remaining cable terminals will be less complex because water depth increases quickly. Site investigations are not yet complete, but it appears that similar burial methods as at English Bluff Terminal may be practical, except where the sea bottom is composed of gravel and cobbles. In this case, it may be necessary to use diver operated air-lifting equipment, to ‘vacuum’ open trenches on the sea bottom before cable laying. Cathodic Protection Systems The existing 138 kV cables have galvanized steel armour wires, which are susceptible to corrosion. Potential for corrosion is usually greatest where the cables are not buried in the subtidal zones, and oxygen content in the seawater is relatively high. Corrosion also occurs where the cables make a transition from natural burial in soft bottom sediments, to where they lay on underwater rock outcrops. Abrasion can also result from cable movement caused by under-water sea currents along submarine - 24 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 rocky ridges, causing greater exposure of the armour wires to corrosion. Areas of greatest potential risk to the submarine cables due to abrasion are considered to be offshore from Montague Harbour Terminal, Maricaibo Terminal, and the Galiano Ridge feature approximately 4 km east of Taylor Bay Terminal. Engineering design evaluations for the new 230 kV submarine cables will include corrosion studies to investigate the extent of the problem for modern cable designs, and to determine possible mitigation methods. Possible solutions include use of: y copper wire armour, which is naturally more corrosion resistant than galvanized steel; y avoidance of rock outcrops where possible; y more extensive burial of the cables beneath the sea bottom where economically feasible; and y high-abrasion resistant insulating layers over the armour wires. In some areas it may be more effective to use shore-based cathodic protection systems to impress a low-voltage, negative electric potential on the armour wires, to resist the loss of metal into the sea water. Such cathodic protection systems are commonly used to protect steel structures in sea water, such as at ferry terminals, bulk lading facilities, and outflow pipes. 6.2.3 Terminals and Substations Cable Terminals Modifications and improvements to the four cable terminal sites (English Bluff Terminal, Taylor Bay Terminal, Montague Harbour Terminal, and Maricaibo Terminal) will include removal and replacement of existing concrete footings for the cable terminals, lightning arrestors, insulating fluid containment systems, cable chases, and other miscellaneous improvements. - 25 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 The cable insulation will be kept pressurized by systems located at each of the four cable terminal sites. For the Georgia Strait crossing, ‘pumping plant’ systems will be used to maintain pre-determined pressures within the cables. The pumping plant systems are able to automatically reduce pressure and the flow of fluid in the unlikely event of a leak, while maintaining minimum pressures until repairs can be made. For the shorter and shallower Trincomali Channel crossing, cable insulation will be pressurized either through a conventional pumping plant at Maricaibo Terminal and a ‘crossover’ at Montague Harbour Terminal, or alternatively, via a passive pressure tank system at each terminal. Both of these options would be effective at maintaining required pressure of the insulating fluid during normal operations and automatically reducing pressure and thereby flow during abnormal conditions. If a leak should occur, the low viscosity fluid would dissipate quickly. Leaks at the cable terminals or within the insulating fluid pressurizing systems would be contained with special insulating fluid containment systems. Substations The Arnott and Vancouver Island Terminal substations will be modified to accommodate the additional 230 kV line positions. This work will be contained entirely within the station property, and will follow normal BCTC and BC Hydro practices. Installation of a phase-shifting transformer at the Vancouver Island Terminal may require expansion of the substation boundary but within the available property. The phase-shifter would be installed within an impervious secondary containment basin of sufficient capacity, consistent with the requirements of the National Fire Code of Canada and with the British Columbia Fire Code of Canada. Details on the - 26 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 configuration and specifications for the phase-shifter will be determined during the detailed engineering phase. In addition, noise abatement measures may need to be incorporated into the modifications at the Vancouver Island Terminal to minimize potential disturbances to surrounding landowners associated with the phase-shifting transformer. 7.0 SCOPE OF ENVIRONMENTAL ASSESSMENT BCTC will prepare and submit draft Terms of Reference for regulatory review and approval which will outline the proposed scope of the technical studies, assessment methodologies, public and First Nations consultation programs, and general format and organization to be implemented during preparation of the Application for an Environmental Assessment (EA) Certificate under BCEAA, and concurrently, to meet the requirements for a screening level environmental assessment under CEAA. The draft Terms of Reference will also identify scope of the environmental assessments to be undertaken to satisfy U.S. regulatory permitting and approval requirements. It is anticipated that the scope of the environmental assessment will consider potential effects to the following biological, physical, and cultural resources: y Marine aquatic life including eelgrass beds, kelp beds, marine fish, benthic invertebrates, marine mammals and species of management concern protected under the Canadian Species at Risk Act (SARA) and U.S. Endangered Species Act (ESA); y Terrestrial wildlife and vegetation resources including mammals, amphibians, reptiles, birds, and plant and animal species protected under Canadian legislation; y Freshwater aquatic resources and riparian habitat; y Current use of lands and resources for traditional purposes by First Nations; y Cultural heritage and archaeological resources; y Socio-economic conditions affecting communities and residents along the proposed corridor; - 27 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 Land uses, including impacts on agricultural and forested lands, residential areas, parks and open spaces; y Visual and recreational quality effects on nearby properties and public facilities within the vicinity of the Project corridor; y Air quality and noise impacts; and, y Other construction-related issues such as traffic and waste management. The following provides a brief overview summary of the key considerations associated with these environmental and cultural resources. It is intended that the baseline characterization and assessment of potential impacts to these, and potentially other resources, will be expanded upon during the preparation of the Terms of Reference, which will serve as a framework for the Application for an EA Certificate/ Screening Level Environmental Assessment Report. 7.1 Marine Flora and Fauna Resources During installation and removal of the submarine cables, potential environmental effects will include loss or disruption of habitat to marine fish, invertebrates, and impacts to marine waterfowl, mammals, including potentially threatened and endangered species which are protected under the Canadian Species at Risk Act (SARA) and/or the U.S. Endangered Species Act (ESA). Therefore, areas and types of marine habitat (both intertidal and subtidal) predicted to be altered or disturbed during the cable removal and installation processes will be determined as part of the impact assessment. In addition, direct impacts on marine mammals and waterfowl resulting from habitat loss and alienation, water quality degradation, noise and other physical disturbances associated with the submarine cable installation and removal activities will be determined. During operation of the new 230 kV submarine cables, potential effects to marine flora and fauna are anticipated to be limited to release of fluids from the cables in the event of a failure or rupture. - 28 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Based on the assessment of potential impacts to marine flora and fauna resources associated with the installation and removal of the submarine cables, BCTC will prepare a habitat compensation plan to achieve no net loss of aquatic habitat, consistent with DFO’s Policy for the Management of Fish Habitat, and with the mandate of the Canada Fisheries Act. Appendix VI provides an overview summary of the general range of typical marine flora and fauna resources likely to occur within Georgia Strait and Trincomali Channel. The summary of marine flora and fauna species listed in Appendix VI is not intended to be an exhaustive listing of all marine resources and habitats potentially occurring within Georgia Strait and Trincomali Channel. 7.2 Freshwater Fish and Aquatic Resources During construction of the overhead transmission line, various watercourses will be crossed along BC Hydro’s right-of-way between the Arnott Substation and Vancouver Island Terminal within Delta, on Galiano and Salt Spring Islands, and along Vancouver Island. Many of these watercourses provide habitat for anadromous and resident populations of fish including coho salmon and cutthroat trout, both of which are protected under the Species at Risk Act (SARA). The Application for the EA Certificate/ Screening Level Environmental Assessment Report will evaluate critical and sensitive spawning and rearing habitats along the corridor, and provide recommendations for environmental mitigation and habitat compensation strategies. These measures will incorporate input to be solicited from regional habitat biologists with DFO and MWLAP, as well as local streamkeepers groups where applicable. 7.3 Terrestrial Environment Construction activities along the existing overhead transmission line right-of-way which could potentially affect terrestrial species include - 29 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 vegetation clearing, foundation construction, and dismantling of the existing structures and related infrastructure. The Application for an EA Certificate/ Screening Level Environmental Assessment will identify terrestrial habitat and wildlife resources along the Vancouver Island Transmission Reinforcement Project right-of-way, including areas used for nesting, breeding, and foraging. Potential effects of installing and operating the new 230 kV overhead transmission line support structures to terrestrial habitat and wildlife populations will be assessed, and wildlife habitat mitigation/ compensation measures will be recommended as necessary. Potential threatened and endangered wildlife species which are protected under the Canadian Species at Risk Act (SARA) will also be identified, and mitigation measures developed as necessary. In addition to consideration of potential impacts to terrestrial wildlife species and their respective habitats, sections of the overhead transmission line right-of-way on Galiano and Salt Spring islands may pass through patches of Garry Oak and arbutus ecosystems, plant communities protected under the Species at Risk Act (SARA). The Garry Oak and arbutus ecosystems are home to a diversity of wildlife species. Twenty-four species, including birds, reptiles, butterflies, vascular plants, and mosses represented in the Garry oak ecosystem are found on the COSEWIC and British Columbia Conservation Data Centre lists for threatened or endangered species. 7.4 Land Use The Application for the EA Certificate/ Screening Level Environmental Assessment Report will consider potential impacts of construction and operation of the Project on surrounding land uses. The assessment will delineate urban, agricultural, commercial, industrial, First Nations lands, parks, ecological reserves, and other protected areas along the Project corridor. Areas of active resource development, such as logging and gravel extraction, as well as areas of urban growth within the vicinity of - 30 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 the Project corridor will be identified. This will enable an assessment of potential land use conflicts associated with the Project. The Application for an EA Certificate/ Screening Level Environmental Assessment Report will include a review of historical land uses and activities along the Project corridor, as a basis for determining potential sources of "onsite" and "offsite" contamination. 7.5 Archaeological and Heritage Resources The Project corridor traverses through the territorial areas of several First Nations. Table 1 (List of Potential Stakeholders for the Vancouver Island Transmission Reinforcement Project) in Section 1.0 provides a preliminary list of First Nations who may have potential interests in the Project, and who BCTC will need to consult with during the environmental assessment and regulatory review process. Within and along the Project corridor is the potential of encountering archaeological and heritage resources. A summary of recorded archaeological sites within the Project corridor as identified in the BC Hydro EGIS database were compared with the provincial RAAD database reveals 5 shell midden and one lithic scatter site. Consultation with First Nations, the BC Archaeology Branch and other stakeholders will need to be undertaken to advance and add to the information provided and to address traditional use issues. An Archaeological Overview Assessment (AOA) will be conducted to evaluate potential locations for impacting unrecorded heritage resources and artifacts along the Project corridor. As part of the technical studies to be conducted in support of the Application for an EA Certificate/ Screening Level Environmental Assessment Report. Based on this Archaeological more Overview Assessment (AOA), a detailed Archaeological Impact Assessment (AIA) involving field investigations with local First Nations, and subsurface investigations at selected locations along the right-of-way may be required to confirm the presence - 31 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 or absence of encountering as-yet unrecorded archaeological and heritage resources, and then taking appropriate mitigation measures. 7.6 Visual and Recreational Resources Construction and operation of the Project may potentially impact visual quality and recreational resources along the corridor. Potential concerns with respect to visual quality impacts may be raised in the urban areas of Tsawwassen, and/or within the rural areas on Galiano and Salt Spring Islands. Recognizing that the new structures required for the 230 kV overhead transmission lines are likely to be higher than the existing 138 kV structures, there may be concerns expressed with respect to visual impacts and loss of quality to recreational resources in some areas along the corridor. 7.7 Electromagnetic Fields (EMF) The proposed replacement and upgrade of the overhead transmission lines and submarine cables from 138 kV to the larger capacity 230 kV will likely raise concerns with respect to potential increase in existing levels of EMF. This issue will be discussed in the Application for an EA Certificate/ Screening Level Environmental Assessment Report. The review will evaluate and report on the results of available scientific research. Computer models will be used to determine EMF levels associated with existing and new facilities. 7.8 Public Health Issues The Application for an EA Certificate / Screening Level Environmental Assessment Report will consider potential effects and mitigation measures for such health issues as increased noise levels and air emissions (e.g., fugitive dust, construction machinery, etc.). 7.9 Resource and Material Requirements The Project is predicted to have little requirement for raw materials, including energy, water, and aggregate resources. The raw material - 32 - British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 requirements for the Project include manufactured products including submarine cables, overhead transmission wires, steel transmission structures, insulators, conductor support hardware, phase-shifting transformers, and other station equipment. Concrete will likely be manufactured off-site by a concrete supplier, and therefore, no borrow pits or aggregate processing operations will need to be developed specifically for this Project. Therefore, the Project is not likely to deplete or consume large quantities of natural non-renewable resources. Energy requirements for the Project include fuel for the cable-laying and cable-removal ships, and construction equipment. Fuel and limited energy requirements will also be necessary for construction equipment associated with works and undertakings at the cable landing sites, and for the overhead transmission crews to access portions of the right-of-way by vehicle or helicopter. It is anticipated that only minor quantities of water will be required for the Project. 7.10 Spill Prevention and Emergency Response BC Hydro Engineering’s contractors will be responsible for preparing and implementing site-specific Spill Prevention and Emergency Response Plans tailored to their particular construction activities, consistent with BC Hydro’s corporate policies and procedures. Spill Prevention and Emergency Response Plans to be prepared by BC Hydro Engineering’s contractors will need to include and address, at a minimum, the following: y A general measure of the probability and severity of an adverse effect to health, property, or the environment on the basis of fuel, oil, and other hazardous materials consumed, handled, and stored; y Spill/release notification and alerting procedures; y Containment, recovery, and clean-up procedures; - 33 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description y Rev. 4, January 2005 On-site spill/release clean-up materials, equipment, and locations; and, y Names and telephone numbers of persons and organizations that may be contacted in the event of a potential environmental incident. The submarine cables will be designed to minimize potential for a fluid leak and to withstand abrasive forces of the cables moving along submarine ridges due to underwater sea currents. Similarly, the cable terminals will incorporate secondary containment design features to minimize the potential for a spill or release of cable insulating fluid. Post-construction spill contingency plans will be modified for each cable terminal and substations to reflect changes to reflect potential hazards and risks as a result of the Project. For example, these plans would address emergency procedures and protocols for the storage and use of cable fluid. 7.11 Waste Disposal Waste materials to be generated from the Project will be reused and recycled in the BC Hydro system wherever possible. BC Hydro Engineering and their contractors will investigate methods for material re-use, recycling, and/or disposal to ensure that the most feasible, environmentally and socially-responsible, and economic management practices are employed. The 138 kV cables that are removed from the Project area will be disposed of in accordance with BCTC’s and BC Hydro’s corporate policies and procedures, and in accordance with the provisions of the B.C. Waste Management Act. Waste steel from the decommissioned overhead transmission line lattice steel structures will be recovered and recycled. - 34 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description 8.0 Rev. 4, January 2005 CONCLUSIONS Details regarding the scope, methodology, consultation processes, and overall organization of the environmental assessment will be provided in the Terms of Reference to be submitted for regulatory review and comment. It is understood that once approved, the Terms of Reference will form the basis of a Section 11 Order under BCEAA, which will specify among other things: y scope of the environmental assessment; y information requirements from BCTC and BC Hydro Engineering; y organizations, including but not limited to the public, First Nations, government agencies and, and neighbouring jurisdictions, to be consulted by BCTC and BC Hydro Engineering during the assessment; and y means by which the persons and organizations are to be provided with notice of the assessment, access to information during the assessment and opportunities to be consulted. In addition to evaluating potential environmental effects of the Project on the above-referenced biological and cultural resources and land uses, the environmental assessment will also consider potential impacts to Project facilities caused by natural events (seismic or weather) or other environmental conditions, as required by CEAA. The Application for an EA Certificate/ Screening Level Environmental Assessment will also evaluate potential environmental effects of accidents and equipment malfunctions, and cumulative environmental effects that may occur in connection with construction and operation of the Project, as required by Section 16(1) of the Canadian Environmental Assessment Act (CEAA). Based on the detailed technical assessments of various disciplines, environmental mitigation and monitoring measures will be recommended for reducing, and where possible, precluding potentially adverse impacts associated with the construction and operation of the Vancouver Island Transmission Reinforcement Project. The environmental assessment will include a - 35 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 determination of the significance of residual effects after implementation of the recommended mitigation measures. Consultation measures are planned to be undertaken with First Nations and public stakeholders throughout the preparation of the environmental assessment report, to invite comment and feedback on potential negative impacts, and to recommend mitigation measures. BCTC will undertake formal public consultation measures such as public open houses, information sessions, and town hall meetings following completion and submission of the environmental assessment report. Environmental assessment and stakeholder consultation programs will be conducted in parallel with BCTC’s application for a Certificate of Public Convenience and Necessity (CPCN) from the British Columbia Utilities Commission (BCUC). Accordingly, BCTC will coordinate the technical submissions and public consultation programs with the requirements of the CPCN process. 9.0 REFERENCES Armstrong, D. A, Armstrong, J. L. and Dinnel, P. A. 1988. Distribution, abundance and habitat associations of Dungeness crab, Cancer magister , in Guemes Channel, San Juan Islands, Washington. J. Shellfish Res. 7:147-148. BC Hydro T&D Engineering. December, 1993. 1993. Vancouver Island Supply Study. BC Hydro. 2003. Project Planning Report. 230 kV Transmission Circuit from Arnott to VIT. Report No. SP2003-04 System Planning BC Species and Ecosystems Explorer. 2003. Victoria, British Columbia, Canada.: http://srmapps.gov.bc.ca/apps/eswp/. Bourne, N. F. and G. D. Heritage. 1997. Intertidal clam surveys in British Columbia - 1992 and 1993 Can. Tech. Rep. Fish. Aquat. Sci. no. 2168; 107 pp. Bracewell & Patterson, L.L.P. 2003. Memorandum to Mr. David Avren re: Replacement of Certain Electrical Transmission Lines from Mainland British Columbia to Vancouver Island. Dated October 16, 2003 - 36 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Burgner, R.L. 1991. Life History of the sockeye salmon (Oncorhynchus nerka). Pages 1-118 In: Pacific Salmon Life Histories. C. Groot and L. Margolis (eds.). UBC Press. Vancouver, British Columbia. Calambokidis, J. and R.W. Baird. 1994. Status of marine mammals in the Strait of Georgia, Puget Sound, and Juan de Fuca Strait and potential human impacts. P 282-303 In: Review of the marine environment and biota of Strait of Georgia, Puget Sound, and Juan de Fuca Strait. Proceedings of the BC/Washington Symposium on the Marine Environment, January 13 and 14, 1994. R.C.H. Wilson, R.J. Beamish, F. Aitkens, and J. Bell, Eds. Canadian Technical Report of Fisheries and Aquatic Sciences No. 1948. Canadian Hydrographic Service. 1999. Canadian Hydrographic Service Tidal Manual. http://chswww.bur.dfo.ca/TCWL/tidalmanual.html Chambers, P.A., R.E. DeWreede, E.A. Irlandi and H. Vandermeulen. 1999. Management issues in aquatic macrophytes ecology: a Canadian perspective. Canadian Journal of Botany. 77:471-487. Cowan, I. McT. And C.J. Guiget. 1973. Mammals of B.C. B.C. Provincial Museum Handbook #11. Department of Fisheries and Oceans. 1998. Strait of Georgia Herring. DFO Science Stock Status Report B6-05 (1998). Department of Fisheries and Oceans 1998. Dunham, J.S. and J.A. Boutillier. 2001. Pandalus danae, coonstripe shrimp: a review of the biology and recommended assessment framework for directed fisheries. Canadian Science Advisory Secretariat Research Document 2001/151 Environmental Protection Service. 1978. West Coast Offshore Environment: Groundfish and Herring Resources. Canada Department of Fisheries and Environment. Fairbanks Environmental Services Inc. August 2004. BC Hydro Eelgrass Assessment Point Roberts Right-of-Way 1L17/18. Prepared for BC Hydro Environmental Fisheries and Oceans Canada. 2004. BC Tidal Waters Sport Fishing Guide 2003-2005. Fisheries and Oceans Canada 2001. CEAA guide. Applying the Canadian Environmental Assessment Act for the fish habitat management program. Ottawa. Fisheries Information Summary System: http://pisces.env.gov.bc.ca Glaholt, R., T. Fung and S. Ong. 2000. Investigation of the potential for a bottom-founded marine pipeline to act as a barrier to the dispersal of Dungeness crab (Cancer magister), California sea cucumber (Parastichopus californicus), green sea urchin (Strongylocentroides - 37 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 droebachiensis) and other species. TERA Environmental Consultants (Alta) Ltd., Calgary, Alberta. 17 pp. Harrison. P.G. 1984. The biology of seagrasses in the intercauseway area of Roberts Bank, B.C. Report submitted to the Port of Vancouver. Harrison, P.G. and R.E. Bigley. 1982. The recent introduction of the seagrass Zostera japonica Aschers. and Graebn. to the pacific coast of North America. Can. J. Fish. Aquat. Sci. 39: 1642-1648. Hart, J.L. 1973. Pacific Fishes of Canada. Fisheries Research Board of Canada, Ottawa. Hay, D.E. and P.B. McCarter. 2004. Herring Spawning Areas of British Columbia: A review, geographic analysis and classification. Fisheries and Oceans Canada, Pacific Biological Station, Nanaimo. Healey, M.C. 1991. Life history of the chinook salmon (Oncorhynchus tshawytscha). Pages 311-394 In: Pacific Salmon Life Histories. C. Groot and L. Margolis (eds.). UBC Press. Vancouver, British Columbia. Howard Paish & Associates. 1975. Some Ecological Considerations for BC Hydro Routing of Cables or Pipeline Across Roberts Bank. Island Adventures Inc. 2004. San Juan www.island-adventures.com/sanjuanwildlife.cfm Wildlife. website: Jamieson, G.S. and S. Dixon. A proposed MPA boundary identification for reproductive refugium establishment, using lingcod (Ophiodon elongatus) as an example of focal species. Can. Sci. Advis. Sec. Res. Doc. 2001/106. Jensen, G.C. 1995. Pacific coast crabs and shrimps. Sea Challengers. Ketchen, K.S., N. Bourne and T.H. Butler. 1983. History and present status of fisheries for marine fishes and invertebrates in the Strait of Georgia, British Columbia. Can. J. Fish. Aquat. Sci. 40: 1095-1119. Levings, C.D., R.E. Foreman and V.J. Tunnicliffe. 1983. Review of the benthos of the Strait of Georgia and contiguous fjords. Can. J. Fish. Aquat. Sci. 40: 1120-1141 Levy, D.A. 1985. Biology and management of surf smelt in Burrard Inlet, Vancouver, B.C. Westwater Research Centre Technical Report No. 28. Love, M.S. M. Yoklavich, and L. Thorsteinson. 2002. The rockfishes of the Northeast Pacific. University of California Press. Morrison, J. M. Kattilakoski, I. Winter, and J. Boutiller. 1998. Prawn trap fishery – 1996-97. PSARC Fisheries update document. Department of Fisheries and Oceans. - 38 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Peterson, C.H., H.C. Summerson, and P.B. Duncan. 1984. The influence of seagrass cover on population structure of a suspension-feeding native bivalve, Mercenaria mercenaria. J. Mar. Res. 42: 123-138. Precision Identification Inc. September 2004. BC Hydro Cable Terminal Eelgrass Assessments: English Bluff, Tsawwassen, Maricaibo, Salt Spring Island, Montague Harbour, Parker Island, Taylor Bay, Galiano Island. Prepared for BC Hydro. Vancouver, B.C. Salo, E.O. 1991. Life history of the chum salmon (Oncorhynchus keta). Pages 231-310 In: Pacific Salmon Life Histories. C. Groot and L. Margolis (eds.). UBC Press. Vancouver, British Columbia. Schweigert, J. 2001. Stock assessment for British Columbia herring in 2001 and forecasts of the potential catch in 2002. Can. Sci. Adv. Secr. 53: 818-841. Theriault, T.W., A.N. McDiarmid, W. Duff and D.E. Hay. 2002. Review of surf smelt (Hypomesus pretiosus) biology and fisheries, with suggested management options for British Columbia. Can. Sci. Advis. Sec. Res. Doc. 2002/115. Triton Consultants Ltd. 1996. A review of recent physical and biological development of the southern Roberts Bank seagrass system 1950-1994. Report to the Roberts Banks Environmental Review Committee. Vancouver, 84 pp. Tunnicliffe, V. 1993. Biodiversity: the marine biota of British Columbia. Pages 191-220. In: Our Living Legacy: Proceedings of a Symposium on Biological Diversity. M.A. Fenger, E.H. Miller, J.A. Johnson and E.J.R. Williams (eds.). Royal British Columbia Museum. Victoria, British Columbia. Walker, W.A., M.B. Hanson, R.W. Baird and T.J. Guenther. 1998. Food habits of the harbour porpoise, Phocoena phocoena, and Dall's porpoise, Phocoenoides dalli, in the inland waters of British Columbia and Washington. pp 63-75 in Marine Mammal Protection Act and Endangered Species Act Implementation Program 1997. AFSC Processed Report 98-10. Yamanaka, K.L. and L.C. Lacko. 2001. Inshore Rockfish (Sebastes ruberrimus, S. malinger, S. caurinus, S. melanops, S. nigrocinctus, and S. nebulosus) Stock Assessment for the West Coast of Canada and Recommendations for Management. Can. Sci. Advis. Sec. Res. Doc. 2001/139, Ottawa. Zhang, Z., W.Halas, A. Phillips and J.A. Boutillier. 2002. Evaluation of an intensive fishery on Dungeness crab (Cancer magister) in Fraser delta, British Columbia. Can. Sci. Advis. Sec. Res. Doc. 2002/118 - 39 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 FIGURES Figure 1 Vancouver Island Transmission Reinforcement Project - Study Area Figure 2 Project Schedule (Sheets 1 and 2) Figure 3 Project Corridor through Corporation of Delta from Arnott Substation to English Bluff Cable Terminal Figure 4 Project Corridor across Galiano Island from Taylor Bay Cable Terminal to Montague Cable Terminal on Parker Island Figure 5 Project Corridor across Salt Spring Island from Maricaibo Cable Terminal to Vancouver Island Terminal Figure 6 Existing Cable Layout and Bathymetry 138 kV and HVDC Corridors Figure 7 Cross Section of a Typical High Voltage Submarine Transmission Cable Figure 8 Existing English Bluff Terminal 138 kV Cable Terminal, Tsawwassen, B.C. Figure 9 Existing Taylor Bay 138 kV Cable Terminal, Galinao Island Figure 10 Existing Montague Harbour 138 kV Cable Terminal, Galiano Island (Parker Island) Figure 11 Existing Maricaibo Terminal 138 kV Cable Terminal, Salt Spring Island - 40 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description www.bctc.com British Columbia Transmission Corporation Figure 1: Vancouver Island Transmission Reinforcement Project Study Area - 41 - Rev. 4, January 2005 Vancouver Island Transmission Reinforcement Project Project Description www.bctc.com British Columbia Transmission Corporation Figure 2: Project Schedule (Sheet 1) - 42 - Rev. 4, January 2005 Vancouver Island Transmission Reinforcement Project Project Description www.bctc.com British Columbia Transmission Corporation Figure 2 Cont'd: Project Schedule (Sheet 2) - 43 - Rev. 4, January 2005 Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Figure 3: Project Corridor through Corporation of Delta from Arnott Substation to English Bluff Cable Terminal - 44 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Figure 4: Project Corridor across Galiano Island from Taylor Bay Cable Terminal to Montague Cable Terminal on Parker Island - 45 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Figure 5: Project Corridor across Salt Spring Island from Maricaibo Cable Terminal to Vancouver Island Terminal - 46 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description British Columbia Transmission Corporation www.bctc.com Figure 6: Existing Cable Layout and Bathymetry 138 kV and HVDC Corridors - 47 - Rev. 4, January 2005 Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Figure 7: Cross Section of a Typical High Voltage Submarine Transmission Cable Item Component Description 1 Insulating Fluid Duct 2 Conductor Cross section Self supporting segmental strips of copper 3 Conductor screen Carbon black papers 4 Insulation Impregnated PPL paper tapes 5 Core screen Carbon black papers copper woven fabric tape 6 Lead sheath Extruded lead alloy 7 Reinforcement Bronze, copper or stainless steel tapes 8 Anti-corrosion jacket Extruded polyethylene sheath 9 Antiteredo protection 10 Bedding Polypropylene yarn 11 Armour Metal wire armour (single or double layers) 12 Serving Polypropylene yarn Approximate outside diameter range = 120 – 145 mm - 48 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Cable crossing sign Figure 8: Existing English Bluff Terminal 138 kV Cable Terminal , Tsawwassen, B.C. Figure 9: Existing Taylor Bay 138 kV Cable Terminal, Galiano Island - 49 British Columbia Transmission Corporation www.bctc.com Vancouver Island Transmission Reinforcement Project Project Description Rev. 4, January 2005 Figure 10: Existing Montague Harbour 138 kV Cable Terminal, Galiano Island, (Parker Island) Figure 11: Existing Maricaibo Terminal 138 kV Cable Terminal, Salt Spring Island - 50 British Columbia Transmission Corporation www.bctc.com