Siemens Industry, Inc. Power Technology Issue 113 Transient Overvoltages during System Restoration Following a Black Start Daniel W. Durbak Senior Staff Consultant daniel.durbak@siemens.com The various overvoltage stresses found during system restoration following a black start include steady state overvoltages that can last indefinitely (minutes), and transient overvoltages that have a limited duration. Switching surges are one type of transient overvoltage which have high frequency (100 Hz to 10 kHz) components that decay quickly (milliseconds). Switching surge waveforms typically contain only one, or just a few, predominant peaks. Another type of transient overvoltage is a temporary overvoltage (TOV); TOVs are of longer duration, from 50 milliseconds to seconds, and may have hundreds of high magnitude peaks. Since the risk of flashover in electrical insulation for transformers, shunt reactors, circuit breakers, and cables increases with magnitude and duration, the overvoltage must be compared to the corresponding voltage withstand rating of each component. For example, a 200 percent temporary overvoltage with a duration of 1 second may be a high risk for a transformer, while a 200 percent switching surge with a duration of 20 milliseconds may be an acceptable risk. Simulation of switching events with an electromagnetic transient program (EMTP) can provide insight into the expected transient overvoltages during system restoration. The three-phase EMTP models used for the analysis include the black start generators, large power transformers with core saturation, lines, cables, circuit breakers, surge arresters and loads. Energizing a large transformer during system restoration can result in higher TOVs than energizing during times of normal operation. TOV results are sensitive to several parameters, including the source impedance, system capacitances, transformer inrush current, load levels and circuit breaker closing times (switching angles). During the first steps of system restoration following a black start, a transmission system will generally be relatively weak with relatively high equivalent system inductances because few generators are on-line. Thus, the first system resonant frequency can be much lower than during normal system operation. Large capacitances from EHV transmission lines also contribute to the low resonant frequencies. Low levels of load reduce the damping and prolong the duration of the TOV. Sufficient load is also required to maintain stability of the turbines and steady state voltages within emergency limits. Top-down versus bottom-up restoration sequence options impact TOV results. Top-down system options restore the system from the highest (top) transmission voltage down to the distribution circuits. Bottom-up options restore the system from lower voltage circuits prior to the highest voltage circuits. The simplified single line diagrams of Figures 1 and 2 show systems in the early stages of restoration with the black start generator unit modeled on the left. The circuit breakers in these figures would be open initially, and then be energized in sequence from left to right. Energizing the generator step-up (GSU) transformer (on left) should not be a significant overvoltage concern. Power Technology August 2012 345 kV 1 115 kV 2 4 3 Z C 2 C 2 Figure 1 – Top-Down Restoration Option: Energize 345 kV Line before Significant Load 115 kV 1 2 345 kV 3 4 C 2 Z C 2 Figure 2 – Bottom-Up Restoration Option: Energize Local 115 kV Circuits and Load before 345 kV Circuits In the top-down option, the high side of the GSU is a 345 kV bus. Energizing Breaker 2 in Figure 1 creates a switching surge on the 345 kV line, where the highest overvoltage occurs at the open end, at Breaker 3. Surge arresters at the end of the line, or pre-insertion resistors in circuit breakers, are usually effective in limiting the peak of the switching surges. These types of switching events can initiate significant power frequency overvoltages if the generator cannot absorb all of the capacitive vars created by the energized system and effectively regulate the voltage at its terminal, or if the Ferranti rise at the end of the line is excessive. Significant TOVs are possible when Breaker 3 in Figure 1 closes to energize the large transformer on the right. At this step in the restoration sequence, the only load on the system is the auxiliary load at the generator terminal, which is relatively small and may not be large enough to significantly dampen any TOV from harmonic resonances. One major drawback of a top-down restoration option is that the load cannot be significantly increased at this step. For a top-down option to be viable from TOV perspectives, the first 345 kV overhead circuits energized prior to load must be kept as short as possible. Short lines have a low total capacitance (C), which yields higher resonant frequencies with the equivalent system inductance back to the source. Higher resonant frequencies usually result in lower TOV magnitudes. In the bottom-up option shown in Figure 2, the 115 kV bus is the high side of the GSU. The load restored from the 115 kV system is significantly larger than the auxiliary load at the generator terminal. Closing Breaker 2 to pick up the transformer to the 345 kV system does not usually initiate a significant TOV concern when the load on the 115 kV system is high enough to dampen the transients. Energizing Breaker 3 in Figure 2 creates a switching surge on the 345 kV line, where the highest overvoltage is on the open end, at Breaker 4. These types of switching events are generally not prone to a significant TOV with the assumption that the generator can absorb all of the capacitive vars created by the energized system. However, significant TOV events are possible when other large transformers are energized from the 345 kV system. In summary, TOVs resulting from energizing large transformers can be a critical concern of the overall electrical assessment of a system restoration plan following a black start. Increasing loads may help reduce high magnitude TOVs. Bottom-up restoration options may pose less of a risk for high magnitude TOVs. Top-down restoration options can also be viable when energizing short distances of EHV lines prior to energizing loads. Page 2