Standard: Distribution Design Manual Vol 4 – Underground Cable Distribution Standard Number: HPC-5DC-07-0004-2014 Document Control Author Name: Anthony Seneviratne Digitally signed by Anthony Seneviratne DN: cn=Anthony Seneviratne, o, ou, email=anthony.seneviratne@horizon power.com.au, c=AU Date: 2014.06.23 11:18:02 +08'00' Position: Standards Engineer Document Owner (May also be the Process Owner) Approved By * Name: Digitally signed by Justin Murphy DN: cn=Justin Murphy, o=Horizon Power, ou=Asset Management Services, email=justin.murphy@horizonpow er.com.au, c=AU Date: 2014.07.07 12:10:28 +08'00' Justin Murphy Position: Manager Power System Services Name: Digitally signed by Justin Murphy DN: cn=Justin Murphy, o=Horizon Power, ou=Asset Management Services, email=justin.murphy@horizonpo wer.com.au, c=AU Date: 2014.07.07 12:10:57 +08'00' Justin Murphy Position: Manager Power System Services Date Created/Last Updated June 2014 Review Frequency ** 3 yearly Next Review Date ** June 2017 * Shall be the Process Owner and is the person assigned authority and responsibility for managing the whole process, end-to-end, which may extend across more than one division and/or functions, in order to deliver agreed business results. ** Frequency period is dependent upon circumstances– maximum is 5 years from last issue, review, or revision whichever is the latest. If left blank, the default shall be 1 year unless otherwise specified. Revision Control Revision Date Description A 17/06/2014 Initial Document STAKEHOLDERS NOTIFICATION LIST The following positions shall be consulted if an update or review is required: The following shall be notified if an update or review is required Manager Engineering Services Engineering & Projects Manager Assets Management Services Operations Page 2 of 47 Print Date: 18/12/2013 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. TABLE OF CONTENTS FOREWORD .............................................................................................................. 7 1 INTRODUCTION .......................................................................................... 8 1.1 General .................................................................................................................... 8 1.2 Design Objectives .................................................................................................... 8 2 DESIGN PROCESS AND INPUTS ............................................................. 10 2.1 Safety in Design ..................................................................................................... 10 2.2 Network Requirements ........................................................................................... 10 2.2.1 Planning ................................................................................................................................ 10 2.2.2 Equipment ............................................................................................................................. 10 2.3 Installation Requirements ....................................................................................... 11 2.3.1 Cable Route .......................................................................................................................... 11 2.3.2 Termites ................................................................................................................................ 11 2.3.3 Equipment Location .............................................................................................................. 11 2.4 Equipment Compatibility......................................................................................... 12 2.5 Environmental and Approval Management ............................................................ 12 3 ELECTRICAL EQUIPMENT USED FOR UDS INSTALLATIONS ............. 13 3.1 Medium Voltage Ring Main Unit (RMU) Switchgear .............................................. 13 3.1.1 Outdoor RMU Kiosks ............................................................................................................ 13 3.1.2 Indoor RMUs ......................................................................................................................... 13 3.2 MV Cables, Joints and Terminations...................................................................... 13 3.2.1 MV Feeder Cables ................................................................................................................ 13 3.2.2 MV Transformer Cables ........................................................................................................ 13 3.2.3 MV Cable Joints .................................................................................................................... 14 3.2.4 MV Terminations ................................................................................................................... 14 3.2.4.1 Non-Loadbreak Terminations .............................................................................................................. 14 3.2.4.2 Load break Terminations..................................................................................................................... 14 3.3 Types of Substations .............................................................................................. 14 3.3.1 Modular Packaged Substations (MPS) ................................................................................. 15 3.3.2 Non MPS Arrangements ....................................................................................................... 15 3.3.3 Customer Owned Substations .............................................................................................. 16 3.3.4 Single Phase Padmount Transformers ................................................................................. 16 3.3.5 25 kVA Single Phase (SPUDS) Transformer ....................................................................... 16 3.3.6 10 kVA Rural Underground Transformer .............................................................................. 17 3.4 Service Pillars ........................................................................................................ 17 3.5 LV Cables, Joints and Terminations....................................................................... 18 Page 3 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 3.5.1 LV Feeder Cables: ................................................................................................................ 18 3.5.2 LV Service Cable .................................................................................................................. 18 3.5.3 LV Street Light Cables .......................................................................................................... 18 3.5.4 Other LV Cables ................................................................................................................... 18 3.5.5 LV Cable Joints/Terminations ............................................................................................... 19 4 VOLTAGE REGULATION .......................................................................... 20 4.1 Voltage Tolerance Limits ........................................................................................ 20 4.1.1 Statutory Voltage Tolerance Limits ....................................................................................... 20 4.2 Voltage Drop Criteria .............................................................................................. 20 4.2.1 Effect of Different Load Cycles ............................................................................................. 21 4.3 Voltage Drops and Line Currents in LV Feeders.................................................... 21 4.3.1 General ................................................................................................................................. 21 4.3.2 Effect of Load Unbalance ..................................................................................................... 21 4.3.3 Voltage Drops/Line Currents in Meshed Networks............................................................... 21 4.3.4 Voltage Drop Limits for LV Networks .................................................................................... 22 4.4 MV Voltage Regulation .......................................................................................... 22 4.4.1 Design Approach .................................................................................................................. 22 4.4.2 Computer Modelling .............................................................................................................. 22 4.4.2.1 Voltage Control Equipment ................................................................................................................. 23 5 UNDERGROUND DISTRIBUTION SCHEMES (UDS) ............................... 24 5.1 Design Procedure .................................................................................................. 24 5.2 Transformers .......................................................................................................... 24 5.2.1 Initial Requirements .............................................................................................................. 24 5.2.2 Transformer Selection .......................................................................................................... 25 5.2.3 Mixed Loads.......................................................................................................................... 25 5.2.3.1 Example 1 ........................................................................................................................................... 25 5.2.4 Regions other than Esperance ............................................................................................. 26 5.3 LV Network Design................................................................................................. 26 5.3.1 Primary Aim .......................................................................................................................... 26 5.3.2 Challenge for Network Designers ......................................................................................... 26 5.3.3 Use of Computer Packages .................................................................................................. 26 5.3.4 Aspects of Electrical Design ................................................................................................. 27 5.3.5 Determination of Cable Size ................................................................................................. 27 5.3.6 Selection of LV Feeder Routes ............................................................................................. 27 5.3.6.1 Proximity to Loads ............................................................................................................................... 28 5.3.6.2 Utilisation/Loading ............................................................................................................................... 28 5.3.7 Typical Route Lengths .......................................................................................................... 28 Page 4 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 5.3.8 Interconnection with Other Feeders...................................................................................... 28 5.3.9 Pillar/Cabinet Positioning and Alignment .............................................................................. 29 5.3.10 Other Considerations ............................................................................................................ 29 5.3.11 Typical Design Issues ........................................................................................................... 29 5.4 MV Design .............................................................................................................. 29 5.4.1 MV Cable Requirements ....................................................................................................... 29 5.4.2 MV Network Systems ........................................................................................................... 30 5.4.2.1 Radial Feeder System ......................................................................................................................... 30 5.4.2.2 Ring Main System ............................................................................................................................... 30 5.4.3 Hybrid System....................................................................................................................... 30 5.4.3.1 Satellite Substations ............................................................................................................................ 30 5.5 Automation ............................................................................................................. 31 5.6 Design Outputs ...................................................................................................... 31 5.6.1 Outputs - MV/LV Layouts ...................................................................................................... 31 5.6.2 Outputs - Cable Ducts .......................................................................................................... 31 6 DETERMINATION OF RECOMMENDED LOAD DEMAND VALUES ....... 32 6.1 Estimation of Load Demand ................................................................................... 32 6.2 Effect of Load Diversity on Maximum Demand ...................................................... 32 6.3 Residential Load ADMDs ....................................................................................... 32 6.3.1 Determination of ADMD when standard values are not used .............................................. 33 6.3.2 Non-Residential Load Demands ........................................................................................... 34 6.3.3 Residential Lot Classification ................................................................................................ 34 7 LV FEEDER PROTECTION ....................................................................... 35 7.1 Introduction ............................................................................................................ 35 7.2 Feeder Protection Policy ........................................................................................ 35 7.3 LV Fuse Selection Policy........................................................................................ 35 7.4 Prescribed Fuse Sizes (MV and LV) ...................................................................... 36 7.5 Maximum Lengths of LV Feeders .......................................................................... 36 7.5.1 General ................................................................................................................................. 36 7.5.2 Equivalent Length of LV Feeders ......................................................................................... 36 7.5.3 Feeder Equivalent Length Calculation .................................................................................. 37 7.5.4 Maximum Equivalent Lengths............................................................................................... 37 7.6 What if the Maximum Allowable Length is Exceeded?........................................... 38 7.7 Calculation of Fault Currents at End of LV Feeders ............................................... 38 7.8 Fault Current Ready Reckoner............................................................................... 40 7.9 Typical LV Fuse Time-Current Characteristics....................................................... 42 Page 5 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 8 INSTALLATION REQUIREMENTS ............................................................ 43 9 STREET LIGHTING.................................................................................... 43 APPENDIX A – REVISION INFORMATION ......................................................................................................... 44 APPENDIX B – CURRENT RATING OF UNDERGROUND CABLES .................................................................. 45 B.1 Continuous Current Rating ............................................................................................. 45 B.1.1 Rating Factors for depth of laying direct in the ground ................................................ 45 B.1.2 Rating Factors for depth of laying direct in a duct ....................................................... 46 B.1.3 Rating Factors for variation in Thermal Resistivity (3 core cables laid directly in the ground) ............................................................................................................................... 46 B.1.4 Rating Factors for variation in Thermal Resistivity (1 core cables laid directly in the ground) ............................................................................................................................... 46 B.1.5 Rating Factors for variation in Thermal Resistivity (3 core cables laid in duct buried in the ground)............................................................................................................................ 46 B.1.6 Rating Factors for variation in Thermal Resistivity (1 core cables laid in duct buried in the ground) ........................................................................................................................ 47 B.1.7 Rating Factors for Variation in Ambient Temperature ................................................. 47 B.1.8 Rating Factors for Variation in Ground Temperature .................................................. 47 Page 6 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. FOREWORD This volume is one in a series of five volumes, which together, form the Horizon Power Distribution Design Manual. The DDM is intended to be a comprehensive reference manual for distribution design work carried out by professional engineers and technical support staff. The five volumes are: Volume 1: Quality of Electricity Supply Volume 2: Low Voltage Aerial Bundled Cable Volume 3: Supply to Large Customer Installations Volume 4: Underground Residential Distribution (URD) Volume 5: Overhead Bare Conductor Distribution The DDM will also serve to initiate "newcomers" to distribution work in Horizon Power without them having to start from scratch. It serves to establish "standards" for design work to ensure that we get the best value from our facilities - not only in terms of initial cost, but also in terms of component availability, length of service life and cost-effective maintenance. In addition to this, the DDM will also serve as a teaching aid for courses run by Horizon Power. This volume describes the engineering process involved in designing and providing electricity supplies using underground cables. It describes the design process in detail, making use of standardised design information for use with routine work. Page 7 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 1 INTRODUCTION 1.1 General This document describes the engineering process involved in designing distribution underground networks. These networks typically originate from Zone substations as medium voltage feeders and are stepped down to low voltage networks through distribution transformers. Low voltage distribution networks then transmit power to customer installations, though some customers are supplied directly from the medium voltage networks. Although, underground cables do not account for a significant proportion of Horizon Power's networks at present, Horizon Power's policy mandates underground power supplies in all sub divisions including residential, rural residential, commercial and industrial. There are variations to this policy in the case of larger lot sizes greater than 10 hectares, which can be found in Horizon Power’s Underground Distribution Schemes Manual. Underground assets are capital intensive, both for Horizon Power and its customers and they need to be properly designed and constructed. It is imperative that a high level of engineering is put into their designs, particularly because cables are buried and are not visible. Effort expended during design could avoid unnecessary expenses and ensure that the requirements (Horizon Power's and its customers’) are catered for. Each cable network may require different design considerations, configurations, layouts, etc. As such, there may be many different ways to approach a design. The information contained in this manual will assist the designer to develop a structured design approach, and ensure that the optimum configuration is selected at all times. 1.2 Design Objectives The objectives of underground cable design are to: a) b) c) d) e) f) g) h) Reduce cost to customers; Reduce life cycle costs; Provide greater durability, with due consideration to location in rocky, saline and marshy soils; Ensure safety of workers and the general public (safety in design); Promote environmental compatibility; Ensure electromagnetic field compatibility; Promote public acceptance (e.g. easements); and Attain and exceed the required supply quality and reliability standards. Page 8 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. The following factors are to be considered before the design can commence: a) b) c) d) e) f) g) h) Potential number of customers and total load; Estimation of potential load growth; Availability and/or requirement for interconnections; Selection of voltage for line operation; Size and location of loads (Bulk supply, transformers); Selection of route; Length of cable route; and Life cycle costs. Note: The size and type of cable to be used will be dictated by the capacity (load) to be carried by the cable during its lifetime together with voltage drop, thermal rating and fault rating considerations. Page 9 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 2 DESIGN PROCESS AND INPUTS This section covers the various considerations and inputs needed as part of design. The steps involved in the design of an underground cable network will depend on the individual project and the context in which the design is performed. It is an iterative process, with the designer making some initial assumptions, e.g. cable type and rating, which may later be adjusted as the design is checked and gradually refined. Delivering an optimum arrangement that meets all constraints as the final outcome. Horizon Power mainly uses underground cable simulation software to aid the design process. 2.1 Safety in Design Whenever design work is undertaken to construct new distribution network assets, or modify existing assets, demonstration of due diligence with respect to safety is required. This must cover the full life cycle of the asset that is created or the remaining life of the modified asset and thought about early in the design stage. The essential elements covering a designer’s responsibility in ensuring the safety of the asset during its life cycle are addressed in the document, Guideline – Safety in Design - HPC-2DC-17-0001-2014. 2.2 Network Requirements Design shall take into account both present and future network requirements. This information is typically covered in the relevant planning report, design specification and equipment specifications. 2.2.1 Planning For new distribution networks or extension to existing distribution networks, planning is carried out during concept development stage. Details covered in the planning reports that need to be considered include but not limited to: a) b) c) d) e) f) g) 2.2.2 Load size; Load distribution centres; Load cycle; Nature of load; Required transfer capacity; Potential interconnection point; and Automation requirements. Equipment Design specification and equipment specifications play a role in capturing requirements that need to be addressed during design. This includes the following: a) b) Equipment and cable rating for normal load, emergency load and for fault conditions (selection of medium voltage cables as feeders based on continuous current rating is covered in Appendix ‘A’); Equipment or cable operating conditions (e.g. Broome versus Esperance); Page 10 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. c) d) e) Network tolerance limits (e.g. statutory voltage tolerance limits); Standard installation requirements (refer to clause 2.3); and Protection grading requirement. In special cases, there may also additional requirements such as: i. Customer request for a higher security supply; and ii. Coordination with road lighting design 2.3 Installation Requirements Installation condition has a significant impact on the overall technical design of an underground distribution network. Factors that must be considered by designer include but not limited to the following: a) b) c) d) e) f) g) h) i) j) k) l) 2.3.1 Ambient air and ground temperature; Soil type and terrain such as: sandy, rocky, water table, etc.; Soil or backfill thermal resistivity; Cable installation arrangement (i.e. numbers of circuit within same easement, use of conduit, installation depth, etc.); Space requirement for installation of ground mounted equipment; Termites activity; Environmental risk such as fire, flood, acid sulphate soil and erosion; Pollution such as dust, salt and noise; Proximity to other utility assets and congestion level from existing services; Proximity to metallic/conductive structures; Proximity to occupiable structures; and Soil salinity. Cable Route Evaluate the terrain to determine issues with ground. For example, suppose a medium voltage underground cable is to be constructed to supply a customer remote from a zone substation, and the line route traverses an area of rock, it would seem prudent for the designer to consider the issues involved in embedding cables in rock and the associated cost. 2.3.2 Termites Termite protection must be installed in all areas prone to termite attack. 2.3.3 Equipment Location Equipment must be suitable for the environment in which it operates. For example, a ground mounted transformer with open bushings may not be suitable for use outside a cement plant or quarry, where the build-up of fly-ash or dust may lead to nuisance tripping or a disproportionately high level of maintenance. Others include mines sites, with open air blasting, etc. Page 11 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. The location of ground mounted substations and other equipment shall take into consideration access, fire separation, touch and step potential, and other related issues. (Refer to Substation Installation Technical Requirements –HPC-9DJ-230001-2012 and Distribution Line Earthing Standard –HPC-9DC-08-0001-2012). 2.4 Equipment Compatibility Standard equipment shall be used as much as possible. In certain cases however, use of non- standard equipment may be required to deliver the required outcome or to deliver the most cost-effective solution. In such cases, equipment compatibility must be considered. Where unusual conditions or other circumstances warrant using alternative equipment the disadvantages in terms of readily available replacements and operational issues must be considered. Cable accessories such as joints and terminations for example, can only be used for cables within a certain size range. Other factors that need to be considered include but not limited to: a) b) Equipment’s rated voltage Equipment’s normal load and fault rating In cases where non-standard equipment is required as part of the design, the designer should seek formal approval from the Standards Group prior to proceeding with the final design. 2.5 Environmental and Approval Management Environmental sensitive areas, land usage, condition and ownership issues along a cable installation route can have a significant impact on the overall project cost and timeline. Relevant factors that need to be considered by designers include but not limited to the following: a) b) c) d) e) f) g) Aboriginal heritage sites or areas; Area with bio-security weeds, pests and disease spread risk (i.e. dieback disease); Threatened ecological communities, sites with declared rare flora and fauna; Land with native title; Protected wetlands; Waste management areas; and Registered and/or private lands. Prior approvals are typically required to perform work at or close to these sites. Where vegetation clearing is required, a permit shall also be obtained prior to proceeding with the clearing. Current statutory processes require a range of approvals to be obtained prior to commencement of works. Due to the time taken to obtain these approvals, these issues must be considered at the commencement of a project. As per the Western Australian Distribution Connections Manual (WADCM Section 6.12) environmental and heritage impacts must be investigated and managed by the applicant for power supply and their agent. Page 12 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 3 ELECTRICAL EQUIPMENT USED FOR UDS INSTALLATIONS 3.1 Medium Voltage Ring Main Unit (RMU) Switchgear 22 kV and 33 kV RMU switchgear is used for switching of the medium voltage network. They are used as a "standalone" kiosk or incorporated into a RMU integrated package substation (only 2 + 1 option is currently available as a packaged substation). 11 kV networks shall make use of 22 kV switchgear. 3.1.1 Outdoor RMU Kiosks The commonly used outdoor RMU combinations at 22 kV and 33 kV are: a) b) c) d) e) f) g) 2 switches plus 1 fuse switch (2+ 1); 2 switches plus 2 fuse switches (2+2); 2 switches plus 3 fuse switches (2+3) – only at 22 kV; 3 switches plus 0 fuse switches (3+0); 3 switches plus 1 fuse switch (3+1); 3 switches plus 2 fuse switches (3+2); and 4 switches plus 0 fuse switches (4+0); 22 kV and 33 kV RMUs are incorporated into either 3, 4 or 5 way kiosks (e.g. 2+2). RMUs are installed in a freestanding aluminium kiosk mounted on a steel frame. This steel frame is buried in the ground to provide a firm foundation and allows easy access to the cables and terminations below the switchgear. 3.1.2 Indoor RMUs Indoor compounds comprising brick enclosures with roof are used to house RMUs and transformers. They are generally used to cater for larger loads (> 630 kVA). Extensible and non-extensible MV RMUs are also installed within buildings owned by customers. 3.2 MV Cables, Joints and Terminations 3.2.1 MV Feeder Cables (a) (b) 3.2.2 3 x 1 core, 95 mm2, 185 mm2, 400 mm2 aluminium and 240 mm2 copper XLPE insulated, PVC/HDPE sheathed cables are used on 22 kV networks. 3 x 1 core, 185 mm2 aluminium and 240 mm2 copper XLPE insulated, PVC/HDPE sheathed cables are used in 33 kV networks. MV Transformer Cables (a) (b) 3 X1 core, 35 mm2 aluminium XLPE insulated, PVC/HDPE sheathed, cables are use on 22 kV systems 3 X 1 core 50 mm2 aluminium XLPE insulated, PVC/HDPE sheathed, cables are use on 33 kV systems Page 13 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 3.2.3 MV Cable Joints Currently, all MV straight-through joints, including transition types, use heat shrink materials, except where otherwise approved. All cable joints shall be installed in accordance with details outlined in the Underground Cable Installations Manual: HPC- 5DJ -03-0001-2012, and the manufacturer's instructions supplied with joint kits. Where not published in specific detail clarification shall be sought from the supplier. In any case, sound engineering practice shall be used. 3.2.4 MV Terminations All pole top cable terminations and some transformer terminations use heat shrink materials, except where otherwise approved. Separable insulated connectors (non-Ioad break type) are used for terminations on transformers (satellite and ringmain), Modular Packaged Substations (MPS), small single phase pad mount transformers (SPUDs) and ringmain switchgear with integral bushings. 3.2.4.1 Non-Loadbreak Terminations The MV connectors, bushings and apparatus used in Horizon Power's underground system are shown in table below: 3.2.4.2 Type of Connector Connector Function Non-Load Bushing break Mounted on the MV side transformer to connect cables Non-Load Elbow break Terminates the XLPE cable to allow connection with the MV bushing of Dead-End Plug Used to protect the non load break elbow when it is not connected to a transformer bushing Dead-End Receptacle Used to protect the transformer bushing when there is no non load break elbow connected to it. Load break Terminations Load break terminations are currently not used by Horizon Power. 3.3 Types of Substations Horizon Power may require that the supply arrangement to an installation be via a particular "type" of substation, i.e.: "District" Substation (With LV street feeds to/from the substation); "Sole Use" Substation (With no LV street feeds); or "Customer Owned" Substation (Supplied at distribution MV voltage levels). Page 14 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. Consideration may also be given to installing a pad-mount or Modular Package Substation (MPS) in lieu of the more common brick enclosure substations. There may be cost advantages as well as land/space advantages with this option. The decision as to which type is selected depends on several factors, including: a) Size of customer's load; b) Location of customer's load centre on the property, and distance of the same from the street boundary; c) Type and nature of loads within the installation (disturbing, passive, etc.); d) Nature of Horizon Power's existing distribution network and loading levels on other substations in the vicinity; e) Horizon Power's need to connect LV street feeds to/from the substation; f) Fire separation requirements LV street feeds may be required to/from a substation for the following reasons: 3.3.1 3.3.2 a) The customer requires a "back-up" LV supply to the installation; b) There will be future developments and load growth in the immediate area; c) The customer's load is expected to increase in the future; d) Ease of maintaining equipment in the substation (e.g. with street feeds into the substation, the customer's load can be partly met while the MV switchgear is being maintained); etc. Modular Packaged Substations (MPS) a) A MPS comes complete with a single transformer and LV switchgear. It is housed in a self contained metal enclosure and is installed on an inverted, direct buried concrete culvert. If MV switchgear is required, this is also housed in a self-contained metal enclosure which is installed adjacent to the transformer on a direct buried steel mounting frame. b) MPS’s are used only as District Substations. They are not used as Sole Use substations and are not fire rated. c) MPS is the preferred arrangement for a District substation with a maximum load of 630 kVA after allowing for future load growth, and where there is no requirement for the substation to be fire rated. Non MPS Arrangements a) A Non MPS arrangement comprises a combination of one or more transformers plus LV switchgear and MV switchgear as required. Each of these items is a separate component housed in a self contained metal enclosure. The transformer is installed on an inverted, direct buried concrete culvert. The LV and MV switchgear enclosures are installed on direct buried steel mounting frames. b) Non MPS components are not installed as a single package. They can be installed either as a “cluster” substation or in a fire rated enclosure (see Section 6). In the latter case, the culvert and switchgear mounting frames are not required. Page 15 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. c) Non MPS arrangements can comprise multiple transformers, with 1000 kVA being the largest individual transformer size. They can be used as both District and Sole Use substations. A Non MPS arrangement shall be used where; 3.3.3 A Sole Use substation is required; or Multiple transformers are required; or The maximum load is greater than 630 kVA after allowing for future load growth; or The substation is to be fire rated. Customer Owned Substations Typically, for loads greater than 4 MVA, a Customer Owned substation shall be provided. Neither the MPS nor the Non MPS arrangements are suitable for Customer Owned Substations. Horizon Power shall provide extensible MV switchgear necessary for connection to the network. The equipment shall be installed in a switch room constructed by the customer, along with the customer’s own MV switchgear (See DSM-3-22 for details). Where a customer’s load is less than 4 MVA, MV outdoor ground mounted switchgear can be considered. (See DSM-3-23 for details). A Customer Owned Outdoor Ground Mounted Substation cannot be upgraded for loads above 4 MVA. In the event that the customer’s load increases above 4 MVA, the substation shall be converted to a MV Indoor Ground Mounted Substation, which will require a switch room to be built. In areas with overhead networks only, MV outdoor aerial mounted switchgear may be used (See DSM-3-24 for details). 3.3.4 Single Phase Padmount Transformers The padmount single phase transformer is available in both 10 kVA and 25 kVA units for 12.7 kV Single Wire Earth Return (SWER) operation or for 22 kV "Two Phase" operation. The transformers are supplied configured for 240 volts, but can be re-configured to 480 volts for "sole use" applications. 3.3.5 25 kVA Single Phase (SPUDS) Transformer The transformer is mounted on a hot-dipped galvanised steel base. The HV side of the transformer is equipped with either 2, 3 or 4 x 200 A tapered bushings which allow connection with separable non loadbreak elbow connectors. An internal, oil-immersed HV fuse is fitted inside the transformer tank. The unit is fitted with an externally operated, off-load tap-changer with steps of 0, ±2.5% and ±5.0%. The LV feeder cables, outgoing from the LV compartment, are protected by one "Red Spot" fuse (100 Amp) for 240 V or two "Red Spot" fuses (63 Amp) for 480 V. For further information refer to SPUDS design and operation manual. Page 16 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 3.3.6 10 kVA Rural Underground Transformer The transformer is mounted on a concrete base. The HV side of the transformer is equipped with 2 x 200 A tapered bushings which allow connection with separable non-loadbreak elbow connectors. An internal, oil-immersed HV fuse is fitted inside the transformer tank. The unit is fitted with an externally operated, off-load tap-changer with steps of 0, ±2.5% and ±5.0%. The outgoing mains from the LV compartment, are protected by one "Red Spot" fuse (50 Amp) for 240 V or two "Red Spot" fuses (32 Amp) for 480 V. 3.4 Service Pillars Customer service pillars facilitate the connection of house services, customer bulk supply cables or interconnections of main LV street cables. In dusk to dawn street lighting areas, some may also provide supplies to streetlights. The service pillars are of a dark-green, polyurethane construction, with base partly buried in the ground. Figure 3-1 shows typical pillars. Figure 3.1 Typical Pillars There are two types of service pillar: 1) "Mini" Pillar (with tunnel terminal blocks): Tunnel block accepts up to 5 outgoing circuits (to 35 mm2 copper cable), usually connected as follows: Pillar on cable side of road: Connect incoming 3 core 25 mm2 cable from LV feeder; and Connect outgoing 2 x 3 phase or 2 x 1 phase services; and outgoing 3 core 25 mm2 road crossing service cable Page 17 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. Pillar on other side of road: 2) Connect incoming 3 core 25 mm2 road crossing service cable; and Connect outgoing 2 x 3 phase or 2 x 1 phase house services Universal" Pillar (with links and tunnel terminals): The universal pillar can be used as: an "interconnector" pillar with provision for solid links, to form a normally open or closed network point. a location to reduce the size of LV cable; to service a large single load (e.g. multiple dwelling lot) with LV HRC fuses (J type) to 315 A The universal pillar also contains tunnel terminals for service cables, as per "mini" pillar. Note: both "mini" pillars and "universal" pillars have provision for a fused terminal for an adjacent lighting column. 3.5 LV Cables, Joints and Terminations 3.5.1 LV Feeder Cables: (a) (b) (c) (d) 3.5.2 120 mm2, 3 core, solid Aluminium conductor, Copper screened (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed 185 mm2, 3 core, solid Aluminium conductor, Copper screened (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed 240 mm2, 3 core, solid Aluminium conductor, Copper screened (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed 630 mm2, 1 core, solid Aluminium conductor, Copper screened (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed neutral neutral neutral LV Service Cable 25 mm2, 3 core, solid Copper conductor, Copper (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed 3.5.3 neutral screened neutral LV Street Light Cables Single core 10 mm2 and 16 mm2 stranded copper, XLPE insulated, helical copper wire neutral screen, PVC sheathed. 3.5.4 Other LV Cables For minor branch and road crossing services use: 25 mm2, 3 core, solid Copper conductor, Copper screened (Wave Wound), 0.6/1 kV, XLPE insulated, PVC sheathed cable. Page 18 of 47 neutral Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 3.5.5 LV Cable Joints/Terminations There are many variations of joints and terminations being used which are summarised below: 1) feeder cable straight through and breeches joints; 2) feeder cable to service cable tee joints; 3) feeder cable pole terminations (to bare and LV ABC overhead conductors); 4) feeder cable termination at universal pillar; 5) feeder cable termination at fused switch; 6) service/street light cable termination at mini pillar; 7) service/street light cable terminations (to bare and LV ABC overhead conductors); and 8) service/street light cable straight through and tee joints. Page 19 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 4 VOLTAGE REGULATION 4.1 Voltage Tolerance Limits 4.1.1 Statutory Voltage Tolerance Limits Horizon Power declares the voltage level at a customer’s point of supply as within ± 6% of the nominal 240 V single phase and ± 6% of the nominal 415 V three phase. As such, the maximum and minimum phase-to-neutral voltage levels at any point of supply on the LV network shall be within 225 V and 254 V for single phase supplies and within 390 V and 440 V for three phase supplies (under normal network conditions). In accordance with AS 61000.3.100 – 2011, Horizon Power expects to adopt the new voltage standard 230 V +6%, -10% for single phase and 400 V +6%, -10% for three phase supplies sometime in the future. When planning and designing a residential distribution network, the designer has to ensure that the voltages at any point of supply on the network will be within the statutory voltage tolerance limits, under normal network conditions. 4.2 Voltage Drop Criteria Impedance in each of the following components of the distribution system leads to voltage drop: 1) Medium Voltage Feeder; 2) Distribution Transformer; 3) Low Voltage Network; 4) Customer Service Leads/Cables. After a distribution system has been constructed, there are only two locations where voltage levels can be adjusted: a) at the zone substation (bus-bar voltage set-point and the use of Line Drop Compensators), and b) at the distribution transformers (off load tap changers). It is therefore important that the non-adjustable parts of the system be designed adequately to fully utilise the voltage control equipment at these locations to keep the customers’ voltages within the statutory voltage tolerance limits. Table 4.1: - Voltage Drop Limits with respect to nominal voltage Non-Adjustable System Components Medium Voltage Feeder Distribution Transformer Low Voltage Network Customer Service Cable Maximum Voltage Drop Limits 5.0% 4.0% 5.0% 2.0% Thus to compensate for voltage drops caused by components in Table 4.1, the Automatic Voltage Regulator (AVR), Line Drop Compensator (LDC) and distribution transformer taps are set accordingly. Page 20 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. With a 2% voltage drop assumed for customer service cables, “coincident” voltage drops, when taken together with zone substation LDC Buck/Boost and distribution transformer tap options are considered a reasonable balance to achieve: 4.2.1 a customer’s voltage at the meter panel between ± 6% of the nominal 240 V. Maintenance and Emergency Voltage Limits are shown in Table 4.2. Effect of Different Load Cycles The majority of customers in a “typical” area will have similar, “normal” load patterns. Some, however, will have load patterns which vary and in extreme cases could be completely opposite to the “normal” pattern. These are usually single customer loads. Such loads of relatively small magnitude with respect to the total feeder load (or of relatively large magnitude with respect to the total distribution transformer load) can be catered for by adjusting the tap settings on the transformer supplying the load. Instances could also arise where a particular MV feeder load profile becomes dominant and “masks” the normal load profile of the remaining feeders on the zone substation. Such a feeder could influence the response of the LDC, to the detriment of the remaining feeders and their individual loads. This problem falls into network load modelling and is not dealt with in this manual. 4.3 Voltage Drops and Line Currents in LV Feeders 4.3.1 General A three phase, four wire distribution system servicing a large proportion of single phase residential loads together with three phase commercial/industrial loads is subject to rapidly fluctuating currents. These currents produce corresponding rapidly fluctuating voltages on the system. 4.3.2 Effect of Load Unbalance It is inevitable that an imbalance between the line currents on the three phases of a feeder will occur if the feeder services a large number of single-phase loads (e.g. residential loads). This imbalance in the line currents leads to a current which flows in the neutral conductor, which adds to the voltage drop caused by the current flowing in the phase conductor. The voltage drop calculation (in LV DESIGN software) takes into account this added voltage drop caused by the load unbalance , as necessary. 4.3.3 Voltage Drops/Line Currents in Meshed Networks A “Null Point ” is a point on the meshed portion of the network, through which no line current flows - the voltage drop from the transformer to either side of the null point is also the same. Page 21 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. In practice, the location of the null point in the meshed portion of the network can change as the loads on the meshed portion vary during the day. However, during times of peak load, the location of the null point would be approximately at the same position. The location of the null point in the meshed portion of the network signifies that the voltage drop from the transformer to either side of the null point is within the maximum allowable limit. Hence, once the location of the null point is known, the network can be assumed to be “opened” at this point and the cable sizes are appropriate to ensure that the voltage drop to the null point (and hence to all other points on the meshed portion of the network) remains within the maximum allowable limits. 4.3.4 Voltage Drop Limits for LV Networks One of the voltage drop criteria is that the maximum allowable voltage drop limit for the LV network is 5.0%. This translates to a phase-to-neutral voltage drop of 12 V between the transformer LV terminals and the Point of Supply of any load on the network. This limit, however, applies for normal or steady state conditions. In general, the network designer shall ensure that the design of the network conforms to the voltage drop limits shown in Table 4.2. Table 4.2 - Maximum Voltage limits for LV Networks Condition Normal or Steady State Maintenance Emergency % ±5.0 ±7.0 ±9.0 Voltage Limits (Phase to Neutral) Volts Max (V) Min (V) 12 252 228 17 257 223 22 262 218 When designing the network, maintenance or emergency conditions must also be considered. Interconnection with adjacent networks is necessary to maintain the supply. 4.4 MV Voltage Regulation 4.4.1 Design Approach The design approach is generally as follows: 4.4.2 (a) Determine loads for maximum, lightly loaded and maintenance conditions. (b) For least cost option, check that voltage remains within limits for the various loads. (c) If voltage goes outside limits try various options. (d) Compare options to determine optimum solution. Computer Modelling In many instances the cable electrical data is entered into a suitable computer program for analysis such as Horizon Power’s Power Factory (Digsilent) program. This calculates the voltage variations for each option. The designer still needs to compare the options. Page 22 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 4.4.2.1 Voltage Control Equipment Some voltage control is built into the standard system equipment as follows: (a) Distribution Transformers: Out of service manual tap changes of ±2.5% and ±5%. (b) Zone Substation Transformers: Typically ±10%, ±13% or +10 - 20%. In urban areas it has been standard practice to utilise the above two measures only and choose appropriate conductor sizes and distribution transformer location/quantity to provide satisfactory voltage regulation. These are covered in Clause 5.3 - LV Network Design. Where longer lines are used it can become uneconomic to increase the conductor size. Additional forms of MV voltage control may become the lowest cost option. The three options usually considered are as follows: a) Capacitors -typically used for lines of moderate length (effective when permanently in service) b) Reactors - typically used for very long lightly loaded lines (effective when permanently in service) c) Regulator - can be used to raise or lower voltage (output voltage varies to suit load conditions) Page 23 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 5 UNDERGROUND DISTRIBUTION SCHEMES (UDS) 5.1 Design Procedure The Underground Distribution Schemes Manual (UDSM) sets out the procedure for a subdivision that is to be supplied with electricity from Horizon Power’s network. The UDSM covers the policies, processes, practices, requirements and equipment that are relevant to designing underground distribution systems and it shall be referred to when designing Underground Distribution Schemes. The challenge for the designer is to produce the most economical selection of equipment, location and cable size that will adequately service the loads within the constraints of achieving Horizon Power’s "quality of supply" objectives. (Refer to HPC-5DC-07-0001-2012: Distribution Design Manual Volume 1 – Quality of Electricity Supply). Section 6 – Determination of Recommended Load Demand Values, provides information about determining loads for underground distribution schemes. General steps involved in design are summarised below: 5.2 Transformers 5.2.1 Initial Requirements Count the lots in the development from which the total number of transformers can be calculated (refer to HPC-3DC-07-0001-2012: Information – Electrical Design for Distribution Networks: After Diversity Maximum Demand). Based on the number of lots to be serviced by a transformer, do a rough grouping of the lots and select tentative transformer locations. Relocate transformers after Step (b) to optimise loading on the LV distribution cables available. Identify non-residential loads such as pumps, shops, schools etc. Identify discrete or sole use transformer loads. The transformer substation should be located as near as possible to the electrical load centre of a group of lots in order to best balance the loads between feeders. This is achieved by locating the transformer close to road intersections and junctions. The designer must be prepared to regroup lots and change transformer locations as the design develops. Standard transformer ratings used by Horizon Power for underground distribution schemes are: i. 160 kVA MPS and non MPS ii. 315 kVA MPS and non MPS iii. 630 kVA MPS and non MPS iv. 1000 kVA non MPS Note: The above transformers are available as indoor or outdoor units Page 24 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 5.2.2 Transformer Selection The designer must also be aware of other factors that may affect transformer selection and location unique to the subdivision under development, such as: 1) 5.2.3 Isolated pockets of UDS that may be serviced from: Satellite substations; Spare capacity from adjacent non residential loads; and Spare capacity from adjacent separate developments. 2) Pockets never likely to be expanded and satisfactorily serviced from a 315 kVA substation (i.e. no future 630 kVA requirement). 3) Topographical features and ground conditions prohibiting installation. 4) Strategies adopted by developers for different schemes. Mixed Loads If the full utilisation of Horizon Power assets is to be achieved then mixed loads are inevitable. Different peak load times for mixed loads must be taken into consideration when selecting transformer ratings or grouping of lots. 5.2.3.1 Example 1 How many residential lots can be supplied from a substation feeding a high school? Available information: School maximum demand is 220 kVA (clause 6.3.2) School is supplied from a 315 kVA transformer ADMD for Esperance is 3 kVA Residential peak occurs between 5:30 and 6:30 PM. School load has been measured at 20% peak during domestic peak. Transformer kVA = (No. of lots x ADMD) + (220 x 20%) Hence, No. of lots = {315 - (0.2 x 220)} / 3.0 = 90 lots now and ultimately No. of lots = {630 - (0.2 x 220)} / 3.0 = 195 lots with 630 kVA transformer It appears that about 195 lots may be mixed with a high school load provided that a 630 kVA transformer replaces the 315 kVA transformer sometime in the future. However, the school peak occurs at 11:30 am when the domestic load has been measured at 50% maximum demand, Therefore, No. of lots = (315 - 220) / 1.5 = 63 lots now and ultimately = (630 - 220) / 1.5 = 273 lots with 630 kVA transformer Page 25 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. An analysis of the above shows that certain options exist depending on the particular circumstance of the subdivision requirements. 1) 63 lots could be serviced now from a 315 kVA substation to be upgraded later to a 630 kVA substation. This would underutilise the 630 kVA transformer unless, as is often the case, there was a requirement for spare capacity (up to 132 lots) at a later stage of development. 2) 195 lots could be serviced now from a 630 kVA transformer saving the cost of upgrade but incurring additional capital costs and early transformation losses. In general, it may be prudent not to take advantage of the 120% overload capacity of the transformer. This allows for contingencies, common in mixed load applications. 5.2.4 Regions other than Esperance It is standard practice to install 630 kVA transformers initially because the flat load profile due to air-conditioning allows little scope for cyclic rating use. 5.3 LV Network Design 5.3.1 Primary Aim The primary aim when designing a LV network is to select and locate equipment that will adequately service both present and future customer loads and also satisfy the reliability and quality of supply standards stipulated by the Electricity Industry (Network Quality and Reliability of Supply) Code 2005. 5.3.2 Challenge for Network Designers The challenge for any network designer is to avoid over/under design of the network. Over design is costly in terms of unnecessary capital investment, whilst under design leads to high losses, costly investigation and rectification of Quality of Supply related complaints. Extra effort expended in optimising the design of LV networks results not only in the efficient utilisation of capital costs but also impacts on the MV network, affecting the number and location of distribution transformers. 5.3.3 Use of Computer Packages Typically, the design studies and calculations are carried out using specially written computer programmes, for the more complex cases or where accurate results are required. Alternatively, manual calculations can sometimes be used, especially for simpler cases or where only estimates are required. LV DESIGN is a PC based computer program, written specifically for studying LV networks. It is particularly suited for underground distribution scheme designs, with distributed loads along the LV feeder. The program automatically accounts for load unbalance and diversity. However, it can also be used to calculate the voltage drops and line currents caused by large commercial loads. LV DESIGN can be used to investigate the impact of new large loads within residential estates, e.g. shopping centres, pumps, etc. Page 26 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. GIS (Geospatial Information System) is one of Horizon Power's prime computer systems. Various distribution plant items are recorded in the system for most parts of the state, e.g. transformers, MV and LV cables and many other assets. Customer property boundaries are also recorded in the GIS database. GIS can be used by the designer to obtain information quickly about the existing supply system around a new proposed installation, from which, various supply alternatives can be considered. GIS can also be used to down-load information on the supply system onto Power Factory (Digsilent) for later analysis. 5.3.4 Aspects of Electrical Design The electrical design aspects: of distribution feeders generally involves the following 1) Estimation of load demands; 2) Selection of distribution transformer; 3) Planning of network layouts; 4) Calculation of Voltage Drops and Cable Currents; 5) Selection of cable sizes to satisfy the voltage drop and current capacity requirements; and 6) Selection of fuse/protection device (if applicable). These aspects are explained in the following sections. 5.3.5 Determination of Cable Size The size of LV cable is chosen to ensure that all of the following criteria are satisfied: 5.3.6 1) Voltage drops during peak network load times being within maximum allowable limits (and during minimum load times being within minimum allowable limits) - Refer to Section 4 2) De-rated current carrying capacity of cable being adequate so that load currents will be within the capacity, not only during steady state conditions, but during maintenance/emergency conditions when the LV network is interconnected with others (Refer to Appendix B); 3) Other cable current ratings (e.g. summer, winter) not being exceeded, wherever applicable ( Refer to Appendix B and cable manufacturers data); 4) Cable impedance satisfying the LV fuse/protection requirements (so that at times of fault at the end of the feeder, the fault current will be large enough to be “seen” by the LV fuse and hence, cleared in time to prevent damage to the cable ( Refer to Section 7). Selection of LV Feeder Routes When selecting LV feeder routes, the designer should take the following into account: Page 27 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 5.3.6.1 Proximity to Loads The feeder route should be chosen such that it will “start to be loaded” as close to the transformer as possible. This is facilitated by locating the transformer as close to heavy load centres as possible or as close to the “centre of gravity” of a group of loads. Feeder routes where the feeder only “picks up” loads after a considerable distance away from the transformer should be avoided (as this causes larger voltage drops than necessary in the initial part of the feeder). 5.3.6.2 Utilisation/Loading LV feeder routes must be chosen such that the transformer will service the required number of loads determined on the basis of design load demand values (refer to Section 6 – Determination of Recommended Load Demand Values and HPC-3DC-07-0001-2012 Electrical Design for Distribution Networks: After Diversity Maximum Demand). 5.3.7 Typical Route Lengths The length of a LV feeder affects the: 1) voltage drop on the feeder; and 2) fault current at the end of the feeder. Very long LV feeders should generally be avoided since this would only result in medium voltage drops than necessary, cause improper operation and lead to possible conductor burnouts. Designs may require up to 500 m route lengths. However, route lengths in excess of 400 m are unusual and may indicate poor substation location. Cable routes should be selected so that feeders start to pick up load as close to the substation as possible. This can be achieved by locating the substation close to the electrical load centre of a group of residential loads or non residential loads. Cable routes that pick up loads at significant distances from the substation entail substantial voltage drops to occur. This can impact adversely on conductor costs and losses. 5.3.8 Interconnection with Other Feeders If a transformer becomes unserviceable, its LV network has to be supplied by adjacent transformers until repairs can be effected or a replacement put into service. As such, the LV network should be provided with sufficient numbers of “interconnecting” points (e.g. via the use of removable solid links, fuse switches) to allow lateral interconnections between LV networks of adjacent transformers. When selecting LV routes, the designer should select routes which can assist in the provision and location of these “interconnecting points”, if possible. The interconnection criteria generally used by Horizon Power is to ensure that the backbone feeder of any transformer can be interconnected with other LV feeders from adjacent transformers, at least twice. If the number of interconnections cannot be provided due to certain constraints, the designer should consider using a smaller transformer size instead. Page 28 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 5.3.9 Pillar/Cabinet Positioning and Alignment When selecting the LV feeder route, the designer must also give consideration to the positioning of Pillars and Cabinets. 5.3.10 Other Considerations Sometimes, in order to mitigate the excessive voltage drops caused by large motor starting currents, it may be necessary to connect up large motors (e.g. large reticulation and sewerage pumps) via a dedicated LV feeder. A similar requirement may be called for to mitigate any interferences caused by “potentially disturbing electrical loads” to other customers on the same LV feeder, e.g. light industrial customers with arc-welders, thyristor controlled motor speed drives, large motors. On the other hand, from the nature of the load itself, or due to special requests from the customer for a more “secure” supply arrangement, certain loads may need to be serviced via dedicated LV feeders or from “sole-use” transformers (e.g. small hospitals, retirement villages, bulk cold food storages). 5.3.11 Typical Design Issues When designing the LV feeder and street lighting, voltage drops with various cable sizes are calculated. If the voltage drop at the end of a radial LV feeder exceeds the prescribed limits the following alternative design choices are possible: a) Adjust lot grouping or change transformer boundaries b) Relocate the transformer to a site nearer the electrical load centre of the grouped lots. c) Upgrade cable size d) Check current flows against the current rating of the cables e) Check LV feeder protection fuse size 5.4 MV Design 5.4.1 MV Cable Requirements When designing the MV layout, the shortest and most direct MV cable routes should be selected. If the design is for a large UDS: a) a detailed and comprehensive study of the existing and proposed MV feeders supplied from adjacent zone substations shall be carried out to determine the effect of the new load on the overall MV network and system security; b) in the overall area concept plan, the location of all the transformers and all existing MV mains adjacent to the subdivision (obtained from GIS) shall be marked; c) transformers that are to be supplied as "satellites" from the adjacent overhead MV mains and the transformers that are to be "ring main" Page 29 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. supplied requiring new underground MV mains, switchgear etc shall be marked; d) MV cables to service distribution transformers, with MV interconnections as required shall be indicated on the layout plans, indicating the ring main switchgear "types" (i.e. 2+2, 3+1 etc.) transformer sites, all new and existing underground and aerial mains with interconnection points. e) Consider aspects of electrical design in clause 5.3.4. 5.4.2 MV Network Systems 5.4.2.1 Radial Feeder System Failure of a radial feeder interrupts the supply to a substation for the period it takes to repair the faulted equipment. Therefore, duplicate feeders to important customers e.g. hospitals, may be considered. Ideally the zone substation should be at the "hub" of the feeders. In built up areas this is rarely possible. 5.4.2.2 Ring Main System In the ring main system, failure of a feeder will interrupt supply only for the time it takes to isolate the faulted equipment and relocate the open points. The zone substation does not need to be central. Ring main systems are associated with high initial costs and used in areas where high reliability of supply is required. 5.4.3 Hybrid System Horizon Power has adopted a hybrid system approach in high density areas to take advantage of the economic and the in-service benefits from both the radial and ring main systems. MV distribution is by ring main normally open at one point in the ring effectively producing two MV feeders. MV Ringmain Switchgear units are "looped in" around the ring and typically will feed two distribution transformer substations. This system can be achieved by installing a 2+2 ring main switchgear unit In-service benefits are gained from layout arrangements that allow sections of the ring network to be isolated or reconnected in order to maintain supplies, under fault and maintenance conditions. 5.4.3.1 Satellite Substations The use of the Satellite Substations is an economic method of supplying small "pockets" of UDS both at the edge of large subdivisions and inside extensive overhead networks. The satellite substation is radially connected from an overhead feeder protected by drop out MV fuses (expulsion type). The fused tee-off is connected to a satellite substation via 11 or 22 kV cable (3 x 1 core 35 mm2 XLPE). In-line pole top switches should be added to the overhead feeder on each side of the tee-off or in an economical arrangement to provide adequate isolation under fault or maintenance conditions. If the overhead feeder is likely to be undergrounded in the near future, the designer may consider an alternative to the fused tee-off arrangement and Page 30 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. Satellite Substation. This could be a cable "loop in, loop out" of the main feeder circuit through a Ring Main Unit. The 3 x 1 core XLPE cable would be sized to match the future feeder fault and current ratings. 5.5 Automation Automation facilitates the interconnection of adjacent feeders and switching of loads during faults and under abnormal conditions. (Refer to DSM - 08 for installation requirements) 5.6 Design Outputs 5.6.1 Outputs - MV/LV Layouts LV Substation locations and site details Cable and Aerial main routes, sizes and lengths; Service pillar locations; Switchgear (MV) types (2+2, 3+ 1 Package etc); Fuse sizes, Tee-off points (if satellite subs); Interconnection points; Street lighting details; Boundary of subdivision; Land requirements 5.6.2 Outputs - Cable Ducts Location, numbers, sizes Alignments; Construction and Installation requirements; Depth in ground; Cable pulling pits Page 31 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 6 DETERMINATION OF RECOMMENDED LOAD DEMAND VALUES 6.1 Estimation of Load Demand Maximum demand is the all important parameter in system design because this value directly determines component sizes (e.g. cables, transformers), voltage drops, line currents and ultimately the cost of servicing the loads. The fluctuating nature of electrical loads, particularly that of residential peaks, makes the measurement of instantaneous demand difficult, and sometimes, undesirable. System components are rated in terms of their thermal (overload) capacity and thus their “average demand ” over a period of, say, 15 minutes is far more meaningful than the moment by moment fluctuations which actually occur. For this reason the demand on electrical equipment is often obtained by the use of special instruments (e.g. load data-loggers) which can provide an average reading for a certain period. The information provided by this type of meter is often employed in system design. Subject to predefined conditions, maximum demands can be measured, adjusted and projected to become the basis of design for new systems. While easily understood in principle, maximum demand can be expressed in various terms and measured in various ways. Unless these aspects are fully understood and appreciated, confusion and inaccurate design may result. 6.2 Effect of Load Diversity on Maximum Demand The peak load of any installation is characterised by the demand fluctuations from the switching in and out of appliances within the installation. It is improbable that every appliance will impose its maximum demand at the same instant. As such, the maximum demand of the installation is generally less than the sum of the individual maximum demands of all the appliances within that installation. Similarly, the maximum demand of a LV feeder is characterised by the demand fluctuations from the varying load demands of all the loads on the feeder. The maximum demand of the feeder will generally be less than the sum of the individual maximum demands due to the “diversity ” between the loads. It is conceptually possible that if the “average maximum demand” of a “typical” load in a group is known, then the maximum demand for the whole group can be obtained by simply multiplying the average maximum demand of this typical load by the number of loads and also by an appropriate “multiplication factor” chosen for that particular number of loads. This multiplication factor is commonly referred to as the “diversity factor ”. Used in conjunction with the number of loads, the diversity factor “scales” the “average demand” of a “typical” load within a group, to the maximum demand for that group of loads. 6.3 Residential Load ADMDs ADMD values for residential loads are provided in Horizon Power document HPC-3DC-07-0001-2012 (Information – Electrical Design for Distribution Networks: After Diversity Maximum Demand). While the ADMD values are applicable only to standard sized lots, there may be cases where the actual ADMDs could be even higher than these values (e.g. for larger lots, beach front Page 32 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. houses, riverside lots, canal developments, etc.). Similarly, it may be necessary to reduce the recommended ADMD values. Changes to recommended ADMD values must, at all times, be made in consultation with the technical staff in the relevant Regional Area office prior to the design being carried out. Since these ADMD values are averaged, they must be “scaled up” to obtain the maximum demand for a group of loads before the LV feeder can be designed. The “scaling” of the ADMD values is automatically taken into account in Horizon Power’s Voltage Drop and Line Current formulae. 6.3.1 Determination of ADMD when standard values are not used The maximum demand on a residential substation, when divided by the number of loads supplied, provides a value which is in essence the “average contribution per customer” to that maximum demand, or simply the “average demand” for a “typical” customer. The larger the number of customers involved, the nearer to its ultimate value will be this “average demand”. For practical purposes, groups of 60 or more loads are considered to produce a figure sufficiently close to the ultimate for it to be considered as the “After Diversity Maximum Demand” or ADMD. Because the load ADMD is the all important basis of residential distribution design, this matter must receive full and careful consideration, concerning its value at the initial loading of the system, the provision for future growth and the repercussions of having to alter the system as a result of a poor choice of design ADMDs Among the factors influencing the choice of the ultimate design ADMD values are: 1) Limited capital resources; 2) Apprehension concerning the future; 3) Penetration of natural gas in traditionally all-electric areas; 4) Climatic, socio-economic and/or geographic influences; 5) Load growth, changing standard of living; 6) Trend towards more efficient appliances/equipment; and 7) Tariff structure. Whatever the ultimate design ADMD figures are, the designer must endeavour to ensure that the system is not under/over designed for the reasons given in clause 5.3. Optimum design requires optimum choice of ADMD. In most cases, a designer has to make a value-judgement as to what value of ADMD is most appropriate for the particular distribution system, after having considered all relevant issues. For most instances, the load demand can be estimated based simply on the designer’s previous experience with similar developments. However, careful thought must still be given to this crucial design parameter for each residential development, rather than simply using highly conservative “standard” values. It is not uncommon for a designer to find himself/herself in the position of having to be a mixture of an engineer, an economist and even a prophet at the same time! Page 33 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 6.3.2 Non-Residential Load Demands As mentioned earlier, maximum demand values are expressed in a variety of ways, e.g. amps, kVA, kVA/hectare, kW etc. The following load demand values for non-residential loads are a mixture of “average demand” type figures (kVA/hectare figures) as well as “maximum demand” type figures (kVA, kW, hp etc. figures). Typical design load demand values for non-residential loads are as follows: 1) High Schools: 220 kVA; 2) Primary Schools: 82 kVA; 3) Neighbourhood Shopping Centres: obtain the load kVA based on an average load density 200 kVA/hectare. (Alternatively, enquire from consultant or measure maximum demand); 4) Large Shops/Business Centres: enquire from consultant; 5) Pumps and other large 3-phase fixed equipment: obtain full load kVA from equipment name-plate or specifications; 6) Small Shop Groups: 200 kVA/hectare; 7) Light Industrial Lots: 100 kVA/hectare. More information is available in Horizon Power document HPC-5DC-07-0032012 (Distribution Design Manual Volume 3 – Supply to Large Customer Installations). 6.3.3 Residential Lot Classification Some lots have an “Rn” classification (e.g. R25, R30). This classification relates to the “density” of houses on the lot. The “n” index refers to the Number of Units/hectare, so that an R25 lot classification refers to 25 units per hectare. Since 1 hectare = 10 000 m2, each unit on a R25 lot would occupy approximately (10 000 ÷ 25) m2 = 400 m2. The number of units in a given “Rn” lot of area, A (m2), can then be calculated as follows: No. of Units = A (m2) × n ÷ 10 000 For example, if an R25 lot has an area of, say, 4898 m2, the number of units in the lot would be 4898 × 25 ÷ 10 000 = 12 units. Page 34 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 7 LV FEEDER PROTECTION 7.1 Introduction Protection devices are installed on underground networks to prevent or to minimise the risk of: (a) fires caused by uncleared faults; (b) thermal damage to the cable insulation and to the transformer; (c) annealing of the conductor; (d) mechanical damage to the cable due to electromagnetic forces caused by high fault currents. Horizon Power uses LV High Rupturing Capacity (HRC) fuses in its LV networks, to protect against: 7.2 (a) three phase faults; (b) phase-to-phase faults; and (c) phase-to-neutral faults. Feeder Protection Policy ''Any segment of LV cable installed within a network, existing or new, shall be protected using appropriately rated LV HRC fuses". For underground networks, the LV feeder shall be protected by LV fuses installed immediately after the transformer. The fuse rating for residential street circuits shall not exceed 315 amps at any substation. Downstream fusing shall not be used to extend the length of a feeder backbone. 7.3 LV Fuse Selection Policy The MV fuse links (full range) exhibit low temperature rise characteristics and are capable of interrupting both overload and short circuit currents up to their rated breaking capacity. The MV fuse is selected essentially for short circuit protection of the transformer. The LV fuse elements must be graded with the MV fuse links but must primarily protect the LV feeder cable against damage due to short circuits and as much as possible, high impedance faults, e.g. physically damaged cable leading to a phase to earth fault with significance impedance (low fault current). Sustained earth faults (not cleared by fuse operation because of the incorrect use of fuses rated at 400 A) have led to overload conditions on the transformer, and in turn fuses of the MV switchgear, resulting in catastrophic failure of MV fused units. The LV fuse/protection concept used in Horizon Power is based on the following assumptions or "rule of thumb": For satisfactory protection, the prospective phase-to-neutral current at the end of the LV feeder should be at least three (3) times the LV fuse current rating. Page 35 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 7.4 Prescribed Fuse Sizes (MV and LV) Standard LV supply arrangements and fusing are shown in HPC-5DA-07-00012012: Distribution Substation Manual Section 1: Customer Supply Arrangements. Fusing of street circuits at all underground substations shall not exceed 315 A. 7.5 Maximum Lengths of LV Feeders 7.5.1 General For any given LV fuse/transformer combination, the maximum length of feeder can be calculated such that if a zero resistance, phase-to-neutral fault were to occur at the end of the feeder, the estimated fault current would be at least three (3) times the LV fuse current rating. This maximum feeder length is mainly dependent on the resistance (R) and reactance (X) of the whole of the LV feeder, as well as the impedance of the transformer. Note: The system fault level at the transformer also affects the maximum length calculation. The equivalent MV system impedance, however, is usually much smaller than the LV feeder and the transformer impedances. As such, its overall effect on the calculated maximum LV feeder length is small. Since the LV feeder can be made up of several sections, each of a different conductor (with different resistances and reactance’s), the actual maximum length of any particular feeder must be calculated individually1. 7.5.2 Equivalent Length of LV Feeders In order to select maximum lengths of LV feeder and for particular fuse sizes, the designer can use the technique termed "equivalent length". For example, by comparing circuit impedances, an LV feeder constructed using several different conductors, can be expressed as a particular length equivalent to a feeder constructed solely of 95 mm2 LV ABC conductor. (The prospective phase-to-neutral fault currents at the end of both feeders will be the same). This length is termed the equivalent length (of 95 mm2 LV ABC) of the LV feeder. Using the "equivalent length" concept, we can express any feeder in terms of an "equivalent length" of 95 mm2 LV ABC. This is particularly useful since this length can then be compared with calculated maximum permissible "equivalent lengths" for various LV Fuse/Transformer combinations (see Table 7-1). 1 Horizon Power's LVDESIGN PC based computer programme has a Feeder Fuse/Protection Check option which can be used to calculate the maximum feeder length for a given LV fuse/transformer combination Page 36 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 7.5.3 Feeder Equivalent Length Calculation To calculate the "equivalent length" for a LV feeder constructed using several different conductors, simply divide the individual conductor length in the particular section with the appropriate "scaling factor" appropriate for the type of conductor, and add up the resulting lengths. The appropriate “scaling factors” are shown in Table 7-1. Table 7-1 LV Feeder Equivalent Length Scaling Factors CONDUCTOR CLASS / TYPE EQUIVALENT LENGTH CONDUCTOR SCALING FACTOR 25 mm² COPPER 2.57 2.08 1.45 0.52 95 mm² LV ABC 1.00 240 mm² ALUM UNDERGROUND CABLES LOW VOLTAGE ABC 185 mm² ALUM 120 mm² ALUM Example Suppose a LV feeder was constructed as follows: 1) 80 m of 185 mm2 AL U/G cable, 2) 300 m of 120 mm2 AL U/G cable, and Then, the "equivalent length" (of 95 mm" LV ABC) of the feeder is: E.Length = (80 + 2.08) + (300 + 1.45) = 245 m 7.5.4 Maximum Equivalent Lengths The maximum "equivalent length” for a given LV fuse/transformer combination can be calculated, as shown in Table 7-2. These lengths of 95 mm2 LV ABC are equivalent to the actual feeder length, at the end of which, the phase-to-neutral fault current will be at least three times the fuse rating. Table 7-2: Maximum Equivalent Lengths of 95 mm2 LV ABC Transformer Size (kVA) 1000 630 315 160 63 315 A 310 310 305 290 240 Maximum Equivalent Length (m) (of 95 mm2 LV ABC) LV Fuse Size 160 A 610 610 610 595 565 Page 37 of 47 100 A 980 980 975 965 940 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. When designing LV feeders, the network designer has to ensure that the LV feeder's "equivalent length" (of 95 mm2 LV ABC) does not exceed the lengths shown in Table 7.2. LVDESIGN automatically calculates the equivalent length of the LV feeder. Note: 7.6 From the above tables it is seen that 440 m of 120 mm2 feeder can be protected by a 315 A fuse for 315 kVA and above transformers. This means that lower rated fuses need rarely be considered on underground schemes. What if the Maximum Allowable Length is Exceeded? If the maximum allowable length is exceeded for any LV feeder, the fault current at the end of the feeder will be less than three times the rating of the LV fuse installed to protect the feeder. This may lead to unsatisfactory fault clearance times. The options available to the designer when the feeder's "equivalent length" exceeds the maximum allowable length are: 1) Consider Shortening the LV Feeder Shorten the feeder so that, its "equivalent length" (of 95 mm2 LV ABC) corresponds to the appropriate length in Table 7-2. This will mean that some of the loads previously serviced by the feeder must then be serviced from an adjacent or new transformer. In some circumstances, this may not be an economical option, particularly if additional expenses are incurred (e.g. MV mains extensions to connect up an additional transformer). 2) Consider Using Larger LV Conductors By using LV conductors with a larger cross sectional area, the feeder's "equivalent length" may be "shortened" to within the maximum allowable length. For example, a 450 m feeder constructed entirely of 120 mm2 cable has an "equivalent length" of 310 m. However, the same feeder constructed using 185 mm2 cable in its first two segment lengths (of, say 40 m each) will have an "equivalent length" of 293 m. (80 / 2.08) + (450-80) /1.45 = 293 m This option may not be economic if the length of the larger conductor needed is excessive. 7.7 Calculation of Fault Currents at End of LV Feeders The "equivalent lengths" in Table 7-2 are calculated by determining the total impedance to the end of the feeder which will result in a fault current of at least three times the fuse rating. Conversely, for a given feeder made up of several different conductor types, the prospective phase-to-neutral fault current at the end of the feeder can be calculated. Page 38 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. The formula for the fault current is given by: where: I= prospective phase-to-neutral fault current at the end of the LV feeder (amps) Xs = source/system impedance from the zone substation to the MV terminals of the transformer (ohms) Xt= transformer impedance (ohms) R= total resistance from the transformer LV terminals to the end of the LV feeder (ohms) X= total reactance from the transformer LV terminals to the end of the LV feeder (ohms) The R and X values are obtained by multiplying the conductors' resistance and reactance values in (Ω/km) with the length of the conductor (in km). When a feeder is made up of several types of conductors, then the resistance and reactance values of each conductor are calculated as described above and added together to give the feeder’s total reactance. where: = resistance (Ω/km) for conductor "i" = length (km) of conductor "i'' K = total number of different conductors on the feeder Similarly, the reactance X is given by: where: = reactance (Ω/km) for conductor "i" The transformer impedance values are as shown in Table 7-3. Table 7-3: Typical Distribution Transformer Impedances Transformer Size (kVA) 1000 630 315 160 63 Impedance, Xt (%) 5.5 4.0 4.0 4.0 3.3 (Ω) 0.01 0.011 0.022 0.043 0.09 Page 39 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. Note: The transformer impedances are calculated as follows: Xt(Ω) = {Xt(%) x 4152} ÷ {100 x Tx kVA} The % impedances are from Horizon Power’s current Technical Specification for Transformers (HPC-8DJ-07-0001-2013). The source or system impedance, Xs can be derived from the fault level at the HV terminals of the transformer. In most instances, the source impedance is so small compared to the transformer impedance that it can usually be ignored altogether in the fault current calculations. Example If a feeder is fed from a 315 kVA transformer, and is constructed as follows: 100 m of 240 mm2 Al cable, 80 m of 185 mm2 Al cable and 40 m of 120 mm2 Al cable, The (phase-to-neutral) fault current at the end of the feeder can be calculated as follows: 1) Transformer Impedance, Xt: The transformer impedance, from Table 8-3 is 0.0267 Ω. 2) Total Resistance, R: The total resistance, R, is: R = (0.1365 x 0.1) + (0.1787 x 0.08) + (0.2739 x 0.04) = 0.03891 Ω 3) Total Reactance, X: X = (0.0690 x 0.1) + (0.0690 x 0.08) + (0.0620 x 0.04) = 0.01490 Ω Hence, the phase-to-neutral fault current is: . . . = 2497 amps 7.8 Fault Current Ready Reckoner The prospective fault current at the end of any length of LV feeder can be approximated using a "Ready Reckoner". Having found the feeder's Equivalent Length, the curve shown in Table 7-4 can be used to obtain the approximate fault current at the end of the LV feeder. From this: 1) the magnitude of the fault current as a "multiple" of the fuse size can then be determined. (The "ideal" multiple of the fuse size is three (3) times. However, multiples as low as 2.5 times may also be satisfactory for some circumstances). 2) the fault clearance times can be estimated (using Figure 7-1). Page 40 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. Figure 7.1: Fault Current Ready Reckoner Note: The minimum curve is for a 63 kVA Tx, while the maximum curve is for a 1000 kVA transformer. Page 41 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 7.9 Typical LV Fuse Time-Current Characteristics The calculated phase-to-neutral fault current (in amps) at the end of the LV feeder can be checked against the typical time-current characteristics of the LV fuses to determine the fusing times (in seconds). The time-current characteristics for most commonly used LV HRC fuses are shown in Figure 7-2. Figure 7.2: Time-Current Characteristics of LV HRC Fuses Page 42 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. 8 INSTALLATION REQUIREMENTS Refer to the following documents: 9 1) Western Australian Distribution Connections Manual (WADCM) 2) Underground Distribution Schemes (UDS) Manual 3) Underground Cable Installation Manual 4) HPC-9DJ-23-0001-2012: Substation Installation Technical Requirements 5) Distribution Substation Manuals ( DSM -1, DSM – 3 & DSM – 6) 6) HPC-9DC-08-0001-2012: Distribution Line Earthing Standard STREET LIGHTING Refer to Section 13 of HPC-5DC-07-005-2012: Distribution Design Manual Volume 5 – Overhead Bare Conductor Distribution. Page 43 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. APPENDIX A – REVISION INFORMATION (Informative) Horizon Power has endeavoured to provide standards of the highest quality and would appreciate notification if any errors are found or even any queries raised. Each Standard makes use of its own comment sheet which is maintain throughout the life of the standard, which lists all comments made by stakeholders regarding the standard. The document HPC-5DC-07-0004-COMM can be used to record any errors or queries found in or pertaining to this standard, which will then be addressed whenever the standard gets reviewed. Date 17/06/2014 Rev No. A Notes Original Issue Page 44 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. APPENDIX B – CURRENT RATING OF UNDERGROUND CABLES B.1 Continuous Current Rating Cable manufacturer’s catalogues provide continuous current ratings for cables installed in the following standard installation conditions; In air Buried direct in ground at a depth of laying of 0.8 m to the top of cable or group of cables In a duct with depth of laying of 0.8 m to the top of the duct The continuous current ratings of cables provided in cable manufacturer’s catalogues are generally based on the following operating conditions: a) Maximum conductor temperature 90°C (XLPE insulated cables) b) Ambient air temperature 40°C c) Ambient soil temperature 25°C d) Soil thermal resistivity 25°C.m/W (Refer to HPC-9EJ-01-0001-2013, Horizon Power Environmental Conditions Standard, for temperature conditions in various parts of the network) Cable manufacturer’s catalogues also provide modifying factors when cables are installed in environments which are different to the above conditions. Cable manufacturer’s catalogues should be used to perform the cable rating calculations in different installation conditions to the above using the formula: Continuous current rating = Rating in Table x factor for depth burial x factor for thermal resistivity x factor for ground temperature Continuous current ratings are used to calculate the cyclic and emergency ratings and are rarely used otherwise in practice. The rating modification tables in this section shall be used only when the cable manufacturer’s catalogues are not available. B.1.1 Rating Factors for depth of laying direct in the ground Depth of Burial (m) (to top of cable) Low Voltage Cables High Voltage Cables ≤ 300 mm2 ≤ 300 mm2 > 300 mm2 > 300 mm2 0.6 1.0 1.0 0.8 0.98 0.97 1.0 1.0 0.9 0.97 0.96 0.99 0.98 1.0 0.96 0.95 0.98 0.97 1.25 0.95 0.93 0.96 0.95 1.5 0.93 0.92 0.95 0.93 1.75 0.92 0.91 0.94 0.91 2.0 0.91 0.90 0.92 0.89 Page 45 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. B.1.2 Rating Factors for depth of laying direct in a duct Depth of Burial (m) (to top of duct) Low Voltage Cables High Voltage Cables Single Core Single Core Three Core Three Core 0.6 1.0 1.0 0.8 0.97 0.98 1.0 1.0 0.9 0.96 0.97 0.99 0.99 1.0 0.95 0.97 0.98 0.99 1.25 0.92 0.96 0.95 0.97 1.5 0.91 0.95 0.94 0.96 1.75 0.92 0.95 0.92 0.96 2.0 0.89 0.94 0.91 0.95 B.1.3 Rating Factors for variation in Thermal Resistivity (3 core cables laid directly in the ground) Conductor size (mm2) Up to 400 Thermal Resistivity (°C.m/W) 1.0 1.2 1.5 2.0 2.5 1.07 1.0 0.92 0.82 0.74 B.1.4 Rating Factors for variation in Thermal Resistivity (1 core cables laid directly in the ground) Conductor size (mm2) Above 400 Thermal Resistivity (°C.m/W) 1.0 1.2 1.5 2.0 2.5 1.08 1.0 0.90 0.79 0.71 B.1.5 Rating Factors for variation in Thermal Resistivity (3 core cables laid in duct buried in the ground) Conductor size (mm2) Up to 400 Thermal Resistivity (°C.m/W) 1.0 1.2 1.5 2.0 2.5 1.04 1.0 0.95 0.87 0.82 Page 46 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version. B.1.6 Rating Factors for variation in Thermal Resistivity (1 core cables laid in duct buried in the ground) Conductor size (mm2) Thermal Resistivity (°C.m/W) Above 400 1.0 1.2 1.5 2.0 2.5 1.06 1.0 0.93 0.84 0.77 B.1.7 Rating Factors for Variation in Ambient Temperature Air Temperature (°C) Rating Factor 25 35 40 45 50 55 1.14 1.05 1.0 0.95 0.89 0.84 B.1.8 Rating Factors for Variation in Ground Temperature Air Temperature (°C) Rating Factor 15 20 25 30 35 40 1.07 1.04 1.0 0.96 0.92 0.88 Page 47 of 47 Print Date 23/06/2014 © Horizon Power Corporation – Document Number: HPC-5DC-07-0004-2014 Uncontrolled document when printed. Printed copy expires one week from print date. Refer to Document No. for current version.