SECTION 01 10 17 AAFES FURNISHED AND INSTALLED EQUIPMENT (AF/AI) PART 1 - GENERAL 1.01 AAFES FURNISHED AND INSTALLED PROPERTY (AF/AI) A. Certain items of equipment will be furnished and installed by AAFES. See drawings references to (AF/AI) B. The Contractor shall provide for and cooperate with personnel installing AAFES furnished materials and equipment, should overlap of work occur. C. Schedule: Contractor shall schedule early completion of designated areas for beneficial occupancy by AAFES usage prior to completion of entire project per approved Phasing plans. D. AAFES will furnish and install equipment as indicated on Fixture and/or Equipment Plans in the drawings. E. Contractor's Duties: 1. Provide access for AAFES personnel. 2. Coordinate work and cooperate with the installers of the AF/AI equipment so that installation can be accomplished in accordance with construction schedule. 3. Provide mechanical and electrical connections to AF/AI equipment and building systems where indicated in the contract documents. 4. Provide security for designated areas. 5. Schedule equipment delivery dates and installation times to coordinate with the overall schedule. Provide AAFES advance notice so equipment can be ordered on time. F. AAFES Duties: 1. Inspect designated area prior to use and issue statement of acceptance of area for installation of property. 2. Make final mechanical and electrical connections between AF/AI property and building systems where indicated in the contract documents. 3. Provide custodial services for designated areas during use after beneficial occupancy. 1.02 DELIVERY DATE CHANGES A. Requests by Contractor to change designated delivery dates shall be made in writing at least 30 days in advance of the designated delivery date. If the Contractor is not ready to accept delivery of AAFES furnished property the Contractor shall be responsible for storage and re-delivery cost. Should AAFES be unable to effect the change, or should the Contractor fail to submit his request within the time stated above, the Contractor's obligation under this contract and as stated herein shall not be relieved and further, the Contractor will have no basis upon which to file a claim under these conditions. 1.03 AAFES ACTIVITIES AFFECTING PROGRESS OF WORK: A. Construction in each area at date scheduled for its use and possession by AAFES shall be sufficiently complete, in accordance with Contract Documents, so that AAFES may occupy the area for the use for which it is intended. Comply with Contract Clauses titled Inspection of Construction, and Use and Possession Prior to Completion. 1.04 ACCEPTANCE OF AREAS FOR BENEFICIAL OCCUPANCY A. Inspection: Prior to acceptance by AAFES of an area for beneficial occupancy, the Contracting Officer will conduct an inspection of the specific area. A list of deficiencies will be provided to the Contractor. B. Acceptance: If the Contracting Officer determines the specific area is sufficiently complete for beneficial occupancy by AAFES, the area will be accepted in writing with the exception of the deficiencies listed. The deficiencies listed shall be completed or corrected prior to final acceptance at the completion of the project. OPTICAL CENTER/CONCESSION SOUTH POST EXCHANGE, FORT BRAGG, NORTH CAROLINA AAFES PROJECT NO. 0530-15-000011 | PWBA 151007 AAFES FURNISHED AND INSTALLED EQUIPMENT (AF/AI) 01 10 17 - 1 C. Damage: Damage resulting from AAFES' use will not be considered the Contractor's responsibility. D. Refer to clause entitled "Final Inspection and Acceptance" of the AAFES "General Provisions." PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION 3.01 FINAL CONNECTIONS A. All final electrical connections to AAFES and Vendor furnished and installed equipment shall be made by the Contractor as part of the construction contract. The GC shall construct all openings, furnish and install required sleeves and conduit, and furnish and install all reinforcing, miscellaneous supports, angles, plates, anchors, and bolts necessary to secure AAFES-furnished equipment in place. Final hookup of plumbing fixtures is by the GC. B. The Contractor shall provide for and cooperate with personnel installing AAFES-furnished materials and equipment should overlap of work occur. 3.02 SCHEDULE OF MATERIALS AND EQUIPMENT (AF/AI) A. Equipment to be furnished and installed by AAFES is as follows and as indicated on the Drawings: 1. All display cases and fixtures. 2. Check-out Fixtures and POS. 3. All loose furnishings (Tables, chairs, desks, etc.). 4. Optometry Care/Optical Center: Fixtures, equipment and furnishings as indicated on drawings. (Plumbing fixtures, and storage shelving by General Contractor unless noted otherwise.) END OF SECTION AAFES FURNISHED AND INSTALLED EQUIPMENT (AF/AI) 01 10 17 - 2 OPTICAL CENTER/CONCESSION SOUTH POST EXCHANGE, FORT BRAGG, NORTH CAROLINA AAFES PROJECT NO. 0530-15-000011 | PWBA 151007