HAL, Inc.

advertisement
HAL, Inc.1
1. Background
It is May 1992. HAL, Inc. is a major manufacturer of computers and computer components. In their Lubbock, TX
plant they make printed circuit boards (PCB's, also referred to as ``panels''), which are used by other plants in the
company in a variety of computer products. The Lubbock plant, built in 1982, represents an $80 million investment
and has approximately 450,000 square feet of manufacturing space.
The plant makes two families of products:
1.
Small Panels: 10" x 15" panels are the original product of the facility and are used primarily for mainframe
computer cards. There are roughly 40,000 different types of small panels, most of which are made for replacement
parts in older computers. The overall demand for small panels is gradually declining.
2.
Large Panels: 19.5" x 24" panels are a newer product, introduced in 1987, used primarily for personal computer
cards. The larger size serves to reduce the cost per card and therefore most new cards are produced in this format.
There are currently about 150 different types of large panel, but this number is steadily increasing.
Both product families follow the same basic sequence of manufacturing operations, which is as follows:
•
•
•
•
•
•
•
•
•
•
Treater Process: woven fiberglass cloth is impregnated with epoxy to make ``prepreg'', the insulator used in multilayer printed circuit boards.
Lamination: layers of copper and prepreg are pressed together to form cores (blank boards).
Machining: the cores are trimmed to size.
Circuitize: through a photographic exposing and subsequent etching process, circuitry is produced in the copper
layers of the blanks, giving the cores ``personality'' (i.e., a unique product character).
Optical Test and Repair: the circuitry is scanned optically for defects, which are repaired if not too severe.
Drilling: Holes are drilled in the boards to connect circuitry on different planes. (Note - that circuitized boards
may return to the Lamination process to build up multi-layer boards).
Copper Plate: the boards are run through a copper plating bath, which deposits copper inside the holes, thereby
connecting the circuits on different planes.
Pro-Coat: a protective plastic coating is applied to the boards.
Sizing: boards are cut to final size. In most cases, multiple cards are manufactured on the same board and are cut
into individual cards at the sizing step. Depending on the size of the card, there could be as few as two cards on a
panel, or as many as twenty.
End-of-Line-Test: an electrical test of each board's functionality is performed.
Some of these processes (Treater, Lamination, Copper Plate) are shared between the two product families. Because of
volumes and because it is difficult to switch between the two panel sizes, the other processes have been dedicated to
a single product family (e.g., there are separate circuitize lines for 10 x 15's and and large panels).
Before 1990, the Large Panel Line had such low volumes and such a small range of part numbers that it was not a
major problem. Order acceptance and scheduling were handled by the Production Control Department. The
Manufacturing Engineering Department kept track of capacity data and studied equipment and process improvements.
The Manufacturing Department ran the line and, because the number of products was small, became accustomed to a
de-facto rule of running only one part number per day on a process. This made managing the line easy, since few
changeovers were required, demand for consumables was predictable, and operators could develop a strong sense of
pacing.
By 1990, however, the number of large panels had increased to around 100 and the de-facto rule of ``one product per
day'' was no longer viable (although managers and operators were still fond of citing it as a goal). Capacity was
estimated by Manufacturing Engineering to be 2000 panels per day, but a more typical daily output was around
1
 Wallace J. Hopp 1996
1
1000 panels per day.2 In addition, although the actual amount of processing time required to make a printed circuit
board was less than one day, manufacturing cycle times had steadily grown over time and were averaging close to 35
days at this point in time and customer service (the fraction of orders delivered on time) was running at about 50\%.
Just prior to these events, the HAL Corporation had begun promoting the use of just-in-time concepts within its plants.
Linda Brown, an internal consultant, was charged with implementing JIT in the Lubbock plant. She chose to
concentrate on the more established 10 x 15 Line and wrote several documents describing basic JIT principles, held
workshops with the personnel in charge of the line, and gave frequent reports to upper management on the sorry state
of the line. However, Linda was promoted to a position outside the Lubbock facility before any concrete action plan
was evolved. No attention at all was devoted to the Large Panel Line. The net result was that the Lubbock
management team was left with a deep cynicism about the applicability of JIT to their system.
In the fourth quarter of 1990, a new plant manager, Salvatore Petitto, took over the plant. Convinced that the plant was
producing well below its capacity−he often cited Manufacturing Engineering capacity estimates−he summarily
increased the target capacity for the large panel line by 50\% to 3000 panels per day. He also instituted a policy of
holding a 4:00 meeting of all first line managers and directly confronted those who failed to make throughput
numbers or had excessive WIP in their sectors.
Mr. Petitto's first focus was Pro-Coat, which had been seriously underperforming for months and had been using an
outside vendor (at a cost of roughly $14 per panel) to make up capacity shortfalls. Through a combination of additional
staffing and procedural changes, Pro-Coat had been able to increase throughput from roughly 1200 boards per day to
2800 boards per day between December 1990 and April 19913
He then turned his attention to Circuitize, which was also experiencing throughput problems and, even more seriously,
frequently had in excess of a week's worth of WIP in it. This time, quality improvements and procedural changes were
implemented that improved throughput slightly, but reduced WIP in half by the early 1992.
After these two successes, Mr. Petitto's policy of holding 4:00 meetings seemed to lose some of its momentum.
Despite a few additional staffing and equipment additions, average throughput for the entire large panel line had stalled
at around 2400 panels per day and cycle time in the line was still close to 30 days. Mr. Petitto began to challenge the
first line managers to adopt more JIT mechanisms, but encountered serious resistance, largely as a result of the negative
experience with JIT two years earlier. Other problems that surfaced in the meetings included:
•
Manufacturing consistently held that the schedules prepared by Production Control were a joke. Production
Control responded that they were merely using the customer orders (customers were exclusively other HAL plants
that ``stuffed'' the raw circuit boards) and the approved MRP system to generate releases and due dates. The
problem, they contended, was that Manufacturing constantly perverted the schedule (by means of expediters who
re-prioritized work already in the plant) to try to meet the needs of high-priority customers.
•
No single process center was a consistent source of the majority of trouble. During one interval, the Copper Plater
was down for almost two weeks, building a huge queue and ruining schedule performance. Soon afterward, a large
buildup of WIP occurred at Drills. Then a problem with two of the Lamination Presses caused the line to run out
of the appropriate core blanks, so that although there was plenty of WIP in the line, the WIP required to meet
2
The capacity calculations made by Manufacturing Engineering were complicated by the fact that different boards
required different amounts of processing at different stations. To compensate, complexity factors were defined,
which represented the number of standard panel equivalents of a given board. This was done by arbitrarily defining
one of the of the boards to have a complexity factor of 1.0 and then defining the complexity factors of the other boards
to be the ratio of time required at Drilling to that required by the standard board. For instance, a board that required
twice as much time at Drills as the standard board would have a complexity factor of 2.0. This system was chosen
because it was generally felt that Drills was a bottleneck. However, because rates of other processes were also a
function of board type, it was recognized that the bottleneck would ``float.'' Considerable controversy about the
identity of the ``true bottleneck'' existed among the managers and engineers.
3
Actual throughput has not always achieved the 2800 boards per day rate due to failure of the rest of
the line to produce sufficient input to Pro-Coat. However, when there has been sufficient WIP, Pro-Coat has been able
to achieve the 2800 rate on a consistent basis
2
schedule was not available. This type of occurance was cited as evidence that the bottleneck ``floated'', making the
line exceedingly difficult to manage. Mr. Pettito was unable to identify an obvious candidate for focused attention
as he had done with Pro-Coat and Circuitize.
•
Manufacturing complained that the capacity numbers generated by Manufacturing Engineering, now at 3000
panels per day were unrealistic. However, when engineers from Manufacturing Engineering demonstrated their
calculations, involving rate data from the equipment manufacturers adjusted by 14 different detractors (setups,
operator efficiency, down time, yield loss, etc.), Manufacturing personnel were unable to give convincing
arguments as to why these numbers were unreasonable. But, they argued, 3000 (standard) panels per day must be
wrong since this rate had never been achieved in the history of the Large Panel Line. Mr. Petitto countered that
this merely showed that Manufacturing was not doing its job. Moreover, he contended that if the target rate were
reduced, workers wouldn't have incentive to strive to get better.
•
Managers in Circuitize complained that the continual evolution of the products prevented them from stabilizing
their processes. As one of them commented, ``As soon as we get decent yields for boards with n lines per inch, we
get products with 2n lines per inch and our problems start all over again.''
•
Managers in End-of-Line Test complained that there had been periods of high yield loss and/or rework due to
problems that should have been caught earlier in the process. As one of them pointed out ``When we lose a
finished multi-layer board, we're throwing away something like $200. It would have been more like $2 if we'd
caught it at the core blank level, or $20 if we caught it at the first pass through Circuitize.'' Everyone agreed that
the extreme pressure to get volumes up might be encouraging people to push work through rather than stop it for
anything other than the most glaring quality problems.
•
Almost everyone felt that the uneven demand placed on the Large Panel Line by the board stuffing plants made
managing the line difficult. Every year, the line experienced a slow period in January and early February, during
which it was difficult to find enough work to keep the workers busy. By March, however, demand would jump,
the line would get overloaded, and the cycle of costly overtime and, with a few minor lulls, capacity vendoring
would start again and continue through December.
2. Data
As part of the ongoing discussion about the capacity of the Large Panel Line, Manufacturing Engineering put together a
rough set of capacity numbers for the processes that represent the basic process flow through the Large Panel Line.4
The numbers, summarized in Table 1, are defined as follows:
•
Number of Machines: the number of tools, generally identical, in a given process center.
•
Base Speed: the rate of a single machine in panels per hour without considering any of the detractors.
•
Efficiency: the fraction of time a machine is up, not counting downtime due to setups or failures (i.e., the overall
availability of a machine, therefore, must be computed by further reducing this efficiency according to the time lost
to setups and failures).
•
Lot Size: the average number of panels run between setups.
•
Setup Time: the average setup time between lots, in hours.
•
Mean Time to Failure: the average time until a machine fails, in hours.
•
Mean Time to Repair: the average repair time of a machine, in hours.
4
Some products require additional steps, such as Gold Plating, which might require the boards to be sent outside the
plant to vendors. However, virtually all the products on the Large Panel Line passed through this basic sequence.
3
Tool
Press (Core)
Thopmson Press
IP Preclean
IP Expose
IP D.E.S.
IP Optrotech
Verify-Repair-Weld
Chlorite
Presses
Machining VNO
TruDrills
Smear Remove
Blast
Cu Plate
EP Preclean
EP Expose
EP D.E.S.
EP Optrotech
EP Anal/Repair
Probimer Coat
Probimer Expose
Dev/Cure/Entek
White ID
Halving
Router
View 1220
Water Wash
PDI 4000
EPC Analyze
No. Mach.
2
2
3
4
3
6
16
1
3
1
31
1
1
2
1
2
1
3
0
1
5
1
2
1
2
2
1
3
3
Base Speed
105
133
95
67
67
40
14
342
68
701
8.1
343
176
90
271
136
223
79
0.044
180
60
180
257
200
149
220
431
143
77.5
Efficiency
99
80
82
81
85
80
100
76
99
95
80
99
84
90
74
81
85
74
100
90
80
83
82
68
80
76
87
75
85
Lot Size
135
72
2,792
72
2,100
72
72
10,103
135
72
131
6,628
3,010
4,067
3,300
72
3,657
1,088
45
3,492
72
3,492
72
2,820
72
2,430
12,938
72
72
Setup Time
0.06
0.03
0.0
0.13
0.0
0.04
0.01
0.0
0.06
0.25
0.6
0.0
0.0
0.0
0.0
0.1
0.0
0.0
0.0
0.0
0.05
0.0
0.35
0.0
0.13
1.0
0.0
0.17
0.1
MTTF
155
57
18
47
22
63
147
22
155
72
232
147
200
16
22
47
35
63
1
12
57
42
28.5
40
35
750
20
120
57
MTTR
1.8
3.0
3.0
3.0
3.0
7.0
3.0
3.0
1.8
3.0
9.7
3.0
2.0
3.0
3.0
3.0
3.0
7.0
0.0
1.3
3.0
1.3
1.5
3.0
3.0
2.0
2.0
2.0
3.0
Table 1: Capacity Data for Large Panel Line.
A basic layout of the process centers in the Large Panel Line is shown in Figure 1
3. Your Mission
Mr. Pettito is growing increasingly impatient with the slow progress at improving throughput, reducing cycle time, and
raising the level of customer service. The 4:00 meetings have revealed a host of problems, but no consensus on
solutions. He is looking to you for general guidance concerning where to look for leverage and ideas for reshaping the
entire system. Because he is concerned that Corporate will eventually decide to outsource the entire PCB
manufacturing process, he is willing to consider virtually any alternative. However, he must be careful to make sure
that the Lubbock plant is cost competitive with non-HAL PCB producers.
4
Drills
Copper Plate
EOL Sizing
EOL Test
Internal
Test & Repair
Procoat
Circuitize
External
Test & Repair
Lamination
Machining
Lamination
Presses
Figure 1: Layout of Large Panel Line.
5
Treater
Tower
Download