STANDARDS AND SUPPLEMENTARY SPECIFICATIONS 1. Applicable Standards All workmanship, materials, and components throughout shall, where applicable and unless otherwise stated in the Contract, comply with the updated standard specifications, including items of works, materials, construction methods and test methods for construction of Roads and Bridges used by the Ministry of Public works & Housing, Directorate of Planning & Development in the Hashemite Kingdom of Jordan. 2. Standard Not Specified If no Standard is indicated, then the relevant American or British Standard, if any, shall apply. PRICING PREAMBLES 1. Introduction: These Pricing Preambles set out the basis on which the Bills of quantities have been prepared. Not with standing the provisions of these pricing preambles, the Contractor is reminded that the Tender Drawings and the Specifications form part of the Tender Documents and as such mutually refer to the intent of the Tender Documents. Where a discrepancy occurs, it will be deemed that the Contractor has allowed for the intent of the Tender Documents unless this is clarified specifically at the time of Tender. 2. Bills of Quantities: The Bills of Quantities define the items that are measurable and the units of measurement represent the entire work to be carried out in accordance with the Drawings and the Specifications. The measurement items in the Bills of Quantities are to be accepted as the full interpretation of the requirement of the Drawings and Specifications. “Descriptions" are given in outline only, the Contractor is to refer to the Specifications and Drawings and make himself familiar with the requirements. No additional measured items will be allowed to interpret further the information so given. Other requirements which are not measurable in terms of quantity of labor and materials (e.g.. specialist supervision, shop drawings, bar bending schedules, as built drawings, samples, tests, mock-ups, maintenance, materials, guarantees and the like) and are not given as specific items in the Bills, are to be included in the prices of the measured items. The method of measurement for the Contract is thus established by the measured items and units of the measurement in the Bills of Quantities. No other measurement method shall be used to measure the executed works. The same method of measurement and no other will be used in re-measuring the executed work. 3. Pricing: The Contractor shall satisfy himself as to the meaning of every item in the Bills of Quantities and the rates and prices inserted by him shall cover all Works required by the Contract Documents. All costs in connection with the proper and successful construction, completion and maintenance of the Works including, but not limited to, completion of all PRICING PREAMBLES.doc Page 1 of 4 temporary works, furnishing all materials, equipment, supply and appurtenance, providing all construction Plants, equipment, tools, sampling, testing, profits, overheads, charges, provision of guarantees, performing all necessary labor and supervision and other cost of whatsoever nature necessary to fully complete the Works, shall be included in the unit and lump sum prices called for in the bills of Quantities. All Works not specifically set fourth as a pay item in the Bills of Quantities shall be considered as subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the Priced Tender. Prices shall be deemed to include for all straight ranking and circular cutting and consequent waste. All prices shall include all fees, levies and taxes excluding the Value Added Tax (VAT). 4. Quantities: All estimated quantities stipulated in the Bills of Quantities or other Tender Documents are approximate and are to be used only; a) As a basis for estimating the probable cost of the Work and b) For the purpose of comparing the bids submitted for the Work. The actual amount of work done under each unit price items may differ from the estimated quantities. The basis of payment for work will be the actual quantities. The Contractor agrees that he will make no claim for damages, anticipated profits or otherwise on account of any difference between the amounts of work actually performed and the estimated amount. 5. Items in Bills of Quantities Such items are the subject of re-measurement of completion in accordance with the General Conditions of Contract. Quantities given in the Bills are based upon measurement from the Contract Drawings and Specifications. 6. Measurement Metric measurements and weights have been used throughout the Bills of Quantities. Work is measured net as fixed in position and each measurement is taken to the nearest centimeter. Fractions of a centimeter less than half are disregarded and all other fractions are regarded as whole centimeters. This principle shall not apply to dimensions stated in item descriptions. Where minimum deductions of voids are dealt with they refer only to openings or voids which are wholly within the boundaries of measured areas. Openings or voids that are at the boundaries of measured areas are always the subject of deduction irrespective of size. 7. Descriptions The order of stating dimensions in descriptions is generally in the sequence of Length, Width and Height. Unless otherwise stated in the Bills of Quantities or herein, all measured items are deemed to include supply and fix in place complete, thus all measured items shall include all incidentals to complete the work in a proper manner such as but not limited to the following: (a) Labor. (b) Materials, including all costs in connection herewith (e.g. conveyance, delivery, unloading, storing, and handling, lowering into position and the like). (c) Customs and import duties as applicable, insurance, levies and the like. PRICING PREAMBLES.doc Page 2 of 4 (d) (e) (f) (g) (h) (i) (j) All shop treatment of materials (e.g. Preservation of timbers, galvanizing, priming, chrome plating, stove enameling, anodizing and the like, pipe wrapping, coatings, etc.). Fitting and fixing materials in position includes all necessary fixing devices and materials. Commissioning & use of plant. Disposal of waste of material. Square, raking or curved cutting. Work in volumes, areas and length of any size, no separate items being measured for isolated work or work in small quantities, short length, narrow widths, etc. Establishment charges, on-costs, overhead charges profits and taxes excluding the Value Added Tax (VAT). Junction between straight, raking and curved work is in all cases included with the work in which they occur. Certain items are referenced directly to detail drawings to eliminate detailed description. All such reference include all work to execute the detail. Where Specification clauses and /or detail drawing numbers are referred to in a description such information is provided for convenience only and the Contractor is to note that all other relevant Specification requirements and relevant drawings and details are to be taken into account. 8. Abbreviations. The following abbreviations are used throughout the Bills of Quantities. B.O.Q Bills of Quantities Mm Millimeter Cm Centimeter L.M. or mr. Linear meter M.S or m2. Square meter M.C or m3 Cubic Meter L.S. Lump Sum No. Number Kg. Kilogram Ref. Reference 9. Definitions The terms “include", “is included“, “including“, and similar, are used herein to indicate that the items and are not specifically mentioned in the descriptions but the costs of which are to be included in the measured items. Such references are not comprehensive and are for convenience only and the Contractor is to note that all relevant requirements of the Specifications and Drawings are to be taken into account in the measured items. The word “Site” used in the Bills of Quantities means the whole of the areas within the Contract limit lies for this Contract as shown on the Contract Drawings. With reference to the clearance of debris, rubbish, trash, excavated material and the like the definition is extended to include the whole of the site. PRICING PREAMBLES.doc Page 3 of 4 The word “ditto” used in the Bills of Quantities means the repetition of all or part of the preceding item as applicable to complete the sense of the item. The word “ extra “ used in the Bills of Quantities means the additional cost of the item of work in question over and above the cost of work already measured. The word "Provisional" used in the Bills of Quantities means the owner has the right to cancel or implement the included works, and the Contractor agrees that he will make no claim for damages, anticipated profits or others as a result. 10. Protection. All rates in the Bills of Quantities shall include for protection as required and deemed necessary. 11. Shop Drawings / co-ordinate drawings. All rates shall include where required for producing shop drawings & co-ordinate drawings and supporting calculations as requested by the Engineer. 12. As Built Drawings. All rates shall include for producing one transparency and four (4) copies of all asbuilt drawings and supporting calculations to the approval of the Engineer. 13. Cutting and Patching. The Contractor shall be responsible for all cutting, patching and making good for all trades for all work and his prices will be deemed to include for all such cutting and patching and making good. 1. Setting out of the buildings, yards, car parks, guardroom, retaining walls & boundaries are to be done by licensed authorized surveyor at the contractor’s expense and responsibility. 2. Rates and Prices shall be clearly spelled out alphabetically and numerically. 3. No item is to be measured twice under separate headings. PRICING PREAMBLES.doc Page 4 of 4 Jericho Agro Industrial Park BOQ Bill No. 1 Excavation, Earth Works and Embankment Work Item No Description 1 The Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications. The words engineer below means owner's/Employer's engineer. The rate include the following: Unit QTY 1.1 Cut in any kind of soil, concrete, asphalt or stone walls to reduce level for site leveling and to reach the desired level according to drawings and site instructions .The price should include the removal of excavated materials from the site to an approved dump location and adjustment store. m3 49700 1.2 Supply and install granular sub-grade course 40 cm thick after compaction (2 layers 20cm thick each) second class for landscaping area, including preparing sub-grade, mixing, spreading, compacting 100% and finishing. Including all test required. All according to specifications, drawings and direction of the site engineer m2 67600 1.3 Ditto but for basecourse first class thick 20cm m2 67600 1.4 Supply and install granular sub-grade course 40 cm thick after compaction (2 layers 20cm thick each) second class for roads, including preparing sub-grade, mixing, spreading and laying cement 10kg / m2 above natural ground during compaction, compacting 100% and finishing. Including all test required. All according to specifications, drawings and direction of the site engineer m2 15180 1.5 Ditto but for basecourse first class thick 20cm m2 15180 1.6 Supply and install soil for embankment between different levels to prevent erosion. The price should include laying a layer of natural ground from site, a second layer of 40cm selected approved fill with compaction each 20cm and a third layer of 30cm agricultural soil as a finish layer. m2 2700 The price should include hiring a survey engineer to be present on site during the project time Total of Bill No. 1 Earth Works - page 1 / 6 Price/ Unit Total USD Jericho Agro Industrial Park Bill No. 2 Steel Works Item No Unit QTY 2.1 Supply and install steel ready made fence angles180cm high fixed 40cm in plain concrete foundation size (40X40X40 cm ) every 3m length along the boundary wall of the site, price shall include the cost of excavation, and disposal of the deprease, subgrade layer of 80X80X40 cm fine aggregate (16mm one size) under the foundation, the plain concrete foundation and welding 3 steel bars Ø 10 35cm length in different direction embedded in the concrete foundation. All as shown on drawings and instructed by the site engineer No. 420 2.2 Supply and install ready made 2.2mm thick galvanized diagonal streched steel mesh 150cm high for the site boundary fence, the price should include supplying and installing of 3mm thick galvanized steel wires to be stretched on the steel angles each 20 cm high and two stretched diagonally between each and every support. All as shown on drawings and instructed by the site engineer m2 1850 2 Description Steel Works A. The submittal of shop drawings for the satisfaction of the Engineer prior to fabricating the units. B. The fabrication and installation of full scale model for part of metal works for inspection and approval of the Engineer before commencement of work. Total of Bill No.2 Steel Works - Page 2 / 6 Price / Unit Total USD Jericho Agro Industrial Park Bill No. 3 Soil test Item Description Unit No 3 soil test 1. Bore Holes Before the Start of work and in the phase of preparing the shop drawings, the contractor shall carry out and on his own expense 10 bore holes 20m depth according to the following terms: QTY 1.1. Locations of boreholes to be determined in cooperation with the consultant to avoid duplication with previous performed test. 1.2. Drilling of boreholes: Boreholes shall be drilled in a way that the surface and subsurface characteristics can be assessed. Properties of the subsurface soil or rocks can be determined through the drilling of boreholes. 1.3. Sampling from Boreholes: Samples shall be taken at different depths all over the drilling depth. Disturbed and undisturbed samples shall be taken. For further investigation, the following undisturbed samples could be obtained depending on encountered soil or rock. 1.3.1. The core samples will be taken from the rock layers, using double tube core barrel (3 inches), these samples will be taken according to (ASTM D 2113-83) “Diamond core drilling for site investigation” 1.3.2. Standard Penetration Test (SPT) will be performed to obtain split spoon samples, in order to assess the consistency and relative density of the soil. This test will be carried out at interval of 1.5 to 2.0 m, or when a different layer in encountered during the drilling. This test will be performed according to (ASTM D 158684), “Standard Test Method Penetration Test and SplitBarrel Sampling of Soils”. 1.3.3. Shelby tube samples will be taken from the cohesive soil, if encountered. This method of sampling will be carried out according to (ASTM D 1587), “Standard Practice for Thin-walled Tube Geotechnical Sampling of Soils”. A. soil drill for bedrock, soil and gravel deposits at 20 m depth including standard penetration test at every 1.5 m intervals in each borehole Meter Depth (MD) Total of Bill No. 3 Bore Holes - Page 3 /6 200 Price / Unit Total USD Jericho Agro Industrial Park Bill No. 4 Storm Water Channel Item No Description 4 The Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications. The words engineer below means owner's engineer. The rate include the following: Unit QTY 4.1 Cut in any kind of soil, concrete, asphalt or stone walls to reduce level below site leveling for storm water channel and to reach the desired level according to drawings and site instructions .The price should include the removal of excavated materials from the site to an approved dump location and adjustment store. m3 3200 4.2 Supply and lay aggregate (16mm one size) first class depth 50 cm below water channel. The price should include preparing the natural ground and compacting it before laying the aggregate. All according to specifications, drawings and direction of the site engineer m3 1120 4.3 Supply & install blinding Concrete B200 of 28 days cube crushing strength 200kg/cm2. Price shall include cleaning, vibration, shuttering and making good of ground surface before casting the concrete. Price shall include all nails, forms and equipments needed. m3 195 4.4 REINFORCED IN-SITU / READY MIXED CONCRETE m3 700 The price should include hiring a survey engineer to be present on site during the project time B300 - 300 Kg / CM2] Supply & install concrete B300 of 28 days cube crushing strength 300kg/cm2. Price shall include the following: 1. Cleaning and making good of surfaces before casting of concrete 2. Steel reinforcement workmanship as per drawings. 3. Form-work of any type or shape . 4. Any materials such as nails, wires , 6mm steel for shuttering or any other material or workmanship needed for a best completion of the works . 5. Installation of water stop 20 cm high, 1cm thick. For expansion joints each 12m length. 6. All steel reinforcement of any diameter and shape of high yield stress steel. Concrete water channel of any shape, depth and size 4.4.1 (every 12m length) including water channel foundations and walls. Total of Bill No. 5 Storm water channel - Page 4 / 6 Price / Unit Total USD Jericho Agro Industrial Park Bill No. 5 Provisional items Item No 5 Description Unit QTY Job 1 L.m 500 No. 170 m2 1050 The Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications. The words engineer below means owner's engineer. The rate include the following: The price should include hiring a survey engineer to be present on site during the project time The Contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings. 5.1 Rehabilitation of the existing building on site to be used as offices for the PIEFZA and all visitors during the entire period of the project. The contractor should estimate the cost of rehabilitation of the building including door, windows, painting, electricity, sanitary, tiles, aluminuim and steel works, insulation, airconditioning... to be functioned as any normal office building 5.2 The following notes should be considered when pricing for the conduit pipes around the PV site: 1- The price shall include all required digging or excavation backfilling,coring and cement covering as specified. 2- The price shall include all connections to exsisting drainage pipes and manholes if needed.includded cutting in tile & asphalt ,retiling,repair the asphalts 3- The contractor must consider keeping the system running where needed during the whole construction period. Supply and install UPVC 10" pipes HOLUIOT Taken to the rain water around the road of the pv site including digging for pipes,gutting,opening in street,supply with all necessary fittings 5.2.1 such as elbow,tee,Y,….etc,for sewage disposal and vent pipe, the price allso include for digging,supports,hanggers,and laying at least 8cm concreate arround the pipes,approve manufacture for pipes and fittings: ( red blassim) 5.3 Supply and install steel ready made fence angles 240cm high fixed 40cm in plain concrete foundation size (40X40X40 cm ) every 3m length along the boundary wall of the PV site, price shall include the cost of excavation, and disposal of the deprease, subgrade layer of 80X80X40 cm fine aggregate (16mm one size) under the foundation, the plain concrete foundation and welding 3 steel bars Ø 10 35cm length in different direction embedded in the concrete foundation. All as shown on drawings and instructed by the site engineer Supply and install ready made 2.2mm thick galvanized diagonal streched steel mesh 200cm high for the PV site boundary, the price should include supplying and installing of 3mm thick 5.3.1 galvanized steel wires to be stretched on the steel angles each 20 cm high and two stretched diagonally between each and every support. All as shown on drawings and instructed by the site engineer Total of Bill No. 4 Provisional items - Page 5 / 6 Price / Unit Total USD Jericho Agro Industrial Park Summary of Civil Works Bill No. Description 1 Excavation & Earth Works 2 Steel Works 3 Soil Test 4 Storm Water Channel 5 Provisional items Total (Excluding Value Added Tax - VAT) The Sum of (in words) And Contractor Name: Authorized signatory: Signature & Stamp : Date: Summary- Civil - Page 6 / 6 Total ( USD )