240-109836076 Unique Identifier ANNEXUTE B OBJECTIVE CRITERIA Revision Rev. 0 Revision Date April 2019 Group Technology and Commercial Step 4 Objective Criteria Objective Criteria (Non-weighted criterion) In terms of the PPPFA, the application of objective criteria may be a valid and justifiable reason why a tender is not awarded to the highest scoring / highest ranked supplier, after application of the 90:10 preference points system. Objective criteria will generally be applied after evaluation, and are generally the criteria / conditions specifically linked to contract award (viz., legal compliance, adherence to contract terms and conditions. The requirements for the objective criteria do not form part of the above Part A and Part B; however, they will be required from the recommended tenderer/s to submit them before the contract award NOTE: SAFETY: The documents required as Objective criteria should be in line with the scope of work NOTE: SD& L: The objective criteria of this package are to advance participation of Local businesses especially those that are within designated Local to site areas. The Project team has therefore, identified opportunities to determine Local development objectives which enable Eskom to maximise its contribution in the growth and development of the Local Economy. The objective criteria include the following: 1. Supplier Development and Localisation The objective criteria for boiler turbine roof repair are to advance participation of businesses that are BBBEE compliant around South Africa. Job Creation Suppliers should mention the number of jobs created and retained as a direct result of the contract. These proposals shall be made in the SD&L Compliance Matrix as shown below. Suppliers are required to source local to site labour on semi-skilled and unskilled labour to increase job creation around Duvha Power Station. Number of jobs to be created as a result of this contract Number of jobs to be retained as a result of this contract 24 240-109836076 Strategy R1M-R10M CONFIDENTIAL TE – Group Technology & Commercial Effective April 2016 Page 1 of 5 240-109836076 Unique Identifier ANNEXUTE B OBJECTIVE CRITERIA Revision Rev. 0 Revision Date April 2019 Group Technology and Commercial The objective criteria for boiler turbine roof repair are to advance participation of businesses that are BBBEE compliant around South Africa. 2. ENVIRONMENT Environmental Policy (In line with ISO 14001), signed and in line with ISO 14001 This requirement is mandatory for submission before the contract award Required: Attach signed copy NOTE: Suppliers need to get Duvha Waste Management Procedure and Oil Management Procedure from the Environment Department prior to the contract commencement. 3. SAFETY Baseline Risk assessment (In line with scope of work) Note: The Client will provide a Project specific risk assessment to be amended into your baseline to the Contractor awarded. This requirement is mandatory for submission before the contract award Required : Attach signed copy Safety Policy This requirement is mandatory for submission before the contract award Required: Attach signed copy Health and Safety Plan (In line with the scope of work) Required: Attach signed copy Fall Protection Plan INCLUDING A ROOF WORK METHOD STATEMENT (In line with scope of work) This requirement is mandatory for submission before the contract award This requirement is mandatory for submission before the contract award Required: Attach signed copy Supervisor Safety Training (HIRA, Legal Liability, Supervisory training, Introduction to OHS Act etc) This requirement is mandatory for submission before the contract award Required : Attach proof of competency 24 240-109836076 Strategy R1M-R10M CONFIDENTIAL TE – Group Technology & Commercial Effective April 2016 Page 2 of 5 240-109836076 Unique Identifier ANNEXUTE B OBJECTIVE CRITERIA Revision Rev. 0 Revision Date April 2019 Group Technology and Commercial The acknowledgement form for Eskom's rules and requirements (in Annexure B) This requirement is mandatory for submission before the contract award Required: signed and submitted Valid letter of good standing Required: Attach copy of a valid Registration with the Compensation Commissioner (COID) or a licenced mutual company or an equivalent of it (for international bidders). This requirement is mandatory for submission before the contract award QUALITY Functionality Requirements SECTION A : Quality Management System Requirements ISO 9001:2008/17025 Option 1) Valid certification of Quality Management System by an ISO accredited body A.1 Product / Service Scoping on ISO certificate is defined and relevant This requirement is mandatory for submission before the contract award A.2 Certificate by Approved and Authorized certification authority A.3 Certification Authority has Recognized International Accreditation A.4 Validity (expiry date) of certificate Sub-Section A Score Option 1 24 A.1 Quality Manual A.2 Copy of Quality Policy signed by top management. A.3 Procedure for Control of Documents A.4 Procedure for Control of Records A.5 Internal Audits Procedure A.6 Procedures for Control of Nonconforming Product A.7 Corrective Action Procedure A.8 Preventive Action Procedure. 240-109836076 Strategy R1M-R10M CONFIDENTIAL This requirement is mandatory for submission before the contract award TE – Group Technology & Commercial Effective April 2016 Page 3 of 5 240-109836076 Unique Identifier ANNEXUTE B OBJECTIVE CRITERIA Revision Rev. 0 Revision Date April 2019 Group Technology and Commercial SECTION B : Evidence of QMS in operation (Tender Quality Requirements -Ref QM-58 or 240-51544462) B.2 Signed Organisational structure & Quality department reporting structure. B.3 Additional Quality Management Accreditations (i.e. NDT/NDE/RBI/Welding) B.4 Copy of procedure for control of suppliers & subcontractors B.5 Copy of Completed non-conformance report (NCR) B.6 Copy of Completed Corrective Action report (CA) B.7 Copy of Completed Preventative Action report (PA) This requirement is mandatory for submission before the contract award B.8 Copy of Customer satisfaction surveys SECTION C : Contract Quality Plan Requirements (Ref QM-58 Annexure C or 240-51544462) Contract Quality Plan as per Scope of Works (Ref ISO 10005 / 39-59 / 39-71) NB!!!! draft Contract/Project Quality Plan has important QA deliverables C.1 Supplier identified the persons responsible for drafting the CQP/PQP C.2 Scope of CQP/PQP is complete, and aligned with the Works Information. C.3 Acceptance of CQP/PQP by Employer (meeting of Quality objectives) Objective Evidence, requirements will be submitted after the contract is awarded C.6 Resources- Quality department organogram of all QA & 24 240-109836076 Strategy R1M-R10M CONFIDENTIAL TE – Group Technology & Commercial Effective April 2016 Page 4 of 5 240-109836076 Unique Identifier ANNEXUTE B OBJECTIVE CRITERIA Revision Rev. 0 Revision Date April 2019 Group Technology and Commercial QC resources. C.8 Setup communication channel on quality issues (fixed contract meetings) C.9 Purchasing- Submit a list of all suppliers and subcontractors. C.11 Describe Procedures in dealing with Customer property C.12 Submit process & procedures for Storage and handling C.13 Procedure & draft Concession request for Nonconforming products C.14 Describe monitoring and measurement procedures C.15Identify Inspection and testing equipment and calibration certificates. Functionality Criteria SECTION E : User defined additional Requirements & miscellaneous (Ref QM-58 or 240-51544462) Customer specific requirements & other standards and required can be listed and evaluated here This requirement is mandatory for submission before the contract award E.1 Annexure (A ) NOTE: ALL THE ABOVE OBJECTIVE CRITERIA REQUIREMENTS WILL BE HANDED IN WITH THE TENDER OR WITHIN ONE WEEKS OF NOTIFICATION BY THE ASSISTANT PROCUREMENT OFFICER 24 240-109836076 Strategy R1M-R10M CONFIDENTIAL TE – Group Technology & Commercial Effective April 2016 Page 5 of 5