LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 1. SCOPE This Section of the Power Systems Live Working Manual details the procedures to be followed when HV overhead lines require to be worked on Live using Hot Stick Working techniques. The procedures apply the principles established by the Electrical & Mechanical Safety Rules (Electrical and Mechanical) 4th Edition to achieve Safety from the System and in particular Specialised Procedure SP3. 2. ISSUE RECORD DATE June 1996 March 1997 September 1998 Issue No. DLWM 5.2 Issue A DLWM 5.2 Issue B PSLWM 5.2 Issue C AUTHOR A Rae J Smart R J McGill February 2004 4 D D Kilday 3. AMENDMENT DETAILS Initial issue. Update. Revised to change “Distribution” to “Power Systems.” Updated for ferroresonance and changes to pole shrouding policy also included - 72 pages. ISSUE AUTHORITY Author Owner Issue Authority David Kilday Senior Standards Engineer Jack Neilson Operational Compliance Manager William Cuthbert Business Risk & Safety Manager __________________________________________________________________________________________ © SP Power Systems Limited -1PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 4. CONTENTS Page No. 1. SCOPE ........................................................................................................................... 1 2. ISSUE RECORD........................................................................................................... 1 3. ISSUE AUTHORITY ................................................................................................... 1 4. CONTENTS .................................................................................................................. 2 5. DEFINITIONS .............................................................................................................. 4 6. ASSESSMENT .............................................................................................................. 4 7. APPLICATION OF SAFETY RULES & GENERAL SAFETY ............................. 5 7.1 Authorisation ....................................................................................................... 5 7.2 Live Line Tools and Equipment ......................................................................... 6 7.3 General Safety Precautions ................................................................................ 6 8. TRAINING & AUTHORISATION OF STAFF ........................................................ 9 9. ORGANISATION, CONTROL & OPERATION OF HV LIVE WORKING ..... 10 9.1 Introduction ....................................................................................................... 10 9.2 Procedures .......................................................................................................... 10 9.3 Organisation....................................................................................................... 10 9.4 Control of HV Hot Stick Working ................................................................... 10 9.5 Operation of HV Hot Stick Working............................................................... 11 10. TOOLS & EQUIPMENT........................................................................................... 11 10.1 Approval ............................................................................................................ 11 10.2 Marking Numbering & Recording .................................................................. 11 10.3 Testing & Care................................................................................................... 12 10.4 Use of Tools & Equipment ................................................................................ 15 10.5 Assessment of Safe Working Loads ................................................................. 26 __________________________________________________________________________________________ © SP Power Systems Limited -2PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11. PROCEDURES FOR WORK ON OR NEAR HV OVERHEAD LINES ............. 34 11.1 Procedure WL1.130........................................................................................... 34 11.2 Procedure WL1.131........................................................................................... 37 11.3 Procedure WL1.132........................................................................................... 39 11.4 Procedure WL1.133........................................................................................... 47 11.5 Procedure WL1.137........................................................................................... 50 11.6 Procedure WL1.140........................................................................................... 55 11.7 Procedure WL1.141........................................................................................... 68 __________________________________________________________________________________________ © SP Power Systems Limited -3PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 5. DEFINITIONS 5.1 Terms printed in bold type are as defined in the ScottishPower Safety Rules (Electrical and Mechanical) 4th Edition. 5.2 For the purposes of this section of the Power Systems Live Working Manual the following definitions apply: HV Live Working The carrying out of work of any kind on Live High Voltage overhead lines, using Approved tools and equipment. HV Hot Stick Working The carrying out of work on Live HV overhead lines from an Approved Insulated Scaffold or where appropriate a pole, using tools and equipment Approved for the purpose. 6. ASSESSMENT 6.1 All work on or so near Live exposed HV conductors that Danger may arise requires assessment before the commencement of work to ensure that Danger will not arise during the course of the work. This assessment will be carried out by the Authorised Person who is to undertake the work. In all cases, however, as part of the assessment, Apparatus shall be subjected to a routine inspection prior to the start of any work to ensure that Danger will not arise due to the condition of the Apparatus. Should this inspection reveal any significant deficiency in the Apparatus which would prevent Approved procedures being applied effectively, no attempt shall be made to work on the Apparatus whilst it is Live. 6.2 Ferroresonance is a phenomenon of instability produced by a particular combination of circuit elements. A ferroresonant circuit may be formed when a cable and a transformer (with a load of less than 3% of its rated capacity) are simultaneously energised or de-energised one phase at a time. An example of energising or deenergising one phase at a time is making/breaking jumpers using “outage free” techniques. The resultant power frequency overvoltage can be up to four times the applied voltage. This overvoltage will start when the first phase is energised/deenergised and will persist until the switching on all phases is complete. Power frequency overvoltage surges of this magnitude will cause deterioration of the cable insulation and the transformer winding insulation and may lead to faults. Surge __________________________________________________________________________________________ © SP Power Systems Limited -4PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ arresters will protect the transformer and the cable from the overvoltage. However, due to the length of time that the surges are on the system, “thermal run-away” may occur within the arrester blocks. “Thermal run-away” will lead to a catastrophic failure of the arrester. When using “outage free” techniques, the overhead network should be assessed for the possibility of ferroresonance. Where making or breaking jumpers will affect a transformer that is within 700m of an HV cable, a ferroresonant circuit may be set up. In order to prevent ferroresonance from occurring, the jumpers must be connected or disconnected within ten seconds. This can be achieved using either: an Approved portable air-break switch or Approved “make and break” tools. 7. APPLICATION OF SAFETY RULES AND GENERAL SAFETY The Safety Rules for HV Hot Stick Working are as stated in SP3 of the ScottishPower Safety Rules (Electrical and Mechanical) 4th Edition. This section of the Power Systems Live Working Manual gives guidance on the application of the Safety Rules and outlines general safety topics. 7.1 Authorisation 7.1.1 The Approved Procedures referred to in SP3 are those Approved for inclusion in this section of the Power Systems Live Working Manual by the Engineering & Transmission Operations Manager, Power Systems Division. HV Hot Stick Working shall be carried out in strict compliance with these procedures. 7.1.2 To comply with SP3.1(i) an Approved procedure may only be used by a team, every member of which will be suitably trained and Authorised according to one of the following categories:WL1.SS1 As a member of a Live working team to carry out and supervise Approved HV Hot Stick Working procedures. WL1.SS2 As a member of a Live working team to carry out Approved HV Hot Stick procedures under the Personal Supervision of a WL1.SS1 Authorised Person. 7.1.3 An HV Hot Stick Working team will consist only of Authorised Persons, one of whom shall be LL1 Authorised. Before any HV Hot Stick Working commences one WL1.SS1 Authorised Person must be nominated as being in charge. All HV Hot Stick Working must be carried out under his Personal Supervision. __________________________________________________________________________________________ © SP Power Systems Limited -5PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 7.2 Live Line Tools and Equipment 7.2.1 7.3 To ensure compliance with SP3, Sub-Section 10 of this Section lists the tools and equipment Approved by the Engineering & Transmission Operations Manager, Power Systems Division which will be used for HV Hot Stick Working and details a numbering and recording system and a testing and maintenance procedure. General Safety Precautions The General Safety Precautions detailed in SP3 must be complied with. 7.3.1 HV Rubber gloves shall be used at the discretion of the linesman or when specifically called for in a procedure. 7.3.2 Safety helmets of Approved type must be worn at all times by all members of the team when working on Live Lines. Any Person in the close vicinity of the team must also wear an Approved safety helmet. 7.3.3 Before any HV Live Working commences, the auto-reclose feature applied to that circuit at the point of work shall, where it is practicable to do so and with the consent of the Control Person, be rendered inoperative. The method of achieving this shall ensure one shot to lockout operation in the event of a fault at the point of work. 7.3.4 Where it is not practicable to render auto-reclose features inoperative, the Control Person shall be notified. 7.3.5 The use of HV Hot Stick Working procedures shall be restricted to favourable weather conditions. Adverse weather conditions include mist, fog, snow, thunder and lightning and where the wind is such that control of Live Line tools is adversely affected. Work may continue in light rain at the discretion of the Person in charge of the team, except in those procedures in which ropes are used in close proximity to Live conductors. 7.3.6 In the event of adverse weather conditions arising, the work shall be made safe as quickly as possible with the conductors either in their normal positions or securely held by HV Live Working equipment. Work shall not recommence until the adverse weather conditions have passed. Where work is suspended through adverse weather arising or darkness overtaking the work, the conductors shall be made safe as above and the Control Person informed immediately. Before recommencing work, the HV Live Working equipment shall be shaken to remove droplets of water and sticks wiped dry using a clean cloth or chamois leather. __________________________________________________________________________________________ © SP Power Systems Limited -6PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ Where they are in contact with Live conductors the sticks shall be wiped within the handling zone only. HV rubber gloves shall be worn for this operation. 7.3.7 All work shall be subject to a preliminary consideration by the linesman in charge to ensure that it may be safely accomplished by HV Hot Stick Working procedures and that the safe working loads of the tools and equipment will not be exceeded. (Sub-Section 10.5 of this Section). HV Hot Stick Working procedures involving displacement of conductors shall not be used if the line conductors to be worked on are damaged or are jointed with mid-span joints other than the compression type in the spans on either side of the point of work. 7.3.8 Where conductors are displaced from their normal positions, safe clearances between conductors and between any conductor and the ground or other object shall be maintained. 7.3.9 No pole that is badly decayed, or damaged, shall be climbed. The only Procedures that may be carried out on a decayed or damaged pole are WL1.140 (Jumper cutting) and W1.41 (pole replacement). In these cases, work must be carried out from replacement poles or from Approved scaffolding. 7.3.10 Before commencing HV Hot Stick Working on lines rated up to 11.5kV any unearthed steelwork shall be tested by the application of the Approved crossarm proving device. If the steelwork is found to be Live, Safety Distance shall be measured from the lowest unearthed steelwork. If it is found to be not Live, Safety Distance many be measured from the lowest Live conductor. On lines rated above 11.5kV, if there is reason to suspect that unearthed steelwork may be Live, Safety Distance shall be measured from the lowest unearthed steelwork. In all other cases unearthed steelwork shall be earthed with the Approved earthing carriage following which the Safety Distance may be measured from the lowest Live conductor. 7.3.11 Before displacing conductors Approved insulated shrouding should be applied to crossarms and stay tops. 7.3.12 All poles on which work is to take place shall be fitted with a red marker band at the Safety Distance. No Person shall allow any part of his body to pass above the marker band. The Safety Distance is specified in SP.3 and shall be measured from the lowest Live conductor or unearthed steelwork as stated in paragraph 7.3.10 above. __________________________________________________________________________________________ © SP Power Systems Limited -7PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 7.3.13 During the progress of work, the marker band may, on the instruction of the person in charge, be removed or repositioned to indicate the new working limits. Before the marker band can be removed or repositioned it may be necessary to remove earth bonding from steelwork at different levels on the pole. 7.3.14 HV Hot Stick Working Procedures involving conductor displacement shall not be used on any pole with over-running earthwire, under-running earthwire or catenary wire. 7.3.15 Wood poles erected under Live Lines in preparation for HV Live Working shall be shrouded in accordance with relevant procedures in this Manual, and shall be so erected as to be 0.15m clear of Live conductors. They shall never be left in constant contact with Live conductors. 7.3.16 Adopting the Procedure WL1.140 jumpers can be cut and removed to create points of Isolation prior to work proceeding under Permit for Work conditions. 7.3.17 PSMSP 1.4 gives dispensation for work to proceed without the issue of a Safety Document on specific items of Apparatus where they have been disconnected by HV Live Working Procedure WL1.140 to create points of Isolation and provide Safety Distance. The specific items are: (a) (b) (c) (d) (e) Pole mounted auto reclose circuit breakers Pole mounted auto sectionalisers Air-break isolating switches Pole mounted HV fuse units Pole mounted transformers The work shall be assessed and Approved by a Senior Authorised Person. 7.3.18 Whilst moving conductors supported by HV Live Working equipment, the operating linesmen shall at all times be prepared to lock the wire tongs in their saddles should a dangerous situation seem likely to arise. No conductor shall be moved on wire tongs unless the safety pins are in place on the wire tong saddles, lever lifts and rope snubbing brackets. 7.3.19 In the event of a conductor being "lost" whilst handling with wire tongs, the operating linesmen shall immediately loosen their grip on all Apparatus and lean back in their safety harnesses. __________________________________________________________________________________________ © SP Power Systems Limited -8PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ This will reduce to a minimum the effects of any voltage gradient down the pole. In recovering a conductor the utmost caution must be exercised even though the conductor may have fallen on to insulated shrouding. In case of doubt, additional wire tongs shall be used to recover the conductor. Failing this the Control Person must be notified with a view to making the line not Live for the recovery of the conductor. 8. 7.3.20 When working at the pole top after the conductors have been removed, operators shall position themselves and the equipment to give optimum clearance from the conductors on either side. 7.3.21 Before any Live conductor is cut, all tension must be removed from it and the conductor is obviously slack. The conductor on each side of the cut must be securely held to prevent reduction of clearances to other Live conductors or equipment once the cut is made. 7.3.22 Limitation of current, which may be broken by conductor cutting as specified in Procedure WL1.140, must be observed. 7.3.23 All pieces of binding wire, stirrups and other debris shall be collected and removed from the site on completion of the work. TRAINING AND AUTHORISATION OF STAFF 8.1 SP3.1(ii) states that "all staff engaged on HV Hot Stick Working shall have received appropriate training and shall possess written Authorisation for HV Hot Stick Working from the Company". 8.2 Linesmen engaged on HV Hot Stick Working require to be appointed and trained as laid down in SP3.1 and Authorised in writing in accordance with PSMSP 5.1. They will therefore require to be thoroughly conversant with the requirements of the Safety Rules (Electrical & Mechanical) 4th Edition and trained in the Approved Procedures and the practical and safe use of Approved tools. 8.3 Although engineers generally require no formal training in HV Hot Stick Working they need to appreciate the possibilities, limitations and general philosophy of HV Hot Stick Working. __________________________________________________________________________________________ © SP Power Systems Limited -9PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 9. ORGANISATION, CONTROL AND OPERATION OF HV LIVE WORKING 9.1 Introduction Live Working as a general term covers work on High Voltage overhead lines with the conductors Live, which may take one of three forms known in nationally agreed terminology set out in A.C.E. Report 14 (1967), as, (i) Hot Stick Working, (ii) Bare Hand Working and (iii) Live Line Tapping. Bare Hand Working and Live Line Tappings are not Authorised for use in Power Systems, Scotland. 9.2 Procedures 9.2.1 This section of the Manual contains the Approved Procedures for Hot Stick Working to be used in ScottishPower and shall be referred to as HV Hot Stick Working. 9.2.2 Specialised Procedure SP3 of ScottishPower Safety Rules (Electrical and Mechanical) 4th Edition contains the Safety procedures for work on Live High Voltage Overhead Lines up to and including 33kV. SP3.1(i) states "No HV Hot Stick Working shall be carried out except in accordance with Approved procedures". 9.2.3 9.3 9.4 To comply with SP3.1 (i) this Section of the Live Working Manual details the Approved Procedures which are issued by the Business Risk and Safety Manager on behalf of the Managing Director, Power Systems Division and must be strictly adhered to. Organisation 9.3.1 The number of persons in a team is dependent on the Procedure being undertaken and shall include at least one WL1.SS1 Authorised Person. 9.3.2 Transport shall be suitable for carrying, in a secure manner, the equipment required to accomplish the Procedures to be carried out. Control of HV Hot Stick Working The Control Person shall be responsible for the recording of work carried out Live using HV Hot Stick Working techniques in accordance with OPSAF-11-032 (PSMSP 5.2). __________________________________________________________________________________________ © SP Power Systems Limited - 10 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 9.5 Operation of HV Hot Stick Working 9.5.1 Jobs to be done by HV Hot Stick Working methods will accumulate from line inspections and construction requirements. 9.5.2 The Linesman in charge of the HV Hot Stick Working shall make the final decision on site that all conditions are suitable before work commences. 10. TOOLS AND EQUIPMENT 10.1 Approval The Engineering & Transmission Operations Manager, Power Systems Division, must approve all tools and equipment for HV Hot Stick Working in accordance with the Approved Equipment Register. 10.2 Marking Numbering and Recording 10.2.1 A clear mark in the form of a red band shall be applied and maintained on every Approved HV Live Working tool or piece of equipment where appropriate, indicating limits of safe handling as detailed in SP3. 10.2.2 Each tool shall be identified by a serial number. The number will be prefixed by a code and will be permanently stamped on the metalwork. 10.2.3 A record card will be kept for each tool and shall contain the following details: (i) (ii) (iii) (iv) (v) The tool number The name or trademark of the manufacturer. The tool type reference or description. The safe working load (SWL) as specified by ScottishPower. The date of manufacture, year and month (if possible). The cards will be used for recording inspection dates and remarks. The cards will be filed in a suitable container and kept beside the HV Live Working tools. __________________________________________________________________________________________ © SP Power Systems Limited - 11 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ A suitable card format is produced below: LIVE LINE EQUIPMENT RECORD MANUFACTURER: DESCRIPTION: SERIAL NO. _________ \ _________ \ ________ DATE COMMISSIONED: S.W.L. _______________ \ _____________ TENSION COMPRESSION MECHANICAL AND/OR ELECTRICAL INSPECTION/TEST DATE 10.3 TYPE CONDITIONS FOUND AND ACTION TAKEN INITIALLED Testing and Care 10.3.1 Introduction 10.3.1.1 The Safety Rules set out the responsibility for ensuring that tools and equipment are in good condition before use. 10.3.1.2 This Section of the Live Working Manual deals with the care and maintenance required for the different types of tools and equipment used in HV Live Working to ensure that they are kept in good condition. 10.3.1.3 All tools and equipment must be clearly numbered and recorded as laid down in Sub-Section 10.2 of this Section. 10.3.1.4 Epoxiglas sticks shall be electrically tested with an Approved tester at 6 monthly intervals, alternately with E.A. Technology test trailer or Approved equivalent and an Approved portable test set. Details of the test shall be entered on the appropriate record card. 10.3.1.5 The mark, which is on all appropriate HV Hot Stick tools indicating limits of safe handling, shall be checked and maintained at 6 monthly intervals. __________________________________________________________________________________________ © SP Power Systems Limited - 12 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.3.1.6 All tools, slings, rope blocks and other items of equipment which are required to take mechanical loading shall be tested and/or inspected on a 6 monthly basis and details of the test/inspection entered on the appropriate record card. Certain items of equipment used for HV Live Working are subject to statutory insurance inspection. These are separately recorded in a Lifting and Handling Register and include rope blocks complete with ropes, slings, draw vices, lifting gins and channel anchors. 10.3.1.7 Additionally all tools and equipment shall be inspected for signs of mechanical damage before and after each operation. A damaged tool or piece of equipment must never be used. 10.3.2 Storage and Transportation 10.3.2.1 All tools and equipment, specifically for HV Hot Stick Working shall be stored in a suitable place. The facilities in the store shall allow for removal of individual tools with them being kept apart to prevent mechanical damage. Heating to provide a warm dry atmosphere and air circulation shall be provided for the HV Hot Stick tools and equipment in storage. 10.3.2.2 The Epoxiglas sticks must be transported in a vehicle adapted to prevent mechanical damage to the sticks. 10.3.3 Epoxiglas Sticks 10.3.3.1 Epoxiglas sticks must never be over-stressed mechanically since the safety of operating personnel is dependent on their condition. Should a stick be accidentally over-stressed it shall be rendered permanently unusable and must be replaced. If a stick is scratched it shall be marked as damaged until it has been repaired and tested or replaced. If a stick is scratched such that the stranding is undamaged the mechanical strength of the stick will be unaffected but the electrical performance may be adversely affected. If a stick is scratched or scored such that stranding is broken the mechanical strength of the stick will be affected and it shall be rendered permanently unusable and must be replaced. __________________________________________________________________________________________ © SP Power Systems Limited - 13 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.3.3.2 These sticks are resistant to moisture but must nevertheless be kept as clean and dry as possible. 10.3.3.3 Before use, each stick must be wiped down with a soft dry cloth. 10.3.3.4 The sticks must never be laid directly on the ground. Racks are provided for laying the sticks out on site and waterproof sheeting is provided for laying equipment on. 10.3.3.5 After use the sticks shall be dried and burnished with a soft cloth before being returned to storage. 10.3.3.6 The high gloss finish on the surface of the tools must be maintained. At regular intervals the tools shall be thoroughly cleaned with an Approved cleaner to remove all traces of dirt or previous coatings of wax. The tools should then be wiped down with a soft cloth and a thin coating of wax polish applied to the entire surface. They should then be burnished with a feltless cloth until a high gloss is obtained. 10.3.3.7 Scratches on Epoxiglas sticks must be repaired as soon as possible using an Approved restorer in accordance with the instructions provided. 10.3.3.8 If any Epoxiglas stick or part of a stick fails the Approved test it shall be withdrawn from service until it has been cleaned, restored and successfully re-tested. 10.3.4 Metal Fittings 10.3.4.1 The metal fittings on Epoxiglas rods shall be kept clean and moving parts properly lubricated with an Approved lubricant. 10.3.4.2 Wire tong saddles shall be inspected for wear on the chains and clamping devices. The wing nuts should be kept free and lightly lubricated with an Approved lubricant. The clamping surfaces should be kept free from grease or oil and regularly cleaned with an Approved cleaner to minimise slip on the rods. 10.3.4.3 Rope blocks shall be inspected for wear on both sheaves and swivels properly lubricated with an Approved lubricant. __________________________________________________________________________________________ © SP Power Systems Limited - 14 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.3.5 Ropes 10.3.5.1 Polythene ropes used for HV Live Working must be stored out of direct sunlight to avoid colour deterioration. They shall be kept free from contamination and abrasion damage. 10.3.5.2 Natural fibre ropes e.g. Manila shall be kept clean and free from damage and shall be replaced if suspect. 10.3.6 Insulated Scaffolding 10.3.6.1 Scaffolding for HV Hot Stick Working shall be used and maintained in compliance with the relevant sections of ScottishPower Procurement Specification 1376/10,002. It shall be kept clean at all times. The Epoxiglas sticks making up the scaffolding shall be inspected and maintained in the same way as the sticks in the tool kit. However they shall not require to be electrically tested. 10.3.7 Approved Cleaners (i) AB Chance Cleaning Kit (ii) White Spirit Approved Lubricant Light machine oil e.g. 3-in-1 oil or equivalent Approved Wax Polish DL Shell wax 1128/28943 available in 3.5 kg tubs from Wilkons/Campbell, Bulennia works, West Drayton, Middlesex Tel. 0735 683886 10.4 Use of Tools and Equipment Tools and equipment shall only be used for a purpose detailed in this Section and in a manner described in the Procedures Section. __________________________________________________________________________________________ © SP Power Systems Limited - 15 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.1 Conductors Moving and Supporting Tools 10.4.1.1 Wire Tongs These are Epoxiglas rods in various lengths from 6 feet to 16 feet, and diameters from 1½ inches to 3 inches with an adjustable clamp jaw operated by rotating the rod. These tongs are used for supporting, manoeuvring and laying off Live conductors clear of the working area. They have a swivelling shackle at the butt end for attachment of a sling, rope block or lever lifts. 10.4.1.2 Wire Tong Saddles Aluminium alloy saddles are used for attaching wire tongs to the line supports. The wood pole type is attached to the pole by a quick acting chain and lever arrangement that incorporates a safety pin device to prevent accidental release. The saddles have clamps that allow the tongs to slide or to be securely held. Where extra clearance is required, extension saddles are used. 10.4.1.3 Lever Lifts These are used in place of wire tong saddles to provide a nonslip fixing at the lower end of the tong where limited movement in line with the tong is acceptable. They are attached to the pole by a quick acting chain tightener and safety pin device. 10.4.1.4 9 foot. Auxiliary Crossarm The 9 foot Auxiliary Crossarm, complete with fork wireholders and fork wireholder insulators, is used as part of a rig to change poles, steelwork or insulators. 10.4.1.5 Wire Tong Block Clamps These are of a similar construction to the clamp associated with the wire tong saddle. When attached to the tong they are used as a fixing for rope blocks where necessary. 10.4.1.6 Insulator Link Sticks These are short Epoxiglas rods fitted with a safety hook at one end and a swivelling shackle at the other. Insulator link sticks are designed for use under tension in series with ropes or rope blocks that cannot be considered to have insulating properties. __________________________________________________________________________________________ © SP Power Systems Limited - 16 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.1.7 Roller Link Sticks These are Epoxiglas rods fitted at one end with a positive locating roller in an adjustable locking gate and at the other end with a swivelling shackle. They are used to exert a lateral pull on conductors or jumpers to give added clearance. 10.4.1.8 Cum-a-long-Clamps The Approved type for HV Live Working is the Klein wire grip. This is placed on the line by an appropriate HV Live Working stick. An automatic gate prevents the clamp from falling from the line. 10.4.1.9 Rope Blocks HV Live Working rope blocks are Gibbs type tufnol blocks reefed with polythene rope. They are normally 3 and 2 type. 10.4.1.10 Crossarm Pulley Anchor This is a steel or aluminium alloy clamp that fits to the crossarm and provides anchorage on both sides for rope blocks etc. 10.4.2 Insulated Hand Tools 10.4.2.1 Tie Sticks This is an Epoxiglas rod fitting with a rotary blade at one end and a universal fitting at the other. It is used for binding and unbinding conductors. 10.4.2.2 Universal Stick This is an Epoxiglas rod fitted with splined universal connectors at both ends and used in conjunction with a range of attachments. 10.4.2.3 Grip-All Clamp Stick This is a general purpose Epoxiglas hand tool fitted with a ring type jaw operated by a ratchet slide on the butt. It is used for the general lifting and handling of accessories. __________________________________________________________________________________________ © SP Power Systems Limited - 17 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.2.4 Wire Holding Stick This is an Epoxiglas hand tool fitted with an adjustable conductor clamp operated by a slide lever. It is used for holding and positioning conductors and tails during conductor cutting and compression operations. 10.4.2.5 Lever Wire Cutters This is an Epoxiglas hand tool fitted with a cutting head; rod operated by a side lever and normally used for cutting light conductors, binders etc. 10.4.2.6 All Angle Cog Wrench An Epoxiglas rod fitted with an adjustable angular head suitable for the attachment of standard socket spanner fittings and operated through cogs by rotating the tool handle. It is used for the insertion and removal of nuts and bolts in the vicinity of Live conductors. 10.4.2.7 Insulated Plier Handles These provide insulated extensions to plier or wire cutter handles when such tools need to be used on or near a Live line. 10.4.3 Tools for Use with Universal Sticks 10.4.3.1 Fixed Head This is used to loosen or pack up binding wires. number of "V" notches for this purpose. It has a 10.4.3.2 Rotary Prong This is a rotating finger or prong also employed for binder work and for the fitting and removal of cum-a-longs and rope blocks etc. on or near Live conductors. 10.4.3.3 Adjustable Insulator Fork This is an adjustable fibre claw for holding and positioning disc insulators. __________________________________________________________________________________________ © SP Power Systems Limited - 18 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.3.4 Security Clip Pusher This is a dual-purpose tool used for pushing out security clips on strain insulators with a curved end for forcing the clips into position again. 10.4.3.5 Security Clip Inserter This tool is used for inserting "W" clips where these have been pushed out or have fallen out of strain insulators on Live lines. 10.4.3.6 All Angle Fuse Puller A versatile adjustable holding and gripping tool used for fuses, shrouding, insulators etc. 10.4.3.7 Inspection Mirror "Mirror and stick" inspections is no longer an authorised procedure in ScottishPower. 10.4.3.8 Conductor Cleaning Brush This is used for the removal of oxide, etc. from conductors before making joints, tappings, etc. Separate brushes must be used for copper and aluminium conductors. 10.4.3.9 Hacksaw This is a standard hacksaw frame fitted with a universal attachment. When this tool is used, goggles must be worn. 10.4.3.10 Pinholder This tool grips the heads of pins or bolts up to approximately 16mm diameter to allow insertion near Live lines. 10.4.3.11 Snap-Out Split-Pin Remover A spring arrangement on this tool facilitates pulling out splitpins. 10.4.3.12 Split-Pin Installing Tool This tool grips split-pins for insertion on Live equipment. __________________________________________________________________________________________ © SP Power Systems Limited - 19 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.3.13 Ratchet Wrench Head This tool allows bolts to be tightened or loosened using a standard socket spanner. 10.4.3.14 Flexible Wrench Head This fits standard socket spanners and its flexibility allows use at limited angles. 10.4.3.15 Skinning Knife This is used for cutting or scraping insulation or cleaning conductors. 10.4.3.16 Hammer Head Where a forceful blow is required near Live conductors, this 1lb. hammer head can be used. It can also be used to detect pole top rot with the line Live. 10.4.3.17 Binder Head This tool is for use with a binder dispenser for rebinding Live conductors on pin insulators. It is made from a blank chuck with a steel rod inserted at right angles. 10.4.3.18 Tie Applicator Ring Head This tool is for applying and removing helical fittings that tie conductors to pin insulators. 10.4.3.19 Tie Pad Applicator Head This tool is for applying the pad onto a conductor where it sits on a pin insulator before application of helical ties. 10.4.4 Other Tools For Use In Contact With Live Conductors 10.4.4.1 Insulated Hanger This tool, installed on a Live conductor, allows safe parking of Live Line taps during installation and disconnection of jumpers and load make-and-break tools. __________________________________________________________________________________________ © SP Power Systems Limited - 20 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.4.2 Chafe Tape Winder This tool is for the application of chafe tape to Live conductors. It is mounted on and fixed to the conductor by a clamp stick. Separate winders should be used for copper and aluminium tapes to prevent contamination. 10.4.4.3 Binder Dispenser In conjunction with the binder head this tool facilitates the binding of Live conductors to pin insulators. 10.4.4.4 Make-and-Break Tool An Approved "make and break" tool shall be used during all jumper connecting or disconnecting operations. The maximum load that can be made or broken using a “make or break” tool without arc-suppression is 50A. Where an Approved “make or break” tool with arc-suppression is used, a maximum load of 185A may be broken. The arc-suppression tool is used also where there is a possibility of ferroresonance, irrespective of load. The tool without arc-suppression operates on the expulsion fuse principle to break load and can be tripped at will by the operation of a trigger. Loads can be made and carried by the closing of a knife switch that is mounted in parallel with the fuse unit. The Approved arc-suppression “make and break” tool is fault rated at 6kA for 1 second. This tool can be used to break the load rapidly and there is spring assistance to make the load. This ensures that all three phases can easily be broken or made in less than 10 seconds and ferroresonance is eliminated. It is recommended that “make and break” tools are used a minimum of 1 span away from poles with surge arresters connected to them. In certain circumstances, this will not be possible, in these instances it is acceptable to use the tools on the same pole as surge arresters. 10.4.4.5 Ampstick Slipon Ammeter This can be fitted to a Universal Hot Stick and used to measure current flowing in an overhead conductor. __________________________________________________________________________________________ © SP Power Systems Limited - 21 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.4.6 Live Line Compression and Cutting Equipment (i) Live Line Hoses 4.6m Hose - BICCON Cat. No. LL H10 - 46. 7.6m Hose - BICCON Cat. No. LL H10 - 76. (ii) Compressor Head Compressor Head - BICCON Cat. No. G10HML (iii) Cutting Head Cutting Head - BICCON Cat. No. G10CM (iv) Appropriate BICCON Compression Dies (v) Compressor For appropriate compressor for use with above equipment, refer to Sub-Section 7.4.5.17 10.4.4.7 By-Pass Jumpers By-pass jumpers of 32mm2 copper or copper equivalent aluminium flexible conductor covered with a 100mm polythene tube with the ends sealed to exclude moisture and terminating in suitable Live Line taps. They are used for bridging sections of conductors before cutting or bridging gaps in conductors before permanent closure. They may be made rigid by insertion in fibreglass or other suitable insulating tubing. The polythene or other insulating materials are not considered as insulation that would reduce minimum clearance. 10.4.4.8 Live Line Tapping Equipment (Fuse Operating Rods) These are sectional or telescopic glass fibre rods for fixing Live Line taps to line conductors from ground level. They may be used in conjunction with a splash plate. __________________________________________________________________________________________ © SP Power Systems Limited - 22 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.5 Ancillary Tools and Equipment 10.4.5.1 Steelwork Shrouding Used to prevent accidental contact of pole-top steelwork by Live conductors, helical ties or binders during binding, unbinding and conductor handling operations. Shrouding is manufactured from glass fibre, polythene or other suitable insulating material in various shapes to suit differing pole-top configurations. 10.4.5.2 Rope Snubbing Bracket A bracket fitted to the pole by means of a quick acting chain tightener with safety pin device and used for securing fall ropes, rope blocks etc. 10.4.5.3 Insulated Platform The Approved platform is Epoxiglas approximately 250mm wide, 1.8m long with pole attachment, Epoxiglas strut and safety rail. This is used where it is necessary to work short distances out from the conductor support. This is a lifting gin which is positioned above equipment, clamped onto the support and used in conjunction with rope blocks and a pulley at the base of the support to raise and lower heavy equipment such as transformers. 10.4.5.5 Cross-arm Proving Device A Seaward CARL Mark 2 Cross Arm Leakage Detector (131A910) which provides a means of checking leakage current on unearthed pole crossarms on Systems up to 11.5kV. A direct earthing device is also available for lines above 11.5kV. 10.4.5.6 Pole Twister This device is fixed by a chain round the pole and provides a lever with which to turn a pole square with a line after erection. __________________________________________________________________________________________ © SP Power Systems Limited - 23 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.5.7 Anchor Pins These are steel rods approximately 1.5m x 38mm which are driven in at an angle to provide anchorage for temporary stays and fall ropes from blocks. 10.4.5.8 Rope Rope used in the vicinity of Live lines shall be polythene rope, normally 3 strand 50mm. Hand lines shall be polythene 3 strand 25mm rope. For temporary stays and extensions to fall ropes attached to insulator link sticks manila rope shall be used. 10.4.5.9 Pole Shrouding There are two Approved methods of shrouding pole tops before erecting the poles close to Live conductors. Approved reusable pole shrouds available can be fitted at pole top or on the pole at any appropriate height. They are rated for touch contact only. On no account must Live conductors be left in constant contact with the shrouding. Bags of 1,000-gauge polythene can be used to shroud the tops of poles erected close to Live conductors. The bags shall be pulled on to the pole top over one another, folded round the pole and bound by tape. Three bags shall be used for 11kV. This is based on accidental touch contact only. On no account shall Live conductors be left in constant contact with the shrouding. Where the new pole is erected other than adjacent to an existing pole then the number of bags shall be doubled to allow for additional contact and rubbing by the conductor. In either case it is bad practice for shrouded poles to be left close to Live conductors for more than 1 week. 10.4.5.10 Scaffolding Scaffolding for HV Hot Stick Working comprises a system scaffold with an aluminium tube base section and up to three insulated upper sections made from Epoxiglas tubing. The scaffolding provides a platform, for carrying out work that cannot be done from a pole. __________________________________________________________________________________________ © SP Power Systems Limited - 24 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.4.5.11 Binoculars These should be suitable for preliminary examination of the pole-top fittings and conductors in the spans on either side of the pole to be worked on. A magnification of 10 x 50 is suitable. 10.4.5.12 Sunglasses Each member of the team must have a pair of suitable anti-glare sunglasses for protection of eyes from sunlight and from particles falling from the lines. 10.4.5.13 Tool Racks for Epoxiglas Rods These are galvanised steel rods with sloping arms on each side, covered with plastic to hold HV Live Working tools without damage. The rods can be driven into the ground to provide a stand for the tools. 10.4.5.14 Waterproof Sheets These are used for laying out HV Live Working tools and equipment on the ground. 10.4.5.15 Rubber Gloves HV rubber gloves as specified in DOM 1.3.1. 10.4.5.16 Portable Test Set AB Chance portable test set. For portable electrical testing of HV Hot Sticks. 10.4.5.17 Compressor Appropriate size of compressor. For use in conjunction with Live Line compression and cutting equipment. Examples BICCON BP10 - CEMBRE CPE-0-P12 __________________________________________________________________________________________ © SP Power Systems Limited - 25 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.5 Assessment of Safe Working Loads 10.5.1 General All overhead lines are erected in accordance with an Approved specification. Factors of safety must not be reduced during the HV Live Working. The methods used therefore must take this into consideration. 10.5.2 HV Hot Sticks - Material Characteristics The HV Hot Sticks are made from "Epoxiglas". "Epoxiglas" consists of thousands of epoxy resin impregnated glass fibres laid lengthways and wound around a unicellular plastic foam core. The core is impervious to water. The strength of these sticks is much greater in tension than in compression. Consequently small diameter tongs are used in tension and large diameter tongs used in compression. As a tong is loaded with compressive force a deflection can be observed. The observed deflection provides a visual guide to prevent overloading. The Safe Working Loads (Compressive) are based on a maximum tong deflection, at its mid-point, of 25mm. Tong break-up in compressive tests to destruction was observed to be of a progressive nature and started with individual strands on the surface breaking with an audible "pop". If during the course of conductors being moved on HV Live Line tongs a "pop" is heard from a stick then the movement should be stopped and reversed immediately and all saddle-clamps locked off. Two tongs in parallel should then be used if work is to proceed. 10.5.3 HV Hot Stick Working-Conductor Support In use the HV Hot Stick Working stick method of conductor support resembles a simple jib crane, the line support and two tongs forming a rigid triangle. One tong acts in tension, the other in compression. The tension tong can if necessary be augmented by use of a rope block between tong and line support. __________________________________________________________________________________________ © SP Power Systems Limited - 26 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ As a result of the different strengths of tongs acting in tension and compression the limiting factor on the loading of a conductor support structure is the S.W.L. of the compression tong. 10.5.4 Safe Working Loads The safe working loads of HV Live Working tools and equipment are shown in Table 1. To avoid the need in every situation to carry out an exercise to calculate the load applied on a support structure, Tables 2(a) and 2(b) have been prepared. These show the maximum wind loading span it is permitted to lift with each size of tong in compression for a given conductor. The method of calculation of these figures is shown in 10.5.5. For the purpose of the calculation the maximum total angle of declination of the conductor on the pole top is taken as 20º. Where a span length greater than that given in Table 2(a) is required to be displaced or where a tong is noted to deflect more than 25mm at its mid point or begins to "pop" then the tong should be augmented by placing another tong of similar size in parallel with it. This method more than doubles the wind loading span which can be displaced. The maximum wind-loading span that can be displaced with two tongs in parallel is given in Table 2(b). __________________________________________________________________________________________ © SP Power Systems Limited - 27 PSLWM 5.2 OPSAF-12-014 Issue 4 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD _________________________________________________________________________________________ TABLE 1 SAFE WORKING LOADS OF HV LIVE WORKING TOOLS SWL Description Wire Tongs 1½ in. x 8 ft. 2½ in. x 10 ft. 2½ in. x 12 ft. 2½ in. x 16 ft. 3 in. x 12 ft. 3 in. x 16 ft. Saddles Lever Lift Snubbing Bracket (per ring) Cum-A-Long Roller Link Stick Insulator Link Stick Rope Blocks 3/2 Small 3/2 Large Polythene Rope 7mm 8mm Manila Rope (Grade 1) 9mm Cross Arm Pulley Anchor Tension lbs. kgf 1,500 2,500 2,500 2,500 >2500 >2500 1,000 1,000 1,000 8,000 1,000 4,000 680 1,135 1,135 1,135 >1135 >1135 450 450 450 3,650 450 1,825 1,400 2,500 635 1,135 425 750 672 >2240 190 325 672 >1000 Compression lbs. kgf 1,030 890 460 1,500 1,300 1,000 1,000 467 403 208 680 590 450 450 __________________________________________________________________________________________ © SP Power Systems Limited - 28 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ TABLE 2(a) MAXIMUM WIND LOADING SPAN FOR SINGLE TONG IN COMPRESSION Tong Size CONDUCTOR H.D. 0.22 Stranded 0.02 Copper 0.05 0.1 No. No. 66 Solid No. 5 H.D. No.3 Copper No.1 1/0 2/0 3/0 4/0 50mm2 ACSR 2½ in. x 10 ft. 3,043 2,616 1,015 47 2,375 1,787 937 270 161 N/A N/A N/A 1,066 2½ in. x 12 ft. 2½ in. x 16 ft. 3 in. x 12 ft. WIND LOADING SPAN (METERS) 2,541 1,000 4,729 2,174 817 4,099 795 116 1,757 N/A N/A 419 1,981 770 3,700 1,462 464 2,877 707 184* 1,709 108 N/A 816 23 N/A 627 N/A N/A 405 N/A N/A 300 N/A N/A 163 759 107* 2,096 3 in. x 16 ft. 4,011 3,468 1,442 261 3,136 2,413 1,381 584 429 233 149 33 1,658 TABLE 2(b) MAXIMUM WIND LOADING SPAN FOR TWO TONGS IN COMPRESSION Tong Size CONDUCTOR H.D. Stranded 0.1 Copper H.D. No. 3 Solid No. 1 Copper 1/0 2/0 3/0 4/0 2 50mm ACSR 2x 2x 2x 2½ in. x 10 ft. 2½ in. x 12 ft. 2½ in. x 16 ft WIND LOADING (SPAN METERS) 862 640 147* 2,630 1,465 1,183 886 722 528 3,323 2,170 1,140 905 645 511 346 2,710 756 143 200* 121* 65* N/A 825 Notes to Tables 2(a) and 2(b) 1 N/A - No span length which can be safely displaced with this tong. 2 * - To achieve this span length the angle of declination of the conductor at the pole top must be no greater than 15º. A method of determining the angle of declination is given in 7.5.6 below. __________________________________________________________________________________________ © SP Power Systems Limited - 29 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 10.5.5 Calculations of Wind Loading Span for Tables 2(a) and 2(b) The loading of a conductor support structure can be considered as the resultant of the following forces: The vertically downward acting weight of the conductor in assumed level adjacent spans plus or minus the vertical component of the tension resulting from line declination or inclination at the work pole. In the worst case the total angle of declination will be 20º i.e. 10º downpull on either side of pole as limited by overhead line specification. As previously stated the conductor support structure is basically a rigid triangle. The effect on the compression tong in this structure of the vertical load produced by the conductor reaches a maximum when that tong is at an angle of approximately 15º to the vertical. If the structure loading is within safety limits at that position, all other positions of the structure will be within the safe limits. Formula W - Conductor weight in kg/m. L1 & L2 - Adjacent span lengths in metres. L3 - L1 + L2 2 T - Conductor Tension in kgf - Conductor angles of inclination or declination (ScottishPower Drawing 00031072, Fig. 1) 1 3 and 2 - 1 ± 2 Total angle of declination For straight line pole with inclination/declination Vertical Force F(Conductor weight) ± (Vertical component) (acting vertically) (conductor tension) F = WL3 ± T (Sin 1 ± Sin F = WL3 ± T Sin ( 1 ± 2) which can be simplified in practice to 2) __________________________________________________________________________________________ © SP Power Systems Limited - 30 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ In worst case 1 and 2 are both 10º Therefore F = WL3 + T Sin 20º Compressive force (b) in tong with conductor laid off at 15º i.e. worst case (ScottishPower Drawing 00031072, Fig. 2) b = COS 15º (WL3 + T Sin 20º) If force in tong is limited to SWL of tong the equation for L3 becomes L3 = SWL/COS 15º - T Sin 20º W Wind Loading Span = SWL/0.966 - 0.342T W 10.5.6 Determination of Angle of Inclination/Declination When considering angles of declination or inclination of a conductor, ignore the sag. Angle 1 and 2 are formed between a level straight line passing through the work pole conductor support and other straight lines passing through the same support and the conductor supports on adjacent poles, as shown in ScottishPower Drawing 00031072, Fig. 3. On site such angles are at pole top level within the Live conductor Danger area. Similar angles must be reproduced at or near ground level where they can be safely measured. The ground level sight lines can be reproduced by using standard fibreglass fuse operating rods fitted with a hook. When doing so, it is assumed that the conductor height above each of the crossarms on the three adjacent poles is the same. When a section is involved adjust levels accordingly. Start at the work pole. alongside the line pole. Hang the fibreglass rods from the crossarm At eye level or other selected level place apply a wrap of yellow or white tape around the pole. Tape the rod at the same level. __________________________________________________________________________________________ © SP Power Systems Limited - 31 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ Hang the rods from each adjacent pole crossarm in turn and tape the poles at level of the tape on the rods. It is then necessary to adjust the levels found to compensate for the off laid conductor position. If the conductor will be uplifted by, say, 1m the work pole PVC band should be lifted 1m or, alternatively, both adjacent pole bands should be lowered 1m. If hedges or the like obstruct intended sight lines all bands can be equally lifted. Measurement of 1 and 2 can then be done by using an Abney level. The Abney level is a simply constructed instrument for measuring angles under field conditions. It has a centre zero degree scale fixed to a sighting tube with a small hole at one end and a wire sight at the other. Part way along the tube and to one side is a fixed mirror set at 45º to the tube sight line. A fast and finely adjustable pointer arm that moves on the degree scale is fitted with a vernier and magnifying lens for accurate reading. A spirit level is fixed to this arm at 90º to the pointer arm centre line. This adjustable spirit level and fixed mirror arrangement allows the horizontal bubble to be seen in a vertical plane alongside the object being sighted. By simultaneously sighting an object, say a pole top or a pole at ground level, and adjusting the instrument until the bubble on its zero line coincides with this object the angle of inclination or declination between a level line passing through the instrument and the object sighted can be read on the instrument scale. To measure the angle hold the Abney level at the height of the PVC band on the work pole, and sight the PVC band on the adjacent pole. Adjust level until bubble coincides with sighted band. Read angle 1, in degrees from Abney scale. To obtain 2 repeat as above but sight on the PVC band on the other adjacent pole. __________________________________________________________________________________________ © SP Power Systems Limited - 32 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 33 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11. PROCEDURES FOR WORK ON OR NEAR HV OVERHEAD LINES 11.1 Procedure WL1.130 - Installation of By-pass Jumpers 11.1.1 Scope of Procedure This Procedure covers the methods and precautions to be followed when using temporary by-pass jumpers to bridge sections of conductor, switches etc. Approved by-pass jumpers consist of 32mm² copper or copper equivalent aluminium flexible conductor covered with a 100mm polythene sleeve, having the ends sealed to exclude moisture. The jumpers terminate in suitable Live Line taps and can be up to 6.5 metres long. 11.1.2 Safety Precautions 11.1.2.1 The polythene sleeve-covering jumper braiding must not be considered as an insulator. 11.1.2.2 When a by-pass jumper is being installed, or is in use, the Safety Distance from it must be maintained at all times. Adequate clearance between the jumper and any steelwork must be maintained. 11.1.2.3 During erection or removal of by-pass jumpers, there is a possibility that one end of the jumper may inadvertently be released when the other end is in contact with a Live conductor. Adequate safety precautions must be taken to prevent the lost end coming into contact with Earth, or infringing Safety Distance to working personnel. 11.1.2.4 During erection and removal of any by-pass jumper, only one Live Line tap at a time shall be connected or disconnected. No attempt shall be made to connect or disconnect both ends simultaneously. 11.1.2.5 No load currents shall be made or broken with a by-pass jumper. Prospective load currents to be broken may be measured with an Approved HV ammeter (installed in a substation or fitted to a Universal Hot Stick) or estimated from transformer full-load capacity. Load current must only be made or broken using either: an Approved portable air-break switch or the appropriate Approved “make and break” tools. The maximum load which can be made or broken using a “make and __________________________________________________________________________________________ © SP Power Systems Limited - 34 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ break” tool without arc-suppression is 50A. Where an Approved “make and break” tool with arc-suppression is used, a maximum load of 185A may be broken. If necessary, load may be reduced by removing LV fuses, where practicable. In order to reduce the possibility of ferroresonance, LV fuses should only be removed from transformers that will not become ferroresonant, as described in Sub-Section 6.2 of this Section. 11.1.2.6 Magnetising currents up to the equivalent of 200kVA connected transformer capacity can be disconnected on Live Line taps used in conjunction with a splash plate. 11.1.2.7 Capacitance current can be made/broken on Live Line taps in conjunction with a splash plate up to the following maximum cable lengths: 1200 metres - (0.06 in²) 1000 metres 70mm² (0.1 in²) 300 metres 95mm² (0.15 in²) 11.1.2.8 When connecting and disconnecting by-pass jumpers, the overhead network should be assessed for the possibility of ferroresonance. Where a transformer is within 700m of an HV cable, a ferroresonant circuit may be set up. In order to prevent ferroresonance from occurring, the by-pass jumpers must be connected/disconnected within 10 seconds. This can be achieved using either: an Approved portable airbreak switch or Approved “make and break” tools. 11.1.3 Erection of Long By-pass Jumper The erection of long by-pass jumpers is no longer an Approved ScottishPower procedure. 11.1.4 Disconnection of Long By-pass Jumper The erection of long by-pass jumpers is no longer an Approved ScottishPower procedure. __________________________________________________________________________________________ © SP Power Systems Limited - 35 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.1.5 Erection of Long By-pass Jumper (Alternative Method) The erection of long by-pass jumpers is no longer an Approved ScottishPower procedure. 11.1.6 Disconnection of Long By-pass Jumper (Alternative Method) The disconnection of long by-pass jumpers is no longer an Approved ScottishPower procedure. 11.1.7 Erection and Disconnection of Short By-pass Jumper 11.1.7.1 Approved tools and equipment for this are as follows: 2 - Grip-all Clamp Sticks 1 - Wire Holding Stick 3 - “Make and Break” Tools 1 - HV Ammeter By-pass Jumpers of required length 11.1.7.2 Test the crossarm steelwork with the Approved crossarm proving device. Mark the pole 0.8 metres down from the lowest Live conductor with a red band. 11.1.7.3 The load current flowing in the overhead conductor should be measured to check if it is within the limitations of the “make and break” tool used. 11.1.7.4 If arc-suppression “make and break” tools are to be used, check that the tools are in the correct position for the work being carried out. The tools are attached to the overhead line near to the jumper that is to be cut. 11.1.7.5 The by-pass jumper is erected with grip-all clamp sticks by two linesmen holding the Live Line taps either on the ends of the jumper or between the end of the jumper and the parking bar of the “make and break” tool. Where required to ensure Safety Distance, the centre of the jumper may be held with a wire holding stick. 11.1.7.6 Apply the first Live Line tap to the “make and break” tool, holding the second tap until the first tap is secure. Apply the second tap to complete the connection. __________________________________________________________________________________________ © SP Power Systems Limited - 36 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.1.7.7 Jumpers shall be connected between the supply line and apparatus in accordance with Sub-Section 11.6.6 of this Section and disconnected in accordance with Sub-Section 11.6.7 of this Section. 11.1.7.8 Using Hot Sticks, open the three “make and break” tools. This may be carried out individually or simultaneously. In either case, all three operations should be completed within 10 seconds. 11.1.7.9 To remove the by-pass jumper, this Procedure is reversed. One tap at a time is removed. The first tap is held clear after disconnection until the second tap is removed. The jumper can then be lowered to ground level and the marker band removed if all work is complete. 11.2 Procedure WL1.131 - Erection and use of insulated scaffolding 11.2.1 Scope of Procedure 11.2.1.1 This Procedure deals with the movement, erection and use of Insulated Scaffolding. 11.2.2 Insulated Scaffolding 11.2.2.1 The function of the insulated scaffolding is to provide a safe working platform for certain HV Hot Stick Working procedures. 11.2.2.2 Equipment Required Insulated Scaffolding Bars and Ground Anchors 30m 12mm dia. rope Earth Lead and Spike Footing Boards for Base and Outrigger Legs 11.2.2.3 Description of Insulated Scaffolding (i) This scaffolding consists of system scaffolding having an aluminium tube base section and up to 3 upper insulated sections. __________________________________________________________________________________________ © SP Power Systems Limited - 37 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ (ii) The aluminium tube base section, complete with outriggers and ladder, is of a fold-up type, and has no removable parts. (iii) The insulated upper sections are made up from lengths of Epoxiglas tubing fitted with interlocking metal ends. (iv) The scaffolding, when erected provides a stable working platform, complete with kickboards and guard-rails. (v) Access to the working platform is via internal ladders. The insulated ladders for access to the upper sections shall not be used for any other purpose. required. 11.2.2.4 Carrying the Scaffolding The scaffolding will normally be transported in its dismantled form in such a manner as to prevent damage to its insulated sections. 11.2.2.5 Erection of the Scaffolding (i) The scaffolding shall only be erected by Competent Persons suitably trained in the erection of system scaffolds to comply DCM 1.3.1 Appendix F (17). These Competent Persons will be HV Hot Stick Working linesmen. (ii) The selection of the erection position for the scaffolding adjacent to and/or underneath Live HV conductors or apparatus shall be made by the LLI Authorised Person in charge of the work and must take into account the following: (a) Ground Conditions (b) Height of working platform required (c) Minimum vertical and horizontal clearance distances required for carrying out HV Hot Stick Working procedures using HV Live Working tools from the platform of the erected scaffold. (d) During erection and dismantling of the scaffolding, the access ladders must only be manoeuvred within the framework of the scaffolding. __________________________________________________________________________________________ © SP Power Systems Limited - 38 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.2.2.6 Safety Precautions (i) Access to the working platform must only be gained via the internal ladders. (ii) When erected adjacent to Live Apparatus, the scaffold must be suitably stayed to prevent movement towards the Live Apparatus. (iii) When erected adjacent to Live Apparatus, the passing up of tools between the scaffold and the Live Apparatus is prohibited. (iv) The uninsulated base section of the scaffold shall be Earthed immediately after its erection. (v) No HV Live Working tools or equipment shall be anchored or fixed to the scaffolding. 11.3 Procedure WL1.132 - Binding and Unbinding Conductors on Pin Insulators 11.3.1 Scope of Procedure This Procedure deals with binding and unbinding conductors on pin insulators using conventional stirrups and binding wire or using helical ties. 11.3.2 Conventional Stirrups and Binds 11.3.2.1 Development work and testing has produced an acceptable stirrup type binder and a suitable method of Live Line application. The design of the stirrup and method of binding are suitable for application to both aluminium and copper. (i) This binding arrangement employs two stirrups with sloping necks and two double binders applied from a dispenser as shown in ScottishPower drawings 00031069 and 00031070, Figs. 1-6 (ii) The sloping neck of the stirrup serves three purposes: (a) It keeps the stirrup clear of the insulator groove where the normal stirrup was found under test to fracture. __________________________________________________________________________________________ © SP Power Systems Limited - 39 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ (b) It provides a facility for firmly binding the stirrups to the insulator (c) It allows the dispenser to operate clear of the insulator sheds during binding in. 11.3.2.2 Approved Tools The Approved tools required for this Procedure are: 1 - 8 ft. universal stick 2 - Binding wire dispensers 1 - Binding wire dispenser head 1 - Insulated wire cutter 11.3.2.3 Applying the Binder 11.3.2.3.1 Two stirrups are fitted round the insulator neck and held in position by fitting a line tap on the slope of the stirrups on one side of the insulator. 11.3.2.3.2 The middle of the binder is placed round the neck of the insulator, above the stirrup and pulled in the opposite direction to the line tap. 11.3.2.3.3 The left end of the binder is passed down between the stirrups and given a half turn anti-clockwise. (Fig. 5A) 11.3.2.3.4 The right end is taken over and round the stirrups then give a half turn anti-clockwise. (Fig. 5A) 11.3.2.3.5 With one leg of binder in each hand tightly wrap the binder anti-clockwise till the top of the slope is reached and stop with the binder ends coming from underneath the stirrups. 11.3.2.3.6 Straighten out the binder and cut the ends to equal lengths. Turn 6mm of the ends of the binder 90º downward. 11.3.2.3.7 Fit binder ends into the dispenser slot furthest away from insulator. Turn dispenser clockwise (looking at the end of the dispenser that the binding wire is applied to) until it reaches the stirrups. Remove the line tap. __________________________________________________________________________________________ © SP Power Systems Limited - 40 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.3.2.3.8 Using a similar technique the other binder is applied. This time the binder is placed under the stirrups and the right end is passed up between the stirrups. The binder is still turned anti-clockwise. The dispenser is turned clockwise. (Fig. 5B) 11.3.2.3.9 The insulator with the stirrups firmly bound to it and the binding wire on the dispensers can now be fitted in position on the crossarm. The conductor can then be lowered into the insulator groove between the dispensers and a universal stick with a dispenser head used to wrap the double bindings tightly round the conductor and stirrups. The ends of the binder should be neatly cut when the binding is complete. 11.3.2.4 Use of the Dispenser 11.3.2.4.1 The binding wire is always wrapped round the conductor and stirrups in the opposite direction to that of the dispenser wrapping (as Drawing, Fig.6), i.e. in crosssection like the letter 'S'. 11.3.2.4.2 When force is applied with the dispenser head at point 'A' (as Drawing Fig 6), the turning moment between the line of the double binding wire and the rod is adequately opposed by the effort needed to straighten both binding wires plus the friction between the rod and the dispenser. The binding can thus be tightly applied. 11.3.2.4.3 During the operation the rod is removed within the dispenser from position 'A' to position 'B' to rotate the dispenser around the conductor. This continues until the bind is complete as indicated in Drawing Fig.2 11.3.2.4.4 The dispenser with any surplus binding wire is cut clear. The dispenser is a re-usable tool. 11.3.2.5 Un-Binding 11.3.2.5.1 To ensure security of the conductor on the pin insulator, no more than 25mm of each binder should be unpicked before the conductor is secured by a wire holding stick. __________________________________________________________________________________________ © SP Power Systems Limited - 41 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.3.2.5.2 Various types of binding will be encountered which will require to be unpicked. With normal cut end binders a fixed blade tie-stick head will be used to start the unbinding and the rotary blade employed to complete it. Where a binder with twisted ends is encountered, it may be necessary to use the small hacksaw on a universal stick or Live Line pliers. 11.3.2.5.3 When un-binding, the tail should never be allowed to attain a length of more than 200mm to avoid possibility of shorting onto the crossarm but should be cut off in pieces as the un-binding progresses. 11.3.2.5.4 Many stirrups are not bound to the top of the insulator. Care should therefore be taken when removing such stirrups that they do not cause injury or shorting by being allowed to fall free. 11.3.2.5.5 Where insulator top clamps have been used in the older lines these will require to be removed using a socket spanner on the all angle cog wrench and care taken on holding the pieces as they are slackened off. 11.3.3 Helical ties 11.3.3.1 This Procedure may be used to apply and remove helical ties when these are used for binding conductors on pin insulators. 11.3.3.2 Approved Tools The Approved tools for this Procedure are: 2 - 8 foot universal sticks 2 - 8 foot conductor holding sticks 1 - tie pad applicator head 1 - tie applicator ring head 1 - fixed blade tie stick head 11.3.3.3 Applying the Helical Tie 11.3.3.3.1 Place the neoprene rubber tie pad (issued with each helical tie) on the two-pronged applicator head fitted to an 8 foot universal stick. __________________________________________________________________________________________ © SP Power Systems Limited - 42 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.3.3.3.2 With the conductor raised clear of the insulator groove place the opened slit of the tie pad against the conductor directly above the insulator and use the angled side of the tie applicator ring on an 8 foot universal stick to push the tie pad off the two pronged head onto the conductor. 11.3.3.3.3 Lower the conductor onto the insulator and ensure that the tie pad is centrally located in the insulator groove. The heads of the holding and lifting tongs require to be adjusted to a minimum of 500mm out from the insulator. 11.3.3.3.4 Grip one leg of a helical tie in an 8 foot holding stick and manoeuvre the tie on to the head of the insulator such that both legs are parallel to the conductor. 11.3.3.3.5 Rotate the helical tie through 180º in anti-clockwise direction ensuring that both legs remain under the conductor. A second holding stick will be required for this operation when working on the middle conductor. 11.3.3.3.6 Continue to hold one leg of helical tie in position alongside conductor and use the ring applicator head on an 8 foot universal stick to wrap the free leg of the tie onto the conductor ensuring that the first turn follows the lay of the tie. When wrapping is complete, snap the end of the leg into place. 11.3.3.3.7 Remove the holding stick from the opposite leg of the helical tie and wrap as described in 11.3.3.3.6 above. 11.3.3.3.8 Finally check that leg ends have snapped into place. A plastic covered fuse puller head on an 8-ft. universal stick may be used to assist in confirming this. 11.3.3.3.9 The lifting and holding tongs can now be removed from the conductor. 11.3.3.4 Removing the Helical Tie 11.3.3.4.1 Lifting and holding tongs should be fitted to the conductor to be worked on. The tong heads require to be a minimum of 500mm out from the insulator. 11.3.3.4.2 Fit a holding stick to the tie and conductor on one side of the insulator. __________________________________________________________________________________________ © SP Power Systems Limited - 43 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.3.3.4.3 Using an 8 foot universal stick with a fixed blade tie head free the tie end on the opposite side of the insulator. 11.3.3.4.4 Use ring applicator head on an 8 foot universal stick to unwrap this leg of the tie. 11.3.3.4.5 Transfer the holding stick to the freed leg of the tie and repeat 11.3.3.4.3 and 11.3.3.4.4 to unwrap the second leg on the tie. 11.3.3.4.6 Use a second holding stick to grip this leg. 11.3.3.4.7 Remove the appropriate holding stick that will allow the tie to be rotated in a clockwise direction. 11.3.3.4.8 Rotate the tie 180º in a clockwise direction and lift clear of insulator head. 11.3.3.4.9 The conductor can now be raised clear of the insulator groove and the neoprene rubber pad removed using a plier head on an 8 foot universal stick. __________________________________________________________________________________________ © SP Power Systems Limited - 44 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 45 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 46 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.4 Procedure WL1.133 - Compression Jointing 11.4.1 Scope of Procedure 11.4.1.1 This Procedure deals with the equipment and fittings that must be used on Live Line compression jointing. It also sets out the correct method of application. 11.4.1.2 Equipment Required 2 - Approved Live Line Hoses 1 - Live Line Compression Head 1 - Live Line Cutting Head Appropriate Compressor and Compression Dies 11.4.2 General 11.4.2.1 The unit for compressing Live terminations and joints is a hydraulic compressor of appropriate size. 11.4.2.2 This unit is used in conjunction with 1 x 7.6m and 1 x 4.6m hydraulic hoses suitable for Live Line use, giving a total length of 12.2m. A longer hose must not be used. 11.4.2.3 If the hoses supplied do not give sufficient length from ground level, the unit can be operated from the pole platform. 11.4.2.4 The hoses are of High Voltage insulation and must be kept clean and periodically inspected for damage that may cause surface leakage. When in use it is advisable that the hose is not held in the hand or in contact with persons or clothing when the compressor head is in contact with Live conductors. 11.4.3 Cutting and Compression 11.4.3.1 The appropriate cutting head must be used with the compressor unit. 11.4.3.2 The compressor head must be fitted with the correct dies for each compression. 11.4.3.3 These heads are supported on a 10-ft. long x 1½ in. diameter epoxy glass universal stick for use in contact with Live conductors. __________________________________________________________________________________________ © SP Power Systems Limited - 47 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.4.3.4 The compressor head is relatively heavy and it is best to work with it balanced as nearly as possible to the vertical. Where horizontal work is necessary an insulated support can be used. 11.4.3.5 When cutting ACSR that has been under tension, the steel strand often springs out of place and gives a difficult conductor end. This can be overcome by fitting a Live Line tap to the conductor before cutting. This line tap should be kept in place until the conductor end is entered into the fitting. 11.4.3.6 If the strand ends are disarranged these can be repositioned usually by fitting a line tap onto the conductor, tightening it until it can just be turned on the conductor and then rotating it with the lay strands along the conductor towards the end. 11.4.4 Compression Fittings 11.4.4.1 Compression fittings have been Approved for conductor terminations and non-tension and tension type joints on copper, steel, and aluminium alloy conductors and ACSR. 11.4.4.2 Copper fittings contain an abrasive coating on the internal walls of the bore and this must not be removed to ease the installation of the fitting as it functions in the ultimate strength of the joint. 11.4.4.3 Aluminium fittings contain abrasive grease and this is essential to give the necessary adhesion of the joint. This grease must not be removed prior to compression. 11.4.5 Application of Fittings 11.4.5.1 Before a fitting is applied to weathered conductor the conductor must be thoroughly cleaned by wire brush to remove any oxide film before insertion into the fitting. 11.4.5.2 After cleaning the conductor it must be clearly marked, using the Approved tool, to indicate the depth of penetration into the fitting. 11.4.5.3 The conductor tail must be securely held in a wire holding stick and the fitting, held in another wire holding stick, offered up to it. Care must be taken at this stage not to dislodge separate strands of the conductor whilst inserting it in the fitting. __________________________________________________________________________________________ © SP Power Systems Limited - 48 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.4.5.4 When the conductor has been entered into the fitting, in the case of copper, the fitting is worked on to the conductor or where necessary, driven on by means of the hammer head attached to a universal stick until the penetration mark coincides with the end of the fitting, showing full penetration. 11.4.5.5 In the case of grease filled ACSR fittings, a polythene rope sling is fitted between the heads of the wire holding sticks and after entering the conductor into the fitting, this sling is tightened by means of the "C assist" on a universal stick. With the working of the conductor into the fitting and the pull of the sling and fitting must be driven onto the conductor until the penetration mark is reached. 11.4.5.6 The assembly is now ready for compressing. Care must be taken that the conductor does not slip out of the fitting before or during compression. A constant monitoring of the penetration mark on the conductor relative to the end of the fitting will indicate this. 11.4.5.7 The compressor head must be fitted with the proper dies for the fitting being used and shall be offered up to the fitting on a 10ft. x 1½ in. diameter universal stick. 11.4.5.8 When attaching "C" crimps to tension conductors always apply the crimp to the main line first to ensure proper seating of the conductor and insert the tap-off conductor after this has been done. This is essential to prevent damage to the tensioned conductor. __________________________________________________________________________________________ © SP Power Systems Limited - 49 PSLWM 5.2 OPSAF-12-014 Issue 4 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD _________________________________________________________________________________________ 11.5 Procedure WL1.137 - Lubricating Air Mechanisms 11.5.1 Scope of Procedure Break Isolating Switch 11.5.1.1 This Procedure covers maintenance of air break isolating switches mounted on all types of wood pole overhead lines. 11.5.1.2 This Procedure does not cover repairs to or replacement of air break isolating switches. 11.5.1.3 There is no HV Live Working Procedure for insulator cleaning. 11.5.1.4 A switch to be maintained may be mounted above or below the conductors and in the latter case may be horizontal or vertical. 11.5.1.5 Air break isolating switch maintenance can only be undertaken when the switch is initially in the closed position. Where a switch is a normally open point, switching shall be undertaken by a suitably Authorised Person to alter the network and have the switch in the closed position before commencement of the procedure. 11.5.1.6 The Authorised Person will confirm to the linesmen that the current in the conductors at the time of carrying out the procedure will not exceed the current carrying capacity of the by-pass jumpers. 11.5.2 Safety Precautions 11.5.2.1 Goggles shall be worn throughout the procedure to protect eyes from cleaning fluid, oil and grit. 11.5.2.2 Rubber gloves shall be worn when operating the switch handle. 11.5.2.3 Before any linesman climbs the switch pole, a bond shall be applied between the steelwork earth and the earth mat connections to prevent any danger from possible potential differences between them. This bond shall remain connected for the duration of the work. __________________________________________________________________________________________ © SP Power Systems Limited - 50 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.5.3 Approved Tools 11.5.3.1 The following tools are required for maintaining an air-break isolating switch. 2 - Universal sticks 1 - Set of socket spanners 1 - Ratchet wrench head 1 - Oiling attachment for universal stick 1 - Oil can for lubricating oil 1 - Oil can for freeing agent 1 - Conductor cleaning brush 1 - Mirror 1 - Pair HV rubber gloves Goggles for each member of Live Line team 1 - Short jumper 2 - Grip all clamp sticks Other tool heads for use with universal sticks may be required. 11.5.3.2 The following tools are required for installing the switch bypass jumpers 3 - 8 foot x 1½ inch holding tongs 3 - Rigid by-pass jumpers 3 - 1½ inch wire tong saddles 1 - Set of Live Line tapping equipment 11.5.4 Method 11.5.4.1 Check that the switch is locked in the closed position and that the linesman in charge has a key for the lock. 11.5.4.2 Visually check that the steelwork earth wire is continuous and that the switch handle connections to the earth mat are complete. Apply a jumper to bond the two earth systems. 11.5.4.3 Mark the pole with a red band below the switch supporting steelwork and a minimum of 0.8m below the lowest conductor. 11.5.4.4 Erect rigid by-pass jumpers 0.23m below bases of switch units leaving Live Line taps secured to rigid tubes. 11.5.4.5 Remove the red band applied in Sub-Section 11.5.4.3 __________________________________________________________________________________________ © SP Power Systems Limited - 51 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.5.4.6 Reposition red band 0.8m below the lowest rigid by-pass jumper. 11.5.4.6 Connect Live Line taps of rigid by-pass jumpers in accordance with Procedure WL1.130. 11.5.4.8 With the linesmen standing clear of the pole, the linesman in charge should unlock the switch handle and attempt to open the switch without using undue force. If the switch fails to open, a member of the team should climb the pole and apply freeing agent to the joints and connections using the oil can attachment on a universal stick. After allowing time for the freeing agent to penetrate, a further attempt should be made to open the switch. 11.5.4.9 After the switch has been successfully opened, lubricant should be applied to all joints and relevant moving parts using the appropriate attachments on a universal stick. During the application of lubricant, the switch should be operated to assist penetration. 11.5.4.10 Nuts and studs should be checked and tightened where accessible, using socket set and appropriate stick. Any contacts and metal parts that have been subject to corrosion should be cleaned using the cleaning brush attachment. 11.5.4.11 When maintenance work has been completed the switch should be operated to the closed position and locked. 11.5.4.12 Disconnect the rigid by-pass jumpers in accordance with Procedure WL1.130 leaving Live Line taps secured to rigid tubes. 11.5.4.13 Reposition the red band to mark the pole as Sub-Section 11.8.4.3 if necessary. 11.5.4.14 Remove rigid by-pass jumpers. 11.5.4.15 Remove red band from the pole. 11.5.4.16 Remove the jumper bonding the two earth systems on the pole. 11.5.4.17 If switch is a normal open point, inform Control Person that network can be restored. __________________________________________________________________________________________ © SP Power Systems Limited - 52 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.5.5 Drawings 00031074 11.5.5.1 Front view of tongs and rigid by-pass jumpers in position. 11.5.5.2 Side view of 1 phase with tong and rigid by-pass jumper in position. __________________________________________________________________________________________ © SP Power Systems Limited - 53 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 54 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6 Procedure WL1.140 - Jumper Cutting and Making Operations 11.6.1 Scope of Procedure 11.6.1.1 This Procedure sets out the general principles governing the connection and disconnection of jumpers. These are applicable when operating on jumpers in all locations and situations. 11.6.2 Approved Tools Approved tools for basic operations are: 1 set 2 sets 2 sets 1 pair 1 1 1 1 2 1 1 3 1 11.6.3 - Live Line Compression Equipment Grip-all Clamp Sticks Wire Holding Sticks Wire Cutters 10 foot x 1½ inch Universal Stick 8 foot x 1½ inch Universal Stick Rotary Prong Head Fuse Puller Head Wire Cleaning Brushes Flexible Wrench Head if required Bolt Wrench Head if required "Make and Break" Tools Approved Scaffolding Limiting Factors on Jumper Connection and Disconnection When connecting or disconnecting jumpers by HV Live Working methods, the following limited factors must be considered. 11.6.3.1 Prospective load currents to be broken may be measured with an Approved HV ammeter (either installed in a substation or fitted to a Universal Hot Stick) or estimated from transformer full-load capacity. Load current must only be made or broken using either: an Approved portable air-break switch or the appropriate Approved “make and break” tools. The maximum load which can be made or broken using a “make or break” tool without arc-suppression is 50A. Where an Approved “make or break” tool with arc-suppression is used, a maximum load of 185A may be broken. If necessary, load may be reduced by removing LV fuses, where practicable. In order to reduce the possibility of ferroresonance, LV fuses should only be removed from transformers that will not become ferroresonant, as described in Sub-Section 6.2 of this Section. __________________________________________________________________________________________ © SP Power Systems Limited - 55 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6.3.2 Jumper making and breaking must not be performed where this will result in making or interrupting load exchange between Primary substations. 11.6.3.3 Magnetising current equivalent to 200kVA of connected transformer capacity may be disconnected on Live Line taps with the use of a splash plate. Above this, and to a maximum of 1000kVA of connected transformer capacity, a “make and break” tool must be used. 11.6.3.4 Capacitance currents equivalent to the following cable lengths may be disconnected or connected on Live Line taps with the use of a splash plate. Above this, a "make and break" took must be used. 1200 metres 0.06 in² or 1000 metres 0.1 in² (70mm²) or 300 metres 0.15 in² (95mm²) or 200 metres 0.2 in² 11.6.3.5 Where making or breaking jumpers will affect a transformer that is within 700m of an HV cable, there is a possibility that a ferroresonant circuit will be set up. In this instance, the jumpers must only be connected or disconnected in conjunction with either: an Approved portable air-break switch or Approved “make and break” tools. 11.6.4 Precautions to be Observed When operating on jumpers work must be carried out from the pole or Approved scaffold or platform. In all cases, the Safety Distances must be maintained during work. Where by-pass jumpers are used as part of the operation to connect or disconnect jumpers, Safety Distance must be calculated from the point to which the by-pass jumper would swing if one were inadvertently released. 11.6.4.1 When making or breaking jumpers on a network section supplied from more than one direction, protection must be checked and where necessary, sensitive earth fault protection rendered inoperative to prevent unwanted operation. 11.6.4.2 When connecting or disconnecting transformers, pole boxes or overhead lines, all metal at points of disconnection must be considered as Live until proved not Live by use of an Approved voltage detector. __________________________________________________________________________________________ © SP Power Systems Limited - 56 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6.4.3 Where jumpers are under tension, they must be adequately secured prior to cutting to ensure that no phase/phase or phase/earth contact is made by jumpers 'springing' on release. 11.6.4.4 Where jumpers are to be re-made at some future time, the jumper conductor must first be thoroughly cleaned in the area to be cut, to facilitate re-making with a compression joint. A stub of sufficient length (not less than 100mm) must be left to allow compression. 11.6.4.5 Bi-metallic connections must not be made onto line conductors that are in tension. If no suitable conductor stubs are available, 'L' stubs must be connected to the main line to facilitate jumper connection. 11.6.4.6 Jumper connections must not be Live Line tapped onto line conductors. If a Live Line tapped jumper is required, solid rod bails must be fitted onto the line conductors and the jumpers connected to the bails. Where jumpers are connected to tension conductors by line taps, they should be replaced. This is particularly important where jumpers are to carry large loads or through fault currents. 11.6.4.7 When connecting jumpers on to a main line, the initial connection should be made via a temporary jumper with a Live Line tap in order to minimise arcing. Where the temporary jumper is made between a tension and a non-tension conductor, it is preferable to connect to the tension conductor first. 11.6.4.8 Jumpers over 1.5 metres in length must not be connected unless they can be permanently supported at some point along their length. 11.6.5 Points of Isolation 11.6.5.1 This procedure can be utilised to cut and remove dropper jumpers to create points of Isolation prior to work proceeding on the Isolated section under Permit for Work conditions. 11.6.5.2 On specific items of Apparatus where clearly defined conditions can be complied with, work or testing may be carried out on Apparatus without the issue of a Safety Document. __________________________________________________________________________________________ © SP Power Systems Limited - 57 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6.5.2.1 The specific items of Apparatus are: Pole mounted auto reclose circuit breakers Pole mounted auto sectionalisers Air-break isolating switches Pole mounted HV fuse units Pole mounted transformers 11.6.5.2.2 The conditions to be complied with are as follows: (a) The disconnection shall provide Safety Distance from Live HV conductors while working or testing on or lifting and lowering the Apparatus. (b) Work or testing on or lifting and lowering of Apparatus shall be carried out without taking access to the area defined as the Upper Portion of the pole in PSMSP 1.4 (c) The HV Points of Isolation shall be on the same support as the Apparatus to be worked on or tested. (d) The work or testing on the Isolated Apparatus shall be carried out by the same Authorised Persons who created the HV Points of Isolation. (e) Before work or testing commences on the Isolated Apparatus, it shall be proved not Live and discharged to Earth. Where it is practical to do so, Drain Earths shall be attached to the Apparatus while work or testing is being carried out. (f) Immediately before work or testing commences on the Isolated Apparatus unearthed steelwork associated with the Apparatus shall be proven not Live using an Approved crossarm proving device. (g) Before work or testing commences on the Isolated Apparatus a red marker band shall be fitted to define the Safety Distance from Live conductors. (h) Apparatus shall be lifted and lowered from the pole using Approved equipment attached to the pole outwith Safety Distances and such that Safety Distances will not be infringed during lifting and lowering operations. __________________________________________________________________________________________ © SP Power Systems Limited - 58 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ (i) The lifting equipment shall be attached to the pole by an Approved method that may include the use of a choking sling or eyebolt. The S.W.L. of all lifting equipment must be appropriate for the load. Note An A.B. Chance transformer gin can be utilised for this operation. The transformer gin is rated as an HV Live Working tool and can therefore be mounted on the pole with the section of the gin above the red mark within the Safety Distance. Once the gin is in position HV Live Working rope blocks can be attached to the gin using an HV Hot Stick. The gin should be mounted with the lifting eye as low as practical and in every case below the conductors. The application and use of the HV Live Working rope blocks should avoid contact with the conductors. If direct contact is anticipated a link stick should be inserted. The HV Live Working transformer gin is designed for vertical loading. The pull rope must be threaded through a pulley block at the base of the structure. The A.B. Chance range of gins have a 0.9 tonne maximum rating, which with suitably rated rope blocks, means that 0.75 tonne maximum load can be lifted. A swivel hook must be used in the eye of the gin. The model C400-440 has a swivel top to allow appropriate positioning of lifting eye. The top is not intended to swivel under load. 11.6.5.2.3 For pole mounted transformers, in addition to the conditions set out in conditions (a) to (h) above, the following additional conditions shall be complied with: (k) Steps shall be taken to prevent any possible backfeed by removing the LV fuses or disconnecting LV leads. Agreement on this precaution shall have been made with the Senior Authorised Person. (l) Precaution shall be taken to avoid Danger from Live LV conductors or cables on the pole. These precautions may include the use of Approved shrouding. __________________________________________________________________________________________ © SP Power Systems Limited - 59 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6.6 Methods of Jumper Connection Jumpers may be connected between supply line and Apparatus in two ways: (a) by fitting the jumper between a short 'L' shaped stub off the supply line and the Apparatus. (b) by fitting the jumper directly between supply line and the Apparatus. Short 'L' stubs will normally be the result of earlier jumper-cutting operations. 11.6.6.1 Connections to the main line may be by straight tension splices where stubs are available or by 'C' type crimps (or preferably bail connectors). In either case, the requisite jumper length is measured accurately and all conductors thoroughly cleaned at points where crimping is to be made. Elbow bail connectors may then be compressed onto jumper ends as necessary, and the jumpers formed to approximate shape. 11.6.6.2 Commencing with any centre phase, a temporary by-pass jumper is fitted, firstly to the supply end, then to the Apparatus to be connected. The temporary jumper is to be fitted clear of points of permanent connection. 11.6.6.3 The permanent jumper may now be compressed, starting at the supply end. During connection, the jumper is held in a wire holding stick, and the jumper ends guided into compression joints, as necessary. 11.6.6.4 The temporary by-pass jumper may then be removed and the procedure repeated with the remaining phases. 11.6.7 Methods of Jumper Disconnection Before removing a jumper, it must firstly be by-passed with a temporary jumper. Live-line tapped clear of the working area to make a parallel connection with the permanent jumper. 11.6.7.1 When cutting jumpers, outer phases must be cut first, and any centre phase last. __________________________________________________________________________________________ © SP Power Systems Limited - 60 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.6.7.2 The jumper to be removed must be secured in a wire-holding stick, and thoroughly cleaned at points where it is to be cut. Cutting must be done firstly at the Apparatus, and secondly at the new supply end to allow the jumper piece to be removed. Throughout the operation, the jumper must be controlled to avoid infringing phase/phase or phase/earth clearances. 11.6.7.3 Once cut, the jumper is removed and the temporary by-pass jumper removed. The procedure may then be repeated for other phases. 11.6.7.4 Where it is intended that the same jumper pieces be re-used, they must be marked at either end to ensure their correct replacement in respective phases. 11.6.7.5 Where jumper stubs are left connected to lines by mechanical connectors, the opportunity should be taken to complete the work with compression fittings. 11.6.8 Drawings Drawing numbers 00031075 to 00031080 illustrate methods to be used and typical situations where connection and disconnection of jumpers may be carried out. __________________________________________________________________________________________ © SP Power Systems Limited - 61 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 62 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 63 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 64 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 65 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 66 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 67 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.7 Procedure WL1.141 - Replacement of Intermediate Pole, Crossarm or Insulators - Auxiliary Crossarm Method 11.7.1 Scope of Procedure This Procedure can be used on the Distribution System to: (a) Replace poles - in which case the work is carried out from the new pole. (b) Change crossarms or insulators The Procedure is Approved for use only on 11kV horizontal formation lines supporting 32mm² copper hard-drawn stranded conductors or smaller and 50mm² ACSR or smaller. Conductors can be raised by this method on straight line intermediate poles supporting wind spans up to the maximum design values for the line specification provided there is minimal downpull at the pole position. The Auxiliary Crossarm which has a rated voltage of 15kV in normal dry conditions can be upgraded to 34kV working by the addition of insulators to the fork wire holders. To ensure that the Auxiliary Crossarm is capable of withstanding the 11kV System voltage in wet conditions it is ScottishPower policy that the optional insulators shall always be fitted. 11.7.2 Approved Tools 1 - 9 foot Dual Auxiliary Crossarm (complete with fork wireholders and insulators) 1 - 6 foot x 2½ inch Wire Tong 2 - 8 foot x 2 inch Wire Tongs 2 - 2½ inch Wire Tong Saddles with extensions 1 - 2½ inch Wire Tong Pole Clevis 1 - Set of rope blocks (Live Line) 2 - Rope snubbing brackets 2 - Tie sticks 2 - Insulated Wire cutters 1 - Grip all clamp stick 1 - Crossarm proving device 4 - Bars for ground anchors Steelwork shrouding Pole shrouding __________________________________________________________________________________________ © SP Power Systems Limited - 68 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.7.3 Replacement of Intermediate Pole 11.7.3.1 Erection of New Pole 11.7.3.1.1 Shroud the top of the new pole and erect it close to the old pole but not closer than 0.4m. Keep a minimum clearance of 0.15m from the nearest Live Conductor. 11.7.3.2 Working on the New Pole Step 1 Mark the new pole with a red band 0.8m from where the lowest conductor passes the pole. Step 2 Shroud the crossarm of the old pole. Step 3 Partially unbind the conductors. Step 4 Fit a saddle on the new pole centred on the opposite side of the pole from where the crossarm will be fitted and immediately below the red marker band. Step 5 Fit a second saddle on the same side of the pole 2.4m below the first saddle. Step 6 Fit a snubbing bracket 0.4m below the top saddle. Step 7 Fit a second snubbing bracket 1m from ground level Step 8 Set the position of the fork wireholders on the auxiliary crossarm to coincide with the conductor spacing. Step 9 Lift the auxiliary crossarm into position against the pole. Clamp to both saddles. This can be done using a rope from the top of the auxiliary crossarm over the top snubbing bracket. Step 10 Attach rope blocks between top snubbing bracket and bottom of the auxiliary crossarm. Step 11 Using a tie stick to guide the conductors and working between the wing nuts on the saddles and the rope blocks raise the auxiliary crossarm until the conductors rest in the fork wireholders. Check that the safety latch trips and locks the conductors into the wireholders. __________________________________________________________________________________________ © SP Power Systems Limited - 69 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ Step 12 Lock off saddles and tie off rope blocks. Step 13 Complete the unbinding of the conductors. Step 14 Raise the auxiliary crossarm and conductors by working between the wing nuts on the saddles and the rope blocks to provide safe working clearance at the pole top. Step 15 Lock off saddles and tie off rope blocks The pole top is now clear and the red band can be removed. Step 16 Remove the dressing from the old pole and dress the new pole. Step 17 Shroud the crossarm of the new pole in preparation for replacing conductors. At this stage the old pole should be felled. Step 18 Replace the red band 0.8m below the lowest conductor. Step 19 Lower the auxiliary crossarm and conductors by working between wing nuts on the saddles and the rope blocks until the conductors rest on the insulators. Step 20 Lock off saddles and tie off rope blocks. Step 21 Apply helical ties to bind the conductors to the insulators as described in Procedure WL1.132. Step 22 Open the latches on the fork wire holders and lower the auxiliary crossarm clear of the conductors. Step 23 Drop the auxiliary crossarm from the pole. This can be done with a rope from the top of the auxiliary crossarm over the top snubbing bracket. Step 24 Remove all Apparatus from pole. Ensure that all pieces of debris have been picked up. Check all tools and equipment, clean with a dry rag and stow away. __________________________________________________________________________________________ © SP Power Systems Limited - 70 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ 11.7.4 Replacement of Crossarm or Insulator If crossarm or insulator change only is required the work will be done from the existing pole in which case mark the pole with a red band 0.8m below the lowest conductor. The procedure as Step 1 to Step 24 should be carried out omitting old pole felling and with Step 16 being modified to replace the crossarm or insulator as required after removing the red band. __________________________________________________________________________________________ © SP Power Systems Limited - 71 PSLWM 5.2 LIVE WORKING MANUAL WORK ON OVERHEAD LINES THE HOT STICK METHOD OPSAF-12-014 Issue 4 _________________________________________________________________________________________ __________________________________________________________________________________________ © SP Power Systems Limited - 72 PSLWM 5.2