Our energy working for you. TM Power topic #6044 | Technical information from Cummins Power Generation Selective coordination standards and design challenges ■ White Paper By Rich Scroggins, Technical Advisor, Sales Application Engineering, Cummins Power Systems Selective coordination is one of the most widely debated and discussed subjects in the electrical engineering community. There is no consensus on what constitutes an appropriately coordinated system. Two of the most commonly applied standards — NFPA 70 (National Electrical Code [NEC]) and NFPA 99 (Health Care Facilities Code) — give seemingly contradictory definitions. With that in mind, let’s look at the tradeoffs involved with designing a coordinated system and outline the technical and regulatory case for applying the NFPA 99 definition of selective coordination. The NEC defines selective coordination as: “Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the choice of overcurrent protective devices and their ratings or settings.” In a selectively coordinated system, a fault is cleared by the protective device nearest upstream from that fault and does not result in unnecessary power loss to other downstream loads. Selective coordination is typically achieved by using an Overcurrent Protective Device (OCPD) with an instantaneous trip setting at the bottom of the distribution and progressively longer time delays higher in the system; in the event of a fault only the OCPD closest to that fault will trip. Without Selective Coordination OPENS OPENS NOT AFFECTED UNNECESSARY POWER LOSS With Selective Coordination Fault NOT AFFECTED Fault Figure 1: Faults with and without selective coordination Designing a selectively coordinated system presents a challenge to engineers; safety and equipment protection, as well as fault isolation, need to be addressed. The effect of using time delays on OCPDs is to expose downstream equipment and cable to fault current for a long period of time. When timedelayed trip settings are used, it is critical that the entire system must be designed for the same minimum level of fault protection. This requirement is mandated by NEC 110-10: “The overcurrent protective devices, the total impedance, the component short circuit ratings, and other characteristics of the circuit to be protected shall be selected and coordinated to permit the circuit protective device used to clear a fault to do so without extensive damage to the electrical components of the circuit.” NEC 110-10 requires that cable and equipment be sized to handle the available fault current for the duration of the OCPD time delay. Table 1 was published by the Insulated Cable Engineers Association and provides an illustration of how an extended fault clearing time delay will require the use of larger cable in an application. 02 | Power Topic #6044 From Table 1 we can see that a circuit fed from a source with 40,000 amps of available fault current should use 3/0 cable if the OCPD will clear the fault in 50 msec (3 cycles at 60 Hz). However, if the OCPD has a 500 msec time delay (30 cycles), 500 kcmil cable would be required to safely handle the fault. Oversizing the cable not only increases the cost of the system, but also results in a higher level of arc flash incident energy at downstream equipment, as the cable resistance is reduced and allows more current to pass through. Table 1: Allowable short circuit currents for insulated copper conductors Table 2 — derived from NFPA 70E, Table H.4(a) — illustrates that arc flash energy is a function of both fault clearing time and the available fault current. Increasing these parameters increases the arc flash incident energy and may require a higher level of PPE to operate and maintain equipment. Mandating coordination for all levels of fault current is at odds with the stated purpose of the NEC, which is “the practical safeguarding of persons and property from hazards arising from the use of electricity” (NEC 90.1(A)) Fault Clearing Time (sec) 0.05 0.1 0.2 0.33 0.5 Max 3 Phase Bolted Fault Current at 480Vac 2 8 cal/cm PPE 68 kA 32 kA 15 kA 8 kA Not Recommended 2 40 cal/cm PPE 200 kA 183 kA 86 kA 50 kA 32 kA Table 2: Arc flash energy is a function of both fault clearing time and the available fault current Selective Coordination Definitions The NFPA 70 definition of selective coordination refers to “the full range of available overcurrent, from overload to the maximum available fault current, and for the full range of overcurrent protective device opening times…” It is for this reason that NFPA 99 defines selective coordination as achieved if it is demonstrated for all time durations greater than 0.1 seconds. The specific text (section 6.4.1.2.1) says “Overcurrent protective devices serving the essential electrical system shall selectively coordinate for the period of time that a fault’s duration exceeds 0.1 second.” In Annex A NFPA 99 clearly states the justification for this requirement (A.6.4.2.1.2) “It is important that the various overcurrent devices be coordinated, as far as practicable, to isolate faulted circuits and to protect against cascading operation on short circuit faults. In many cases, however, full coordination could compromise safety and system reliability.” Requiring coordination only for time durations greater than 0.1 second gives the engineer the flexibility to use instantaneous trip settings for high levels of fault current and use time-delayed trips on the lower level fault currents. This way the system will be protected for all levels of fault current up to the theoretical maximum and will be coordinated for the likelier event of arcing ground faults and overload conditions. Figure 2 illustrates a system that is coordinated based on the NFPA 99 definition. The trip curves for the two breakers in this example overlap in the instantaneous region; however, there is no overlap for longer time durations, so this system would meet the NFPA 99 selective coordination requirements. Figure 2: System showing overlapped breakers based on the NFPA 99 definition of selective coordination There appears to be a conflict between NFPA 99 and NFPA 70 on whether a system needs to be coordinated for all levels of fault current and fault clearing times or only for the duration of a fault that extends beyond 0.1 second. The NFPA has developed a policy for resolving such conflicts. They determined that NFPA 99 is responsible for the performance of healthcare electrical systems and NFPA 70 is responsible for the installation of these systems. NFPA 70 must defer to NFPA 99 on performance issues. Clearly, selective coordination describes the performance of the system, so NFPA 99, the performance standard, is the appropriate standard to apply. NFPA 110 (Standard for Emergency and Standby Power Systems) has language similar to NFPA 99 regarding selective coordination. Annex A (A.6.5.1) states: “It is important that the various overcurrent devices be coordinated, as far as practicable, to isolate faulted circuits and to protect against cascading operation on short circuit faults. In many systems, however, full coordination is not practicable without using equipment that could be prohibitively costly or undesirable for other reasons.” NFPA 110 applies to all emergency and standby power systems, and the language gives the engineer discretion in determining the level of coordination. The engineer may cite the NFPA 99 standard of requiring coordination only in excess of 0.1 second as a best practice. NFPA 70 Articles 700 (Emergency Systems), 701 (Legally Required Standby Systems) and 708 (Critical Operations Power Systems) all state: “Selective coordination shall be selected by a licensed professional engineer or other qualified persons engaged primarily in the design, installation, 03 | Power Topic #6044 Maximum available fault current typically refers to the current that would theoretically flow in the event of a three phase bolted fault, although a three phase bolted fault rarely occurs in practice. Single phase arcing ground faults are much more common and typically result in lower current levels for which delayed interruption is more manageable. Designing a system so that it will coordinate in the unlikely event of a three phase bolted fault at the theoretical maximum level of fault current results in a system that will allow higher levels of fault current to flow in the more likely event of a single phase fault. This could create higher levels of arc flash incident energy at downstream equipment and compromise system safety. About the author Rich Scroggins is a Technical Advisor in the Application Engineering group at Cummins Power Generation. Rich has been with Cummins for 20 years in a variety of engineering and product management roles. Rich has led product development and application work with transfer switches, switchgear controls and networking and remote monitoring products and has developed and conducted seminars and sales and service training internationally on several products. Rich received his bachelors degree in electrical engineering from the University of Minnesota and an MBA from the University of St. Thomas. or maintenance of electrical systems. The selection shall be documented and made available to those authorized to design, install, inspect, maintain, and operate the system.” The language in these standards has been interpreted as allowing a licensed PE discretion over system performance. The PE is allowed to use engineering judgment in determining that selectively coordinating the system only for faults beyond 0.1 second and allowing OCPDs to clear instantaneously in the event of higher levels of fault current are the best ways to balance system reliability and performance considerations with the NEC purposes of safety and fire prevention. Summary Designing a selectively coordinated system presents challenges. The engineer needs to balance the risks of temporarily cutting power to the system against safety risks and the risk of permanent system damage due to the increased level of arc flash energy. Requiring coordination only for time durations greater than 0.1 second gives the engineer the flexibility to use instantaneous trip settings for very high levels of fault current and use time-delayed trips on the lower level fault currents, which are more likely to occur. power.cummins.com ©2015 Cummins Power Generation Inc. All rights reserved. Cummins Power Generation and Cummins are registered trademarks of Cummins Inc. “Our energy working for you.” is a trademark of Cummins Power Generation. GLPT-6044-EN (01/15) 04 | Power Topic #5590 A requirement for “total” selective coordination means that OCPDs must be coordinated for all faults, including a three-phase bolted short circuit, a worst case scenario and one not commonly seen in real applications. Delaying interruption of such high levels of fault current results in exposing downstream equipment and cables to excessively high levels of fault energy and could increase the risk of arc flash.