Hydro One’s LDC DG
Connection Review
•
Toll Free Dial In Number: 1-855-353-9183
•
Toronto Dial In Number: 416-623-0333
•
Participant Pass Code: 41364#
August 16, 2012
1
Agenda for Today
1. Overview of Hydro One’s LDC DG
approval process using examples
2. Review of Tx Capacity limitations
3. Review of DAT coordination with LDC’s
4. Review of the DG connection
authorization process
5. Q & A Session
2
LDC Feeder Supply Types
LDC owned
•
•
•
•
Owned by the LDC up to the TS
Billed by the IESO
Listed in TCA Schedule A
Monitoring for > 500 kW
Shared
•
•
•
•
Hydro One owned to LDC boundary
Supplies other H1 customers
Listed in DCA Schedule D
Monitoring for > 250 kW
Express
•
•
•
•
Hydro One owns a section from the TS (usually outside LDC)
Only serves one LDC (no other load)
Listed in DCA Schedule D
Monitoring for > 500 kW
3
LDC CIA Example #1
• 200 kW Small FIT (CAE)
• Solar (Inverter based)
• Connecting to an LDC owned feeder
• No H1 DAT required
4
Tx Constraints and Upgrades
Presented by: Bing Young, Director of System Development
5
Transmission Constraints & Upgrades
• Transmission Constraints Overview
1)
Transformer station constraints
2)
115kV short circuit constrained areas
3)
Other upstream transmission constraints
a.
Local limitations
b.
Area limitations
• Update on Transformer Station upgrades
• Update on other transmission upgrades
6
Threshold CIA Option
Presented by: Stan Dafoe, Senior Account Executive
7
Threshold CIA Option
At Hydro One discretion:
• Allocates1 MW (min) of capacity per TS bus
• Available for LDC owned & express feeders
• One Small FIT project required for TCIA
• LDC may connect one or more inverter based Small FIT’s
• 6 month, renewable term
• 2 MW capacity must remain at the TS
• Connection authorization required for each project
8
LDC CIA Example #1
• 200 kW Small FIT (CAE)
• Solar (Inverter based)
• Connecting to an LDC owned feeder
• No H1 DAT required
• Qualifies for Threshold CIA (LDC owned
feeder)
9
Threshold CIA (TCIA) Process
• LDC applies for TCIA for an entire TS bus
• No Charge for TCIA
• LDC provides P. Eng. stamped LDC Form B
• LDC allocated 1 MW+ on one TS bus
• No monitoring required (<500 kW, LDC
feeder)
• Coordinate with OGCC as project connects
• Sign Letter of Equivalency post connection
10
TCIA Report
Connection Authorization
Presented by: Stan Dafoe, Senior Account Executive
12
Connection Authorization for
TCIA DG’s
Pre-connection (6 days in advance)
• Contact your OGCC outage planner (per
operating schedule A or D)
• Provide “draft” (unsigned) Letter of
Equivalency (LoE)
• Provide Single Line Diagram (SLD) &
Nomenclature
13
Connection Authorization for
TCIA DG’s
Post connection
• LDC submits signed LoE after commissioning
• LOE signed by the P. Eng. or LDC officer
• DG info captured in OGCC NMS system
• Operating schedule A or D updated
14
Date:
Letter of Equivalency - Confirmation of Verification Evidence Report (COVER)
[Insert name of LDC] acknowledges that the embedded connection of [Insert H1 CIA Project Reference] does not materially
adversely affect the safety, reliability and efficiency of the distribution system and meets the technical requirements specified in
Appendix F.2 of the Distribution System Code, in accordance with section 6.2.25 of the Distribution System Code.
[Insert name of LDC] verifies that the embedded connection of [Insert H1 CIA Project Reference] has been properly commissioned
in accordance with Appendix F.1 of the Distribution System Code.
Existing feeder protections are confirmed to be suitable within the stated terms of the CIA.
Please reference the project data below for your operational schedules.
Name of Facility (Generator)
OPA Contract Number (if applicable)
Generator Site LDC Operating Designation
Proposed Energization Date
Supply TS
Supply Feeder(s) Designation
Generator Site Legal Address
Instructions: The letter is to be provided on LDC letterhead by a LDC employee or agent acting on behalf of the LDC. The
equivalency letter needs to be signed by a Professional Engineer registered in the Province of Ontario or a LDC Officer.
• Please file with the Business Call Centre at DXGENERATIONCONNECTIONS@hydroone.com along with a copy to the
applicable control authority Outage Planner identified in your Connection Agreement Operating Schedule A/D. Unless otherwise
specified for “M” designated feeders, this will be the Network Operating Division, for “F” designated feeders, this will be the
appropriate provincial Lines Zone Scheduler. Check your Schedule for the appropriate contact numbers and email addresses.
• For projects over 250 KW, an “as constructed’ single line drawing of the generators facility should be included with this letter.
Signature
Name
PEO ID (if applicable)
Renewal/Expiry of TCIA
• Reminder letter sent at 5 months
• LDC can renew TCIA or let it expire
• Submit updated original application to renew -
including project listing
• Or on expiry provide the list of DG’s
connecting
16
Individual CIA Option
Presented by: Stan Dafoe, Senior Account Executive
17
LDC Individual CIA Example
• 400 kW Small FIT (CAE)
• Solar (Inverter based)
• Connecting to Hydro One shared feeder
• LDC is embedded in Hydro One
• Hydro One DAT is required (shared feeder)
• Monitoring is required (>250 kW, shared
feeder)
18
Hydro One’s Approach to the
Distribution Availability Test
(DAT)
Presented by: Martin Huneault, Coordinator for Generation Connections
Presented by: Alexander Hamlyn, Engineer with Generation Connections
All DAT request will come through the OPA Portal (FAME)
20
Communication between Hydro One and Upstream LDCs
Example 1: Hydro One Application to a Upstream LDC
(Shared Feeder)
TS
Hydro One
Upstream LDC
DG
•~
•
DG is listed in Hydro One territory (FAME)
•
Hydro One will communicates with upstream LDC to request completion of a DAT
– Hydro One to send letter to Upstream LDC (CC. Account Executive)
•
Upstream LDC performs a DAT and communicates result to Hydro One
•
Hydro One uploads result to FAME
Communication between Downstream LDC and Upstream (Hydro One)
Example 2: Downstream LDC Application to Hydro One
(Shared Feeder)
TS
Hydro One
Downstream LDC
DG
•~
•
DG is listed in the Downstream LDC’s Territory in FAME
•
Downstream LDC communicates with Hydro One to request completion of a DAT
– Downstream LDC to send letter to Hydro One
•
Hydro One performs a DAT and communicates result to Downstream LDC
•
Downstream LDC uploads result to FAME
Communication between Downstream LDC and Upstream (Hydro One)
Example 3: Downstream LDC Application to Hydro One
(Express Feeder)
TS
Downstream LDC
DG
•
DG is listed in the Downstream LDC’s Territory in FAME
•
Downstream LDC communicates with Hydro One.
–
•
Downstream LDC to send letter to Hydro One
Hydro One will assess our portion of the feeder and relay that information to the
Downstream LDC
•
•~
Downstream LDC uploads result to FAME
Contact information for all DAT requests for Hydro One:
gcdcoordinator@hydroone.com
Individual CIA Application
Presented by: Stan Dafoe, Senior Account Executive
25
LDC Individual CIA Process
• Specific to only ONE DG project
• $3000 CIA fee for Small FIT (CAE)
• LDC submits individual CIA application form
• LDC submits P. Eng. stamped Form B & payment
• May incur project costs (Class C estimate)
• Monitoring required if shared feeder >250 kW
• LOE & Teleprotection Verification Report (TVR)
26
CIA Report
Connection Cost Agreement
(CCA)
• Required 6 month’s from CIA sent date (DSC)
• LDC must apply to the BCC for a CCA
• Full payment for estimated costs required at
time of execution
• Hydro One Project Manager (PM) assigned
• PM initiates kick-off meeting and Hydro One
connection process
28
Connection Cost Recovery
Agreement (CCRA)
• For LDC owned feeders (Tx connected)
• LDC should apply for CCRA
• Payment for estimated costs required on
execution
• Negotiated by AE
• PM initiates kick-off meeting and Hydro One
connection requirements
29
Monitored Connection Process
• PM administers:
 Single Line Diagram (SLD)
 Nomenclature
 Letter of Equivalency (LoE)
 Teleprotection Verification Report (TVR)
 Data captured in OGCC NMS system
 Operating Schedule A or D updated
30
LDC DG Connections – Key
Points
• Check Capacity (OPA website/Restricted
Stations/DAT)
• Consider a Threshold CIA for LDC & Express
feeders
• DAT is required for embedded feeders
• Contact the OGCC before connecting
• A Letter of Equivalency is required for all LDC
DG connections
• A TVR report is required for monitored projects
32
Thank You
Please stay in touch with your Account Executive
and monitor www.HydroOne.com for future
developments.