10b. National Storage Projects In Portugal Ricardo

advertisement
Storage Projects in EDP Portugal
Grid + Storage Workshop, Madrid
15th February of 2016
Agenda
1.
2.
3.
4.
5.
6.
7.
Project Overview
Main Functions
System Dimensioning
Location
Interactions with other projects
Main Project Constraints
Project’s Future
2
Project Overview / Technical Characteristics
•
•
•
•
•
Located in Évora - UNESCO World Heritage Site
Commissioning Date - December of 2015
Lithium Ion Batteries- (Siemens/LG)
Power / Energy ratings - 493 kW/ 196 kWh
Flexible and Removable
• 15 or 30 kV
• Installed in Évora University campus.
• Weighting aprox. 30 tons
• Life Cycle:
• 10 years
• 3600 full cycles
• Efficiency
• Around 92%
15 kV
15 kV
30 kV
30 kV
15/30 kV
15 kV
3
Storage Container 3D View
Storage Container 3D View
Storage Container 3D View
Storage Container Real View
7
Project Location and surrounding environment
Located at a rural area, within an university campus
Impacto nas perdas e no perfil de tensão em regime
permanente
8
Grid Connection
9
Project Proposed Benefits
System dimensioning according to load diagram profile
Annual peak load
Energy Quality – Long and
short term interruptions
11
System dimensioning according to load diagram profile
Daily Profiles:
Correlation between power and shortages:
12
System dimensioning – Batteries degradation
•
•
•
Depf of Discharge (DoD) – 80%
State of Charge (SoC) – 50%
End Of Life (EoL) – 80%
13
Interaction with other projects - SENSIBLE
Sensible Scope - Demonstration of distributed energy storage
and energy management
•
Demonstrate distributed energy storage (thermal, electro-chemical
and electro-mechanical) and energy management in grids,
communities and buildings
Highlights
•
•
•
•
•
Led by Siemens Corporate Technology A.G.
Overall budget of 15,4 M€ (EDP secured 2,2 M€ of a total of 11,8M€)
EDP Labelec / N.E.W. R&D leads demonstration WP
EDP’s works involves 7 FTEs (Labelec/NEW – 5; EDPD – 2)
42 months duration
Three Demonstrators
•
•
•
Évora (focus on rural / semi-urban grids-DSO)
Nottingham (focus on urban community energy management)
Nuremberg (focus on building energy management)
EDP Objectives
•
•
•
•
Demonstrate concrete applications of distributed energy storage and energy management in the distribution grid creating
value for the distribution grid operator and enabling innovative business models and competitiveness / efficiency on the retail
side
Understand how EDP’s Smart Grid concept should evolve in order to facilitate referred applications
Develop business cases of the different distributed energy management and energy storage applications in order to determine
the optimal mix of applications in different scenarios (different grid contexts, penetration of distributed generation, etc.)
Understand what regulatory framework and policy developments should be promoted
14
SENSIBLE Use Cases
UC 1 - OPTIMIZING THE OPERATION OF STORAGE DEVICES IN THE MV NETWORK
The main goal is to manage MV distributed storage devices in order to solve technical problems at the MV network level (e.g.
degradation of voltage profiles, losses). The storage devices are assumed to have two objectives: (a) reserve capacity to support
continuity of service of an installation (or building) and (b) the residual capacity is used for grid support.
Grid operation
UC 2 - OPTIMIZING THE OPERATION OF STORAGE DEVICES IN THE LV NETWORK
The main goal is to manage local distributed storage devices in order to solve technical problems in the LV grid (namely related to
voltage issues) and minimize technical losses. The storage devices are to be coordinated with renewable generation at the LV level as
well as with demand side management schemes, considering residential storage and controllable loads.
UC 3 - ISLANDING OPERATION OF LOW VOLTAGE NETWORKS
The main goal is to enable the operation of LV networks in islanding mode, ensuring the secure transition to islanding operation and
the system stability, by providing adequate frequency and voltage regulation mechanisms.
UC 4 - MICROGRID EMERGENCY BALANCE
During islanding operation, the unbalance between LV generation and load will have to be minimized in order to avoid the
system collapse. The main objectives of this module are i) Minimize energy not supplied and time of service interruption; ii)
Ensure that the MG has sufficient capacity to ensure frequency regulation following islanding; iii) Maintain frequency
Customer
excursions within admissible limits.
UC 5 - FLEXIBILITY AND DSM IN MARKET PARTICIPATION
The scope is about LV customer flexibility market participation (wholesale and retail) and also regarding grid assess
management in case of grid operation optimization regarding investment deferral.
15
Extended Islanding
Added objectives:
 Maximizing continuity of service: Maximize the time the MV grid can operate in islanded mode
 Integrated management: Coordinated operation of storage units connected both at MV and LV levels; LV Grid supporting MV Grid in case of
severe voltage sags or in case of MV overhead line trip
 Quality-of-service: Ensure that voltage and current (THD) are maintained within limits
 Grid services: Ensure adequate reactive power dispatch
 Transient coordination between different storage systems at different levels: Ensuring a secure islanding transient
In case of contigency LV grid will
contribute with P and Q
Proposed by EDP
Distribuição
under MV
Storage project
LV management-LV tool
MV management-MV tool
Integrated management MV/LV – NEW tool
16
Legal and
Regulatory
• Secondary substation adaptation for storage test and commissioning
Other
Constraints
• Safety issues regarding the use of high power batteries
Technical
Main Project Constraints
• Storage Licensing with specific Island Mode operation
• LV protection systems compliance with regulation requirements
• System adaptation for all required functions (PQ, Vf, Hybrid mode)
• Corporate systems adaptation for the project (SCADA, GIS…)
• Knowledge retention and transfer.
• Training on system operation and maintenance.
17
Future Developments
EDP Distribuição currently exploring new possibilities, besides the initial scope of
the project, namely:
1.
2.
3.
4.
5.
6.
7.
8.
9.
Business models for the use of storage in flexibility and ancillary services.
Lifecycle optimization of the use of storage, minimizing power losses and
battery degradation – Energy Efficiency.
Assessment of renewables integration benefits.
Interaction and coordination with other projects or new storage projects
Continued cooperation with universities and R&D organizations.
Further exploring legal and regulatory issues.
Understanding storage impact for network planning.
Exploring storage use to promote grid energy efficiency.
Development of algorithms for authomatic centralized control.
18
The End
Thank You
19
SENSIBLE Overview
WP1 - Requirements
Define,
develop
• Define demonstrators
requirements and usecases definitions
WP2 – Storage integration and
improvements
• Overview on storage technologies
and improvements in order to
enable SENSIBLE requirements
WP3 – Tools for energy
management and grid operation
• Developing tools and functionalities
to implement in demonstrators
regarding grid management and
energy market integration
WP4 – Demonstrators
Lab validation
Demonst.,
validate
Lab validation of
developed tools and
equipments
• INESC-P
• Nottingham
• Nuremberg
Évora
Nottingham
Nuremberg
Demonstrate tools
and developments
applied to grids and
end-user
• Storage
• uG
• DSM
Demonstrate tools
and developments
applied to
communities
• Storage
• uG
• DSM
Demonstrate tools
developments applied
to building energy
management
• Heat storage
• DSM
WP5 – Business models and impact
Evaluate,
replicate
• Storage-enabled energy business models
• Life-cycle impact of storage business models
• Use cases cost-benefit analysis
WP7 – Project
management
• Overall
coordination
• Project
management
• Quality and risk
management
WP 6 – Dissemination, exploitation and
standardization
• Lessons learnt
• How to create value with SENSIBLE achievements
• Standard and regulatory issues
20
Download