Equipment Qualification – Fit for Intended Use Karem Y. Monge Sepúlveda MS Physics, CQA Senior Scientist-Technical Services Mylan LLC 10/27-29/15 1 General Information 2 Why Qualify an equipment? › References – ASTM E2500-13 Standard Guide for Specification, Design, and Verification of Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment – ASTM 2537-08 Standard Guide for Application of Continuous Quality Verification to Pharmaceutical and Biopharmaceutical Manufacturing – Pharmaceutical cGMPs for the 21st Century – Commissioning, Qualification, and Verification: A Review Solving the Terminology Conundrum by R. Adamson, N. Calnan, R. E. Chew, and S. J. Wisniewski – ICHQ8 thru ICHQ11 – ISPEs Guidance Documents for Commissioning and Qualification – ISPEs Science and Risk-Based Approach for the Delivery of Facilities, Systems, and Equipment – ISPEs White Paper on Risk-Based Qualification for the 21st Century, March 2005 – US FDA 21 CFR Part 11, 210 & 211, and 820 – EU GMPs 3 Why Qualify an equipment? › Design and verify that an equipment that has the potential to affect product quality and patient safety complies with specifications that are for its intended use. › Provide manufacturing capability to support defined and controlled processes that can consistently produce product meeting defined quality requirements. 4 What it means “fit for intended use”? › An equipment identified and designed for a particular task, with a particular purpose, and performs during the manufacturing process ensuring consistent product quality and patient safety. › ASTM E2500 objective: – Ensure that equipment is “fit for intended use” throughout it’s lifecycle from concept to retirement in a systematic, efficient, and effective way. – Provide manufacturing capability to support defined and controlled processes that can consistently produce product meeting defined quality requirements. – Satisfy international regulatory expectations. The main objective is to reduce cost while improving quality and safety. 5 What is the equipment lifecycle approach? › The lifecycle of an equipment begins from the time it is requested through the end of its useful life or when it is disposed. › In general, the Site shall establish a lifecycle system complemented by written SOPs that require the documentation and testing of an equipment, from design through initial testing, qualification, requalification, maintenance, and eventual retirement. 6 Identify the need Impact Assessment New Equipment Buy the equipment Decommissioning Modify and/or upgrade Qualify, Maintain, and Monitor 7 What is the equipment lifecycle approach? › The lifecycle of an equipment consists of: – Identifying the need for a particular equipment, giving special attention to applications › Equipment that do not have a GMP significance and does not have a direct impact on product quality must be commissioned following GEP. – Performing an Impact Assessment › May be integrated with a risk management process used to determine product impact and the extent of the verification/qualification and re-qualification period. › Defines the boundaries of what to include/exclude from the verification/qualification. – Buying the equipment – Qualifying, Maintaining, and Monitoring 8 – Decommissioning What is the equipment lifecycle approach? › Design phase that sets the equipment requirements. › Testing phase consisting of evaluation and development to ensure that the equipment meets the design specifications. › Qualification phase to verify that the equipment meets requirements consistently. › Maintenance phase that includes calibration, preventive maintenance, change control, and formal evaluation documented using SOPs. › Defining phase of requalification requirements and period. › Decommissioning phase (retirement) consisting of final testing and formal documentation. 9 YES Identify all utilities, equipment, and systems GMP Significance Define boundaries NO Perform Impact Assessment GEP Commissioning and Recertification required Qualification not required CC review may be required YES (e.g. Air Quality) Direct product contact NO (e.g. Building Management System) YES Produces data which impacts product release NO YES (e.g. WFI) Provides an excipient or produces an ingredient or solvent NO YES (e.g. PLC) Confirm boundaries and redefine if necessary Process Control System with no independent verification NO (e.g. Clean Steam) YES Used in final Cleaning or Sterilization NO Qualification Process YES (e.g. Nitrogen) Preserves product quality NO YES Failure or alarm has direct effect on product NO YES BU or SME review direct impact NO YES GEP Commissioning and/or Recertification required Qualification not required CC review required 10 New Utilities/Equipment Qualification Request Existing Utilities/Equipment Study Request (Process and/or Utilities/Equipment Requalification Study Request NO Re-design or purchase new Utilities, Equipment, System Is Utilities/Equipment adequate for new application? YES NO Gather Utilities/Equipment maintenance records, or other operational data Check existing Protocols and Reports, are they adequate for new application? YES Are SOPs adequate for new application? NO NO Review Functional Requirement Specification, Manufacturer’s recommendations and drawings Existing Requalification SOPs? Draft Operation SOPs (if applicable) YES Develop, review, and approve Protocol YES Execute Protocols or Requalification SOPs NO Meet Acceptance Criteria? Record the deviation(s) and ensure corrective actions YES Finalize Operation SOPs (if applicable) Prepare, review, and approve Final Report 11 What entails the Qualification Process? › Systematically verify that an equipment, acting singly or in combination, are fit for intended use, have been properly installed, and are operating correctly. › ASTM 2500 describes two approaches to the specification, design, and verification of the equipment that have the potential to affect product quality and patient safety. – Risk-Based Approach – Science-Based Approach › ISPE describes the Science and Risk-based Approach (RBA) as a paradigm. 12 What entails the Qualification Process? › Risk -Based Approach – Apply risk management to specifications, design, and verification – ICH Q9: › The evaluation of the risk to quality should be based on scientific knowledge and ultimately link to protection of the patient. › The level of effort, formality, and documentation of the quality risk management process should be commensurate with the level of risk. – QRM is a systematic process for the assessment, control, communication, and review of risks to the quality of the drug (product) across the product lifecycle. 13 What entails the Qualification Process? › Science-Based Approach – Use product and process information as the basis for making science- and risk-based decisions. This ensures that manufacturing systems are designed and verified to be fir for their intended use. – Examples: › › › › Critical Quality Attributes (CQAs) Critical Process Parameters (CPPs) Process Control strategy information Prior execution experience 14 What entails the Qualification Process? › ISPEs Science/Risk-Based Approach: – There is a shift in the global pharmaceutical industry. It is applying an all-encompassing approach to qualification and toward using focused methodologies to assess the scope of qualification. – It consists of: › The identification and control of risks to product quality › Formality and documentation commensurate with the risk › Use of Good Engineering Practices (GEPs) to verify installation and operation of the system / equipment › Verification that the system / equipment performance meets product and process user requirements “Fit for Intended Use”!!! 15 What entails the Qualification Process? › Risk-Based Qualification Principles1: – Focus on that which affects product quality – User requirements, based on the process (not on the equipment or system) are the key to acceptability. – Risk assessments and Process Knowledge used to identify critical elements – Use of Critical Process Parameters (CPPs) as the basis for the qualification – All activities must be value-added. That is, contribute in the manufacturing capacity. – Risk-based asset delivery – Value-added documents based on technical merit. – Use of supplier documentation – Test planning (one-time testing) – Foster innovation 1. ISPE: “A White Paper on Risk-Based Qualification for the 21st Century” – March 2005 16 Specification, Design, and Review Process Good Engineering Practice Product Knowledge Process Knowledge Requirements Specifications and Design Verification Acceptance and Release Operations and Continuous Improvement Regulatory Requirements Risk Management Quality Design Review Change Management 17 - 13 1. ASTME2500 Equipment Qualification 18 Qualification › Commissioning, Qualification, and Verification Riddle – Commissioning › A planned, documented, and managed engineering approach to the start-up and turnover of systems (e.g. facilities, equipment, and software) to the enduser that results in a safe and functional environment that meets established design requirements and stakeholder expectations – Qualification › A sub-set of validation that provides documentation that critical components of direct impact systems (e.g. facilities, equipment, software) are properly deigned, installed, and tested according to predefined acceptance criteria › A state, or determination, that the equipment has been found to be suitable for its intended use – Verification › The act of confirming, through objective evidence, that a particular specification has been met 19 Commissioning – Start-Up, setting to work, physical adjustment, physical inspection, functional testing, performance testing SAT Verification Work Commissioning Verification Work FAT Verification Work Basis for suitability (process requirements, risk control) Qualified as Suitable for Intended Use Other Verification Work Solving the Terminology 20 2 ) Conundrum (Fig. Qualification Phases › Functional Requirement Specifications (FRS) – A document that delineates the operational characteristics of the equipment as well as any design or construction details that have cGMP implications. It is utilized as the basis for any design, Factory Acceptance Test (FATs), Site Acceptance Test (SATs), Commissioning, and Validation Activities. › Enhanced Commissioning – Commissioning documentation used to fulfill field-testing requirements for the IQ and OQ › Commissioning – Systematic challenge that establishes that the equipment is manufactured and installed properly, and that it operates in normal conditions in accordance with the design and installation requirements and acceptance criteria. – Planned and systematic process for challenging and verifying that a facility, system and equipment is constructed, installed and functionally operates through all normal modes and conditions in accordance with the 21user, design, and installation requirement and acceptance criteria. Qualification Phases › Installation Qualification (Verification) – Documented verification that all key aspects of the equipment have been properly selected, constructed, and installed in accordance with the design requirements and established specification. › Operational Qualification (Verification) – Documented evidence establishing confidence that the equipment operates as intended and is capable of consistent operation within established specifications. › Performance Qualification – Documented evidence that the process or system, when operating in its environment under typical conditions performs as intended in meeting determined specifications 22 Purpose and Common Tests › Enhanced Commissioning – Identify requirements for the facility, system, equipment to be commissioned, such as: › Change Control, Factory Acceptance Test (FAT), Functional Requirements Specification (FRS), User Requirement Specification (URS), verification of construction completion, passivation, system leak test, pressure test, system cleaning, among others 23 › Purpose and Common Tests Enhanced Commissioning – Test Plan should include: › › › › › › › › › › Identification and listing of all equipment, systems/sub-systems, critical utilities, their specifications, normal operating limits, and acceptance criteria Identification of pre-requisites such as FAT, FRS and URS. Identification of system boundaries. Commissioning roles and responsibilities Approval Matrix Drawings Area for deficiencies documentation, how they will be managed, and resolutions Test conditions (usually manufacturer’s recommendations) and acceptance criteria Commissioning Schedule Unique identification number. 24 › Purpose and Common Tests IQ – Equipment/System Specifications and Installation Verification › › › – Equipment Drawing Verification › › – Compare the equipment/change against the key design specifications. Fabrication and assembly will be per manufacturer specifications. Document the equipment/change information and record the required information, such as model number, serial number, company identification, etc. Identify the equipment/change major components, such as motors, valves, sensors, etc. Inspect the individual system components for proper installation. Document the inspection results. All equipment must be installed according to the manufacturer and design specifications. › Identify (red lines) the equipment/change drawings that provide the equipment/system physical location and identify the utilities required. Verify the accuracy of as-built drawings against the actual installation and visually compare the system with the manufacturer drawings. Equipment Change Parts Verification Identify and document the equipment/change parts and verify that all change parts are in stock. The change parts should be under custody of the 25 equipment owner. › Purpose and Common Tests IQ – General Documentation › Review the equipment/system manuals available for installation, operation and maintenance manuals. › Verify the impacted Standard Operating Procedures (SOPs). › Store a copy of the equipment/system manual in the Engineering Department and in the Owner’s Department (make copies). › Verify and document the existence of the equipment/system Functional Requirements and/or System Specifications that define the intended application of the system. › Verify the equipment/change parts materials that are in direct contact with the product. Document if the material used is safe, appropriate, and free of contaminants. › Review the construction material documentation such as: material certification, passivation, welding logs/certifications and other applicable documents. › Verify the critical utilities such as Clean Steam and Water for 26 Injection (WFI) pipelines. › Purpose and Common Tests IQ – Instrument Identification and Calibration Verification › › › Verify and document that the equipment/system instrumentation has been categorized as either GMP (critical/non-critical) or non-GMP instrumentation, and calibrated within manufacturer and design specified ranges. Verify that all critical instruments (manufacturer supplied) and supplemental indicators, gauges and/or instrument loops are properly identified with an instrument number and calibration label, and have been entered into the Site Calibration Program. All instruments associated with critical components must be categorized as critical. – For example, if a conveyor is identified as a critical component of the equipment, the tachometer associated with that conveyor is a critical instrument. – Assure that all the standards required to verify the calibration of the equipment are available and instructions or methodologies for the handling, labeling, receipt, storage and replacement of them are in place. These procedures should be in accordance with the manufacturer recommendations and process requirements . 27 › Purpose and Common Tests IQ – Utilities Verification › Verify (through tests, measurements, etc.) that the required utilities adhere to equipment/change requirements. The utilities must be installed and available in conformance with design and manufacturer specifications. › Verify that the electrical utility includes an additional source panel and a breaker. Utilities with product contact, such as Water for Injection, Clean Steam, etc, must have qualification packages completed or at least executed. › A certified electrician must take the electrical measurements. › Include a Wiring Certification from a qualified engineer/technician, in order to certify that all field wiring of the equipment/change has been properly connected and as specified in the electrical and wiring diagrams. 28 › Purpose and Common Tests IQ – Maintenance/Preventive Maintenance (PM) Review › › – Recommended Spare Parts List › › – Review the recommended and required Preventive Maintenance (PM). Verify that the specified equipment/system items (battery back-up, lubrication, etc.) and/or critical components (e.g. conveyor, vial rotator, fans, etc.) either mechanical or controls have been entered in the Site Preventive Maintenance Program. In addition, methods for recording irregular repair or unscheduled maintenance should be in place. Note: Critical components are those which have parameters or ranges that maintain the performance and qualified state of the equipment/system. The appropriate PM must assure that this is verified. › Review, verify, and document which spare parts are required for operation and routine maintenance. Include referenced documents and an inventory parts list. Verify and document that such list have been submitted to the proper Department. Include a documented evidence of the transaction. Filter Installation Verification Verify the proper identification and installation of filters (e.g., HEPA, ULPA) related to the equipment and provide evidence of inclusion to the applicable Certification Program. Include all certification and integrity testing 29 evidence. › Purpose and Common Tests OQ – Preventive Maintenance (PM) Review › – – – › › Perform an assessment of the periodic re-qualification of the equipment/system. If the equipment/system requires periodic requalification, verify that the re-qualification activity has been entered into the System. Include copy of the transaction. Alarms Test Challenge each alarm of the equipment/system following the established test procedures and verify the machine response. Identify the alarms that are not in use and document the reason for being disabled. Controls Verification Verify that the equipment operates as described by the manufacturer. Start-up Sequence and Power Failure Verification › › Verify that all steps following the activation of the equipment (“on” mode) are satisfactorily achieved according with manufacturer specifications. Verify that the equipment operates correctly after a power failure, and that all restart conditions are met as well as the status of any set-up configuration. 30 › Purpose and Common Tests OQ – Radio Frequency (RFI) and Electromagnetic Interference (EMI) Verification › – Verify and document that radio frequency and electromagnetic interference do not adversely affect the operation of the system. Functionality Test › › Verify the function of each main component of the equipment and operational sequence functions. Challenge the boundary limit of the ranges specified in the functional specifications and verify the system capability (stress) and/or challenge the machine speed, if applicable. 31 › Purpose and Common Tests OQ – Operational Qualification of Steam Sterilizers, Dry Heat/Depyrogenation Ovens and Tunnels, and component preparation equipment, additional tests include, but are not limited to: › › › › – Temperature Distribution: Perform a temperature profile Chamber Seal Integrity: Verify that the integrity of the door seals to hold pressure Door Interlocks: Verify that the door opening sequence is correct and prevents the aseptic area to be compromised. Particulate Removal: Determine the level of particulate on components and closures after processing. Development consists of, but is not limited to, the following tests: › › › › › Heat Penetration Study Machine ability Sterilization Humidity Particulate Removal. 32 › Purpose and Common Tests PQ – Objective: › › › – Documented evidence that the equipment/system can consistently and reliably perform the desired functions under actual or simulated conditions of use (including environment) within the required process operating ranges and meeting predetermined specifications. It is executed at normal production environment (with the inclusion of the expected load that to be managed by the equipment/system). The equipment/system will be tested as a unit integrating all its parts and sub-systems. Preventive Maintenance (PM) Review › › › If the equipment/system requires periodic re-qualification, verify that the re-qualification activity has been entered into the proper system. Include a copy of the transaction as part of the qualification binder. Note: For re-qualification date purposes of new equipment, the year will start counting from the date of finalization of the first worst case successful run instead of the date of report approval. 33 How to Maintain the Qualified State? › Develop a Validation Master Plan stating the overall philosophy and approach used by the Facility / Functional Unit for planning, designing, organizing, executing, and reporting validation / qualification. The plan includes the current state of validation. Equipment Qualification - Include the approach to evaluate and perform the equipment validation, which should include the computerized control system that controls documents or acquire data for GMP related activities, when applicable. – › – “Critical qualified equipment are re-qualified every 12 months.” Validation Maintenance - Monitoring and Control Program to ensure that a process once validated continues to operate in a validated state. Include frequency of re-qualification and quantity of runs and tests. 34 How to Maintain the Qualified State? › Generate a List of GMP Equipment to be re-qualified including the re-qualification schedule – List should include the following: Equipment Type Equipment Name Equipment No. Next Due Date Current Report No. Autoclave Finn-Aqua A1 11/15 Report #1 Fedegari A2 01/16 Report #2 Precision B1 12/15 Report #3 Thermo Forma B2 Hotpack B3 Incubator Decommissioned 11/15 Report #5 – List should be complemented with the Preventive Maintenance System. 35 How to Maintain the Qualified State? › Create an SOP for the Re-qualification Program – › Describe how the “periodic” Re-qualification Program is run in the Facility/Site, to which equipment it applies, frequency of the requalification per type of equipment, and general process of the re-qualification. Create SOPs per type of equipment to re-qualify instead of a Protocol/Test Plan (Pre-approved Protocol/Test Plan) – – – – Overall exercise preparation Execution of Test Runs Handling of Deviations Attachments for execution 36 Attachment I: Incubator HOTPACK (B3) - sensors Location Diagram Place each sensor tip approximately three inches from the shelf surface Load description: Incubator full of Product A samples in plastic trails (or equivalent to simulated full conditions). 37 How to Maintain the Qualified State? › If it was determined that the equipment requires periodic re-qualification, make sure that the applicable procedures and Site Validation Master Plan is updated and contemplates this requirement in its re-qualification schedule. › Complete the necessary documentation in the proper system to activate the scheduled re-qualification, to indicate when the next re-qualification will take place. › If there are no procedures to adequately address the requalification requirements, develop a new procedure based on the original validation exercise and current technical procedures. 38 39 Documentation 40 How to Write an Effective Protocol? › The general purpose of all technical writing is to inform the reader as efficiently as possible. › The aim of all technical writing is to transfer information. 41 How to Write an Effective Protocol? › Write for the reader – Means identifying who the audience for your document is and what the purpose of your document is › Write clear concise English – Means creating clear concise sentences that are easy to read and understand – Structure the document in a logical order › Select relevant appropriate details – Means to focus on the essentials › Make writing process effective – Means to follow essential rules and guidelines in a systematic way and maintain the focus on these every time a technical document is written 42 How to Write an Effective Protocol? › Technical Writing is a 4-phase process: – Requirements: audience, purpose › Clarify the audience and purpose (who are we writing for and what we are trying to achieve) – Design: organization and structure › Define the structure that our document will have and organize the information accordingly – Implementation: draft › Write the draft – Testing: revision › Review the draft; first by the writer, then it is distributed for a more formal review 43 How to Write an Effective Protocol? › Audience (Write for the reader) – Before writing anything, define clearly: › Primary Audience: who, what, when, how – Who is the main person or main group who will read and use this document? – Who will perform? › Secondary Audience: who else will read it › Level of knowledge: about this specific subject – Key question: Do they know about X, Or have they done Y before? – NOTE: The sign-offs are not the Primary Audience, they are the Secondary Reader. – NOTE: The Auditor is not the Primary Reader / Audience. What they have is a level of knowledge. Thus, no matter time, the document 44 should read effortlessly. How to Write an Effective Protocol? › Specific Purpose (Write for the reader) – The specific question for each document: › What is this document meant to achieve? It is a tool to do a job, where you must define exactly what that job is. › What difference will it make? The document must make a difference. › What the reader will be able to do? This is the key question for instructional material like procedures and work instructions and protocols and operator’s manuals. › What the reader understand? This is the key question for technical reports. › What action or response do I want? This is a key question for proposals and or technical correspondence. 45 How to Write an Effective Protocol? › Structure (Write Clear Concise English) – Do’s and Don’ts: › Do make it brief (1 or 2 sentences). › Do take time to be precise. › Do stick to facts known at the time. › › › › Don’t be vague. Don’t include opinions. Don’t include assumptions. Don’t give too much or too little information. 46 How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” – Sentences › Short sentences – avoid long sentences › Avoid complicated constructions › Keep to 1 or 2 ideas › Average of 15 to 20 words or less › Break up long sentences › Ex. The test cycle was restarted because two units were contaminate. (10 – one idea) › Ex. The Operations Department compiles inventory forecasts on Friday and issues them to suppliers on Monday. (15 – two ideas/use of clauses) › Caution: – Do not write telegraphese (like text messaging) – Do not omit words 47 – Do not abbreviate normal words How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – Paragraphs › The basic building block › A set of related sentences › Divide your subject into topics › Cover each topic in one paragraph › Keep paragraphs short › Aim for a maximum of 5 sentences › Aim for a maximum of 10 lines. – NOTE: The main point is to be clear about what the role of the paragraph is – then the correct use of the paragraph will happen naturally. 48 How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – Verbs › Tenses: past – present – future – Past: we observed the reaction (this is after the execution) – Present: we observe the reaction (used mostly for instructions) – Future: we will observe the reaction – Keep the framework of tenses consistent › Active and Passive – Active – subject performs the action expressed in the verb – Passive – subject receives the action expressed in the verb or action is performed on the subject of the sentence 49 How to Write an Effective Protocol? Clear Concise English “The Golden Rule” Cont’d › Verbs – In Reports: › Use Passive Voice to report actions and results › Use the Past Tense to report actions and results › Optionally, use the Present Tense for discussion, conclusions, and recommendations › Above all, BE CONSISTENT › Verbs – In Instructions: › Use Present Tense for instructions › Pretend everything happens in the Present Tense › Also, describe processes in Present Tense › Use the Imperative, if possible › Place the Imperative at the start of the instruction, if possible 50 How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – Verbs (Common Mistakes) › Open the nozzle until the light flashes. – Ideal Form: “Open” is the Imperative and is at the start, instruction is short and self-contained, addresses the reader directly › The operator must open the nozzle until the light flashes. – Most used: reader is not addressed directly because there is more than 1 person involved; thus, imperative cannot be used. › The nozzle is opened by the operator until the light flashes. – Passive Voice: not to be used for instructions; does not even read like an instruction, it reads like a description of something. Avoid This. › The nozzle shall be opened until the light flashes. – Passive Voice and Future Tense: it is not clear who should carry out the instruction, and it is not clear if it is an instruction at all. 51 Avoid This. How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – – Modifier Stacks › Is a word which describes a noun or a noun phrase. It acts like an adjective. › The guideline: do not place strings of modifiers before nouns. › Rule of Thumb: use no more than 2 modifiers per noun › Ex. AVOID: she audited the revised document archive management procedure – USE: she audited the revised procedure for managing the document archive Vocabulary › Use words that are familiar, short, concrete – They inform › Avoid words which are unusual, long, fancy, abstract › Ensure that the vocabulary is appropriate for your audience 52 How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – – Deadwood › Is a meaningless padding in your writing; words and phrases which either mean nothing at all or are very long-winded. › Ex. In consequence of the fact…=as a result, because In the event that… = if It is to be noted that…=note or “leave out” In this point in time=now, at the moment Lean Writing – (Select Relevant Appropriate Details) › Three rules: – Omit needless words – Omit irrelevant information (not relevant to the purpose of the document – Omit unnecessary repetition 53 How to Write an Effective Protocol? › Clear Concise English “The Golden Rule” Cont’d – Lean Writing – (Select Relevant Appropriate Details) Cont’d › Common Errors, Foreign Words, Copy and Paste › Technical Jargon – Only use jargon that the audience understands – Explain any word that the audience does not understand – Use footnotes or a glossary – Use the words consistently › Abbreviations – Are convenient for the reader, not the writer – Avoid abbreviating ordinary words – Universally understood abbreviations are acceptable – Expand abbreviations the first time they occur 54 How to Write an Effective Protocol? › Draft and Revision – Review your own draft › › › › › – Review the Draft thoroughly before distribution Take a break between finishing the draft and starting your review Try to see the document as your reader would see it Get someone else to review it, if possible (peer reviewing) “print it out, put it aside, revise with fresh eyes” Review someone else’s draft › Make two careful passes to ensure: – – – The document does what it is meant to do. The mechanics of the document are correct. Suggestions for reviewers › › › › › › Be constructive ●Adopt a standard dictionary Explain what the problem is ● Adopt a style guide Suggest alternatives, if possible ●Avoid red ink for markup Be consistent Provide templates and Guidelines Provide a library of model documents 55 › How to Structure a Test? Develop the equipment qualification protocol using the following required documents, as applicable: – Change Control and it’s documentation – Functional Requirements Specifications and/or Functional Specifications Documentation. › These documents shall define the system boundary, if necessary. The boundary describes the equipment/system process and systems operating or the processing limits for qualification purposes. – Design/Vendor drawings – Operation and/or Maintenance Manuals – Factory Acceptance Test (FAT) documents and/or Commissioning Documentation. Change Control Manual, FAT, SAT 56 Commissioning How to Structure a Test? › To develop a protocol for new equipment, system or process: – obtain and review the Change Control documentation, Regulatory requirements, Technology Transfer Report, Validation Master Plan, Project Scope document, Functional Requirements Specification, Factory Acceptance Test, Commissioning Report, Vendor Operating Manuals, and draft Standard Operating Procedures (SOPs), as applicable. › To develop a protocol for a change to existing equipment, system, process or product: – obtain the applicable archived Validation Books from previous qualifications and applicable current PPGs. Identify quality and operational items affected by the change. › Generate a protocol following the minimum format requirements. You should have a procedure and/or template. 57 How to Structure a Test? › If it is an Existing Equipment: – Evaluate the “nature of change” (e.g., upgrade, modification, replacement, etc.) to identify the testing requirements to be covered in the qualification protocol. › Verify the following required documentation to develop the Qualification Protocols (IQ/OQ/PQ): – Original Qualification Package and/or Validation Book – Identify the capability of the equipment/system “change” within the required process operating variables. – If the equipment/system “change” capabilities are out of the system operating ranges, the Operational Qualification (OQ) protocol must test the new operating parameters proposed to ensure system/process state of control upon change control closure. – If the “change” specifies current operating parameters limits, the system/process state of control must be established in the OQ conclusion. 58 How to Structure a Test? › Incorporate technical content as identified in the applicable validation program(s). › Provide for the inclusion of the supporting evidence (as applicable) that can assure that the circumstances of the execution can be reconstructed. › Include a rationale on sampling and acceptance criteria, if applicable, and use (as required) a statistical base plan (e.g. AQL, sampling levels, etc) or according to the manufacturer specifications and industrial, regulatory and/or company standards. 59 How to Structure a Test? › The applicable validation phases of Installation, Operational, Development, Qualification/Study, and Performance Qualifications must be sequentially executed. – Testing related to Computer Qualifications must be completed prior to the related equipment operational tests. › Installation and Operational Qualification (IOQ) protocols may be combined in a single document and identical elements need to be documented only once. › If all prerequisite conditions for protocol execution are not met (e.g., a previous phase is not completed or its Technical Report is not approved), and interim approval must be obtained in order to start execution of a subsequent protocol. 60 › How to Structure a Test? Test Design – – – – – Some qualification activities, such as documentation and/or verification steps, may occur either simultaneously or subsequent to commissioning activities Document a rationale/justification for exceptions if any of the qualification requirements (e.g., tests, documentation, etc) cannot be fulfilled or is not applicable in order to proceed with the protocol approval and qualification exercise. › Ex. The compressed air is an existing point of use qualified under Protocol X. Label the equipment/system (i.e., “equipment under qualification”), including the date, phone number and name of the person responsible. Become familiar with the equipment/system; if possible, attend to equipment/system presentation meetings and participate in the evaluation and selection of the equipment/system or change Review key documents and/or publications developed by the owner, manufacturers and distributors, such as: user and functional requirements specifications, general design, factory acceptance test, construction, materials, operation, manufacturer recommendations, safety devices, speeds, capabilities, drawings outputs, and equipment/system limitations. 61 How to Structure a Test? › Interim Approval is a document that serves to document the completion of a phase and requests the authorization to proceed to the next phase. › Interim approval for a subsequent protocol may be granted provided that: – All specified testing for the protocol is complete. – All data for the protocol have been thoroughly reviewed, including failed run, and all acceptance criteria have been achieved. – All events are resolved or an action plan for resolving them is in place. – All requirements of the protocol have been met. – A compelling business necessity warrants proceeding. 62 63 › How to Structure a Test? IQ › OQ – Equipment/System – Preventive Maintenance (PM) Review Specifications and Installation Verification – Alarms Test – Controls Verification – Equipment Drawing Verification – Start-up Sequence and Power Failure Verification – Equipment Change Parts – Radio Frequency (RFI) and Verification Electromagnetic Interference – General Documentation (EMI) Verification – Instrument Identification – Functionality Test and Calibration Verification – Operational Qualification of Steam Sterilizers, Dry – Utilities Verification Heat/Depyrogenation Ovens – Maintenance/Preventive and Tunnels, and component Maintenance (PM) Review preparation equipment – Recommended Spare Parts › PQ List – Preventive Maintenance (PM) – Filter Installation Verification Review 64 65 66 67