UNDERGROUND SERVICE ENTRANCE LOCATED ON A BUILDING Northwestern Wisconsin Electric Company requirements: 200 AMP UL Approved Meter Socket With Lever Bypass The service entrance or disconnect should be located at the point where the wires enter the building. NWEC wires on top lugs Customer wires on bottom lugs Lock Nuts Bushing Riser pipe must be Schedule 80 PVC conduit Or rigid metal. 2” minimum. Meter height minimum 4’ maximum 6’ Ground wire to main disconnect Use Copper ( # 6 or larger) Ground wire from main panel *ALL MATERIALS USED FOR THE METERING ASSEMBLY ARE FURNISHED BY THE CUSTOMER Approved Ground Wire Clamps Ground Rods 12” under ground 18” below ground 8 feet apart minimum 2 ground rods required 5/8” x 8’ copperweld NORTHWESTERN WISCONSIN ELECTRIC COMPANY OVERHEAD ELECTRIC WIRE SERVICE ENTRANCE LOCATED ON A BUILDING Customer provides wire from the meter socket to 18” past the top of the mast 3’ minimum Company wires shall not be less than 18” above roof, and shall not extend more than 48” across roof Overhead wire to the mast provided by NWEC. All other materials seen in this diagram to be furnished by the customer. Mast must be 2” rigid conduit 200 Amp UL approved meter socket with Lever-Bypass Ground wire to main panel - #6 copper or larger Meter height 6’maximum 4’ minimum Rods 1’ underground Ground Rods 5/8” x 8’ copperweld 2 required for each service 8’ minimum Rods 2’ minimum from foundation Northwestern Wisconsin Electric Company Trailer Hookup or Temporary Service Overcurrent protection device (fuse or breaker) meter socket with lever bypass The metering assembly and service equipment should be mounted on a sturdy, weather resistant support 200 AMP UL approved Riser pipe must be rigid metal, or schedule 80 PVC conduit. 2” minimum Meter Socket with Lever Bypass 12” approved ground wire clamps 18” bushing or fitting required Ground wire #6 copper or larger customer wires Ground rods 5/8” x 8’ copperweld – 2 required Bushing Lock nuts (2) 8’ minimum 1. Materials in metering assembly are furnished by the customer. (everything you see on this page) 2. Our company wires should enter the meter socket through the bottom left knockout. 3. NWEC requires a signed wiring affidavit from the person who wired this service. 4. The meter socket should be mounted no less than 4 feet, and no more than 6 feet from the ground.