XI SIMPÓSIO DE ESPECIALISTAS EM PLANEJAMENTO DA OPERAÇÃO E EXPANSÃO ELÉTRICA XI SEPOPE 17 a 20 de Março 2009 March – 17th to 20th – 2009 XI SYMPOSIUM OF SPECIALISTS IN ELECTRIC OPERATIONAL AND EXPANSION PLANNING BELÉM (PA) - BRASIL Non-Conventional AC Solutions Adequate for Very Long Distance Transmission C. PORTELA COPPE / UFRJ Brazil SUMMARY There are several cases around the world in which the use of very important energy resources, interesting in a strategic, economic and ambient impact point of view, imposes an adequate solution to transmit large electric power, at very long distance. As an example, the natural medium term option for the Brazilian electric sector is to base its growth in the hydroelectric resources of Amazon basin, with moderate complementary generation based in other sources. This choice imposes an adequate solution to transmit most of such energy at distances of the order of 2500 km. In order to obtain an adequate transmission system, a specific analysis must be done, with careful optimization, global, and considering a long-term point of view. It is not adequate to extrapolate solutions developed for medium distances, of the order of a few hundred kilometers. There are two types of solutions potentially interesting: A- Transmission in alternating current (AC) based in non-conventional transmission lines (LNC), with also a non-conventional conception of the transmission trunk. B- Transmission in direct current (DC). The solutions A and B are, both, essentially “point to point”, without prejudice of eventual “adaptations”, of “subsidiary” type, and have quite different optimization constraints. The correct comparison imposes a separate optimization of both solution types (A and B), and the objective and quantitative comparison of results. In some conditions, a hybrid solution may be justified. We have done studies of non-conventional solutions, deliberately abandoning the criteria of choosing solutions similar to lines and compensation equipment of present systems, but considering very robust criteria of physical validity, ambient impact and joint global optimization of transmission trunk. For instance, very interesting solutions have been obtained, based in alternating current transmission trunks, non-conventional, with unitary transmission capability from 2 GW to 12 GW, and electric length a little higher than half wave length (at power frequency), without the need of reactive compensation, or with very small reactive compensation, and without the need of intermediate substations. Such trunks can be energized and de-energized switching a single circuit breaker, with moderate switching overvoltages, have moderate losses, very good behaviour for load variations and for electromechanical stability of interconnected networks, originate moderate electromagnetic field near the line, have low ambient impact and have cost typically much lower than some recent transmission systems based in conventional solutions (by example, the costs per unit of transmission capability of described trunks are of the order of one fifth to one third of the costs of recent transmission systems). In this article it is presented a discussion of mentioned non-conventional solutions, with emphasis in conceptual aspects and in optimization and validation procedures. Also, examples will be presented, in the power and parameters range potentially interesting for transmission electric power from Amazon basin to main consumption regions of Brazil. KEYWORDS Very long distance transmission, Non-conventional AC solutions, Lines with a little more than half wave length. 1 Type here the contact info of the main author as a footnote. * Author contact. E-mail: portelac@ism.com.br, Phone: 55-21-24934201, Fax: 55-21-24934201 Adress: Rua Eng. Cesar Grillo, 249, Rio de Janeiro, RJ, CEP 22640-150, Brazil _ 1. Introduction This article presents non-conventional transmission systems potentially convenient to transmit large electric power, at very long distance, e.g. of the order of two to three thousand kilometers. The development of such systems was originated when searching adequate solutions for the development of Brazilian power system. The natural medium term option is to base its growth in the hydroelectric resources of Amazon basin, with moderate complementary generation based in other sources. This choice imposes an adequate solution to transmit most of such energy at distances of the order of 2500 km. The direct use of traditional solutions for typical transmission systems, developed for quite different constraints, was naturally put in doubt and it was decided to search eventually different solutions, founded in basic physical constraints, operational requirements and robust optimization and validation procedures. The main purpose of this article is to present one of the results of the research work, namely: transmission in alternating current (AC), based in non-conventional transmission lines (LNC), with also a non-conventional conception of the transmission trunk, with electric length a little higher than half wave length (at power frequency). This type of solution was studied for applications in the medium term development of Brazilian network, to which some presented examples apply, although their main features are valid for a large spectrum of similar conditions in other countries. In Fig. 1 are represented the basic transmission distances, between new power stations in Amazon basin and main Brazilian load centers, and the geographical distribution of hydroelectric power stations in 2003. 2. A Non-Conventional Very Long Distance Transmission System Alternative We present now some of the main aspects of transmission systems based in “Non-Conventional Lines” (LNC), three-phase, double three-phase or six-phase, defined with basis in the following criteria: - Do not consider restrictions that result merely of usual solutions. - To impose only restrictions related to basic physical constraints and to performance, security and ambient impact. - Physical parameters optimization according the specific operational functions and objectives of the line, including costs, losses, operational reliability, transmission range and operation constraints, and ambient impact, ponderated along the useful life of the transmission system and pertinent scenario range. It was identified a set of basic physical properties that allows to choose a limited number of parameters with high correlation with several other physical, performance and cost parameters. It is viable a robust optimization analysis, based in a moderate number of parameters and the specific constraints of the considered transmission system. In previous work, have been defined optimization and validation methodologies, according this type of analysis [1-22]. The transmission at very long distances (of the order of 2000 km or more) has constraints much different of “usual” transmission distances (till a few hundred kilometers). So, the simple extrapolation of “usual” procedures, for very long distances, leads to inadequate or non-optimized solutions. The defined methodologies were applied to a significant range of conditions and to a large number of examples. This analysis has allowed an approximate definition of practically feasible transmission powers, with prudent criteria, for transmission at very long distances. Naturally, for each specific condition, it is necessary an optimization and validation analysis. For transmission at very long distance (of the order of 2000 km or more), there are interesting solutions based, approximately, in: - Selection of transmission trunks that behave with an “electric length” a little longer than half wave length (at power frequency). - Point to point connection, without section switching. - Null or very reduced reactive compensation. - Non-conventional lines (LNC) with large transmission capability (in comparison with conventional lines). - Joint optimization of lines, network equipment and switching and protection criteria, detecting and avoiding potentially critical conditions. 2 Brazil Fig. 1 - Basic transmission distances, between new power stations in Amazon basin and main Brazilian load centers, and geographical distribution of hydroelectric power stations in operation in Sept. 2003. These solutions allow: - Good performance of the transmission trunk in what concerns electromechanical stability. - Good performance of the transmission trunk in what concerns switching overvoltages. - Cost much lower than “traditional” solutions. - Operational reliability much higher than “traditional” solutions. - Ambient impact much lower than “traditional” solutions. For these solutions, the characteristic power is, approximately, the limit of transmitted power (differently of what happens with “short” distance lines), and, within some conditions range, the maximization of characteristic power corresponds also, exactly or approximately, to: - Maximization of transmitted power limit. - Minimization of losses. - Minimization of corona effect. - Maximization of viable operation voltage. - Minimization of reactive power in several operation conditions. - Minimization of sustained overvoltages in several operation conditions. - Minimization of switching overvoltages for several switching operations. 3 14 Pc 12 [GW] 10 8 6 4 2 600 800 1200 Uc [kV] 1000 Fig. 2 - Characteristic power, Pc , that can be obtained with prudent criteria with LNC three-phase lines, in function of voltage, Uc , between phases, for voltage till 1250 kV . Curves in red and violet represent the typical range of Pc that can be obtained, depending on specific conditions and options. Fig. 3 – Schematic representation of a 2550 km, three-phase line, without reactive compensation, switched from one extremity (all the line). ! We present, now, some results for non-conventional lines (LNC), three-phase, of voltage till 1250 kV, optimized for transmission at very long distance (of the order of 2000 km or more) [1-22]. In Fig. 2 it is represented the characteristic power, Pc , that can be obtained with prudent criteria, with LNC three-phase lines, in function of voltage, Uc , for voltage till 1250 kV . In Fig. 3 it is represented, schematically, a three-phase line, with 2550 km, at a 60 Hz network, without reactive compensation, which can be switched from one extremity (all the line). As examples of this type of line, in Fig. 4, it is shown some bundle geometries and structures’ variants of two lines, of 1000 kV and 800 kV, with characteristic power, Pc , 8.6 GW and 4.8 GW. Sustained overvoltage in one terminal (opened) is 1.017 pu (referred to the other terminal voltage). The three types of structures shown for the 800 kV line apply to different conditions, namely in what concerns wind. It is also shown, in the same Fig. 4, the power, P (in GW), and the reactive power, Q (in Gvar), at line terminal 1, with voltage U1 = 1000 kV or 800 kV (respectively for the two example lines), in function of phase difference, α , and ratio, R , between modules, of voltages at terminals 2 and 1 (as indicated in Fig. 3). A phase range (of α − π) of the order of ± 0.2 radian allows to vary the transmitted power in a range ± Pc . It is out of the scope of this article a discussion of all aspects of the electrical and mechanical behaviour of this type of solution, that have been studied, in order to validate it as a convenient and a potentially optimum alternative for several real conditions ! of long distance transmission, including the medium term new main transmission trunks adequate for Brazil electrical network expansion. So, we have chosen a few results, illustrating some important aspects of the example lines’ behaviour. A first example refers to switching overvoltages. In order to separate and characterize the fundamental line behaviour, avoiding the influence of network transient behaviour and of specific soil electric parameters, chosen examples consider the line energization from an “infinite” busbar, with the opposite terminal open and with simultaneous switching on of the three phases. Results are presented in Fig. 5. This example shows that it is obtained a remarkable low value of switching overvoltage, energizing the 2550 kV line with a very simple switching procedure, in a single step. A second example refers to the possibility of, for single-phase faults, to open only the fault phase, in both 4 y [m] Uc = 1000 kV U1 = 1000 kV Pc = 8.6 GW Pc = 8.6 GW → R Guyed structure, 1000 kV line y [m] x [m] α − π [rad] Uc = 800 kV U1 = 1000 kV Pc = 4.8 GW Pc = 8.6 GW → R y [m] α − π [rad] x [m] Guyed structure, 800 kV line Uc = 800 kV U1 = 800 kV Pc = 4.8 GW Pc = 4.8 GW → R Chainette type structure, 800 kV line y [m] α − π [rad] x [m] Uc = 800 kV U1 = 800 kV Pc = 4.8 GW Pc = 4.8 GW → R Cross-rope type structure, 800 kV line x [m] α − π [rad] Fig. 4 – Examples of bundles and phase geometry, and line structures, for two 2550 km LNC lines, with nominal voltages, Uc , 1000 kV and 800 kV , and characteristic power, Pc , respectively 8.6 GW and 4.8 GW . It is also shown, in this Fig. 4, the power, P (in GW), and the reactive power, Q (in Gvar), at line terminal 1, with voltage U1 = 1000 kV or 800 kV (respectively for the two example lines), in function of phase difference, α , and ratio, R , between modules, of voltages at terminals 2 and 1. line extremities, and to use procedures that assure a high probability of extinction of secondary arc, in faulted phase, in a reasonably short time, allowing its fast reclosure, with a small network disturbance. As the large majority of line faults are single-phase faults, originated by lightning, and such faults, with successful fast reclosure, have little impact in the network, this possibility allows an important increase in 5 u1a u2b u2a t [ms] ! t [ms] t [ms] Fig. 5 – Examples of switching overvoltages of the example line of 2550 km , 1000 kV, in function of time. u1a – Applied voltage, in one phase, switched in terminal 1 at the “infinite” busbar, at t = 0 , in pu of phase voltage amplitude at the infinite busbar, Û . For the nominal voltage 1 MV at the busbar, it is Û = 2/3 . 1 MV = 816.5 kV. u2a – Transient voltage, in the same phase, in the other line extremity, with no pre-insertion resistor at the circuit breaker, and without surge arresters at terminal 2 . Peak value of | u2a | is 1.88 pu . Power frequency voltage amplitude at terminal 2 , with no load, is 1.017 by the voltage amplitude at terminal 1 . u2b – Transient voltage, in the same phase, in the other line extremity, with a pre-insertion resistor of 77.5 Ω in the switching circuit breaker, connected during 1 cycle (16.7 ms). Peak value of | u2b | is 1.13 pu (923 kV for nominal voltage at terminal 1 ). For the nominal voltage 1 MV at the busbar, the energy dissipated in the pre-insertion resistor is 11.5 MJ . I [kA] I I [A] [A] α - π [rad] U [kV] α - π [rad] U U [kV] [kV] α - π [rad] A α - π [rad] α - π [rad] B α - π [rad] C Fig. 6 – Example of a 2550 kV, 1000 kV line behaviour, for single-phase fault in an unfavourable point. α – Phase angle between line terminal busbars. I , U – Sustained fault current and phase-ground voltage at fault point, neglecting arc impedance. A – Line terminals connected to busbars at both extremities, in the three phases. B – Line terminals of fault phase open at both extremities, and closed in the other two phases. C – Same as B and with connected auxiliary circuits, to reduce secondary arc current. line and network reliability. Fig. 6 shows the result of a procedure that allows an important reduction of secondary arc current and recovery voltage, that assures a high probability of success of single phase opening and reclosure, for single phase faults, in the presented type of very long transmission trunks. Some other procedures, using secondary arc physical behaviour, are also promising, and are being investigated. We notice that conventional type long transmission trunks, with massive compensation, do not allow successful single phase open and reclosure, due to physical reasons, which have been identified. 6 3. Some Basic Economical and Cost Aspects We present, now, some brief comments about economical and cost aspects of non-conventional transmission systems of the type presented in this article. The indication of absolute specific costs, in a general context, would have a large error margin, due to the many aspects that affect the “indicated cost” and are, in a large proportion, independent from the technical effective cost, according an objective set of clear conditions. So, we present only some approximate relative costs, taking as a basis some recent transmission trunks of about 1000 km, with 1 GW maximum transmitted power. Such systems are based in “conventional” transmission systems for lengths of a few hundred kilometers, and use massive reactive compensation, in the transmission trunks and in the interconnected networks. It is out of the scope of this article to discuss such projects, that are referred only because they were object of recent decisions and options and reflect what was the “chosen” reality in a specific context. For this comparison, it is considered as “unitary cost” the “technical cost” of a line (Case A), with 2550 km, similar to a line of a relatively recent project, 500 kV, 1 GW, excluding intermediate substations and reactive compensation, along the line and in the interconnected networks, required to allow line operation. Such cost was decomposed in representative parcels, from which, with uniform criteria, were estimated the costs of example trunks presented in item 2. , with 2550 km, one of 1000 kV, 8.6 GW (Case B), and other of 800 kV, 4.8 GW (Case C). The result is indicated in Table I. Table I – Cost comparison of: - Transmission system similar to a recent project based in conventional systems (Case A). - Example of non-conventional system of 1000 kV, P = 8.6 GW (Case B). - Example of non-conventional system of 800 kV, P = 4.8 GW (Case C). Total costs, C Cost parcel Relative costs, c = C / P CA(Case A) CB (Case B) CC (Case C) cA (Case A) P = 1 GW P = 8.6 GW P = 4.8 GW P = 1 GW cB (Case B) cC (Case C) P = 8.6 GW P = 4.8 GW cB / c A cC / cA C1 1.00 2.56 1.80 1.00 0.298 0.375 0.298 0.375 C2 0.70 0.00 0.00 0.70 0.000 0.000 0.000 0.000 Ct = C1 + C2 1.70 2.56 1.80 1.70 0.298 0.375 0.175 0.221 C1 Line cost, excluding intermediate substations and reactive compensation, along the line and in C2 interconnected networks, to allow line operation. Cost of intermediate substations and reactive compensation, along the line and in interconnected networks, to allow line operation. In the assumptions of Table I (for Case B and Case C, presented in item 2): - The total costs of presented examples, with transmission capacity 8.6 GW and 4.8 GW, at 2550 km, are only about 51 % and 6 % higher than the total transmission cost of a transmission system with 1 GW transmission capacity, similar to a recent transmission system based in conventional solutions (for the same line length, in compared costs). - The relative costs (per unity of transmission power capacity, and for the same line length), of the presented examples: - Are of the order of 30 % and 38 % of the relative cost of comparison line, based in conventional solutions, excluding intermediate substations and reactive compensation (along the line and in interconnected networks, to allow the line operation). - Are of the order of 18 % and 22 % of the relative cost of comparison line, based in conventional solutions, including intermediate substations and reactive compensation (along the line and in interconnected networks, to allow the line operation). Anyhow, the presented non-conventional solution allows transmission costs at very long distances (of the order of 2000 to 3000 km) much lower than costs obtained with AC transmission systems based in solutions developed for traditional transmission systems, with transmission distances of a few hundred kilometers. 7 4. Application of the Presented Alternative to Madeira Transmission System A few years ago [1-22], we examined the use of the presented alternative for the transmission of hydroelectric energy from Amazonian region to main consumption centers and it appeared quite interesting, as a natural AC alternative, that should be adequately studied and compared with the DC alternative, in order to optimise such transmission. Some presentations were done, with participation of persons of the electric sector. Also, some presentations were done to agencies related to electric sector development, but, although no technical argument was presented against the alternative, it was always said that there was no time to consider it, because options at to be done within, e.g., “two weeks”. Much more than “two years” elapsed, with the successive “two weeks” argument, and the alternative was, in fact, ignored, by “responsible agencies”, for the Madeira Transmission System. In the mean time, it was studied and discussed, by several people, and the obtained and presented results, informed to responsible agencies, and presented and discussed in several forums, showed that the alternative was competitive and evidenced important advantages, in comparison with alternatives studied and chosen by such agencies. It is out of the scope of this article a detailed discussion of results, for the Madeira Transmission System, of an alternative of the type presented in this article. We present, only, some of its important aspects, and its comparison with the alternatives chosen by responsible agencies. In Fig. 7 it is represented the configuration of the proposed alternative, and are indicated some of its parameters and characteristics. This configuration is much simpler than the alternatives proposed, e.g., in document R1 that was available at agencies’ internet sites. For instance, the final configuration of the AC alternative, according page 31 of R1 EPE’s document, has three AC 765 kV lines, nominal power 3 x 2.1 GW = 6.3 GW, six intermediate substations, total length 2375 km, and: - Inductive compensation: fixed 21.75 Gvar; switched 3.05 Gvar. - Capacitive compensation: fixed 69.33 % of longitudinal lines inductance, switched 2.2 Gvar. - Controlled compensation: –0.84 / +1.75 Gvar, more reactive power exchanged with terminal networks and power generators. It was concluded that, for Madeira Transmission System, the alternative presented in this article is competitive with all the alternatives presented by responsible agencies. To situate the subject, in Table II it is presented a summary of the cost comparison of the proposed alternative with the alternatives proposed by EPE, in R1, for Madeira Transmission System. It was also done a comparison of the presented alternative (of a little more than half wave length) with the three R1 alternatives, for the Madeira Transmission System, in what concerns technological risk, Fig. 7 − Madeira Transmission System. Configuration of the alternative of trunks with a little more than half wave length, 800 kV AC lines, with nominal power 2 x 4.85 GW = 9.7 GW, without intermediate substations, total length 2500 km, with 8 Bittern cables per phase. The transmitted power may vary continuously between – 9.7 GW and +9.7 GW . There is no inductive compensation (neither fixed, nor switched), no capacitive compensation (neither fixed, nor switched), and no controlled reactive compensation. 8 Table II – Cost comparison of the alternative of trunks a little longer than half wave length, with LNC lines, with the three alternatives of R1, for the Madeira Transmission System - Case a – Transmission system in AC, of the presented type, based in two 800 kV lines. - Cases b/c – Transmission system in DC of R1 (Case b, considering information of published articles and public EPE documents, and Case c, considering relative comparison costs, published by EPE, of Cases c, d, e). Case b and Case c are assumed “analogous”. - Case d – AC “conventional” transmission system, of R1, based in 765 kV lines. - Case e – Hybrid transmission system, of R1, based in a DC bipole and in a “conventional” AC transmission system, with 500 kV lines. Comparison taking as basis (unity of relative cost) the Case a Total cost (investment) [109 R$] Case a Case b=c Case d Case e 5.34 7.02 9.48 to 9.87 8.55 to 8.78 Difference of total cost (investment) [109 R$] Dif. a-a Dif. b-a = c-a Dif. d-a Dif. e-a 0 1.68 4.14 to 4.53 3.21 to 3.44 Relative cost (investment) Case b=c Case d Case e 1.31 1.78 to 1.85 1.60 to 1.64 Difference of relative cost (investment) Dif. a-a Dif. b-a = c-a Dif. d-a Dif. e-a 0 0.31 0.78 to 0.85 0.60 to 0.64 Case a 1 reliability and execution time. For all this aspects, the presented alternative has also shown important comparative advantages. The proposed alternative presents, also, important advantages, especially in comparison with the DC alternative, in what concerns operational and evolutionary flexibility. Namely: - Allows the connection of each of the trunk terminals to a single busbar, or to several near busbars (at distances till about 200 km). - Allows interconnections in trunk intermediate points, maintaining the same functional and operational conception. For instance, for Madeira Transmission System, it is viable to have several connections, with the power in each one limited to a few hundred MW. - May evolve, if and when that may become justified, for a set of lines, incorporated in a network, some of them with eventual series or shunt reactive compensation. It is important to notice that, when doing the comparison of the proposed methodology with the alternatives proposed by EPE, in R1 document, for Madeira Transmission System, we have found several aspects of such alternatives that imply in important technological risks, including: - Several consequences of alternatives’ conceptual aspects, which imply in important risk of operational problems, with reliability consequences, and whose “correction” is not trivial and may result in the necessity of improvement measures, with eventual large costs and delays. An example: conceptual options, of phases and insulators arrangement, and of structures, for 765 kV and 500 kV AC lines. - Lack of specification precautions, for several important technological aspects of the R1 alternatives, namely related to the very long length of the transmission system, to the important relative variation of available generation power of Madeira power stations and to single pole operating constraints. - Problems occurred in power transmission equipment that have not been adequately solved or corrected by the electric sector, but that must be duly studied and object of efficient actions that assure an adequate quality of important transmission systems. An example: transformers of converter stations. Several of the mentioned aspects and problems have been presented and discussed in a public seminar and are described in documents available in internet [21-22]. Its detailed presentation and discussion is not within the scope of this article. As example, we comment here, only, one of such problems. In Fig. 8 we indicate, briefly, the frequency behaviour of a 2500 km transmission trunk, comparing the proposed alternative with an AC transmission trunk of the type presented in R1 responsible agencies’ document. It is evidenced that the R1 type has parameters with several poles and zeroes that originate low damping transients and that, associated to active or non linear effects in network, may originate several resonance or almost resonance phenomena. This behaviour occurs in other recent Brazilian transmission systems and, typically, does not allow single-phase opening and fast reclosing for single-phase faults. This restriction implies in an important negative effect in transmission trunk and electrical network reliability. The comparison of Fig. 8 shows that this problem does not occur in transmission trunks of the proposed type, for which a large majority of line faults may be eliminated, without significant effects. 9 2500 km Im [Z e] Im [Z e] [Ω] [Ω] f [Hz] Transmission trunk, with 2500 km, and its equivalent π scheme, for nonhomopolar components or modes. Imaginary part of elements Ze and Ye2 of equivalent π scheme: A - For the presented transmission trunk (without reactive compensation). B - For R1 type AC transmission trunk (with 100 % shunt and 70 % series compensation). f [Hz] Im [Ye2] Im [Ye2] [S] [S] f [Hz] f [Hz] A B Fig. 8 − Frequency behaviour of a 2500 km transmission trunk, comparing the presented alternative with an AC transmission trunk of the type presented in R1 responsible agencies’ document. 5. Conclusions Very interesting solutions have been obtained, based in alternating current transmission trunks, nonconventional, with unitary transmission capability from 2 GW to 12 GW, and electric length a little higher than half wave length (at power frequency), without the need of reactive compensation, or with very small reactive compensation, and without the need of intermediate substations. An example of its application is the natural medium term option for the Brazilian electric sector, leading to base its growth in the hydroelectric resources of Amazon basin, with moderate complementary generation based in other sources. This choice imposes an adequate solution to transmit most of such energy at distances of the order of 2500 km. The proposed solution type has been carefully studied and was object of robust validation procedures. It was presented in several forums and was proposed, a few years ago, to responsible agencies, to study it as an alternative to compare objectively with other ones for Madeira Transmission System. However, although no technical contrary argument was given, the alternative was, in fact, ignored, by “responsible agencies”. It has also shown very important advantages, namely in comparison with the “traditional” type solution, that has been applied in recent transmission systems in Brazil, and with all the alternatives included in R1 document, prepared by responsible agencies, for Madeira Transmission System, as discussed briefly in this article and, with more detail, in [1-22]. It is important to notice that, when doing the comparison of the proposed methodology with the alternatives proposed in R1 document, for Madeira Transmission System, we have found several important aspects of such alternatives that imply in important technological risks, including [21-22]: - Several consequences of the conceptual aspects of such alternatives, which imply in important risk of operational problems, with reliability consequences, and whose “correction” is not trivial and may result in the necessity of improvement measures, with eventual large costs and delays. - Lack of specification precautions, for several important technological aspects of the R1 alternatives, namely related to the very long length of the transmission system, to the important relative variation of available generation power of Madeira power stations and to single pole operating constraints. - Problems occurred in power transmission equipment that have not been adequately solved or corrected by the electric sector, but that must be duly studied and object of efficient actions that assure an adequate quality of important transmission systems. 10 BIBLIOGRAPHY [*] [1] C. Portela – “Brazilian Electric System – Realities and Options” (in Portuguese) – Symposium Prof. Carlos Portela 70 years; The Science in Electrical Engineering, 60 p., December 2005 (reproduced in [21]) [2] C. Portela, M. Tavares – “Modeling, Simulation and Optimization of Transmission Lines. Applicability and Limitations of Some Used Procedures” – Transmission and Distribution 2002, IEEE - PES Society, 38 p., Invited speech, http://www.ieee/pesTD2002, São Paulo, Brazil, March 2002 [3] C. Portela, M. Aredes – “Very Long Distance Transmission” – Proceedings 2003 International Conference on AC Power Delivery at Long and Very Long Distances, pp. 385-394, Novosibirsk, Russia, September 2003 [4] C. Portela, M. Tavares – “A New Methodology to Optimize Large EHV-Transmission System Transient Studies” – Proceedings 2003 International Conference on AC Power Delivery at Long and Very Long Distances, pp. 444-454, Novosibirsk, Russia, September 2003 [5] M. Aredes, E. Emmerik, R. Dias, C. Portela – “Facts Applied to Very Long Distance Transmission Lines” – Proceedings 2003 International Conference on AC Power Delivery at Long and Very Long Distances, pp. 395-403, Novosibirsk, Russia, September 2003 [6] M. Aredes, E. Sasso, E. Emmerik, R. Dias, C. Portela – “The GTO-Controlled Series Capacitor Applied to HalfWave Length Transmission Lines” – Proceedings International Conference on Power Systems Transients (IPST’ 2003), pp. 1-6, New Orleans, United States, September/October 2003 [7] C. Portela, M. Tavares – “Six-Phase Transmission Line . Propagation Characteristics and New Three-Phase Representation” – IEEE Transactions on Power Delivery, vol. 8, nº 3, pp. 1470-1483, July 1993 [8] C. Portela, G. Moreno, M. Tavares – “Advantages of Six-Phase Transmission as Compared with Three-Phase Transmission Concerning Environmental Impact” – Eighth International Symposium on High Voltage Engineering, ISHVE, Yokohama, Japan, Proceedings, art. 91.04, vol.4, pp. 349-352, August 1993 [9] C. Portela – “Some Aspects of Very Long Lines Switching” – CIGRE SC 13 Colloquium 1995, Florianópolis, art. 2.2, 12 p., September 1995 [10] C. Portela, S. Gomes – “Analysis and Optimization of Non-conventional Transmission Trunks, Considering New Technological Possibilities” – VI SEPOPE, Symposium of Specialists in Electric Operational and Expansion Planning, SP-092, pp. 1-6, Salvador, BA, Brazil, May 1998 [11] E. Watanabe, M. Aredes, C. Portela – Electric Energy and Environment: Some Technological Challenges in Brazil – chapter of book Energy and Environment - Technological Challenges for the Future - editors Y. H. Mori, K. Ohnishi - Springer - ISBN 4-431-70293-8 Springer-Verlag, p. 10-40, 2000 [12] C. Portela – “Six-Phase Transmission Systems . Functional Characteristics and Potential Application Domains” (in Portuguese) – X SNPTEE, Curitiba, Brazil, art. CTBA/GSP/27, 8 p., October 1989 [13] C. Portela, M. Tavares – “Behavior and Optimization of a Six-Phase Transmission System for Normal Operation and Transient Phenomena” (in Portuguese) – XI SNPTEE, Rio de Janeiro, Brazil, art. RJ/GAT/20, 6 p., October 1991 [14] S. Gomes, C. Portela, C. Fernandes – “Principles and Advantages of Using LPNEs and Comparative Results” (in Portuguese) – XIII SNPTEE, Florianópolis, SC, Brazil, art. FL/GLT/23, 6 p., October 1995 [15] C. Portela – “A Computational System for Optimization of Non-Conventional Transmission Lines (LNC)” (in Portuguese) – XIV SNPTEE, Belém, Pará, Brazil, 6 p., October 1997 [16] C. Portela – “Present Situation and Perspectives of Brazilian Electric Sector – Perturbations and Risks of Panaceas and Wishes to Control Complex Physical Systems with Rules of Speculative Games” (in Portuguese) – 58th Annual Meeting of SBPC – Technological Symposium – Power Systems Control – The Electric Energy and the Brazil Development – Florianópolis, SC, Brazil, pp. 1-28, available at www.labspot.ufsc.br and in [21], 16-21 July 2006 [17] C. Portela. – Overvoltages and Insulation Coordination (in Portuguese), Vols. I, II, III - Vol. I, 349 p. , Vol. II, 304 p. , Vol. III, 140 p. - edition COPPE/UFRJ, Rio de Janeiro, 1982 [18] Portela, C. – Transient Regimen (in Portuguese), Vol. I, II, III, IV - Vol. I, 357 p. , Vol. II, 365 p. , Vol. III, 318 p. , Vol. IV, 280 p. - edition COPPE/UFRJ and ELETROBRÁS, Rio de Janeiro, 1983 [19] C. Portela, J. Silva, M. Alvim – “Non-Conventional AC Solutions Adequate for Very Long Distance Transmission ‒ An Alternative for the Amazon Transmission System” – IEC/CIGRE UHV Symposium Beijing 2007-07-18/21, article 2-2-5, 29 p. – Beijing, China, 18-21 July 2007 [20] C. Portela, M. Alvim – “Non-Conventional AC Solutions Adequate for Very Long Distance Transmission ‒ An Alternative for the Amazon Transmission System” (in Portuguese) – Seminar Transmission of Electric Energy at Long Distance, 30 p. – Recife, Brazil, 05 October 2007 [21] Documents related to the presented alternative, including pdf versions of part of previous references – http://www.pee.ufrj.br/labs/corona/portela/lnc.html [22] Documents presented and discussed in a Seminar about the presented alternative – Amazonian Hydroelectric Resources – Non-conventional Alternatives for the Transmission Trunks - COPPE/UFRJ, 21 July 2008 http://www.pee.ufrj.br/labs/corona/portela/seminario20080721/seminario.html [*] – Part of the indicated references are reproduced, in pdf version, in [21] and [22]. Acknowledgement The author thanks the support received from CNPq National Council of Scientific and Technological Development (Brazil) in part of research work in which this article is based. 11