Test Requirements for Electrical / Electronic Equipment and Systems

advertisement
VI
Rules for Classification and Construction
Additional Rules and Guidelines
7
Guidelines for the Performance of Type Approvals
2
Test Requirements for Electrical / Electronic Equipment and Systems
Edition 2012
The following Guidelines come into force on 1 September 2012.
Alterations to the preceding Edition are marked by beams at the text margin.
Germanischer Lloyd SE
Head Office
Brooktorkai 18, 20457 Hamburg, Germany
Phone: +49 40 36149-0
Fax: +49 40 36149-200
headoffice@gl-group.com
www.gl-group.com
"General Terms and Conditions" of the respective latest edition will be applicable
(see Rules for Classification and Construction, I - Ship Technology, Part 0 - Classification and Surveys).
Reproduction by printing or photostatic means is only permissible with the consent of
Germanischer Lloyd SE.
Published by: Germanischer Lloyd SE, Hamburg
Table of Contents
VI - Part 7
GL 2012
Chapter 2
Page 3
Table of Contents
Section 1
A.
B.
C.
D.
Section 2
A.
B.
Section 3
A.
B.
General Conditions
Scope ..........................................................................................................................................
Reference to other Rules and Regulations ..................................................................................
Definitions ..................................................................................................................................
Documents for Submission .........................................................................................................
1111-
1
1
1
1
Requirements to be met by the Products
General .......................................................................................................................................
Environmental Categories ..........................................................................................................
2- 1
2- 1
Test Requirements
General .......................................................................................................................................
Tests ...........................................................................................................................................
1. Visual inspection ...............................................................................................................
2. Performance test ................................................................................................................
3. Power supply failure ..........................................................................................................
4. Power supply variations .....................................................................................................
5. Cold ...................................................................................................................................
6. Dry heat .............................................................................................................................
7. Damp heat ..........................................................................................................................
8. Salt mist .............................................................................................................................
9. Vibrations ..........................................................................................................................
10. Inclinations ........................................................................................................................
11. Flammability ......................................................................................................................
12. Pressure test .......................................................................................................................
13. Insulation resistance ...........................................................................................................
14. High voltage .......................................................................................................................
15. Electrostatic discharge .......................................................................................................
16. Electromagnetic fields .......................................................................................................
17. Conducted fast transients (burst) ........................................................................................
18. Conducted high frequency interference .............................................................................
19. Conducted slow transients (surge) .....................................................................................
20. Conducted low frequency interference (harmonics) ..........................................................
21. Conducted emissions .........................................................................................................
22. Radiated emissions from enclosure port ............................................................................
3- 1
3- 1
3- 1
3- 2
3- 2
3- 2
3- 3
3- 4
3- 4
3- 5
3- 6
3- 8
3- 8
3- 9
3- 10
3- 10
3- 10
3- 12
3- 14
3- 14
3- 16
3- 18
3- 20
3- 20
VI - Part 7
GL 2012
Section 1
D
General Conditions
Chapter 2
Page 1–1
Section 1
General Conditions
A.
Scope
1.
These Guidelines apply to electrical, electromechanical and electronic equipment, computers and
peripherals.
2.
The scope of the tests required for a specific
product will be determined on a case by case basis by
GL depending on the product, its use and the environmental category to which it belongs.
3.
GL reserve the right, in justifiable cases, to
request the performance of additional tests.
4.
Electrical and electronic equipment on board
ships, required neither by classification rules nor by
international conventions, liable to cause electromagnetic disturbance shall be of a type which fulfils the
test requirements of Section 3, B.21 and B.22.
C.
Definitions
1.
Electric/electronic equipment
Electric/electronic equipment are products such as
systems, appliances or components which consist of
mechanical, electrical and electronic parts and combinations thereof.
2.
Computer systems are equipment or systems such as
PC, workstation or programmable controls which specific functions are designated by application software.
3.
Reference to other Rules and Regulations
1.
These Guidelines are based on the IACS Unified Requirements E10, "Testing Procedure for Electrical, Control and Instrumentation Equipment, Computers and Peripherals covered by Classification".
2.
In connection with these Guidelines also apply the GL Guidelines for Procedure (VI-7-1) as well
as the GL Rules for Electrical Installations (I-1-3) and
Automation (I-1-4).
3.
Navigation and radiocommunication equipment and systems will be tested and approved in accordance with IEC publication 60945 "Maritime navigation and radiocommunication equipment and systems, General requirements, Methods of testing and
required test results".
The relevant test and performance standards for specific equipment and systems like SOLAS 74 as ammended, IMO instruments and IEC or ISO Publications are to be observed.
4.
Other standards may be recognised, provided
that they are equivalent or higher graded.
Peripherals
Peripherals are devices such as monitors, keyboards,
sensors or actuators which are necessary for process
monitoring and control.
4.
B.
Computer systems
Equipment subject to type approval
Equipment subject to type approval refers to all products (systems, appliances and components) identified
as such in the relevant Rules for Classification and
Construction.
5.
Environmental categories
Classification of equipment on the basis of the expected environmental conditions, with regard to the
necessary test conditions (temperature, relative humidity, vibrations).
D.
Documents for Submission
1.
Documents shall be submitted in accordance
with the GL Guidelines for Procedure (VI-7-1), Section 3, B.
2.
In addition, in the case of computers and
computer systems, documents shall be submitted in
accordance with the GL Rules for Electrical Installations (I-1-3), Section 10.
3.
The lists contained in the above Regulations
are by way of example. If necessary, further documents may be required.
VI - Part 7
GL 2012
Section 2
B
Requirements to be met by the Products
Chapter 2
Page 2–1
Section 2
Requirements to be met by the Products
A.
General
The requirements to be met by the products in terms
of design, choice of materials, functions and operational conditions are set out in the relevant Rules for
Classification and Construction and associated Guidelines.
B.
Environmental Categories
The products will be allocated to the environmental
categories A to H.
The assignment of the environmental categories to the
test conditions is specified in Section 3, Table 3.34.
VI - Part 7
GL 2012
Section 3
B
Test Requirements
Chapter 2
Page 3–1
Section 3
Test Requirements
A.
General
1.
Choice of equipment under test
In the case of series-manufactured products, the
equipment under test (EUT) shall be taken from the
current production cycle. The choice of equipment
under test shall be agreed with GL.
Example of use:
Equipment subject to the Rules for Classification and
Construction except for the tests "Electrostatic Discharge, Conducted fast transients (burst) and Conducted slow transients (surge) ".
–
The EUT shall continue to operate as intended
after the test. No degradation of performance or
loss of function is allowed, as defined in the relevant equipment standard in the technical specification published by the manufacturer. During the
test, degradation or loss of function or performance which is self-recoverable is, however, allowed, but no change of actual operating state or
stored data is allowed.
If the equipment under test is a prototype, GL reserve
the right to carry out subsequent comparative tests on
series-manufactured products.
2.
Test sequence
There is no pre-defined test sequence. Before the start
of the tests, the manufacturer shall determine the
sequence and notify GL accordingly.
All the tests required for the product shall be performed on one equipment under test. Any alternative
arrangements are subject to consent.
3.
Procedure of immunity tests to electromagnetic environment
For these tests the EUT shall conform to its normal
operational configuration, mounting and earthing
arrangements and shall operate under mentioned test
conditions.
Example of use:
Equipment not subject to the Rules for Classification
and Construction and the tests "Electrostatic Discharge, Conducted fast transients (burst) and conducted slow transients (surge)" for equipment subject
to the Rules.
–
Common mode tests (line/earth) are those applied
between groups of lines and a common reference,
normally earth.
For the tests the results are evaluated against performance criteria relating to the operating conditions
and functional specifications of the EUT, and defined
as follows:
–
performance criterion A:
The EUT shall continue to operate as intended
during and after the test. No degradation of performance or loss of function is allowed, as defined in the relevant equipment standard and in
the technical specification published by the
manufacturer.
performance criterion C:
Temporary degradation or loss of function or
performance is allowed during the test, provided
the function is self-recoverable, or can be restored at the end of the test by the operation of
the controls, as defined in the relevant equipment
standard and in the technical specification published by the manufacturer:
Particular interfaces of the EUT with the external
electromagnetic environment are referred to as ports.
The physical boundary of the EUT through which
electromagnetic fields may radiate or impinge is the
enclosure port.
Differential tests (line/line) are those applied between
electrical power, signal and control lines.
performance criterion B:
Example of use:
Equipment not subject to the Rules for Classification
and Construction.
B.
Tests
1.
Visual inspection
The equipment under test is tested for conformity with:
–
GL Rules for Classification and Construction and
Additional Rules and Guidelines
–
the manufacturer's specifications
–
the design drawings
–
the specified standards
Chapter 2
Page 3–2
1.1
Section 3
B
Test Requirements
Test procedure
3.
Not specified
1.2
Test conditions
General instructions for test performance
The visual inspection is carried out before commencement of type approval and shall be repeated as
necessary after each stage of the test with a view to
detecting visible damage to the equipment under test.
1.4
Test result
The test is deemed to have been passed if the equipment under test meets the requirements of GL Rules
for Classification and Construction and Regulations,
as well as the requirements of the specification and
the documentation and does not show evidence of
any visible damage.
2.
Test conditions
The tests are performed at the rated operational voltage Ue.
Not specified
3.2
External environmental conditions in
the test laboratory
Temperature
Relative humidity
Atmospheric pressure
+ 15 °C to + 35 °C
30 % to 90 %
860 hPa to 1060 hPa
General instructions for test performance
The functions to be tested shall be performed in accordance with the requirements of GL Rules for Classification and Construction and Regulations and the
characteristic features of the equipment under test.
International testing standards for specific equipment
e.g. measuring relays and protection equipment are to
be observed and may require additional testing.
2.4
Test conditions
In the case of electrical components, the tests are performed at the rated operational voltage Ue and, in the
case of hydraulic/pneumatic components, at the rated
control pressure.
–
3 interruptions within a 5-minute period
–
30 s pause between switching off and switching
back on.
3.3
General instructions for test performance
None
3.4
Test result
The test is deemed to have been passed if the specified functions are demonstrated, the results fall within
the specified tolerance limits and no damage to the
equipment under test is detected.
Test result
The test is deemed to have been passed if the specified
functions are demonstrated, the results fall within the
specified tolerance limits and no damage to the equipment under test is detected.
4.
Table 3.1
2.3
Test procedure
Test procedure
Basis: Rules for Classification and Construction,
product specification.
2.2
3.1
Performance test
The functions (switching points, characteristic
curves, self-monitoring, etc.) are to be demonstrated.
2.1
Power supply failure
This test serves to demonstrate that on restoration of
the power supply no damage is caused to the equipment under test and malfunctions occur.
According to the environmental category
1.3
VI - Part 7
GL 2012
Power supply variations
This test serves to demonstrate that in the event of
power supply variations no damage is caused to the
equipment under test and no permanent or temporary
malfunctions occur.
4.1
Procedure
Not specified
4.2
Test conditions
In the case of electrical components, the basis for the
tests is the rated operational voltage Ue and, in the case
of hydraulic/pneumatic components, the rated control
pressure, in accordance with the equipment specification.
Voltage- and frequency deviations refer to the system
nominal voltage and frequency. The range of the system nominal voltage and frequency within the test
conditions are fulfilled shall be specified.
VI - Part 7
GL 2012
Section 3
Table 3.2
Electrical supply
(alternating current)
B
Test Requirements
4.4
Voltage deviation
(permanent)
Frequency deviation
(permanent)
+ 6%
+ 5%
+ 6%
– 5%
– 10 %
– 5%
– 10 %
+ 5%
Voltage deviation
(short-term, 1,5 s)
Frequency deviation
(short-term, 5 s)
+ 20 %
+ 10 %
– 20 %
– 10 %
Table 3.3
Chapter 2
Page 3–3
Electrical supply
(rectified alternating current)
Voltage deviation (permanent)
The test is deemed to have been passed if the specified
functions are demonstrated, the results fall within the
specified tolerance limits and no damage to the equipment under test is detected.
5.
5.1
Voltage deviation
+ 30 %
Test procedure
Basis: IEC publication 60068-2-1
–
Test A): for products inside the ship
–
Test B): for products on the open deck or in
cold areas.
± 10 %
Electrical battery supply for equipment connected to the battery during
charging
Cold
This test serves to demonstrate that under the influence
of cold no damage is caused to the equipment under
test and no permanent or temporary malfunctions occur.
5.2
Table 3.4
Test result
Test conditions
The functional tests are performed at the rated operational voltage Ue.
Table 3.7
– 25 %
Table 3.5
Electrical battery supply for equipment not connected to the battery
during charging
Voltage deviation
A) Products installed inside the ship
Test chamber conditions (Fig. 3.1)
Temperature
5 °C ± 3 °C
Test duration
2h
Table 3.8
B) Products installed on the open deck
or in cold areas
+ 20 %
– 25 %
Table 3.6
Pneumatic/hydraulic power supply
Control pressure deviation
+ 20 %
– 20 %
Test duration: 15 minutes per test
4.3
General instructions for test performance
If the test duration is not specified, the test shall be
performed until such time as a stationary condition is
achieved.
Test chamber conditions (Fig. 3.1)
Temperature
– 25 °C ± 3 °C
Test duration
2h
5.3
General instructions for test performance
Before commencing the test an insulation resistance
measurement shall be taken in accordance with test
No. 13.
The equipment under test is placed in the test chamber
at room temperature and remains connected, but not
switched on, during the cooling phase and throughout
the test. During the final 60 minutes of the test functional tests shall be performed at test temperature.
Section 3
Chapter 2
Page 3–4
Test Requirements
B
Once the test is complete and the equipment under
test has reached room temperature once again, a further functional test shall be performed, as well as, as
a retest, the insulation resistance measurement in
accordance with test No. 13.
VI - Part 7
GL 2012
Table 3.10
Test chamber conditions (Fig. 3.2)
70 °C ± 2 °C
Temperature
30
≤ 50 %
Relative humidity at test temperature
20
10
5 °C Test
Test duration after the EUT has
reached the test temperature
0
16 h
-10
-20
- 25 °C Test
6.3
-30
0
0,5
1
1,5
2
2,5
3
3,5
Hours [h]
Fig. 3.1 Cold test cycle
5.4
During the final 60 minutes of the test functional tests
shall be performed
Test result
The test is deemed to have been passed if the specified functions are demonstrated, the values of the
insulation resistance measurement fall within the
specified tolerance limits and no damage to the
equipment under test is detected.
6.
Dry heat
This test serves to demonstrate that under the influence of dry heat no damage is caused to the equipment under test and no permanent or temporary malfunction occur.
6.1
Test procedure
Once the equipment under test has reached room temperature once again a further functional test shall be
performed.
80
–
Test A): products without increased heat stress
–
Test B): products with increased heat stress or
on the open deck.
Test conditions
70 °C Test
70
55 °C Test
60
50
40
30
16 h
20
10
0
0
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15 16 17 18 19 20
Hours [h]
Fig. 3.2 Dry heat test cycle
6.4
Basis: IEC publication 60068-2-2
6.2
General instructions for test performance
The equipment under test is placed in the test chamber
at room temperature and remains connected and
switched on throughout the test.
Temperature [°C]
Temperature [°C]
B) Products installed in areas with
increased heat stress or on the
open deck
Test result
The test is deemed to have been passed if the specified
functions are demonstrated, the results fall within the
specified tolerance limits and no damage to the equipment under test is detected.
7.
Damp heat
The functional tests are performed at the rated operational voltage Ue.
This test serves to demonstrate that under the influence
of damp heat no damage is caused to the equipment
under test and no permanent or temporary malfunctions
occur.
Note
7.1
Equipment to be mounted in consoles or
switchboards together with other equipment shall be
tested in accordance with test B).
Basis: IEC publication 60068-2-30
–
Test Db
7.2
Table 3.9
A) Products installed in areas without increased heat stress
Test chamber conditions (Fig. 3.2)
Temperature
Relative humidity at test temperature
Test duration
55 °C ± 2 °C
≤ 50 %
16 h
Test procedure
Test conditions
The functional tests are performed at the rated operational voltage Ue.
Table 3.11
Test chamber conditions (Fig. 3.3)
Temperature
Relative humidity
Test duration
1 For tolerances see Fig. 3.3
55 °C ± 2 °C
95 % 1
2 test cycles 2 × (12 + 12 h)
VI - Part 7
GL 2012
7.3
Section 3
B
Test Requirements
Chapter 2
Page 3–5
Once the equipment under test has reached room temperature once again a further functional test shall be
performed, as well as, as a retest, the insulation resistance measurement in accordance with test No. 13.
General instructions for test performance
Before commencing the test an insulation resistance
measurement shall be taken in accordance with test
No. 13.
7.4
The equipment under test is placed in the test chamber at room temperature. The test should start before
the first cycle with a stabilizing period with 25 °C
± 3 °C and at least 95 % humidity for maximum
1 hour remains connected and switched on throughout the first test cycle. During the second test cycle
the equipment under test is switched off except for
the functional tests.
The test is deemed to have been passed if the specified
functions are demonstrated, the results fall within the
specified tolerance limits and no damage to the equipment under test is detected.
8.
Relative
humidity [%]
90
96 %
95 %
95 %
90 %
80
60
Salt mist
This test serves to demonstrate that under the influence
of a saline atmosphere no damage (corrosion) is caused
to the components of the equipment under test and no
functional affections occur. This test is only performed
on products which are to be installed on the open deck
area.
Functional tests shall be performed at test temperature within the first 2 hours of the first and the last
2 hours of the second test cycle.
100
Test result
15 min
± 15 min
80 %
Functional tests
2h
Functional tests
2h
+57 °C
55
+53 °C
50
Temperature [°C]
40
Functional tests
2h
30
+28 °C
25
20
10
3h
12 h
± 0,5 h
± 0,5 h
+22 °C
3h
6h
EUT connected and switched on
EUT connected and switched off
except for functional tests
1 cycle = 24 h
1 cycle = 24 h
6
12
18
24
30
Hours [h]
Fig. 3.3 Damp heat test cycle
36
42
48
Section 3
Chapter 2
Page 3–6
8.1
B
Test Requirements
the insulation resistance measurement fall within the
specified tolerance limits.
Test procedure
Basis: IEC publication 60068-2-52
–
VI - Part 7
GL 2012
Test Kb
9.
Vibrations
The functional tests are performed at the rated operational voltage Ue.
This test serves to demonstrate that under the influence of external initiated vibrations no damage is
caused to the equipment under test and no permanent
or temporary malfunctions occur.
Table 3.12
9.1
8.2
Test conditions
Basic requirements
Test procedure
Basis: IEC publication 60068-2-6
Severity level
1
Number of sprayings
4
Storage period in damp
chamber
Table 3.13
Spray chamber conditions
Spray duration
2 hours
+ 25 °C ± 10 °C
Temperature
Saline solution
Table 3.14
7 days, after each spraying
5 % sodium chloride
(NACl);
pH value 6,5 % to 7,2 % at
20 °C ± 2 °C
–
9.2
Test Fc
Test conditions
The functional tests are performed at the rated operational voltage Ue.
Equipment under test with a mass of ≥ 100 kg for
characteristic curve 1 or ≥ 10 kg for characteristic
curves 2a/b can be tested with reduced acceleration
values, but the acceleration values may not be smaller
than 0,35 g for characteristic curve 1 and 0,7 g for
characteristic curve 2. The requirements shall be
agreed with GL.
Table 3.15
General vibration strain
(characteristic curve 1)
Vibration strain (Fig. 3.4)
Damp chamber conditions (storage)
Displacement
Temperature
Relative humidity
40 °C ± 2 °C
93 % + 2 % / – 3 %
2 (+ 3 / – 0) Hz up to 13,2
Hz
8.3
0,7 g
max. 1 oktave / minute
General instructions for test performance
Before commencing the test an insulation resistance
measurement shall be taken in accordance with test
No. 13 and a functional test shall be performed.
During the test the equipment under test is connected
but is not switched on. The test consists of 4 sprayings
and 7 days' storage period functional tests shall be
performed.
The characteristic curve 1 applies to equipment and
components which, in view of their mounting position,
do not have to meet stringent requirements.
Table 3.16
On completion of the test a functional test is performed and an insulation resistance measurement
taken in accordance with test No. 13 and the condition
of the equipment under test is evaluated (visual inspection).
Test result
The test is deemed to have been passed if the equipment under test exhibits no visible corrosion, the
specified functions are demonstrated and the values of
High vibration strain
(characteristic curve 2a)
Vibration strain (Fig. 3.4)
On the 7th day of each storage period functional tests
shall be performed.
8.4
± 1,0 mm
13,2 Hz up to 100 Hz
Sweep rate
Acceleration
Displacement
2 (+ 3 / – 0) Hz up to 25 Hz
25 Hz up to 100 Hz
Sweep rate
Acceleration
± 1,6 mm
4g
max. 1 oktave / minute
The characteristic curve 2a applies to equipment and
components operated on compressors or in the steering gear compartment, as well as under other comparable mounting conditions.
VI - Part 7
GL 2012
Section 3
B
Test Requirements
Chapter 2
Page 3–7
amax = 2,5 mm
amax = 1,6 mm
amax = 1,0 mm
1
Curve 3
Curve 1
2485
a = _____
f2
175
a = _____
f2
Curve 4
Amplitude a [mm]
0,1
570
a = _____
f2
Curve 2a/2b
1000
a=
f2
2b = 2a +
0,01
0,001
0,0006
1
10
1000
100
Frequency f [Hz]
Fig. 3.4 Vibration curve
Table 3.17
High vibration strain (curve 2b)
Table 3.18
Vibration strain (Fig.. 3.4)
Displacement
2 (+ 3 / – 0) Hz to 25 Hz
25 Hz to 300 Hz
Sweep rate
Extreme vibration strain
(characteristic curve 3)
Vibration strain (Fig. 3.4)
Acceleration
± 1,6 mm
4,0 g
max. 1 octave/minute
Temperature
Acceleration
40 Hz up to 2000 Hz
600 °C
10,0 g
Sweep rate
max. 1 oktave/ minute
The characteristic curve 2b applies for electric and
electronic equipment mounted on combustion engines.
The characteristic curve 3 applies to equipment and
components installed on the exhaust gas pipes of die-sel
engines, especially for medium and high speed engines.
The minimum strain is:
This test applies only for new equipment after the
2 January 2013 and shall be performed at a temperature of 90 °C.
If even more severe vibration strain is expected at the
location in question, the latter shall be considered for
the test.
Chapter 2
Page 3–8
Table 3.19
Section 3
B
Test Requirements
Vibration strain on masts
(characteristic curve 4)
VI - Part 7
GL 2012
Table 3.20
Inclinations
Static
Dynamic
Vertical
± 22,5 °
up to ± 22,5 ° 1
Horizontal
± 22,5 °
up to ± 22,5 ° 1
Rolling period
−
10 seconds
Test duration per level
2
min. 15 minutes
Vibration strain (Fig. 3.4)
Displacement
2 (+ 3 / – 0) Hz up to 15 Hz
15 Hz up to 50 Hz
Sweep rate
Acceleration
± 2,5 mm
2,3 g
max. 1 oktave / minute
The characteristic curve 4 applies to equipment and
components installed on masts.
9.3
General instructions for test performance
The equipment under test is fastened by means of its
fastening devices in its normal mounting position in
accordance with the manufacturer's instructions.
The tests are performed in three mutually perpendicular axes (X:Y:Z).
During the tests the functions shall be demonstrated
on the equipment under test.
At the start of the test the points of resonance of each
axis are determined.
If points of resonance are determined at tests according to curve 1, 2 and 4 on the equipment under test
which have an amplification factor Q < 2, the test
duration is 90 minutes per axis at a frequency of 30
Hz. For tests according to curve 3 a sweep over the
complete frequency range with a duration of 120
minutes has to be performed in that case.
If points of resonance are determined on the equipment under test which have an amplification factor
Q ≥ 2, the test duration is 90 minutes per resonance
frequency.
In the case of several resonance frequencies are detected close to each other a sweep test can be chosen.
The test duration is 120 minutes.
9.4
Test result
The test is deemed to have been passed if the specified functions are demonstrated, the results fall within
the specified tolerance limits and no damage to the
equipment under test is detected.
10.
Inclinations
The functional tests are performed at the rated operational voltage Ue.
General instructions for test performance
Test result
The test is deemed to have been passed if the specified functions are demonstrated, the results fall within
the specified tolerance limits and no damage to the
equipment under test is detected.
11.
Flammability
The flammability test is applicable to electrotechnical
equipment, its sub-assemblies and components and to
solid electrical insulating materials or other combustible materials. The tests serves to demonstrate that
the fire hazard inside of electrotechnical equipment
(end-products) by an electrically induced ignition is
minimized and a propagation of fire is limited to the
inner housing of the electrotechnical equipment
11.1
Test procedure
The following tests for the provision of the fire hazard should be performed after coordination with GL:
–
Test conditions
The duration of the test should be sufficient to allow the behaviour of the equipment under test to be evaluated.
10.4
10.1
10.2
2
The equipment under test is fastened by means of its
fastening devices in its normal mounting position in
accordance with the manufacturer's instructions.
–
Not specified
On ships for the carriage of liquefied gases and chemicals, the
emergency power supply is to remain operational up to a
maximum athwart ship inclination of ± 30°.
10.3
This test serves to demonstrate that under the influence of inclinations the equipment under test remains
operational and no unintentional switching operations
or functional changes occur.
Test procedure
1
glow-wire test to according to
IEC Publication 60695-2-11
needle-flame test according to
IEC Publication 60695-11-5
Alternatively material specific according to IEC
60695-11-10, UL 94 or IEC 60695-2-12 may be
accepted.
VI - Part 7
GL 2012
11.2
Section 3
B
Test Requirements
When flames were emitted during the glow-wire test,
additional tests according to the above mentioned
IEC e.g. with needle flame may be required.
Test conditions
Table 3.21
Flammability
Test
IEC 60695-11-5
Test
IEC 60695-2-11
3
1
12 mm ± 1 mm
– 960 °C
45° from the
Horizontal
Vertical
30 seconds
30 seconds
1
3
EUT
EUT
Number of
specimen
Flame length
Angle of
application
Test duration per
test specimen
Number of
flames
Test specimen
11.3
The test is considered passed if no flame or no incandescence have occurred or
–
any flames or glowing on the test specimen
extinguish not later than 30 seconds after removal of the glow-wire
–
no ignition of the silk paper while dripping of
the material
11.4.3
General instructions for test performance
The needle flame test is used to simulate the effect of
small flames that may arise in malfunctioning electrical equipment. A 12 mm high flame held at a 45°
angle is applied to the base of the EUT for a specified
period of time. Tissue paper is laid out 200 mm beneath the test specimen. The needle flame test should
be used only for small parts.
The glow-wire test is used to evaluate the risk of fire
hazard. Cover and non-conducting material should be
tested at 960 °C ±10 °C for 30 s.
11.4
Test result
11.4.1
Test according to IEC 60695-11-5
The test is deemed to have been passed if the following conditions are observed on the plastic components of the equipment under test (housing, coverings):
–
no flame, no incandescence or
–
in the event of a flame or incandescence being
present, it shall extinguish itself within 30 s of
the removal of the needle flame without full
combustion of the test specimen.
Any dripping material shall extinguish itself in
such a way as not to ignite a wrapping tissue.
The drip height is 200 mm ± 5 mm.
11.4.2
Chapter 2
Page 3–9
Test according to IEC 60695-2-11
The glow-wire test should not be used for small
equipment or components, as listed in the above
mentioned testing standard. Small equipment or
components should be tested with the needle-flame
test in 11.4.1.
Test material specific
Classification V-0 and V-1 according to IEC 6069511-10 or UL 94 may be accepted depending on the
thickness of the material is the same as on the test
specimen.
V-2 classified material should be additionally tested
by the needle flame test.
The glow wire flammability index GWFI according
to IEC Publication 60695-2-12 should be 850 °C or
higher at the related thickness of the material.
12.
Pressure test
This test serves to demonstrate that components of
electrical equipment exposed to pneumatic or hydraulic also withstand such pressures.
12.1
Test procedure
Basis:
GL Guidelines Test Requirements for Components
and Systems of Mechanical Engineering and Offshore Technology (VI-7-8)
12.2
Test conditions
Pressure and tightness tests are to be performed at
room temperature. For the burst pressure test the test
specimen is to be subjected to a continuously raised
pressure up to the test pressure.
12.3
General instructions for test performance
During the test the equipment under test is connected
and switched on.
12.4
Test results
The test is deemed to have been passed if no permanent deformations or other damages occur on the
pressurized parts at the specimen and if no inadmissible leakages on the body or the closures can be detected.
The burst pressure test is deemed to have been passed
if the test pressure can be maintained over the test
duration without leakage and if no other damage can
be detected on the test specimen.
Chapter 2
Page 3–10
Table 3.22
Section 3
B
Test Requirements
VI - Part 7
GL 2012
Pressure tests
Pressure test
Tightness test of the closure
Burst pressure test
Test pressure
1,5 × nominal pressure
Nominal pressure
4 × nominal pressure or
maximum allowable working
pressure
Test medium
Water or water-oil emulsion
Water or water-oil emulsion
Water or water-oil emulsion
Test duration
2 min
2 min
2 min
13.
Insulation resistance
14.1
This test serves to demonstrate that the insulation
resistance at the electrical connections of the equipment under test remains within the specified tolerance
limits. The insulation resistance shall be measured
before and, as a test, subsequent to the following tests:
–
–
–
–
cold (Test No. 5)
damp heat
(Test No. 7)
salt mist (Test No. 8)
high voltage (Test No. 14)
13.1
Test procedure
Not specified
14.2
Test conditions
The test is performed with alternating current at 50 Hz
or 60 Hz.
Table 3.24
Rated operational voltage
Ue [V]
Test voltage
Ueff [V]
up to
2 × Ue + 500
Test procedure
Not specified
13.2
Test conditions
Table 3.23
Insulation resistance
Min. insulation
resistance
Rated
operational
voltage
Ue
Test voltage
[AC/DC]
[DC]
before
[MΩ]
after
[MΩ]
≤ 65 V
2 × Ue, min.
24 V
10
1
> 65 V
500 V
100
10
13.3
General instructions for test performance
Where practicable, the test is performed on all connections as follows:
–
–
all connections in relation to frame potential
connections against each other
Certain components e.g. for EMC protection may be
required to be disconnected for this test
13.4
Test results
The test is deemed to have been passed if the values
are not lower than those specified in the table.
14.
High voltage
This test serves to demonstrate that the dielectrical
characteristics at the electrical connections of the
equipment under test meet the requirements of the test
standard, against each other and in relation to the
frame potential.
High voltage
65
66
up to 250
1500
251
up to 500
2000
501
up to 690
2500
Test duration
14.3
1 minute per test
General instructions for test performance
The test is performed on all connections with a corresponding test voltage, for each voltage potential:
–
–
connections against each other
whereby all connections of equal potential are
interconnected
The following applies to equipment fitted with protective circuit:
Application of the test voltage may activate the surge
protection devices, which shall disconnect the test
voltage. Once the rated operational voltage has been
switched on, the equipment under test shall be restored
to operation without the need for replacement parts.
If so, printed circuits with electronic components may
be removed during the test.
14.4
Test results
The test is deemed to have been passed if no flashover
is observed.
15.
Electrostatic discharge
This test serves to demonstrate that under the influence of electrostatic discharges no damage is caused
to the equipment under test and no permanent malfunctions occur.
VI - Part 7
GL 2012
Section 3
Table 3.25
Electrostatic discharge
B
Test Requirements
15.2
Contact
discharge
Severity level
6 kV
Test duration per test point
8 kV
min. 10 individual discharges
per polarity
Time between individual
discharges
min. 1 second
Wave form parameters
– first peak current of
discharge
– rise time
– current at 30 ns
– current at 60 ns
15.1
Air
discharge
3
Test voltage
Chapter 2
Page 3–11
22,5 A
Test conditions
During the test, the equipment under test is operated at
its rated operational voltage Ue.
15.3
General instructions for test
performance
The tests are performed in accordance with the IEC
publication.
Electrostatic discharge will be performed at all hose
points and surfaces of the equipment under test which
can be touched by persons during operation.
The following methods are used:
0,7 to 1 ns
12 A
6A
Test procedure
–
contact discharge on conductive surfaces and
coupling planes
–
air discharge on insulating surfaces
Example of a test set-up for freestanding equipment is
given in Fig. 3.5, for table-top equipment in Fig. 3.6.
Basis: IEC publication 61000-4-2.
Typical position for
direct application
Indirect discharge by vertical
coupling plane (VCP)
Protective
conductor
Typical position for
discharge to vertical
coupling plane (VCP)
0,1 m
0,5
mx
0,5 VCP
m
Power cable
Alimentation
Power supply
470 kW
Insulation pallet
h = 0,1 m
Ground
reference plane
Signal cable
Power supply
Fig. 3.5 Example of test set-up for floor standing equipment
Chapter 2
Page 3–12
Section 3
B
Test Requirements
VI - Part 7
GL 2012
Typical position for
Typical position for indirect direct application
discharge to horizontal
coupling plane (HCP)
Typical position for indirect
discharge to vertical coupling
plane (VCP)
Horizontal
coupling plane
1,6 m ´ 0,8 m
P
VC 0,5m
´
,5m
0
0,1
m
on
lati
u
Ins
Re
47sistor
0k
W
Ground reference
plane
Power supply
Non conducting table
h = 0,8 m
Fig. 3.6 Example of test set-up for table-top equipment
16.
Electromagnetic fields
Table 3.26
This test serves to demonstrate that under the influence of electromagnetic fields no damage is caused to
the equipment under test and nor permanent or temporary malfunctions occur.
Severity level
16.1
Field strength
Test procedure
Basis: IEC publication 61000-4-3.
16.2
Test conditions
During the test the equipment under test is operated
at its rated operational voltage Ue.
16.3
General instructions for test performance
The tests are performed in accordance with the IEC
publication. During the test functional tests shall be
performed on the equipment under test.
Test chamber conditions
Frequency range
Sweep rate
3
80 MHz to 2 GHz
≤ 1,5 × 10-3 dec/s (1%/ 3s)
10 V/m
Modulation
AM 80% at 1000 Hz 1
sinewave
Polarization
vertically and horizontally
1 If for tests of equipment an input signal with a modulation
frequency of 1000 Hz is necessary a modulation frequency
of 400 Hz should be chosen.
If the wiring to and from the equipment under test is
not specified, unshielded parallel conductors as usual
in shipbuilding shall be used.
Examples of a test set-up are given in Fig. 3.7 and
Fig. 3.8.
VI - Part 7
GL 2012
Section 3
B
Test Requirements
Chapter 2
Page 3–13
Chamber
wall
Shielded connection
trough chamber wall
Area of
uniform field
Shielded power
cable
Non-conducting
table
0,8 m
Cable length 1 m
Field generating
antenna
Power cable
filter
0,1 m
Non-conducting
support
Optional anechoic material
in case of semi-anechoic chamber
to reduce floor refelections
Shielded signal
cable
Absorbing ferrite
or EMI filter
Fig. 3.7 Example of test set-up for floor-standing equipment
Area of
uniform field
Non-conducting
table
Wiring 1 m £ £ 3 m
bundled non-inductively
to 1 m overall length
No specific arrangement
for wiring length < 1 m
as is
Field generating
antenna
Wiring > 3 m or not
specified illuminated
length shall be 1 m
Absorbing ferrite or
EMI filter
Optional anechoic material in case
of semi-anechoic chamber to
reduce floor reflections
Fig. 3.8 Example of test set-up for table-top equipment
Section 3
Chapter 2
Page 3–14
Table 3.27
Test Requirements
B
No damage, no permanent or temporary malfunction
shall occur on equipment under test with software
class requirement 4 or higher, or required by specific
testing standards e.g. protection relays.
Conducted fast transients (burst)
Power
connections
Severity level
Data, control
and
communications
connections
17.1
3
Coupling
2 kV
Polarity
1 kV
17.2
positive / negative
Repetition rate of
pulses
5 kHz
Waveshape of voltage
Test procedure
Basis: IEC publication 61000-4-4.
line / earth
Test voltage (open
circuit)
Test conditions
During the test the equipment under test is operated as
its rated operational voltage Ue, on which the test
voltage is superimposed.
5 kHz
5 / 50 ns
Burst-duration
17.3
15 ms
Burst-period
General instructions for test performance
The tests are performed in accordance with the IEC
publication. During the test functional tests shall be
performed on the equipment under test. The test is
performed at the feed lines and on external control,
data and communications lines.
300 ms
Test duration per
polarity and test point
17.
VI - Part 7
GL 2012
5 Minutes
Conducted fast transients (burst)
If a galvanic coupling on the connections of the
equipment under test is not possible a capacitive coupling clamp shall be used.
This test serves to demonstrate that under the influence of interference on power and signal connections
which may occur at switching contacts as a result of
arcs, no damage is caused to the equipment under test
and no permanent malfunctions occur.
Examples of a test set-up are given in Fig. 3.9 and
Fig. 3.10.
PE
N
L
= protective earth
= neutral
= phase line
DC terminals shall be treated
in a similar way
Generator
EUT
Power
supply
<1m
£ 1 m (cable)
L
N
C c li
PE
0,1 m
Non-conducting
support
Coupling/decoupling
network
Power supply
Ground reference plane
Grounding connection
according to the
manufacturer's specification
Cc
li
Fig. 3.9
L
N
PE
Filtering
= coupling capacitors = 33 nF
= decoupling inductor > 100 mH
Example of test set-up for direct coupling of the test voltage to
AC/DC power supply ports/terminals
Section 3
VI - Part 7
GL 2012
B
Test Requirements
Chapter 2
Page 3–15
-
When both EUT are tested simultaneously:
l1 = l2 ­ 1 m between clamp and EUT
-
When one EUT only is tested:
l2 > 5 m or 5 ´ l1 for decoupling purposes
EUT
EUT
Power
supply
l1
Capacitive
coupling clamp
0,1 m
Drounding connection
according to the
manufacturer's specification
Fig. 3.10
Ground reference plane
Grounding connection
according to the
manufacturer's specification
Example of test set-up for application of the test voltage by
the capacitive coupling clamp
Conducted high frequency interference
Test method
Basis: IEC publication 61000-4-6.
18.2
Non-conducting support
to Generator
This test serves to demonstrate that under the influence of interference which may occur on power and
signalling lines as a result of HF signal radiation, no
damage is caused to the equipment under test and no
permanent or temporary malfunction occur.
18.1
0,1 m
0,1 m
Non-conducting support
18.
Power
supply
l2
Test conditions
During the test the equipment under test is operated
at its rated operational voltage Ue, on which the test
signal is superimposed.
During application of HF interferences functional
tests shall be performed on the equipment under test.
Examples of a test set-up are given in Fig. 3.11 and
Fig. 3.12.
Table 3.28
Severity level
Coupling
Carrier signal (open
circuit)
Frequency range
Modulation
Sweep rate
18.3
General instructions for test performance
The tests are performed in accordance with the IEC
publication.
The power supply lines shall be treated directly while
signal and data lines shall be treated via a coupling
clamp.
Conducted high frequency interference
2
line / earth
3 Veff (130 dBµV) 1
150 kHz to 80 MHz
AM 80 % at 1000 Hz
sinewave 2
≤ 1,5 × 10-3 dec/s (1 %/ 3 s)
1 For equipment installed on bridge deck and deck zone the
test levels shall be increased to 10 Veff for spot frequencies
in accordance with IEC 60945 at 2 MHz, 3 MHz, 4 MHz,
6,2 MHz, 8,2 MHz, 12,6 MHz, 16,5 MHz, 18,8 MHz,
22 MHz, 25 MHz.
2 If for tests of equipment an input signal with a modulation
frequency of 1000 Hz is necessary a modulation frequency
of 400 Hz should be chosen.
Chapter 2
Page 3–16
Section 3
Test Requirements
B
VI - Part 7
GL 2012
Generator
EUT
< 1m
*)
0,1 m
Power supply
Coupling/decoupling
network
Ground reference plane
Non-conducting support
*) Grounding connection according to
the manufacturer's specification
Fig. 3.11 Example of test set-up for direct coupling
EUT
0,1 m <
< 0,3 m
Monitoring probe
Coupling/ 50 W
decoupling
network
AE
Injection clamp
Non-conducting support
(optional)
Measuring
equipment
Generator
Short earthing strap
Ground reference
plane
Non-conducting support
(optional)
Fig. 3.12 Example of a test set-up using injection clamps
19.
Conducted slow transients (surge)
This test serves to demonstrate that under the influence of interference which may occur on power lines
(AC and DC) as a result of high-energy interference
(switching overvoltages caused by inductive loads), no
damage is caused to the equipment under test and no
permanent malfunctions occur.
No damage, no permanent or temporary malfunction
shall occur on equipment under test with software
class requirement 4 or higher, or required by specific
testing standards e.g. protection relays.
19.1
Test procedure
Basis: IEC publication 61000-4-5.
19.2
Test conditions
During the test the equipment under test is operated at
its rated operational voltage Ue, on which the test
pulse is superimposed.
If the equipment under test has been fitted a standard
with suppressors at its connections, these protective
devices shall be included in the test.
VI - Part 7
GL 2012
Section 3
Table 3.29
Conducted slow transients (surge)
B
Test Requirements
Severity level
line / earth
2
Test voltage (open circuit)
Polarity
0,5 kV
1 kV
positive / negative
1,2 / 50 μs
Waveshape of voltage
Repetition rate
min. 1 pulse / minute
Test duration per test
point
19.3
General instructions for test performance
The tests are performed in accordance with the IEC
publication.
Coupling
line / line
Chapter 2
Page 3–17
min. 5 pulses/ Polarity
During application of interferences functional tests
shall be performed on the equipment under test.
Equipment under test using the same lines for power
supply and signal transmission are to be tested according to Fig. 3.15.
This applies also to data, control and communication
connections of the equipment under test, which may
get direct connection to power lines by external wiring
required by applications.
Examples of a test set-up are given in Fig. 3.13 to
Fig. 3.15.
Generator (Ri = 2 W)
Decoupling network
C = 18 mF
L
Power
supply
L = 1,5 mH
N
EUT
PE
Earth reference
Fig. 3.13 Example of test set-up for line-to-line coupling on power supply lines
Generator (Ri = 2 W)
R = 10 W
C = 9 mF
Decoupling network
L
Power
supply
L = 1,5 mH
N
EUT
PE
Earth reference
Fig. 3.14 Example of test set-up for line-to-earth coupling on power supply lines
Section 3
Chapter 2
Page 3–18
B
Test Requirements
VI - Part 7
GL 2012
Generator (Ri = 2 W)
R = 40 W
C = 0,5 mF
S2
S1
Auxiliary
equipment
Protection
equipment
0
1
2
3
4
1
2
3
4
Decoupling network
EUT
L
RL
Earth reference
1)
Switch S1
- line/earth: 0
- line/line: positions 1 to 4
2)
Switch S2
- during the test positions 1 to 4, but not in the same positions with switch S1
3)
L = 20 mH, RL represents the resistive part of the coil
Fig. 3.15 Example of test set-up for unshielded interconnection lines
20.
Conducted low frequency interference
(harmonics)
This test serves to demonstrate that under the influence of interference caused in power supply networks
as a result of system perturbations no damage is
caused to the equipment under test and no permanent
or temporary malfunctions occur.
Table 3.30
Signal level (sine)
3 Veff, max. 2 W
Frequency range
50 Hz to 10 kHz
Sweep range
1,5 × 10-3 dec/s (1%/ 3s)
Test duration
see 20.3
Table 3.31
20.1
AC 50/60 Hz supply voltage:
Test procedure
Not specified
20.2
DC supply voltage
Test conditions
During the test the equipment under test is operated at
its rated operational voltage Ue, on which the test
voltage is superimposed, and, where necessary, at its
rated operational current Ie.
Test level: Ueff, max. 2 W
(Fig. 3.17)
– up to 15th harmonics
10 % of Ue
– 15th to 100th harmonics
decreasing from 10 %
to 1 % of Ue
– 100th to 200th harmonics
1 % of Ue
Test duration
see 20.3
VI - Part 7
GL 2012
20.3
Section 3
B
Test Requirements
Chapter 2
Page 3–19
reaching saturation point.
General instructions for test performance
The harmonics shall be reciprocally tested at supply
voltages of AC 50/60 Hz. The sweep rate shall be
sufficiently slow to allow influences on the operational behaviour of the equipment under test to be
readily detected.
The test signal is injected into the supply voltage via a
coupling transformer (Fig. 3.16). The impedance
should be < 1 Ω. The coupling transformer shall be
designed in such a way that it can also support the
rated current of the equipment under test without
1
EUT
1
Generator
2
Coupling transformer
3
Voltmeter or oscilloscope
3
Power supply
2
Ground reference
Example for coupling
~
Generator
Coupling transformer
L1
N
pE
Power supply
Fig. 3.16 Example of test set-up, conducted low frequency interference (harmonics)
% - Signal voltage of Ue
10
1
0,1
1
10
15
100
Harmonic, n
Fig. 3.17 Signal voltage for AC supply voltages
200
Chapter 2
Page 3–20
21.
Section 3
B
Test Requirements
VI - Part 7
GL 2012
22.
Conducted emissions
Radiated emissions from enclosure port
This test measures any signals generated by equipment which appear on its power supply port and
which can, therefore, be conducted into the power
supply, and potentially disturb other ship's equipment.
This test measures any signals radiated by an equipment which can potentially disturb other equipment.
21.1
22.2
Test procedure
Basis: CISPR 16-1, 16-2.
21.2
22.1
Test procedure
Basis: CISPR 16-1, 16-2.
Test conditions
During the test the equipment under test is operated
of its rated operational voltage Ue.
Test conditions
During the test the equipment under test is operated
at its rated operational voltage Ue.
Table 3.33
Site
Table 3.32
Conducted emissions
Site
Frequency range
Bridge and open deck 10 kHz – 150 kHz
zone
150 kHz – 350 kHz
350 kHz – 30 MHz
– EMC 1 1
General power
distribution zone
– EMC 2 1
Bridge and open
deck zone
Limits
96 dBµV – 50 dBµV
60 dBµV – 50 dBµV
50 dBµV
10 kHz – 150 kHz 120 dBµV – 69 dBµV
79 dBµV
150 kHz – 500 kHz
73 dBµV
500 kHz – 30 MHz
1 see Table 3.34
21.3
General instructions for test performance
The emission shall be measured by means of the
quasi-peak measuring receivers specified in CISPR
16-1-1. An artificial mains network in accordance
with CISPR 16-2 shall be used.
The measuring bandwidth in the frequency range
10 kHz to 150 kHz shall be 200 Hz, and in the frequency range 150 kHz to 30 MHz shall be 9 kHz.
The power input cables between the AC and DC
power ports of the EUT and the artificial mains network shall be screened and not exceed 0,8 m in
length. Longer power cords shall be folded into a
serpentine-like bundle and not coiled. If the EUT
consists of more than one unit with individual AC
and/or DC power ports, power ports of identical
nominal supply voltage may be connected in parallel
to the artificial mains supply network.
Measurements shall be made with all measuring
equipment and the EUT mounted on, and bonded to,
an earth plane. Where provision of an earth plane is
not practicable, equivalent arrangements shall be
made using the metallic frame or mass of the EUT as
the earth reference.
21.4
Test result
The radio-frequency voltage at the power supply
terminals of the EUT shall not exceed the limits
shown in Fig. 3.18.
– EMC 1 1
Radiated emissions from
enclosure port
Frequency range
except for:
156 MHz – 165 MHz
General power
distribution zone
– EMC 2 1
Limits
150 kHz – 300 kHz 80 dBµV/m – 52 dBµV/m
300 kHz – 30 MHz 52 dBµV/m – 34 dBµV/m
30 MHz – 2 GHz
54 dBµV/m
24 dBµV/m
150 kHz – 30 MHz 80 dBµV/m – 50 dBµV/m
30 MHz – 100 MHz 60 dBµV/m – 54 dBµV/m
100 MHz – 2 GHz
54 dBµV/m
except for:
156 MHz – 165 MHz
24 dBµV/m
1 see Table 3.34
22.3
General instructions for test procedure
The radiation limit at distance 3 m from the enclosure
port over the frequency range shall be measured.
The quasi-peak measuring receivers specified in
CISPR 16-1-1 shall be used. The receiver bandwidth
in the frequency ranges 150 kHz to 30 MHz and
156 MHz to 165 MHz shall be 9 kHz, and in the
frequency ranges 30 MHz to 156 MHz and 165 MHz
to 2 GHz shall be 120 kHz.
For frequencies from 150 kHz to 30 MHz measurements shall be made of the magnetic H-field.
The correction factor for the antenna shall include the
factor + 51,5 dB to convert the magnetic field
strength to equivalent electric field strength.
For frequencies above 30 MHz measurements shall
be made of the electric E-field.
The test antenna shall be placed at a distance of 3 m
from the EUT. The centre of the antenna shall be at
least 1,5 m above the ground plane.
The E-field antenna shall be adjusted in height and
the EUT shall be placed at the mid-point of a plane
orthogonal to the test antenna and be rotated to
achieve the maximum emission level.
22.4
Test result
The radiation limit from the enclosure port shall not
exceed the limits shown in Fig. 3.19.
VI - Part 7
GL 2012
Section 3
B
Test Requirements
Chapter 2
Page 3–21
120
110
100
96
EMC 2
90
80
EMC 1
dB [mV]
70
60
50
40
30
B = 200 Hz
B = 9 kHz
20
10
0
0,15
0,01
0,35 0,5
0,1
1,5
1
Frequency
30
10
[MHz]
B
Measuring receiver bandwidth
EMC 1
EMC 2
Bridge and open deck zone
General power distribution zone
Fig. 3.18 Radio frequency terminal voltage limits for conducted emission
100
Chapter 2
Page 3–22
Section 3
Test Requirements
B
VI - Part 7
GL 2012
Field strength E measured at 3 m
120
110
100
90
80
dB [mV/m]
70
EMC 2
156 MHz - 165 MHz
60
50
EMC 1
B = 9 kHz
40
30
20
B = 9 kHz
B = 120 kHz
10
0
0,1
0,15
0,3
1
10
Frequency
30
100
200
[MHz]
B
Measuring receiver bandwidth
EMC 1
EMC 2
Bridge and deck zone
General power distribution zone
Fig. 3.19 Limit values for radiated emissions from enclosure ports
2000
1000
VI - Part 7
GL 2012
Section 3
Table 3.34
Required test conditions for the defined environmental categories
Test Requirements
Chapter 2
Page 3–23
Test Conditions
Open Deck Area
Temperature
Comments
Climate
Temperature
Relative
Humidity
Salt mist
55 °C
5 °C
55 °C
95 %
–
0,7 g
B
0 °C
up to
to
100 %
45 °C
4g
55 °C
5 °C
55 °C
95 %
–
4g
Has to withstand a high level of
vibration strain, e. g. in steering
gear compartment.
C
0 °C
up to
to
100 %
55 °C
0,7 g
70 °C
5 °C
55 °C
95 %
–
0,7 g
Has to withstand a high degree
of heat, e. g. for equipment to
be mounted in consoles, housings.
4g
70 °C
5 °C
55 °C
95 %
–
4g
4g
90 °C 5 °C
55 °C
95 %
–
4g
55 °C
5 °C
55 °C
80 %
–
0,7 g
For use in air-conditioned areas. With GL’s special consent
only.
D
DT
E
F
G
H
0°C
up to
to
100 %
55 °C
0°C
up to
to
100 %
90°C
0 °C
to
40 °C
up to
80 %
Vibrations
0,7 g
Relative
Humidity
0 °C
up to
to
100 %
45 °C
Vibrations
A
Relative
Humidity
Cold
The short sign of the location
EMC 1/ EMC 2 where the
equipment is installed according to test 18, 21 and 22 should
be added to the short sign of the
environmental category.
Dry Heat
Temperature
Closed Area
Temperature
Environmental Category
Environmental Conditions
Vibrations
B
0,7 g
- 25 °C
to
+ 45 °
C
- 25 °C
to
+ 45 °
C
For general applications
Has to withstand a high degree
of heat and a high level of vibration strain, e. g. for equipment to be mounted on combustion engines and compressors.
up to
100 %
0,7 g
70 °C
55 °C
25 °C
95 %
Test
re0,7 g
quired
Has to withstand the additional
influences of salt mist and
temporary inundation, e. g. on
open deck.
up to
100 %
2,3 g
70 °C
55 °C
25 °C
95 %
Test
re2,3 g
quired
For use on masts, with the
additional influence of salt
mist.
according to manufacturer’s specification
only in combination with environmental categories A-G
The provisions contained in the
certificates shall be observed.
Download