SUBSTITUTIONS SECTION 01620-PAGE 1 PART 1.00 – GENERAL 1.01 RELATED DOCUMENTS: The general provisions of the Contract, including General and Supplementary Conditions and other General Requirement Sections, apply to the work specified in this Section. 1.02 DESCRIPTION OF REQUIREMENTS: A. Definitions and Explanations – The requirements for substitutions do not apply to specified Contractor options on products, materials and construction methods. Revisions to the Contract Documents, where requested by the Owner, or Engineer, are “changes”, not “substitutions”. Requested substitutions during the bidding period, which have been accepted prior to the Contract Date, are not subject to the requirements for substitutions as specified herein. The Contractor’s determination of and compliance with governing regulations and lawful orders issued by governing authorities do not constitute “substitutions”, and do not constitute a basis for change orders, except as provided for in the contract documents. Otherwise, the Contractor’s request for changes in the products and/or materials required by the contract documents are considered requests for “substitutions” and are subject to the requirements herein. 1. “Or Equal” – Where names products, materials or methods are accompanied by “or equal” or other language of the same effect, the Contractor’s requests to use unnamed products, materials or methods are considered requests for substitutions, and are subject to the requirements hereof. B. Refer to Section 01600: Products, Materials and Equipment, for general products, materials and equipment requirements which are hereby made applicable to substitutions. 1.03 LIMITATIONS FOR MAKING SUBSTITUTIONS: A. Conditions – After the Effective Date of the Agreement, Engineer will consider formal requests from Contractor for substitution of products in place of those specified. Such requests shall be submitted in a timely, fully documented manner such that the progress schedule is not affected by the review process. One or more of the following conditions must be satisfied, as judged by the Engineer. Requests that do not meet the criteria below will be returned without action except to record non-compliance with these requirements. 1. Request for substitution is directly related to an “or equal” clause or other similar language in the contract documents. 2. Where required products and/or materials cannot be provided within the Contract Time, but not as a result of the Contractor’s failure to pursue the work promptly or coordinate the various activities properly. 3. Where the required product and/or material cannot be provided in a manner which is compatible with other materials or the work, or cannot be used without adversely affecting the Owner’s insurance coverage on the completed work, or will encounter other substantial non-compliances which are not possible to otherwise overcome, except by making the requested substitution, which the Contractor thereby certifies to overcome such non-compatibility, non-coordination, non-warranty/guarantee, noninsurability or other non-compliance as claimed. 4. Where required product and/or material cannot receive required approval by a governing authority, and the requested substitution can be so approved. 5. Where substantial advantage is offered the Owner, in terms of cost, time or other valuable considerations, after deducting offsetting responsibilities the Owner may be required to bear, including additional compensation to Engineer for redesign and evaluation services, increased cost of other work by Owner or separate contractors, and similar considerations. B. Work-Related Submittals – The Contractor’s submittal of, and the Engineer’s acceptance of, shop drawings or samples which indicate work not complying with the requirements of the contract documents, does not constitute an acceptable and valid request for, nor approval of, a substitution. C. In making request for substitution, Bidder/Contractor represents: 1. He has personally investigated proposed product or method, and determined that it is equal to or superior in all respects to that specified. 2. He will provide the same guarantee for substitution as for product or method specified. 3. He will coordinate installation of accepted substitution in work, making such changes as may be required for work to be complete in all respects. PROJECT # 2013-015.02 Y:\Jobfiles\2013-015_Extraco-Water\2013-015.02_Low-Roof\04_Specifications\51_2013-015.02_01620.docx SUBSTITUTIONS SECTION 01620-PAGE 2 4. He waives all claims for additional costs related to substitution that consequently becomes apparent. 5. Cost data is complete and includes all related costs under his contract or other contracts that may be affected by the substitution. 6. He will reimburse the Owner for any redesign costs by the Engineer for accommodation of the substitution. D. Substitutions will not be considered if: 1. They are indicated or implied on Shop Drawings without formal request submitted in accordance with this paragraph 1.03. 2. Acceptance will require substantial revision of Contract Documents. 1.04 SUBMITTALS: A. Requests for Substitutions – Submit one (1) electronic Adobe PDF format copy of requests for substitutions on the form provided in these documents. Include the following information: 1. Complete product data, drawings, and descriptions of materials and methods substantiating compliance of proposed substitution with Contract Documents. 2. Product identification, including manufacturer’s name and address. 3. Manufacturer’s literature, including: a. Production description b. Performance and test data c. Reference standards 4. Samples where applicable or requested. 5. Detailed comparison of the significant qualities (size, weight, durability, performance and similar characteristics, and including visual effect where applicable) for the proposal substitution in comparison with the original requirements. 6. List, with addresses, of three (3) projects where proposed substitution has been used previously and successfully in a similar application. 7. Coordination information, indicating every required change in every other element of the work that is affected by the substitution, extended to include work by the Owner and separate contractors. 8. A complete statement of the effect the substitution will have upon the schedule of the work, including its effect (if any) on the Contract Time (in comparison with compliance with the requirements without approval of the proposed substitution). 9. Cost information, including a proposal of the net change in the Contract Sum (if any). 10. Certification by the CONTRACTOR to the effect that, in his opinion and after his thorough evaluation, the proposed substitution will result in total work which is equal-to-or-better-than the work originally required by the contract documents, in every respect of significance except as specifically stated in the certification; and that it will perform adequately in the application indicated, regardless of equality and exceptions thereto. a. Include in certification, Contractor’s waiver of rights to additional payment and time which may subsequently be necessitated, by failure of the substitution to perform adequately, and for the required work to make corrections thereof. b. Change Order Form – Submit requests for substitutions that propose a change in either the Contract Sum or Contract Time, in the form and by the procedures required for change order proposals. c. Action by Engineer – Within one week of receipt of Contractor’s request for substitution, the Engineer will request whatever additional information or documentation may be needed for his evaluation of the request. Within two (2) weeks of receipt of request, or within one (1) week of receipt of requested additional information or documentation (whichever is later), the Engineer will notify the Contractor of either his acceptance or his rejection of the proposed substitution. 1. Rejection will include statement of the reasons for rejection (non-compliances with the requirements for requested substitutions, or other reasons as detailed). 2. Acceptance will be in the form of a change order, when required by the contract documents. END OF SECTION PROJECT # 2013-015.02 Y:\Jobfiles\2013-015_Extraco-Water\2013-015.02_Low-Roof\04_Specifications\51_2013-015.02_01620.docx