Distribution Substation - Network Feeder `Back Feed` Protection

advertisement

Distribution Substation - Network Feeder

‘Back Feed’ Protection

Don Sevcik

CenterPoint Energy Houston Electric

EEI Fall 2013 Transmission, Distribution & Metering

October 6-9, 2013

Charleston, SC

Company   Overview

• CenterPoint Energy is a gas and electric delivery company operating in several states.

• CenterPoint Energy Houston Electric (CEHE) is a structurally unbundled transmission and distribution utility serving Houston,

Galveston, Freeport, Baytown, and surrounding communities in the state of

Texas. CEHE does not own or operate power plants, nor does CEHE participate in competitive electric energy markets.

• CEHE has a small geographic footprint, but serves approximately 25% of the electric load in the ERCOT region.

2

‘Street   Network’   and   ‘Spot   Network’

CenterPoint Energy offers a range of overhead and underground single phase, two phase and three phase types of services.

At CenterPoint Energy’s option, in certain locations, CenterPoint Energy offers service from 208V underground secondary ‘Street Network’ and 480V & 4160V secondary

‘Spot Networks’.

These secondary networks are characterized by a bus fed by multiple network transformers with a given secondary network operating voltage (208 V, 480 V, 4160 V).

Each network transformer has a 12.47 kV delta connected primary voltage winding.

For a given secondary network, each network transformer is connected to a separate

12.47 kV substation feeder.

All of the 12.47 kV feeders that supply a set of network transformers originate from the same substation.

Two substation power transformers supply all of the network feeders that make up a

‘network grid’.

3

Substation

‘Street   Network’   and   ‘Spot   Network’

Distribution   Substation   Bus

Feeder

Breaker

MUG   Network   Vault

Network   Xfmr

Δ /Y

Network

Protector

Secondary  

Network   Bus

Local

Customer   Loads

N.C.

• Two   substation   transformers   are   connected   to   a   common   bus.

  (Networked   Substation   Bus)  

• Networked   underground   feeders   leave   the   sub   to   serve   MUG   network   vaults.

• Each   feeder   serves   a   MUG   network   transformer.

• The   network   transformer   secondaries are   connected,   through   a   network   protector,   to   a   common   bus.

• The   secondary   network   is   a   bus   fed   by   multiple   transformers,   from   multiple   locations,   at   a   given   operating   network   voltage   (208   V,  

480   V,   4160   V).

• CNP   has   1 ‐ 208V   secondary   network   and   numerous   480V/4160V   spot   networks.

To   208V   Street  

Network   Grid

• CNP   Network   Systems   are   designed   to   be   able   to   lose   a   circuit   without   effecting   the   customer  

(N ‐ 1).

4

69 KV LINE 138-69 KV

AUTOTRANSFORMER

69 KV LINE

INDOOR SWITCHGEAR

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

12.47 KV OH FEEDERS

12.47 KV OH FEEDERS

12.47 KV UG NON-NETWORK FDRS

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

12.47 KV UG NETWORK FEEDERS

CABLE RISERS

POWER BUILDING

69-12.47 KV

TRANSFORMERS

69 & 12.47 KV

PROTECTIVE RELAYS

AND CONTROL

SUBSTATION

CONFIGURATION

5

POWER   BUILDING

I

I

OPEN TRANSFORMER

BUSES

ENCLOSED

I

I

SWITCHGEAR

SWITCHGEAR

FEEDER

CABLES

FEEDER

CABLES

October   5,   2006

TRANSMISSION

LINE AUTOTRANSFORMER

TRANSMISSION

LINE

TRF   2

A1

A4

A7

A10

A13

A16

TRIP

B2

B5

B8

B11

B14

B17

TRIP

A3

A6

A9

A12

A15

A18

TRF   5

Y

Y

Y

Y

INITIAL

1 ‐ PHASE

FAULT

7

October   5,   2006

TRANSMISSION

LINE AUTOTRANSFORMER

TRANSMISSION

LINE

TRF   2

A1

A4

A7

A10

A13

A16

TRIP

B2

SUBSEQUENT

MULTI ‐ PHASE

FAULT

B5

B8

B11

B14

B17

A6

TRIP

A9

TRIP

A12

TRIP

A15

TRIP

A18

TRIP

TRF   5

TRIP

Y

Y

Y

Y

8

October   5,   2006

SUBSTATION   69   KV

DIGITAL   FAULT

RECORDER

T   =   0

B2   opens   but   A3   interrupter   fails

Results   in   multi ‐ phase   fault

977   A   rms 2850   A   rms

Trf#5   69   kV   bkr   open

1900   A   rms

All   Trf#5   “A”   bkrs   open

1110   A   rms

983   A   rms 2860   A   rms

960   A   rms 2990   A   rms

1900   A   rms

1860   A   rms

1110   A   rms

1090   A   rms

9 9

Trf#2   69   Kv   bkr   open

1670   A   rms

October   5,   2006

1080   A   rms

1340   A   rms

1860   A   rms

1080   A   rms

1060   A   rms

SUBSTATION   69   KV

DIGITAL   FAULT

RECORDER

T   =   5   min.

10

SWITCHGEAR   CIRCUIT   BREAKER   COMPARTMENT

11

REMAINS   OF   SWITCHGEAR   CIRCUIT   BREAKER

12

SWITCHGEAR   ‘A ‐ B ‐ A’   CIRCUIT   BREAKER   COMPARTMENTS

AND   CABLE   RISERS   TO   INDOOR   OVERHEAD   BUS

13

INDOOR   OVERHEAD   12.47

  KV   BUS

14

RESTORATION

• OTHER   TRANSFORMERS   WERE   MANUALLY   TRIPPED   TO   ALLOW   FIRE   DEPARTMENT   TO  

PUT   OUT   THE   FIRE   IN   THE   CUBICLE.

 

• TOOK   8   HOURS   TO   ISOLATE   DAMAGED   EQUIPMENT,   CLEAN,   TEST   AND   RE ‐ ENERGIZE  

FEEDERS   THAT   WERE   NOT   DAMAGED.

• REMAINING   CLEANUP   EFFORTS   TOOK   7 ‐ 10   DAYS   TO   COMPLETE.

• DAMAGED   SWITCHGEAR   AND   CIRCUIT   BREAKERS   WOULD   HAVE   TO   BE   REPLACED  

LATER.

15

NEAR   TERM   FIXES

• SEND   similar   SWITCHGEAR   CIRCUIT   BREAKERS   FROM   FOUR   SUBSTATIONS   TO  

MANUFACTURER   FOR   REHAB  ‐ ADD   STRUT   UPGRADE   KIT,   REPLACE   PUSH   RODS,  

REPLACE   PRIMARY   TRIP   PROP   ASSEMBLY,   REPLACE   TRIP   SPRINGS,   REPLACE   CONTACT  

SPRINGS,   ROUTINE   MAINTAINCE   LUBRICATION,   TESTS   AND   CHECKS.

• REPLACE   INDOOR   ENCLOSED   TRANSFORMER   BUS   WITH   OPEN   AIR   BUS.

• ADD   FIRE ‐ PROOF   BARRIER   TO   INDOOR   CONTROL   CABLE   TRAY.

• DEVELOP   AND   IMPLEMENT   A   NEW   SUBSTATION   BASED   ‘BACK   FEED’   PROTECTIVE  

RELAYING   SCHEME.

16

TYPICAL   PROTECTION   SCHEME

69 kV

TR2

A1

50

BF

B2

TR5

A3

50

BF

C-T-S

50/

51

R-T-S

W/V

12 kV NETWORK

17

SUBSTATION   BASED   ‘BACK ‐ FEED’   PROTECTION  

SCHEME

69 kV

TR2

A1

50

BF

B2

3 Split-

X F2

Core

1200/5

C150

A3

TR5

F3 X

50

BF

F4 X F1 X

12 kV NETWORK

C-T-S

50/

51

R-T-S

W/V

“BACK-FEED”

Protection

Scheme

“TRIP1” wire for BF schemes which utilizes “50” relays OR “TRIP1B” wire for BF schemes which utilize uP relays.

“BACK-FEED” MICROPROCESSOR RELAY

Either input starts & seals-in internal timer.

Timer set for BF clearing time + margin ( 30 to

60 cycles ). If 50 element is picked-up after timer delay then:

Trip

Both

Trf.’s

Alarm

SCADA

18

POWER   BUILDING

OPEN TRANSFORMER

BUSES

OPEN

I

I

SWITCHGEAR

SWITCHGEAR

FEEDER

CABLES

Install   Split ‐ Core   Feeder   CT’s   &  

“Back   Feed”   Microprocessor   

Relays

FEEDER

CABLES

I

I

19

‘BACK   FEED’   PROTECTION   – SPLIT ‐ CORE   FEEDER   CT’S

20

‘BACK ‐ FEED’   PROTECTION   – NORMAL   CONDITIONS

TRF   2

BUS

“Back ‐ Feed   trip”   scheme

Normal   conditions  ‐ No   trip   applied   to   any   breaker   or   to   the   microprocessor   relay  

1200:5 300A 300A

A1 B2 A3

1200:5

1.25A

50/

BF

600A

1.25A

50/

BF

1.25A

1.25A

50/

51

2.5A

1.25A

2.5A

TRF   5

BUS

1200:5 uP

SUBSTATION

2.5A

1.25A

1.25A

NETWORK   FEEDERS

600A

21

TRF   2

BUS

A1

“F1”   FAULT   ‐ – NO   TRIP   FROM   ‘BACK   FEED’  

MICROPROCESSOR   RELAY

0A Tripped   by feeder   protection

B2

50/

BF

0A

0A

SUBSTATION

NETWORK   FEEDERS

F1

X

0A

Tripped   by feeder   protection

A3

0A

TRF   5

BUS

0A

0A

0A

50/

BF

0A

50/

51 uP uP   relay timer   starts when   50/51   relay   operates

22

“F2”   FAULT   ‐ TRIP   FROM   ‘BACKFEED’   MICROPROCESSOR  

RELAY   REQUIRED   AFTER   SET   TIME   DELAY

Tripped   by   ‘back ‐ feed’   protection

TRF   2

BUS

A1

0A Tripped   by feeder   protection

B2

F2

X

Tripped   by feeder   protection

A3

0A

Tripped   by   ‘back ‐ feed’   protection

TRF   5

BUS

50/

BF

0A

2400A   Max.

240A   Min.

SUBSTATION

10A   Max.

1A   Min.

0A

50/

BF

0A

0A

50/

51

10A   Max.

1A   Min.

uP uP   relay timer   starts when   50/51   relay   operates

23

NETWORK   FEEDERS

“F3”   FAULT   AND   A3   BREAKER   FAILURE   – TRIP   FROM  

‘BACKFEED’   MICROPROCESSOR   RELAY   REQUIRED  

AFTER   SET   TIME   DELAY

Tripped   by   ‘back ‐ feed’   protection

TRF   2

BUS

0A

A1

Tripped by   BF

B2

50/

BF

0A

2400A   Max.

240A   Min.

10A   Max.

1A   Min.

2400A   Max.

240A   Min.

Tripped   by bus   protection

TRF   5

BUS

F3 X

10A   Max.

1A   Min.

0A

10A   Max.

1A   Min.

50/

BF uP

10A   Max.

1A   Min.

50/

51 uP   relay timer   starts when   BF   scheme operates

SUBSTATION

24

NETWORK   FEEDERS

“F4”   FAULT   AND   B2   BREAKER   FAILURE   – NO   TRIP  

FROM   ‘BACK   FEED’   MICROPROCESSOR   RELAY

TRF   2

BUS

Tripped   by feeder   protection

A1

2400A   Max.

240A   Min.

50/

BF

10A   Max.

1A   Min.

Tripped by   BF

A3

0A

TRF   5

BUS

10A   Max.

1A   Min.

0A

10A   Max.

1A   Min.

0A

50/

BF

10A   Max.

1A   Min.

50/

51 uP uP   relay timer   starts when   BF   operates

F4 X

2400A   Max.

240A   Min.

SUBSTATION

NETWORK   FEEDERS

25

December   27,   2012

A FAULT OCCURRED IN THE12 KV CIRCUIT BREAKER A3 COMPARTMENT.

THE NORMAL FEEDER AND TRANSFORMER PROTECTIVE RELAYS TRIPPED

TRANSFORMER #5 AND 12 KV CIRCUIT BREAKER B2 IN SIX CYCLES BUT THE FAULT

IN A3 CONTINUED TO BE BACK FEED FROM THE FEEDER VIA TRANSFORMER #2

AND THE DISTRIBUTION NETWORK.

THE SPECIAL ‘BACK FEED’ PROTECTIVE RELAYING OPERATED AND TRIPPED

TRANSFORMER #2 IN APPROXIMATELY ONE SECOND AFTER THE TRANSFORMER

#5 TRIP.

SUBSEQUENTLY IT WAS DETERMINED THAT A RAT HAD CAUSED THE FAULT.

THE B ‘BACK FEED’ OPERATED AS DESIGNED AND INITIATED ALARMS THROUGH

SCADA.

ABLE TO ISOLATE THE CIRCUIT IN THE BUILDING AS WELL AS ISOLATE THE FEEDER

IN THE FIELD.

SWITCHING AND RESTORATION WAS COMPLETE IN 90 MINUTES.

26

A3 3-phase fault

December   27,   2012

Trf#5 69 kV bkr opens

All Trf#5 “A” bkrs and B2 open

SUBSTATION   69   KV

DIGITAL   FAULT

RECORDER

T   =   0

27

December   27,   2012

Trf#2 69 kV bkr opens

SUBSTATION   69   KV

DIGITAL   FAULT

RECORDER

T   =   1   second

28

SWITCHGEAR   CIRCUIT   BREAKER   COMPARTMENT

29

LONG   TERM   OPTIONS   TO   ADDRESS   A   POSSIBLE  

FUTURE   MAJOR   EVENT   INSIDE   OF   POWER   BUILDING

SHORTLY AFTER THIS EVENT SEVERAL LONG TERM OPTIONS WERE

PROPOSED FOR EVALUATION TO PREVENT OR LESSEN DAMAGE IF A

SIMILAR OF MORE DESTRUCTIVE EVENT WERE TO OCCUR:

• FIRE DETECTION/SUPPRESSION/POWER-DOWN SYSTEM

• CHANGE TO AN OPEN AIR SUBSTATION DESIGN

• ADD SECOND POWER BUILDING SEPARATED WITH FIREWALLS

• MOBILE BREAKER “SIX PACK” TRAILER RESTORATION SCHEME

• REAL TIME CAMERA MONITORING INSIDE OF POWER BUILDING

LATER IT WAS DETERMINED THAT GAS INSULATED SWITCHGEAR (GIS)

HAD SEVERAL ADVANTAGES FOR THIS PARTICULAR APPLICATION.

30

LONG   TERM   PLAN

12.47

  KV   GAS   INSULATED   SWITCHGEAR   (GIS)

GIS SYSTEM INCORPORATES VACUUM BOTTLES INSIDE CAST ALUMINUM TANKS

UNDER SF6 GAS PRESSURE AND IS A SINGLE PHASE DESIGN. THEREFORE, PHASE-

TO-PHASE FAULT IS NOT POSSIBLE.

ALL THE LIVE PARTS ARE LOCATED INSIDE THE TANK AND THE GEAR IS SAFE TO

TOUCH.

NO RACKING AND UNRACKING OF CIRCUIT BREAKERS WOULD BE INVOLVED WITH

THE GIS AS OPPOSED TO AIR INSULATED GEAR. THIS WOULD ELIMINATE

RACKING/UNRACKING OF THE CIRCUIT BREAKERS. IF A GIS CIRCUIT BREAKER WERE

TO FAIL IT WOULD BE COMPLETELY CONTAINED INSIDE THE TANK AN NO DAMAGE

WILL BE DONE TO THE BUILDING OR THE OTHER CIRCUIT BREAKERS.

GIS USES CABLE ‘PLUGS’ FOR ALL TRANSFORMER AND FEEDER CONNECTIONS

WHICH ELIMINATES ANIMAL CAUSED FAULT.

SINCE THE HIGH VOLTAGE PARTS ARE INSIDE A PRESSURIZED TANK (SEALED

ENVIRONMENT), NO MAINTENANCE WOULD BE REQUIRED FOR THE LIFE OF THE

CIRCUIT BREAKER. THE MECHANISM IN A CONVENTIONAL MECHANISM AND CAN BE

MAINTAINED LIKE OTHER CIRCUIT BREAKERS.

BACK FEED PROTECTIVE RELAYING SCHEME WILL CONTINUE TO BE USED AS A

PRECAUTION.

31

Circuit

Breaker

CT’s

LONG   TERM   PLAN

12.47

  KV   GAS   INSULATED   SWITCHGEAR

‘Back-Feed’ CT’s

32

LONG   TERM   PLAN

12.47

  KV   GAS   INSULATED   SWITCHGEAR

‘Circuit Breaker CT’s

‘Back-Feed’ CT’s

33

Distribution   Substation  ‐ Network   Feeder

‘Back   Feed’   Protection

Questions/Comments?

34

Download
Study collections