Don Sevcik
EEI Fall 2013 Transmission, Distribution & Metering
October 6-9, 2013
Charleston, SC
Company Overview
• CenterPoint Energy is a gas and electric delivery company operating in several states.
• CenterPoint Energy Houston Electric (CEHE) is a structurally unbundled transmission and distribution utility serving Houston,
Galveston, Freeport, Baytown, and surrounding communities in the state of
Texas. CEHE does not own or operate power plants, nor does CEHE participate in competitive electric energy markets.
• CEHE has a small geographic footprint, but serves approximately 25% of the electric load in the ERCOT region.
2
‘Street Network’ and ‘Spot Network’
CenterPoint Energy offers a range of overhead and underground single phase, two phase and three phase types of services.
At CenterPoint Energy’s option, in certain locations, CenterPoint Energy offers service from 208V underground secondary ‘Street Network’ and 480V & 4160V secondary
‘Spot Networks’.
These secondary networks are characterized by a bus fed by multiple network transformers with a given secondary network operating voltage (208 V, 480 V, 4160 V).
Each network transformer has a 12.47 kV delta connected primary voltage winding.
For a given secondary network, each network transformer is connected to a separate
12.47 kV substation feeder.
All of the 12.47 kV feeders that supply a set of network transformers originate from the same substation.
Two substation power transformers supply all of the network feeders that make up a
‘network grid’.
3
Substation
‘Street Network’ and ‘Spot Network’
Distribution Substation Bus
Feeder
Breaker
MUG Network Vault
Network Xfmr
Δ /Y
Network
Protector
Secondary
Network Bus
Local
Customer Loads
N.C.
• Two substation transformers are connected to a common bus.
(Networked Substation Bus)
• Networked underground feeders leave the sub to serve MUG network vaults.
• Each feeder serves a MUG network transformer.
• The network transformer secondaries are connected, through a network protector, to a common bus.
• The secondary network is a bus fed by multiple transformers, from multiple locations, at a given operating network voltage (208 V,
480 V, 4160 V).
• CNP has 1 ‐ 208V secondary network and numerous 480V/4160V spot networks.
To 208V Street
Network Grid
• CNP Network Systems are designed to be able to lose a circuit without effecting the customer
(N ‐ 1).
4
69 KV LINE 138-69 KV
AUTOTRANSFORMER
69 KV LINE
INDOOR SWITCHGEAR
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
12.47 KV OH FEEDERS
12.47 KV OH FEEDERS
12.47 KV UG NON-NETWORK FDRS
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
12.47 KV UG NETWORK FEEDERS
CABLE RISERS
POWER BUILDING
69-12.47 KV
TRANSFORMERS
69 & 12.47 KV
PROTECTIVE RELAYS
AND CONTROL
SUBSTATION
CONFIGURATION
5
POWER BUILDING
I
I
OPEN TRANSFORMER
BUSES
ENCLOSED
I
I
SWITCHGEAR
SWITCHGEAR
FEEDER
CABLES
FEEDER
CABLES
October 5, 2006
TRANSMISSION
LINE AUTOTRANSFORMER
TRANSMISSION
LINE
TRF 2
A1
A4
A7
A10
A13
A16
TRIP
B2
B5
B8
B11
B14
B17
TRIP
A3
A6
A9
A12
A15
A18
TRF 5
Y
Y
Y
Y
INITIAL
1 ‐ PHASE
FAULT
7
October 5, 2006
TRANSMISSION
LINE AUTOTRANSFORMER
TRANSMISSION
LINE
TRF 2
A1
A4
A7
A10
A13
A16
TRIP
B2
SUBSEQUENT
MULTI ‐ PHASE
FAULT
B5
B8
B11
B14
B17
A6
TRIP
A9
TRIP
A12
TRIP
A15
TRIP
A18
TRIP
TRF 5
TRIP
Y
Y
Y
Y
8
October 5, 2006
SUBSTATION 69 KV
DIGITAL FAULT
RECORDER
T = 0
B2 opens but A3 interrupter fails
Results in multi ‐ phase fault
977 A rms 2850 A rms
Trf#5 69 kV bkr open
1900 A rms
All Trf#5 “A” bkrs open
1110 A rms
983 A rms 2860 A rms
960 A rms 2990 A rms
1900 A rms
1860 A rms
1110 A rms
1090 A rms
9 9
Trf#2 69 Kv bkr open
1670 A rms
October 5, 2006
1080 A rms
1340 A rms
1860 A rms
1080 A rms
1060 A rms
SUBSTATION 69 KV
DIGITAL FAULT
RECORDER
T = 5 min.
10
SWITCHGEAR CIRCUIT BREAKER COMPARTMENT
11
REMAINS OF SWITCHGEAR CIRCUIT BREAKER
12
SWITCHGEAR ‘A ‐ B ‐ A’ CIRCUIT BREAKER COMPARTMENTS
AND CABLE RISERS TO INDOOR OVERHEAD BUS
13
INDOOR OVERHEAD 12.47
KV BUS
14
RESTORATION
• OTHER TRANSFORMERS WERE MANUALLY TRIPPED TO ALLOW FIRE DEPARTMENT TO
PUT OUT THE FIRE IN THE CUBICLE.
• TOOK 8 HOURS TO ISOLATE DAMAGED EQUIPMENT, CLEAN, TEST AND RE ‐ ENERGIZE
FEEDERS THAT WERE NOT DAMAGED.
• REMAINING CLEANUP EFFORTS TOOK 7 ‐ 10 DAYS TO COMPLETE.
• DAMAGED SWITCHGEAR AND CIRCUIT BREAKERS WOULD HAVE TO BE REPLACED
LATER.
15
NEAR TERM FIXES
• SEND similar SWITCHGEAR CIRCUIT BREAKERS FROM FOUR SUBSTATIONS TO
MANUFACTURER FOR REHAB ‐ ADD STRUT UPGRADE KIT, REPLACE PUSH RODS,
REPLACE PRIMARY TRIP PROP ASSEMBLY, REPLACE TRIP SPRINGS, REPLACE CONTACT
SPRINGS, ROUTINE MAINTAINCE LUBRICATION, TESTS AND CHECKS.
• REPLACE INDOOR ENCLOSED TRANSFORMER BUS WITH OPEN AIR BUS.
• ADD FIRE ‐ PROOF BARRIER TO INDOOR CONTROL CABLE TRAY.
• DEVELOP AND IMPLEMENT A NEW SUBSTATION BASED ‘BACK FEED’ PROTECTIVE
RELAYING SCHEME.
16
TYPICAL PROTECTION SCHEME
69 kV
TR2
A1
50
BF
B2
TR5
A3
50
BF
C-T-S
50/
51
R-T-S
W/V
12 kV NETWORK
17
SUBSTATION BASED ‘BACK ‐ FEED’ PROTECTION
SCHEME
69 kV
TR2
A1
50
BF
B2
3 Split-
X F2
Core
1200/5
C150
A3
TR5
F3 X
50
BF
F4 X F1 X
12 kV NETWORK
C-T-S
50/
51
R-T-S
W/V
“BACK-FEED”
Protection
Scheme
“TRIP1” wire for BF schemes which utilizes “50” relays OR “TRIP1B” wire for BF schemes which utilize uP relays.
“BACK-FEED” MICROPROCESSOR RELAY
Either input starts & seals-in internal timer.
Timer set for BF clearing time + margin ( 30 to
60 cycles ). If 50 element is picked-up after timer delay then:
Trip
Both
Trf.’s
Alarm
SCADA
18
POWER BUILDING
OPEN TRANSFORMER
BUSES
OPEN
I
I
SWITCHGEAR
SWITCHGEAR
FEEDER
CABLES
Install Split ‐ Core Feeder CT’s &
“Back Feed” Microprocessor
Relays
FEEDER
CABLES
I
I
19
‘BACK FEED’ PROTECTION – SPLIT ‐ CORE FEEDER CT’S
20
‘BACK ‐ FEED’ PROTECTION – NORMAL CONDITIONS
TRF 2
BUS
“Back ‐ Feed trip” scheme
Normal conditions ‐ No trip applied to any breaker or to the microprocessor relay
1200:5 300A 300A
A1 B2 A3
1200:5
1.25A
50/
BF
600A
1.25A
50/
BF
1.25A
1.25A
50/
51
2.5A
1.25A
2.5A
TRF 5
BUS
1200:5 uP
SUBSTATION
2.5A
1.25A
1.25A
NETWORK FEEDERS
600A
21
TRF 2
BUS
A1
“F1” FAULT ‐ – NO TRIP FROM ‘BACK FEED’
MICROPROCESSOR RELAY
0A Tripped by feeder protection
B2
50/
BF
0A
0A
SUBSTATION
NETWORK FEEDERS
F1
X
0A
Tripped by feeder protection
A3
0A
TRF 5
BUS
0A
0A
0A
50/
BF
0A
50/
51 uP uP relay timer starts when 50/51 relay operates
22
“F2” FAULT ‐ TRIP FROM ‘BACKFEED’ MICROPROCESSOR
RELAY REQUIRED AFTER SET TIME DELAY
Tripped by ‘back ‐ feed’ protection
TRF 2
BUS
A1
0A Tripped by feeder protection
B2
F2
X
Tripped by feeder protection
A3
0A
Tripped by ‘back ‐ feed’ protection
TRF 5
BUS
50/
BF
0A
2400A Max.
240A Min.
SUBSTATION
10A Max.
1A Min.
0A
50/
BF
0A
0A
50/
51
10A Max.
1A Min.
uP uP relay timer starts when 50/51 relay operates
23
NETWORK FEEDERS
“F3” FAULT AND A3 BREAKER FAILURE – TRIP FROM
‘BACKFEED’ MICROPROCESSOR RELAY REQUIRED
AFTER SET TIME DELAY
Tripped by ‘back ‐ feed’ protection
TRF 2
BUS
0A
A1
Tripped by BF
B2
50/
BF
0A
2400A Max.
240A Min.
10A Max.
1A Min.
2400A Max.
240A Min.
Tripped by bus protection
TRF 5
BUS
F3 X
10A Max.
1A Min.
0A
10A Max.
1A Min.
50/
BF uP
10A Max.
1A Min.
50/
51 uP relay timer starts when BF scheme operates
SUBSTATION
24
NETWORK FEEDERS
“F4” FAULT AND B2 BREAKER FAILURE – NO TRIP
FROM ‘BACK FEED’ MICROPROCESSOR RELAY
TRF 2
BUS
Tripped by feeder protection
A1
2400A Max.
240A Min.
50/
BF
10A Max.
1A Min.
Tripped by BF
A3
0A
TRF 5
BUS
10A Max.
1A Min.
0A
10A Max.
1A Min.
0A
50/
BF
10A Max.
1A Min.
50/
51 uP uP relay timer starts when BF operates
F4 X
2400A Max.
240A Min.
SUBSTATION
NETWORK FEEDERS
25
December 27, 2012
A FAULT OCCURRED IN THE12 KV CIRCUIT BREAKER A3 COMPARTMENT.
THE NORMAL FEEDER AND TRANSFORMER PROTECTIVE RELAYS TRIPPED
TRANSFORMER #5 AND 12 KV CIRCUIT BREAKER B2 IN SIX CYCLES BUT THE FAULT
IN A3 CONTINUED TO BE BACK FEED FROM THE FEEDER VIA TRANSFORMER #2
AND THE DISTRIBUTION NETWORK.
THE SPECIAL ‘BACK FEED’ PROTECTIVE RELAYING OPERATED AND TRIPPED
TRANSFORMER #2 IN APPROXIMATELY ONE SECOND AFTER THE TRANSFORMER
#5 TRIP.
SUBSEQUENTLY IT WAS DETERMINED THAT A RAT HAD CAUSED THE FAULT.
THE B ‘BACK FEED’ OPERATED AS DESIGNED AND INITIATED ALARMS THROUGH
SCADA.
ABLE TO ISOLATE THE CIRCUIT IN THE BUILDING AS WELL AS ISOLATE THE FEEDER
IN THE FIELD.
SWITCHING AND RESTORATION WAS COMPLETE IN 90 MINUTES.
26
A3 3-phase fault
December 27, 2012
Trf#5 69 kV bkr opens
All Trf#5 “A” bkrs and B2 open
SUBSTATION 69 KV
DIGITAL FAULT
RECORDER
T = 0
27
December 27, 2012
Trf#2 69 kV bkr opens
SUBSTATION 69 KV
DIGITAL FAULT
RECORDER
T = 1 second
28
SWITCHGEAR CIRCUIT BREAKER COMPARTMENT
29
LONG TERM OPTIONS TO ADDRESS A POSSIBLE
FUTURE MAJOR EVENT INSIDE OF POWER BUILDING
SHORTLY AFTER THIS EVENT SEVERAL LONG TERM OPTIONS WERE
PROPOSED FOR EVALUATION TO PREVENT OR LESSEN DAMAGE IF A
SIMILAR OF MORE DESTRUCTIVE EVENT WERE TO OCCUR:
• FIRE DETECTION/SUPPRESSION/POWER-DOWN SYSTEM
• CHANGE TO AN OPEN AIR SUBSTATION DESIGN
• ADD SECOND POWER BUILDING SEPARATED WITH FIREWALLS
• MOBILE BREAKER “SIX PACK” TRAILER RESTORATION SCHEME
• REAL TIME CAMERA MONITORING INSIDE OF POWER BUILDING
LATER IT WAS DETERMINED THAT GAS INSULATED SWITCHGEAR (GIS)
HAD SEVERAL ADVANTAGES FOR THIS PARTICULAR APPLICATION.
30
LONG TERM PLAN
12.47
KV GAS INSULATED SWITCHGEAR (GIS)
GIS SYSTEM INCORPORATES VACUUM BOTTLES INSIDE CAST ALUMINUM TANKS
UNDER SF6 GAS PRESSURE AND IS A SINGLE PHASE DESIGN. THEREFORE, PHASE-
TO-PHASE FAULT IS NOT POSSIBLE.
ALL THE LIVE PARTS ARE LOCATED INSIDE THE TANK AND THE GEAR IS SAFE TO
TOUCH.
NO RACKING AND UNRACKING OF CIRCUIT BREAKERS WOULD BE INVOLVED WITH
THE GIS AS OPPOSED TO AIR INSULATED GEAR. THIS WOULD ELIMINATE
RACKING/UNRACKING OF THE CIRCUIT BREAKERS. IF A GIS CIRCUIT BREAKER WERE
TO FAIL IT WOULD BE COMPLETELY CONTAINED INSIDE THE TANK AN NO DAMAGE
WILL BE DONE TO THE BUILDING OR THE OTHER CIRCUIT BREAKERS.
GIS USES CABLE ‘PLUGS’ FOR ALL TRANSFORMER AND FEEDER CONNECTIONS
WHICH ELIMINATES ANIMAL CAUSED FAULT.
SINCE THE HIGH VOLTAGE PARTS ARE INSIDE A PRESSURIZED TANK (SEALED
ENVIRONMENT), NO MAINTENANCE WOULD BE REQUIRED FOR THE LIFE OF THE
CIRCUIT BREAKER. THE MECHANISM IN A CONVENTIONAL MECHANISM AND CAN BE
MAINTAINED LIKE OTHER CIRCUIT BREAKERS.
BACK FEED PROTECTIVE RELAYING SCHEME WILL CONTINUE TO BE USED AS A
PRECAUTION.
31
Circuit
Breaker
CT’s
LONG TERM PLAN
12.47
KV GAS INSULATED SWITCHGEAR
‘Back-Feed’ CT’s
32
LONG TERM PLAN
12.47
KV GAS INSULATED SWITCHGEAR
‘Circuit Breaker CT’s
‘Back-Feed’ CT’s
33
Distribution Substation ‐ Network Feeder
‘Back Feed’ Protection
34