Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 Transport Infrastructure Projects Completed 2008/2009 Period Description Installation Completed Notional cost/(£) Actual cost/(£) 2008/2009 Quays bus stop August 2009 Y 15,000 12,696 2008/2009 Car Sharing Bays Easter 2009 N 2,000 1,915 2008/2009 Litter Bins N/A N 1,000 0 CCTV for car park 'A' 2008/2009 and power the 2 P&D machines (10 & 11) Easter 2009 Y 10,000 10,465 Expansion of cycle 2008/2009 storage on top of boiler house roof July 2009 Y 10,000 9,053 2008/2009 *Improve CCTV cycle storage surveillance July 2009 Deferred* 5,000 0 2008/2009 Bus seats for Boundary July 2009 Road bus stands Y 6,650 2,769 2008/2009 Cycle storage at Loughton July 2009 Y 10,000 3,993 Cycle Storage and 2008/2009 Manifestation at Southend 2009 Y Expansion of cycle 2008/2009 storage on top of boiler house roof July 2009 Y £1,310 10,000 9,053 Comment Location by bus stop in front of Quays Accommodation office. Constable Building parking and lining of bays in front of Wivenhoe House Hotel carried out instead. Not undertaken Cabling works undertaken and P&D machines now operating on mains power, including machine 14 for Sports Centre and University users. Cycle storage capacity on Rayleigh Square now increased to 192, accessed by the new Rayleigh Route due for completion December. Camera installed under square 5within cycle shelter project. BUG requested cycle surveillance funds to be allocated for provision of Dr Bike services. In situ and provided through EMS rather using Ollerton bus seats which were unsuitable. 17 racks fitted at Loughton Southend Cycle Town (SBC) match funded (50%) installation of 8 racks at Southend Cycle storage capacity on Rayleigh Square now increased to 192, accessed by the new Rayleigh Route due for completion December. Revenue 2009/2010 Dr Bike Services on campus October 2009 Ongoing 5000 *Provision of term time weekly Dr Bike services. Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 Ongoing Transport Infrastructure Projects - 2009/2010 Description Project Installation Completed 2009/2010 South Courts bus stop traffic calming September 2009 2009/2010 Replace obsolete cameras & cabling in 2009/10 car park 'B' and Valley car park 2009/2010 Installation of drop kerbs for bus stands & pedestrian footways Notional Cost to cost/(£) date/(£) Comment Increased passenger safety by moving bus stop (in accordance with Atkins Safety Check report) and assists in speed reduction on Boundary Road Cabling component undertaken and included in car park ‘A’ improvements. Further CCTV camera works in car parks awaiting appointment of Security Manager. Drop kerbs and pedestrian crossing on Valley Road installed. Crossing improves pedestrian safety by Under Podia area as well as enabling disabled access to bus stands. Shelter and surveillance system installed and cycle access created by fire road barrier for those accessing the cycle storage from the Wivenhoe direction. Yes 36,000 36,100 Awaiting appointment of Security Manager. 15,000 0 Completed September 2009 Yes 12,000 2,235 2009/2010 Cycle shelter for outer row of Sheffield stands September under Square 5 with 2009 surveillance system Yes 11,000 10,360 2009/2010 Pedestrian crossing linking public footpath September to Wivenhoe with 2009 campus path Yes 35,000 Zebra crossing improves pedestrian 23,015 access. Ramped crossing contributes to speed reduction on Boundary Road. 2009/2010 Re-modelling of Car Park B October 2009 Yes 92,000 Car parking spaces increased by 41 although pedestrian marking to be undertaken in Spring to improve 94,122 pedestrian passage through car parks and additional spaces will reduce to 32. 2009/2010 Cycle route from Boundary Road to Rayleigh Square December 2009 Yes 78,000 76,879 See agenda item 8 2009/2010 External signage for car parking October 2009 *2009/2010 Car Sharing Bays 2009/2010 Approval Requested 2000 *2009/2010 Nursery Drop Off Bays/Late comers bay Spring 201 Approval Requested 500 *2009/2010 Improve CCTV across campus for car parks, cycle storage and pedestrian access Spring 2010 Approval Requested 15,000 Yes 20,000 Signage for enforcement of new car parking management system with Liberty installed. Revisions made to 15535 University car park signage and lining. Further minor amendments to correct ambiguities scheduled. To support the University’s car share scheme 8 bays in Valley Car Park and 8 in the North Towers Car park will be marked as car share bays only with signage. Agenda item 5 As petitioned by the CUG and the Campus Nursery 8 further spaces will be allocated drop off only between 07:30 and 10:30 hours. And 16:00 and 18:00. Agenda item 5 Previous allocation diverted to funds Dr Bike, Security will take up LTM Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 Description *2009/2010 Project Installation Completed Increased cycle storage Autumn 2010 Approval Requested Notional Cost to cost/(£) date/(£) 66000 Comment As detailed in TPSC Agenda item 8 Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 Transport Revenue Projects/Items Description Traffic Officer costs Transport Policy Coordinator Dr Bike Services *CarShare Website Branding *CarShare Scheme Promotion Implementation Drivers Notional Cost to cost/(£) date/(£) Security Manager & TCP /5th TPSC /5th Cyclist,STP /5th Spring 2010 TCP/Liftshare 750 Sping 2010 TCP/Liftshare 800 From October 2009 From October 2009 From October 2009 – June 2011 Comment One Traffic Officer in post full-time. Second 3,870 officer commencing 15 February 2010.. Patrol officer overtime also included. 16,712 Full time Transport Policy Coordinator Services to be provided twice weekly term time 2085 between April & October inclusive, and once weekly term time from November to March. To brand the Colchester 2020 car share scheme as the University’s Marketing campaign to promote the University’s car share scheme and launch car share bays Planned event for Bike to Work Week 2010 Breakfasts *Bike to Work Week June 2010 TCP 1500 *Walk to Work Day May 2010 TCP 1500 Planned events for Walk to Work Week 2010 August 2010 TCP/Bus Operators 5000 Match funding for a multi operator bus ticket ‘Octopus’ for staff and students in Southend. March 2010 Car Users 6000 Current machine failing & pc to facilitate the machine 1500 University/Community *Introduction of the Octopus Card for Southend Students *Smart Card ticket machine for Helpdesk Fund Hoarding at the Hythe Station *Cycle Lockers *Guaranteed Ride home scheme When new Rail TOC appointed Users/Visitors ECC funding Spring Student Support/BUG February 2010 TCP 300 ECC willing to match fund the purchase of cycle lockers 500 Scheme is necessary to assure success of the car share scheme. All items starred require approval from the TPSC. Charlotte Humphries Transport Policy Coordinator Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee Car Parking Income and Expenditure Statement at December 2009 February 2010 £ £ Income Wheel Clamp Income 1,215 Pay & Display Income 84,295 Car Registration Via Payroll 7,237 Student standard car registration 18,372 Barrier controlled student registration 12,703 Cash And Cheque Paid By Staff 14,790 Barrier Controlled Staff 15,677 External Support Income -107 Internal Recharge Income Total Income 154,182 Staff Cost Office Support 3,870 Senior Support 16,712 20,581 Non Staff Cost EMS Unprogrammed Services 10,994 Car Park - Expenditure 16,929 Printing 4,455 Stationery 25 Tools & Equipment Travel & Subsistence Membership Dues Uniforms Clothing Cleaning Sustainable Transport Events and Training Upheld clamping fees Depreciation (5 months) Woodland Services (Aug- Oct) Student Union Sundries Total Non staff 0 119 5,000 497 52 225 7,431 13,922 2,501 766 62,916 Total Expenditure 83,498 SURPLUS 70,684 Agenda item 9 TPSC/09/13 Transport Policy Sub-Committee 9 February 2010 Agenda item 9 TPSC/09/13 University of Essex Transport Policy Sub-Committee 2009-10 Transport Related Projects Funded by Car Parking Income at 31st December 2009 February 2010 Annual Budget Profile Budget £ Year to Dec Actual £ Profile Variance £ Profile Variance % £ % 52 Cycle Route from Boundary Road to Rayleigh Square 69,095 32,195 33,430 (1,235) -4 35,665 Cycle storage at Loughton 10,000 6,135 728 5,407 88 9,272 93 Dr Bike Services 14,722 2,085 0.00 2,085 100 14,722 100 Expansion of cycle storage on boiler house roof 80,929 4,165 675 3,490 84 80,254 99 Re - Modelling of Car Park B 77,270 33,720 87,295 (53,575) -159 (10,025) -13 5,000 28,790 0 28,790 100 5,000 100 257,016 107,090 122,129 (15,039) -14 134,887 52 Replace Camera's in Car Park B and Valley Car Park Agenda item 9 TPSC/09/13