Vermont-VEIC Contract for EEU ATTACHMENT N PERFORMANCE INCENTIVE MECHANISM: January 1, 2009 to December 31, 2011 I. Overview The Contractor and the Board agree that a portion of payments to the Contractor shall be based on the Contractor’s performance in achieving the Board’s objectives and successfully delivering the strategies and initiatives described in the Scope of Work. The performance incentive mechanism is designed to reward superior performance by the Contractor in the overall administration and delivery of energy efficiency services that achieve specific resource acquisition outcomes and market transformation goals. For the period January 1, 2009 through December 31, 2011, the Contractor can earn up to $2,180,000 in Electric PI Awards for meeting the 100% Target Level for performance indicators supported by Contractor Electric EEU Funds. Table N-1 shows the Contractor Electric EEU Funds performance indicators and the dollar amount allocated to each indicator, if the Contractor achieves each indicator’s 100% Target Level. For the same period, the Contractor can earn additional Electric PI Awards if the Contractor exceeds the 100% Target Level for each of the Contractor Electric EEU Funds performance indicators as identified in Tables N-1 and N-3. The maximum amount of Electric PI Awards that the Contractor can earn for performance indicators supported by Contractor Electric EEU Funds for the period January 1, 2009 through December 31, 2011, is $2,532,000. The Contractor can also earn an Unregulated Fuel PI Award of up to $100,000 for a performance indicator supported by Contractor Unregulated Fuel Funds. The actual performance indicator for Contractor Unregulated Fuel Funds is to be decided as stated in Paragraph II.H, below. The maximum amount of Performance Awards that the Contractor can earn for all performance indicators for the period January 1, 2009 through December 31, 2011, is $2,632,000. The schedule and processes for documenting and verifying achievement of performance indicators is outlined in Paragraph VI of this Attachment. The Contractor shall submit claims for Performance Awards. The DPS and/or the Contract Administrator will verify the Contractor’s claims. The Contract Administrator will make recommendations regarding all Performance Awards to the Board. Payment of any earned Performance Awards for the period January 1, 2009 through December 31, 2011 (up to a maximum of $2,632,000) shall be made by July 1, 2012. The performance incentive mechanism is subject to a set of five minimum performance requirements, which are summarized in Tables N-4 and N-5. The final amount of Performance Awards granted to Contractor will be subject to achievement of these minimum N-1 Vermont-VEIC Contract for EEU performance requirements and will be adjusted in accordance with Paragraph IV should the Contractor fail to meet any of the minimum performance requirements. II. Description of Performance Indicators The Contractor is eligible to earn an incentive for superior performance in certain specified areas. This section provides a more detailed description of individual performance indicators, their weights as a percentage of the total Electric PI Award or the Unregulated Fuel PI Award at the 100% Target Level, their individual 100% Target Levels, their minimum thresholds, and the scaling between their thresholds and their 100% Target Levels. The threshold and scaling for each indicator supported by Contractor Electric EEU Funds are summarized in Table N-2. A. Cumulative Annual Electricity Savings 1. Weighting The overall weight for this performance indicator is 33% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 * 0.33 = $719,400). 2. 100% Target Level For the period January 1, 2009 through December 31, 2011, the 100% Target Level for this indicator (also known as the Electricity Savings Target) is 360,000 MWh (at generation and net of free riders).1 The Electricity Savings Target measures the sum of annualized first-year savings achieved by implementation of all EEU strategies and initiatives that are funded by Contractor Electric EEU Funds, except for the Customer Credit initiative, during the period 1/1/2009 through 12/31/2011. During the contract period the Electricity Savings Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Electricity Savings Target will be increased (or decreased) by 3.81 MWh per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Electricity Savings above a specified threshold. The threshold is set at 80% of the Electricity Savings Target or 288,000 MWh. Results from services implemented by BED shall not be counted towards the Contractor’s performance for the purposes of determining any Performance Awards under this Contract. In addition, results from activities implemented by the Contractor pursuant to Paragraph II.T of Attachment L shall not be counted towards the Contractor’s performance for the purposes of determining any Performance Awards. Any results from activities implemented with funds from other sources (e.g., grants, Vermont Gas Systems), except for savings from activities implemented with funds from Vermont electric utilities pursuant to Paragraph II.T of Attachment L, shall be counted toward the Contractor’s performance for the purposes of determining Performance Awards. 1 N-2 Vermont-VEIC Contract for EEU If the Contractor achieves 80% of its Electricity Savings Target, it can earn $359,700 (50% of the amount it would earn if it achieved 100% of its Electricity Savings Target). The Performance Award shall be scaled linearly between 80% and 100% of the actual Electricity Savings as detailed in Paragraph II.A.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified cumulative annual Electricity Savings are less than 288,000 MWh. $359,700 for achieving 288,000 MWh (80% of the 100% Target Level) plus $4.996 per MWh for verified cumulative annual Electricity Savings between 288,000 MWh and 360,000 MWh. B. Total Resource Benefits This incentive is designed to encourage the Contractor to maximize energy-related and other resource benefits in implementing energy-efficiency measures and projects during their economic lifetime. 1. Weighting The overall weight for this performance indicator is 25% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.25 = $545,000). 2. 100% Target Level For the period 1/1/2009 through 12/31/2011, the 100% Target Level for this indicator (also known as the Total Resource Benefits (“TRB”) Target) is $342,386,000 (in year-2006 dollars). The TRB Target measures the cumulative TRB achieved by implementation of all EEU services and initiatives that are funded by the Contractor Electric EEU Funds except the Customer Credit initiative. The TRB for any given service is defined as the present value (in year-2006 dollars) of lifetime net resource savings in electricity, fossil fuel, and water, which are valued at current projections of avoided resource costs.2 Avoided costs do not include environmental or any other externalities (e.g., indirect economic benefits), such as the 0.7 cents/kWh value stipulated in ¶ 51 of the MOU. During the contract period the TRB Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the TRB Target will be increased (or decreased) by $3,634 (in 2006 dollars) per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. 2 TRB does not include measure costs, or any other costs or benefits to customers (e.g., productivity increases, changes in O&M costs). N-3 Vermont-VEIC Contract for EEU 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents TRB above a specified threshold. The threshold is set at 75% of the TRB Target or $256,789,500. If the Contractor achieves 75% of its TRB Target, it can earn $272,500 (50% of the amount it would earn if it achieved 100% of its TRB Target). The Performance Award shall be scaled linearly between 75% and 100% of the actual TRB, as detailed in Paragraph II.B.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified TRB are less than $256,789,500. $272,500 for achieving TRB of $256,789,500 (75% of the 100% Target Level) plus $.003184 per TRB Dollar for verified TRB between $256,789,500 and $342,386,000. C. Summer Peak Demand Savings This performance incentive is designed to encourage the Contractor to achieve superior levels of peak summer demand savings in addition to annual energy savings and total resource benefits. 1. Weighting The overall weight for this performance indicator is 12% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.12 = $261,600). 2. 100% Target Level For the period 1/1/2009 through 12/31/2011, the 100% Target Level for this indicator (also known as the Summer Peak Demand Savings Target) is 51,200 kW. The Summer Peak Demand Savings Target measures the cumulative annual summer peak demand savings achieved by implementation of all EEU services and initiatives that are funded by the Contractor Electric EEU Funds except the Customer Credit initiative. Peak summer demand savings are reductions in Vermont's diversified electric demand (in kilowatts, kW) that coincide with the regional power market's peak load periods in the summer as defined by ISO-NE. During the contract period the Summer Peak Demand Savings Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Summer Peak Demand Savings Target will be increased (or decreased) by0.54 kW per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. N-4 Vermont-VEIC Contract for EEU 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Summer Peak Demand Savings above a specified threshold. The threshold is set at 75% of the Summer Peak Demand Savings Target or 38,400 kW. If the Contractor achieves 75% of its Summer Peak Demand Savings Target, it can earn $130,800 (50% of the amount it would earn if it achieved 100% of its Summer Peak Demand Savings Target). The Performance Award shall be scaled linearly between 75% and 100% of the Summer Peak Demand Savings Target, as detailed in Paragraph II.C.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified Summer Peak Demand Savings are less than 38,400 kW. $130,800 for achieving Summer Peak Demand Savings of 38,400 kW (75% of the 100% Target Level) plus $10.219 per kW for verified cumulative annual Summer Peak Demand Savings between 38,400 kW and 51,200 kW. D. Winter Peak Demand Savings This performance incentive is designed to encourage the Contractor to achieve superior levels of peak winter demand savings in addition to annual energy savings and total resource benefits. 1. Weighting The overall weight for this performance indicator is 5% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.05 = $109,000). 2. 100% Target Level For the period 1/1/2009 through 12/31/2011, the 100% Target Level for this indicator (also known as the Winter Peak Demand Savings Target) is 54,000 kW. The Winter Peak Demand Savings Target measures the cumulative annual winter peak demand savings achieved by implementation of all EEU services and initiatives that are funded by the Contractor Electric EEU Funds except the Customer Credit initiative. Peak winter demand savings are reductions in Vermont's diversified electric demand (in kilowatts, kW) that coincide with the regional power market's peak load periods in the winter as defined by ISO-NE. During the contract period the Winter Peak Demand Savings Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Winter Peak Demand Savings Target will be increased (or decreased) by0.57 kW per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. N-5 Vermont-VEIC Contract for EEU 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Winter Peak Demand Savings above a specified threshold. The threshold is set at 75% of the Winter Peak Demand Savings Target or 40,500 kW. If the Contractor achieves 75% of its Winter Peak Demand Savings Target, it can earn $54,500 (50% of the amount it would earn if it achieved 100% of its Winter Peak Demand Savings Target). The Performance Award shall be scaled linearly between 75% and 100% of the Winter Peak Demand Savings Target, as detailed in Paragraph II.D.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified Winter Peak Demand Savings are less than 40,500 kW. $54,500 for achieving Winter Peak Demand Savings of 40,500 kW (50% of the 100% Target Level) plus $4.037 per kW for verified cumulative annual Winter Peak Demand Savings between 40,500 kW and 54,000 kW. E. Summer Peak Demand Savings in Certain Geographic Areas This performance incentive is designed to encourage the Contractor to achieve superior levels of peak summer demand savings in portions of Chittenden County, Rutland and St. Albans City/Town as generally described by the Board in the Geographic Targeting Order 2009-2011. 1. Weighting The overall weight for this performance indicator is 13% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.13 = $283,400). 2. 100% Target Level For the period 1/1/2009 through 12/31/2011, the 100% Target Level for this indicator is 8,100 kW. The Summer Peak Demand Savings in Certain Geographic Areas measures the sum total of all summer peak capacity reductions in the geographic areas designated in Paragraph II.E, above. It includes all of the cumulative annual summer peak demand savings achieved by implementation of all EEU services and initiatives that are funded by the Contractor Electric EEU Funds within the abovereferenced geographic areas except the Customer Credit initiative. During the contract period the Summer Peak Demand Savings in Certain Geographic Areas Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Summer Peak Demand Savings in Certain Geographic Areas Target will be increased (or decreased) by0.09 kW per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. N-6 Vermont-VEIC Contract for EEU 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Summer Peak Demand Savings in Certain Geographic Areas above a specified threshold. The threshold is set at 75% of the Summer Peak Demand Savings in Certain Geographic Areas Target or 6,075 kW. If the Contractor achieves 75% of its Summer Peak Demand Savings in Certain Geographic Areas Target, it can earn $141,700 (50% of the amount it would earn if it achieved 100% of its Summer Peak Demand Savings Target). The Performance Award shall be scaled linearly between 75% and 100% of the Summer Peak Demand Savings in Certain Geographic Areas Target, as detailed in Paragraph II.E.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified Summer Peak Demand Savings in Certain Geographic Areas are less than 6,075 kW. $141,700 for achieving Summer Peak Demand Savings in Certain Geographic Areas of 6,075 kW (75% of the 100% Target Level) plus $69.975 per kW for verified Summer Peak Demand Savings in Certain Geographic Areas between 6,075 kW and 8,100 kW. F. Winter Peak Demand Savings in Geographic Areas This performance incentive is designed to encourage the Contractor to achieve superior levels of peak winter demand savings in the Southern Loop as generally described by the Board in the Geographic Targeting Order 2009-2011. 1. Weighting The overall weight for this performance indicator is 7% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.07 = $152,600). 2. 100% Target Level For the period 1/1/2009 through 12/31/2011, the 100% Target Level for this indicator is 2,400 kW. The Winter Peak Demand Savings in Certain Geographic Areas measures the sum total of all winter peak capacity reductions in the geographic areas designated in Paragraph II.F, above. It includes all of the cumulative annual winter peak demand savings achieved by implementation of all EEU services and initiatives that are funded by the Contractor Electric EEU Funds within the above referencedgeographic areas except the Customer Credit initiative. During the contract period the Winter Peak Demand Savings in Certain Geographic Areas Target will be adjusted to reflect changes in Contractor Electric EEU Funds N-7 Vermont-VEIC Contract for EEU that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Winter Peak Demand Savings in Certain Geographic Areas Target will be increased (or decreased) by0.03 kW per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Winter Peak Demand Savings in Certain Geographic Areas above a specified threshold. The threshold is set at 75% of the Winter Peak Demand Savings in Certain Geographic Areas Target or 1,800 kW. If the Contractor achieves 75% of its Winter Peak Demand Savings in Certain Geographic Areas Target, it can earn $76,300 (50% of the amount it would earn if it achieved 100% of its Winter Peak Demand Savings Target). The Performance Award shall be scaled linearly between 75% and 100% of the Winter Peak Demand Savings in Certain Geographic Areas Target, as detailed in Paragraph II.F.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified Winter Peak Demand Savings in Certain Geographic Areas are less than 1,800 kW. $76,300 for achieving Winter Peak Demand Savings in Certain Geographic Areas of 1,800 kW (75% of the 100% Target Level) plus $127.167 per kW for verified Winter Peak Demand Savings in Certain Geographic Areas between 1,800 kW and 2,400 kW. G. Business End Uses This performance incentive is designed to encourage the Contractor to achieve increased levels of non-lighting, non-fuel-switching and non-snowmaking measures in the Business Existing Facilities and Business New Construction markets. 1. Weighting The overall weight for this performance indicator is 5% of the Contractor’s total maximum Electric PI Award at the 100% Target Level ($2,180,000 *0.05 = $109,000). 2. 100% Target Level For the period January 1, 2009 through December 31, 2011, the 100% Target Level for this indicator (also known as the Business End Uses Target) is 3,500 MWh in the Business Existing Facilities and Business New Construction markets for all end uses except: Lighting; non-fuel-switching; and N-8 Vermont-VEIC Contract for EEU snow making. During the contract period the Electricity Savings Target will be adjusted to reflect changes in Contractor Electric EEU Funds that might occur, consistent with the limitation set forth in Paragraph 5 of the Main Body. Specifically, the Business End Uses Target will be increased (or decreased) by0.04 MWh per $1,000 of increase (or decrease) in Contractor Electric EEU Funds. 3. Threshold and Scaling Up to 100% Target Level The Contractor shall be eligible to receive a Performance Award for this indicator only if the Board determines that the Contractor successfully achieves and documents Business End Uses Savings above a specified threshold. The threshold is set at 75% of the Electricity Savings Target or 2,625 MWh. If the Contractor achieves 75% of its Business End Uses Target, it can earn $54,500 (50% of the amount it would earn if it achieved 100% of its Electricity Savings Target). The Performance Award shall be scaled linearly between 75% and 100% of the actual Business End Uses savings as detailed in Paragraph II.G.4. 4. Performance Award Up to 100% Target Level The Contractor’s Performance Award shall be: $0 if verified cumulative annual Business End Uses are less than 2,625 MWh. $54,500 for achieving 2,625 MWh (75% of the 100% Target Level) plus $62.286 per MWh for verified cumulative Business End Uses savings between 2,625 MWh and 3,500 MWh. H. Performance Indicator for Unregulated Fuels Activities Funded by Contractor Unregulated Fuel Funds The Contractor will work with the DPS and the Contract Administrator to define an appropriate indicator by 4/30/2009 to reward the Contractor for superior performance in its Unregulated Fuel Funds activities (as detailed in Attachment L, Scope of Work, Section II.B). This includes coming to agreement on the 100% Target Level; minimum and maximum thresholds and associated scaling (if appropriate); ability of Contractor to earn performance award for exceeding the 100% Target Level; and agreed-upon approaches for documenting and verifying achievement of this indicator. It is agreed that the dollar amount available for this performance award is $100,000 of the Contractor Unregulated Fuel Funds. I. Revised Avoided Cost Projections The Board may approve updated Avoided Cost Projections during the period of 1/1/2009 to 12/31/2011. The Contractor will be provided a mutually agreed-upon time frame to implement the use of these new avoided costs. The Board and the Contractor N-9 Vermont-VEIC Contract for EEU shall execute a contract amendment to modify the TRB Target on a prospective basis to reflect updated projections of avoided resource costs. Unless mutually agreed otherwise by the Contractor and the Board, the following process will be used to make the appropriate adjustments to the TRB Target: Recalculate the total for the TRB Target using the new avoided cost projections; Determine the percentage of the above original TRB Target that Contractor has achieved by the implementation date of the new avoided cost projections; and Multiply the new TRB Target by that percentage to determine the amount of the new Targets that the Contractor has already achieved as of the implementation date of the new avoided costs. TRB achieved after the revised targets are adopted will be tracked using the updated avoided costs. Any additional issues associated with new avoided costs (including but not limited to any mid-year implementation issues) will be agreed upon in advance by the Contractor and the Contract Administrator in consultation with the DPS. III. Additional Performance Awards for Achievement Above 100% Target Level The Contractor may earn additional Electric PI Awards if the Contractor exceeds the 100% Target Level for any of the following indicators which are defined in Paragraph II: Cumulative Annual Electricity Savings Total Resource Benefits Summer Peak Demand Savings Winter Peak Demand Savings Summer Peak Demand Savings in Geographic Areas Winter Peak Demand Savings in Geographic Areas Business End Uses There is no limit on the dollar amount of additional Electric PI Awards the Contractor may earn for exceeding the 100% Target Level for any single performance indicator, other than the overall total performance award cap of $2,532,000. The additional Electric PI Awards for these indicators shall be calculated as follows: $8.0667 for each Verified MWh above 360,000 MWh (100% Target Level) of Verified Electricity Savings; $.0064 for each Verified TRB$ above $342,386,000 (100% Target Level) of Verified TRB; N -10 Vermont-VEIC Contract for EEU $20.6250 for each Verified Summer Peak kW above 51,200 kW (100% Target Level) of Verified Summer Peak Demand Savings; $8.1481 for each Verified Winter Peak kW above 54,000 kW (100% Target Level) of Verified Winter Peak Demand Savings; $141.2346 for each Verified Summer Peak kW in Geographic Area above 8,100 kW (100% Target Level) of Verified Summer Peak kW in Geographic Area; $256.6667 for each Verified Winter Peak kW in Geographic Area above 2,400 kW (100% Target Level) of Verified Winter Peak kW in Geographic Area; and $125.7143 for each Verified MWh above 3,500 MWh (100% Target Level) of Verified Business End Uses Savings. Scaling above the 100% Target Level for these seven performance indicators is summarized in Table N-3. IV. Minimum Performance Requirements The Contractor’s eligibility to earn full or partial Performance Awards is contingent on achievement of five Minimum Performance Requirement (MPR) standards. These standards, and associated impacts on Performance Awards, are set forth in Table N-4. A. Five Minimum Performance Requirement Standards 1. Minimum electric benefits. This requirement is intended to ensure that the Contractor produces a minimum benefit-cost ratio of electricity resource savings relative to the costs incurred to implement and evaluate the EEU and the EEC. Electric benefits are defined as the present value (in year-2006 dollars) of lifetime net electricity savings, valued at current projections of avoided resource costs. Total electric benefits shall not include any electric benefits from the Customer Credit program or from BED’s self-implementation of EEU services within BED’s service territory. Total costs for the purposes of this minimum performance requirement standard are defined as the sum of: a. all expenses paid out by the Fiscal Agent from February 2009 through January 2012, except for those related to: i. the Customer Credit program, ii. BED’s self-implementation of EEU services within BED’s service territory (including the DPS’s monitoring and evaluation of BED’s EEU activities), iii. any performance incentive paid to the Contractor in 2009 resulting from the Contractor’s 2006-2008 activity, iv. participation in regional capacity market activities; and v. Contractor Unregulated Fuel Funds. N -11 Vermont-VEIC Contract for EEU b. the amount collected to pay for possible Contractor earned performance incentives resulting from the Contractor’s 2009-2011 activity. Failure to meet this minimum standard of performance would disqualify the Contractor from receiving any Performance Award. 2. Minimum spending on residential customers. This requirement is designed to ensure that the Contractor devotes a minimum level of Contractor Electric EEU Funds to serving residential customers. Failure to attain this minimum standard of performance would automatically reduce the amount the Contractor could earn if it reached the 100% Target Level for all performance indicators supported by Contractor Electric EEU Funds ($2,180,000) by 18% (or $392,400). 3. Minimum low-income spending. This requirement is designed to ensure that the Contractor devotes a minimum level of Contractor Electric EEU Funds to serving Vermont’s low-income population. Low-income spending is defined as the total cost to provide EEU services to Vermont ratepayers whose household income is at or below 80% of the Vermont state median household income. Failure to attain this minimum standard of performance would automatically reduce the amount the Contractor could earn if it reached the 100% Target Level for all performance indicators supported by Contractor Electric EEU Funds ($2,180,000) by 18% (or $392,400). 4. Minimum participation by small non-residential customers. This requirement ensures that the Contractor serves with Contractor Electric EEU Funds a minimum acceptable percentage of small non-residential customers out of all non-residential participants. For this purpose, small non-residential customers are defined as nonresidential electric accounts with annual energy consumption of 40,000 kWh or below. Failure to attain this minimum standard of performance would automatically reduce the amount the Contractor could earn if it reached the 100% Target Level for all performance indicators supported by Contractor Electric EEU Funds ($2,180,000) by 18% (or $392,400). 5. Geographic equity. This requirement is designed to ensure that the Contractor provides a minimum acceptable level of benefits to each of Vermont’s counties through its activities supported by Contractor Electric EEU Funds. It is agreed that Essex and Orleans Counties will be treated as one geographic region for the purposes of this minimum performance requirement.3 Failure to meet this minimum standard 3 It is necessary to combine Essex and Orleans counties in order to mitigate the unintended consequence of Essex County’s customer base. Essex County has one customer that is so large, relative to all other customers in Essex County combined, that it would be virtually impossible for the Contractor to meet the minimum performance standard for Essex County if the large customer did not complete a significant project. The geographic equity minimum performance standard is intended to encourage the Contractor to focus its efforts throughout the state, not to target one particular customer. Combining Essex and Orleans counties for the purpose of the minimum performance standard will encourage the Contractor to focus its efforts throughout both counties, rather than solely on Essex County’s one large customer. N -12 Vermont-VEIC Contract for EEU of performance would automatically reduce the amount the Contractor could earn if it reached the 100% Target Level for all performance indicators supported by Contractor Electric EEU Funds ($2,180,000) by 6% (or $130,800). The reductions in the maximum Electric PI Award at the 100% Target Level described above are cumulative. For example, if the Contractor fails to meet both minimum performance standards two and three, the maximum Electric PI Award at the 100% Target Level will be reduced by $784,800. If the Contractor achieves the 100% Target Level on all performance incentives described in Paragraph II, and fails to meet one or more minimum performance standards, it will not be able to earn an Electric PI Award that exceeds the reduced maximum Electric PI Award at the 100% Target Level. If the Contractor exceeds the 100% Target Level for the performance indicators identified in Paragraph III, it still may earn performance incentives above the reduced maximum Electric PI Award at the 100% Target Level. Notwithstanding the previous sentence, if the Contractor does not meet one or more minimum performance standards, irrespective of how much the Contractor exceeds the 100% Target Level for one or more performance indicators, the maximum Electric PI Award that the Contractor may earn is $2,532,000 less the required reductions described above. B. Calculating Performance Awards In determining the Contractor’s eligibility for an Electric PI Award, the first step will be to assess whether the Contractor met the five minimum performance standards. If the Contractor fails to meet a minimum performance standard and the maximum Electric PI Award at the 100% Target Level is reduced accordingly, the Contractor will only be eligible to receive the reduced Electric PI Award, even if the sum of the amounts the Contractor would otherwise have been eligible to receive for meeting the 100% Target Level exceeds this reduced amount. For example, if the Contractor fails to meet minimum performance standard two, but meets the 100% Target Level for all seven performance indicators described in Paragraph II, the Contractor would only receive an Electric PI Award of $1,787,600 even though the Contractor would have been eligible for an Electric PI Award of $2,180,000 if it had met all the minimum performance standards. A more complicated example would be if the Contractor fails to meet minimum performance standard two, and fails to meet the minimum threshold for performance indicator seven, but achieves 102% of performance indicator one, and meets the 100% Target Level for the remaining five performance indicators. In this situation the Contractor’s Electric PI Award would be calculated as follows Step 1: Reduce the 100% Target Level Electric PI Award cap by $392,400 to $1,787,600 because the Contractor failed to meet minimum performance standard two; Step 2: Sum the amounts the Contractor would have been eligible to earn at the 100% Target Level if it had met all minimum performance standards, excluding the extra amount the Contractor is eligible to earn for achieving 102% of performance indicator one ($719,400 + $545,000 + $261,600 + $109,000 + $283,400 + $152,600 + $0 = $2,071,000); N -13 Vermont-VEIC Contract for EEU V. Step 3: Compare the results of steps one and two. The Contractor is eligible to earn an Electric PI Award equal to the lesser of the two amounts for its 100% Target Level performance, in this example, $1,787,600; Step 4: Calculate the amounts the Contractor is eligible to earn above the 100% Target Level (in this case $58,080 for achieving 2% above the 100% Target Level for performance indicator one);4 and Step 5: Add the results of steps three and four. The Contractor earns an Electric PI Award equal to the sum of these amounts, in this example, $1,845,680. One-Time Adjustment to 100% Target Levels and Associated Factors for Cumulative Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, and Winter Peak Demand Savings in Geographic Areas Due to the rapidly changing market for Residential Standard CFLs and the fact that the DPS evaluation activities related to Residential Standard CFLs are not expected to be completed until after January 1, 2009 the Board and the Contractor agree to the following: The 100% Target Level in Table N-1 and stated above for Cumulative Annual Electricity Savings contain agreed assumptions about the net MWh savings per Residential Standard CFL (Row 2 in Table N-6). These assumptions result in total expected MWh savings to be achieved from Residential Standard CFLs for all three years as shown in Row 3, Column 4. The Contractor Administrator, the DPS and the Contractor will work cooperatively to develop new TRM values (“measure characterizations”) for Residential Standard CFLs. These measure characterizations will result in new overall net savings per Residential Standard CFL. If the new net MWh savings per CFL is multiplied by the total assumed Residential Standard CFL quantities (Row 1 in Table N-6) it will result in a new total MWh savings for all three years. If this total MWh savings is 15% higher or lower than the total three-year MWh savings contained in Table N-6, then the 100% Target Levels for Cumulative Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, and Winter Peak Demand Savings will be adjusted. The adjustments for the 100% Target Level for Cumulative Annual Electricity Savings will be arrived at as follows: 1. Multiply the new agreed-upon MWh savings per Residential Standard CFL by the quantities in Row 1 of Table N-6 to arrive at a new three-year MWh savings to be achieved from Residential Standard CFLs. 2. This difference between the total MWh savings calculated in step 1 and the total MWh savings shown in Table N-6 (Row 3, Column 4) is added or subtracted to the 100% Target Level for Cumulative Annual Electricity 4 In no case would the Contractor be eligible to earn more than the total available Electric PI Award amount of $2,532,000 less the amount of the failed minimum standard, in this case $2,532,000 less $392,400 or $2,139,600 for its achievements above the 100% Target Level. N -14 Vermont-VEIC Contract for EEU Savings as stated in Table N-1 to arrive at a new 100% Target Level for this performance indicator. 3. The new 100% Target Level for Cumulative Annual Electricity Savings will be used to update the adjustment factor stated in Paragraph II.A.2 that updates savings at the 100% Target Level as a result of any changes in Contractor Electric EEU Funds. 4. The new 100% Target Level for Cumulative Annual Electricity Savings will be used to update the “Threshold and Scaling Up to 100% Target Level” amounts shown in Paragraph II.A.2 and II.A.3, above. 5. The new 100% Target Level for Cumulative Annual Electricity Savings will be used to update the “Additional Performance Awards for Achievement Above 100% Target Level” earnings rate as shown in Paragraph III, above. VI. The 100% Target Level for Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, and Winter Peak Demand Savings in Geographic Areas will be adjusted using the same method outlined above for Cumulative Annual Electricity Savings. The only difference will be that the quantities of Residential Standard CFLs for Winter and Summer Peak Demand in Geographic Areas will be as stated in Tables N-7 and N-8. The updated measure characterizations referenced above for Residential Standard CFL will be agreed upon no later than March 31, 2009. No further adjustments to the 100% Target Levels will be made due to any future changes to Residential Standard CFL TRM measure characterizations. Documentation and Verification A. Cumulative Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses In order to establish and validate achievements for the Performance Awards for these seven indicators, the Contractor and the Board agree to the following documentation and verification process. 1. Verification Process By April 1 of 2010, 2011 and 2012 the Contractor will submit a report to the Board, Contract Administrator and DPS that establishes its claim for Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses for the previous year. The Contract Administrator and the DPS will review the Contractor’s report and, at their own discretion, review the Contractor’s project files in order to assess savings estimates for custom measures, comprehensive projects, or key input assumptions. N -15 Vermont-VEIC Contract for EEU The Contract Administrator and the DPS will then meet with the Contractor in an attempt to resolve any differences on claimed savings. By June 1, 2010, 2011 and 2012, the DPS will provide a technical report or memorandum to the Contract Administrator with its recommendation on Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses for the previous year. Following receipt of the DPS’s report, the Contract Administrator will provide a recommendation to the Board regarding Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses for the preceding year. Following receipt of the DPS’s report in 2012, the Contract Administrator will also provide a recommendation to the Board on the appropriate Performance Award for each category. Each year the Board will make a final determination regarding Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses from the previous year. By July 1, 2012, the Board will make a final determination regarding cumulative Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas, and Business End Uses and the appropriate Performance Award for each category. However, if the Contractor is not chosen as the entity to continue to operate the EEU after December 31, 2011 then the annual savings verification process for Year 2011 shall be in accordance with the following schedule: The Contractor’s 2011 savings claim shall be submitted by March 1, 2012. The Board, the Contract Administrator, and the DPS shall complete the savings verification process by May 15, 2012. The Board will make a final determination regarding Cumulative Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas and Business End Uses and the appropriate Performance Award for each category by June 15, 2012. 2. Establishment and Documentation of Savings Estimates The Contractor shall work with the Contract Administrator and the DPS to establish and maintain reasonable savings estimates for prescriptive energy efficiency measures offered. The Contractor shall maintain its documentation of all prescriptive measure savings assumptions in the Technical Reference Manual (TRM). For custom measures or projects, where prescriptive measure savings assumptions have not been established or do not apply, the Contractor shall maintain in its files documentation of all assumptions and calculations used to establish its claim for Electricity Savings, N -16 Vermont-VEIC Contract for EEU Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas and Business End Uses. All information on savings assumptions and calculations used shall be available for review by the DPS and Contract Administrator. 3. Updating of Estimates As part of its ongoing management and planning, the Contractor shall review and update, as appropriate, its estimates of Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, and Winter Peak Demand Savings for measures, technologies and projects in order to reflect information obtained from measurement and evaluation studies, experiences gained from implementation of energy efficiency services and initiatives, and changes in building and appliance standards and codes. The Contractor shall use these revised estimates of Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, and Winter Peak Demand Savings on a prospective basis for measures installed in reporting claims of Annual Electricity Savings, Total Resource Benefits, Summer Peak Demand Savings, Winter Peak Demand Savings, Summer Peak Demand Savings in Geographic Areas, Winter Peak Demand Savings in Geographic Areas and Business End Uses in future years. B. Performance Indicator for Unregulated Fuels Activities Funded by Contractor Unregulated Fuel Funds The Contractor will work with the DPS and the Contract Administrator to define an agreed upon documentation and verification process and schedule for this performance indicator. C. Minimum Performance Requirements In order to establish and validate achievements for the Minimum Performance Requirements, the Contractor agrees to the following documentation and verification process. 1. Verification Process By April 1, 2012, the Contractor shall submit a report to the Contract Administrator that establishes its claims regarding whether it met the five minimum performance requirements that are defined in Paragraph IV. The Contract Administrator will review the Contractor’s report and, at its own discretion, review the Contractor’s supporting information for its claims. The Contract Administrator will then meet with the Contractor in an attempt to resolve any differences on claims regarding whether the Contractor met the five minimum performance requirements. Following this meeting, the Contract Administrator will provide a recommendation to the Board regarding whether the Contractor met each of the minimum performance requirements. By July 1, 2012, the Board will make a final determination regarding whether the Contractor met each of the minimum performance requirements, and whether any adjustments to the Contractor’s Performance Awards are required. N -17 Vermont-VEIC Contract for EEU However, if the Contractor is not chosen as the entity to continue to operate the EEU after December 31, 2011 then the above process will be completed such that the Board can make a final determination regarding whether the Contractor met each of the minimum performance requirements, and whether any adjustments to the Contractor’s Performance Awards are required, by June 15, 2012. N -18