ILC R&D in the Americas Region Tor Raubenheimer (for Gerry Dugan)

advertisement
Americas Region
ILC R&D in the Americas
Region
Tor Raubenheimer
(for Gerry Dugan)
SLAC
AARD Meeting
Palo Alto, Dec. 21, 2005
Americas Region
FALC
ICFA
FALC
Resource Board
ILCSC
GDE
Directorate
GDE
GDE
Executive Committee
GDE
R & D Board
GDE
Change Control Board
Global
R&D Program
GDE
Design Cost Board
RDR
Design Matrix
From Barry Barish, GDE Meeting, Frascati, Italy, December, 2005
Americas Region
The GDE Schedule
2005
2006
2007
2008
2009
2010
Global Design Effort
Project
Baseline configuration
Funding
Reference Design
Technical Design
regional coord
globally coordinated
sample sites
ICFA / ILCSC
expression ofSiting
interest
FALC
ILC R&D Program
Hosting
International Mgmt
From Barry Barish, GDE Meeting, Frascati, Italy, December, 2005
Americas Region
ILC Program
• The ILC program has two portions:
– Reference Design Report
• A conceptual design based on sample sites with a cost estimate
• Accelerator physics and engineering efforts are being developed
– R&D Program
• Presently administered through the different regions
• ILC Global Design Effort is trying to coordinate effort more globally
• ILC timeline
– RDR at end of CY2006
– TDR based on supporting R&D in 2009
• ILC Americas
– Effort spread between RDR and R&D programs
– Some redistribution may be needed to complete the RDR
– Coordinated by Gerry Dugan – MOUs between GDE and labs
http://www.lns.cornell.edu/~dugan/LC/Labs/
Americas Region
GDE Structure and Organization
• Executive Committee for Baseline Configuration
– GDE Director
• Barish
– Regional Directors
• Dugan – Americas
• Foster – Europe
• Takasaki – Asia
– Accelerator Leaders
• Yokoya - Asia
• Raubenheimer - Americas
• Walker - Europe
GDE
Executive
Committee
• Responsible for decisions and documentation for the
Baseline Configuration Document (BCD)
Americas Region
GDE Structure and Organization
• GDE Groups
– Design / Cost Engineers
• Shidara – Asia
• Bialowons – Europe
• Garbincius – Americas
– Siting, Civil Construction and Infrastructure
• Baldy - Europe
• Enomoto – Asia
• Kuchler – Amercas
– Physics / Detectors (WWS chairs)
• Brau - Americas
• Richard - Europe
• Yamamoto - Asia
– Accelerator Experts (44 GDE members)
Americas Region
GDE Organizational Evolution for RDR
• Selected additions to the GDE following the BCD
completion having needed skills in design, engineering,
costing, etc
• Change Control Board
– The baseline will be put under configuration control and a
Board with a single chair will be created with needed expertise.
• Design / Cost Board
– A GDE Board with single chair will be established to coordinate
the reference design effort, including coordinating the overall
model for implementing the baseline ILC, coordinating the
design tasks, costing, etc.
• R&D Board
– A GDE Board will be created to evaluate, prioritize and
coordinate the R&D program in support of the baseline and
alternatives with a single chair
Americas Region
Reference Design Matrix
Area Systems
e- source
e+ source
Damping Rings
RTML
Main Linac
BDS
Kiriki
Gao
ES Kim
Hayano
Yamamoto
Lilje
Angal-Kalinin
Adolphsen
Seryi
Guiducci
Brachmann
Sheppard
Wolski
??
Tenenbaum
Solyak
Technical Systems
Vacuum systems
Magnet systems
Cryomodule
Cavity Package
RF Power
Instrumentation
Dumps and Collimators
Accelerator Physics
Suetsugu
Sugahara
Ohuchi
Saito
Fukuda
Urakawa
Ban
Kubo
Michelato
??
Pagani
Proch
??
Burrows
??
Schulte
Noonan
Thomkins
Carter
Padamsee
Larsen
Ross
??
??
Teranuma
Michizono
Hosoyama
Enomoto
Shidara
Elsen
Simrock
Tavian
Baldy
Bialwons
Himel
Carwardine
Peterson
Kuchler
Garbincius
Global Systems
Commissioning, Operations & Reliability
Control System
Cryogenics
CF&S
Installation
• Area systems leaders
are responsible for
design and cost
• Technical systems are
to provide engineering
and costing
• Global systems have
support and design roles
Americas Region
ANL
ILC-Americas Regional Team
BNL
Jefferson Lab
Cornell LEPP
LLNL
SLAC
Fermilab
TRIUMF
LBNL
Universities
FY06 resources
FTE
SLAC
FNAL
ANL
Jlab
LLNL
LBNL
BNL
Cornell
Universities
59.9
31.0
0.0
1.0
0.0
2.3
0.0
0.0
0.0
Labor
7,182
3,565
140
170
580
330
0
0
0
sum
94.1
11,967
M&S
3,700
4,635
14
651
230
0
0
165
0
Indirect
2,909
1,826
0
79
390
170
0
0
0
Total
13,791
10,026
154
900
1,200
500
500
165
841
9,395
5,374
28,077
University program:
Wisconsin, Northwestern, Old Dominion, Yale, MIT, Tennessee,
Princeton, Illinois, NCA&T, UCLA, Berkeley, Vanderbilt, Colorado State,
UC Davis
Additional funding for infrastructure from laboratory operating funds
Americas Region
Fermilab
ILC R&D at Fermilab
• The ILC R&D effort at Fermilab is focused on key design &
technical issues in support of the RDR, cost estimate and
eventually the TDR for the ILC.
• Fermilab’s efforts are focused on two main areas of the ILC
– Main Linac Design
– Civil and Site Development
• Main Linac R&D:
– The goals are to demonstrate the feasibility of all Main Linac
technical components, develop engineering designs, estimate
costs, explore cost reduction, and engage industry in the
Americas region
• Civil and Site Development
– Fermilab is working with the GDE and international partners to
develop a matrix for comparing possible ILC sites
– Fermilab is also working to develop Americas region sites at or
near Fermilab for the RDR.
Americas Region
Fermilab
Main Linac R&D at Fermilab
•
The main thrust of the Fermilab ILC Accelerator R&D is to establish
Americas region technical capabilities in the Superconducting RF Cavity and
Cryomodule technology. The main goals are
– 1) Cavity technology development in the Americas region to routinely
achieve > 35 MV/m and Q ~0.5-1X1010,
– 2) ILC Cryomodule design, fabrication, and cost reduction
– 3) Develop facilities (ILC Test Accelerator-ILCTA) to fully test the basic
building blocks of the Main Linac (to evaluate performance and
reliabilities issues)
– 4) Explore Main Linac accelerator physics and design issues ( e.g.
simulation of emittance preservation, RF control, feedback systems, etc.)
– 5) RF power system development ( modulators )
– 6) LLRF, Instrumentation and Controls development
Americas Region
Fermilab
ILC 1.3 GHz Cavities at FNAL
Bead pull RF
Testing @
FNAL
4 cavities received from ACCEL
4 cavities on order at AES
4 cavities expected from KEK
•
•
•
•
•
•
•
Joint ANL/FNAL
BCP/EP
Facility
Industrial fabrication of cavities.
BCP and vertical testing in collaboration with Cornell (25 MV/m)
EP and vertical testing in collaboration with JLab. ( 35 MV/m)
Joint BCP/EP facility being developed at ANL (late 06)
High Power Horizontal test facility @ FNAL (ILCTA-MDB)
Vertical test facility under development @ FNAL (ILCTA-IB1)
Single/large grain Crystal cavity development in collaboration with Jlab.
Americas Region
Fermilab
SCRF Infrastructure at FNAL
PPD
Machine
shop
(MAB)
Meson
Detector
Building
(MDB)
ILCTA-MDB
Cryogenics
Installation
60 W @ 1.8 K
TD MP9
Cryomodule
Assembly
Facility (CAF)
First 1.3 GHz
TESLA Cavity
in MDB
Cold and RF
power in Dec
AD Cryo
Dept.
Americas Region
Fermilab
Cryomodule Assembly Facility (CAF) at FNAL
• Vertically tested cavities will be dressed (He vessel, coupler,
etc) in CAF clean rooms prior to horizontal test at ILCTA-MDB.
•Horizontally tested cavities assembled into a string at CAF
• Final Cryo-module assembly takes place at CAF
CAF-MP9
Class 10 and 100 clean rooms
ordered, operational by March 06
Parts for new Cryomodule
Assembly fixture in IB4
•CAF design intended to improve on DESY facility
•Expect parts for a type III cryomodule from DESY; FNAL is
building a 3.9 GHz ( 3rd harmonic) cryomodule for DESY
•CAF ready to start fabrication of cryomodules by summer of 06
Americas Region
Fermilab
Cryomodule Design at FNAL
• Industrial fabrication and cost reduction of the ILC cryomodule
are both crucial issues for a realistic ILC cost estimate
• In FY05 Fermilab started on converting drawings of the
DESY/INFN design of the ILC cryomodule (Type-III+) to US
standards for U.S. vendor fabrication and for cost reduction.
• Next goal is to design an improved ILC cryomodule (Type-IV).
Also working on the quadrupole
design and on piezo-electric
control of Lorentz detuning
Americas Region
Fermilab
Cryomodule string test: ILCTA-NML at Fermilab
New Muon Lab
(NML)
FNPL Photo-Injector
Building a dedicated ILC cryomodule string test facility in the New Muon
Lab
– Building is cleaned out except for removal of CCM ( in progress)
– Started to install cryogenic system
– Move FNPL Photo-injector to provide electron beam (Late FY06)
– Upgraded FNPL will provide beam tests of ILC cryomodules
Americas Region
Jefferson Lab
Jefferson Lab : Develop electropolishing processes for
1.3 GHz cavities
•
•
•
FY06 Funding (MOU with FNAL)
$600k
Objectives:
– Commission the Jefferson Lab EP and HPR processing and Vertical
Test systems for 1.3 GHz TESLA cavities.
– Carry out processing of cavities from a variety of sources
– Develop and refine processing parameters.
– Carry out detailed test program planning for individual cavities and
evaluation of results.
– Develop more cost effective procedures with high yield.
– Develop written procedures and proposals for future improvements
and toward industrial transfer.
– Provide or process samples as appropriate for the SCRF materials
program at FNAL
– Fabricate two TESLA 9-cell cavities from large grain material
Status:
– DESY cavities needed to begin
infrastructure development
-- received by FNAL
Americas Region
Jefferson Lab
Jefferson Lab : Fabricate, process and test cavities from
large-grain/single-crystal material
• FY06 Funding (direct transfer)
$300k
• Objectives:
– Several single cell and at least one multi-cell cavity made from
large grain/single crystal niobium
– Improved buffered chemical polishing system for producing
very smooth rf surfaces on large grain/single crystal material
– Test cavity for superconducting rf joint investigations
– Optimization studies of superstructure configuration based on
superconducting joint
– Two cavities suitable to be combined into a superstructure
– Engineering package for the completion of a superstructure
assembly ready for cold tests
Americas Region
Jefferson Lab
Status: large-grain/single-crystal material
cavity: fabrication and test
• Superconducting joint cavity
- completed, tests pending
• single cell cavities from large grain material of different vendors
(CBMM, Ningxia, Wah Chang and W.C.Heraeus)
– fabricated, treated and tested
• A 7-cell Low Loss cavity from large grain material
– completed, being tuned and will be tested in next 2 weeks
• fabrication of 9- cell aluminum model, 2 LL single-cells, 9-cell
TESLA-shape Nb cavity, and dies and trim fixtures for the TESLA
shape cavity
– complete
• Issue: Determining correct modification of cell shape to yield LL
geometry after stiffening ring welding
Americas Region
Cornell
Cornell LEPP ILC SCRF activities
Preparations for BCP and HPR in Clean Room for
9-cell from Fermilab (ACCEL production)
Vertical EP
Development at
Cornell
Americas Region
Cornell
Cornell LEPP ILC SCRF activities
Re-entrant Cavity Shape
47 MV/m at Cornell…Later 52 MV/m at KEK
9-cell re-entrant cavity ordered from AES
Americas Region
Cornell
Cornell LEPP ILC accelerator physics activities
• RTML design
• LET emittance preservation simulation studies
• Damping ring optimization:
• studies of wigglers: electromagnetic design, impact
on ring dynamic aperture
• studies of fast kickers
• Positron source
•undulator design:
•E166 participation
• Study of the use of CESR as an ILC positron damping
ring test facility (after 2007)
• Supported by NSF and DOE university grants and NSF
LEPP co-operative agreement
Americas Region
ANL
ANL Plan for ILC-GDE/FY06
• SCRF Cavity Electropolishing at the ANLFNAL Joint Facility
– Leverage the new (~$2M) chemistry
facility and Argonne expertise to build a
complete EP apparatus for ILC-type 9-cell
cavities
– Close collaboration with FNAL
– The EP to be operational in FY 06,
processing in FY07
• Positron Source Development (1.95 FTE and $10K M&S; ANL will
provide $90K)
– A comprehensive start-to-end simulation of conventional,
polarized, and keep-alive sources, in collaboration with SLAC
– Optics for positron beam separation and selection
– Conventional adiabatic matching device based on Bitter magnet
Americas Region
ANL
ANL Plan for ILC-GDE/FY06
• Damping Ring Design and Optimization(1.4 FTE and
$10K M&S; ANL will provide $40K )
– Lattice optimization including practical effects (errors,
injection/extraction,...) using multi-objective
evolutionary algorithms; Improve simulation tools and
correction schemes for vertical emittance and
coupling
– Particle tracking for single-bunch instabilities with 3-D
wakefield
– Studies of ion instability in the APS ring
– Design of a hybrid wiggler satisfying the field quality
tolerance
• ANL can contribute significantly in other areas, for
example in the control system
Americas Region
SLAC
SLAC ILC Accelerator Design (RDR)
• Strong efforts throughout the machine design
–
–
–
–
–
–
Electron and positron sources
Contributions to the damping rings and RMTL
Main linac design and instrumentation
Rf sources
Beam Delivery System
Civil construction and conventional facilities
• Able to provide leadership for some RDR Area
Sub-systems
For more detail see: http://www-project.slac.
stanford.edu/ilc/talks/SLAC_SPC_ILC_12-05.pdf
Americas Region
SLAC
SLAC ILC R&D Program
• Broad R&D Program
– Availability issues (~1.3 M$)
Fast
(redundant)
kicker for
DR
• Kickers, Power supplies, and control system
– Beam instrumentation (~1 M$)
signal from ACC1, cav 1, cplr 2
1.4
1.3
1.2
1.1
Volts
1
0.9
0.8
0.7
0.6
0.5
0
0.5
1
1.5
2
2.5
time - s
3
3.5
4
4.5
-4
x 10
TTF HOM
Signal
800 monitors
installed
RF BPM
for linac
– Linac beam dynamics (~0.5 M$)
• SC quad and BPM
SC Quad for
magnetic
center tests
Americas Region
SLAC
12 KV Marx Cell
SLAC ILC R&D Program
• Broad R&D Program (cont.)
– Linac rf sources (~1.5 M$)
• Marx generator modulator
– Electron and Positron sources
(~1.2 M$)
• NC structure, E-166, electron
laser, and cathode
– Damping rings (~ 0.3 M$)
• SEY studies in PEP-II
Positron capture
structures
SEY Test Chamber for PEP-II
Americas Region
SLAC
ATF Extraction Kicker
SLAC ILC Test Facilities
• Five efforts:
– ATF damping ring (~0.7 M$) (includes R&D)
• Over 1 FTE in residence at KEK
– ATF-2 (~1 M$) (includes R&D efforts)
• Construction of magnets, PS, and
instrumentation
– ILCTA at FNAL (~0.2 M$)
• Cryo-system design and modulator switch
– ESA MDI Test Facility (~0.5 M$)
– ESB L-band klystron station (~1.4 M$)
ATF2 Optics
ESA Energy
Spectrometer
Americas Region
SLAC
SLAC End Station B (RF Test Fac.)
• Develop 5 MW and 10 MW stations
– Test rf system components
– Reuses extensive infrastructure
Americas Region
LBNL
LBNL: Accelerator Design
• Lattice designs for damping rings and
injection/extraction lines (1.0 FTE)
• Characterization of some collective
effects, including space-charge, IBS
and microwave instability (0.7 FTE)
• Contribution to development and
optimization of bunch compressor
lattices (0.2 FTE)
Americas Region
LBNL
LBNL: Test Facilities
• Physics design of stripline kickers for
single-bunch extraction at KEK-ATF
(0.15 FTE)
• Contribution to beam-dynamics studies
at KEK-ATF, including CSR studies,
low-emittance tuning and nonlinear
dynamics (0.2 FTE)
Americas Region
LLNL
LLNL ILC Activities in FY06
• Positron target design
– $600K (1.5FTE)
– Detailed engineering
– Target simulations
• Energy deposition,
radiation damage,
activation
• Marx modulator
– $200K (.75 FTE)
– Mechanical engineering of
modulator and test
equipment
Americas Region
• Coupler Test Stand
– $100K (.25FTE)
– Evaluation and analysis of
RF coupler designs
LLNL
• NanoBPM
– $100K (.35 FTE)
– Installation and data taking
of nanometer resolution
metrology frame
$1M (3 FTE) program using LLNL’s engineering
resources to advance the ILC design
Americas Region
BNL
ILC Final Focus Magnet Development
Brookhaven National Lab
FY06 goals:
•Continue to support the baseline design efforts in
WG4
•Support the development of the Conceptual
Design/Cost Estimate for the Beam Delivery System
•Fabricate and test a short proof of principle shielded
final-focus-like quadrupole coil
•Fabricate and test a short proof of principle
sextupole/octopole corrector-like coil
Americas Region
BNL
Final Focus Magnet Development
Brookhaven National Lab
Winding tests octopole coil - how
small can you go ?
Shielded quadrupole proof of
principle coil fabrication
Beam delivery system
Conceptual Design
work
2 FTE’s ( 1 Sci, 0.75
Eng, 0.25 Design)
$320K (labor)
Coil R&D
1 FTE (0.5 Eng, 0.5
Tech)
$130K (labor) $50K
(materials)
Total
3 FTE’s
$500K
Americas Region
TRIUMF
Potential TRIUMF Accelerator R&D Resources for ILC
The specific nature of Canadian involvement is under
development. Some potential collaboration areas
have been identified, along with relevant LHC
experience:
The design of kicker magnets and the construction of
associated pulse-forming networks and fast switches
using power semiconductors
Precision room temperature magnet systems
e.g. 52 twin-aperture quadrupoles built at Alstom Canada
Beam instrumentation and readout systems
e.g. 2000 matched-pair 70MHz low pass filters
e.g. VME64x compliant Digital Aquisition Board (DAB)
Contributions to beam dynamics & lattice calculations
for damping rings.
Americas Region
TRIUMF
Building on expertise developed for TRIUMF
ISAC radioactive beams accelerator, additional
possible areas are:
Remote handling design/consulting of target
stations possible applicability to conventional
positron source
Peripheral aspects of superconducting r.f. such
as cryogenic coolant distribution system
design/consulting small quantity e-beam welding
of niobium for low-beta, low-frequency
UBC -Tom Mattison
Vibration control systems and alignment of components for final focus
system; also interest in abort kickers
Americas Region
Funding for the TDR (FY07-09)
• TDR to be developed during the FY07-09 period
– Ready for construction start around 2010
• R&D funds must grow substantially to support TDR
– Need a global R&D plan without which it is difficult to
estimate funding requirements – working on this
• Rough funding plan listed below given to DOE
– Develop of facilities for sources, DRs, BDS, etc but …
– Growth mainly for main linac R&D and industrialization
– Site development work must begin if US is to offer to host
R&D activity
FY07
FY08
FY09
Total
TDR+supporting R&D at DOE labs
60
70
60
190
Industrialization
10
20
45
75
30
60
90
120
165
355
Site civil engineering (host region only)
Total
70
Americas Region
ILC-Americas Regional Team
Summary/Conclusion
FY06 resources by functional area
W BS
1
2
3
4
5
Description
Program direction and administration
Accelerator design, including RDR
Research and development
Engineering, including cost estimates
Infrastructure and test facilities
Laboratory
W P leader FTE
Total
9.4
32.4
33.5
0
18.9
Labor
1,097
4,050
4,600
0
2,220
94.1
11,967
M&S
780
764
5,221
0
2,630
Indirect
453
1,553
2,298
0
1,069
Total
2,330
6,367
13,460
0
5,919
9,395
5,374
28,077
FY06 resources by machine area
MACHINE AREA
FTE
Program direction and administration
9.4
Management
4.3
Global systems
5.5
Electron sources
3.3
Positron sources
7.5
Damping rings
7.9
Bunch compressor
1.6
Main Linacs: Optics, beam dynamics, instrumentation 7.1
Main Linacs: RF systems
18.0
Main Linacs: Cavities and Cryomodules
16.5
Beam delivery system
10.2
Conventional facilities
3.0
TOTAL
94.1
Labor
1,097
506
744
390
1,310
1,061
198
837
2,240
1,958
1,267
360
11,967
M&S
780
100
460
100
202
567
0
50
2,170
3,896
520
550
Indirect
453
188
330
151
574
446
77
295
1,019
1,115
514
212
Total
2,330
794
1,707
676
2,086
2,298
312
1,248
5,493
7,143
2,867
1,122
9,395
5,374
28,077
Download