Centralized Homeless Service System (C.H S.S.)

advertisement
Centralized Homeless
Service System
(C.HeS.S.)
The Green Team
Tuesday, July 26, 2016
CS410 – Workforce Training
November 5, 2007
CS410 Green Team
1
The Green Team
Supervisor
Janet Brunelle
Software
Coordinator
Hardware
Coordinator
Project Manager
Keith Barth Jr.
Nathan Aldrich
Nathapon “Max”
Siangchokyoo
Financial Analyst
Marketing
Coordinator
David Bonatz
Jeffrey Taylor
November 5, 2007
CS410 CHeSS
2
Homelessness Defined
• An individual who lacks a fixed, regular,
and adequate night time residence
• An individual who has a primary night
time residence that is:
• A public or private place not designed for, or
ordinarily used as, regular sleeping
accommodations for human beings
• Supervised publicly or is a privately operated
shelter designed to provide temporary living
accommodations
November 5, 2007
CS410 CHeSS
3
What Causes Homelessness?
•
•
•
•
•
Low Income - Can’t Afford Rent
Alcohol and Drug Abuse - Sudden Loss of Employment
Domestic Abuse
Mental or Physical Disability
Many more…
http://www.nationalhomeless.org/civilrights/lawrence/lawrence.html
November 5, 2007
CS410 CHeSS
4
Who is Homeless?
• On any given night in Norfolk, 500800 people are on the streets
• Approximately 10,400 Virginians are
homeless
• Roughly 3.5 million Americans will
experience homelessness each year
•
•
•
•
November 5, 2007
25% have jobs
20% have mental disorders
40% are American Veterans
33% are families with children
CS410 CHeSS
5
Effects of Homelessness
Damaged reputation of localities with notable
homeless outbreaks
Concern for public safety from both criminal and
medical standpoints
The appropriation of tax money to fund homeless
service projects
November 5, 2007
CS410 CHeSS
6
The Price of Homelessness
•
"A study in San Diego that tracked 15
homeless individuals for 18 months found
they alone cost the government and other
organizations $3 million in that period, or
around $133,000 per person per year.”1
•
Proposed budget for homeless aid of
$35.2 billon nationally in 2008 2
1. http://www.uticaod.com/opinion/x751579913/index.html?printview=true
2. http://www.hud.gov/news/release.cfm?content=pr07-008.cfm
November 5, 2007
CS410 CHeSS
7
What is the Problem?
Homeless people are not getting
the individualized assistance
they need due to a lack of
communication and failure to
coordinate efforts.
November 5, 2007
CS410 CHeSS
8
Problem Characteristics
• Outdated or complete lack of communication between
organizations, the government, and the homeless
population
• Lack of understanding of homelessness on a grand
scale and an individual level
• Lack of real time information for certain homeless
people and the homeless population of a locality
November 5, 2007
CS410 CHeSS
9
Communication Issues
• Information is shared through verbal
communication, hard copy reports, email, etc.
• Information about services is not always
shared with homeless people
• Data is handwritten or entered manually into
basic spreadsheets and other files
• Data cannot be provided to the government
and other organizations instantly
November 5, 2007
CS410 CHeSS
10
The Assistance Cycle
More
Homeless
Organizations
Population
Volunteer to Help
Grows
Lack of
Communication
Lack of
Understanding
November 5, 2007
Problem
Fewer
People
Helped
Inefficient Use
of
Resources
CS410 CHeSS
“Understanding
homelessness
is a necessary
step in
addressing it
successfully”
– HUD Secretary
Alphonso
Jackson
11
Resource Efficiency
Wasted
Resources
Homeless
Population Utilization
Services Being
Provided by the
Government
Wasted
Resources
Services Being
Provided by
Organizations
Services Being
Received
November 5, 2007
CS410 CHeSS
12
Current National Efforts
HMIS - Homeless Management Information
System
• Started in 1998 as a directive from the Department of
Housing and Urban Development
• It was decided to use aggregated data rather then a
national database
November 5, 2007
CS410 CHeSS
13
Current Local Efforts
• HIMS was created as a local HMIS
• The software was too expensive for groups to
purchase ($500-600)
• Nonprofit groups did not have access to a network
infrastructure for information and communication
purposes
• HIMS is now open source with a GNU General Public
License
• Identification is required by local organizations before
an individual can receive assistance
November 5, 2007
CS410 CHeSS
14
Current Local Efforts
• Ghent Area
Ministries
• Project Connect
• Individual
Organizations
• Government
Services
November 5, 2007
CS410 CHeSS
15
Objectives
• Increase Communication
• Real-time information exchange
• Raise homeless awareness of
service provided
November 5, 2007
CS410 CHeSS
16
CHeSS
• Centralized
Homeless Service
System (CHeSS)
– Communication
Network
Infrastructure
– Real-time Statistics
– Uniform Data Entry
– Simple
Identification
November 5, 2007
CHeSS
CS410 CHeSS
17
Features of CHeSS
• Centralized database of homeless profiles
• Centralized calendar system of services
• One-time manual user input
• Easy-to-use GUI
• Identification software that will update information
November 5, 2007
CS410 CHeSS
18
How Does CHeSS Work?
November 5, 2007
CS410 CHeSS
19
What’s in the Box
Government CHeSS
Organization CHeSS
Database Administration
Package
Identification Hardware to
Database Interface
November 5, 2007
Identification
Hardware
CS410 CHeSS
20
Through the Door
Homeless
Person
Identified
Already Registered?
Homeless person enters
service building/area
and is identified.
If not in the system,
person is entered.
All relevant data is
entered in person’s
profile.
Person is served.
November 5, 2007
Yes
Automatic
Profile Updates
No
Manual Data
Entry – Basic
Yes
Enter Personal
Information?
Manual Data
Entry – Advanced
CS410 CHeSS
No
Service is Provided
21
GUI Screen1
November 5, 2007
CS410 CHeSS
22
GUI Screen2
November 5, 2007
CS410 CHeSS
23
The Hallway
Personal information through
case management or
voluntary participation opens
the door to individualized
services and opportunities.
In the time to come, the
homeless person’s needs will
be identified by the groups
that already exist for those
people in need.
November 5, 2007
CS410 CHeSS
24
Business Plan
CHeSS
Marketing Plan
Evaluation Plan
Funding Plan
Risk Plan
Management Plan
November 5, 2007
CS410 CHeSS
25
Marketing Strategy
1. Show federal government CHeSS meets and
surpasses their standards
2. Show local government how they will benefit
from investing in CHeSS
•
The above are via letters, lobbyists, and the like
3. Convince organizations to utilize CHeSS
•
•
Show how real-time communication aids their cause
Government may help in this by manipulating funding
November 5, 2007
CS410 CHeSS
26
Who is the Customer?
The National Government has many programs to fund the
development of a technological solution to homelessness.
The Local and State Governments are left with the responsibility of
handling the homeless problem.
Non-profit organizations and government services are offered to
homeless and impoverished citizens.
Primary Customer:
Local and State Governments
November 5, 2007
CS410 CHeSS
27
Customer Costs
Organizations and The Government
• Government Database Package - $47,270
Based on an average 25 Organizations
Item
•
•
•
•
•
Barcode Printer - $1500
Film Roll - $20 (100 cards)
Barcode Scanner - $130
Printing Software - $10
Card - $.18
Cost
Government Software
Package
1
$
25,000.00
Organization Software
Package
1 per org
$
-
Organization Training
$250 per
org
$
6,250.00
Bar Code Scanner
$129 per
org
$
3,225.00
Yearly
$
5,000.00
5
$
7,795.00
$
47,270.00
Software Maintance
Bar Code Printer
Total
November 5, 2007
#
CS410 CHeSS
28
What are the Benefits?
Organizations and The Government
• Improved communication will lead to a more
efficient distribution of services
• Recorded data will provide an overall
understanding of the homeless situation
• Real time information will help the government
distribute services and resources based on
individual needs
November 5, 2007
CS410 CHeSS
29
Who Benefits?
HOMELESS
CITIZENS
BUSINESSES
November 5, 2007
CS410 CHeSS
GOVERNMENT
30
Customer ROI
• Each city’s return on investment can be
seen when the original cost of
implementing CHeSS has been saved
through a more efficient distribution of
resources.
November 5, 2007
CS410 CHeSS
31
Competition Matrix
November 5, 2007
CS410 CHeSS
32
Management Plan - Communication
Live:
Sunday Night
Monday Morning
Tuesday Night
Wednesday
Morning
Saturday Morning
November 5, 2007
Other Communication:
MSN Chat: Thursday
E-Mail: Daily Updates
Cell Phones: Planning
CS410 CHeSS
33
Risks and Mitigations Plan
• Market limitations
– Government does not buy
– Organizations do not participate
• Security concerns
– Storage of personal information
– Access of medical information
• Social Acceptance
– Homeless do not storage of information
– Homeless lose or do not carry cards
November 5, 2007
CS410 CHeSS
34
Risk Probability/Impact Matrix
a)
5
I
m
p
a
c
t
4
3
b)
c)
a
e
2
1
c
b
f
d
d)
e)
g
1
2
3
Probability
November 5, 2007
4
5
f)
g)
CS410 CHeSS
The government does not
buy the system
Migration of Data
Personal information
storage
Medical information
access
Lack of organization
participation
Homeless do not want
information stored
Homeless lose or do not
carry cards
35
Project Flow - Outline
November 5, 2007
CS410 CHeSS
36
Milestones and Deliverables
Phase 0 (CS410)
Phase 1 (CS411)
Feasibility Presentation
Team website
Presentation
Software
Requirements Document
Design Document
Application Code
Data Mining Code
Formatting Code
Milestone Presentation
Presentation
Final Presentation
Product Website
Presentation
Demonstration Prototype
Completed Prototype
Testing
Test Plan Document
SBIR document
NSF SBIR Proposal Phase 1
November 5, 2007
CS410 CHeSS
SBIR document
Grant Proposal Phase 2
37
Milestones and Deliverables
Phase 2: Critical Design
Phase 3: Production
Out Years
Hardware
Hardware Requirements
Document
Database Setup
Production
Government Contract
Organization Contract(s)
Software
Requirements Document
Design Document
Database Application Code
POS Application Code
Data Mining Code
Test Plan
November 5, 2007
Financing
Venture Capital/Investment
Distribution
Distribution Contract
Marketing
Advertising Campaign Launch
CS410 CHeSS
38
Phase 0 - Organization
November 5, 2007
CS410 CHeSS
39
Phase 0 – Gantt Chart
November 5, 2007
CS410 CHeSS
40
Phase 0 - WBS
ID
Task name
Duration
Start
Finish
1 Phase 0 - Concept
86 days
9/19/2007
12/14/2007
2
Project Start
0 days
9/19/2007
9/19/2007
3
Conception
30 days
9/19/2007
10/19/2007
4
Develop Project Team
1 day
9/19/2007
9/20/2007
5
Individual Project research
11 days
9/19/2007
9/30/2007
6
Define Project
18 days
10/1/2007
10/19/2007
7
Project Research And Documentation
69 days
10/2/2007
12/10/2007
8
Feasibility Research and Presentation
14 days
10/8/2007
10/22/2007
9
Milestone and Final Research and Presentation
41 days
10/29/2007
12/10/2007
10
Design
4 days
11/1/2007
11/5/2007
11
Marketing
4 days
11/6/2007
11/10/2007
12
Financial
3 days
11/11/2007
11/14/2007
13
Technical
3 days
11/15/2007
11/18/2007
14
Risk
3 days
11/19/2007
11/22/2007
15
SBIR Creation
21 days
11/19/2007
12/10/2007
16
Website
78 days
9/27/2007
12/14/2007
November 5, 2007
CS410 CHeSS
41
Phase 1 Organization
November 5, 2007
CS410 CHeSS
42
Phase 1 – Gantt Chart
November 5, 2007
CS410 CHeSS
43
Phase 1 - WBS
ID
Task name
Duration
Start
Finish
1 Phase 0 - Concept
86 days
9/19/2007
12/14/2007
2
Project Start
0 days
9/19/2007
9/19/2007
3
Conception
30 days
9/19/2007
10/19/2007
6
Define Project
18 days
10/1/2007
10/19/2007
7
Project Research And Documentation
69 days
10/2/2007
12/10/2007
8
Feasibility Research and Presentation
14 days
10/8/2007
10/22/2007
9
Milestone and Final Research and Presentation
41 days
10/29/2007
12/10/2007
15
SBIR Creation
21 days
11/19/2007
12/10/2007
16
Website
78 days
9/27/2007
12/14/2007
17 Phase 1 - Proof of Concept
100 days
1/17/2008
4/27/2008
18
Reassemble Project Team
0 days
1/17/2008
1/17/2008
19
Planning and Requirements
22 days
1/17/2008
2/8/2008
20
Define Approach
3 days
1/18/2008
1/21/2008
21
Define Functional Level Requirements
10 days
1/22/2008
2/1/2008
22
Determine Development Platform
4 days
2/2/2008
2/6/2008
23
Requirements
7 days
1/19/2008
1/26/2008
24
Interface Design
18 days
2/9/2008
2/23/2008
25
Development
18 days
2/24/2008
3/14/2008
26
Testing
17 days
3/15/2008
3/31/2008
27
Implement and Design
15 days
4/1/2008
4/15/2008
28
SBIR Creation
27 days
3/31/2008
4/27/2008
29
Website
98 days
1/19/2008
4/27/2008
November 5, 2007
CS410 CHeSS
44
Phase 1 - Budget
Direct Labor
#
Hourly
Project Manager
1
$ 49.85
Publication Specialist
1
Documentation Specialist
Risk Management Director
Hours
Direct Labor
Overhead
Total
150
$
7,478
$
2,991
$
10,469
$ 35.00
110
$
3,850
$
1,540
$
5,390
1
$ 28.00
110
$
3,080
$
1,232
$
4,312
1
$ 45.00
90
$
4,050
$
1,620
$
5,670
Software Director
1
$ 70.00
140
$
9,800
$
3,920
$
13,720
PHP Programmer
2
$ 31.25
130
$
8,125
$
3,250
$
11,375
GUI Programmer
1
$ 37.50
130
$
4,875
$
1,950
$
6,825
MySQL Programmer
1
$ 46.75
130
$
6,078
$
2,431
$
8,509
C++ Programmer
1
$ 19.50
130
$
2,535
$
1,014
$
3,549
Data Analyst
1
$ 46.85
135
$
6,325
$
2,530
$
8,855
1
$ 35.00
140
$
4,900
$
1,960
$
6,860
Financial Director
1
$ 35.85
120
$
4,302
$
1,721
$
6,023
Financial Research Specialist
1
$ 23.00
90
$
2,070
$
828
$
2,898
CS410 CHeSS$
67,467
$
26,987
$
45
94,453
Administration
Production
Software
Hardware
Hardware Director
Financial
Total
November 5, 2007
Phase 2 – Organization
November 5, 2007
CS410 CHeSS
46
Phase 2 – Gantt Chart
November 5, 2007
CS410 CHeSS
47
Phase 2 - WBS
ID
Task name
1 Phase 0 - Concept
Duration
Start
Finish
86 days
9/19/2007
12/14/2007
17 Phase 1 - Proof of Concept
100 days
1/17/2008
4/27/2008
30 Phase 2 - Critical Design
424 days
5/1/2008
6/30/2009
31
Develop Project Team
36 days
5/1/20008
6/5/2008
32
Planning and Requirements
101 days
6/6/2008
9/14/2008
34
General system design
29 days
6/7/2008
7/6/2008
35
Models
9 days
7/7/2008
7/16/2008
36
Views
23 days
7/17/2008
8/9/2008
37
Main Template
20 days
8/10/2008
8/30/2008
33
Setup
52 days
9/15/2008
11/6/2008
38
Design Database
61 days
11/7/2008
1/7/2009
39
Database Population
23 days
12/15/2008
1/7/2009
40
Development
67 days
1/8/2009
3/24/2009
41
Testing
82 days
3/25/2009
6/15/2009
42
Documentation and Finalize Production
64 days
4/27/2009
6/30/2009
43
Website
420 days
5/5/2008
6/30/2009
November 5, 2007
CS410 CHeSS
48
Phase 2 - Budget
Direct Materials
# of Units
Cost/Unit
Total
Server (PowerEdge T105)
1
$
723.00
$
723
Windows Server 2003, Standard Edition
1
$
799.00
$
799
Windows Server 2003, CAL
25
$
49.00
$
1,225
Microsoft Project Server
1
$
999.00
$
999
barcode ID card
1000
$
0.18
$
180
Bar Code Printer
1
$ 1,559.00
$
1,559
Bar Code Scanner
2
$
129.00
$
258
Domain Name Registrations
5
$
19.00
$
95
Bar Code ID Kit
1
$
900.00
$
900
$
6,738
Total
November 5, 2007
CS410 CHeSS
49
Phase 2 - Budget
Direct Labor
#
Hourly
Project Manager
1
$
49.85
Publication Specialist
1
$
Documentation Specialist
1
Risk Management Director
Hours
Direct Labor
Overhead
Total
1000
$
49,850
$
19,940
$
69,790
35.00
950
$
33,250
$
13,300
$
46,550
$
28.00
950
$
26,600
$
10,640
$
37,240
1
$
45.00
500
$
22,500
$
9,000
$
31,500
Software Director
1
$
70.00
900
$
63,000
$
25,200
$
88,200
PHP Programmer
4
$
30.00
950
$
114,000
$
45,600
$
159,600
GUI Programmer
1
$
37.50
900
$
33,750
$
13,500
$
47,250
MySQL Programmer
1
$
46.75
950
$
44,413
$
17,765
$
62,178
C++ Programmer
1
$
19.50
900
$
17,550
$
7,020
$
24,570
Data Analyst
1
$
46.85
900
$
42,165
$
16,866
$
59,031
1
$
35.00
900
$
31,500
$
12,600
$
44,100
Financial Director
1
$
35.85
850
$
30,473
$
12,189
$
42,662
Financial Research Specialist
1
$
23.00
900
$
20,700
$
8,280
$
28,980
$
529,750
$
211,900
$
741,650
Administration
Production
Software
Hardware
Hardware Director
Financial
Total
November 5, 2007
Combined Total
CS410 CHeSS
50
$
748,388
Phase 3 - Organization
November 5, 2007
CS410 CHeSS
51
Phase 3 – Gantt Chart
November 5, 2007
CS410 CHeSS
52
Phase 3 - WBS
ID
Task name
Duration
1 Phase 0 - Concept
Start
Finish
86 days
9/19/2007
12/14/2007
17 Phase 1 - Proof of Concept
100 days
1/17/2008
4/27/2008
30 Phase 2 - Critical Design
424 days
5/1/2008
6/30/2009
44 Phase 3 - Production and Out Years
183 days
4/1/2009
9/30/2009
45
26 days
4/1/2009
4/27/2009
5 days
4/22/2009
4/27/2009
46
Organize Team
Office Setup
47
Hiring People
14 days
4/28/2009
5/11/2009
48
Prepare Production
31 days
5/12/2009
6/12/2009
49
Manufacture
45 days
6/12/2009
7/26/2009
50
Initial and Nationwide Rollout
168 days
6/16/2009
9/30/2009
61 days
6/16/2009
8/16/2009
51
Advertising
52
Determine Advertising Agency
4 days
6/16/2009
6/20/2009
53
Prepare Advertising Materials
7 days
6/21/2009
6/28/2009
54
Launch Marketing Campaign
14 days
6/29/2009
7/13/2009
55
GUI Design
10 days
7/14/2009
7/24/2009
56
Add Company Claim Policies
10 days
7/25/2009
8/4/2009
57
Setup Servers and Hardware at customer location
1 day
Varies
Varies
58
Update Best-fit Module
20 days
8/5/2009
9/30/2009
173 days
4/10/2009
9/30/2009
59
Website maintanence and Documentation
November 5, 2007
CS410 CHeSS
53
Phase 3 - Budget
Direct Labor
#
Hourly
Hours
Direct Labor
Overhead
Total
1
$
49.85
700
$
34,895
$
13,958
$
48,853
Software Director
1
$
70.00
550
$
38,500
$
15,400
$
53,900
Database Administrator
1
$
46.85
650
$
30,453
$
12,181
$
42,634
Web Developer
1
$
29.00
625
$
18,125
$
7,250
$
25,375
1
$
35.00
650
$
22,750
$
9,100
$
31,850
Marketing Director
1
$
85.00
650
$
55,250
$
22,100
$
77,350
Market Research Manager
1
$
48.85
650
$
31,753
$
12,701
$
44,454
Marketing Specialist
1
$
38.50
625
$
24,063
$
9,625
$
33,688
Customer Support Rep
1
$
11.50
625
$
7,188
$
2,875
$
10,063
Technical Instructor
1
$
24.00
650
$
15,600
$
6,240
$
21,840
Lobyist
1
$
58.00
625
$
36,250
$
14,500
$
50,750
1
$
35.85
650
$
23,303
$
9,321
$
32,624
$ 135,251
$
473,379
Adminstration
Project Manager
Production
Software
Hardware
Hardware Director
Marketing
Financial
Financial Director
Total
November 5, 2007
CS410 CHeSS
$ 338,128
54
Funding Plan
• SBIR Grant Proposal – Phase 1
$100,000
6 Months
NSF
• SBIR Grant – Phase 2
$750,000
2 Years
NSF
• Small Business Loan – Phase 3
$475,000
November 5, 2007
Start-up
Loan
CS410 CHeSS
55
Break-Even
Break Even Analysis
$400,000
$300,000
$200,000
$100,000
$$(100,000) 0
5
10
15
20
25
30
35
$(200,000)
$(300,000)
$(400,000)
$(500,000)
$(600,000)
# of Cities
November 5, 2007
CS410 CHeSS
56
Evaluation Plan
•
•
•
•
•
Design Reviews
Technical
Financial (Cost)
Schedule
Unit and Acceptance Testing
– required to complete milestones
• Testing
– Risks and other factors
November 5, 2007
CS410 CHeSS
57
Conclusion
• People are homeless for many different reasons,
and homelessness drains societal resources.
• Current efforts to help the less fortunate are
inefficient and outdated.
• CheSS will provide a network infrastructure to
improve communication and provide services to
the homeless on an individual basis.
November 5, 2007
CS410 CHeSS
58
Questions
November 5, 2007
CS410 CHeSS
59
References
•
•
•
•
•
•
•
•
Barrett Transitional Home (BTH) - transitional housing in Norfolk
– http://groups.hamptonroads.com/BTH/
Non profit congress - effective things of a non-profit organization
– http://www.nonprofitcongress.org/files/Briefing%20Book%20Excerpt%20pg%20816.pdf
List of how much federal government is spending as well as in VA
– http://www.hud.gov/local/va/news/pr2007-02-20.cfm
Directory of Organizations in VA
– http://www.nationalhomeless.org/resources/local/virginia.html
Study about fewer homeless people in Norfolk
– http://content.hamptonroads.com/story.cfm?story=118740&ran=11099
Nation taking a new look at homelessness, solutions
– http://www.usatoday.com/news/nation/2005-10-11-homeless-cover_x.htm
Homelessness
– http://en.wikipedia.org/wiki/Homelessness
Homeless Statistics
– http://www.uticaod.com/opinion/x751579913/index.html?printview=true
November 5, 2007
CS410 CHeSS
60
References
•
•
•
•
•
•
•
•
HUD's Proposed budget of 2008
– http://www.hud.gov/news/release.cfm?content=pr07-008.cfm
HUD federal funding
– http://www.hud.gov/news/release.cfm?content=pr05007.cfm&CFID=2483991&CFTOKEN=13285473
Service opportunities for the homeless(education, etc...)
– http://www.virginiahomeless.org/
Gospels available by Country/State
– http://www.agrm.org/missions.html
HUD's homeless information in VA
– http://www.hud.gov/local/index.cfm?state=va&topic=homeless
Interagency Council on Homelessness (a 10 year plan)
– http://www.ich.gov/slocal/index.html
Solution to Homelessness
– http://www.csmonitor.com/2006/0104/p13s01-lihc.html?s=planetizen
Homelessness
– http://www.policyalmanac.org/social_welfare/homeless.shtml
November 5, 2007
CS410 CHeSS
61