Orange Team December 10, 2007
1. Phase 0 ………………………………………………………………………….. 3
1.1. Staff and Responsibilities
………………………………………………… 3
2.
Phase 1……….………………………………………………………………….. 4
2.1. Staff and Responsibilities
………………………….……………………… 5
3.
Phase 2……….………………………………………………………………….. 6
3.1. Staff and Responsibilities………………………….……………………… 7
4.
Phase 3……….………………………………………………………………….. 8
4.1. Staff and Responsibilities………………………….……………………… 9
2
Orange Team December 10, 2007
The purpose of this plan is to define the staffing for each phase of the project. This document describes the staff that will be needed for each phase as well as their responsibilities. The salary 1 for each employee is determined at http://www.indeed.com
.
1. Phase 0
This is the first phase of the project where the initial SBIR will be created along with the proposal and milestone presentations. As well, the project's website is created.
For Phase 0, we need the following staff
Figure 1
1.1. Staffs and Responsibility
Project Manager
Assure that all tasks are assigned and are performed with high quality
Resolve difference and conflict
Develop the WBS
Assign resources
Prioritize tasks
Define tasks dependencies
1 Please refer to funding plan for further details.
3
Orange Team
Marketing Specialist
Determine the target market
Support the marketing aspect of the project
Choose and manage the marketing vendor
Determine the overall marketing plan
December 10, 2007
Hardware Specialist / Webmaster
Determine the best hardware for Triton System
Estimate the cost of hardware
Assist the financial specialist with hardware budget
Research sensor technologies and other hardware for Triton System
Research the best method of developing and attaining hardware components
Create the team website that includes team biography, presentations, and documentations
Software Specialist
Determine the algorithm for the Triton System
Estimate the cost of developing the software
Financial Specialist
Determine the most suited method for developing and maintaining the software
Receive fund
Create budget
Determine product cost
Financial and funding plan
2. Phase 1
In this phase, a lab prototype will be developed. Along with this, the SBIR phase 2 proposal will be written. Success will be measured by the successful completion of those
The following staffs will be needed for this phase.
4
Orange Team December 10, 2007
Figure 2
2.1. Staffs and Responsibility
Project Manager
Assure that all tasks are assigned and are performed with high quality
Resolve difference and conflict
Develop the WBS
Assign resources
Prioritize tasks
Define tasks dependencies
Marketing Researcher
Determine the target market
Hardware Specialist/ (Webmaster)
Support the marketing aspect of the project
Determine the overall marketing plan
Determine the best hardware for Triton System
Estimate the cost of hardware
Assist the financial specialist with hardware budget
Research sensor technologies and other hardware for Triton System
Research the best method of developing and attaining hardware components
Create the team website that includes team biography, presentations, and documentations
Software Specialist
Determine the algorithm for the Triton System
Estimate the cost of developing the software
5
Orange Team
December 10, 2007
Determine the most suited method for developing and maintaining the software
Financial Specialist
Receive fund
Create budget
Determine product cost
Financial and funding plan
Product Manager
Determine the functionality that will be included in the Triton System
D efining the requirements from a customer’s perspective
Technical Director
Determine the technical requirements
Managing the technical staff
Determine and solve technical problems
Risk Specialist
Managing project risk
Determine what risks exists in the project
Evaluate risk severity
Probability of the risks
Attempt to mitigate the risks
3. Phase 2
In this phase, an actual prototype of the product will be created.
The following staffs will be needed for this phase.
6
Orange Team December 10, 2007
Figure 3
3.1 Staffs and Responsibility
Project Manager
Assure that all tasks are assigned and are performed with high quality
Resolve difference and conflict
Develop the WBS
Assign resources
Prioritize tasks
Define tasks dependencies
System Hardware Engineer 1 & 2
Determine the best hardware for Triton System
Estimate the cost of hardware
Assist the financial specialist with hardware budget
Research sensor technologies and other hardware for Triton System
Research the best method of developing and attaining hardware components
Webmaster
Create the team website that includes team biography, presentations, and documentations
Manage the web developers in the future
Software Engineer 1 & 2
Determine the algorithm for the Triton System
7
Orange Team
Estimate the cost of developing the software
December 10, 2007
Determine the most suited method for developing and maintaining the software
Financial Specialist
Receive fund
Create budget
Determine product cost
Financial and funding plan
Product Manager
Determine the functionality that will be included in the Triton System
D efining the requirements from a customer’s perspective
Technical Director
determine the technical requirements
managing the technical staff
HR Manager 2
Hire new employees
handle all employees’ paper work
4. Phase 3
In this phase, the delivery of the first product occurs. With the warehouse and manufacturer is secured, the actual product begins. Also, the marketing campaign is rolled out.
The following staffs are needed for this phase.
2 Human resource management skills needed
8
Orange Team December 10, 2007
Figure 4
4.1. Staffs and Responsibility
Project Manager
Assure that all tasks are assigned and are performed with high quality
Resolve difference and conflict
Develop the WBS
Assign resources
Marketing Specialist
Prioritize tasks
Define tasks dependencies
Determine the target market
Support the marketing aspect of the project
Choose and manage the marketing vendor
Determine the overall marketing plan
System Hardware Engineer 1 & 2
Determine the best hardware for Triton System
Estimate the cost of hardware
Assist the financial specialist with hardware budget
Research sensor technologies and other hardware for Triton System
Research the best method of developing and attaining hardware components
9
Orange Team
Webmaster
December 10, 2007
Create the team website that includes team biography, presentations, and documentations
Manage the web developers in the future
Software Engineer 1 & 2
Determine the algorithm for the Triton System
Estimate the cost of developing the software
Determine the most suited method for developing and maintaining the software
Financial Specialist
Receive fund
Create budget
Determine product cost
Financial and funding plan
Product Manager
Determine the functionality that will be included in the Triton System
Define the requirements from a customer’s perspective
Technical Director
Determine the technical requirements
Manage the technical staff
Procurement Manager 3 / Lawyer
Create all contracts
Handle customer negotiations
HR Manager 4
hire new
employees
handling all employees’ paper work
Administrative Assistant
Manage the administrative needs of the staffs
Take minutes, type up paper work, et cetera
Bookkeeper
Produce financial reports of the project
Operations Manager
3 Require legal procurement experience
4 Human resource management skills needed
10
Orange Team December 10, 2007
Manage functional organization of the project
Manage the staff who maintains the product after the project is closed
Triton Customer Support
Take customer orders
Take complaints and questions
G enerally, take care of customers’ needs
11