TRITON STAFFING PLAN TEAM ORANGE

advertisement

TRITON

TM

STAFFING PLAN

TEAM ORANGE

Orange Team December 10, 2007

Table of Contents

1. Phase 0 ………………………………………………………………………….. 3

1.1. Staff and Responsibilities

………………………………………………… 3

2.

Phase 1……….………………………………………………………………….. 4

2.1. Staff and Responsibilities

………………………….……………………… 5

3.

Phase 2……….………………………………………………………………….. 6

3.1. Staff and Responsibilities………………………….……………………… 7

4.

Phase 3……….………………………………………………………………….. 8

4.1. Staff and Responsibilities………………………….……………………… 9

2

Orange Team December 10, 2007

The purpose of this plan is to define the staffing for each phase of the project. This document describes the staff that will be needed for each phase as well as their responsibilities. The salary 1 for each employee is determined at http://www.indeed.com

.

1. Phase 0

This is the first phase of the project where the initial SBIR will be created along with the proposal and milestone presentations. As well, the project's website is created.

For Phase 0, we need the following staff

Figure 1

1.1. Staffs and Responsibility

Project Manager

 Assure that all tasks are assigned and are performed with high quality

 Resolve difference and conflict

Develop the WBS

Assign resources

Prioritize tasks

Define tasks dependencies

1 Please refer to funding plan for further details.

3

Orange Team

Marketing Specialist

Determine the target market

Support the marketing aspect of the project

Choose and manage the marketing vendor

Determine the overall marketing plan

December 10, 2007

Hardware Specialist / Webmaster

 Determine the best hardware for Triton System

 Estimate the cost of hardware

Assist the financial specialist with hardware budget

Research sensor technologies and other hardware for Triton System

Research the best method of developing and attaining hardware components

Create the team website that includes team biography, presentations, and documentations

Software Specialist

 Determine the algorithm for the Triton System

 Estimate the cost of developing the software

Financial Specialist

Determine the most suited method for developing and maintaining the software

Receive fund

Create budget

Determine product cost

Financial and funding plan

2. Phase 1

In this phase, a lab prototype will be developed. Along with this, the SBIR phase 2 proposal will be written. Success will be measured by the successful completion of those

The following staffs will be needed for this phase.

4

Orange Team December 10, 2007

Figure 2

2.1. Staffs and Responsibility

Project Manager

 Assure that all tasks are assigned and are performed with high quality

Resolve difference and conflict

Develop the WBS

Assign resources

Prioritize tasks

Define tasks dependencies

Marketing Researcher

 Determine the target market

Hardware Specialist/ (Webmaster)

Support the marketing aspect of the project

Determine the overall marketing plan

Determine the best hardware for Triton System

Estimate the cost of hardware

Assist the financial specialist with hardware budget

Research sensor technologies and other hardware for Triton System

Research the best method of developing and attaining hardware components

Create the team website that includes team biography, presentations, and documentations

Software Specialist

Determine the algorithm for the Triton System

Estimate the cost of developing the software

5

Orange Team

December 10, 2007

Determine the most suited method for developing and maintaining the software

Financial Specialist

 Receive fund

Create budget

Determine product cost

Financial and funding plan

Product Manager

Determine the functionality that will be included in the Triton System

D efining the requirements from a customer’s perspective

Technical Director

Determine the technical requirements

Managing the technical staff

Determine and solve technical problems

Risk Specialist

Managing project risk

Determine what risks exists in the project

Evaluate risk severity

Probability of the risks

Attempt to mitigate the risks

3. Phase 2

In this phase, an actual prototype of the product will be created.

The following staffs will be needed for this phase.

6

Orange Team December 10, 2007

Figure 3

3.1 Staffs and Responsibility

Project Manager

 Assure that all tasks are assigned and are performed with high quality

Resolve difference and conflict

Develop the WBS

Assign resources

Prioritize tasks

Define tasks dependencies

System Hardware Engineer 1 & 2

 Determine the best hardware for Triton System

Estimate the cost of hardware

Assist the financial specialist with hardware budget

Research sensor technologies and other hardware for Triton System

Research the best method of developing and attaining hardware components

Webmaster

Create the team website that includes team biography, presentations, and documentations

Manage the web developers in the future

Software Engineer 1 & 2

 Determine the algorithm for the Triton System

7

Orange Team

 Estimate the cost of developing the software

December 10, 2007

 Determine the most suited method for developing and maintaining the software

Financial Specialist

Receive fund

Create budget

Determine product cost

Financial and funding plan

Product Manager

Determine the functionality that will be included in the Triton System

D efining the requirements from a customer’s perspective

Technical Director

determine the technical requirements

managing the technical staff

HR Manager 2

Hire new employees

handle all employees’ paper work

4. Phase 3

In this phase, the delivery of the first product occurs. With the warehouse and manufacturer is secured, the actual product begins. Also, the marketing campaign is rolled out.

The following staffs are needed for this phase.

2 Human resource management skills needed

8

Orange Team December 10, 2007

Figure 4

4.1. Staffs and Responsibility

Project Manager

 Assure that all tasks are assigned and are performed with high quality

Resolve difference and conflict

Develop the WBS

Assign resources

Marketing Specialist

Prioritize tasks

Define tasks dependencies

Determine the target market

Support the marketing aspect of the project

Choose and manage the marketing vendor

Determine the overall marketing plan

System Hardware Engineer 1 & 2

Determine the best hardware for Triton System

Estimate the cost of hardware

Assist the financial specialist with hardware budget

Research sensor technologies and other hardware for Triton System

 Research the best method of developing and attaining hardware components

9

Orange Team

Webmaster

December 10, 2007

Create the team website that includes team biography, presentations, and documentations

Manage the web developers in the future

Software Engineer 1 & 2

Determine the algorithm for the Triton System

Estimate the cost of developing the software

 Determine the most suited method for developing and maintaining the software

Financial Specialist

 Receive fund

Create budget

Determine product cost

Financial and funding plan

Product Manager

Determine the functionality that will be included in the Triton System

Define the requirements from a customer’s perspective

Technical Director

Determine the technical requirements

Manage the technical staff

Procurement Manager 3 / Lawyer

Create all contracts

Handle customer negotiations

HR Manager 4

hire new

employees

 handling all employees’ paper work

Administrative Assistant

Manage the administrative needs of the staffs

Take minutes, type up paper work, et cetera

Bookkeeper

Produce financial reports of the project

Operations Manager

3 Require legal procurement experience

4 Human resource management skills needed

10

Orange Team December 10, 2007

Manage functional organization of the project

Manage the staff who maintains the product after the project is closed

Triton Customer Support

Take customer orders

Take complaints and questions

G enerally, take care of customers’ needs

11