262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) [Ameresco] See 006290S01 to 006290S04 for ESCO Buildings List / Compliance Requirements. A. BACnet Device ID numbers and Device Names shall only be assigned by Bobbie Tincher or Galen Tolliver. Device ID and Device Names assignment shall be the sole responsibility of the University of Kentucky. B. The servers shall be joined to the UK’s Active Directory domain. C. The names of the servers shall be assigned solely by CPPD IT Andrew Blues or Shawn Reynolds. D. Provide control equipment, including any associated hardware and software, that is Year 2000 compliant. E. Provide and install and fully commission a complete system of Automatic Temperature Controls as specified herein, and as illustrated on the contract drawings to allow for a complete and operational temperature control system. The Temperature Control system shall be a combination electronic Direct Digital Control (DDC) with pneumatic actuation. All necessary control panels, relays, switches, system software, valves, valve actuators, sensing devices, and damper operators shall be provided, installed, and commissioned to insure proper operation of the temperature control system as detailed in the sequence of operation, whether noted on the plans and specifications or not. The systems shall be properly connected, piped and wired in a manner conforming to the laws, ordinances and codes now in force in the Commonwealth of Kentucky. F. The facility management system (FMS) specified for this project shall seamlessly interface to the existing Johnson Controls Metasys, facility management system. If the existing facility management system cannot meet the requirements specified in this section, the controls manufacturer shall provide all hardware, software, installation, control wiring, engineering and programming etc. to upgrade the existing facility management system to meet the requirements of this section. All new and existing manufacturers specific hardware points, software points, DDC controllers, Network Controllers, Workstations and software system objects shall be monitored, controllable and accessible as described in this section from either the Johnson Controls ADX Operator Workstation, located in the Peterson Service Building Delta Room. Providing additional computer workstations, Internet IP Protocol Access, Java script programming, windowing between different or loading separate facility management system software on one of the above Workstations for interface to the new and existing facility management system is not acceptable. G. The facility management system shall interface to the existing Campus FDDI segmented WAN network via 10BASET communication hub(s). With respect to all new and existing DDC controllers, Network Controllers and workstations communicating over the campus WAN network, all control points and software features described in this section shall be operable from one of the existing operator terminals located in the Peterson Service building. Modem communication is not acceptable for this application. There shall only be one physical connection to the campus FDDI WAN network. H. All controller programs shall have the ability to download and upload over the campus Ethernet network. I. UK Communications department shall provide all required HUB’s routers and switches required to interface to the campus WAN network. The cost for this work shall be included by the controls manufacturer. Obtain pricing from the UK Campus Communication Department prior to bid. J. EMS Connections to Third Party Equipment: Provide these connections and points as indicated in the Sequence of Operation and/or the I/O Summary Sheets. Third Party equipment includes but is not limited to, computer room air conditioning units, condensate pumps, transfer switches, HVAC variable speed pumping systems, sump pumps, fire alarm systems, lighting systems, etc. 262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) Page 1 of 3 Dated: 12/2015 Applies to: All Projects University of Kentucky 262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) K. Coordinate with third party equipment suppliers to determine equipment devices, such as, printed circuit boards, contacts, etc. required for EMS connections. Provide any necessary connection devices not provided by the third party equipment suppliers. L. Electrical power wiring and interlock wiring for all controls, signal devices, alarms, etc., shall be in accordance with diagrams and instructions from the supplier of the systems. All power and control wiring, conduit and wiring connections required for the complete installation, including wiring to smoke dampers and combination fire/smoke dampers and their motors, shall be provided by this Contractor in accordance Electrical 16 specification requirements. M. Acceptable manufacturer: Schneider Electric PM800 Series Meters BACNet compatible N. Meter shall be provided with LCD for local display. The meter shall be read locally and by the Delta room. The LCD shall show at minimum current, voltage, power, true power factor, frequency active/reactive energy and metered values. [Existing UK Standard] METER KWH/KW (Power/Demand) Polyphase - 3-phase Delta 3 wire with chassis ground Wye 4 wire Other Stators 3 stator (most accurate) X 2.5 stator (more accurate) 2 stator (balanced loads) Mounting Socket (outdoor or indoor) Socket (bottom conn indoor) Flush switchboard type Voltage 3 wire Delta, 3 phase 120 Volt/60 Hz 240 Volt/60 Hz 480 Volt/60 Hz 4 wire Wye, 3 phase 208/120 Volt/60 Hz 480/277 Volt/60 Hz Current Rating X 2.5 Amp Class 10 2.5 Amp Class 20 not swbd. 15 Amp Class 100 not swbd. 30 Amp Class 200 not swbd. Number registers - 5 Multiplier - whole number (divisible by 100) Accuracy - calibrated 262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) Dated: 12/2015 Applies to: All Projects University of Kentucky Page 2 of 3 262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) CASE Socket Socket (bottom connected indoor) Flush switchboard type with shorting bars DEMAND REGISTER Electronic Input-frictionless optically coupled pulses of kW Output Display - Liquid crystal display (LCD) Outputs - Display scroll of: All 8's segment check Kilowatt hours Minimum kW demand Cumulative or continuous cumulative demand Number of demand resets Alternative display scroll of: All programmed constants Programming- Field programmable Pulse initiator - output dry contact Form C, KYZ (10 pulses per second max.) (40 ms closed min 25 ms open min.) Pulse initiator ratio - programmable 01-99. Installer shall wire the KYZ output in 3/4" conduit to a junction box near an available Honeywell Data Gathering Panel (DGP). Contact the UKPPD Energy Management Engineer to determine if this DGP is located in the building or in one of the surrounding buildings. Current Transformers Primary/Secondary AMP/5 AMP Rating Factor 1.25 Indoor MTD @ 30 degree C 1.50 Indoor MTD @ 30 degree C X 3.00 Indoor MTD @ 55 degree C 2.00 Outdoor MTD @ 30 degree C X 3.00 Outdoor MTD @ 55 degree C CT Accuracy - ANSI 0.3 Class Installation Note: The maximum mounting height of any display or register on the meter is five (5) feet. No Exceptions! 262713S02 ELECTRICITY METERING: KWH/ -KW-BUILDING METERING (Ameresco) Page 3 of 3 Dated: 12/2015 Applies to: All Projects University of Kentucky