LCLS BCR Overview and EIR LOIs Mark Reichanadter LCLS Deputy Project Director Project Progress / Status Revised Project Baseline Overview EIR Lines of Inquiry (LOIs) Summary October 9-11, 2007 LCLS EIR Mark Reichanadter reich@slac.stanford.edu Progress to Date LCLS Status on Approved Baseline (May05) TPC $379M (TEC $315M, OPC $64M) % Comp (Jun07): Planned: 60.1% Actual: 51.5% LCLS Status @ Level 2 Injector TEC & OPC essentially complete. Linac recovering from CR effects. Installing equipment. Undulator accepting deliverables. Prep for installation XTOD has a mature design. Procurements underway. XES in design, planning procurements Conventional Facilities in construction Injector S20 Facilities, MMF in operations Most remaining civil work under contract FEH Hutches, Office space renovation still in design October 9-11, 2007 LCLS EIR 2 Mark Reichanadter reich@slac.stanford.edu LCLS Progress on Approved Baseline LCLS Project Performance (TEC) • TEC SPI = 0.85 • TEC CPI = 0.90 350,000 300,000 AYK$ 250,000 BCWS (TEC) BCWP (TEC) 200,000 ACWP (TEC) BAC 150,000 BA 100,000 OBL-S (TEC) EAC • EAC up-trend BCWP downtrend, due to CR • $ total burn rate ~$7-8M per/mo • SLAC labor portion burns ~ $2.5M/mo 50,000 0 09 bFe 8 -0 ct O 08 nJu 8 0 bFe 7 -0 ct O 07 nJu 7 0 bFe 6 -0 ct O 06 nJu 6 0 bFe 5 -0 ct O 05 nJu 5 0 bFe 4 -0 ct O October 9-11, 2007 LCLS EIR 3 Mark Reichanadter reich@slac.stanford.edu LCLS TEC Earned Value (through Jun07) Cum Work Scheduled (BCWS) Cum Work Performed (BCWP) Cum Actual Costs (ACWP) Estimate at Complete (EAC) % Contingency on EAC $183.8M $157.0M $174.1M $302.3M 10.9% •% contingency/ETC dropped from ~22% to 10.9% since Oct06 due to CR and funding uncertainties. Project team working on unplanned work (CR scenarios, replanning project, review preparation, etc.) October 9-11, 2007 LCLS EIR 4 Mark Reichanadter reich@slac.stanford.edu CR Funding Uncertainty Time-Line LCLS CD-2 Funding Profile 120 Continuing Resolution 100 80 60 LCLS funded incrementally at ~$86M level. FY07 planned funding $122M 40 20 Funding Uncertainty A S O N D 2006 Possible year-long CR No funding restoration until FY09 Hold on all LCLS Procurements October 9-11, 2007 LCLS EIR J 0 FY02 FY03 FY04 FY05 FY06 F M A M 2007 J J FY07 FY08 A Funds arrive at ANL Budget passed. LCLS funded at $114M level 5 DOE directs LCLS to revise baseline plan. Mark Reichanadter reich@slac.stanford.edu FY09 S FY10 CR Impacts and Mitigation Actions Impact: FY07 funding uncertainties for six months $8M FY07 funding reduction, no restoration until FY09 Mitigation: Directed to develop revised plan with reduced FY07 funding profile. Defer selected procurements from FY07 to FY09. Accelerate shutdown procurements to recover schedule Cost: $41.0M Project extended by 16 months Staffing costs, no changes to scope Project is funding limited in FY08 October 9-11, 2007 LCLS EIR 6 Mark Reichanadter reich@slac.stanford.edu Mitigation – Defer Procurements and Replan Beam Transport Hall Undulator Hall Near Experimental Hall Far Experimental Hall X-Ray Transport Tunnel Defer Photon equipment and FEH hutches until FY09 October 9-11, 2007 LCLS EIR 7 CD-4 LCLS Operations in FEH - July 2010 Mark Reichanadter reich@slac.stanford.edu Revised Baseline Plan Revise LCLS baseline to deliver technical scope on cost and on schedule Address effects of the CR and FY07 funding reduction Shift photon and FEH procurements from FY07 to FY09 Update remaining work (ETC) using current estimates No changes in scope or technical capabilities Update overhead rates and escalation Update OPC to reflect LCLS transition to operations Update cost/schedule contingencies and risk planning October 9-11, 2007 LCLS EIR 8 Mark Reichanadter reich@slac.stanford.edu Revised Baseline Plan Development Status baseline Primavera (P3) for M/E June 2007. Update FY07 funding. Replan remaining work. Review WBS Dictionary, update as necessary. Update costs and schedule estimates for ETC. Update schedule logic, durations and optimize float Review/adjust obligations plan to fit funding, resources Identify critical paths, update milestones as necessary Re-assess contingency at the task level Re-assess risks, handling plans and impacts. Establish funding levels for FY09 and FY10 October 9-11, 2007 LCLS EIR 9 Mark Reichanadter reich@slac.stanford.edu Bottoms-Up Contingency Assessment Factor Design Maturity (Labor-Related Costs) 1.45 The task/item is a conceptual design and/or advances the state of the art. 1.35 The task/item is a new design and/or requires some R&D (not beyond state of the art). 1.25 The task/item is a new design, not exotic, being estimated with no prior experience. 1.15 The task/item is a new design, not exotic, being estimated with prior experience. 1.10 The task/item is a modification of an existing design. 1.0 The task/item is fully invoiced/completed. Factor Design Maturity (Material & Subcontract Costs) 1.35 The task/item has only a conceptual design or scaled from analogous system. 1.25 The task/item has an engineering estimate with sketches only. 1.15 The task/item has an engineering estimate with engineering drawings. 1.10 The task/item has a budgetary quote or is an off-the shelf item. 1.0 The task/item is fully invoiced/completed. Judgment Factor (Additional External Factors) (Ranges from 1.0 to 1.1, but can be higher under unusual conditions) Schedule Risks: Technical Risks: Other Risks: Does the task/item land on or impact the critical path? Is the task/item a new design or beyond the state of the art and/or critical to the LCLS? Are there out-year inflation risks? Are you a buyer in a tight supply economy? Are there exposures to foreign currencies/markets? Is there only one qualified (or strongly preferred) supplier? Does the item require specialty resources? Any other unusual circumstances? October 9-11, 2007 LCLS EIR 10 •Contingency assessed on the base cost by CAMs at lowest activity. •Design Maturity •Judgment Factor •For more info on cost and schedule estimating, see PMD 1.1-020, and PMD 1.1-021 Mark Reichanadter reich@slac.stanford.edu Revised ETC, BAC @ L2 WBS ACWP through Remaining Work Jun07 (ETC) % Complete Budget at Completion 1.1 Project Management 16.69 5.41 76% 22.10 1.2 Injector 20.07 0.10 99% 20.17 1.3 Linac 15.01 12.89 54% 27.90 1.4 Undulator 29.49 14.56 67% 44.05 1.5 X-ray Transport 13.86 10.70 56% 24.56 1.6 X-ray Endstations 1.77 6.69 21% 8.46 1.9 Conventional Facilities 59.09 73.29 45% 132.38 1.X Controls 1 LCLS Total Base Cost 18.17 174.15 22.07 145.72 45% 54% 40.24 319.87 2 LCLS Other Project Cost LCLS Total Project Cost (TPC) October 9-11, 2007 LCLS EIR LCLS Total Estimated Cost (TEC) 352.00 Available Contingency 32.13 % Contingency on Cost to Go (ETC) 22.1% 17.11 42.89 28.5% 60.00 LCLS Total Other Project Costs (OPC) 68.00 Available Mgmt Reserve 8.00 % Mgmt Reserve on ETC 18.7% 191.26 188.61 11 45.5% 420.00 Mark Reichanadter reich@slac.stanford.edu BASIS OF ESTIMATE LCLS PROJECT: TEC Basis of Estimate on Remaining Work (TEC) Catalog/Construction Database 0% Significant portion of ETC is contracts in hand. Reduce cost risk. Engineering Estimates (Similar Items or Procedures) 29% Under Contract/Bids in Hand 45% Vendor Quote Estimate (Dwgs/Sketches/Specs) 9% Engineering Estimate (Analysis) 5% Expert Opinion (Allowance) 0% October 9-11, 2007 LCLS EIR Engineering Estimates (Dwgs, Sketches/Specs) 12% 12 Mark Reichanadter reich@slac.stanford.edu Updated L2 milestones L2 milestones have 2 months float to ‘early finish’ date to allow some replanning discretion in response to changing conditions. October 9-11, 2007 LCLS EIR 13 Mark Reichanadter reich@slac.stanford.edu Revised TEC Funding & Obligations LCLS TEC Funding and Commitments 400 350 300 (AY$M) 250 BCWS 200 Commitments DOE Funding 150 100 50 0 FY07 October 9-11, 2007 LCLS EIR FY08 FY09 14 FY10 Mark Reichanadter reich@slac.stanford.edu EIR Lines of Inquiry Work Breakdown Structure LCLS is organized into fully integrated (design through commissioning) L2 systems Controls embedded in technical systems. No significant change to WBS Structure or Dictionary due to CR effects. Breakout Session (Fornek) Resource-Loaded Schedule P3 file provided in advance documentation. Presentation (Mast) October 9-11, 2007 LCLS EIR 15 Mark Reichanadter reich@slac.stanford.edu EIR Lines of Inquiry Key Technical, Cost, Schedule and Programmatic Assumptions See documentation provided Breakout Session (Mast/Reichanadter) Critical Path 101 days (~5months) of float to CD-4 3 shortest (critical) paths are provided in advance documentation Breakout Session (Mast/Chan) October 9-11, 2007 LCLS EIR 16 Mark Reichanadter reich@slac.stanford.edu EIR Lines of Inquiry Start-Up Test (Commissioning) Plan LCLS uses a broad, global start-up plan as a blueprint to commission the LCLS. Detailed commissioning plans are prepared, reviewed (externally) and approved by SLAC and DOE management. DOE Accelerator Safety Order requirements are addressed in detailed commissioning plans Injector Commissioning Complete Linac ARR due in late FY08 BTH–FEH ARR due in Spring 09 Breakout Session (Saenz/Schultz/Arthur) October 9-11, 2007 LCLS EIR 17 Mark Reichanadter reich@slac.stanford.edu EIR Lines of Inquiry System Functions and Requirements (SFRs) Technical specifications are arranged in a hierarchical fashion from the LCLS GRD GRD, PRDs, ESD, ICD, RDSs Documents are added/ revised as the design evolves. Technical specifications are under revision control and configuration management No significant change to SFRs due to CR Breakout Talk (Marsh/Reichanadter) Integrated Project Team See responses provided in Advance Questions Breakout Session (Lee/Joma/Brown/Galayda/Reichanadter) October 9-11, 2007 LCLS EIR 18 Mark Reichanadter reich@slac.stanford.edu EIR Lines of Inquiry Risk Management System Managers ‘own’ and manage project risks Add/close risks, evaluate handling plans, assess impacts Review monthly with senior management team. Residual risk impacts are evaluated as part of the overall contingency analysis As the project has evolved, risk management has adapted to an punch list of actionable items. Presentation (Galayda), Breakout Session (ALL) Project Execution Plan (PEP) See documentation provided Breakout Session (Lee/Joma) October 9-11, 2007 LCLS EIR 19 Mark Reichanadter reich@slac.stanford.edu Summary FY07 CR significantly impacted the LCLS project. 2 quarter CR during project’s peak funding year FY07 funding reduction with earliest restoration in FY09 Directed change to revise cost and schedule baseline LCLS has prepared a revised ETC addressing the FY07 funding and CR effects Reschedule FY07 procurements to FY09 Delay CD-4 (16mo extension to project). TPC = $420M Revised ETC will allow the project to complete its commitments to DOE No changes to scope or technical capabilities Cost/schedule contingency adequate to complete project October 9-11, 2007 LCLS EIR 20 Mark Reichanadter reich@slac.stanford.edu