XTOD FY07 Plan LCLS FAC Review October 12, 2006 Donn H. McMahon

advertisement
XTOD FY07 Plan
LCLS FAC Review
October 12, 2006
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
LCLS Layout at SLAC
XTOD Transports Photons from e- Dump to FEH
Linac-toUndulator
(227m
e- beam)
Undulator
Hall (175m
e- and g
beam)
eBeam
Dump
(40M eand g
beam)
Near
Expt.
Hall
Far
Expt.
Hall
Linac ebeam
(FEE) Front
End
Enclosure
(29m g
beam)
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
X-ray Vacuum
Transport
(250m g beam)
Donn H. McMahon
mcmahon4@llnl.gov
XTOD plan has stabilized with minor
modifications
Modifications:
FEL spectrometer has been redefined as the Low
Energy Spectrometer
Number of “Pop-up” cameras in the FEE reduced from
13 to 9
Additions:
K-measurement system in FEE moved from XES to
XTOD scope w/ XES providing crystals
Deletions:
none
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
The Proposed Baseline has nearly all XTOD
instruments and diagnostics in the FEE
FEE
NEH
FEH
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
Diagnostics Occupy Upstream End of the
Front End Enclosure (FEE)
Slit
Spectrometer
Package
Solid
Attenuators
Collimator 1
Total Energy
Fixed
Mask
Gas
Detector
Gas Attenuator
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
Gas
Detector
Direct Imager
(Scintillator)
UCRL-PRES-225471
FEL Offset Mirror System
Donn H. McMahon
mcmahon4@llnl.gov
FEE Schematic
5 mm
diameter
collimators
Windowless
Gas
Detector
Start of
Experimental
Hutches
K Spectrometer Direct Imager
Solid
Attenuator
e-
Fixed Mask,
High-Energy
Slit
Gas
Attenuator
Muon
Shield
NFOV
Grating
Total
Energy
Thermal
Detector
WFOV
FEL Offset
mirror
system
Windowless
Gas
Detector
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
Tunnel Contains XTOD X-Ray Beam Transport System
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD Staff by Discipline
Rodney Victorine
Resource Manager
Jay Doubrava
PMCS
EE
E. Ables
P. Pax
B. Abraham
R. Bionta
LLNL LCLS Project Leader
D. McMahon
XTOD Project Engineer
ME
P. Duffy
M. Mckernan
S. Shen
J. Trent
L. Tung
P. Tirapelle
M. Roeben
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
Comp. & Ctrls
K. Fong
K. Kishiyama
S. Lewis
L. Ott
UCRL-PRES-225471
C. Kelly-Clark
Administrator
R. Souza
Procurement
Physics
S. Friedrich
S. Hau-Reige
R. London
M. Pivovaroff
D. Ryutov
Hazards
R. Beale
Donn H. McMahon
mcmahon4@llnl.gov
XTOD Organization by WBS
1.5.1
Management and Safety
Account # 8866-01
Richard Bionta x 3-4846
Donn McMahon x 3-1475
Rodney Victorine x 33326
1.5.3.2
FEE Mech/Vac Design
Account #8866-04
Mark McKernan x 3-3825
1.5.4.2.1
Fast Valve
Account #8866-TBD
Pat Duffy x 2-8747
John Trent x 2-5723
Pat Duffy x 2-8747
1.5.4.2.2
Fixed Mask
Account #8866-06
Hazards Control
Procurement
Ray Souza
Keith Stickle
Mary Ross
1.5.3.3
NEH Mech & Vacuum
Account #8866-29
Stewart Shen x 3-4826
Pat Duffy x 2-8747
Louann Tung x 2-1274
John Trent x 2-5723
1.5.2.1
Controls
Account #8866-81
1.5.5.3.1
Direct Imager
Account #8866-39
Mike Pivovaroff x 2-7779
Paul Pax x 4-3004
Sasa Bajt x 4-3768
Elden Ables x 2-4809
Stewart Shen x 3-4826
Louann Tung x 2-1274
Richard Beale x 2-3112
1.5.4.2.7
FEL Offset Mirror System
Account #8866-16
1.5.3.4
X-Ray Tunnel Mech & Vacuum
Account #8866-29
Stewart Shen x 3-4826
Steve Lewis x 3-4751
Pat Duffy x 2-8747
Keith Kishiyama x 2-8602
Louann Tung x 2-1274
William Abraham x 2-6418
John Trent x 2-5723
1.5.3.5
FEH Mech & Vacuum
Account #8866-29
Pat Duffy x 2-8747
1.5.4.2.3
Slit
Account #8866-08
1.5.5.3.6
Gas Detector
Account #8866-43
Dmitri Ryutov x 2-9832
Stephan Friedrich x 3-1527
Stewart Shen x 3-4826
Owen Drury x 2-0034
Martin Roeben x 3-0612
Elden Ables x 2-4809
Paul Pax x 4-3004
Stefan Hau-Riege x3-2021
John Trent x 2-5723
Pete Tirapelle x 2-8749
1.5.4.2.5
Gas/Solid Attenuator
Account #8866-10
Dmitri Ryutov x 2-9832
Stewart Shen x 3-4826
Martin Roeben x 3-0612
Keith Kishiyama x 2-8602
1.5.4.2.6
TTF Damage Experiment
Account #8862-85
Stewart Shen x 3-4826
Stefan Hau-Riege x 2-5892
Pat Duffy x 2-8747
Rich London x 3-2021
1.5.5.4.2
Total Energy
Account #8866-53
2.5.5.2
Modeling & Simulation
Account #8866-71
1.5.5.4.4
Low Energy Spectrometer
Account #8866-56
Mike Pivovaroff x 2-7779
Paul Pax x 4-3004
Linda Ott x 2-6446
Kirby Fong x 2-4205
1.5.5.4.5
Pop-Up Cameras
Account #8866-TBD
Paul Pax x 4-3004
Elden Ables x 2-4809
1.5.5.4.6
K-Spectrometer
Account #8866-TBD
Mike Pivovaroff x 2-7779
Paul Pax x 4-3004
Louann Tung x 2-1274
John Trent x 2-5723
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD scope has stabilized and a revised go
forward plan has been defined
Design completion of all systems: [FY07]:
Complete final design and procurement of most XTOD systems
Fixed Mask, Slit, Gas Detectors, Attenuators, Low Energy
Spectrometer, Total Energy Calorimeter, Direct Imagers, LE Offset
Mirror System, Mechanical and Vacuum systems for FEE, NEH, Tunnel,
and FEH
Remaining systems will be in FDR/fabrication stages
HE Offset Mirrors System, NEH & FEH Imagers, K-Measurement
System, and Pop-up Cameras
Finalize details for Beneficial Occupancy (2.15.08,3.21.08)
and commissioning activities: [FY07-2nd Half/FY08-1st Qtr]:
Test systems @ LLNL
Conduct readiness reviews
Develop shipping/staging plans
Vet installation plans
Develop commissioning plans
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD FY07 Development Status & Plan
WBS
Description
Status
FY07 Plan
1.05.03.02
FEE M&V
Need RP input for 10.06 PRD
Leverage off XVTS, Complete Final Design & Procure, Ready
for B.O.
1.05.03.03(.01)
NEH M&V
Need RP input for 10.06 PRD
Leverage off XVTS, Complete Final Design & Procure Ready
for B.O.
1.05.03.04
XVTS M&V
Final Design scheduled for
10.18.06
Complete Design, Procure, Ready for B.O..
FEH M&V
Need RP input for 10.06 PRD
Leverage off XVTS, Complete Final Design & Procure
Fast Valve
Commence preliminary design
Place in EBD,Complete Final Design & Procure Ready for B.O.
1.05.04.02.02
Fixed Mask
Finish ESD, Nearing FDR (11.06)
Complete Design, Procure, Ready for B.O.
1.05.04.02.03
Slit
Finish ESD, Nearing FDR (12..06)
Complete Design, Procure, Ready for B.O.
1.05.04.02.05
Attenuator
Finish ESD & Prototype Activities
Complete Design, Procure, Ready for B.O.
1.05.04.02.06
TTF Damage Experiment
Sept Experiments @ FLASH VUVFEL
Complete analyses
1.05.04.02.07.01
FEL Offset - Low
PRD in review
Complete Design, Procure, Ready for B.O.
1.05.04.02.07.02
FEL Offset - High
PRD to commence
Complete Final Design (8.07), Procure Substrates
1.05.05.03.01
Direct Imager
Finish PRD, Prototype, Component Eval
Complete Design, Procure, Ready for B.O.
1.05.05.03.02
Gas Detector
SCR complete, Prototyping
Conduct Calibration Tests (SSRL), Complete Design, Procure,
Ready for B.O
1.05.05.03.07
NEH Imager
PRD (12.06)
Leverage off DI, Complete Final Design, Procure systems
1.05.05.03.08
FEH Imager
PRD (12.06)
Leverage off DI, Complete Final Design, Procure systems
1.05.05.04.02
Total Energy Monitor
SCR Complete, Prototyping
Complete Design, Procure, Ready for B.O.
1.05.05.04.04
Low Energy Spectrometer
PRD to start (11.06)
Complete Design, Procure, Ready for B.O.
1.05..05.04.05
Pop Ups (N)
PRD (1.07)
Complete Final Design, Procure systems
1.05..05.04.06
K-Spectrometer
PRD to start (11.06)
Complete Final Design, Procure systems
1.05.03.05(.01)
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD Key Dates
Target XTOD Dates
Key Documents
WBS
Design Reviews
Install
B.O.
Description
PRD
ESD
SCR
PDR
FDR
1.05.03.02
FEE M&V (need RP Input)
10.06
2.22.07
1.24.07
3.12.07
4.23.07
2.15.08
11.08.07
1.05.03.03(.01)
NEH M&V (need RP Input)
10.06
2.22.07
1.24.07
3.12.07
4.23.07
2.15.08
11.01.07
XVTS M&V
2.15.06
1.25.06
-
11.14.05
10.18.06
3.21.08
12.11.07
FEH M&V (need RP Input)
11.07.06
2.22.07
Combine w/ NEH reviews
2.15.08
1.02.08
Fast Valve
-
11.10.06
--
11.28.06
1.30.07
2.15.08
11.08.07
10.20.06
4.06;
5.4.06
11.14.06
2.15.08
11.08.07
10.20.06
4.06;
5.4.06
12.14.06
2.15.08
11.08.07
1.05.03.04
1.05.03.05(.01)
1.05.04.02.02
Fixed Mask
5.14.04
Cooccupancy
8.14.06
1.05.04.02.03
Slit
1.05.04.02.05
Attenuator
2.03.06
10.31.06
4.13.06
12.01.06
3.02.07
2.15.08
11.08.07
1.05.04.02.07.01
FEL Offset - Low
10.27.06
1.08.07
11.22.06
2..06.07
4.23.07
2.15.08
11.08.07
1.05.04.02.07.02
FEL Offset - High
1.03.07
2.07
2.07
5.07
8.07
4.29.08
11.08.07
1.05.05.03.01
Direct Imager
10.13.06
11.28.06
10.27.06
1.12.07
3.15.07
2.15.08
11.08.07
1.05.05.03.02
Gas Detector
6.23.06
10.30.06
6.27.06
10.27.06
1.29.07
2.15.08
11.08.07
1.05.05.03.07
NEH Imager
2.05.07
4.24.07
3.27.07
5.22.07
8.10.07
2.15.08
11.01.07
1.05.05.03.08
FEH Imager
2.20.07
5.08.07
4.10.07
6.06.07
8.10.07
2.15.08
1.02.08
1.05.05.04.02
Total Energy Monitor
8.06
10.06
8.17.06
10.06.06
12.06
3.07
2.15.08
11.08.07
1.05.05.04.04
Low Energy Spectrometer
11.03.06
1.05.07
11.21.06
1.23.07
3.21.07
2.15.08
11.08.07
1.05..05.04.05
Pop Ups (N)
1.23.07
3.28.07
2.28.07
5.16.07
8.08.07
4.16.08
11.08.07
1.05..05.04.06
K-Spectrometer
12.14.06
2.28.07
1.30.06
4.25.07
7.20.07
3.08?
11.08.07
October 12, 2006
Completed
XTOD Breakout: XTOD FY07 Schedule
Near Term Completion (<1mo) Donn H. McMahon
UCRL-PRES-225471
mcmahon4@llnl.gov
XTOD Key Dates – 6 Month Look ahead (<6/07)
Target XTOD Dates
Key Documents
WBS
Design Reviews
Install
B.O.
Description
PRD
ESD
SCR
PDR
FDR
1.05.03.02
FEE M&V (need RP Input)
10.06
2.22.07
1.24.07
3.12.07
4.23.07
2.15.08
11.08.07
1.05.03.03(.01)
NEH M&V (need RP Input)
10.06
2.22.07
1.24.07
3.12.07
4.23.07
2.15.08
11.01.07
XVTS M&V
2.15.06
1.25.06
-
11.14.05
10.18.06
3.21.08
12.11.07
FEH M&V (need RP Input)
11.07.06
2.22.07
Combine w/ NEH reviews
2.15.08
1.02.08
Fast Valve
-
11.10.06
--
11.28.06
1.30.07
2.15.08
11.08.07
10.20.06
4.06;
5.4.06
11.14.06
2.15.08
11.08.07
10.20.06
4.06;
5.4.06
12.14.06
2.15.08
11.08.07
1.05.03.04
1.05.03.05(.01)
1.05.04.02.02
Fixed Mask
5.14.04
Cooccupancy
8.14.06
1.05.04.02.03
Slit
1.05.04.02.05
Attenuator
2.03.06
10.31.06
4.13.06
12.01.06
3.02.07
2.15.08
11.08.07
1.05.04.02.07.01
FEL Offset - Low
10.27.06
1.08.07
11.22.06
2..06.07
4.23.07
2.15.08
11.08.07
1.05.04.02.07.02
FEL Offset - High
1.03.07
2.07
2.07
5.07
8.07
4.29.08
11.08.07
1.05.05.03.01
Direct Imager
10.13.06
11.28.06
10.27.06
1.12.07
3.15.07
2.15.08
11.08.07
1.05.05.03.02
Gas Detector
6.23.06
10.30.06
6.27.06
10.27.06
1.29.07
2.15.08
11.08.07
1.05.05.03.07
NEH Imager
2.05.07
4.24.07
3.27.07
5.22.07
8.10.07
2.15.08
11.01.07
1.05.05.03.08
FEH Imager
2.20.07
5.08.07
4.10.07
6.06.07
8.10.07
2.15.08
1.02.08
1.05.05.04.02
Total Energy Monitor
8.06
10.06
8.17.06
10.06.06
12.06
3.07
2.15.08
11.08.07
1.05.05.04.04
Low Energy Spectrometer
11.03.06
1.05.07
11.21.06
1.23.07
3.21.07
2.15.08
11.08.07
1.05..05.04.05
Pop Ups (N)
1.23.07
3.28.07
2.28.07
5.16.07
8.08.07
4.16.08
11.08.07
1.05..05.04.06
K-Spectrometer
12.14.06
2.28.07
1.30.06
4.25.07
7.20.07
3.08?
11.08.07
October 12, 2006
Completed
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD milestones have been revised per scope
changes and new Beneficial Occupancy dates
XTOD Level 3 Milestones
MS #
MS ID
Milestone Title
Date*
MS3_XT035
Low Energy Spectral Measurement
Design Review Complete
7/21/2007
This milestone is complete when the designs of the low
energy spectral measurement instruments have been
certified as ready for procurement.
MS3_XT009
Far Hall Mech/Vac Design Review
Complete
5/27/2007
This milestone is complete when the design of the mechanical
and vacuum assemblies of the Endstation Systems that
are located in the Far Experimental Hall has been
approved as ready for procurement.
MS3_XT025
Solid Attenuator Ready to Ship to
SLAC
4/15/08
This milestone is complete when the solid attenuator system
has been completed by the vendor and is ready to ship
to SLAC.
MS3_XT043
Start XTOD Installation in Near Hall
4/15/2008
This milestone is complete when the NEH has been certified
as ready for installation of x-ray transport and optics
components.
MS3_XT030
Fixed Mask Ready to Ship to SLAC
4/15/2008
This milestone is complete when the fixed Mask system has
been completed by the vendor and is ready to ship to
SLAC.
MS3_XT007
Tunnel Mech/Vac Design Review
Complete
12/26/2006
This milestone is complete when the LCLS X-TOD transport
tunnel hardware design is complete.
MS3_XT060
Total Energy Measurement Installation
Complete
5/13/08
This milestone is complete when the total energy
measurement system has been installed.
MS3_XT040
Solid Attenuator Installation Complete
5/7/08
This milestone is complete when the solid attenuator system
has been installed.
113
122
116
117
120
121
128
123
Milestone Completion Criteria
* Proposed Dates
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD milestones have been revised per scope
changes and new Beneficial Occupancy dates
XTOD Level 3 Milestones
MS #
MS ID
Milestone Title
Date*
MS3_XT045
Gas Attenuator Installation Complete
5/7/08
This milestone is complete when the gas attenuator system
has been installed.
MS3_XT050
Tunnel Mech/Vac Installation
Complete
6/15/2008
This milestone is complete when the LCLS X-TOD transport
tunnel hardware has been installed and is ready for x-rays.
MS3_XT000
FEE Mechanical/Vacuum Installation
Complete
9/16/08
This milestone is complete when the mechanical and vacuum
components of the Endstation Systems have been installed
and certified as operational in the FEE.
MS3_XT080
Start Front End Enclosure Checkout
9/16/08
This milestone is complete when the XTOD instrumentation
has been installed through the FEE and it is possible to pump
down the beam line through the FEE, and the XTOD
instrumentation can be powered up.
MS3_XT066
Start Near Experimental Hall Checkout
8/17/2008
This milestone is complete when the XTOD instrumentation
and vacuum systems have been installed in the first hutch,
and it is possible to have an unobstructed vacuum pathway
from the FEE through the first hutch, and the XTOD
instrumentation can be powered
MS3_XT071
Start Far Experimental Hall Checkout
8/17/2008
This milestone is complete when the XTOD instrumentation
and vacuum systems have been installed in the first hutch,
and it is possible to have an unobstructed vacuum pathway
from the tumble through the first hutch, and the XTOD
instrumentation can be powered
124
131
127
126
129
130
Milestone Completion Criteria
* Proposed Dates
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
The FEL Offset Mirror Systems are critical
systems for LCLS Experimental Operations
Low Energy Mirror System:
Final PRD preparation
nearly complete
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
The FEL Offset Mirror Systems are critical
systems for LCLS Experimental Operations
The High Energy Mirror
System requires long
lead procurements
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD is approximately 36% complete (current baseline)
and is tracking schedule and performance plans
X-RAY TRANSPORT & DIAGNOSTICS SYSTEMS (TEC) Cost + Open Commitments vs BCWS ($K)
25,000.0
20,000.0
15,000.0
X-RAY TRANSPORT & DIAGNOSTICS SYSTEMS (TEC) - SPA
12,000,000
10,000,000
10,000.0
FY06
8,000,000
6,000,000
5,000.0
4,000,000
2,000,000
0.0
0
-2,000,000
-5,000.0
10_05 11_05 12_05 01_06 02_06 03_06 04_06 05_06 06_06 07_06 08_06 09_06 10_06 11_06 12_06 01_07 02_07
Prior Mo's
SEP_05
OCT_05
NOV_05
DEC_05
JAN_06
FEB_06
MAR_06
APR_06
MAY_06
JUN_06
JUL_06
AUG_06
Mo S
4,355,692
451,262
601,056
458,997
-34,418
590,136
515,929
582,847
541,147
595,091
-111,160
505,660
752,608
Mo P
4,224,577
514,461
429,509
363,551
310,657
690,081
298,614
474,733
370,965
379,288
537,203
344,123
Mo A
03_07
4,102,016
364,082
412,796
384,898
534,801
263,062
424,889
423,123
523,173
471,850
479,966
589,636
0
4,355,692
4,806,954
5,408,010
5,867,007
5,832,589
6,422,725
6,938,654
7,521,501
8,062,648
8,657,739
8,546,580
9,052,239
9,804,847
6,831,450
7,306,183
7,677,148
8,056,435
8,593,638
8,937,761
6,486,545
6,909,667
7,432,840
7,904,690
8,384,656
8,974,292
Cum S
04_07 05_07 06_07 07_07 08_07 09_07
Mo S+O
601.1
459.0
-37.4
620.4
646.0
623.8
542.9
595.1
643.8
522.1
486.5
436.8 1,489.8 285.2
832.6 1,261.2 2,761.8 1,806.1
652.9 162.0
4,739,038 229.7
5,168,547 279.4
5,532,098 717.2
5,842,755 486.5
6,532,836
Cum P 4,224,577
Mo S
601.1
459.0
-34.4
590.1
515.9
582.8
541.1
595.1
643.8
488.6
505.3
453.2
448.6
942.6
821.6
Cum A
4,102,016
4,466,099
648.0 1,547.8 2,555.5 1,748.1 980.8
4,878,894
337.8
5,263,792
333.6
5,798,594
737.1
6,061,656
538.5
0
FY07 is the largest funding year at $12M and includes nearly all XTOD procurements
Cum S+O 5,408.0 5,867.0 5,829.6 6,450.0 7,096.0 7,719.8 8,262.7 8,857.8 9,501.6 10,023. 10,510. 10,946. 12,436. 12,721. 13,554. 14,815. 17,577. 19,383. 20,036. 20,198. 20,428. 20,707. 21,424. 21,911.
Cum S
5,408.0 5,867.0 5,832.6 6,422.7 6,938.7 7,521.5 8,062.6 8,657.7 9,301.5 9,790.1 10,295. 10,748. 11,691. 12,512. 12,961. 13,609. 15,157. 17,712. 19,460. 20,441. 20,779. 21,112. 21,849. 22,388.
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov
XTOD work flow will follow ISMS practices for each
WBS element
LCLS Physics
Requirements
WBS Dictionary
ICDs
Hardware
Installation
Operations
Servicing
ESDs
Designs
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
Eng. Safety
Notes
UCRL-PRES-225471
IWS (Integrated Work
Sheet) is LLNL wide eform for documenting
ISMS for each work
package:
Scope
Hazards
Controls
Roles (RI…)
Responsibilities
Training
Signoff
Certified Parts
Lists
Donn H. McMahon
mcmahon4@llnl.gov
Integrated Safety Worksheets will be Developed for
Each Task
IWS#
12599 B
12662 B
12877 B
WAL
Title
RI
Testing of Prototype Gas Attenuator Vacuum System
LLNL Collaboration at Stanford LCLS: Off-Site
Work
LCLS Optics testing at DESY laboratory in
Hamburg Germany
Alt-RI
Shen
Location
1
132S/1571
Location Location
2
3
Bionta
12920 B
LCLS X-Ray Tunnel Vacuum Transport System
Bionta
13253 B
LCLS Solid Attenuator
Shen
13321 C
LCLS Total Energy Monitor
132S/1571
132S/variou
Friedrich Niedermayr s
13453 B
13474 B
LCLS Fixed Mask, and X-Ray Slit
B141 LCLS lab
Bionta
Bionta
Trent
McKernan
132S/Labs
SLAC
approved
DESY
approved
SLAC
in review
SLAC
in review
132S/1571 141/1145 SLAC
141/1145
in review
approved
13474 B
B141 LCLS lab .01 version
Bionta
McKernan
13527 B
LCLS Gas Detector
Bionta
McMahon
132S/1571 141/1145 SLAC
in review
13680 B
LCLS Direct Imager
Bionta
McMahon
132S/1571 141/1145 SLAC
draft
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Notes
approved
Bionta
Trent/
McKernan
Status
141/1145
in review
Donn H. McMahon
mcmahon4@llnl.gov
up to R.
Bionta
awaiting
pre-start
review
up to
Friedrich
awaiting
pre-start
review
waiting on
ES&H
Team
awaiting
pre-start
review
awaiting
pre-start
review
Summary
FY2006 was a design and replan year
Scope changes were accommodated
Revised Estimate to Complete (ETC)
The go forward plan will meet required install and commissioning dates
FY07 is characterized by the design completion and procurement of all
systems with most ready for shipping to SLAC for BO
Many physics requirements have been finalized
XTOD designs have been undergoing reviews
Nearly all XTOD staff has been added and aligned with WBS elements
XTOD is tracking the current plan
Critical path items are being actively scrutinized to ensure success
(concurrent tasking and early procurement of long lead items)
Work flow follows the principle of ISM (development to
install/commissioning)
October 12, 2006
XTOD Breakout: XTOD FY07 Schedule
UCRL-PRES-225471
Donn H. McMahon
mcmahon4@llnl.gov