Ernest Williams for Controls Department Controls System

advertisement
Controls System
Installation Status
Ernest Williams
for
Controls Department
Control Systems Software Section
FAC November 2008
1
Ernest Williams
Outline
LCLS Control System Installation
Project Staff and Assignments
Schedule & the Process
Cable Plant, racks and other infrastructure
I&C Systems status and schedule
Software Status
Issues & Concerns
Summary
Control Systems Software Section
FAC November 2008
2
Ernest Williams
Project Staff
Dedicated LCLS Control System Deputy (E. Carrone)
to help drive the project.
E. Williams: Installation Manager.
M. De Salvo: Coordination Manager.
Each subsystem “owned” by a System Lead,
responsible for schedule, resources and costs.
Additional support provided by services from PCD.
Cable Shops and Fab Shops.
Controls Coordination Forum: every Thursday at 9.00
am.
Control Systems Software Section
FAC November 2008
3
Ernest Williams
Plans & Process for LCLS Controls System
Installation
Controls installation takes place in several steps:
Design, documentation, procurement and Installation of
the cable plant including long haul DC and I&C cables
Cables termination and connection to beam line
components (Mechanical Systems)
Procurement & preparation of electronics racks
Installation of electronics chassis and modules
including crates, IOCs, networks & timing modules in
the racks
Rack installation in the field, AC & cable plant
connection
Control Systems Software Section
FAC November 2008
4
Ernest Williams
Cable Plant Design & Installation Process
From the list of devices to be installed…
Develop racks layout & cable tray
design
Generate rack profiles for electronics
modules
Identify DC & I&C cabling requirements
& document in CAPTAR
Produce installation bid package from
CAPTAR and tray designs
Generate installation bid package &
award contract
Procure trays, cables, connectors, etc.
Install cable plant and terminate to
beam line components
The readiness status of each Controls
Subsystem is tracked weekly
LCLS
Controls System Installation
System Engineer
Rack
Profile
EI
Diagram
Cable
Coding
Procurements
MAGNET
Bellomo, De Lira
100%
99%
99%
85%
FEE SYSTEMS
VACUUM
BEAM LOSS MON.
OTR, YAG, TDUND
COLL, WIRE SCAN
BPM
TOROID
TIMING
NETWORKS
Bill Abraham
Boyes
Krejcik
Peng
Alarcon
Johnson
Peng
Krejcik, Dusatko
Lahey
99%
100%
40%
75%
45%
98%
?%
90%
100%
100%
100%
0%
100%
70%
100%
100%
100%
40%
99%
90%
ADS
Peters, Gassner
MPS
SYSTEM
90%
90%
99%
90%
100%
90%
100%
100%
80%
10%
95%
100%
100%
40%
100%
65%
80%
50%
100%
Norum, Tilgman
100%
100%
100%
60%
BCS
Bennett
100%
60%
100%
90%
LION
PPS
Tilghman/ Bennett
P. Bong
100%
100%
0%
100%
100%
100%
100%
75%
TCs, TRP
Tilghman
100%
100%
100%
95%
ALL
50%
50%
50%
Di Salvo
100%
Flow SWITCHES
(general)
TRUNKS
100%
MAJOR PROCUREMENTS
I&C CABLE PLANT
Connectors
DC CABLES, TRAYS
RACKS
CRATES
IOCS
DiSalvo
100%
Rodriguez/Rogers
Di Salvo
Di Salvo
Alarcon
100%
100%
100%
The readiness status of all controls racks are
reviewed weekly (sheet on SharePoint)
Rack Profiles on SharePoint
For each I&C rack we
track the equipment to
be installed in each
“row”
Green – Installed
Yellow – Not installed,
but there are no issues
Red – Cause for
concern
Controls Installation Schedule Overview
LTU/Undulator/e-Dump
Controls Installation
Overview
Control System Cable Plant & Racks
Nearly 100% of cable plant is installed and
terminated.
All Instrumentation Racks are installed and
operational
Control Systems Software Section
FAC November 2008
10
Ernest Williams
Control System Crates & IOCs, Modules
VME Crates are all installed and operational
All IOCs are installed and operational
We are in the end-to-end checkout phase
There are currently no anticipated major
delays in completing most of the pre-beam
checkout.
Control Systems Software Section
FAC November 2008
11
Ernest Williams
IOCs
Large number of IOCs running reliably for
LCLS Accelerator
136 Coldfire-based embedded IOCs
Mainly used for BPM and LLRF front-end processors
104 MVME6100 IOCs
33 MVME3100 IOCs
Beamlines will also use some number
RTEMS-based IOCs for Slow controls
Control Systems Software Section
FAC November 2008
Ernest Williams
Magnet Power Supply Control
Magnet Control System ready to support
end-to-end checkout
Alarm Handler, SCORE, ChannelWatcher
and Archiver configs are ready
Control Systems Software Section
FAC November 2008
13
Ernest Williams
Safety Systems
Separate talks later today on Safety Systems
BCS
Mature design
Project is on schedule
PPS
The Initial Acceptance Test of the Undulator Complex has been
executed.
New documentation control process in place
Control Systems Software Section
FAC November 2008
14
Ernest Williams
MPS Systems
MPS
Concurrently developing new LCLS MPS
Response time of less than one pulse at 120 Hz
New hardware extended 1.2 km past current
MPS
Non-CAMAC
Ready for photon section
Pre-beam checkout will begin mid November
Control Systems Software Section
FAC November 2008
Ernest Williams
Networks
Accelerator Network Infrastructure supports I&C Ethernet
and MPS
The project consists of:
Network architecture design
Cable Plant Davis Bacon Phase IV & Phase V Contracts
Fiber Termination Contract
e-Controls networks Integrate with other networks:
Undulator Alignment Diagnostics System Network
Conventional Facilities
Photon Sections
SLAC Scientific Computing and Computing Services (SCCS)
centralized networking groups are helping with all networks
New network tech hired on to support Terri Lahey
Control Systems Software Section
FAC November 2008
16
Ernest Williams
Network Design
Accelerator Switches reside in service buildings 911, 912,
913 and 921, and FEE
Undulator accelerator switches are in service buildings
B913 & B921 to reduce heat-load
The network consists of Cat6 long hauls between service
building patch panels and cat6 boxes at racks
Tunnel walkup stations: one each COW and wireless
access
Other IOCs are located in service buildings: MPS, BPM,
etc.
Fiber Trunks support Ethernet switches and MPS
Control Systems Software Section
FAC November 2008
17
Ernest Williams
Davis Bacon & Fiber Contracts
Phase IV:
install and test cat6 long hauls
Phase V:
fiber pull
Fiber Termination Contract
terminate and test fibers for e-beam, photon, & timing
SCCS/Lahey created contract using knowledge/process
learned from BC2 fiber termination contract
Control Systems Software Section
FAC November 2008
18
Ernest Williams
Networks Procurements
Fiber trunks purchased
The order for network switches is in
purchasing
DIGI terminal servers have been ordered
Patch panels have been ordered
Remaining: fiber jumpers and FODU (Fiber
Optic Distribution Units)
Control Systems Software Section
FAC November 2008
19
Ernest Williams
Timing System
The scope is to deliver triggers and timestamp data
to all subsystems requiring such.
The system can be split into two parts
Long-haul distribution of triggers from the EVG to EVRs
in LTU and beyond
Short-haul back end consisting of the HW & SW to
receive the EVG timing signal and generate triggers.
This is the extension of the timing for BC2
We have a procurement for the "back end" of the
timing system consisting of all the HW (fan-outs,
EVRs, crates, cables) to deliver triggers to the end
subsystem.
Control Systems Software Section
FAC November 2008
20
Ernest Williams
Beam Diagnostics
Profile Monitors:
OTR30 and OTR33 installed and checked out. Waiting on air from
Central Facilities
OTRDMP controls are ready but device will be installed in the tunnel
this week. End-to-End checkout follows.
YAGXRAY controls is in progress. Waiting on fiber pull this week.
TOROIDs (Controls are ready):
IM31 (system checkout complete)
IM36 (system checkout complete)
IMUNDO (waiting on cable termination)
IMUNDI (waiting for device installation and cable termination this week.)
IMDMP (waiting on cable termination)
Control Systems Software Section
FAC November 2008
21
Ernest Williams
Beam Diagnostics (Cont’d)
BPMs
All new Stripline BPMs controls pre-beam
checkout complete
Cavity BPM controls pre-beam checkout in
progress.
Cavity BPM Calibration software is now in
development.
Control Systems Software Section
FAC November 2008
Ernest Williams
Beam Diagnostics (Cont’d)
Alignment Diagnostic System (ADS)
Interface to EPICS in good shape undergoing
checkout
Control Systems Software Section
FAC November 2008
Ernest Williams
Facilities
HVAC
EPICS Interface complete and undergoing
checkout.
Chiller/Boiler
EPICS Interface complete and undergoing
checkout
LCW
EPICS Interface complete and undergoing
checkout
Control Systems Software Section
FAC November 2008
Ernest Williams
Vacuum
Vacuum Pump Controllers
Vacuum Guage Controllers
Vacuum Valve Controllers
PLCs for interlocks and control
Cabling and Connectors
Drawing and documentation in progress and
in good shape.
Control Systems Software Section
FAC November 2008
25
Ernest Williams
Controls Subsystem Risk Matrix
System
Risk
Magnet Power Supply control
Racks, Crates, IOC
Vacuum Control
PPS, BCS
Motion Control
OTR/YAG
Networks
Cavity BPM ADC
MPS
BPM
Undulator Control
Cable Plant
Control Systems Software Section
FAC November 2008
In good shape
Complete
In good shape
In good shape
In good shape
In good shape
Complete
New design
New design
New design
Handover Concerns
Complete
26
Ernest Williams
Test Plan and Risk Analysis
Control Systems Software Section
FAC November 2008
27
Ernest Williams
Testing & Checkout Strategies
Rack loading & testing
Will accomplish as much as possible in B024
prior to transporting racks to the field.
In-field loading (Davis-Bacon) and intra-rack
cabling is less efficient.
Networks and Timing will be the first system
to be made operational in field to allow
booting of IOCs and testing
Control Systems Software Section
FAC November 2008
28
Ernest Williams
Rack Assembly Area (B024 )
B913 & B921 PS racks
B911 & B912 PS racks
Control Systems Software Section
FAC November 2008
29
Ernest Williams
Procedure for AC Power Release to Rack
Systems
Purpose:
To provide for safe AC power application to the individual rack
distribution systems (plug molds, outlets, breaker panels, ect.) and
equipment in the racks
Constraints:
Ensure that with the application of AC power to each rack no
electrical hazards are created via rack equipment, cable plant or
conductors (either within or leaving the rack).
Procedure
Identify/list all potential hazards, correct or neutralize any potential
electrical hazard, request and receive approval from LCLS Controls
Manager and the LCLS Installation Manager (R. M. Boyce) for the
release/application of AC power to identified rack.
Once approval is given appropriate breakers will be unlocked and
control of breakers turned over to responsible system engineer.
Control Systems Software Section
FAC November 2008
30
Ernest Williams
PP-6 After Contractor Turn-over & LCLS Safety Lockout
PP-7 After Contractor Turn-over & LCLS Safety Lockout
Control Systems Software Section
FAC November 2008
31
Ernest Williams
Rear of Racks LKG-03 thru LKG-10 (12/05/06)
Control Systems Software Section
FAC November 2008
32
Ernest Williams
Software Installation Status
All IOCs have loaded their software from a central EPICS file
server. The server is ready to support pre-beam checkout and
commissioning.
All controls software will be installed and checked out according
to a “signed off” test plan.
Alarm Handler, Archiver, autosave/channelWatcher, Channel
Access Security, and SCORE ready to support pre-beam
checkout and commissioning
Software has been installed following the LCLS software
RELEASE procedure.
Control Systems Software Section
FAC November 2008
33
Ernest Williams
Issues & Concerns
Schedule & Resources
Controls is the systems “integrator” – delays in other
systems directly impact our installation. This has been
the case in the Injector and BC2 installation phases
Support of operations while completing final
installation and pre-beam checkout of
LTU/UND/EDMP
System Functionality
The new MPS – pre-beam checkout will be tight
Control Systems Software Section
FAC November 2008
34
Ernest Williams
Summary
Controls in general is in good shape for 2008 installation
No major design or production issues dominate the plan
There are concerns about the transfer of systems from ANL
to SLAC.
We will use BLMs from PEP (Thanks to Alan Fischer)
We have received a draft “HandOver” and a draft
“Detailed Software Design Document” plan from ANL
A large number of sub-systems have been installed and
pre-beam checkout is the major activity before Dec. 1, 2008
Control Systems Software Section
FAC November 2008
35
Ernest Williams