Photon Systems Update John Arthur LCLS Photon Systems Manager FAC recommendations Current status New plan for Photon Systems October 29, 2007 Photon Systems 1 John Arthur jarthur@slac.stanford.edu Recommendations from April 2007 Get mirrors spec’ed and ordered asap Refine commissioning plan Get a good system in place, then make it better Response: Trying to follow recommendations. However, the new plan has significantly affected the X-ray schedule October 29, 2007 Photon Systems 2 John Arthur jarthur@slac.stanford.edu XTOD Status Design phase ending Beamline layout details almost complete Nearly all technical components at or near Final Design Review phase Procurements underway Soft X-ray mirrors on order, Hard X-ray mirrors to be ordered in Dec 2007 (breakout talk) October 29, 2007 Photon Systems 3 John Arthur jarthur@slac.stanford.edu XES Status Now in design phase AMO instrument design going well (breakout talk) 2-d detector development going well Controls/DAQ going well (plenary, breakout talks) PPS stopper design being finalized October 29, 2007 Photon Systems 4 John Arthur jarthur@slac.stanford.edu Effects of the CR CR caused delays and inefficiencies in FY07 Design reviews were delayed due to uncertain scope, schedule and busy managers XTOD procurements were delayed in FY07 October 29, 2007 Photon Systems 5 John Arthur jarthur@slac.stanford.edu The New Plan: Big Picture Try to move as much budget as possible beyond FY08, consistent with first light in May 2009, experiments later in FY09 Phased approach to X-ray beamline delivery NEH in FY09, FEH in FY10 Diagnostics ready for first light in May 2009 First AMO experiment ready late July 2009 Remove as much schedule float as possible October 29, 2007 Photon Systems 6 John Arthur jarthur@slac.stanford.edu The New Plan: Details Delay many AMO procurements until FY09 Pushes AMO instrument availability to 7-09 Delay some FEE work until FY09 First light in FEE 5-09 First light in NEH 7-09 Puts this some XTOD work on the project critical path October 29, 2007 Photon Systems 7 John Arthur jarthur@slac.stanford.edu The New Plan: Details 2 Ready to support LUSI in NEH in late FY09 Hard X-ray line to Hutch 3 will be complete Get authority to begin expt’l operations Experiments in NEH in FY09 AMO and LUSI experiments October 29, 2007 Photon Systems 8 John Arthur jarthur@slac.stanford.edu XTOD key milestones (Level 3) Award High-Energy mirror PO 12-2007 Start FEE installation 7-2008 October 29, 2007 Photon Systems 9 John Arthur jarthur@slac.stanford.edu XES key milestones (Level 3) AMO Preliminary Design Review 11-2007 Award Laser system PO 11-2008 Start installation in NEH 1-2009 October 29, 2007 Photon Systems 10 John Arthur jarthur@slac.stanford.edu October 29, 2007 Photon Systems 11 John Arthur jarthur@slac.stanford.edu Preparation for good news: Possible X-ray speedups If more FY08 funds become available, we could: Speed up controls and collimators for FEE (1000k) Speed up X-ray monitors in FEE (300k) Speed up NEH controls and motors (450k) Speed up XES laser system (340k) Speed up AMO focusing mirrors (115k) Maybe advance first light date by 1-2 months October 29, 2007 Photon Systems 12 John Arthur jarthur@slac.stanford.edu LCLS Installation and Commissioning Time-Line X-ray tunnel/FEH Install LTU/Und/Dump Install FEH X-rays CF Early Occupancy NEH X-rays FEE/NEH Install CD-4 (7/30/10) PPS PPS S OND J FMAM J J A S OND J FMAM J J A SOND J FMAM 2007 2008 2009 2010 Linac/BC2 Install October 29, 2007 Photon Systems Linac/BC2 Commissioning LTU/Und Commissioning Tunnel/FEH Commissioning FEE/NEH Commissioning 13 John Arthur jarthur@slac.stanford.edu Summary XTOD is in procurement phase, XES still in design XTOD and XES have suffered delays due to CR New plan allows recovery with extended project, phased completion, some procurement delays Aiming for first light 5-09, first experiments in NEH shortly thereafter Working closely with LUSI October 29, 2007 Photon Systems 14 John Arthur jarthur@slac.stanford.edu