Photon Systems Update FAC recommendations Current status New plan for Photon Systems

advertisement
Photon Systems Update
John Arthur
LCLS Photon Systems Manager
FAC recommendations
Current status
New plan for Photon Systems
October 29, 2007
Photon Systems
1
John Arthur
jarthur@slac.stanford.edu
Recommendations from April 2007
Get mirrors spec’ed and ordered asap
Refine commissioning plan
Get a good system in place, then make it better
Response: Trying to follow recommendations.
However, the new plan has significantly affected
the X-ray schedule
October 29, 2007
Photon Systems
2
John Arthur
jarthur@slac.stanford.edu
XTOD Status
Design phase ending
Beamline layout details almost complete
Nearly all technical components at or near
Final Design Review phase
Procurements underway
Soft X-ray mirrors on order, Hard X-ray mirrors
to be ordered in Dec 2007 (breakout talk)
October 29, 2007
Photon Systems
3
John Arthur
jarthur@slac.stanford.edu
XES Status
Now in design phase
AMO instrument design going well (breakout talk)
2-d detector development going well
Controls/DAQ going well (plenary, breakout talks)
PPS stopper design being finalized
October 29, 2007
Photon Systems
4
John Arthur
jarthur@slac.stanford.edu
Effects of the CR
CR caused delays and inefficiencies in FY07
Design reviews were delayed due to uncertain
scope, schedule and busy managers
XTOD procurements were delayed in FY07
October 29, 2007
Photon Systems
5
John Arthur
jarthur@slac.stanford.edu
The New Plan: Big Picture
Try to move as much budget as possible beyond FY08,
consistent with first light in May 2009, experiments later
in FY09
Phased approach to X-ray beamline delivery
NEH in FY09, FEH in FY10
Diagnostics ready for first light in May 2009
First AMO experiment ready late July 2009
Remove as much schedule float as possible
October 29, 2007
Photon Systems
6
John Arthur
jarthur@slac.stanford.edu
The New Plan: Details
Delay many AMO procurements until FY09
Pushes AMO instrument availability to 7-09
Delay some FEE work until FY09
First light in FEE 5-09
First light in NEH 7-09
Puts this some XTOD work on the project critical path
October 29, 2007
Photon Systems
7
John Arthur
jarthur@slac.stanford.edu
The New Plan: Details 2
Ready to support LUSI in NEH in late FY09
Hard X-ray line to Hutch 3 will be complete
Get authority to begin expt’l operations
Experiments in NEH in FY09
AMO and LUSI experiments
October 29, 2007
Photon Systems
8
John Arthur
jarthur@slac.stanford.edu
XTOD key milestones (Level 3)
Award High-Energy mirror PO
12-2007
Start FEE installation
7-2008
October 29, 2007
Photon Systems
9
John Arthur
jarthur@slac.stanford.edu
XES key milestones (Level 3)
AMO Preliminary Design Review
11-2007
Award Laser system PO
11-2008
Start installation in NEH
1-2009
October 29, 2007
Photon Systems
10
John Arthur
jarthur@slac.stanford.edu
October 29, 2007
Photon Systems
11
John Arthur
jarthur@slac.stanford.edu
Preparation for good news:
Possible X-ray speedups
If more FY08 funds become available, we could:
Speed up controls and collimators for FEE (1000k)
Speed up X-ray monitors in FEE (300k)
Speed up NEH controls and motors (450k)
Speed up XES laser system (340k)
Speed up AMO focusing mirrors (115k)
Maybe advance first light date by 1-2 months
October 29, 2007
Photon Systems
12
John Arthur
jarthur@slac.stanford.edu
LCLS Installation and Commissioning Time-Line
X-ray tunnel/FEH Install
LTU/Und/Dump
Install
FEH X-rays
CF Early
Occupancy
NEH X-rays
FEE/NEH Install
CD-4
(7/30/10)
PPS
PPS
S OND J FMAM J J A S OND J FMAM J J A SOND J FMAM
2007
2008
2009
2010
Linac/BC2
Install
October 29, 2007
Photon Systems
Linac/BC2
Commissioning
LTU/Und
Commissioning
Tunnel/FEH
Commissioning
FEE/NEH
Commissioning
13
John Arthur
jarthur@slac.stanford.edu
Summary
XTOD is in procurement phase, XES still in design
XTOD and XES have suffered delays due to CR
New plan allows recovery with extended project, phased
completion, some procurement delays
Aiming for first light 5-09, first experiments in NEH shortly
thereafter
Working closely with LUSI
October 29, 2007
Photon Systems
14
John Arthur
jarthur@slac.stanford.edu
Download