Report to the LCLS Facilities Advisory Committee Mark Reichanadter LCLS Deputy Project Director Project Management Project Progress / Status Revised Project Baseline Overview Procurement Status Risk Management and PM Issues Summary October 29-31, 2007 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Progress to Date LCLS Status on Approved Baseline TPC $379M (TEC $315M, OPC $64M) % Comp (Aug07): Planned: 67.8% Actual: 57.7% LCLS Status @ Level 2 Injector TPC complete. All commissioning goals met. Linac recovering from CR effects. Installing equipment. Undulator accepting deliverables. Prep for installation XTOD has a mature design. Procurements underway. XES in design, planning procurements Conventional Facilities in construction Injector S20 Facilities, MMF in operations >98% of all civil construction under contract FEH Hutches, Office space renovation still in design October 29-31, 2007 LCLS FAC Meeting 2 Mark Reichanadter reich@slac.stanford.edu LCLS Progress on Approved Baseline LCLS Project Performance (TEC) • TEC SPI = 0.85 • TEC CPI = 0.92 350,000 300,000 AYK$ 250,000 BCWS (TEC) BCWP (TEC) 200,000 ACWP (TEC) BAC 150,000 BA 100,000 OBL-S (TEC) EAC • EAC up-trend BCWP downtrend, due to CR • $ total burn rate ~$7-8M per/mo • SLAC labor portion burns ~ $2.5M/mo 50,000 0 09 bFe 8 -0 ct O 08 nJu 8 0 bFe 7 -0 ct O 07 nJu 7 0 bFe 6 -0 ct O 06 nJu 6 0 bFe 5 -0 ct O 05 nJu 5 0 bFe 4 -0 ct O October 29-31, 2007 LCLS FAC Meeting 3 Mark Reichanadter reich@slac.stanford.edu LCLS TEC Earned Value (through Aug07) Cum Work Scheduled (BCWS) Cum Work Performed (BCWP) Cum Actual Costs (ACWP) Cum Cost + Com to Date Estimate at Complete (EAC) % Contingency on EAC $207.4M $176.1M $191.7M $233.5M $303.9M 10.9% •% contingency/ETC dropped from ~22% to 10.9% since Oct06 due to CR and funding uncertainties. Project team working on unplanned work (CR scenarios, replanning project, review preparation, etc.) October 29-31, 2007 LCLS FAC Meeting 4 Mark Reichanadter reich@slac.stanford.edu Cost and Schedule Variance Trend LCLS TEC Cost and Schedule Variances 5,000 0 AYK$ (10,000) (15,000) (20,000) SV (25,000) CV (30,000) (35,000) • CV and SV show significant degradation •Redirected staff to address directed rebaseline •Delay and acceleration costs due to CR uncertainty •Defer XT and XE procurements until FY09 October 29-31, 2007 LCLS FAC Meeting 5 Mark Reichanadter reich@slac.stanford.edu 7 l-0 Ju 7 r- 0 Ap 07 nJa 6 -0 ct O 6 l-0 Ju 6 r- 0 Ap 06 nJa 5 -0 ct O 5 l-0 Ju 5 r- 0 Ap 05 nJa 4 -0 ct O (5,000) CR Funding Uncertainty Time-Line LCLS CD-2 TPC Funding Profile AYM$ Continuing Resolution LCLS funded incrementally at ~$86M level. FY07 planned funding $122M Funding Uncertainty A S O N D 2006 Possible year-long CR No funding restoration until FY09 Hold on all LCLS Procurements October 29-31, 2007 LCLS FAC Meeting J 120 100 80 60 40 20 0 FY02 FY03 FY04 F M A M 2007 FY05 FY06 FY07 FY08 J J A S Funds arrive at ANL Budget passed. LCLS funded at $114M level 6 DOE-BES directs LCLS to revise baseline plan. Mark Reichanadter reich@slac.stanford.edu FY09 CR Impacts and Mitigation Actions Impact: FY07 funding uncertainties for six months $8M FY07 funding reduction, no restoration until FY09 Mitigation: Directed to develop revised plan with reduced FY07 funding profile. Defer selected procurements from FY07 to FY09. Accelerate shutdown procurements to recover schedule Cost: $41.0M Project extended by 16 months Staffing costs, no changes to scope Project is funding limited in FY08 October 29-31, 2007 LCLS FAC Meeting 7 Mark Reichanadter reich@slac.stanford.edu Mitigation – Defer Procurements and Replan Beam Transport Hall Undulator Hall Near Experimental Hall Far Experimental Hall X-Ray Transport Tunnel Defer Photon equipment and FEH hutches until FY09 October 29-31, 2007 LCLS FAC Meeting 8 CD-4 LCLS Operations in FEH - July 2010 Mark Reichanadter reich@slac.stanford.edu Revised Baseline Plan Revise LCLS baseline to deliver technical scope on cost and on schedule Address effects of the CR and FY07 funding reduction Shift photon and FEH procurements from FY07 to FY09 Update remaining work (ETC) using current estimates No changes in scope or technical capabilities Update overhead rates and escalation Update OPC to reflect LCLS transition to operations Update cost/schedule contingencies and risk planning October 29-31, 2007 LCLS FAC Meeting 9 Mark Reichanadter reich@slac.stanford.edu Revised ETC, BAC @ L2 WBS ACWP through Remaining Work % Jun07 (ETC) Complete Budget at Completion 1.1 Project Management 16.69 5.41 76% 22.10 1.2 Injector 20.07 0.10 99% 20.17 1.3 Linac 15.01 12.89 54% 27.90 1.4 Undulator 29.49 14.56 67% 44.05 1.5 X-ray Transport 13.86 10.70 56% 24.56 1.6 X-ray Endstations 1.77 6.69 21% 8.46 1.9 Conventional Facilities 59.09 73.29 45% 132.38 1.X Controls 1 LCLS Total Base Cost 18.17 174.15 22.07 145.72 45% 54% 40.24 319.87 2 LCLS Other Project Cost LCLS Total Project Cost (TPC) October 29-31, 2007 LCLS FAC Meeting LCLS Total Estimated Cost (TEC) 352.00 Available Contingency 32.13 % Contingency on Cost to Go (ETC) 22.1% 17.11 42.89 28.5% 60.00 LCLS Total Other Project Costs (OPC) 68.00 Available Mgmt Reserve 8.00 % Mgmt Reserve on ETC 18.7% 191.26 188.61 10 45.5% Revised baseline presented to Lehman in Sep07 and EIR in Oct07. 420.00 Mark Reichanadter reich@slac.stanford.edu BASIS OF ESTIMATE LCLS PROJECT: TEC Basis of Estimate on Remaining Work (TEC) Catalog/Construction Database 0% Significant portion of ETC is contracts in hand. Reduce cost risk. Engineering Estimates (Similar Items or Procedures) 29% Under Contract/Bids in Hand 45% Vendor Quote Estimate (Dwgs/Sketches/Specs) 9% Engineering Estimate (Analysis) 5% Expert Opinion (Allowance) 0% October 29-31, 2007 LCLS FAC Meeting Engineering Estimates (Dwgs, Sketches/Specs) 12% 11 Mark Reichanadter reich@slac.stanford.edu Revised TEC Funding & Obligations LCLS TEC Funding and Commitments 400 Project is fundinglimited in FY08 350 300 (AY$M) 250 BCWS 200 Commitments DOE Funding 150 100 50 0 FY07 October 29-31, 2007 LCLS FAC Meeting FY08 FY09 FY10 12 Mark Reichanadter reich@slac.stanford.edu LCLS Schedule & Milestones Major Milestones Sept 2009 – Initiate Early Experimental Operations FY09 Funding – Pop-Up Cameras – install – NEH commission Total float ~49 working days to L2 milestone Near CP – BPMs, Undulator vacuum system, Undulator testing July 2010 – Photons in FEH (CD-4, Project Complete) FY09 Funding – Pop-Up Cameras – install – FEH commission Includes 2 months to process DOE project closeout activities Total float to CD-4; ~101 working days to CD-4 Near CP – XT/XE procurements, FEH Hutches LCLS schedule includes integrated Turner Schedule “Early-occupancy” dates meet LCLS requirements Turner earned-value tracked by site walks, OAC meetings LCLS installation schedules integrated with Turner RM Boyce providing oversight on global integration October 29-31, 2007 LCLS FAC Meeting 13 Mark Reichanadter reich@slac.stanford.edu Rebaseline Timeline Sep5 – PMOG Meeting Review revised baseline plan Cost and schedule contingencies considered adequate Response to Jul07 Lehman recommendations ~reasonable Sep7 – EIR Pre-Briefing Documentation Complete Sep18 – Mini-Review (Lehman) with DOE-BES Endorsed revised cost and schedule baseline. Expressed concern over not enough management staffing Oct 9-12 – OECM on-site EIR (w/LMI) Validated reasonableness of cost and schedule baseline. ~10-12 findings in Out-Brief, EIR Draft not yet received Developing Corrective Action Plan (CAP) to address findings ~mid-Nov – ESAAB to approve new LCLS baseline LCLS to ‘retire’ old baseline and start reporting on new baseline October 29-31, 2007 LCLS FAC Meeting 14 Mark Reichanadter reich@slac.stanford.edu LCLS Procurements LCLS using co-located procurement group (7 staff) Procurement Manager – D. Pindroh B. Miller ~rolled-off, J. Dee (Negotiator) roll-off ~early 08. Weekly status meetings monitor Critical and APPs ~$30M of $190M of procurements yet to be awarded Space Renovation, 2 FEH Hutches, Install Contracts Field Change Order Process monitored closely <4% FCO’s on work accomplished This is working well. Same organization to procure LUSI Procurement Issues DOE SSO to approve all SLAC procurement actions >$100K Use detailed tracking document. Added to risk registry. Turner Claim. May go to arbitration. Support from SLAC Counsel and Stanford Attorney Additional time sink on CF & PO staff. Tracked in risk registry. October 29-31, 2007 LCLS FAC Meeting 15 Mark Reichanadter reich@slac.stanford.edu Technical Requirements Summary Requirements Document Total No. Documents Number Approved Number in Sign-Off % Complete Comments Global Requirements Document (GRD) 1 1 0 100 Complete Physics Requirements Documents (PRDs) 85 78 1 92 Electron Beam Systems XTOD XES Conventional Facilities 61 15 7 2 61 11 4 2 0 0 0 0 100 73 57 100 Engineering Specification Documents (ESDs) 143 111 0 77 Management Controls Injector Linac Undulator XTOD XES Conventional Facilities 3 21 31 22 19 20 15 12 3 20 31 21 14 10 0 12 0 0 0 0 0 0 0 0 100 95 100 95 74 50 0 100 Room Data Sheets (RDSs) 54 54 0 100 Interface Control Documents (ICDs) 14 12 0 86 Injector Linac/Controls Undulator XTOD XES 3 5 1 2 3 3 5 1 2 1 0 0 0 0 0 100 100 100 100 33 October 29-31, 2007 LCLS FAC Meeting 16 Mark Reichanadter reich@slac.stanford.edu Project Management Risks & Mitigations Contingency Analysis Rebaseline project. Need a baseline to measure against Implement contingency management plan through FY08 Control Account Mischarges (at SLAC) Effective use of project tools to track actual costs Timely closure of control accounts SSO Prior Approval of Bids & Contracts >$100K Track weekly active procurements Installation Schedules Track weekly installation status, Integrate installation schedules Safety Incident or Accident Implement ISM plan, work authorization processes Lessons learned at the completion of major activities Owner-Directed Changes to Conventional Facilities Implement weekly walk-arounds by Photon Systems, LUSI staff System Managers and LUSI Staff review shop drawings October 29-31, 2007 LCLS FAC Meeting 17 Mark Reichanadter reich@slac.stanford.edu Project Management Staffing LCLS management responsibilities expanding Year-long CR + Rebaseline effort SLAC Transitioning to multi-program (BES-driven) LCLS Directorate Formed LUSI integrated into LCLS LCLS includes Operation and Science Insufficient management staffing to meet requirements Identified as an Action Item in DOE Sep07 Mini-Review LCLS adding key staff to Project Office Considerable assistance from SLAC Acting Director, P. Drell Emphasis on project management and integration resources Final staffing plan to be completed by early November Needed for ESAAB approval October 29-31, 2007 LCLS FAC Meeting 18 Mark Reichanadter reich@slac.stanford.edu Summary Despite FY07 CR and rebaseline LCLS making satisfactory progress. TPC/TEC 58%/62% complete. Milestone performance reasonable. Injector complete, steady progress in civil construction. LCLS has prepared a revised baseline to address the FY07 CR effects. TPC of $420M and delayed CD-4 (16 month extension) ESAAB scheduled for Nov07. Revised ETC allows the project to complete its commitments to DOE. No changes to scope or technical capabilities Cost and schedule contingencies are adequate Contingency remains tight in FY08. Need to manage carefully. Challenges ahead: Maintain construction progress, refocus on building the project Major installation push through FY08. Preparation for LCLS transition to operations and LUSI Continue to add staff to prepare for LCLS Experiment Support and Operations. October 29-31, 2007 LCLS FAC Meeting 19 Mark Reichanadter reich@slac.stanford.edu