Control System Overview April 16, 2007 Outline Injector control system installation &

advertisement
Control System Overview
April 16, 2007
Hamid Shoaee
for the
LCLS Controls Group
Outline
Injector control system installation &
commissioning
Status update
Linac & beyond
Summary
April 2007
LCLS Facility Advisory Committee
1
Hamid Shoaee
hamid@slac.stanford.edu
Accomplishments in the past six months
Field installation of large amount of cable plant, networking,
racks, electronics and software for injector control
Development of detailed plans for linac and BC2 installation
Coordination and re-planning of undulator control with ANL
Development of a conceptual design for X-ray End Stations
DAQ and Controls
AIP projects for MCC networks upgrade, LCLS MPS and
Linac BPM
Starting the design of next generation applications software
April 2007
LCLS Facility Advisory Committee
2
Hamid Shoaee
hamid@slac.stanford.edu
The main focus in the past six months has
been the installation and commissioning of the
injector Controls
Installation of the cable plant including trays, long haul DC
and I&C cables, terminations, etc.
Phase 1 (Apr. ’06 thru Jun. ’06)
Phase II (Aug. ’06 thru Dec. ’06, including Christmas holidays)
Final terminations were occasionally delayed pending mechanical
installations
Installation of the electronics racks, loading of crates,
electronics chassis, modules, and intra-rack wiring
Installation of the Controls software on the front-end
computers (IOC) and production servers
April 2007
LCLS Facility Advisory Committee
3
Hamid Shoaee
hamid@slac.stanford.edu
Phase II Installation Scope - Gun to TD11
April 2007
LCLS Facility Advisory Committee
4
Hamid Shoaee
hamid@slac.stanford.edu
MCC, Networks, Servers, & Workstations
Production Systems Delivered
Networks at S20 RF Hut & MCC: physical and
wireless
LCLSDMZ, LCLS private, wireless
MCC infrastructure upgrade: power & racks
LINUX Servers for applications and EPICS data
archiving
Control Room Linux Workstation
MCC and S20 Laser Room are actively in use
for commissioning
April 2007
LCLS Facility Advisory Committee
6
Hamid Shoaee
hamid@slac.stanford.edu
Main Control Center is in full operation
All LCLS Safety Systems Are Operational
Laser Safety System (LSS)
Was needed early to allow laser commissioning
PPS
Passed many reviews by internal and external reviewers, citizens
committees
The FIRST SLAC programmable PPS is online and operational
BCS
Prevents radiation from ‘escaping’ the shielding enclosure
Direct measurements of radiation or beam loss
Protection of safety-critical collimators and stoppers
The need for BCS was identified late, and the system had an
aggressive schedule, but was completed and certified in time for
ARR approval
April 2007
LCLS Facility Advisory Committee
8
Hamid Shoaee
hamid@slac.stanford.edu
Safety Systems – MPS
Interim MPS
Using existing linac infrastructure (1553 MPS)
Adding new signals and devices for LCLS
Interim MPS will be used for gating beam
Single Shot Mode
Burst Mode
Pockels cell and MPS mechanical shutter limit laser rate
on cathode
LCLS MPS (presentation at break out)
Will be used to protect the undulator and photon
sections
Held conceptual design review, now proceeding to
detailed design
April 2007
LCLS Facility Advisory Committee
9
Hamid Shoaee
hamid@slac.stanford.edu
Controls Sub-Systems installed













 Faraday Cup
Cable Plant, Racks, etc.
Networking
MCC infrastructure
Magnet power supply
Vacuum Controls
LLRF
Timing
Laser control
Laser alignment
OTR/YAG image acquisition
BPM
Toroid
Wire Scanners
April 2007
LCLS Facility Advisory Committee












10
Cerenkov monitor
Moveable collimator
BC1 beamline control
Bunch length monitor
LSS
PPS
MPS
BCS
Gun Temp stabilization
Image management
Online Models
MATLAB interface
Hamid Shoaee
hamid@slac.stanford.edu
…and arriving soon
BPM acquisition through SCP (SLC-AWARE IOC)
Orbit fitting
April 2007
LCLS Facility Advisory Committee
11
Hamid Shoaee
hamid@slac.stanford.edu
LCLS Controls Home Screen
Schuh
Norum
Graphical displays help with identifying
components
April 2007
LCLS Facility Advisory Committee
13
Hamid Shoaee
hamid@slac.stanford.edu
Magnet Controls
Magnet software tested & in production
April 2007
LCLS Facility Advisory Committee
15
Hamid Shoaee
hamid@slac.stanford.edu
Vacuum System has been in operation over one month
with signal in data archiving
April 2007
LCLS Facility Advisory Committee
16
Hamid Shoaee
hamid@slac.stanford.edu
Wire Scanner Control
April 2007
LCLS Facility Advisory Committee
17
D. Murray
Hamid Shoaee
hamid@slac.stanford.edu
Movable Beamline
successfully exercised this weekend
April 2007
LCLS Facility Advisory Committee
18
Hamid Shoaee
hamid@slac.stanford.edu
Injector LLRF Work Completed
Linac Sector 0 RF Upgrade
R. Akre
D. Kotturi
All 3 RF Chassis completed and Installed
Sector 20 RF distribution system Phase and Amplitude Controllers (SPAC) - Operational
Phase and Amplitude Detectors (PAD) - Operational
Phased Locked Oscillator – Use SPPS unit for Turn On
LO Generator - Operational
Multiplier – 476MHz to 2856MHz - Operational
4 distribution chassis - Operational
LLRF Control and Monitor System
1 kW Solid State S-Band Amplifiers – 5 units
PADs – 6 Klystron units in Fabrication
PADs – Gun, L0A, L0B, L1S –Operational
PACs – Gun, L0A, L0B, L1S –Operational
Beam Phase Cavity
Pill box cavity with 2 probes and 4 tuners – Complete
April 2007
LCLS Facility Advisory Committee
19
Hamid Shoaee
hamid@slac.stanford.edu
Operational Phase &
Amplitude Detectors
S-Band
Ref
System
Laser
Gun
L0 (A&B)
L1-S
April 2007
LCLS Facility Advisory Committee
20
Hamid Shoaee
hamid@slac.stanford.edu
Operational
Phase &
Amplitude
Controllers
S-Band
Reference
System
Laser
Gun
L0-A
L0-B
L1-S
April 2007
LCLS Facility Advisory Committee
21
Hamid Shoaee
hamid@slac.stanford.edu
Monitoring front end computers (IOC)
April 2007
LCLS Facility Advisory Committee
22
Hamid Shoaee
hamid@slac.stanford.edu
Injection Laser Control System
The injector laser stabilization system includes two
feedback loops
The first loop includes two mirrors, each with two
actuators and one camera. It stabilizes laser traveling
through a 10-meter tube
The second loop includes one mirror with two actuators
and adjusts the laser position on the cathode.
The IOC reads the image from camera, calculates
the laser’s position error and applies a correction to
the actuators.
The loop operates @ 1 Hz, and the camera is
synced to 120Hz.
April 2007
LCLS Facility Advisory Committee
23
Hamid Shoaee
hamid@slac.stanford.edu
Timing System
~
Break out talk
Linac main drive line
FIDO
119 MHz
SLC
MPG
P
N
E
T
SLC
events
360 Hz
E
V
G
LCLS
events
I
O
C
I E
O V
C R
P S
m N T
P E B
T
April 2007
LCLS Facility Advisory Committee
TTL
TTL-NIM
convert.
SLC Trigs
24
LCLS Digitizer
LLRF
BPMs
Toroids
Cameras
GADCs
Old klystrons
Hamid Shoaee
hamid@slac.stanford.edu
Timing System Progress since October, 2006
Completed Installation in sectors 20 and 21
Commissioning is in progress
Finished hardware bench testing
Finished PMC-EVR driver
EVG sequence RAM programming at 360Hz
Timestamp distribution on the EVR IOCs
Completed cabling plans and documentation
Completed beam-synchronous acquisition
April 2007
LCLS Facility Advisory Committee
25
Hamid Shoaee
hamid@slac.stanford.edu
The injector design optics model is now
available online
April 2007
LCLS Facility Advisory Committee
26
Hamid Shoaee
hamid@slac.stanford.edu
MCC Applications & Infrastructure
Configuration management (save & restore)
Alarm management
Error Logs
Data archiving
Correlations plot
Buffeted acquisition
Online model
Artemis problem tracking
Operations and Physics E-logs
The SLC-aware IOC provides beam synchronous data to Buffered
Acquisition and Correlation Plots from a number of sources
AIP network upgrade at MCC for gigabit traffic to support digital control
room
April 2007
LCLS Facility Advisory Committee
27
Hamid Shoaee
hamid@slac.stanford.edu
Applications provided in MATLAB
Image Management
Bunch Length
Measurement
Emittance and Energy
Application
Linac & BC2 Controls Installation (Fall ‘07)
BC2 installation, similar scope to BC1
Very little engineering development
The biggest challenge is meeting the
schedule
The scope includes
Extending the new timing system
Safety systems (MPS, BCS)
Adding new magnets including pulsed horizontal
dipole magnet
Adding BPM, x-collimator, OTR screen
BPM electronics upgraded (resolution improved)
April 2007
LCLS Facility Advisory Committee
29
Hamid Shoaee
hamid@slac.stanford.edu
Linac & BC2 Controls Installation Schedule
Overview: Controls ready 12/3/2007
April 2007
LCLS Facility Advisory Committee
30
Hamid Shoaee
hamid@slac.stanford.edu
X-Ray End Station DAQ & Controls
(Presentation at controls breakout)
Developed a conceptual design for end station data acquisition and control
Held a Conceptual Design Review
Developed a detailed task list and a project plan
The AMOS experiment may eventually take data @120Hz producing ~700
MB/second or 2.4 TB/hour or ~58 TB/24 hour
The plan is to build on previous experience.
Initially use commercial digitizer and COTS CPU for spectrometer data.
Use scalable technology developed for LSST for CCD data.
Capitalize on years of BaBar experience with hierarchical storage and
management of HEP data.
~1 TB/day raw data.
~1 TB/day derived data.
~1.5 PB total Babar data.
Extend/integrate several SLAC-developed Java-based technologies for
data retrieval and analysis.
April 2007
LCLS Facility Advisory Committee
31
Hamid Shoaee
hamid@slac.stanford.edu
XES Detail – Data Acquisition
1. Channel Access (Ethernet)
2. Beam Line 120 Hz Data
4. MPS (Reflective Memory Fiber)
5. SLAC WAN (Ethernet)
3. EVR (Fiber)
6. DAQ Data to SCCS
XES Hutch
XES
private
subnet
EELOG
2 Detector Types
2 DAQ Types
Spectrometer
SBC DAQ
XES Controller
PC
5
1 Gb E
D
A
Non-RTOS
TOF/Momentum
Instrument
1 Gb E
cPCI ADC
G
1 Gb E
Visual Data Monitor
PC
RTOS
Spectrometer Monitor
EPICS Config PVs
Non-RTOS
1 Gb E
1 Gb E
1 Gb E
CCD Pixel
Detector
Beam Line
Processor
SBC
4
MPS PMC
EVR VME
2
Beam Line
Data PMC
1
RTOS
PPC
RTOS
E
Front End Board
1 Gb E
Fast Serial
1 Gb
E
F
CCD Monitor
EPICS Config PVs
C
1 Gb E
10 Gb Enet
Experiment Chamber
Channel Access
Gateway
A. EPICS & Local Control (Hutch Subnet)
D. ADC Control & Digitized Data
FPGA
G
1 Gb E
3
B
CE Module DAQ
XES
Data
Cache
B. Distributed EVR Hardware Triggers
C. Beam Line & Timestamp Data (dedicated Enet)
E. Detector Control & Digitized Data
F. DAQ Data to Cache
April 2007
LCLS Facility Advisory Committee
32
G. Visual Monitor Data
Hamid Shoaee
hamid@slac.stanford.edu
6
Plans for the Next Six Months
Complete the majority of Linac BC2 installation
Develop detailed plans for LTU, Undulator
installation
Complete the design of XES controls, DAQ and
data management
Complete AIP projects
Detailed design for next generation high level
applications
April 2007
LCLS Facility Advisory Committee
33
Hamid Shoaee
hamid@slac.stanford.edu
Breakout Session 4 – CONTROLS
Location – Redwood A, Bldg 48
Monday, April 16th
Time
1:30pm
2:00pm
2:30pm
Topic
Controls commissioning experience
LCLS MPS
BPM and Toroid Update
3:00pm
Break
3:30pm
4:00pm
4:30pm
5:00pm
X-ray End Station (XES) Controls
Timing Systems update
BC2/Linac Controls Installation Planning
Discussion
Presenter
P. Krejcik
S. Norum
S. Smith
R. Sass
S. Allison
H. Shoaee
Tuesday, April 17th
8:00am
MATLAB Applications Software
April 2007
LCLS Facility Advisory Committee
34
M. Zelazny
Hamid Shoaee
hamid@slac.stanford.edu
Conclusions
The injector control system is online & operational
It has taken heroic effort by Controls group to meet
the commissioning deadline
The plans are in place for linac & BC2 installation
We have developed a detailed plan for the
undulator control in collaboration with ANL
A conceptual design is in place for X-ray End
Station data acquisition and control
The major risk for the above items is schedule
rather than technical complexity
April 2007
LCLS Facility Advisory Committee
35
Hamid Shoaee
hamid@slac.stanford.edu
Download