Report to the LCLS Facilities Advisory Committee LCLS Project Management M. Reichanadter / SLAC April 16-17, 2007 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Overview Funding / Cost Status FY07 CR and funding uncertainties have impacted the project. Overall ~2 month delay. Hold on procurements ~six weeks. Redirect resources to evaluate reduced funding options. DOE-BES Directed Baseline Change. July ‘Lehman’ Review – EIR to validate new baseline. Schedule Status Technical systems making steady progress. Milestone performance ~OK. Dip in recent performance (CR). Injector complete in March! Late on Injector installation. Construction in full swing! Start delayed due to high subcontract bids, tunneling coordination. Schedule is CP. Updated Co- and Beneficial milestones. Some issues with Turner activities. Coordination, safety. Most of on-site Turner team have been replaced. April 16-17, 2007 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Overview Management Status Procurement performance ~OK with dedicated cell. Consultants (Miller/Dee), COR/FCO expediter and BOA’s ~95% of civil construction under contract. Remaining technical procurements largely commodities and installation contracts. Integration management team in place (RM Boyce) Organization Injector complete. Good time to re-org. Stronger emphasis on functions (Engr, Controls, Main & Ops, Commissioning, improved integration with Lab operations) Preparing for EVM Certification (Surveillance audit, LBL) April 16-17, 2007 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu LCLS showing steady progress overall LCLS Project Performance (TEC = $315M) • 46% TEC comp • 43% TPC comp 350,000 300,000 $249.6M 250,000 AYK$ BCWS (TEC) 200,000 • SPI = 0.91 • CPI = 0.92 BCWP (TEC) ACWP (TEC) 150,000 BAC • Project burn rate ~$7-8M per/mo BA 100,000 OBL-S (TEC) 50,000 • Labor burn rate ~$2.5M/mo • ~175 SLAC FTE’s 0 09 bFe 8 -0 ct O 08 nJu 08 bFe 7 -0 ct O 07 nJu 07 bFe 6 -0 ct O 06 nJu 06 bFe 5 -0 ct O 05 nJu 5 0 bFe 4 -0 ct O April 16-17, 2007 LCLS FAC Meeting 4 Mark Reichanadter reich@slac.stanford.edu LCLS Project Performance LCLS Cost/Schedule Performance - February 2007 (AYK$) Work Accomplished % Complete Total Budget at Completion 1.1 Project Management 14,432 80.1% 18,013 1.2 Injector 16,196 96.6% 16,760 1.3 Linac 9,783 54.6% 17,932 1.4 Undulator 23,712 62.7% 37,833 1.5 X-ray Transport 10,776 47.8% 22,531 1.6 X-ray Endstations 1,665 17.4% 9,580 1.9 Conventional Facilities 39,572 31.5% 125,535 1.X Controls 1 LCLS Total Base Cost 13,263 129,398 43.0% 46.4% 30,865 279,049 WBS 2 LCLS Other Project Cost LCLS Total Estimated Cost (TEC) 315,000 Available Contingency 35,951 % Contingency on ETC 24.0% 13,805 24.4% • Injector construction completed in March. Commissioning underway. 56,689 LCLS Total Other Project Costs (OPC) 64,000 Available Mgmt Reserve 7,311 % Mgmt Reserve on ETC 17.0% LCLS Total Obligations = $173,402K LCLS Total Project Cost (TPC) April 16-17, 2007 LCLS FAC Meeting 143,203 42.7% 5 379,000 Mark Reichanadter reich@slac.stanford.edu Cost & Schedule Performance LCLS Cost and Schedule Indices (TEC Only) 1.5 1.4 BCWP/BCWS (SPI) 1.3 BCWP/ACWP (CPI) 1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5 07 bFe 06 cDe 6 -0 ct O 06 gAu 06 nJu 6 r- 0 Ap 06 bFe 05 cDe 5 -0 ct O 05 gAu 05 nJu 5 r- 0 Ap 05 bFe 04 cDe 4 -0 ct O • CPI trend: Low-Green. Some benign (Inj / Und Spares), but there are real cost overruns. (Injector Design/Install, RF, MMF, PO Staff). • SPI Trend: Low-Green. CR impacting SPI and CPI (recent downward trend). April 16-17, 2007 LCLS FAC Meeting 6 Mark Reichanadter reich@slac.stanford.edu Contingency Performance % Contingency AvaIlable (on remaining work) • Steady, consistent rise in project % complete. 50% 45% % Complete 40% Cont/ETC • % complete trend expected to increase with CF work ramping up. 35% 30% 25% • CF contingency (FCO) versus earned-value is a modest ~7%. 20% 15% 10% • Contingency based on BAC ‘Cost to Go’. 5% 0% 07 bFe 6 0 cDe 6 -0 ct O 6 0 gAu 6 0 nJu 6 r- 0 Ap 6 0 bFe 5 0 cDe 5 -0 ct O 5 0 gAu 5 0 nJu 5 r- 0 Ap 5 0 bFe 4 0 cDe 4 -0 ct O April 16-17, 2007 LCLS FAC Meeting 7 Mark Reichanadter reich@slac.stanford.edu LCLS Estimate at Complete At Completion WBS Budget at Completion ($K) Estimate at Completion ($K) Variance ($K) 1.1 Project Management 18,013 18,858 844 1.2 Injector 16,760 20,385 3,626 1.3 Linac 17,932 21,112 3,180 1.4 Undulator 37,833 40,209 2,376 1.5 X-ray Transport 22,531 23,714 1,183 9,580 9,456 -124 125,535 126,536 1,001 30,865 32,658 1,792 1 LCLS Total Base Cost 279,049 292,927 13,878 LCLS Total Estimated Cost 315,000 315,000 35,951 22,073 1.6 X-ray Endstations 1.9 Conventional Facilities 1.X LCLS Controls Contingency AYK$ Remaining Work (EAC - BCWP) Contingency Based on EAC 151,434 Outstanding Phase-funded Awards Outstanding Phase-funded CF Awards (Includes A/E, CM/GC and Trade Subcontracts) 82,615 65,766 9,865 15.0% Outstanding Phase-funded Technical Awards 16,849 842 5.0% Remaining Uncommitted Work 68,819 11,365 16.5% April 16-17, 2007 LCLS FAC Meeting 8 •EAC includes all remaining work, overruns, potential credits / liens and corrections for mischarges. •EAC degraded due to funding uncertainties over the past three months. Mark Reichanadter reich@slac.stanford.edu 6-mo Back/Forward L3 Milestones April 16-17, 2007 LCLS FAC Meeting 9 Mark Reichanadter reich@slac.stanford.edu LCLS Schedule LCLS Integrated Schedule Turner Contract Schedule Approved. 100% Resource/Cost Loaded (>95% using trade input) Early-occupancy” dates acceptable and folded into LCLS P3 schedule. CP - Und Hall E.O. – install – FEL commission – Photons in FEH Total project float to CD-4; 131 working days (~6-1/2months) Working to recover recent procurement delays for upcoming shutodwn Near CP – Undulator vacuum system, Undulator testing Schedule Issues Construction schedule is critical path. Delays in civil construction (tunneling coordination, utilities, weather) Track Turner EV in LCLS PMCS, site walk validation, OAC meetings Equipment installation schedule is critical path. (RM Boyce talk) BTH-NEH equipment installation must be well-planned CR uncertainty required a hold procurements in Project Office. Installation reviews for FY07 shutdown and BTH-NEH installation. April 16-17, 2007 LCLS FAC Meeting 10 Mark Reichanadter reich@slac.stanford.edu Procurement planning in decent shape Major LCLS Procurements to be Awarded (~$31.0M) •Procurement cell (8 staff) 12% 19% Controls 10% Laser 3% Linac UN (ANL) 9% 12% XT (LLNL) XES CF 13% D-B Install 22% April 16-17, 2007 LCLS FAC Meeting 11 •Tracking APPs, FCOs, CORs, and Crit. Proc. •LCLS-BSD-SSO meet regularly for good coordination. •B. Miller reducing on-site presence Mark Reichanadter reich@slac.stanford.edu Technical specs continue to mature LCLS Specs • Open ICD’s •XTOD-LUSI •XES-LUSI •XES-CT • Most open requirements are in photon area. April 16-17, 2007 LCLS FAC Meeting 12 Mark Reichanadter reich@slac.stanford.edu Risk registry identifies key project risks Project System Total Risks Identified Risks Retired Risks Open Management 24 20 4 Injector 13 13 0 Linac Undulator 5 29 5 26 0 3 X-Ray, Transport, Optics & Diagnostics 14 11 3 User Requirements, Mirror Design and Procurements X-Ray Endstations Conventional Facilities 5 30 3 20 2 10 120 98 22 Procurement and Scope Uncertainties Tunneling, Linac Legacies, Utilities, CF and UTR Staffing, Turner Management and Legal Total Comments Contingency, Cost Control, Installation, Integration, Controls Management Design, Procure, Construct phase is 100% Complete. Undulator Motion, Vacuum Chamber, RF BPMs • The Risk Registry is now ‘owned’ by the LCLS System Managers. •Better uniformity in assessing risks across the project •Greater visibility with senior management (reviewed monthly) •Better execution of resources (FTE’s & $$$) to handle the risks. April 16-17, 2007 LCLS FAC Meeting 13 Mark Reichanadter reich@slac.stanford.edu Project Management Issues Turner CM/GC contract Still have open issues with Turner. Additional partnering sessions may improve relations. Stay up with FCO’s, RFI’s and trade correspondence Directed Baseline Change FY07 ~$114M (peak funding year), ~$8M less than planned Restore funding in FY2009. Key goals: Maintain civil construction, technical procurements under contract. Maintain core staff an ANL, LLNL and SLAC Full Injector – BC1 commissioning plans CD-4a ~Mar-Jun 2009 soft X-ray science in Near Hall CD-4b ~Mar2010 hard X-ray science in Far Hall Rebaseline cover extended schedule, escalation, army costs April 16-17, 2007 LCLS FAC Meeting 14 Mark Reichanadter reich@slac.stanford.edu ‘Top-down’ projection of revised baseline LCLS Rebaseline Funding Profile AYM$ (TPC = $406M, TEC = $338M, OPC = $68M) 180 160 140 120 100 80 60 40 20 0 FY10 funding TEC = $7.4M Complete Install, Constr staff, PO Pre-Ops = $12.5M, XT, XE, FEH Commission, Physics Support, Pow er, etc. Ops = $13.0M, supports 6-mo NEH and FEH Operations, 1000 hours operations FY09 funding TEC = $30.5M XT, XE Proc + Install, Constr staff, PO Pre-Ops = $16.0M, BTH-NEH Commission, Physics Support, Pow er, etc. Ops = $9.0M, supports ~6-mo NEH Science, ~500 hours operations Ops OPC TEC FY11 funding Ops = $27.3M, Full LCLS operations Prior Yr April 16-17, 2007 LCLS FAC Meeting FY07 FY08 FY09 15 FY10 FY11 Mark Reichanadter reich@slac.stanford.edu Project Management Issues Estimate At Complete shows contingency tight. ~16.5% on commitments to go. Track performance on commitments and FCO’s. Timely closing of control accounts on labor. Hire Deputy Controls Manager ASAP Recent offer did not converge. Still interviewing. EVM Certification Surveillance review Feb12 with J. O’Hearn (LBNL). Scheduling OECM visit for certification in near future. End game planning Installation / Integration must be well-planned Rebaseline will optimize segue into operations. April 16-17, 2007 LCLS FAC Meeting 16 Mark Reichanadter reich@slac.stanford.edu Summary LCLS continues to make steady progress TPC/TEC 46%/43% complete. Milestone performance is good. ~All beam path civil contracts awarded or in hand. CLOC removed. Cost and schedule contingencies adequate for stage of the project. Contingency on EAC will be managed carefully. Remaining cost risk related to schedule, labor overruns or FCO’s Staffing in all areas is adequate (except Controls Manager). Critical path and obligation planning understood, being optimized. Turner management and safety performance is primary concern. Project staff making plans for presenting a revised cost and schedule baseline to address reduction in FY07 funding. April 16-17, 2007 LCLS FAC Meeting 17 Mark Reichanadter reich@slac.stanford.edu