LUSI X-Ray Correlation Spectroscopy Instrument Final Instrument Design Review INTRODUCTION Thomas Fornek Project Manager June 17, 2009 LUSI XCS FIDR June 17, 2009 1 1 T. Fornek tomf@slac.stanford.edu LUSI WBS Organization WBS LUSI XCS FIDR June 17, 2009 TITLE 1.1 Project Management 1.2. X-ray Pump Probe Instrument (XPP) 1.3 Coherent X-ray Imaging Instrument (CXI) 1.4 X-ray Correlation Spectroscopy Instrument (XCS) 1.5 Diagnostics and Common Optics (DCO) 1.6 Controls and Data Acquisition (CDA) 2 2 T. Fornek tomf@slac.stanford.edu Project description (1) LUSI is Providing Instruments for Three of the Six LCLS Instrument Hutches Near Experimental Hall 1 AMO Part of LCLS 2 SXR X-ray Transport 3 4 XCS Mono XPP XCS 5 6 CXI H6 Installation Part of LCLS FES ARRA Funds Beam Transport LCLS LUSI Offset Monochromator Exp. Chamber Detector H6 LUSI XCS FIDR June 17, 2009 Far Experimental Hall 3 3 T. Fornek tomf@slac.stanford.edu Project description (2) CXI WBS 1.3 X-ray transport tunnel (200 m) LCLS SXR XCS WBS 1.4 XPP WBS 1.2 XCS Offset Monochromator WBS 1.5 H6 LCLS AMO LUSI XCS FIDR June 17, 2009 4 4 T. Fornek tomf@slac.stanford.edu Project Status (1) LUSI Baseline Performance (through Apr09) TPC = $60M (MIE = $55.1M, OPC = $4.9M) CD-4 = August 2012 TPC >26% Complete, TEC >18% Complete Contingency on MIE = $11.8M 33.2% on remaining work OPC is complete $50K remaining for close-out ARRA Funds ($33.6M) Received in April Part of the $60M TPC Most recent added scope to enhance LUSI science program Large Offset Monochromator for XPP Focusing lens for CXI LUSI XCS FIDR June 17, 2009 5 5 T. Fornek tomf@slac.stanford.edu Project Status (2) Design Completion XPP Instrument Design through FIDR CD-3 Ready CXI Instrument FIDR Held June 3 CD-3 Ready Now - Solid Instrument Configuration XCS Instrument FIDR in June 90% CD-3 Ready Now - Instrument configuration is solid Diagnostics and Common Optics Design 90% CD-3 Ready Now Harmonic Rejection Mirror PDR held June 15 Controls and Data Acquisition 100% CD-3 Ready Now Inherited Designs from LCLS comprise many items LUSI XCS FIDR June 17, 2009 6 6 T. Fornek tomf@slac.stanford.edu Project Status (3) Final DOE-IPR Status Review Report Received Responses have been prepared to the report recommendations Preparing for the July 15, 2009 CD-3 Review The XCS FIDR is the final pre-requisite for this milestone Held in Germantown LUSI PM, Instrument Scientists and Controls Rep to travel Working on the second part of the Baseline Change to incorporate ARRA effects into the baseline This change incorporates two L2 milestones into schedule One of these milestones is XCS “Early Science” Instrument Complete First month of reporting on ARRA accounts has been completed Some corrections are needed to the baseline – These are nearing completion LUSI XCS FIDR June 17, 2009 7 7 T. Fornek tomf@slac.stanford.edu April Milestone Status LUSI XCS FIDR June 17, 2009 8 8 T. Fornek tomf@slac.stanford.edu Schedule Advancement Milestone Current Baseline Advanced Baseline April 2010 October 2009 XPP Early Science October 2010 October 2010 CXI Early Science August 2011 June 2011 XCS Early Science (New) NA August 2011 Project Ready for CD-4 (New) NA March 2012 August 2012 August 2012 CD-3 CD-4 XCS “Early Science” allows for a functioning XCS instrument one year earlier than original schedule LUSI XCS FIDR June 17, 2009 9 9 T. Fornek tomf@slac.stanford.edu April Status SLAC Linear Accelerator Center Menlo Park, California WBS[2] LUSI Cost/Schedule Status Report (April 2009) Date: Performance Data Cumulative to Date Actual Budgeted Cost Cost Variance Work Work Work Schedule Cost Budgeted Scheduled Performed Performed At Completion Latest Revised Estimate 6/1/2009 Indices Variance SPI CPI 1.1 PROJECT MANAGEMENT 2,353,987 2,353,987 2,265,241 0 88,746 4,955,382 4,896,892 58,490 1.00 1.04 1.2 X-RAY PUMP PROBE (XPP) 2,167,147 2,078,757 2,066,028 -88,390 12,729 5,728,269 5,680,774 47,495 0.96 1.01 1.3 COHERENT X-RAY IMAGING (CXI) 1,249,718 1,246,825 1,041,390 -2,893 205,435 9,890,267 9,913,328 -23,061 1.00 1.20 911,719 819,441 836,065 -92,278 -16,624 6,995,690 7,056,112 -60,422 0.90 0.98 1,213,822 1,203,493 1,191,269 -10,329 12,224 8,311,095 8,541,527 -230,433 0.99 1.01 516,891 504,095 514,934 -12,796 -10,839 7,223,124 7,259,346 -36,223 0.98 0.98 0 0 0 0 0 0 0 0 0 0 0 43,103,826 43,347,980 -244,154 11,996,174 11,752,020 244,154 0.98 1.04 1.4 X-RAY CORRELATION SPECTROSCOPY (XCS) 1.5 DIAGNOSTICS & COMMON OPTICS 1.6 CONTROLS AND DATA ACQUISITION Gen. and Admin. Undist. Budget Sub Total 8,413,284 8,206,598 7,914,927 -206,685 291,671 Management Resrv. (MIE) Total MIE 8,413,284 8,206,598 7,914,927 -206,685 291,671 55,100,000 55,100,000 0 2.0 Other Project Costs (OPC) 4,851,861 4,851,861 4,851,861 0 0 4,851,861 4,851,861 0 48,139 48,139 0 Management Resrv. (OPC) Total OPC Sub Total (MIE+OPC) 4,851,861 4,851,861 4,851,861 0 0 4,900,000 4,900,000 0 13,265,145 13,058,459 12,766,788 -206,685 291,671 47,955,687 48,199,841 -244,154 12,044,313 11,800,159 244,154 60,000,000 60,000,000 0 Total Management Reserve Total Project Cost (TPC) LUSI XCS FIDR June 17, 2009 13,265,145 13,058,459 12,766,788 -206,685 10 10 291,671 T. Fornek tomf@slac.stanford.edu Project Risks and Mitigation LUSI Follows the LCLS Risk Management Plan and uses the LCLS Risk Registry LCLS Project Management Document 1.1-002 Risk Registry Updated May, 2009 Major Risks Do something to cause loss or suspension of ARRA funds Annual funding - Continuing Resolutions (Retired) Foreign procurements – Dollar fluctuation, sole source Loss and/or availability of critical personnel (Exercised) Ability to place procurements in a timely manner CXI mirror delivery, performance XPP, XCS Monochromator delivery, performance XPP, XCS Detector delivery, performance LUSI XCS FIDR June 17, 2009 11 11 T. Fornek tomf@slac.stanford.edu Part of an Advance Procurement Review LUSI XCS FIDR June 17, 2009 12 12 T. Fornek tomf@slac.stanford.edu LCLS Directorate – Detail 1/2009 LCLS Directorate Dale Knutson Mark Reichanadter, Deputy ESH / Work Planning & Control Michael Scharfenstein Richard Hislop Administration Helen O’Donnell, LA De Wan, B. Espiritu, D. Ford, S. Matni, R. Matter, D. Mitchell, P. Tank Special Projects Richard M. Boyce Uli Wienands Accelerator Systems Division Experimental Facilities Division John Seeman Jochen Schneider TBD - Deputy TBD - Chief Operating Officer P. Miller, Accelerator Safety Officer Business Office Cindy Lowe TBD – Beam Line Safety Officer Engineering & Physics Division Strategic Projects Division Dave Schultz James Krebs, Deputy John Galayda TBD - Deputy TBD – ES&H Coordinator LUSI XCS FIDR June 17, 2009 13 13 M. Scharfenstein – Construction Safety T. Fornek tomf@slac.stanford.edu Strategic Projects Division (SPD) John Galayda M. Scharfenstein, Construction Safety Project Org = 83 FTEs Project Org = 7 FTEs LCLS Construction Project J. Galayda M. Reichanadter, Deputy J. Albino, AD, Civil Const. LUSI MIE Project T. Fornek TBD, Deputy RSB J. Albino G. Herman, K. Chan-Hui PULSE D. Rich Project Org = 27 FTEs Project Org = 10 FTEs Future Upgrades J. Galayda LUSI XCS FIDR June 17, 2009 14 14 T. Fornek tomf@slac.stanford.edu LUSI Project’s Integrated Project Team DOE-HQ Harriet Kung, Acquisition Executive T.E. Kiess, Program Manager DOE-SSO H. Joma DOE Federal Project Director Instrument Team Leaders Technical Configuration Control Committee . WBS 1.2 XPP IIT D. Fritz (Instr. Scientist) LUSI XCS FIDR June 17, 2009 SLAC T. Fornek LUSI Project Manager RM Boyce - Deputy WBS 1.3 CXI IIT S. Boutet (Instr. Scientist) WBS 1.4 XCS IIT A. Robert (Instr. Scientist) 15 15 DOE-SSO Support LCLS Directorate Support Engineering, Procurement, QA, ES&H, Finance & Budget, PMCS Installation Manager B. Poling WBS 1.5 Diagnostics & Common Optics Y. Feng (Lead Scientist) WBS 1.6 Data Acquisition & Controls G. Haller (Lead) T. Fornek tomf@slac.stanford.edu CHARGE - 1 Technical Scope Is the design of the partial instrument mature and technically sound to enable early scientific experiments at LCLS? Have all of the major interfaces been identified and incorporated in the design? Have design reviews been performed? Is the design likely to meet performance expectations? Management Is the instrument team organized and staffed to successfully achieve the milestone? Have all the major risks been identified and effectively managed? Are procurements appropriately planned for the partial instrument? LUSI XCS FIDR June 17, 2009 16 16 T. Fornek tomf@slac.stanford.edu CHARGE - 2 Cost and Schedule Are the cost and schedule reasonable to achieve the planned scope? Have the XCS cost and schedule been recently updated? Is there sufficient cost and schedule contingency to ensure successful completion of the partial instrument on schedule? ES&H Are all related ES&H aspects being properly addressed? Overall Readiness Is XCS ready to begin fabrication and installation at LCLS to begin conducting early scientific experiments? LUSI XCS FIDR June 17, 2009 17 17 T. Fornek tomf@slac.stanford.edu