LUSI PROJECT BUDGET AND SCHEDULE STATUS Thomas Fornek LUSI Project Manager June 8, 2009 LCLS FAC June 8, 2009 1 1 T. Fornek tomf@slac.stanford.edu Outline Project Status Funding, Obligations & Costs Cost and Schedule Performance Contingency & EAC Milestones & Critical Path Procurement Status Risk Management Summary LCLS FAC June 8, 2009 2 2 T. Fornek tomf@slac.stanford.edu LUSI Cost Baseline LCLS FAC June 8, 2009 Baseline Oct 2008 February 2009 Base Cost (BCWS) $42.10 M $42.37 M Contingency $13.00 M $12.73 M TEC $55.10 M $55.10 M OPC $4.90 M $4.90 M TPC $60.00 M $60.00 M 3 3 T. Fornek tomf@slac.stanford.edu LUSI ARRA Modified Funding Profile ARRA Modified Profile Moves FY10-FY12 Funds into FY09 LUSI Funding Profile (AYM$) With ARRA Funds Prior Yrs FY07 FY08 FY09 FY10 FY11 FY12 Total Pre ARRA 0.50 6.00 15.00 15.00 13.50 5.10 55.10 MIE 0.50 6.00 15.00 0 0 0 21.50 33.60 MIE (ARRA) OPC 3.40 1.50 Total 3.40 2.00 33.60 4.90 6.00 48.60 0 0 0 60.00 Still waiting for $7.6M of FY09 Funds Total received in April, 2009 LCLS FAC June 8, 2009 4 4 T. Fornek tomf@slac.stanford.edu Project Status (1) LUSI Baseline Performance (through Apr09) TPC = $60M (MIE = $55.1M, OPC = $4.9M) CD-4 = August 2012 TPC >26% Complete, TEC >18% Complete Contingency on MIE = $11.8M 33.2% on remaining work OPC is complete $50K remaining for close-out Most recent added scope to enhance LUSI science program Large Offset Monochromator for XPP Focusing lens for CXI LCLS FAC June 8, 2009 5 5 T. Fornek tomf@slac.stanford.edu Project Status (2) Design Completion XPP Instrument Design through FIDR CD-3 Ready CXI Instrument FIDR held June 3 CD-3 Ready Now - Solid Instrument Configuration XCS Instrument FIDR June 17 90% CD-3 Ready Now - Instrument configuration is solid Diagnostics and Common Optics Design 90% CD-3 Ready Now Harmonic Rejection Mirror PDR June 15 Controls and Data Acquisition 100% CD-3 Ready Now Inherited Designs from LCLS comprise many items LCLS FAC June 8, 2009 6 6 T. Fornek tomf@slac.stanford.edu Project Status (3) DOE-IPR Status Review Report from April Received Responses have been prepared to the report recommendations Preparing for the July 15, 2009 CD-3 Review Held in Germantown LUSI PM, Instrument Scientists and Controls Rep to travel Working on the second part of the Baseline Change to incorporate ARRA effects into the baseline Still need to incorporate two L2 milestones into schedule and adjust schedules appropriately (Waiting on TCCC) First month of reporting on ARRA accounts has been completed Some corrections are needed to the baseline – These will be incorporated in May LCLS FAC June 8, 2009 7 7 T. Fornek tomf@slac.stanford.edu April Status SLAC Linear Accelerator Center Menlo Park, California LUSI Cost/Schedule Status Report (April 2009) Date: 6/1/2009 Performance Data WBS[2] Cumulative to Date Actual Budgeted Cost Cost Variance Work Work Work Schedule Cost Scheduled Performed Performed At Completion Budgeted Latest Revised Estimate Indices Variance SPI CPI 1.1 PROJECT MANAGEMENT 2,353,987 2,353,987 2,265,241 0 88,746 4,955,382 4,896,892 58,490 1.00 1.04 1.2 X-RAY PUMP PROBE (XPP) 2,167,147 2,078,757 2,066,028 -88,390 12,729 5,728,269 5,680,774 47,495 0.96 1.01 1.3 COHERENT X-RAY IMAGING (CXI) 1,249,718 1,246,825 1,041,390 -2,893 205,435 9,890,267 9,913,328 -23,061 1.00 1.20 911,719 819,441 836,065 -92,278 -16,624 6,995,690 7,056,112 -60,422 0.90 0.98 1,213,822 1,203,493 1,191,269 -10,329 12,224 8,311,095 8,541,527 -230,433 0.99 1.01 516,891 504,095 514,934 -12,796 -10,839 7,223,124 7,259,346 -36,223 0.98 0.98 0 0 0 0 0 0 0 0 0 0 0 43,103,826 43,347,980 -244,154 11,996,174 11,752,020 244,154 0.98 1.04 1.4 X-RAY CORRELATION SPECTROSCOPY (XCS) 1.5 DIAGNOSTICS & COMMON OPTICS 1.6 CONTROLS AND DATA ACQUISITION Gen. and Admin. Undist. Budget Sub Total 8,413,284 8,206,598 7,914,927 -206,685 291,671 Management Resrv. (MIE) Total MIE 8,413,284 8,206,598 7,914,927 -206,685 291,671 55,100,000 55,100,000 0 2.0 Other Project Costs (OPC) 4,851,861 4,851,861 4,851,861 0 0 4,851,861 4,851,861 0 48,139 48,139 0 Management Resrv. (OPC) Total OPC Sub Total (MIE+OPC) 4,851,861 4,851,861 4,851,861 0 0 4,900,000 4,900,000 0 13,265,145 13,058,459 12,766,788 -206,685 291,671 47,955,687 48,199,841 -244,154 12,044,313 11,800,159 244,154 60,000,000 60,000,000 0 Total Management Reserve Total Project Cost (TPC) LCLS FAC June 8, 2009 13,265,145 13,058,459 12,766,788 -206,685 8 291,671 8 T. Fornek tomf@slac.stanford.edu Project Performance April Actuals LUSI MIE Project Actual Cost of Work Performed WBS Level 2 Non-ARRA Total 1.1 PROJECT MANAGEMENT $2,237,907 $27,334 $2,265,241 1.2 X-RAY PUMP PROBE (XPP) $2,056,925 $9,103 $2,066,028 1.3 COHERENT X-RAY IMAGING (CXI) $954,315 $87,074 $1,041,390 1.4 X-RAY CORRELATION SPECTROSCOPY (XCS) $784,255 $51,810 $836,065 $1,169,522 $21,748 $1,191,269 $486,563 $28,371 $514,934 $7,689,488 $225,440 $7,914,927 1.5 DIAGNOSTICS & COMMON OPTICS 1.6 CONTROLS AND DATA ACQUISITION Total LCLS FAC June 8, 2009 ARRA 9 9 T. Fornek tomf@slac.stanford.edu Project Performance April 2009 Performance Total Project Cost (TPC) AYK$ $60,000 Planned % Complete (MIE) 19.4% Actual % Complete (MIE) 18.1% Total Estimated Cost (MIE) $43,108 Cost and Commitments to Date (MIE) $7,915 Estimate at Complete (MIE) $43,348 Work Remaining (MIE) $35,433 MIE Remaining Management Reserve (Based on EAC) $11,752 % Contingency on Uncommitted Work Remaining (MIE) 33.2% This will be reduced once XCS “Early Science” detector is added LCLS FAC June 8, 2009 10 10 T. Fornek tomf@slac.stanford.edu Critical Path(s) Critical Path (CP) to CD-4 XPP Sample Goniometer System Order Placed – Est. Delivery March 31, 2010 Secondary – XPP detector – Est. Delivery December, 2009 CXI 1 Micron KB Mirror System Order not placed – Delivery 11 months ARO XCS Detector System Estimated Delivery – December, 2011 Secondary - XCS Diffractometer System Purchase Requisition Process Started – Estimated Delivery December 2010 LCLS FAC June 8, 2009 11 11 T. Fornek tomf@slac.stanford.edu Procurements LUSI using same co-located procurement “cell” as LCLS Demand on SLAC Purchasing Dept. still high LUSI “Cell” still supports LCLS SLAC authority is $1M without DOE approval Only $100K for foreign procurements SLAC ARRA projects increasing demand Meeting with Procurement on a daily basis LCLS FAC June 8, 2009 12 12 T. Fornek tomf@slac.stanford.edu Project Risks and Mitigation LUSI Follows the LCLS Risk Management Plan and uses the LCLS Risk Registry LCLS Project Management Document 1.1-002 Risk Registry Updated May, 2009 Major Risks Do something to cause loss or suspension of ARRA funds Annual funding - Continuing Resolutions (Retired) Foreign procurements – Dollar fluctuation, sole source Loss and/or availability of critical personnel (Exercised) Ability to place procurements in a timely manner CXI mirror delivery, performance XPP, XCS Monochromator delivery, performance XPP, XCS Detector delivery, performance LCLS FAC June 8, 2009 13 13 T. Fornek tomf@slac.stanford.edu Lessons Learned LUSI has reviewed the SNS Instrument Beamline Construction Lessons Learned – Many items were already incorporated System Integration Design Procurement Scheduling Construction Project Management LCLS has started a Beamline Lessons Learned Document LUSI Lessons Learned Procurements demand substantial resources – Project and SLAC LCLS FAC June 8, 2009 14 14 T. Fornek tomf@slac.stanford.edu Lessons Learned (1) System Integration Design Criteria – In place and controlled for LUSI Baseline Scope Review – LUSI uses established LCLS procedures Design Guide – Could be developed Naming – Names established early P&ID – Not standard at SLAC Radiation Shielding Configuration CD-4 Parameters Drawing – Key Performance Parameters Subject Matter Experts involved early in design Integration of electrical systems – Function of Controls System Integration Review Plan for Instrument Operation Early – Scientists are already planning for operation PPS Beam Sweep Plan early – LCLS ops working on this Plan for Shielding Configuration Control Complete Shielding Early Confirm “As-built” conditions early LCLS FAC June 8, 2009 15 15 T. Fornek tomf@slac.stanford.edu Lessons Learned (2) Design Shielding Keep SLAC RP involved – Follow LCLS procedures – One POC Documentation Don’t wait for “just in time delivery” – strains resources Integration of PPS and non-PPS cabling - Controls Mechanical Interferences We are working on processes to minimize this Vacuum Compatibility LCLS standards exist Ergonomic Features Scientists and Engineers are very involved – experienced Motion Control – Standards established by controls Crane Design Extra Vessel Penetrations – Where possible LCLS FAC June 8, 2009 16 16 T. Fornek tomf@slac.stanford.edu Lessons Learned (3) Procurement Involve Procurement Early Advanced Procurement Plans Also plan for advanced procurements in PEP Scheduling PPS and Detectors Allow appropriate installation time Component Delivery History Huber goniometers Motion Control Testing Scientists working with controls LCLS FAC June 8, 2009 17 17 T. Fornek tomf@slac.stanford.edu Lessons Learned – (4) Construction Survey and Alignment Involve Survey and Alignment early Oxygen Deficiency (ODH) Detectors Install when clean conditions exist Project Management Advance Procurement Approvals Heavily used on LUSI IRR Procedures and Approach to IRR LCLS to generate for AMO – LUSI will follow these Project Close-out Takes longer than expected LCLS Photon Systems Scope Definition and Tracking needs more attention Affects interfaces – Who is doing what LCLS FAC June 8, 2009 18 18 T. Fornek tomf@slac.stanford.edu ARRA Milestones – Look Ahead May, 2009 - Advance Procurement Approval XCS & DCO Procurement Review held April 23, 2009 Final Report Received May 5, 2009 Responses complete July, 2009 - Final Instrument Design Reviews for CXI & XCS June 3 – CXI Completed June 17 – XCS Scheduled August, 2009 - SC IPR of Revised Baseline & CD-3 Readiness SC IPR for LUSI CD-3 planned for July 15 September, 2009 - ESAAB Approval of Revised Baseline and CD-3 October, 2009 - CD-3, Approve Start of Fabrication December, 2010 - XPP Complete Instrument Ready for Science LCLS FAC June 8, 2009 19 19 T. Fornek tomf@slac.stanford.edu April ARRA Status SLAC Linear Accelerator Center Menlo Park, California LUSI Cost/Schedule Status Report ARRA Funds Only (April 2009) Date: 5/22/2009 Performance Data WBS[L2] Cumulative to Date Actual Budgeted Cost Cost Variance Work Work Work Schedule Cost Scheduled Performed Performed At Completion Budgeted Latest Revised Estimate Indices SPI Variance CPI 1.1 PROJECT MANAGEMENT 59,764 59,764 27,334 0 32,430 1,436,094 1,463,428 -27,334 1.00 2.19 1.2 X-RAY PUMP PROBE (XPP) 51,881 103,861 9,103 51,980 94,758 2,339,784 2,323,372 16,413 2.00 11.41 1.3 COHERENT X-RAY IMAGING (CXI) 156,479 130,517 87,074 -25,962 43,442 6,714,712 6,678,839 35,873 0.83 1.50 1.4 X-RAY CORRELATION SPECTROSCOPY (XCS) 103,847 86,744 51,810 -17,103 34,934 3,006,985 3,046,343 -39,358 0.84 1.67 1.5 DIAGNOSTICS & COMMON OPTICS 80,005 88,206 21,748 8,202 66,459 4,771,951 4,789,866 -17,915 1.10 4.06 1.6 CONTROLS AND DATA ACQUISITION 40,920 35,780 21,181 -5,140 14,598 6,743,434 6,764,615 -21,181 0.87 1.69 0 0 0 0 0 0 0 0 25,012,960 25,066,463 -53,503 8,587,040 8,533,537 53,503 33,600,000 33,600,000 0 1.02 2.31 Gen. and Admin. 0 0 0 Undist. Budget Sub Total 492,895 504,871 218,250 11,976 286,621 Management Resrv. (ARRA) Total ARRA LCLS FAC June 8, 2009 492,895 504,871 218,250 11,976 20 20 286,621 T. Fornek tomf@slac.stanford.edu Other ARRA Items Procurements Eleven ARRA procurements in various procurement stages Staffing LUSI hiring plan in place Additional management support brought on Technical Scope XCS “Early Science” Milestone and plans for associated detector has been reviewed and approved by the Technical Configuration Control Committee LCLS FAC June 8, 2009 21 21 T. Fornek tomf@slac.stanford.edu Schedule Advancement Milestone Current Baseline Advanced Baseline April 2010 October 2009 XPP Early Science October 2010 October 2010 CXI Early Science August 2011 June 2011 XCS Early Science (New) NA August 2011 Project Ready for CD-4 (New) NA March 2012 August 2012 August 2012 CD-3 CD-4 XCS “Early Science” allows for a functioning XCS instrument one year earlier than original schedule LCLS FAC June 8, 2009 22 22 T. Fornek tomf@slac.stanford.edu April Milestone Status LCLS FAC June 8, 2009 23 23 T. Fornek tomf@slac.stanford.edu Summary Substantial Project Completion is only 27 months away LUSI needs CD-3 to utilize ARRA funds effectively Procurements demand substantial staff attention Making progress Need to complete second Baseline Change to tie up loose ends in the schedule LCLS FAC June 8, 2009 24 24 T. Fornek tomf@slac.stanford.edu